formwork11.ppt

77
CIV030 Formwork Temporary Structures Department of CIVIL LIE- Poly

Upload: anish-ohri

Post on 01-Jan-2016

85 views

Category:

Documents


1 download

DESCRIPTION

abc

TRANSCRIPT

Page 1: formwork11.ppt

CIV030Formwork Temporary Structures

Department of CIVIL

LIE- Poly

Page 2: formwork11.ppt

CIV030 - Concrete Technology/ Formwork

• Lecture Goals– What is Shuttering / Formwork– concrete formwork construction Materials– Cost of Formwork– Connectors– Scaffolding

Page 3: formwork11.ppt

DEFINITION: FORMWORKS FOR IN-SITU

CONCRETE WORK

“ A mould or box into which wet concrete can be poured and compacted so that it will flow and finally set to the inner profile of the box or mould.”

Page 4: formwork11.ppt

Formwork

• Forms are molds to receive concrete in its’ plastic form.

• Formwork is temporary structure, as such, it is not normally shown on the drawings.

Page 5: formwork11.ppt

Formwork for Concrete• Formwork development has paralleled the

growth of concrete construction throughout the 20th century.

• The increasing acceptance of concrete as a major construction material presents the form builder a new range of problems in the development of appropriate sheathing materials and maintenance of rigid tolerances.

Page 6: formwork11.ppt

Formwork for Concrete• Formwork is a classic temporary

structure in the sense that:– it is erected quickly– highly loaded for a few hours

during the concrete placement– and within a few days

disassembled for future use.• Also classic in their temporary nature

are the connections, braces, tie anchorages, and adjustment devices which forms need.

Page 7: formwork11.ppt

Formwork for Concrete• The term "Temporary Structures" may not fully imply

the temporary, since some forms, tie hardware, and accessories are used hundreds of times, which necessitates high durability and maintainability characteristics and design that maximizes productivity.

• Unlike conventional structures, the formwork disassembly characteristics are severely restricted by concrete bond, rigidity, and shrinkage, which not only restricts access to the formwork structure but causes residual loads that have to be released to allow stripping from the concrete which initiates disassembly.

Page 8: formwork11.ppt

Formwork for Concrete• Lumber was once the predominant form material,

but developments in the use of plywood, metal, plastics, and other materials, together with the increasing use of specialized accessories have changed the picture.

• Formwork was formerly built in place, used once, and wrecked.

• Because of high labor costs in the U.S., the trend today is toward increasing prefabrication, assembly in large units, erection by mechanical means such as “flying” forms into place by crane, and continuing reuse of the forms.

Page 9: formwork11.ppt

Formwork for Concrete In 1908 the use of wood versus steel formwork was

debated at the ACI convention. Also, the advantages of modular panel forming with its own connecting hardware, and good for extensive reuse were realized.

By 1910 steel forms for paving were being produced commercially and used in the field.

A 1909 construction scene shows the first application of steel forms for street paving.

Page 10: formwork11.ppt

Formwork for Concrete• Today modular panel forming is the norm.

Page 11: formwork11.ppt

11

Form Materials and Accessories

Typical wall form with components identified. Plywood sheathing is more

common than board sheathing material.

Page 12: formwork11.ppt
Page 13: formwork11.ppt
Page 14: formwork11.ppt
Page 15: formwork11.ppt
Page 16: formwork11.ppt
Page 17: formwork11.ppt

Formwork for Beams and Slabs

Page 18: formwork11.ppt

Objectives of Form Building

• Forms mold the concrete to desired size and shape and control its position and alignment.

• But formwork is more than a mold; it is a temporary structure that supports:– its own weight +– the freshly placed concrete + – construction live loads (including materials,

equipment, and personel).

Page 19: formwork11.ppt

Objectives of Form Building• Basic objectives in form building are three fold:

– Quality - In terms of strength, rigidity, position, and dimensions of the forms

– Safety - for both the workers and the concrete structure

– Economy - the least cost consistent with quality and safety requirements

• Cooperation and coordination between engineer / architect and the contractor are necessary to achieve these goals.

Page 20: formwork11.ppt

20

Ties• A concrete form tie is a tensile unit adapted to holding

concrete forms secure against the lateral pressure of unhardened concrete.

• A wide variety of ready-made ties with safe load ratings ranging from 1000 lb to more than 50000 lb are used today.

• They consist of internal tension unit and external holding device, and are manufactured in two basic types:– Continuous single member– Internal disconnecting type

Page 21: formwork11.ppt

Formwork Materials

• Wood– Either all-wood or some wood components

• Plywood• Aluminum• Steel• Plastics

Page 22: formwork11.ppt

22

Internal disconnecting Type Ties• Internal disconnecting

type, in which the tensile unit has an inner part with threaded connections to removable external members which make up the rest of the tensile unit. They generally remain in the concrete.

Page 23: formwork11.ppt

23

Ties• The two types of tying devices are identified

commercially by various descriptive names, such as form clamps, coil ties, rod clamps, snap ties, etc.

• Except for taper ties, the continuos single member type is generally used for lighter loads, ranging up to about 5000 lb safe load.

• The internal disconnecting type of tie is available for light or medium loads but finds its greatest application under heavier construction loads (up to about 70,000 lb).

Page 24: formwork11.ppt

FORMWORK DESIGN

Loads include in design process are as followsa) Fresh concreteb) Rebarc) Formwork materiald) Wind and lateral loadse) Live loads due to – Formwork construction - Reinforcing installation

- Concrete placement

Page 25: formwork11.ppt

Plywood Orientation

Face Grain Direction Face Grain Direction

Weak Orientation of Plywood(Face grain parallel to span)

Strong Orientation of Plywood(Face grain perpendicular to span)

Page 26: formwork11.ppt

Aluminum

• Pure aluminum chemically attacked by wet concrete

• Light weight allow larger forming units• High reuse value

Aluminum beam“nailer - type”

Page 27: formwork11.ppt

Steel

• For heavy concrete work• With reasonable care will last indefinitely• High initial cost and high handling cost

Page 28: formwork11.ppt

Objectives of Form Building• Economy is a major concern since formwork costs

constitutes up to 60 percent of the total cost of concrete work in a project.

In designing and building formwork, the contractor should aim for maximum economy without sacrificing quality or safety.

Page 29: formwork11.ppt

How Formwork Affects Concrete Quality• Size, shape, and alignment of slabs, beams, and other

concrete structural elements depend on accurate construction of the forms, The forms must be: Sufficiently rigid under the construction loads to maintain the designed shape of the concrete,Stable and strong enough to maintain large members in alignment, andSubstantially constructed to withstand handling and reuse without losing their dimensional integrity, The formwork must remain in place until the concrete is strong enough to carry its own weight, or the finished structure may be damaged.

Page 30: formwork11.ppt

TIMBER FORMWORK

Timber Formwork:After Concrete Was

Poured

Timber Formwork : For The Slab

Page 31: formwork11.ppt

ADVANTAGES OF TIMBER FORMWORK

Among the advantages of timber formwork are as follow:a) Easy handling because it’s light weightb) Easy to disassemblec) Damaged parts can be replaced with new oned) Very flexible

Page 32: formwork11.ppt

DISADVANTAGES OF TIMBER FORMWORK

Among the advantages of steel formwork are as follow:a) Can’t be used for long. Have limited re-use. Can only

be re-used 5 or 6 timesb) If the timber is dry, it will absorb moisture from wet

concrete which could weaken the resultant concrete member.

c) Timber with high moisture content (more than 20 % moisture content), wet concrete will shrink & cup leading to open joints & leakage of grout.

Page 33: formwork11.ppt

Concrete Footing

9’6

Wall tie

3/4” plywood sheathing2”x 4”x 10’- 0 “ stud2- 2”x 4”wale

2”x 4” x 10’- 0”brace @ 6’- 0”

2”x 4” sill25’4”

2”x 4”x 3’- 0”Stake @ 6’- 0”

Page 34: formwork11.ppt

Timber formwork used for the construction of 2nd and the 3rd floor.

Page 35: formwork11.ppt

ADVANTAGES OF STEEL FORMWORK

Among the advantages of steel formwork are as follow:a) Very strong and able to carry heavy loadb) Easy to be fixedc) Uniform size and surfaced) Can be used for a very long time

Page 36: formwork11.ppt

DISADVANTAGES OF STEEL FORMWORK

Among disadvantages of steel formwork are as follow:a) Limited size or shapeb) Excessive loss of heatc) A very smooth surface will be produced

which would give problems for finishing process

d) Limited fixing (Pemasangan terhad)

Page 37: formwork11.ppt

STEEL FORMWORK

Page 38: formwork11.ppt

• The first floor circular columns were constructed using steel column forms. The steel column form should be oiled before

concreting.

Page 39: formwork11.ppt

• After concreting to the first floor columns, the steel column forms were dismantled

easily.

Page 40: formwork11.ppt

ADVANTAGES OF GLASS REINFORCED PLASTIC FORMWORK

Among the advantages of glass reinforced plastic formwork are as follow:a) Very useful for complex shape and special

featuresb) Easy to disassemblec) Light (not heavy)d) Damages on the formwork can be easily be

repaired

Page 41: formwork11.ppt

Permanent Formwork

It’s a part of the permanent structure of the building.

Permanent formwork is a structural element that is used to contain the placed concrete, mould it to the required dimensions and remain in place for the life of the structure.

Page 42: formwork11.ppt

Among the Advantages• Reducing the skill level needed

on site. • Increasing the potential for

standardisation and repetition. • Permitting off-site fabrication in

factory conditions followed by scheduled and appropriate deliveries.

• Speeding up erection times, particularly in building works.

Page 43: formwork11.ppt

• Eliminating the need to strike formwork and falsework.

• Allowing early access for following or concurrent operations.

• Eliminating the programme limitations of reuse of formwork.

Page 44: formwork11.ppt

Causes of Formwork Failure• Formwork failures are the cause of many accidents and failures

that occur during concrete construction which usually happen when fresh concrete is being placed.

• Generally some unexpected event causes one member to fail, then others become overloaded or misaligned and the entire formwork structure collapses.

Formwork collapse causes injuries, loss of life, property damage, and construction delays

Page 45: formwork11.ppt

Causes of Formwork Failure• The main causes of formwork failure are:

1 - Improper stripping and shore removal2 - Inadequate bracing3 - Vibration4 - Unstable soil under mudsills*, shoring

not plumb5 - Inadequate control of concrete

placement6 - Lack of attention to formwork details.

*Mudsill: A plank, frame, or small footing on the ground used as a base for a shore or post in formwork.

Page 46: formwork11.ppt

Causes of Failure

Improper Stripping and Shore Removal

Case study:

Too early shore removal at Bailey's Crossroads in Virginia (1972):26-stories + apartment buildingForms were supported by floors 7-days old or olderFailure occurred on the 24th floor, where it was shored to the 5-day-old 23rd floor.The overloaded 23rd floor failed in shear around one or more columns, triggering a collapse that carried through the entire height of the building.

Premature stripping of forms, premature removal of shores, and careless practices in reshoring can produce catastrophic results.

Page 47: formwork11.ppt

Causes of Failure

Inadequate Bracing The more frequent causes of formwork

failure, however, are other effects that induce lateral force components or induce displacement of supporting members.

Inadequate cross bracing and horizontal bracing of shores is one of the factors most frequently involved in formwork accidents.

Investigations prove that many accidents causing thousands of dollars of damage could have been prevented only if a few hundred dollars had been spent on diagonal bracing for the formwork support.

Page 48: formwork11.ppt

Causes of FailureInadequate BracingUse of Diagonal Bracing High shoring with heavy load at the top is

vulnerable to eccentric or lateral loading.

Diagonal bracing improves the stability of such a structure, as do guys or struts to solid ground or competed structures.

Page 49: formwork11.ppt

Causes of Failure

Inadequate Bracing The main exhibition floor of the New York

Coliseum collapsed when concrete was being placed.

Forms for the floor slab were supported on two tiers of shores.

Case study:New York ColiseumFormwork collapse, where rapid delivery of concrete introduced lateral forces at the top of high shoring.

Page 50: formwork11.ppt

Causes of FailureInadequate BracingUse of Diagonal BracingCase study: New York Coliseum Increased diagonal bracing was added to all

remaining shoring, following partial collapse of formwork.

Page 51: formwork11.ppt

Causes of FailureInadequate BracingUse of Diagonal Bracing

When a failure occurs at one part, inadequate bracing may permit the collapse to extend to a large portion of the structure and multiply the damage.

Suppose a worker accidentally rams or wheelbarrow into some vertical shores and dislodges a couple of them. This may set up a chain of reaction that brings down the entire floor.

One major objective of bracing is to prevent such a minor accident or failure from becoming a disaster.

Page 52: formwork11.ppt

Causes of FailureVibration

Forms sometimes collapse when their supporting shores or jacks are displaced by vibration caused by:

passing traffic movement of workers and

equipment on the formwork the effect of vibrating concrete to

consolidate it. Diagonal bracing can help prevent

failure due to vibration.

Page 53: formwork11.ppt

Causes of FailureUnstable Soil under Mudsills, Shoring not Plumb Formwork should be safe if it is adequately

braced and constructed so all loads are carried to solid ground through vertical members.

Shores must be set plumb and the ground must be able to carry the load without settling.

Shores and mudsills must not rest on frozen ground; moisture and heat from the concreting operations, or changing air temperatures, may thaw the soil and allow settlement that overloads or shifts the formwork.

Site drainage must be adequate to prevent a washout of soil supporting the mudsills.

Page 54: formwork11.ppt

Causes of FailureInadequate Control of Concrete Placement The temperature and rate of vertical placement of

concrete are factors influencing the development of lateral pressures that act on the forms.

If temperature drops during construction operations, rate of concreting often has to be slowed down to prevent a build up of lateral pressure overloading the forms. If this is not done, formwork failure may result.

H

FreshConcrete

Failure to regulate properly the rate and order of placing concrete on horizontal surfaces or curved roofs may produce unbalanced loadings and consequent failures of formwork.

Page 55: formwork11.ppt

• Even when the basic formwork design is soundly conceived, small differences in assembly details may cause local weakness or overstress loading to form failure.

• This may be as simple as insufficient nailing, or failure to tighten the locking devices on metal shoring.

• Other details that may cause failure are:– Inadequate provisions to prevent rotation of beam forms

where slabs frame into them on the side.– Inadequate anchorage against uplift for sloping form faces.– Lack of bracing or tying of corners, bulkheads, or other

places where unequal pressure is found.

Causes of FailureLack of Attention to Formwork Details

Page 56: formwork11.ppt

Planning for Safety• OSHA (Occupational Safety and Health

Administration) regulations, ACI recommendations, and local code requirements for formwork should be followed.– Supervision and Inspection– Platform and Access for Workers– Control of Concreting Practices– Improving Soil Bearing and Bracing– Shoring and Reshoring– Relationship of Architect, Engineer and Contractor– Maintaining and Coordinating Tolerances– Preparing a Formwork Specification

Page 57: formwork11.ppt

57

Form Materials and Accessories

Parts of typical slab formwork

Page 58: formwork11.ppt

58

Form Materials and Accessories

Engineered Wood Products• Plywood

– Plywood is widely used for job built forms and prefabricated form panel systems.

– Plywood is a flat panel made of a number of thin sheets of wood. A single sheet in the panel may be referred to as a ply, or layer.

– A layer may consist of a single ply or it may be two or more plies laminated together with their grain direction parallel.

Page 59: formwork11.ppt

59

Form Materials and Accessories

Plywood• Plywood at the bottom

face grain parallel to span is used the strong way. With face grain perpendicular to the span direction, the specimen at the top is used the weak way.

Page 60: formwork11.ppt

60

Vertical Loads

• Vertical loads on formwork include:– the weight of reinforced concrete– the weight of forms themselves (dead load)– the live loads imposed during the construction

process (material storage, personnel and equipment).

– The concrete weighs 150 pcf, it will place a load on the forms of 12.5 psf for each inch of slab thickness. i.e., a 6-inch slab would produce a dead load of 12.56 = 75 psf (neglecting the weight of the form)

Page 61: formwork11.ppt

61

Vertical Loads

Live load including power buggy and the concrete crew

(A minimum live load of 75 psf is recommended for design where power buggies are used)

Page 62: formwork11.ppt

62

Vertical Loads• When slab form members are continuous over several

supporting shores, dumping concrete on one span of the form member may cause uplift of the form in other spans.

• Forms must me designed to hold together under such conditions.

• If form members are not secured to resist this uplift, they should be built as a simple pan.

Page 63: formwork11.ppt

63

Lateral Pressure of Fresh Concrete

• Loads imposed by fresh concrete against wall or column forms differ from the gravity load on a horizontal slab form.

• The freshly placed concrete behaves temporarily like a fluid, producing a hydrostatic pressure that acts laterally on the vertical forms.

• This lateral pressure is comparable to full liquid head when concrete is placed full height within the period required for its initial set.

Page 64: formwork11.ppt

64

Lateral Pressure of Fresh Concrete

• With slower rate of placing, concrete at the bottom of the form begins to harden and lateral pressure is reduced to less than full fluid pressure by the time concreting is completed in the upper parts of the form.

• The effective lateral pressure a modified hydrostatic pressure has been found to be influenced by the weight, rate of placement, temperature of concrete mix, use of retardant admixtures, and vibration.

Page 65: formwork11.ppt

65

Factors Affecting Lateral Pressure on Forms

• Weight of concrete• Rate of placing (the average rate of rise in the form)

• Vibration• Temperature (affecting the set time)

• Other variables– Consistency of concrete– Ambient temperature– Amount and location of reinforcement– Maximum aggregate size (MSA)– Cement type, etc.

Page 66: formwork11.ppt

66

Form Design• When the material for formwork have been

chosen, and the anticipated loading estimated, a form should be designed strong enough to carry the anticipated loads safely, and stiff enough to hold its shape under full load.

• At the same time the builder or contractor wants to keep costs down by not overbuilding the form.

Page 67: formwork11.ppt

CONCRETE FORMWORK

Page 68: formwork11.ppt

• Formwork being erected

Page 69: formwork11.ppt

• Most of the pads and concrete footing poured

Page 70: formwork11.ppt

• Formwork for the parkade walls is built for each pour

Page 71: formwork11.ppt

• Most of the parkade walls been completed

Page 72: formwork11.ppt

STRIPING TIMEDeviation from specifieddimensions of cross-sectionof columns and beams

+ 12- 6 MM

Deviation from dimensionsof footings1) Dimensions in plan

+ 50mm-12

Eccentricity 0.02 times thewidth of the footingin the directionof deviationbut not more thanSomnl

Thickness f 0.05 times thespecified thickness

Page 73: formwork11.ppt

STRIPING TIMEType of formwork Minimum

period

Vertical formwork to columns, walls, beams 16-24 h

Soffit formwork to slabs(Props to be refixedimmediately after removal of formwork)

3 days

Soffit formwork to beams (Props to be refixed immediately after removal of formwork)

7 days

Page 74: formwork11.ppt

STRIPING TIMEType of formwork Minimum period

Props to slabs:1) Spanning up to 4.5 m2) Spanning over 4.5 m

7 days14 days

Props to beams and arches:1) Spanning up to 6 m2) Spanning over 6 m

14 days21 days

Page 75: formwork11.ppt

•ANY QUESTIONS??????

Page 76: formwork11.ppt

• Before we ENDS

• Precautions to be taken during concrete Operations regarding Formwork.

Page 77: formwork11.ppt