free pmp exam sample question 190
DESCRIPTION
The following PMP® Exam Sample Question is taken from the Free PMP Exam SimulatorTRANSCRIPT
![Page 1: Free PMP Exam Sample Question 190](https://reader036.vdocument.in/reader036/viewer/2022081813/55cf9a15550346d033a0659b/html5/thumbnails/1.jpg)
Free PMP® Exam Sample Question
PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.
![Page 2: Free PMP Exam Sample Question 190](https://reader036.vdocument.in/reader036/viewer/2022081813/55cf9a15550346d033a0659b/html5/thumbnails/2.jpg)
2
The following PMP® Exam Sample Question is taken from the Free PMP Exam Simulator:
![Page 3: Free PMP Exam Sample Question 190](https://reader036.vdocument.in/reader036/viewer/2022081813/55cf9a15550346d033a0659b/html5/thumbnails/3.jpg)
3
PMP® Exam Sample Question
You are managing a software development project. You want to create the basis that will be used later on for estimating, scheduling, executing, monitoring, and controlling the project work. Which process performs this activity? a) Create WBS b) Define Scope c) Define Activities d) Create Project Management Plan
![Page 4: Free PMP Exam Sample Question 190](https://reader036.vdocument.in/reader036/viewer/2022081813/55cf9a15550346d033a0659b/html5/thumbnails/4.jpg)
4
Estimating is performed when the activities are defined and the schedule is prepared. All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP® Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI® Registered Education Provider.
Hint:
![Page 5: Free PMP Exam Sample Question 190](https://reader036.vdocument.in/reader036/viewer/2022081813/55cf9a15550346d033a0659b/html5/thumbnails/5.jpg)
5
The correct answer is C.
Explanation: Activities form a basis for estimating, scheduling, executing, and monitoring and controlling the project work. This is performed in the Define Activities process.
Answer and Explanation: