from wind to wires wind to wires 2018... · 2019. 4. 18. · epri project manager b. madsen 3420...

54
2018 TECHNICAL UPDATE From Wind to Wires Insight into a Developing Framework for Incidental Take Permits for Eagles 10399377

Upload: others

Post on 10-Mar-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

Electric Power Research Institute 3420 Hillview Avenue, Palo Alto, California 94304-1338 • PO Box 10412, Palo Alto, California 94303-0813 USA

800.313.3774 • 650.855.2121 • [email protected] • www.epri.com

2018 TECHNICAL UPDATE

From Wind to Wires Insight into a Developing Framework for Incidental Take Permits for Eagles

10399377

Page 2: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

10399377

Page 3: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

EPRI Project Manager B. Madsen

3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813 USA 800.313.3774 650.855.2121

[email protected] 3002014192 www.epri.com Technical Update, August 2018

From Wind to Wires

Insight into a Developing Framework for Incidental Take Permits for Eagles

10399377

Page 4: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES

THIS DOCUMENT WAS PREPARED BY THE ORGANIZATION(S) NAMED BELOW AS AN ACCOUNT OF WORK SPONSORED OR COSPONSORED BY THE ELECTRIC POWER RESEARCH INSTITUTE, INC. (EPRI). NEITHER EPRI, ANY MEMBER OF EPRI, ANY COSPONSOR, THE ORGANIZATION(S) BELOW, NOR ANY PERSON ACTING ON BEHALF OF ANY OF THEM:

(A) MAKES ANY WARRANTY OR REPRESENTATION WHATSOEVER, EXPRESS OR IMPLIED, (I) WITH RESPECT TO THE USE OF ANY INFORMATION, APPARATUS, METHOD, PROCESS, OR SIMILAR ITEM DISCLOSED IN THIS DOCUMENT, INCLUDING MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE, OR (II) THAT SUCH USE DOES NOT INFRINGE ON OR INTERFERE WITH PRIVATELY OWNED RIGHTS, INCLUDING ANY PARTY'S INTELLECTUAL PROPERTY, OR (III) THAT THIS DOCUMENT IS SUITABLE TO ANY PARTICULAR USER'S CIRCUMSTANCE; OR

(B) ASSUMES RESPONSIBILITY FOR ANY DAMAGES OR OTHER LIABILITY WHATSOEVER (INCLUDING ANY CONSEQUENTIAL DAMAGES, EVEN IF EPRI OR ANY EPRI REPRESENTATIVE HAS BEEN ADVISED OF THE POSSIBILITY OF SUCH DAMAGES) RESULTING FROM YOUR SELECTION OR USE OF THIS DOCUMENT OR ANY INFORMATION, APPARATUS, METHOD, PROCESS, OR SIMILAR ITEM DISCLOSED IN THIS DOCUMENT.

REFERENCE HEREIN TO ANY SPECIFIC COMMERCIAL PRODUCT, PROCESS, OR SERVICE BY ITS TRADE NAME, TRADEMARK, MANUFACTURER, OR OTHERWISE, DOES NOT NECESSARILY CONSTITUTE OR IMPLY ITS ENDORSEMENT, RECOMMENDATION, OR FAVORING BY EPRI.

THE FOLLOWING ORGANIZATION, UNDER CONTRACT TO EPRI, PREPARED THIS REPORT:

Applied Biomathematics

This is an EPRI Technical Update report. A Technical Update report is intended as an informal report of continuing research, a meeting, or a topical study. It is not a final EPRI technical report.

NOTE

For further information about EPRI, call the EPRI Customer Assistance Center at 800.313.3774 or e-mail [email protected].

Electric Power Research Institute, EPRI, and TOGETHER…SHAPING THE FUTURE OF ELECTRICITY are registered service marks of the Electric Power Research Institute, Inc.

Copyright © 2018 Electric Power Research Institute, Inc. All rights reserved.

10399377

Page 5: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

This publication is a corporate document that should be cited in the

literature in the following manner:

From Wind to Wires: Insight into a Developing Framework for Incidental

Take Permits for Eagles. EPRI, Palo Alto, CA: 2018.

3002014192.

iii

Acknowledgments

The following organization, under contract to the Electric Power Research Institute (EPRI), prepared this report:

Applied Biomathematics 100 North Country Rd. Setauket, NY 11733

Principal Investigator N.A. Friedenberg

Research Associate C.M. Foley

This report describes research sponsored by EPRI.

10399377

Page 6: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

10399377

Page 7: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

v

Product

Description

The 2016 final rule revising the permitting of incidental take under the U.S. Bald and Golden Eagle Protection Act (BGEPA) indicated that new protocols and permit terms and conditions will be developed for take by transmission and distribution line projects, but at the present time many of the details are uncertain. This report is intended to provide an overview of the issues involved and a summary of some of the changes that may be enacted, as well as opportunities that exist for stakeholder contributions to the emerging framework.

Background Unpermitted incidental take of eagles in the United States is prohibited under the BGEPA. Concern over turbine-related fatalities amid rapid growth in the wind energy sector led to the development of a quantitative framework for predicting and assessing incidental take at wind farms, and in a final rule released at the end of 2016, the U.S. Fish and Wildlife Service (FWS) announced it will apply this framework to other activities. However, it acknowledged that some activities warrant their own protocols. Transmission and distribution (T&D) projects were cited as a specific example of an activity that requires changes to the incidental take permitting framework, but details on those changes were not part of the final rule.

Objectives To identify similarities and differences between the frameworks

for wind and T&D To give technical detail on the FWS approach to permitting

incidental eagle take at T&D projects

To identify aspects of the approach that remain unclear or undecided

To identify opportunities for the electric power industry to contribute to the emerging framework

Approach Investigators conducted interviews with FWS personnel to gain insight into their approach to and progress toward a quantitative framework for permitting the incidental take of eagles at T&D

10399377

Page 8: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

vi

projects. This information was further enhanced through the review of online resources, peer-reviewed literature, and the 2016 final rule.

Results The research and development of tools for predicting fatalities at T&D projects is being led by the Western Golden Eagle Team (WGET) within the FWS, and this group and its collaborators have made significant progress toward developing the new framework for T&D projects. Their approach is highly quantitative and depends on multiple models to predict eagle abundance and electrocution hazard, the topics that have been the focus of research so far. Release of final guidance is expected in late 2019 or early 2020.

Several aspects of the framework are still unclear or undecided. Significantly, no specific information on post-construction fatality monitoring was identified. WGET personnel indicated that they are yet undecided on their approach to predicting electrocutions. They have developed one approach that predicts power pole density from landscape features as a proxy for electrocution hazard. However, they indicated that their preferred approach would utilize a GIS database of pole locations and configurations.

The high data demands of the proposed framework, as well as the need for regional coordination of data collection, create opportunities for the electric power industry to contribute to both the development and the maintenance of data products for use in T&D project permitting. WGET also acknowledged that their models are trained on golden eagle data but will be applied to bald eagles, as well. The electric power industry could contribute to the development of a parallel set of models and parameters for bald eagles, likely facilitating better management outcomes.

Applications, Value, and Use Having an understanding of the specific goals for the developing framework, as well as the decisions that remain to be made, provides an opportunity to educate stakeholders prior to the release of final guidance. EPRI is available to develop collaborative research projects and facilitate dialogue between the electric power industry and FWS staff.

Keywords BGEPA Eagles Electrocution Incidental take Transmission and distribution

10399377

Page 9: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

EXECUTIVE SUMMARY

vii

Deliverable Number: 3002014192 Product Type: Technical Update

Product Title: From Wind to Wires: Insight into a Developing Framework for Incidental Take Permits for Eagles

PRIMARY AUDIENCE: Environmental managers at electric utilities and wind operating companies SECONDARY AUDIENCE: Interested researchers and agency staff engaged in golden eagle management issues

KEY RESEARCH QUESTION

The 2016 final rule revising the permitting of incidental take under the Bald and Golden Eagle Protection Act (BGEPA) indicated that new protocols and permit terms and conditions will be developed for take by transmission and distribution (T&D) line projects. What will this framework share in common with the framework for wind farms? What parts will differ and what new approaches will be used?

RESEARCH OVERVIEW

This report is intended to provide a quick but thorough overview of issues around an emerging BGEPA incidental take permit framework for transmission and distribution. Research being conducted to support the development of this framework is being led by the Western Golden Eagle Team (WGET), a group within the U.S. Fish and Wildlife Service (FWS) with a large network of private and academic collaborators. Insight into their approach and progress was gained through interviews and augmented by a review of online resources, peer-reviewed literature, and the text of the final rule itself. This report summarizes the T&D incidental take framework and provides technical detail on developments in golden eagle abundance estimation, prediction of electrocutions, and mitigation options. This information is supported with background on the existing permitting protocol for wind farms and an independent evaluation of possible approaches to electrocution risk assessment.

KEY FINDINGS • The incidental take permitting protocol for T&D projects is still in development, but significant progress

has been made and is supported by peer-reviewed publications. • The approach to predicting and managing take at T&D projects uses multiple quantitative

mathematical models. These models address local population size (step 1 in Figure 1), historical patterns of wires-related eagle fatality (step 2), and calculation of compensatory mitigation (step 3). This report reviews the modeling involved in all of these steps in detail.

10399377

Page 10: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

EXECUTIVE SUMMARY

viii

Figure 1. Cumulative incidental eagle take will be managed through a framework incorporating eagle population density and dynamics, activity-specific impacts, and options for compensatory mitigation.

• Local eagle population abundance will be estimated using multiple habitat-based models for the breeding season, migration, and winter (Figure 2).

Figure 2. FWS is developing tools to better understand where, when, and how many eagles are exposed to the hazard of incidental take.

• Regarding T&D sector impacts, WGET’s research focuses on golden eagle electrocution (circled in the middle column of Figure 3) on distribution equipment. Collision does not seem to be a focus, and transmission is not mentioned outside of the generic label for the industry sector. The framework and parameter values developed for golden eagles will also apply to bald eagles.

• Electrocutions may be predicted in one of two ways. The initial approach is likely to base electrocutions on a combination of predicted power pole density and eagle habitat (circled in the left column of Figure 3). A more detailed model based on specific relationships between pole configurations and electrocution hazard will not be useful until a comprehensive GIS database of pole configurations is available.

10399377

Page 11: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

EXECUTIVE SUMMARY

ix

• The model-based approach to predicting electrocutions will reduce reliance on project-specific pre-construction monitoring. FWS has not yet decided whether pre-construction monitoring will be required at all projects or at a subset of projects that meet certain conditions. No detail is available yet on the protocol for post-construction fatality monitoring.

Figure 3. Take will be predicted by different models at wind energy and T&D projects. It appears that FWS will use predicted power pole density to determine electrocution hazard.

• FWS and collaborators are exploring new mitigation options for incidental eagle take (Figure 4). A 2017 publication by WGET and the American Wind Wildlife Institute (AWWI) indicated interest in developing a mitigation banking system. The 2016 final rule facilitates such development by allowing third-party mitigation at sites removed from the project footprint.

Figure 4. Power-pole retrofits are the only compensatory mitigation option that has been fully developed so far. New mitigation options are being explored. FWS is also open to mitigation banking.

10399377

Page 12: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

EXECUTIVE SUMMARY

x

• Based on this research, the emerging T&D will only differ from the existing wind energy framework in how take is predicted and how post-construction fatality monitoring will be conducted (Figure 5).

Figure 5. Incidental take permitting for wind energy and T&D projects. Boxes extending across both columns indicate shared protocols.

• Release of full guidance is expected in late 2019 or early 2020. • Opportunities for contributions from the electric power industry arise from the framework’s large data

demands, the need for regionally coordinated data collection, and possible benefits of technological innovation for pole inventory and fatality monitoring (summarized in Section 9).

10399377

Page 13: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

EXECUTIVE SUMMARY

xi

WHY THIS MATTERS

The process of developing the framework for incidental take of eagles by wires projects is still underway. This report integrates the partial information available to the public with a technical understanding of the data demands and modeling techniques being used. Having an understanding of the specific goals for this framework, as well as the decisions that remain to be made, provides an opportunity to educate stakeholders prior to the release of final guidance.

HOW TO APPLY RESULTS

This report identifies several aspects of the emerging incidental take permit framework for T&D that remain either undecided or unclear, such as how electrocutions will be predicted, how local eagle abundance will enter this calculation, and how post-construction fatality monitoring will be conducted. The report also highlights potential opportunities for participation by the electric power industry and other stakeholders. Interested stakeholders may read this document to gain a comprehensive understanding of the emerging framework ahead of its release. Electric Power Research Institute (EPRI) members may direct research toward specific technological challenges, such as artificial intelligence-assisted collection of distribution pole inventory data or the design and validation of statistically sound fatality monitoring studies at T&D projects. There is also a need to customize both wind and T&D frameworks to bald eagles. EPRI members may wish to continue dialogue with FWS (and WGET in particular) to keep abreast of new information.

LEARNING AND ENGAGEMENT OPPORTUNITIES • EPRI is available to develop collaborative research projects and facilitate dialogue between the electric

power industry and FWS staff involved in BGEPA. • A 2015 overview of WGET objectives and progress is summarized here: Williams et al., 2015. • This report may be of interest to environmental managers at electric utilities as well the broad range

of industry, academic, nonprofit, and agency researchers engaged in golden eagle management and bald eagle issues.

• The report provides a framework for future research opportunities including bald eagle habitat modeling, T&D inventory methods, and eagle fatality monitoring.

• EPRI previously funded research that took an approach to eagle abundance estimation very similar to that being pursued by FWS. Members may be interested in EPRI report 3002004770, Population-Level Impacts of Wind Energy Development on Golden Eagles (Aquila chrysaetos): A Framework for Quantitative Risk Assessment.

EPRI CONTACTS: Becca Madsen, Senior Technical Leader, [email protected]; Christian Newman, Principal Technical Leader, [email protected]

PROGRAM: Protected and Endangered Species, P195

10399377

Page 14: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

10399377

Page 15: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

xiii

Table of Contents

Abstract ................................................................ v

Executive Summary ............................................. vii

Section 1: Introduction ....................................... 1-1 Roadmap .................................................................. 1-3

Section 2: T&D-Related Statements in the 2016 Final Rule ........................................... 2-1

Activity-Specific Protocols (81 FR 91520) ...................... 2-1 A Protocol for Transmission and Distribution (81 FR 91522) .......................................................... 2-1 Compatibility of Local Area Population (LAP) Analysis with Long Linear Projects (81 FR 91527) ...................... 2-1 Take Prior to 2009 (81 FR 91534) .............................. 2-2 Mitigation and Third-Party Monitoring .......................... 2-2

Section 3: How the Wind Framework Could Be Improved ...................................... 3-1

Eagle Abundance Affects Risk ..................................... 3-1 Stage- and Season-Specific Risk ................................... 3-2 Update the Avoidance Prior ........................................ 3-2 Develop a Separate Avoidance Prior for Bald Eagles ..... 3-3

Section 4: A Menu of Models for Electrocution Prediction, from Simple to Complex .... 4-1

Simplest Approach ..................................................... 4-1 Brief Case Study of Constant Electrocution Rate Per Pole .................................................................... 4-1 Intermediate Complexity ............................................. 4-2 The “Full Monty” ........................................................ 4-2

Section 5: Incidental Eagle Take at T&D Projects: An Overview...................................... 5-1

A Note on Fatality Estimation ................................. 5-3

10399377

Page 16: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

xiv

Section 6: FWS Models for Eagle Distribution and Abundance .................................. 6-1

Breeding Habitat Model ............................................. 6-2 Winter Habitat Model ................................................ 6-3 Migratory Habitat Model ............................................ 6-3

Section 7: FWS Approaches to Predicting Electrocutions ..................................... 7-1

Risk Factors ............................................................... 7-2 Equipment ............................................................ 7-2 Age .................................................................... 7-2

Deciding on an Electrocution Model ............................. 7-3 Project-Specific Pre-Construction Monitoring .................. 7-4

Section 8: Mitigation .......................................... 8-1 Mitigation Ratio ......................................................... 8-1 New Mitigation Options on the Horizon ....................... 8-2 A Future for Mitigation Banking ................................... 8-2 Mitigation Roll-Over ................................................... 8-2

Section 9: Conclusion and Opportunities ............. 9-1 A Work in Progress .................................................... 9-1 Opportunity ............................................................... 9-1

T&D Inventory Data ............................................... 9-2 Fatality Monitoring ................................................ 9-2 Eagle Population Data ........................................... 9-2

Section 10: References....................................... 10-1

10399377

Page 17: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

xv

List of Figures

Figure 1-1 Three components of management for the cumulative incidental take of eagles ............................. 1-2

Figure 5-1 Incidental take permitting for wind energy and T&D projects. Boxes extending across both columns indicate shared protocols. ........................................... 5-2

Figure 6-1 A diverse array of information and models will be used to better predict and manage incidental take of eagles. .................................................................. 6-1

Figure 6-2 Three habitat models intended to improve the assessment of spatial and seasonal variation in eagle abundance. ............................................................... 6-2

Figure 7-1 Power pole density may be used as a proxy for more detailed equipment inventory in a model that predicts golden eagle electrocutions at distribution projects. .................................................................... 7-1

Figure 8-1 The mitigation assessment framework will be similar for wind and wires. .......................................... 8-1

10399377

Page 18: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

10399377

Page 19: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

xvii

List of Tables

Table 7-1 Simulation results: electrocution risk by age class .................................................................. 7-3

10399377

Page 20: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

10399377

Page 21: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

1-1

Section 1: Introduction Unpermitted incidental take of eagles in the United States is prohibited under the Bald and Golden Eagle Protection Act (BGEPA). Concern over turbine-related fatalities amid rapid growth in the wind energy sector led to the development of a quantitative framework for predicting and assessing incidental take at wind farms. In a final rule released at the end of 2016 (referred to hereafter as “the 2016 rule”), the U.S. Fish and Wildlife Service (FWS) announced that it will apply this framework to other activities (FWS 2016b). However, it acknowledged that some activities warrant their own protocols. Transmission and distribution (T&D) projects were cited as a specific example of an activity that requires changes to the incidental take permitting framework, but details on those changes were not part of the final rule.

By early 2017, there was interest and some concern regarding upcoming changes to the rules. The outline of those changes was not immediately apparent, but a number of statements in the final rule indicated that the framework for permitting wind farms would be applied to T&D (or “wires”) projects.

The question arose whether the data requirements and mathematical model FWS uses to predict incidental take at wind projects could be applied to T&D projects. Ultimately, this question gave rise to the original purpose of the present report: to determine which parts of the wind energy framework would work for wires, which would not, and what changes would be necessary.

However, in our research we have found the questions that motivated this report are already being considered but still left uncertainty as to how FWS might approach transmission and distribution. As stated in the 2016 rule, FWS recognizes that eagle interactions with wires differ from those with wind farms and that the sheer magnitude of T&D projects demands a specialized protocol (81 FR 91522). In fact, this was not a forward-looking statement. FWS has already identified specific changes and is actively developing the knowledge and tools necessary to implement them. The Service’s approach to understanding eagle interactions with wires is highly dependent on multiple quantitative mathematical models. These models address local population size (step 1 in Figure 1-1), historical patterns of wires-related eagle fatality (step 2), and calculation of compensatory mitigation (step 3) (Figure 1-1). This model-based approach differs most significantly from the wind farm protocol in its potential shift from project-specific pre-construction monitoring to regional monitoring.

As stated in the 2016 rule, FWS recognizes that eagle interactions with wires differ from those with wind farms and that the sheer magnitude of T&D projects demands a specialized protocol (81 FR 91522).

10399377

Page 22: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

1-2

Figure 1-1 Three components of management for the cumulative incidental take of eagles

One thing is clear: the focus of FWS’s research is on golden eagle electrocution on distribution equipment. Collision does not seem to be a focus and no mention is made of transmission projects outside of the generic label for the industry sector, “transmission and distribution.” As with the existing framework for wind energy projects, relatively little attention is being paid to bald eagles and their interaction with wires. The framework and parameter values developed for golden eagles will also apply to bald eagles.

Significant opportunities exist for the electric power industry, which routinely collects and reports data on T&D-related avian fatality, to contribute to the data and organizational needs of the emerging incidental take permit framework for wires. Low-hanging fruit includes administration of regional programs for the collection and maintenance of T&D equipment inventory data. Such programs would need to standardize data protocols across service areas and address data-poor regions serviced by rural co-ops. Other opportunities include innovation in post-construction fatality monitoring and the coordination of eagle population information to improve the prediction of incidental take. A more difficult task in need of leadership is the data collection and analysis necessary to derive parameters specific to bald eagles for the wires model. Section 9 of this report describes opportunities and research needs in greater detail.

Much of the content of this report is based on conversations with FWS personnel. Where further clarification on the technical approaches or state of progress was needed we relied on the FWS Western Golden Eagle Team’s (WGET’s) progress reports (Woodbridge and Williams 2016; Woodbridge and Williams 2017) and FWS staff slide presentations (Woodbridge 2015; Williams 2017), which are publicly available online resources that reiterate much of what was discussed interviews, while providing more technical information. Peer-reviewed literature and the text of the 2016 final rule were also useful resources.

The focus of FWS’s research is on electrocution as opposed to collision. Additionally, there is a focus on distribution whereas transmission is rarely noted.

Little attention is given to bald eagles. What is developed for golden eagles will also apply to bald eagles.

10399377

Page 23: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

1-3

Uncertainty remains in aspects of the emerging framework, such as which of two electrocution risk models will be used and how post-construction fatality monitoring will be conducted. This uncertainty is highlighted where appropriate in the report. In some cases we obtained confirmation that matters have not yet been decided. In other cases, we have relied on our familiarity with the process of mathematical modeling to speculate about technical approaches and the possible future evolution of model complexity. Instances of speculation will be clearly indicated as such. Importantly, the framework for wires is a work in progress and has not yet been set forth in any official guidance document or rule. Statements in this technical update about FWS intentions or approaches should be treated as forward-looking and therefore subject to modification.

Roadmap

This report is intended to give environmental managers and researchers a quick but thorough overview of emerging issues around permitting incidental eagle take by electric distribution projects. The update begins by summarizing statements in the 2016 rule relevant to the question of how incidental take by T&D projects will be treated. Section 3 summarizes previous research on opportunities for improving predicting incidental take at wind farms. These points serve as a prelude to the approach FWS is taking with wires. Section 4 then illustrates the spectrum of possible approaches that could theoretically be used to predict incidental take by distribution projects, from simple to complex. In Section 5 we give an overview of the framework proposed by FWS for permitting the incidental eagle take by T&D projects and summarize how it will differ from that for wind. Sections 6-8 go into greater technical detail on the components of that framework: models of eagle abundance, prediction of electrocution risk, and developing options for mitigation. Finally, Section 9 lays out several opportunities for stakeholders to participate in the development of the wires permitting framework for eagles.

The framework for wires is a work in progress and has not yet been set forth in any official guidance document or rule. In this report, any statements about FWS intentions or approaches should be treated as forward-looking and therefore subject to modification.

10399377

Page 24: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

10399377

Page 25: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

2-1

Section 2: T&D-Related Statements in the 2016 Final Rule

The 2016 final rule included a number of statements, mostly in response to comments, that give some insight into the intended design of T&D-specific permitting for eagle take (FWS, 2016b). All references to 81 FR below are page numbers within the final rule.

Activity-Specific Protocols (81 FR 91520)

In response to comments that application of the survey protocol for wind would be inefficient for other activities, FWS replied that it intends to develop protocols specific to other activities. Until such standards are developed, however, the existing wind framework will be applied.

A Protocol for Transmission and Distribution (81 FR 91522)

FWS agreed with comments that eagle mortality associated with T&D projects differs from other sources of mortality due to the substantial magnitude of such projects. This difference warrants special “pre-permitting data standards and permit terms and conditions for monitoring incidental take of eagles.”

Compatibility of Local Area Population (LAP) Analysis with Long Linear Projects (81 FR 91527)

FWS dismissed objections that its LAP analysis cannot be applied to industries other than wind. The concept of the LAP addresses the problem of defining what population is being impacted by a permitted activity. Golden eagles can disperse over long distances during their lifetimes, making it hard to delineate local or regional populations. Therefore, FWS defines the local population as the area encompassed by a buffer around the project footprint equal to the average distance a juvenile settles from its natal nest, 175 km. There is some tedious GIS work involved in calculating the number of eagles expected to reside within the local area (FWS 2009), so FWS has developed a tool that automates their calculation (FWS, 2016b). The tool can accommodate any project of any size or shape within the United States.

Regardless of activity, if cumulative permitted take is expected to exceed 5% of the LAP, a National Environmental Policy Act (NEPA) analysis is triggered. Concerns that this creates a priority effect and penalizes later-arriving projects

In the 2016 final rule, FWS acknowledged that T&D projects warrant a separate approach to incidental take permitting for eagles.

10399377

Page 26: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

2-2

have some validity. There is extra cost and time involved if NEPA is triggered. However, FWS points out that the 5% threshold does not impose a limitation on further take. For golden eagles, FWS has determined that the golden eagle population will decline with any additional take if such take is not mitigated. Hence, even in cases where cumulative LAP take is less than 5%, a compensatory mitigation plan will be necessary if golden eagle fatalities are expected.

Take Prior to 2009 (81 FR 91534)

The western golden eagle population is considered stable (FWS 2016a). This stability has been achieved in the presence of many sources of mortality, including electrocution by existing T&D projects. Therefore, FWS considers projects existing prior to 2009 to be part of the baseline environment in which they have measured eagle demography and assessed population stability. Some risk of prosecution exists for unpermitted take of eagles prior to 2009 insofar as permit applicants remain open to enforcement actions. However, this risk seems to be mitigated by the 5-year statute of limitations on enforcement of unpermitted take violations, suggesting that take prior to the 2009 baseline will not be prosecuted.

Mitigation and Third-Party Monitoring

Though not specific to wires, the final rule included two important changes to eagle take permitting. Both apply only to permits of greater than 5 years, which is relevant to wires projects. The first is that, following a 5-year review of post-construction monitoring data, any excess compensatory mitigation that has been performed can be rolled into the following 5-year period (81 FR 91516). The second is that post-construction monitoring must be performed by an independent third party (81 FR 91503). This party must be “qualified, independent entities.” No mention is made of new certifications for monitoring services, and the text of the rule refers to the common existing practice of employing consultants for project monitoring.

10399377

Page 27: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

3-1

Section 3: How the Wind Framework Could Be Improved

As a prelude to considering how to predict electrocutions on distribution poles, we summarize previous research on potential improvements to the framework for predicting incidental eagle take at wind farms. This starting point provides a reference for the changes in the proposed T&D framework.

Eagle Abundance Affects Risk

The FWS collision risk model (CRM) predicts collisions using project design parameters and field measurements of eagle activity (New et al. 2015). The CRM is based on the Band collision model (Band et al. 2007) (Whitfield 2009). A study of the Band collision model, “Collision fatality of raptors in wind farms does not depend on raptor abundance” (de Lucas et al. 2008), has been broadly interpreted to indicate that the number of collisions is not proportional to abundance. However, a close reading reveals its main conclusion is that the Band model had no predictive value in that study.

While abundance is not considered for collision prediction in the United States, it is incorporated by methods used in other countries (Smales et al. 2013). Doing so may have value even if collisions are not strictly proportional to population size. For instance, knowledge of local abundance sets an upper limit on the number of birds at risk, providing a “sanity check” in scenarios where a project is expected to cause, say, 5 fatalities a year when only one breeding pair inhabits the surrounding area.

Eagle abundance is a difficult thing to quantify. Some eagles are resident breeders and may be easy to enumerate during the breeding season. Others are non-territorial and likely have much larger home ranges and can exhibit long-range relocations, adding a certain amount of flux to the local population size. The problem of counting birds is further complicated by winter migrants, which may settle locally for part of the year or may simply pass through.

Hence, the incorporation of abundance into collision prediction, even if limited to sanity checking, requires a detailed understanding of the seasonal spatial dynamics of eagle populations that is most appropriately pursued on a regional or even national basis. Large-scale studies of the eagle population can produce mathematical models of abundance. The value of such models would be realized

Knowledge of local abundance sets an upper limit on the number of birds at risk, providing a “sanity check” in scenarios where a project is expected to cause, say, 5 fatalities a year when only one breeding pair inhabits the surrounding area.

10399377

Page 28: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

3-2

through easier site scoping and a reduced need for project-specific monitoring prior to construction.

As will be described in Section 6, FWS is addressing the complicated seasonal patterns of abundance through a multi-model approach based on extensive empirical survey and tracking efforts. The resulting models may inform take predictions for both wind and wires, though the methods for incorporating this information are not yet clear.

Stage- and Season-Specific Risk

The CRM for wind, as well as the calculation of compensatory mitigation requirements, assumes that collisions are random with respect to the age and status of birds. Early research on turbine collisions at the Altamont Wind Resource Area highlighted a concentration of collision risk in non-territorial subadult and adult life stages (Hunt 2002). Juveniles and breeding adults were rare among fatalities. Modern turbines have changed significantly from the relatively short lattice-tower designs common in the Altamont study, so it is unclear whether this non-random pattern of risk exists at other wind farms. However, it is easy to imagine an explanation for the pattern: juveniles remain in or near their nests and breeding adults remain within their territories, but non-territorial subadults and adults spend more time moving through the landscape and perching near foraging areas, possibly placing a greater proportion of their activity in the vicinity of turbines.

An age or status bias in fatality risk can also indicate seasonal changes in risk. For instance, if non-territorial individuals are at higher risk of collision, then winter migrants, all of which are non-territorial during the winter months, may account for a disproportionate share of annual fatalities.

Understanding what ages or types of individual are most affected by a particular activity can improve management in at least two ways. The first is that it could add information to the CRM. Knowing, for instance, that migrants are at higher risk might suggest putting more weight on the activity measured during winter months. The second advantage to understanding individual variation in risk is that it provides greater insight into the potential impact of fatalities on population viability. Activities that affect adults may tend to have a higher impact on population growth rate than those that affect juveniles (Tack et al. 2017).

Studies of electrocution on distribution equipment by FWS personnel and collaborators have indicated a strong bias toward juvenile fatalities (Lehman et al. 2010; Mojica et al. 2018). How this information will enter into the fatality prediction and compensatory mitigation calculation is not yet clear. Section 7 discusses juvenile risk in greater detail.

Update the Avoidance Prior

The CRM that currently applies to wind and all other activities (in the absence of other protocols) is a Bayesian model (New et al. 2015). In practice, this means

10399377

Page 29: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

3-3

that analyses begin with an accepted understanding of the range of possible activity and avoidance rates characteristic of eagle populations interacting with wind farms. These starting points are called priors, and each is a distribution rather than just a point value or a range. Pre-construction monitoring adds project-specific information to the prior for eagle activity. The more data are collected, the less effect the prior has on the answer.

A recent study suggested that the current prior for eagle avoidance is too low (Bay et al. 2016), leading to overestimates of predicted collision fatalities at wind farms. While the FWS approach is intentionally conservative, it is intended to produce an accurate estimate of expected collisions; caution is then added to this estimate by using the upper 80% Bayesian confidence limit. FWS has addressed the need for updated priors. Revised golden eagle activity and avoidance priors were released for public comment in Jun, 2018 (83 FR 28858).

Develop a Separate Avoidance Prior for Bald Eagles

Development of the incidental take permitting process has focused largely on golden eagles, while bald eagles have received less attention. This may be because golden eagles comprise a larger number of collision fatalities at wind farms than do bald eagles. There are relatively more bald eagles in the United States, though their local distribution is more restricted due to a largely fish-based diet. Currently, bald eagle collision predictions use golden eagle parameters. This most likely overestimates predicted incidental take of bald eagles at wind farms. In practice, the burden of this overestimate is reduced by the allowance of some bald eagle take without mitigation (FWS 2016b).

The newly released activity and avoidance priors for the wind CRM include separate priors specific to bald eagles (83 FR 28858). Both feature greater variance than the golden eagle priors. FWS explains that this is due to larger variation among facilities in bald eagle local population density and interaction intensity. A larger variance in the priors leads to an a priori higher expected number of fatalities at the 80% upper quantile used to assess future take. While local pre-construction monitoring will modify the activity prediction on a site-by-site basis, the avoidance prior is only updated periodically. Hence, continued data collection on turbine-related bald eagle fatalities and research into the factors that determine site-specific risk continue to have value.

A recent study suggested that the current prior for eagle avoidance is too low (Bay et al. 2016), leading to overestimates of predicted collision fatalities. FWS personnel indicated that an updated avoidance prior will be released in June or July of 2018.

10399377

Page 30: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

10399377

Page 31: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

4-1

Section 4: A Menu of Models for Electrocution Prediction, from Simple to Complex

How should electrocutions be predicted? As part of the answer to this question, it is important to consider the ever-present tradeoff between model simplicity and realism. This section gives a brief overview of three levels of detail that could be incorporated into an electrocution risk model (ERM). This is not speculation about the FWS approach. Rather it is a tour of the menu of options facing anyone charged with developing an ERM. What emerges is an argument for a fairly complex model in line with what FWS may be developing.

Simplest Approach

As late as 2012, organizations like the National Wind Coordinating Collaborative and the National Renewable Energy Laboratory discussed avian fatalities at wind farms in terms of collisions per turbine or per rotor-swept area. The current CRM is really a minor increase in complexity from this model of constant unit risk. The avoidance parameter of the CRM is a constant representing the rate of collisions per unit of eagle exposure per rotor-swept area. That rate is assumed to be the same everywhere. The major innovation of the CRM and the Band model on which it is based is that it incorporated site-specific eagle activity.

Electrocutions could be predicted in a similar manner. The simplest approach is to use a constant fatality rate per pole or kilometer of wire. However, a light case study quickly makes it clear that this approach will not work.

Brief Case Study of Constant Electrocution Rate Per Pole

Lehman et al. (2010) estimated a rate of 0.0036-0.0066 golden eagle fatalities/km/year due to electrocution in an area of the Intermountain West with a high density of high-risk pole configurations. To extrapolate this to a west-wide estimate of golden eagle fatalities, consider that there could be 165-203.5 million distribution poles in the United States (Loss et al. 2014). For simplicity, assume that all golden eagle electrocutions occur in the western states and that poles are distributed in proportion to the human population. The Census Bureau estimated that 316.2 million people lived in the United States in 2013, of which 23.5% resided in the western coterminous states. Holding the per-pole

A case study illustrates why using a constant fatality rate per pole or kilometer of wire does not work. Extrapolating a constant rate out to the entire Western U.S. suggests that a magnitude of 100,000-300,000 golden eagles would be electrocuted, but only 31,000 golden eagles have been estimated for the entire U.S. and FWS estimates there are only 504 electrocutions annually.

10399377

Page 32: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

4-2

electrocution rate constant suggests there are 140,000-315,000 golden eagle electrocutions annually. However, FWS estimates the entire national population of golden eagles to comprise only 31,000 individuals and suggests there are only 504 electrocutions annually (FWS 2016a).

Intermediate Complexity

The above case study is obviously limited in part by the use of an electrocution rate measured from an area with high-risk equipment. Risk factors for raptor electrocution on distribution poles are well understood. This knowledge has led to the development of best practices for new construction and retrofitting of older equipment (APLIC 2006). Retrofitting high-risk poles has the potential to greatly reduce eagle mortality (Janss and Ferrer 1999; Janss and Ferrer 2001).

A consideration of the types of pole configurations in a project is likely to show great gains in predictive performance over an electrocution risk model with a constant per-pole risk. With enough data relating existing pole configurations to eagle fatalities, a statistical model can be developed to forecast incidental take at proposed projects.

The equipment-based approach has limitations. Most notable is the challenge of cataloging pole inventory data, given the magnitude of distribution projects. Another limitation is that risk per configuration will not be the same everywhere. Factors contributing to spatial variation in risk include population density and habitat (Mojica et al. 2018).

The “Full Monty”

The most comprehensive approach to predicting electrocutions would consider local eagle abundance. To parameterize the ERM, statistical relationships between equipment and fatalities would need to be adjusted for local eagle population density. To use the ERM, eagle population density would need to be known along the route of new distribution projects.

As described in Section 3, enumerating eagles is difficult. Demands for eagle abundance data for both retrospective and forecasting analyses could be met using models that relate landscape and habitat characteristics to variation in eagle population density. Such models could reduce or eliminate the need for project-specific eagle surveys during pre-construction phases and would provide insight into areas of high risk.

FWS will consider eagle distribution or abundance along with equipment information when predicting incidental take by electrocution on distribution poles, placing their approach in the “full Monty” category of models described in this section.

With enough data relating existing pole configurations to eagle fatalities, a statistical model can be developed to forecast incidental take at proposed projects. Aggregating this inventory would be challenging. The approach would also be incomplete in that it ignores other risk factors.

The most comprehensive approach to predicting electrocutions would consider local eagle abundance.

10399377

Page 33: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

5-1

Section 5: Incidental Eagle Take at T&D Projects: An Overview

FWS has assembled a team to coordinate golden eagle research meant to support incidental take permitting. The group, called the Western Golden Eagle Team (WGET) has been working since 2013. WGET itself is small, with between four and eight FWS personnel on the team. But it has an extensive network of collaborators, including industry consultants, NGOs, and academic scientists (Woodbridge and Williams 2016; Woodbridge and Williams 2017).

The approach to predicting and managing take at T&D projects relies heavily on mathematical models and is comprehensively quantitative. One set of models projects eagle population density across the landscape. Additional models incorporate population and project information to predict electrocutions. As with wind, cumulative take is managed through local area population (LAP) analysis, and compensatory mitigation requirements are assessed through the use of a demographic model.

Most of the framework for wires is shared with that for wind (Figure 5-1). Besides the prediction of take, the only other difference from wind will be in post-construction fatality monitoring. The methods for this survey activity are as yet undecided. WGET team member Gary Williams mentioned an interest in drone technology for locating carcasses. However, we speculate that the fatality monitoring protocol will use study plots representing a subset of the project, just as monitoring at wind farms is performed near a subset of turbines.

The approach to predicting and managing take at T&D projects relies heavily on mathematical models and is comprehensively quantitative. One set of models projects eagle population density across the landscape. Additional models incorporate population and project information to predict electrocutions.

10399377

Page 34: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

5-2

Figure 5-1 Incidental take permitting for wind energy and T&D projects. Boxes extending across both columns indicate shared protocols.

Much of the work performed by WGET and its collaborators is now coming to press in the peer-reviewed literature. This includes an entire issue of the Journal of Raptor Research in 2017. That issue included papers on the following topics: Sources of fatality for mitigation (Allison 2012; Herring et al. 2017) Prey, diet, and reproduction (Bedrosian et al. 2017; Preston et al. 2017)

Management units with respect to eagle distribution and migration (Brown et al. 2017)

Electrocution at improper retrofitted poles (Dwyer et al. 2017)

Most of the framework for wires is shared with that for wind. Besides the prediction of take, the only other difference from wind will be in post-construction fatality monitoring.

Much of the work performed by FWS’ WGET group is now coming to press in the peer-reviewed literature, including an entire issue of the Journal of Raptor Research in 2017.

10399377

Page 35: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

5-3

Juvenile dispersal (Murphy et al. 2017) Impact of take for religious ceremonial purpose (Stahlecker et al. 2017)

Conservation action prioritization (Tack et al. 2017) Spatial demographic modeling (Wiens et al. 2017)

Other recent publications from the WGET group include a model to predict power pole density (Dwyer et al. 2016) and a review of risk factors for electrocution (Mojica et al. 2018). Other research efforts by FWS personnel continue to expand knowledge about eagle populations status, including a spatial model to predict summer activity based on the ongoing west-wide aerial eagle survey (Nielson et al. 2016).

Greater clarity in the approach to modeling both wind and wires will emerge as more papers come to press. More papers should be expected soon, as Williams indicated in February 2018 that FWS plans to release a full guidance document on eagles and wires in 18-24 months, or between August 2019 and February 2020.

A Note on Fatality Estimation

For both wind and wires, the number of carcasses identified is used to estimate the total number of fatalities under the assumption that only a fraction of such fatalities was found (Huso 2011). A recent development in fatality estimation is the extension of this logic to the case where no carcasses are found (Huso et al. 2015). That is, absence of evidence is not necessarily evidence of absence. As a result of this innovation, all projects are now estimated to have some fatality.

One point of speculation is particularly relevant to wires: the inflation factor for total electrocutions is likely to be large. If monitoring covers a smaller percentage of a project, the number of carcasses will be inflated more. The use of Huso’s non-zero assumption may therefore indicate an appreciable level of incidental take.

The zero-detect problem could be ameliorated in a number of ways, for instance by the incorporation of information about eagle population density that might give more or less credence to absence. However, if the same model of abundance is used to predict take and to estimate fatality, then fatality estimates cannot be used to train the prediction model. Established methodology around confirming extinction may provide a good reference for discerning absence. Optionally, survey effort could be kept high to minimize the inflation factor.

WGET personnel indicated plans to release a full guidance document on eagles and wires in 18-24 months.

FWS is now estimating some fatality where zero carcasses are found. For T&D, with significant length and likely low percent of area covered by mortality monitoring, the use of this non-zero assumption may indicate an appreciable level of incidental take.

10399377

Page 36: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

10399377

Page 37: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

6-1

Section 6: FWS Models for Eagle Distribution and Abundance

Previous sections (3 and 4) discussed how abundance may theoretically improve take predictions. This section describes efforts the FWS WGET group is taking to increase their understanding of local eagle population density. Their approach draws on a wide array of data sources to develop multiple models that will be considered in combination at points in the incidental take permitting process that consider abundance (Figure 6-1).

Figure 6-1 A diverse array of information and models will be used to better predict and manage incidental take of eagles.

The 2016 final rule states that FWS will improve its understanding of the “spatial and temporal variation in eagle density” (81 FR 91524). This effort will likely affect the LAP analysis for both wind and wires projects by changing the estimated number of eagles in the LAP. The current approach recognizes that each eagle management unit (EMU) differs in its regional eagle population size. However, FWS assumes population density is uniform within EMUs. Hence, a given local area overlapping 5% of an EMU is assumed to affect 5% of the eagles in that region. An improved understanding of how the relative abundance of eagles changes with landscape and habitat features will enable a more nuanced projection of the population size within the local area. A similar EPRI-funded effort by Friedenberg and Shoemaker (2014) highlighted that a habitat-based

10399377

Page 38: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

6-2

estimate of LAP size can deviate substantially from that based on the uniform assumption.

Using a habitat-based model of eagle population density can impact the permitting process. For example, in areas projected to have high eagle density, a given amount of take will now represent a smaller percentage of the LAP and is therefore less likely to trigger a NEPA analysis.

Three models are being developed to improve the assessment of spatial and seasonal variation in eagle abundance (Figure 6-2). The methods differ for each model, as do the data sources.

Figure 6-2 Three habitat models intended to improve the assessment of spatial and seasonal variation in eagle abundance. Image sources: breeding (Woodbridge and Williams 2017), winter and migration (Woodbridge and Williams 2016).

Breeding Habitat Model

FWS is using an enormous database of nest locations assembled from multiple studies. The database now includes more than 107,000 nests (Williams 2017). Nest surveys tend to concentrate on finding as many nests as possible and only report locations where nests are found. A habitat suitability model based on nest locations is therefore restricted to using presence-only data, meaning it has no information about the frequency with which nests are associated with particular habitats. Hence, such models cannot directly predict abundance. However, they can be taken as a measure of relative abundance. FWS will use the breeding habitat model to assess the relative abundance of EMU residents during the summer months. The model is fitted separately for each EMU, allowing different landscape features to drive the eagle distribution in different regions.

bree

ding

win

ter

mig

ratio

n

FWS has amassed an enormous database of more than 107,000 nest locations assembled from multiple sources.

10399377

Page 39: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

6-3

Winter Habitat Model

The winter distribution model has more data inputs and differs from the modeling approach used for breeding habitat. Data from multiple surveys and citizen science reports (eBird) are used to establish a history of presence and absence in each 100-km2 cell of a 10-km grid. This history is used to estimate a probability of occupancy in each cell of the grid. Occupancy is then related to landscape variables using a machine learning technique called boosted regression trees (Williams 2017). Images portraying preliminary results look somewhat like a more spread-out version of the breeding habitat model. As with the breeding model, FWS will use the winter model to assess the relative abundance of eagles within each EMU.

Migratory Habitat Model

Less detail is available about the migratory habitat model. Data from satellite-tracked golden eagles will be used to describe patterns of migratory movements and then to develop a habitat-based model that may delineate habitat where migrants travel or locations where they are likely to settle. It is not clear whether this model would be used to add further information about the number of winter migrants in the LAP or if its use will be restricted to delineating migratory corridors.

A recent study used the telemetry data to look at the correspondence between eagle migrations and various regional networks such as EMUs or landscape conservation cooperatives (Brown et al. 2017).

The winter distribution model includes use of citizen science observations (eBird) and machine learning to estimate probability of occupancy in relation to landscape variables.

Data from satellite-tracked golden eagles will be used to describe patterns of migratory movements and then to develop a habitat-based model that may delineate habitat where migrants travel or locations where they are likely to settle.

10399377

Page 40: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

10399377

Page 41: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

7-1

Section 7: FWS Approaches to Predicting Electrocutions

This section describes the FWS WGET efforts to improve understanding of the risk of eagle electrocution at distribution projects. From the range of theoretical approaches that could be taken (described in Section 4), FWS has chosen a complex model that considers both equipment factors and eagle habitat. Electrocution prediction is the most obvious way in which a T&D-specific protocol will differ from that for wind farms, though it will contribute to decision-making under a cumulative take management framework that encompasses both activities (Figure 7-1).

Figure 7-1 Power pole density may be used as a proxy for more detailed equipment inventory in a model that predicts golden eagle electrocutions at distribution projects.

Raptor electrocution on distribution lines is a well-studied topic. This research led to industry guidelines for best practices in distribution design (APLIC 2006) and informs the only compensatory mitigation measure developed so far for the permitted eagle take, pole retrofitting (FWS 2013).

10399377

Page 42: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

7-2

Risk Factors

Equipment

Factors contributing to electrocution were comprehensively reviewed by Mojica et al. (2018). The foremost risk factor for electrocution of raptors generally and golden eagles specifically is pole configuration, with equipment-bearing poles representing the greatest risk. Three methods of retrofitting can reduce or eliminate the chance of electrocution on risky poles (Dwyer et al. 2017). One of these is greater separation between contact points such that even a large raptor like a golden eagle cannot touch two energized components simultaneously. Insulation can also prevent direct contact with energized components, but this approach requires maintenance. Finally, structures added to poles can redirect eagles away from energized contact points by providing a safe perch or discouraging perching.

Age

Beyond the danger represented by equipment, the Mojica et al. review (2018) highlighted the strong bias toward juvenile eagles among electrocution fatalities. Of the 148 fatalities in their dataset, 53% were juveniles. However, even this number does not convey the extent to which electrocution risk is age-biased.

To get a better sense of the relative risk for electrocution among age classes of eagle, we ran simulations of eagle population dynamics representative of a typical golden eagle population in the United States. We used the survival and fecundity parameters reported in the FWS eagle status update (FWS 2016a). Simulations were performed in RAMAS Metapop (Akçakaya and Root 2013) using a published custom module for territorial raptors (Monzón and Friedenberg 2018). Results were averaged over 1000 replicate population projections (Table 7-1). Juveniles are the rarest age class. Golden eagle populations are dominated by adults, which makes sense given their long life span and relatively low annual production of young. When the high rate of juveniles among fatalities is combined with their rarity in the population, we see that a juvenile is 15 times more prone to electrocution than an adult (Table 7-1). Subadults are also at elevated risk at four times the adult rate.

Our analysis indicates juvenile golden eagles are 15 times more prone to electrocution by distribution equipment than are adults.

10399377

Page 43: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

7-3

Table 7-1 Simulation results: electrocution risk by age class

Stage Percent of populationa

Percent of electrocutions

Relative per capita riskb

Juvenile 12% 53% 15

Subadult 20% 27% 4

Adult 68% 20% 1 a Age distribution calculated using FWS survival and fecundity parameters (FWS 2016a) in a stochastic simulation using the territorial life history model of Monzón and Friedenberg (2018). b Per capita rate of electrocution relative to adults.

The age bias in electrocution fatalities has conservation implications. First, it suggests that juvenile survival could be greatly enhanced through retrofitting or guidance-compliant new construction. As an example, a study of imperial eagles in Spain found electrocution risk of juveniles to be 23 times that of adults on a per capita basis (Janss and Ferrer 2001). Retrofitting about one-fifth of poles in the area was projected to reduce total fatality by over 50%, most of which would represent increased juvenile survival.

A second conservation implication of the age bias in electrocutions is that their reduction may not have as great a benefit for the population as one might expect. For long-lived species with delayed maturation, the general rule is that adult survival is the highest-priority target for conservation. A small increase in adult survival has a far larger effect on population growth rate than does a similar increase for juveniles. A recent study suggested this rule holds true for golden eagles, as well (Tack et al. 2017).

The current approach to resource equivalency analysis (REA) of pole retrofitting assumes there is no age bias among electrocutions; fatalities are proportional to age class abundance (FWS 2013). If FWS incorporates information on age bias in its REA for retrofitting, a greater amount of compensatory mitigation will be necessary to offset a given amount of projected incidental take.

However, FWS could also incorporate the juvenile bias of electrocutions into its assessment of golden eagle population status. A shift in the attribution of existing levels of mortality toward juveniles will result in improved population growth characteristics.

Deciding on an Electrocution Model

Note: This and the following subsections address uncertain aspects of the emerging framework. Statements about FWS intentions or approaches should be treated as forward-looking and therefore subject to modification.

A small increase in adult survival has a far larger effect on population growth rate than does a similar increase for juveniles.

FWS will likely initially use a model predicting power pole density (PPD) to predict electrocutions. A GIS inventory of distribution poles would be needed before equipment-specific risks can be part of the prediction.

10399377

Page 44: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

7-4

WGET researchers face real-world limitations on their ability to develop the ideal modeling framework to predict electrocutions. Their ideal would make use of spatially referenced information detailing pole locations and equipment (G. Williams, pers. comm.). We speculate that a comprehensive dataset on fatalities collected as part of a statistically sound survey effort would inform a statistical model that related landscape characteristics, habitat, eagle abundance, and pole configuration to the risk of a fatality. Unfortunately, neither the GIS database of poles nor the perfect study of electrocution risk is available.

A decision on how electrocutions will be predicted has not yet been made. Based on our interpretation of statements from WGET personnel and the group’s dissemination products, it appears likely that an initial approach—using what information is currently available—will be improved or replaced over time as more data are gathered. The likely initial approach uses power pole density (PPD) as a measure of project complexity. WGET has been developing a model to predict PPD based on landscape features (Dwyer et al. 2016). Fatality data collected at projects of differing PPD can then be used to train a statistical model that uses PPD to predict the number of fatalities in any area. We expect the resulting function will predict that the rate of fatalities per pole increases with PPD, as more complex distribution projects likely include disproportionately more high-risk pole configurations (Dwyer et al. 2016; Williams 2017).

It is not clear yet how eagle abundance or distribution information will enter the electrocution model. An ongoing study in cooperation with Powder River Energy Corporation is examining how the hazard quantified in PPD and the habitat value quantified in the golden eagle distribution models (Section 6) combine to predict electrocutions (Williams 2017). The approach may simply identify high-risk areas as those with high habitat value. Alternatively, electrocution may be considered as a per capita rate derived from PPD that is then applied to an estimate of local population size obtained from the distribution models following a method similar to that used in LAP analyses.

Project-Specific Pre-Construction Monitoring

It is not yet decided whether pre-construction monitoring will be required. We surmise that it has therefore also not been decided what such monitoring would entail. Options being considered are to require monitoring at all proposed project locations or only at those where certain conditions indicate the need. What those conditions might be is unclear.

One reason for a possible shift away from project-specific monitoring is that the large-scale spatial models being used to predict eagle abundance and electrocution risk may benefit more from systematic regional surveys. Permit applicants may pay a fee to support such regional programs. It is not yet clear who would administer the surveys, what information they would collect, or how they would be designed.

FWS has not yet decided whether pre-construction monitoring will be required at all projects or at a subset of projects that meet certain conditions.

10399377

Page 45: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

8-1

Section 8: Mitigation The 2016 final rule confirmed that compensatory mitigation is required for all incidental take of golden eagles and cumulative take in excess of 5% of the local area population of bald eagles. Mitigation actions are agnostic to the cause of incidental take, meaning that the options for compensatory mitigation of wind turbine collision fatalities or distribution line electrocutions is the same. Differences in the process will enter in how fatalities are predicted (Figure 8-1). Theoretically, differences in the amount of mitigation required per fatality could also arise from activity-specific adjustments to the models used to calculate impacts to the population and the unit benefit of mitigation (Figure 8-1).

Figure 8-1 The mitigation assessment framework will be similar for wind and wires.

Mitigation Ratio

The 2016 final rule confirms a continued use of a 1.2:1 mitigation ratio. This ratio is applied to the future production foregone associated with projected take. The final rule did not indicate activity-specific changes in the assumptions of resource equivalency analysis. However, we speculate that the strong juvenile bias in electrocutions (Lehman et al. 2010) could warrant a wires-specific computation of production foregone.

10399377

Page 46: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

8-2

New Mitigation Options on the Horizon

To date, pole retrofitting remains the only compensatory mitigation option that has been fully developed. However, WGET is supporting research to identify and quantify sources of mortality that could be targets for mitigation. This work is being coordinated by the American Wind Wildlife Institute (AWWI). They are focused on reducing lead poisoning from ammunition fragments left in animal remains, reducing vehicle strikes by removing roadkill that attracts eagles, improving reproductive success and survival through prey management, nest site improvements, and the rehabilitation of injured or diseased eagles (Allison 2012). They have published a quantitative approach to mitigation credits for reduced lead poisoning (Cochrane et al. 2015).

A Future for Mitigation Banking

Mitigation can be performed in a location removed from the wind or wires project, and third-party mitigation is allowed. These rules create an informal fee-based system for mitigation. FWS is open to the development of formal systems for fee-based mitigation as well as mitigation banking (Allison et al. 2017).

Mitigation Roll-Over

Projects with incidental take permits exceeding 5 years have 5-year reviews of post-construction fatality estimates. If the estimates are lower than expected, excess mitigation can be rolled into the next 5-year period. This roll-over option will likely be used often, for two reasons. The first is that the permitted take is intentionally inflated by using the upper 80% confidence limit of predicted fatalities. This inflation is conservative both in terms of protecting eagle populations and in terms of minimizing the regulatory risk associated with exceeding permitted take. Roll-over is also likely to be common because permittees are encouraged to “front-load” their mitigation efforts, making mitigation excessive in the early years of the permit.

To date, pole retrofitting remains the only compensatory mitigation option that has been fully developed. However, WGET is supporting research (in coordination with the American Wind Wildlife Institute) to identify and quantify sources of mortality that could be targets for mitigation.

10399377

Page 47: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

9-1

Section 9: Conclusion and Opportunities The developing framework for managing incidental take of eagles is highly quantitative. A multi-model framework built on a very large amount of data will be used (Figures 6-1, 7-1, and 8-1). Parts of this framework contribute to a general understanding of eagle populations, such as their distribution, abundance, and robustness to additional sources of fatality. These will be applied across types of activities, including wind and wires.

Other parts of the framework will be activity-specific. For T&D projects, electrocution will be predicted using different models than wind turbine collisions. These models will have unique data requirements. It appears that there will be a shift toward regional monitoring programs supported by fees paid by permit applicants and a simultaneous shift away from pre-permit, project-specific monitoring.

A Work in Progress

Several aspects of the developing framework remain undecided. Prominent among these are: Whether project-specific monitoring will be required at all projects or only

on a conditional basis,

How electrocutions will be predicted, and How post-construction monitoring will be conducted.

These points and others will need to be decided quickly if FWS plans to adhere to its timetable of releasing full guidance for T&D eagle take permitting between August 2019 and February 2020.

Opportunity

The high data demand of the models being developed, along with the complexity and magnitude of T&D projects, introduces significant opportunities for industry-agency cooperation in research as well as electric power industry leadership of programs that will cross service areas and jurisdictions.

Three general areas in which the electric power industry may be in a position to contribute to the data and organization demanded by the emerging eagles framework are inventory data collection, fatality monitoring, and eagle population data.

Significant opportunities exist for research as well as leadership of programs that will cross service areas and jurisdictions.

10399377

Page 48: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

9-2

T&D Inventory Data

While FWS appears to be focused on initially using power pole density as a predictor of electrocution hazard, they indicated a preference for using more detailed information on the actual location and configuration of poles. This information needs to be gathered across the range of golden eagles, though it would be most useful to coordinate early inventory efforts with eagle fatality surveys so that the pole data and fatality data can contribute to an understanding of configuration-specific electrocution rates.

Using pole location and configuration data has distinct advantages over predicted pole density. For instance, it delivers electrocution predictions that account for eagle-friendly equipment options. The existence of a comprehensive pole database also provides a means for identifying high-risk poles that are good targets for a compensatory mitigation plan.

Electric utilities and their contractors have the training to take inventory and contribute data to regional or national GIS databases. Utilities may also be able to coordinate and administer inventory programs that cross service areas and address under-resourced areas served by co-ops. There may also be the possibility of deriving a dataset of pole location and configuration via imagery (e.g., satellite, Google Street View) and automated image classification, although technical capability is uncertain.

Fatality Monitoring

The protocol for post-construction fatality monitoring at T&D projects is not yet clear. Stakeholders may be able to contribute to the design and validation of monitoring protocols. WGET personnel expressed interest in technology that could enable more comprehensive or accurate fatality monitoring at T&D projects, such as the use of drones or aerial imagery in combination with artificial intelligence for carcass identification. However, a statistically sound sampling design is likely to achieve greater cost savings in the short term.

Eagle Population Data

Management of all sources of incidental take could be improved with a firmer understanding of the number and distribution of eagles. Data on eagles gathered during routine surveys of T&D projects could contribute to this understanding, particularly if collected using a standardized protocol and entered into a shared repository.

Importantly, FWS has not tailored a set of models to bald eagles. The incidental take frameworks for both wind and T&D are built largely around research on golden eagles. Industry could contribute to the development of a parallel set of models and parameters for bald eagles, likely facilitating better management outcomes. Even with the release of new priors for the wind collision model that are specific to bald eagles, there is a need for an improved understanding of the factors that determine site-specific risks.

10399377

Page 49: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

10-1

Section 10: References Akçakaya, H. R., and W. Root. 2013. RAMAS Metapop: viability analysis for

stage-structured metapopulations (Version 6). Applied Biomathematics, Setauket, NY.

Allison, T. D. 2012. Eagles and Wind Energy: Identifying Research Priorities. American Wind Wildlife Institute, Washington, DC.

Allison, T. D., J. F. Cochrane, E. Lonsdorf, and C. Sanders-Reed. 2017. A review of options for mitigating take of golden eagles at wind energy facilities. Journal of Raptor Research 51:319-333.

APLIC. 2006. Suggested practices for avian protection on power lines: the state of the art in 2006, Edison Electric Institute, Avian Power Line Interaction Committee, Washington D.C. and the California Energy Commission, Sacramento, CA.

Band, W., M. Madders, and D. P. Whitfield. 2007. Developing field and analytical methods to assess avian collision risk at wind farms, pages 259-275 in M. De Lucas, G. F. E. Janss, and M. Ferrer, eds. Birds and Wind Farms: Risk Assessment and Mitigation. Madrid, Quercus.

Bay, K., K. Nasman, W. Erickson, K. Taylor, and K. Kosciuch. 2016. Predicting eagle fatalities at wind facilities. Journal of Wildlife Management 80:1000-1010.

Bedrosian, G., J. W. Watson, K. Steenhof, M. N. Kochert, C. R. Preston, B. Woodbridge, G. E. Williams et al. 2017. Spatial and temporal patterns in golden eagle diets in the western United States, with implications for conservation planning. Journal of Raptor Research 51:347-367.

Brown, J. L., B. Bedrosian, D. A. Bell, M. A. Braham, J. Cooper, R. H. Crandall, J. DiDonato et al. 2017. Patterns of spatial distribution of golden eagles across North America: how do they fit into existing landscape-scale mapping systems? Journal of Raptor Research 51:197-215.

Cochrane, J. F., E. Lonsdorf, T. D. Allison, and C. A. Sanders-Reed. 2015. Modeling with uncertain science: estimating mitigation credits from abating lead poisoning in golden eagles. Ecological Applications 25:1518-1533.

10399377

Page 50: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

10-2

de Lucas, M., G. F. E. Janss, D. P. Whitfield, and M. Ferrer. 2008. Collision fatality of raptors in wind farms does not depend on raptor abundance. Journal of Applied Ecology 45:1695-1703.

Dwyer, J. F., R. E. Harness, and D. Eccleston. 2017. Avian electrocutions on incorrectly retrofitted power poles. Journal of Raptor Research 51:293-304.

Dwyer, J. F., R. E. Harness, B. D. Gerber, M. A. Landon, P. Petersen, D. D. Austin, B. Woodbridge et al. 2016. Power pole density informs spatial prioritization for mitigating avian electrocution. Journal of Wildlife Management 80:634-642.

Friedenberg, N. A., and K. T. Shoemaker. 2014. Population-level impacts of wind energy development on golden eagles (Aquila chrysaetos): a framework for quantitative risk assessment. EPRI, Palo Alto, California. 3002004770.

FWS. 2009. Final Environmental Assessment: Proposal to Permit Take Provided Under the Bald and Golden Eagle Protection Act. Washington, D.C., U.S. Fish and Wildlife Service.

FWS. 2013. Eagle Conservation Plan Guidance Module 1 - Land-based Wind Energy. Version 2. Washington, D.C., Division of Migratory Bird Management, U.S. Fish and Wildlife Service.

FWS. 2016a. Bald and golden eagles: population demographics and estimation of sustainable take in the United States, 2016 update. Washington, D.C., Division of Migratory Bird Management.

FWS. 2016b. Final Rule: Eagle permits; revisions to regulations for eagle incidental take and take of eagle nests. Federal Register 81:91494-91554.

Herring, G., C. A. Eagles-Smith, and J. Buck. 2017. Chatacterizing golden eagle risk to lead and anticoagulant rodenticide exposure: a review. Journal of Raptor Research 51:273-292.

Hunt, G. 2002. Golden eagles in a perilous landscape: predicting the effects of mitigation for wind turbine blade-strike mortality. Predatory Bird Research Group, University of California, Santa Cruz, Report P500-02-043F to Public Interest Energy Research, California Energy Commission.

Huso, M. 2011. An estimator of wildlife fatality from observed carcasses. Environmentrics 22:318-329.

Huso, M., D. Dalthorp, D. Dail, and L. Madsen. 2015. Estimating wind-turbine-caused bird and bat fatality when zero carcasses are observed. Ecological Applications 25:1213-1225.

Janss, G. F. E., and M. Ferrer. 1999. Mitigation of raptor electrocution on steel power poles. Wildlife Society Bulletin 27:263-273.

10399377

Page 51: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

10-3

Janss, G. F. E., and M. Ferrer. 2001. Avian electrocution mortality in relation to pole design and adjacent habitat in Spain. Bird Conservation International 11:3-12.

Lehman, R. N., J. A. Savidge, P. L. Kennedy, and R. E. Harness. 2010. Raptor electrocution rates for a utility in the intermountain western United States. Journal of Wildlife Management 74:459-470.

Loss, S. R., T. Will, and P. P. Marra. 2014. Refining estimates of bird collision and electrocution mortality at power lines in the United States. Plos One 9.

Mojica, E. K., J. F. Dwyer, R. E. Harness, G. E. Williams, and B. Woodbridge. 2018. Review and synthesis of research investigating golden eagle electrocutions. Journal of Wildlife Management 82:495-506.

Monzón, J., and N. A. Friedenberg. 2018. Metrics of popualtion status for long-lived territorial birds: a case study of golden eagle demography. Biological Conservation 220:280-289.

Murphy, R. K., J. R. Dunk, B. Woodbridge, D. W. Stahlecker, D. W. LaPlante, B. A. Millsap, and K. V. Jacobson. 2017. First-year dispersal of golden eagles from natal areas in the southwestern United States and implications for second-year settling. Journal of Raptor Research 51:216-233.

New, L., E. Bjerre, B. Millsap, M. C. Otto, and M. C. Runge. 2015. A collision risk model to predict avian fatalities at wind facilities: an example using golden eagles, Aquila chrysaetos. Plos One 10.

Nielson, R. M., R. K. Murphy, B. A. Millsap, W. H. Howe, and G. Gardner. 2016. Modeling late-summer distribution of golden eagles (Aquila chrysaetos) in the Western United States. Plos One 11:e0159271.

Preston, C. R., R. E. Jones, and N. S. Horton. 2017. Golden eagle diet breadth and reproduction in relation to fluctuations in primary prey abundance in Wyoming's Bighorn Basin. Journal of Raptor Research 51:334-346.

Smales, I., S. Muir, C. Meredith, and R. Baird. 2013. A description of the Biosis model to assess risk of bird collisions with wind turbines. Wildlife Society Bulletin 37:59-65.

Stahlecker, D. W., Z. P. Wallace, D. G. Mikesic, and C. S. Smith. 2017. Does Hopi religious harvest of eaglets affect golden eagle territory occupancy and reproduction on the Navajo Nation? Journal of Raptor Research 51:305-318.

Tack, J. D., B. R. Noon, Z. H. Bowen, L. Strybos, and B. C. Fedy. 2017. No substitute for survival: perturbation analyses using a golden eagle population model reveal limits to managing for take. Journal of Raptor Research 51:258-272.

10399377

Page 52: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

10-4

Whitfield, D. 2009. Collision avoidance of golden eagles at wind farms under the "Band" collision risk model. Report to Scottish Natural Heritage. Banchory, UK, Natural Research Ltd.

Wiens, J. D., N. H. Schumaker, R. D. Inman, T. C. Esque, K. M. Longshore, and K. E. Nussear. 2017. Spatial demographic models to inform conservation planning of golden eagles in renewable energy landscapes. Journal of Raptor Research 51:234-257.

Williams, G. 2017. Existing data and the use of models: golden eagle distribution, hazards, and conservation planning. Western Golden Eagle Team presentation slides downloaded 3/20/2018.

Woodbridge, B. 2015. Predictive models for golden eagle conservation planning and renewable energy development in the western United States. Western Golden Eagle Team presentation from the Febraury 15, 2015 WINDExchange webinar, downloaded 3/20/2018.

Woodbridge, B., and G. Williams. 2016. Western Golden Eagle Team FY15 Progress Report.

Woodbridge, B., and G. Williams. 2017. Western Golden Eagle Team FY2016 Progress Report.

10399377

Page 53: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

10399377

Page 54: From Wind to Wires wind to wires 2018... · 2019. 4. 18. · EPRI Project Manager B. Madsen 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813

Electric Power Research Institute 3420 Hillview Avenue, Palo Alto, California 94304-1338 • PO Box 10412, Palo Alto, California 94303-0813 USA

800.313.3774 • 650.855.2121 • [email protected] • www.epri.com

© 2018 Electric Power Research Institute (EPRI), Inc. All rights reserved. Electric Power Research Institute, EPRI, and TOGETHER...SHAPING THE FUTURE OF ELECTRICITY are registered service marks of the Electric Power Research Institute, Inc.

Export Control RestrictionsAccess to and use of this EPRI product is granted with

the specific understanding and requirement that respon-

sibility for ensuring full compliance with all applicable

U.S. and foreign export laws and regulations is being

undertaken by you and your company. This includes an obligation to

ensure that any individual receiving access hereunder who is not a U.S.

citizen or U.S. permanent resident is permitted access under applicable

U.S. and foreign export laws and regulations.

In the event you are uncertain whether you or your company may law-

fully obtain access to this EPRI product, you acknowledge that it is your

obligation to consult with your company’s legal counsel to determine

whether this access is lawful. Although EPRI may make available on

a case by case basis an informal assessment of the applicable U.S.

export classification for specific EPRI products, you and your company

acknowledge that this assessment is solely for informational purposes

and not for reliance purposes.

Your obligations regarding U.S. export control requirements apply dur-

ing and after you and your company’s engagement with EPRI. To be

clear, the obligations continue after your retirement or other departure

from your company, and include any knowledge retained after gaining

access to EPRI products.

You and your company understand and acknowledge your obligations

to make a prompt report to EPRI and the appropriate authorities regard-

ing any access to or use of this EPRI product hereunder that may be in

violation of applicable U.S. or foreign export laws or regulations.

The Electric Power Research Institute, Inc. (EPRI, www.epri.com)

conducts research and development relating to the generation, delivery

and use of electricity for the benefit of the public. An independent,

nonprofit organization, EPRI brings together its scientists and engineers

as well as experts from academia and industry to help address

challenges in electricity, including reliability, efficiency, affordability,

health, safety and the environment. EPRI members represent 90% of the

electric utility revenue in the United States with international participation

in 35 countries. EPRI’s principal offices and laboratories are located in

Palo Alto, Calif.; Charlotte, N.C.; Knoxville, Tenn.; and Lenox, Mass.

Together...Shaping the Future of Electricity

3002014192

10399377