fuelcellapplicationspresentation
DESCRIPTION
TRANSCRIPT
ers energy&resource solutions © 2003 ERS, Inc.
Assessment of Fuel Cell Applications for Assessment of Fuel Cell Applications for Critical Industrial ProcessesCritical Industrial Processes
presented byDan Birleanu
ERS
ACEEE Summer Study on Energy Efficiency in IndustryAugust 2003
ers energy&resource solutions © 2003 ERS, Inc.
Assessment of Fuel Cell Applications for Assessment of Fuel Cell Applications for Critical Industrial ProcessesCritical Industrial Processes
Power Quality and Critical Applications
Premium Power Equipment
Overview of Fuel Cell Technology
Fuel Cells Current Challenges
Feasibility Assessment Methodology
Case Study: Semiconductor Crystal Growth Facility
Conclusions
ers energy&resource solutions © 2003 ERS, Inc.
High Voltage Spikes and Surges
Low Voltage Electrical Noise
Harmonics
Voltage Fluctuations
Power Outages and Interruptions
Power Quality and Critical ApplicationsPower Quality and Critical Applications
ers energy&resource solutions © 2003 ERS, Inc.
Medical Treatment Facilities
Advanced Manufacturing Facilities
Communication and Data Centers
High-Security Facilities
Remote Sites
Air Traffic Control Facilities
Power Quality and Critical Applications Power Quality and Critical Applications (cont.)(cont.)
ers energy&resource solutions © 2003 ERS, Inc.
RequirementsAvailability: Respond in Milliseconds without Significant Distortions
Reliability: 99.999…%
Maintainability: Easily Accessible while Maintaining Availability
TechnologiesEnergy Storage: Batteries, Flywheel, Super-capacitors, Super-conducting Magnetic Energy Storage (SMES), Compressed Air Storage (CAES)
Back-up Power: Generator Sets, Micro-turbines, Small Gas Turbines, Fuel Cells.
Premium Power EquipmentPremium Power Equipment
ers energy&resource solutions © 2003 ERS, Inc.
PAFC PEMFC MCFC SOFC Size Range 100-200 kW 3-250 kW 250 kW - 10 MW 1 kW - 10 MW Fuel Hydrogen, Natural
Gas, Landfill Gas, Digester Gas, Propane
Natural Gas, Hydrogen, Propane,
Diesel
Natural Gas, Hydrogen
Natural Gas, Hydrogen, Landfill Gas, Fuel Oil
Capacity 0.1-0.3 W/cm2 0.6-0.8 W/cm2 0.1-0.2 W/cm2 0.3-0.5 W/cm2 Efficiency 36-42% 30-40% 45-55% 45-60% Environment Nearly zero emissions
(when running on H2) Nearly zero emissions (when running on H2)
Nearly zero emissions (when running on H2)
Nearly zero emissions (when running on H2)
Other Features
Cogeneration (Hot Water)
Cogeneration (Hot Water)
Cogeneration (Hot Water or Steam)
Cogeneration (Hot Water or Steam)
Estimative Cost
$4,000 per kW $5,000 per kW $2,000-$4,000 per kW
$1,300 per kW (Desired)
Commercial Status
Available Pre-commercial Pre-commercial Pre-commercial
Strengths Quiet Low Emissions High Efficiency
Proven Reliability
Quiet Low Emissions High Efficiency
Quiet Low Emissions High Efficiency
Quiet Low Emissions High Efficiency
Weaknesses High Cost High Cost Need to Demonstrate
Limited Field Test Experience
High Cost Need to Demonstrate
High Cost Need to Demonstrate
Overview of Fuel Cell TechnologyOverview of Fuel Cell Technology
ers energy&resource solutions © 2003 ERS, Inc.
PAFC Reduction of manufacturing and operating costs Further improved durability and reliability Reducing space requirements Improving heat recovery potentials Staying economically competitive with other fuel cell technologies as they mature
PEMFC Reduction of manufacturing and operating costs Understanding the influences of operating conditions Understanding transient load response Improve fuel processing to accommodate different type of fuels Improve cold-start Catalyst loading
MCFC Reduction of manufacturing and operating costs Reducing the rate of cathode dissolution Improve retention of the electrolyte Improving resistance to catalyst poisoning
SOFC Reduction of manufacturing and operating costs Identifying configurations that require less stringent material purity specifications Use of less exotic alloys, which is directly related to the high operating temperature Maintenance of seals and manifolds under severe thermal stresses
Fuel Cells Current ChallengesFuel Cells Current Challenges
ers energy&resource solutions © 2003 ERS, Inc.
Description of the Operation and Need for Premium PowerApplicable End Uses and Equipment
Utility Usage
Outage and Low Power Quality History
Technical Impacts of Downtime
Cost Impacts of Outage and Low Power Quality Incidents
Capital Project Financing and Investment Requirements
Assessment of Power QualityCritical Equipment Service Lines
Tolerance Range of Critical Equipment
Impact Assessment of Power Quality
Feasibility Assessment MethodologyFeasibility Assessment Methodology
ers energy&resource solutions © 2003 ERS, Inc.
Assessment of Economic Losses Associated with Power Reliability and Power Quality Problems
Estimates of Economic Impacts
Technical and Economic Scenarios
Research and Review of the Premium Power Systems Technical Options
Review of Premium Power Systems
Considered Technologies: Features and Advantages
Preliminary Technical and Economic Screening of OptionsSimplified Estimates of Energy Impacts
Simplified Estimates of Costs
Simplified Estimates of Economic Impacts
Feasibility Assessment Methodology Feasibility Assessment Methodology (cont.)(cont.)
ers energy&resource solutions © 2003 ERS, Inc.
Preparation of Conceptual Design for Cost-Effective Application
Site-Specific Systems Components
Desired Location Requirements
Detailed Conceptual Design
System Cost Estimation
Detailed Energy, Environmental and Economic AnalysesSystem Modeling
Environmental Impact
Life Cycle Cost Analyses
Feasibility Assessment Methodology Feasibility Assessment Methodology (cont.)(cont.)
ers energy&resource solutions © 2003 ERS, Inc.
Molecular Beam Epitaxy (MBE) Process
Facility DescriptorsDemand: 2.5 MW
Critical Demand: 1.5 MW
Energy Usage: 20 million kWh annually
Two Separate Feeding Circuits from the Utility Network
UPS Batteries Capacity: 600 kW
Emergency Generators Capacity: 1.5 MW
Critical SystemsUltra-High Vacuum System
Heating System (Crystal Growth Process @ 1,700 F)
Cooling System (1,700 Tons)
Case Study: Semiconductor Crystal Case Study: Semiconductor Crystal Growth FacilityGrowth Facility
ers energy&resource solutions © 2003 ERS, Inc.
Power Quality IncidentsSeven Separate Power Outages in 2001
Voltage Sags
Over Voltages
Impact of Power Quality IncidentsShutdown of Crystal Growth Process
Process Resume Takes Several Hours
Labor Costs: $50,000 per hour
Material Losses: up to $500,000 per hour
Case Study: Semiconductor Crystal Case Study: Semiconductor Crystal Growth Facility (cont.)Growth Facility (cont.)
ers energy&resource solutions © 2003 ERS, Inc.
PAFC Proven reliability: installations in different locations all over the world with many hours of successful operation
Commercially available in sizes that are attractive for the facility (200 kW) For premium power, requires a reliable source of fuel To make it highly cost-effective, requires cogeneration opportunities - which
may not be present PEMFC Not sufficiently proven for this application
Commercially available in sizes too small (maximum 50 kW) For premium power, requires a reliable source of fuel To make it highly cost-effective, requires cogeneration opportunities - which
may not be present MCFC Not sufficiently proven for this application
Still in the pre-commercial stage For premium power, requires a reliable source of fuel Can produce steam, which could be used in absorption chillers – would require
chiller replacement SOFC Not sufficiently proven for this application
Still in the pre-commercial stage For premium power, requires a reliable source of fuel Can produce steam, which could be used in absorption chillers – would require
chiller replacement
Case Study: Semiconductor Crystal Case Study: Semiconductor Crystal Growth Facility (cont.)Growth Facility (cont.)
ers energy&resource solutions © 2003 ERS, Inc.
Selected Fuel Cell System: UTC Fuel Cells PC25Rated electrical Capacity: 200 kW/235 kVA
Thermal Capacity: 900,000 Btu/h @ 140 F
Efficiency (LHV): 37% Electric and 50% Thermal
Natural Gas Consumption: 2,100 cu.ft./hour
Emissions: <2 ppm CO, <1 ppm NOx, negligible SOx
Proposed Premium Power System Characteristics and Cost Integration of the Fuel Cells with the Existing Back-up System
Eight (8) Fuel Cell Units
Fuel Cells Will Operate 8,000 hours/year
Total Estimated Cost: $9,600,000
Case Study: Semiconductor Crystal Case Study: Semiconductor Crystal Growth Facility (cont.)Growth Facility (cont.)
ers energy&resource solutions © 2003 ERS, Inc.
Case Study: Semiconductor Crystal Case Study: Semiconductor Crystal Growth Facility (cont.)Growth Facility (cont.)
0
2
4
6
8
10
12
14
16
$500,000 $750,000 $1,000,000 $1,250,000 $1,500,000 $1,750,000 $2,000,000
Total Annual Cost of Losses Due to Power Q uality Issues
Payb
ack
Peri
od [y
ears
]
Payback Period for the Fuel Cell System vs. Cost of LossesAverage Prices (Northeast): Natural Gas – $6.38/ccf and Electricity – $0.0772/kWh
ers energy&resource solutions © 2003 ERS, Inc.
PAFC and PEMFC Could Provide Clean and Reliable Power for Critical Industrial Applications
Installation Costs Represent a Considerable Barrier to Widespread Commercialization of the Available Fuel Cell Systems
Cost-effectiveness of the Large Fuel Cell Based Premium Power Application Rises in the Probability that Major Events with High Impact on Company’s Revenues Occur
Very Critical Operations (Communication/Data Centers, Financial Transaction Operations, High-Tech Manufacturing Facilities) are the most Suitable Applications for Future Implementation of These Systems
ConclusionsConclusions
ers energy&resource solutions © 2003 ERS, Inc.
Assessment of Fuel Cell Applications for Assessment of Fuel Cell Applications for Critical Industrial ProcessesCritical Industrial Processes
Thank you!
Questions?