functional safety demystified - iica · pdf file17/09/2014 4 iec 61508 or iec 61511...

31
17/09/2014 1 Functional Safety Demystified BOB WEISS - FUNCTIONAL SAFETY CONSULTANT IICA TECHNICAL EVENING - 16 TH SEPTEMBER 2014 16 September, 2014 1 FUNCTIONAL SAFETY DEMYSTIFIED Purpose TOPICS What is Functional Safety? SIS, SIF and SIL Standards IEC 61508 and IEC 61511 An example to demonstrate compliance 4.5 day TÜV FSEng course in 45 minutes! One day course also available Explains how to comply with AS IEC 61511-2004 using a case study

Upload: lydiep

Post on 01-Feb-2018

276 views

Category:

Documents


8 download

TRANSCRIPT

Page 1: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

1

Functional Safety DemystifiedBOB WEISS - FUNCTIONAL SAFETY CONSULTANT

IICA TECHNICAL EVENING - 16TH SEPTEMBER 2014

16 September, 2014 1FUNCTIONAL SAFETY DEMYSTIFIED

Purpose

TOPICS

What is Functional Safety?◦ SIS, SIF and SIL

Standards IEC 61508 and IEC 61511

An example to demonstrate compliance

4.5 day TÜV FSEng course in 45 minutes!◦ One day course also available

Explains how to comply with

AS IEC 61511-2004

using a case study

Page 2: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

2

What is Functional Safety?

Part of Overall Safety◦ freedom from unacceptable risk

Achieved by a Safety Instrumented System (SIS)◦ E/E/PE Safety System in IEC 61508

◦ Examples:

◦ Emergency Shutdown System

◦ Burner Management System

◦ Includes field devices as well as logic solver

A SIS places or maintains a process in a safe state◦ Process = Equipment Under Control (EUC) in IEC 61508

◦ Implements Safety Instrumented Functions (SIFs)

◦ Each SIF achieves a Safety Integrity Level (SIL)

Acronyms to remember: SIS, SIF and SIL !.

16 September, 2014 FUNCTIONAL SAFETY DEMYSTIFIED 3

Why Functional Safety?Buncefield, England 11 Dec 2005

Storage tank level gauge showed constant reading

High level switch left in test mode

Gasoline tank overflowed

Mist exploded◦ largest explosion in peacetime

◦ 20 tanks on fire

◦ burned for three days

◦ significant environmental impact

◦ hundreds of millions of pounds damage

16 September, 2014 FUNCTIONAL SAFETY DEMYSTIFIED 4

Page 3: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

3

SIF 1: TZH1234

Safety Instrumented Function - SIF

Basic Terminology

16 September, 2014

SIF 2: PZHH1234

Safety Instrumented System - SIS

Logic Solver(e.g. Safety PLC)

Temperaturetransmitter

Temperaturetransmitter

Pressuretransmitter

Flowtransmitter

Shut-offvalve

Solenoid

Globevalve

Solenoid

Relayin MCC

Component

SIL 2

SIL 1

Safety Integrity Level - SIL

Sensing subsystem Final element subsystemLogic subsystem

Subsystems

FUNCTIONAL SAFETY DEMYSTIFIED 5

Safety Integrity Level vs. Risk Reduction

For Demand Mode SIFs only

16 September, 2014 FUNCTIONAL SAFETY DEMYSTIFIED 6

= 1 / RRF

SafetyAvailability

> 99.99%

> 99.9 ≤ 99.99%

> 99 ≤ 99.9%

> 90 ≤ 99%

Probability of Failureon Demand (PFDavg)

≥ 10-5 < 10-4

≥ 10-4 < 10-3

≥ 10-3 < 10-2

≥ 10-2 < 10-1

SIL

4

3

2

1

Risk ReductionFactor

> 10,000

> 1,000 ≤ 10,000

> 100 ≤ 1,000

> 10 ≤ 100

= 100(1 – PFDavg)= 1 / PFDavg

BPCS* ≤ 10 ≥ 10-1 ≤ 90%

Used to specify SIL achievedUsed to specify SIL required

* Basic Process Control System

Page 4: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

4

IEC 61508 or IEC 61511

Integrators & users in the process industries can use either IEC 61508 or IEC 61511

IEC 61511 is generally simpler to apply

16 September, 2014 FUNCTIONAL SAFETY DEMYSTIFIED 7

SISdevice

manufacturers

SISintegrators & users

SIL 1-3

SIS integrators &

usersSIL 4

SISintegrators & users

SIL 1-3

for process industries

IEC61508

IEC61511

Safety Lifecycle – IEC 61511

16 September, 2014 FUNCTIONAL SAFETY DEMYSTIFIED 8

Hazard and risk assessment CDV

Allocation ofsafety functions

to protection layers

Design andengineering of

safety instrumented system

Installation, commissioningand validation

Operation and maintenance

Modification

Decommissioning

Design anddevelopment

of other meansof risk reduction

Safety requirementsspecification for the

safety instrumented system

Managementof functional

safety andfunctional

safetyassessment

and auditing

Safetylife-cyclestructure

andplanning

Verification

10 11

5

6

7

8

4

3

1

2

9

Engineering Contractor

SIS Vendor

End User

Page 5: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

5

Complying with IEC 61511Target SIL must be specified for each SIF based on hazard and risk analysis

Processes for SIS throughout lifecycle must comply

Each SIF must meet target SIL requirements for:◦ Random failure rate (PFDavg)

◦ Architectural constraints (hardware fault tolerance)

◦ Systematic capability for each component◦ Field devices, logic solver, shutdown valves etc.

Not just TÜV certification◦ Though it helps !

Not just meeting PFDavg target.

16 September, 2014 FUNCTIONAL SAFETY DEMYSTIFIED 9

Comply Throughout LifecycleFor the rest of the presentation we’ll follow the SIS lifecycle

What do we need to do to comply at each stage?

See the following example…◦ Only the main elements of compliance are covered.

16 September, 2014 FUNCTIONAL SAFETY DEMYSTIFIED 10

Page 6: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

6

1 Hazard and Risk Assessment

16 September, 2014 11

Output is a list of hazardous events with their process risk and acceptable risk.

Hazard and risk assessment

Allocation ofsafety functions

to protection layers

Design andengineering of

safety instrumented system

Installation, commissioningand validation

Operation and maintenance

Modification

Decommissioning

Design anddevelopment

of other meansof risk reduction

Safety requirementsspecification for the

safety instrumented system

Managementof functional

safety andfunctional

safetyassessmentand auditing

Safetylife-cyclestructure

andplanning

Verification

10 11

5

6

7

8

4

3

1

2

9

FUNCTIONAL SAFETY DEMYSTIFIED

A hazard

A “potential source of harm”

300t of Liquefied Petroleum Gas can potentially cause harm

Hazardous Event Example – BLEVE (video)

16 September, 2014 12

300t LPG

P-1

Feed

P-2

Product

PSV-1

LIC

1

FUNCTIONAL SAFETY DEMYSTIFIED

Page 7: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

7

300t LPG

P-1

Feed

P-2

Product

PSV-1

LIC

1

Identify Hazardous Events: HAZOP

16 September, 2014 13

Node: LPG Tank

Guideword: HIGH LEVEL

Consequence: High Pressure, possible tank rupture & major fire

Existing Controls: Pressure Safety Valve (PSV-1)

New Controls: Add High Level Alarm

H

FUNCTIONAL SAFETY DEMYSTIFIED

RiskThe product of severity and likelihood

“The expected value of loss”

16 September, 2014 14

Consequenceseverity

Likelihood of occurrence

Minor

Medium

Major

LOW HIGHMEDIUM

FUNCTIONAL SAFETY DEMYSTIFIED

Page 8: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

8

Risk reduction concept

16 September, 2014 15

Overall risk reduction achieved by all means

Residualrisk

Processrisk

Necessary risk reduction

Actual risk reduction

Increasingrisk

Partial risk reductionby SIS

Partial risk reductionby “other means of risk reduction”

Acceptablerisk

FUNCTIONAL SAFETY DEMYSTIFIED

Is risk acceptable ?

16 September, 2014 16

Process under control

Process deviation or disturbance

Process out of control

Hazardous situation

Hazardous event

Impact / Consequence

Level stable

Control valve sticks

Level Increasing

High Pressure

Vessel fails

300t of boiling LPG released -likely major fire and fatalities

PSV

LAH Alarm

Hazard - 300t of LPG

What is risk ?Is it tolerable?

FUNCTIONAL SAFETY DEMYSTIFIED

Page 9: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

9

Risk Analysis - Layers of Protection

16 September, 2014 17

Mechanical PSV

Alarm LAH

Process

Control System(BPCS)

Hazardous Event !!

Risk Reduction

Hazardous Situation : 1 per y

Target:1 per 10,000y

Required: x 10,000

X 100

Only havex 100 !!

X 1 !

FUNCTIONAL SAFETY DEMYSTIFIED

2 Allocation of Safety FunctionsOften called SIL Assessment, SIL Analysis or SIL Determination

Output is a list of Safety Instrumented Functions together with their required Safety Integrity Level.

16 September, 2014 18

Hazard and risk assessment

Allocation ofsafety functions

to protection layers

Design andengineering of

safety instrumented system

Installation, commissioningand validation

Operation and maintenance

Modification

Decommissioning

Design anddevelopment

of other meansof risk reduction

Safety requirementsspecification for the

safety instrumented system

Managementof functional

safety andfunctional

safetyassessment

and auditing

Safetylife-cyclestructure

andplanning

Verification

10 11

5

6

7

8

4

3

1

2

9

FUNCTIONAL SAFETY DEMYSTIFIED

Page 10: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

10

Risk is unacceptable - reduce further

16 September, 2014 19

Process under control

Process deviation or disturbance

Process out of control

Hazardous situation

Hazardous event

Impact / Consequence

Level stable

Control valve sticks

Level Increasing

High Pressure

Vessel fails

300t of boiling LPG released -likely major fire and fatalities

PSV

LAH Alarm

Hazard - 300t of LPG

LZHH Trip

How do wereduce risk further?

FUNCTIONAL SAFETY DEMYSTIFIED

300t LPG

P-1

Feed

P-2

Product

PSV-1

LIC

1

H

LZHH

2

LZT

2

Add a high level trip

16 September, 2014 20

High Level Trip LZHH2 added◦ Shuts off flow when High High level reached

FUNCTIONAL SAFETY DEMYSTIFIED

Page 11: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

11

Layers of Protection – SIL assessment

16 September, 2014 21

Mechanical PSV

Alarm LAH

Process

Control System(BPCS)

Hazardous Event !!

Risk Reduction

Hazardous Situation : 1 per y

Target:1 per 10,000y

Required: x 10,000

X 100

X 1 !

SIF LZHH

X 100SIL 2

SIF must reduce risk by10,000/100 = 100

FUNCTIONAL SAFETY DEMYSTIFIED

Safety Integrity Level vs. Risk Reduction

For Demand Mode SIFs only

16 September, 2014 22

= 1 / RRF

SafetyAvailability

> 99.99%

> 99.9 ≤ 99.99%

> 99 ≤ 99.9%

> 90 ≤ 99%

Probability of Failureon Demand (PFDavg)

≥ 10-5 < 10-4

≥ 10-4 < 10-3

≥ 10-3 < 10-2

≥ 10-2 < 10-1

SIL

4

3

2

1

Risk ReductionFactor

> 10,000

> 1,000 ≤ 10,000

> 100 ≤ 1,000

> 10 ≤ 100

= 100(1 – PFDavg)= 1 / PFDavg

BPCS ≤ 10 ≥ 10-1 ≤ 90%

Used to specify SIL achievedUsed to specify SIL required

FUNCTIONAL SAFETY DEMYSTIFIED

Page 12: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

12

Phase 1 & 2 Compliance Achieved !

Target SIL must be specified for each SIF based on hazard and risk analysis

Processes for SIS throughout lifecycle must comply

Each SIF must meet target SIL requirements for:◦ Hardware Fault Tolerance (architectural constraints)

◦ random failure rate (PFDavg)

◦ Systematic Capability of each component

16 September, 2014 23FUNCTIONAL SAFETY DEMYSTIFIED

3 Safety Requirements Specification - SRSDefines functional and integrity requirements of SIS

Output is a set of documents ready for detail design.

16 September, 2014 24

Hazard and risk assessment

Allocation ofsafety functions

to protection layers

Design andengineering of

safety instrumented system

Installation, commissioningand validation

Operation and maintenance

Modification

Decommissioning

Design anddevelopment

of other meansof risk reduction

Safety requirementsspecification for the

safety instrumented system

Managementof functional

safety andfunctional

safetyassessment

and auditing

Safetylife-cyclestructure

andplanning

Verification

10 11

5

6

7

8

4

3

1

2

9

FUNCTIONAL SAFETY DEMYSTIFIED

Page 13: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

13

Safety Requirements SpecificationFunctional Requirements

◦ desired behaviour of each SIF

◦ behaviour in response to faults

◦ timing requirements

◦ human machine interface

◦ normal and abnormal modes of operation

◦ bypass requirements

◦ etc.

Safety Integrity Requirements◦ Safety Integrity Level for each SIF

◦ basis for SIL

◦ testing requirements

◦ special requirements to maintain SIL

◦ etc.

16 September, 2014 25FUNCTIONAL SAFETY DEMYSTIFIED

Cause-and-Effect Diagram SIFs commonly documented byCause and Effect diagrams

Should include required SIL somewhere – examples:

16 September, 2014 26

Tag# Description SIF

Instr

um

ent

Range

Trip P

oin

t

Units

CLO

SE

VA

LV

E L

ZV

-02

CLO

SE

VA

LV

E U

V-0

3A

CLO

SE

VA

LV

E U

V-0

3B

OP

EN

S V

ALV

E U

V-0

3C

Set

LIC

1 t

o M

AN

, O

P=

0

BS-01 Burner Loss of Flame 12 ~ ~ X X X

PSL-01 Fuel Gas Pressure Low ~ 7 X X X

LZHH-02 LPG Tank High High Level 13 0-3500 3200 mm 2 0

FUNCTIONAL SAFETY DEMYSTIFIED

Page 14: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

14

4 Design and EngineeringSIS vendor or contractor for logic solver

EPC contractor or end-user for field hardware

Hazard and risk assessment

Allocation ofsafety functions

to protection layers

Design andengineering of

safety instrumented system

Installation, commissioningand validation

Operation and maintenance

Modification

Decommissioning

Design anddevelopment

of other meansof risk reduction

Safety requirementsspecification for the

safety instrumented system

Managementof functional

safety andfunctional

safetyassessment

and auditing

Safetylife-cyclestructure

andplanning

Verification

10 11

5

6

7

8

4

3

1

2

9

16 September, 2014 27FUNCTIONAL SAFETY DEMYSTIFIED

Standards Compliance

Target SIL must be specified for each SIF based on hazard and risk analysis

Processes for SIS throughout lifecycle must comply

Each SIF must meet target SIL requirements for:◦ Hardware Fault Tolerance (architectural constraints)

◦ Random failure rate (PFDavg)

◦ Systematic Capability of each component

16 September, 2014 28FUNCTIONAL SAFETY DEMYSTIFIED

Page 15: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

15

Types of failuresRandom failures – components (“elements”) wear out

◦ use high reliability components

◦ use redundant components

◦ test frequently◦ automated and/or manual

Systematic failures – human error◦ redundant components provide no protection!

◦ “techniques and measures” to◦ avoid faults

◦ detect faults to avoid failures

◦ Functional Safety Management System◦ quality system for functional safety

16 September, 2014 29FUNCTIONAL SAFETY DEMYSTIFIED

Control of systematic failuresFor integration of components into a system (SIS):

◦ Functional Safety Management System (FSMS)◦ for all phases of lifecycle including operation

◦ quality system for SIS

◦ verification, validation, audit and assessment

◦ can comply with either IEC 61511 or IEC 61508

Within each component:◦ ensure quality design in accordance with IEC 61508

◦ ensure appropriate techniques and measures from IEC 61508 used for the SIL of the target SIF

◦ measured by the term “systematic capability”◦ SC 1 to 4 corresponding to SIL 1 to 4

◦ Formerly called “SIL x Capability”

◦ independent certification or “prior use”

16 September, 2014 30FUNCTIONAL SAFETY DEMYSTIFIED

Page 16: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

16

Target SIL must be specified for each SIF based on hazard and risk analysis

Processes for SIS throughout lifecycle must comply

Each SIF must meet target SIL requirements for:◦ Hardware Fault Tolerance (architectural constraints)

◦ Random failure rate (PFDavg)

◦ Systematic Capability of each component

Standards Compliance

16 September, 2014 34FUNCTIONAL SAFETY DEMYSTIFIED

300t LPG

P-1

Feed

P-2

Product

PSV-1

LIC

1

H

LZHH

2

LZT

2

SIL Verification

16 September, 2014 35

Does the design of SIF LZHH2 meet SIL 2?

SIL 2

FUNCTIONAL SAFETY DEMYSTIFIED

Page 17: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

17

Hardware Fault Tolerance“Architectural constraints” in IEC 61508

Aim is to avoid unrealistic reliability claims◦ from single components

IEC͏ 61508-2 (Route 1H) constrains SIF architecture based on:◦ Safe Failure Fraction

◦ complexity of device (“Type A” or “Type B”)

◦ target SIL

Outcome is required minimum Hardware Fault Tolerance (HFT)◦ no. of voted devices minus no. required to perform safety function

◦ For MooN architecture, HFT = N - M

Use Tables in IEC 61508 part 2◦ or use Route 2H

◦ or use IEC 61511 simplified requirements◦ these are subject to significant change in the forthcoming 2nd edition

16 September, 2014 36FUNCTIONAL SAFETY DEMYSTIFIED

Safe Failure FractionBlock valve, normally open & normally energized

In case of an out of control process, the valve has to close

Closesspontaneouslydue to lossof energy

SAFE

Undetected

Detectedby diagnostics

Undetected

Detectedby voltage control

DANGEROUS

Stuck atopen

SFF

16 September, 2014 37FUNCTIONAL SAFETY DEMYSTIFIED

Page 18: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

18

Architectural Constraints – IEC 61508-2

16 September, 2014 38

Type A Subsystems e.g. pressure switches

Safe Failure Fraction

Hardware Fault Tolerance

0 1 2

< 60% SIL 1* SIL 2* SIL 3*

≥ 60 < 90% SIL 2 SIL 3 SIL 4

≥ 90 < 99% SIL 3 SIL 4 SIL 4

≥ 99% SIL 3 SIL 4 SIL 4

Type B Subsystems e.g. logic solver, smart transmitters

Safe Failure Fraction

Hardware Fault Tolerance

0 1 2

< 60% Not allowed SIL 1 SIL 2

≥ 60 < 90% SIL 1* SIL 2* SIL 3*

≥ 90 < 99% SIL 2 SIL 3 SIL 4

≥ 99% SIL 3 SIL 4 SIL 4

Table 2

Table 3

* IEC͏ 61511-2003

HFT forfield devices

For MooNN-M = HFT

FUNCTIONAL SAFETY DEMYSTIFIED

300t LPG

P-1

Feed

P-2

Product

PSV-1

LIC

1

H

LZHH

2

LZT

2

Case Study: Architectural Constraints

Transmitter LZT 2 is a smart radar gauge

Can we use single transmitter to satisfy SIL 2?

Must also check for logic solver and valve

16 September, 2014 39FUNCTIONAL SAFETY DEMYSTIFIED

Page 19: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

19

Type B Subsystems e.g. logic solver, smart transmitters

Safe Failure Fraction

Hardware Fault Tolerance

0 1 2

< 60% Not allowed SIL 1 SIL 2

≥ 60 < 90% SIL 1* SIL 2* SIL 3*

≥ 90 < 99% SIL 2 SIL 3 SIL 4

≥ 99% SIL 3 SIL 4 SIL 4

Case Study: Architectural ConstraintsSmart Transmitter = Type B device

◦ use Table 3 in IEC 61508-2

Safe Failure Fraction = 91%◦ from certificate

For SIL 2, required Hardware Fault Tolerance = 0

Therefore one transmitter is ok for SIL 2

LTZ 2

16 September, 2014 40FUNCTIONAL SAFETY DEMYSTIFIED

Standards Compliance

Target SIL must be specified for each SIF based on hazard and risk analysis

Processes for SIS throughout lifecycle must comply

Each SIF must meet target SIL requirements for:◦ Hardware Fault Tolerance (architectural constraints)

◦ Random failure rate (PFDavg)

◦ Systematic Capability of each component

16 September, 2014 41FUNCTIONAL SAFETY DEMYSTIFIED

Page 20: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

20

300t LPG

P-1

Feed

P-2

Product

PSV-1

LIC

1

H

LZHH

2

LZT

2

SIL Verification

16 September, 2014 42

What is calculated “PFDavg” for SIF LZHH-2?

SIL 2

FUNCTIONAL SAFETY DEMYSTIFIED

Safety Integrity Level vs. Risk Reduction

For Demand Mode SIFs only

16 September, 2014 43

= 1 / RRF

SafetyAvailability

> 99.99%

> 99.9 ≤ 99.99%

> 99 ≤ 99.9%

> 90 ≤ 99%

Probability of Failureon Demand (PFDavg)

≥ 10-5 < 10-4

≥ 10-4 < 10-3

≥ 10-3 < 10-2

≥ 10-2 < 10-1

SIL

4

3

2

1

Risk ReductionFactor

> 10,000

> 1,000 ≤ 10,000

> 100 ≤ 1,000

> 10 ≤ 100

= 100(1 – PFDavg)= 1 / PFDavg

BPCS ≤ 10 ≥ 10-1 ≤ 90%

Used to specify SIL achievedUsed to specify SIL required

FUNCTIONAL SAFETY DEMYSTIFIED

Page 21: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

21

Case Study: PFD CalculationTest interval = 1 y

Reliability data:◦ Valve: λDU = 1/10y (= 0.1 y-1)

◦ Logic solver: λDU = 1/1000y (= 0.001 y-1)

◦ Sensor: λDU = 1/100y (= 0.01 y-1)

PFDavg = λDU x TI / 2= 0.1 x 1 / 2 = 0.05 for valve

0.001 x 1 / 2 = 0.0005 for logic solver0.01 x 1 / 2 = 0.005 for transmitter

Total PFDavg = 0.05 + 0.0005 + 0.005 = 0.0555

Calculated SIL = 1 (PFDavg range 0.01 – 0.1)

Required SIL = 2 Not OK!

How can this be fixed?

16 September, 2014 44

LZHH

2

LZV 2

LZT

2

FUNCTIONAL SAFETY DEMYSTIFIED

Case Study: Adjust Test IntervalTest interval = 1 month

Reliability data:◦ Valve: λDU = 1/10y (= 0.1 y-1)

◦ Logic solver: λDU = 1/1000y (= 0.001 y-1)

◦ Sensor: λDU = 1/100y (= 0.01 y-1)

PFDavg = λDU x TI / 2= 0.1 / 12 / 2 = 0.004 for valve

0.001 / 12 / 2 = 0.00004 for logic solver0.01 / 12 / 2 = 0.0004 for transmitter

Total PFDavg = 0.004 + 0.00004 + 0.0004 = 0.00444

Calculated SIL = 2 (PFDavg range 0.001 – 0.01)

Required SIL = 2 OK

BUT operations object to monthly testing !

16 September, 2014 45

LZHH

2

LZV 2

LZT

2

FUNCTIONAL SAFETY DEMYSTIFIED

Page 22: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

22

Case Study: Duplicate Block ValvesTest interval = 1 year

Reliability data:◦ Valve: λDU = 1/10y (= 0.1 y-1)

◦ Logic solver: λDU = 1/1000y (= 0.001 y-1)

◦ Sensor: λDU = 1/100y (= 0.01 y-1)

For 2 valves 1oo2 voting: PFDavg = 0.0033 (was 0.05)

PFDavg = 0.0033 + 0.0005 + 0.005 = 0.0088

Calculated SIL = 2 (PFDavg range 0.001 – 0.01)

Required SIL = 2 OK

LZHH

2

LZV 2A

LZT

2

LZV 2B

16 September, 2014 46FUNCTIONAL SAFETY DEMYSTIFIED

Standards ComplianceTarget SIL must be specified for each SIF based on hazard and risk analysis

Processes for SIS throughout lifecycle must comply

Each SIF must meet target SIL requirements for:◦ Hardware Fault Tolerance (architectural constraints)

◦ random failure rate (PFDavg)

◦ Systematic Capability of each component.

How likely is it that each component is free from systematic faults (“bugs”) ?

16 September, 2014 47FUNCTIONAL SAFETY DEMYSTIFIED

Page 23: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

23

Control of systematic failuresFor integration of components into a system (SIS):

◦ functional safety management system◦ for all phases of lifecycle including operation

◦ verification, validation, audit and assessment

◦ can comply with either IEC 61511 or IEC 61508

Within each component:◦ ensure quality design in accordance with IEC 61508

◦ ensure appropriate techniques and measures from IEC 61508 used for the SIL of the target SIF

◦ measured by the term “systematic capability”◦ SC 1 to 4 corresponding to SIL 1 to 4

◦ formerly called “SIL Capability”

◦ independent certification or “prior use”

16 September, 2014 48FUNCTIONAL SAFETY DEMYSTIFIED

Case Study: Transmitter SelectionMust control systematic faults

Transmitter selected must comply with IEC 61508 and IEC 61511

Must either:

be designed and manufactured in accordance with IEC 61508◦ confirmed by independent certificate (e.g. by a “TÜV” or exida)

◦ Systematic Capability from 1 to 4◦ i.e. techniques and measures are suitable for SIL 1 to 4

OR

meet requirements for Prior Use (or “proven in use”):◦ sufficient experience gained in a comparable application

Best practice: require BOTH prior use and certification

16 September, 2014 49FUNCTIONAL SAFETY DEMYSTIFIED

Page 24: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

24

Component CertificationAn independent organisation certifies that the component meets the requirements of IEC 61508 for a particular SIL

◦ not only “TÜV” !!!

Parts 2 and 3 contain numerous “techniques and measures” required to avoid and control faults

◦ the rigour required increases with SIL

The aim is to reduce the likelihood of systematic faults to an acceptably low level relative to the SIL

The result is expressed as “Systematic Capability” or SC from 1 to 4◦ corresponding to SIL 1 to 4

◦ was previously called “SIL Capability”

The certificate also usually also includes failure data and whether the component is “Type A” or “Type B”

◦ details are in a companion report

16 September, 2014 50FUNCTIONAL SAFETY DEMYSTIFIED

Transmitter TÜV Certificate

16 September, 2014 51FUNCTIONAL SAFETY DEMYSTIFIED

Page 25: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

25

Transmitter TÜV Certification

16 September, 2014 52FUNCTIONAL SAFETY DEMYSTIFIED

Prior Use (IEC 61511)Requires that appropriate evidence is available that the component is suitable based on consideration of:

◦ the manufacturer’s quality systems

◦ adequate identification of the devices

◦ demonstration of performance in similar operating environments

◦ the volume of operating experience

Focus is on demonstrating freedom from systematic faults

IEC 61508 term is “Proven in Use”◦ more rigorous requirements

16 September, 2014 53FUNCTIONAL SAFETY DEMYSTIFIED

Page 26: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

26

Standards ComplianceTarget SIL must be specified for each SIF based on hazard and risk analysis

Processes for SIS throughout lifecycle must comply

Each SIF must meet target SIL requirements for:◦ Hardware Fault Tolerance (architectural constraints)

◦ random failure rate (PFDavg)

◦ Systematic Capability of each component

Design now complies

16 September, 2014 54FUNCTIONAL SAFETY DEMYSTIFIED

5 Installation, Commissioning, ValidationLogic Solver installed with field equipment

Includes loop checking, validation and final functional safety assessment.

Hazard and risk assessment

Allocation ofsafety functions

to protection layers

Design andengineering of

safety instrumented system

Installation, commissioningand validation

Operation and maintenance

Modification

Decommissioning

Design anddevelopment

of other meansof risk reduction

Safety requirementsspecification for the

safety instrumented system

Managementof functional

safety andfunctional

safetyassessment

and auditing

Safetylife-cyclestructure

andplanning

Verification

10 11

5

6

7

8

4

3

1

2

9

16 September, 2014 55FUNCTIONAL SAFETY DEMYSTIFIED

Page 27: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

27

Standards ComplianceTarget SIL must be specified for each SIF based on hazard and risk analysis

Processes for SIS throughout lifecycle must comply

Each SIF must meet target SIL requirements for:◦ Hardware Fault Tolerance (architectural constraints)

◦ random failure rate (PFDavg)

◦ Systematic Capability of each component

Verification, Validation, Functional Safety Assessment

16 September, 2014 56FUNCTIONAL SAFETY DEMYSTIFIED

Case Study: Verification and ValidationProject Verification and Validation Plan required

◦ Consider level of independence required (i.e. independent engineer)

◦ Define responsibilities

Verify each phase e.g.◦ Safety Requirements Specification◦ Verify hardware design documents◦ Verify functional specifications etc◦ Implement code walkthrough

Logic Solver Factory Acceptance Test ◦ Complete integration test validates application software on target hardware

Logic Solver Site Acceptance Test◦ Power up test on site

Safety Function Testing◦ SIS validation

Functional Safety Assessment

Note that terminology is from the ISO9000 discipline◦ Some disciplines swap the meanings of “verification” and “validation”!

16 September, 2014 57FUNCTIONAL SAFETY DEMYSTIFIED

Page 28: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

28

6 Operations, Maintenance and ModificationThe Cinderella Phases !

User must follow a Functional Safety Management System for the life of the SIS.

16 September, 2014 62

Hazard and risk assessment

Allocation ofsafety functions

to protection layers

Design andengineering of

safety instrumented system

Installation, commissioningand validation

Operation and maintenance

Modification

Decommissioning

Design anddevelopment

of other meansof risk reduction

Safety requirementsspecification for the

safety instrumented system

Managementof functional

safety andfunctional

safetyassessment

and auditing

Safetylife-cyclestructure

andplanning

Verification

10 11

5

6

7

8

4

3

1

2

9

FUNCTIONAL SAFETY DEMYSTIFIED

Ops and Maintenance ObligationsTrain operators & maintainers

Proof test each SIF at specified interval

Monitor design assumptions◦ demand rates

◦ component reliability

Adjust test interval to suit

Control modifications

Ensure Maintenance and Operational Overrides are used as designed

Monitor and promptly follow-up diagnostics

16 September, 2014 63FUNCTIONAL SAFETY DEMYSTIFIED

Page 29: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

29

300t LPG

P-1

Feed

P-2

Product

PSV-1

LIC

1

H

LZHH

2

LZT

2

Case Study: Operation and MaintenanceRisk analysis assumed:

◦ demand on SIF once per year

◦ what happens in practice?

SIL verification assumed:◦ transmitter failure rate 0.01 y-1

◦ what happens in practice?

Etc etc . . .

Must verify actual performance against assumptions and adjust testing as required

Documentation of assumptions is critical

Mechanical: PSV

SIF: LZHH

AlarmLAH

Process

Control System(BPCS)

Hazardous Event !!

Risk Reduction

Hazardous Situation

Target:1 per 10,000y

Required: X 10,000

X 100

X 100SIL 2

1 per y

16 September, 2014 64FUNCTIONAL SAFETY DEMYSTIFIED

Summary 1 – The SIS Lifecycle

16 September, 2014 65

Hazard and risk assessment

Allocation ofsafety functions

to protection layers

Design andengineering of

safety instrumented system

Installation, commissioningand validation

Operation and maintenance

Modification

Decommissioning

Design anddevelopment

of other meansof risk reduction

Safety requirementsspecification for the

safety instrumented system

Managementof functional

safety andfunctional

safetyassessment

and auditing

Safetylife-cyclestructure

andplanning

Verification

10 11

5

6

7

8

4

3

1

2

9

Engineering Contractor

SIS Vendor

End User

FUNCTIONAL SAFETY DEMYSTIFIED

Page 30: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

30

Summary 2 – RequirementsTarget SIL must be specified for each SIF based on hazard and risk assessment

Processes for SIS throughout lifecycle must comply

Each SIF must meet target SIL requirements for:◦ Hardware Fault Tolerance (architectural constraints)

◦ random failure rate (PFDavg)

◦ Systematic Capability of each component.

Not just TÜV certification◦ though it helps !

Not just meeting PFDavg target

Don’t forget spurious trip rate!

16 September, 2014 66FUNCTIONAL SAFETY DEMYSTIFIED

Need more?IICA runs the following courses:

ISA One-day Introduction to SIS◦ runs periodically or on request

TÜV Rheinland Functional Safety Engineer course◦ NEW!! from March 2015

◦ For those with 3+ years experience in functional safety

◦ Leads to Functional Safety Engineer (TÜV Rheinland) qualification

If interested please email [email protected]

17 September, 2014 FUNCTIONAL SAFETY DEMYSTIFIED 67

Page 31: Functional Safety Demystified - IICA · PDF file17/09/2014 4 IEC 61508 or IEC 61511 Integrators & users in the process industries can use either IEC 61508 or IEC 61511 IEC 61511 is

17/09/2014

31

Questions?

16 September, 2014 68FUNCTIONAL SAFETY DEMYSTIFIED