fundamental of corporate finance,chpt9

Upload: yin-sokheng

Post on 06-Apr-2018

227 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Fundamental of Corporate Finance,chpt9

    1/13

    Chapter 9

    Net Present Value and Other

    Investment Criteria

    Prepared and Taught by Lecturer : YIN SOKHNG

    E-mail: [email protected]

    Tel:(855) 16889872 / 17989972

    Chapter Outline

    9.1 Net Present Value (NPV)

    9.2 The Payback Rule (PR)

    9.3 The Discounted Payback Period Rule (DPR)

    9.4 The Average Accounting Return (AAR)

    9.5 The Internal Rate of Return (IRR)

    9.6 The Profitability Index (PI)

    9.7 The Practice of Capital Budgeting

    2Instructed by YIN SOKHENG, Master in Finance

    3

    Accepting positive NPV projects benefits

    shareholders.NPV uses cash flows

    NPV uses all the cash flows of the project

    NPV discounts the cash flows properly

    The difference between the market value of aproject and its cost

    How much value is created from undertakingan investment?

    9.1 Net Present Value

    Instructed by YIN SOKHENG, Master in Finance

  • 8/3/2019 Fundamental of Corporate Finance,chpt9

    2/13

    4

    The Net Present Value (NPV) Rule

    Net Present Value (NPV) =Initial Investment (costs)

    + PV of future CFs

    Estimating NPV: 1. Estimate initial costs

    2. Estimate future cash flows: how much? and when?

    3. Estimate discount rate

    Minimum Acceptance Criteria: Accept if NPV > 0

    Ranking Criteria: Choose the highest NPV

    Instructed by YIN SOKHENG, Master in Finance

    5

    Good Attributes of the NPV Rule

    1. Uses cash flows

    2. Uses ALL cash flows of the project

    3. Discounts ALL cash flows properly

    Reinvestment assumption: the NPV rule

    assumes that all cash flows can be reinvested

    at the discount rate.

    Instructed by YIN SOKHENG, Master in Finance

    6

    For example of NPV

    Year Cash flow (net income)

    0 $9,0001 6,000

    2 4,000

    3 3,000

    4 2,000

    Initial cash flow = $9,000; IR = 10%; Do you

    Recommend this project?

    Instructed by YIN SOKHENG, Master in Finance

  • 8/3/2019 Fundamental of Corporate Finance,chpt9

    3/13

    7

    For example of NPV

    PV = 6,000 /(1.1) + 4,000 /(1.1)2 + 3,000

    /(1.1)3 + 2,000 /(1.1)4 = $12,377

    NPV = $12,3779,000 = $3,377

    EX2: IBM Company has two projects to invest:

    1. Project (A) is initial cost of $350,000 and

    cash inflow in year one is $400,000

    2. Project (B) invests in treasury bill with 7%

    of interest rate, Do you recommend?

    Instructed by YIN SOKHENG, Master in Finance

    8

    For example of NPV

    PV of Project (B)= 400,000 / (1.07) =

    $373,832

    NPV = $373,832350,000 = $23,832

    Invest in project (A) is best

    Instructed by YIN SOKHENG, Master in Finance

    9

    9.2 The Payback Period

    How long does it take the project to pay

    back its initial investment?

    Computation

    Estimate the cash flows

    Subtract the future cash flows from the initial cost

    until the initial investment has been recovered

    Payback Period = number of years to recover

    initial costs

    Instructed by YIN SOKHENG, Master in Finance

  • 8/3/2019 Fundamental of Corporate Finance,chpt9

    4/13

    10

    The Payback Period Rule

    Decision RuleAccept if the payback

    period is less than some preset limit Minimum Acceptance Criteria:

    set by management

    Ranking Criteria:

    set by management

    Instructed by YIN SOKHENG, Master in Finance

    11

    The Payback Period Rule

    Disadvantages:

    Ignores the time value of money

    Ignores cash flows after the payback period

    Biased against long-term projects

    Requires an arbitrary acceptance criteria

    A project accepted based on the payback criteriamay not have a positive NPV

    Advantages:

    Easy to understand Biased toward liquidity

    Instructed by YIN SOKHENG, Master in Finance

    12

    Computing Payback For The

    Project

    Assume we will accept the project if it pays

    back within two years.

    Year 1: 165,00063,120 = 101,880 still to recover

    Year 2: 101,88070,800 = 31,080 still to recover

    Year 3: 31,08091,080 = -60,000project pays

    back in year 3

    Do we accept or reject the project?

    Instructed by YIN SOKHENG, Master in Finance

  • 8/3/2019 Fundamental of Corporate Finance,chpt9

    5/13

    13

    Payback Period

    Assume ABC Co. plans to invest in a project

    that has a $50,000 initial outlay. It is estimatedthat the project will provide regular cashinflows of $30,000 in year 1, $20,000 in year 2,

    $10,000 in year 3, and $5,000 in year 4.

    Payback period = 2 years

    Instructed by YIN SOKHENG, Master in Finance

    14

    For example of Payback period

    Year A B C D E

    0 -100 -200 -200 -200 -50

    1 30 40 40 100 100

    2 40 20 20 100 -50,000

    3 50 10 10 10 -200

    4 60 130 200

    Instructed by YIN SOKHENG, Master in Finance

    15

    For example of Payback period

    Payback period (A) = 2 years + (10070 )/ 50 = 2.6 years

    Payback period (B) = Never payback

    Payback period ( C) = 4 years

    Payback period (D) = 2 years

    Payback period (E) = 6 months

    Instructed by YIN SOKHENG, Master in Finance

  • 8/3/2019 Fundamental of Corporate Finance,chpt9

    6/13

    16

    9.3 The Discounted Payback

    Period Rule

    How long does it take the project to pay

    back its initial investment taking the timevalue of money into account?

    By the time you have discounted the cash

    flows, you might as well calculate the NPV.

    Instructed by YIN SOKHENG, Master in Finance

    17

    9.4 The Average Accounting Return Rule

    Another attractive but fatally flawed approach.

    Ranking Criteria and Minimum Acceptance Criteriaset by management

    Disadvantages: Ignores the time value of money

    Uses an arbitrary benchmark cutoff rate

    Based on book values, not cash flows and market values

    Advantages: The accounting information is usually available

    Easy to calculate

    Instructed by YIN SOKHENG, Master in Finance

    18

    InvestentofValueBookAverage

    IncomeNetAverageAAR

    Book value is a started investment

    Average book value of Investment

    = a stated investment / 2

    Decision Rule: Accept the project if the AARis greater than a preset rate.

    Instructed by YIN SOKHENG, Master in Finance

  • 8/3/2019 Fundamental of Corporate Finance,chpt9

    7/13

    19

    Computing AAR For The Project

    Assume we require an average accounting

    return of 25%

    Average Net Income:

    (13,620 + 3,300 + 29,100) / 3 = 15,340

    AAR = 15,340 / 72,000 = .213 = 21.3%

    Do we accept or reject the project?

    Instructed by YIN SOKHENG, Master in Finance

    20

    Example of AAR

    Assume we require an average accounting return of25%

    Assume that net earnings for the next 4 years areestimated to be $10,000, 15,000, $20,000, and$30,000, respectively. If the initial investment is$100,000, find the average rate of return

    Average net earnings = 10,000 + 15,000 + 20,000 +30,000 / 4 = $18,750

    Average Book value = 100,000 / 2 = $50,000

    AAR = $18,750 / $50,000 = 37.5% Do we accept or reject the project?

    Instructed by YIN SOKHENG, Master in Finance

    21

    9.5 The Internal Rate of Return (IRR)

    Rule IRR: the discount that sets NPV to zero

    Minimum Acceptance Criteria: Accept if the IRR exceeds the required return.

    Ranking Criteria: Select alternative with the highest IRR

    Reinvestment assumption: All future cash flows assumed reinvested at the IRR.

    Disadvantages: Does not distinguish between investing and borrowing. IRR may not exist or there may be multiple IRR Problems with mutually exclusive investments

    Advantages: Easy to understand and communicate

    Instructed by YIN SOKHENG, Master in Finance

  • 8/3/2019 Fundamental of Corporate Finance,chpt9

    8/13

    22

    The Internal Rate of Return:

    ExampleConsider the following project:

    0 1 2 3

    $50 $100 $150

    -$200

    The internal rate of return for this project is 19.44%

    32 )1(

    150$

    )1(

    100$

    )1(

    50$0

    IRRIRRIRRNPV

    Instructed by YIN SOKHENG, Master in Finance

    23

    The NPV Payoff Profile for This Example

    Discount Rate NPV

    0% $100.00

    4% $71.04

    8% $47.32

    12% $27.79

    16% $11.65

    20% ($1.74)

    24% ($12.88)

    28% ($22.17)

    32% ($29.93)36% ($36.43)

    40% ($41.86)

    If we graph NPV versus discount rate, we can see the

    IRR as the x-axis intercept.

    IRR = 19.44%

    ($60.00)($40.00)

    ($20.00)

    $0.00

    $20.00

    $40.00

    $60.00

    $80.00

    $100.00

    $120.00

    -1% 9% 19% 29% 39%

    NPV

    Discount rate

    Instructed by YIN SOKHENG, Master in Finance

    24

    Problems with the IRR Approach

    Multiple IRRs. Are We Borrowing or Lending?

    The Scale Problem

    The Timing Problem

    Instructed by YIN SOKHENG, Master in Finance

  • 8/3/2019 Fundamental of Corporate Finance,chpt9

    9/13

    25

    Multiple IRRs

    There are two IRRs for this project:

    0 1 23

    $200 $800

    -$200 - $800

    ($150.00)

    ($100.00)

    ($50.00)

    $0.00

    $50.00

    $100.00

    -50% 0% 50% 100% 150% 200%

    Discount rate

    NPV

    100% = IRR2

    Which one

    should we use?

    0% = IRR1

    Instructed by YIN SOKHENG, Master in Finance

    26

    The Scale Problem

    Would you rather make 100% or 50% on your

    investments?

    What if the 100% return is on a $1 investment

    while the 50% return is on a $1,000

    investment?

    Instructed by YIN SOKHENG, Master in Finance

    27

    The Timing Problem

    0 1 2 3

    $10,000 $1,000 $1,000

    -$10,000

    Project A

    0 1 2 3

    $1,000 $1,000 $12,000

    -$10,000

    Project B

    The preferred project in this case depends on the discount rate, not

    the IRR.

    Instructed by YIN SOKHENG, Master in Finance

  • 8/3/2019 Fundamental of Corporate Finance,chpt9

    10/131

    28

    The Timing Problem

    ($4,000.00)

    ($3,000.00)

    ($2,000.00)

    ($1,000.00)

    $0.00

    $1,000.00

    $2,000.00

    $3,000.00

    $4,000.00

    $5,000.00

    0% 10% 20% 30% 40%

    Discount rate

    NPV

    Project A

    Project B10.55% = crossoverrate

    16.04% = IRRA12.94% = IRRB

    Instructed by YIN SOKHENG, Master in Finance

    29

    Calculating the Crossover RateCompute the IRR for either project A-B or B-A

    Year Project A Project B Project A-B Project B-A

    0 ($10,000) ($10,000) $0 $0

    1 $10,000 $1,000 $9,000 ($9,000)

    2 $1,000 $1,000 $0 $0

    3 $1,000 $12,000 ($11,000) $11,000

    ($3,000.00)($2,000.00)

    ($1,000.00)

    $0.00

    $1,000.00

    $2,000.00

    $3,000.00

    0% 5% 10% 15% 20%

    Discount rate

    NPV A-B

    B-A

    10.55% = IRR

    Instructed by YIN SOKHENG, Master in Finance

    30

    Mutually Exclusive vs.

    Independent Project

    Mutually Exclusive Projects: only ONE of several

    potential projects can be chosen, e.g. acquiring anaccounting system.

    RANK all alternatives and select the best one.

    Independent Projects: accepting or rejecting oneproject does not affect the decision of the otherprojects. Must exceed a MINIMUM acceptance criteria.

    Instructed by YIN SOKHENG, Master in Finance

  • 8/3/2019 Fundamental of Corporate Finance,chpt9

    11/13

    31

    IRR and Mutually Exclusive

    Projects

    Mutually exclusive projects

    If you choose one, you cant choose the other

    Example: You can choose to attend graduate

    school next year at either Harvard or Stanford, but

    not both

    Intuitively you would use the following

    decision rules:

    NPVchoose the project with the higher NPV

    IRRchoose the project with the higher IRR

    Instructed by YIN SOKHENG, Master in Finance

    32

    Example With Mutually Exclusive Projects

    Period Project A Project B

    0 -500 -400

    1 325 325

    2 325 200

    IRR 19.43% 22.17%

    NPV 64.05 60.74

    The required

    return for both

    projects is 10%.

    Which project

    should you

    accept and why?

    Instructed by YIN SOKHENG, Master in Finance

    33

    9.6 The Profitability Index (PI) Rule

    Minimum Acceptance Criteria: Accept if PI > 1

    Ranking Criteria:

    Select alternative with highest PI

    Disadvantages:

    Problems with mutually exclusive investments

    Advantages:

    May be useful when available investment funds are limited

    Easy to understand and communicate

    Correct decision when evaluating independent projects

    InvestentInitial

    FlowsCashFutureofPVTotalPI

    Instructed by YIN SOKHENG, Master in Finance

  • 8/3/2019 Fundamental of Corporate Finance,chpt9

    12/131

    34

    9.7 The Practice of Capital Budgeting

    Varies by industry:

    Some firms use payback, others use accounting

    rate of return.

    The most frequently used technique for large

    corporations is IRR or NPV.

    Instructed by YIN SOKHENG, Master in Finance

    35

    Example of Investment Rules

    Compute the IRR, NPV, PI, and payback period for the

    following two projects. Assume the required return is

    10%.

    Year Project A Project B

    0 -$200 -$150

    1 $200 $50

    2 $800 $100

    3 -$800 $150

    Instructed by YIN SOKHENG, Master in Finance

    36

    Example of Investment Rules

    Project A Project BCF0 -$200.00 -$150.00

    PV0 of CF1-3 $241.92 $240.80

    NPV = $41.92 $90.80

    IRR = 0%, 100% 36.19%

    PI = 1.2096 1.6053

    Instructed by YIN SOKHENG, Master in Finance

  • 8/3/2019 Fundamental of Corporate Finance,chpt9

    13/13

    37

    Example of Investment Rules

    Payback Period:

    Project A Project B

    Time CF Cum. CF CF Cum. CF

    0 -200 -200 -150 -150

    1 200 0 50 -100

    2 800 800 100 0

    3 -800 0 150 150

    Payback period for project B = 2 years.

    Payback period for project A = 1 or 3 years?

    Instructed by YIN SOKHENG, Master in Finance

    38

    Relationship Between NPV and IRR

    Discount rate NPV for A NPV for B

    -10% -87.52 234.77

    0% 0.00 150.00

    20% 59.26 47.92

    40% 59.48 -8.60

    60% 42.19 -43.07

    80% 20.85 -65.64

    100% 0.00 -81.25120% -18.93 -92.52

    Instructed by YIN SOKHENG, Master in Finance

    39

    Project AProject B

    ($200)

    ($100)

    $0

    $100

    $200

    $300

    $400

    -15% 0% 15% 30% 45% 70% 100% 130% 160% 190%

    Discount rates

    N

    PV

    IRR 1(A) IRR (B)

    NPV Profiles

    Cross-over Rate

    IRR 2(A)

    Instructed by YIN SOKHENG, Master in Finance