furnish and install emergency … a technical specifications to furnish and install emergency...

74
EXHIBIT A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS\Telecommunications\Facilities\Generators_BigPine KeyFDOT\BigPineKeyFDOT_Generator Tech Spec 2015 11 05 REV 0.0.docx

Upload: vancong

Post on 12-Apr-2018

225 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

EXHIBIT A

TECHNICAL SPECIFICATIONS

TO

FURNISH AND INSTALL

EMERGENCY GENERATOR POWER SYSTEM

AT BIG PINE KEY FDOT

November 5, 2015

FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS\Telecommunications\Facilities\Generators_BigPine

KeyFDOT\BigPineKeyFDOT_Generator Tech Spec 2015 11 05 REV 0.0.docx

Page 2: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 1 of 56

1. PROJECT SCOPE ........................................................................................................................................ 3 1.1 General ................................................................................................................ 3

1.2 Conduct of the Work ............................................................................................ 3

1.3 Drawings and Project Plans ................................................................................. 4

1.4 Definitions ............................................................................................................ 4

1.5 Acronyms and Abbreviations ............................................................................... 5

1.6 Applicable Publications, Standards and Codes .................................................... 7

1.7 Vendor’s Responsibility ...................................................................................... 10

1.8 Authority to Suspend Vendor’s Operations ........................................................ 10

1.9 Method and Rate for Extension of Project Schedule .......................................... 10

1.10 Changes in Work ............................................................................................... 11

1.11 No Waiver of Contract ........................................................................................ 11

1.12 Site Access and Security Requirements ............................................................ 11

1.13 Right to Remove Personnel from Project ........................................................... 11

1.14 Material and Workmanship ................................................................................ 12

1.15 Software Updates and Vendor Documentation .................................................. 12

1.16 Patents and Royalties ........................................................................................ 12

1.17 Kickoff Meeting .................................................................................................. 13

1.18 Progress Reporting ............................................................................................ 13

1.19 Submittals .......................................................................................................... 13

1.20 Project Closeout ................................................................................................ 17

2. EQUIPMENT INSTALLATIONS AND CONFIGURATIONS ...................................................................... 20 2.1 General .............................................................................................................. 20

2.2 Site Address ...................................................................................................... 20

2.3 Emergency Generator Power System ................................................................ 21

2.4 Automatic Load Transfer Controls ...................................................................... 22

2.5 Fuel System and Storage ................................................................................... 26

2.6 Grounding and Surge Protection ........................................................................ 27

2.7 Remote Alarm Monitoring .................................................................................. 32

2. PRE-CONSTRUCTION SUBMITTAL REQUIREMENTS .......................................................................... 36 3.1 Design Documentation Submittal ....................................................................... 36

3.2 Site Plan Requirements ..................................................................................... 36

3.3 Maintenance of Traffic ....................................................................................... 36

3.4 Engine Generator Submittals ............................................................................. 37

3.5 Automatic Transfer Switch Submittals ................................................................ 39

4. SITE WORK ................................................................................................................................................ 40 4.1 General .............................................................................................................. 40

4.2 Permits .............................................................................................................. 40

Page 3: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 2 of 56

4.3 Existing Communications System ...................................................................... 41

4.4 Clearing of Land ................................................................................................ 41

4.5 Weed Prevention Material .................................................................................. 41

4.6 Compound Gravel .............................................................................................. 41

4.7 Excavations ....................................................................................................... 42

4.8 Wall Penetrations ............................................................................................... 42

4.9 Compound Treatment and Fencing .................................................................... 42

4.10 Sanitary Provisions ............................................................................................ 43

4.11 Debris Removal ................................................................................................. 43

4.12 Excess Garbage and Clutter .............................................................................. 43

5. POST INSTALLATION SUBMITTAL REQUIREMENTS ........................................................................... 43 5.1 As-Built Survey and Drawings ............................................................................ 43

5.2 Engine Generator Documentation ...................................................................... 44

5.3 Automatic Transfer Switch Documentation......................................................... 44

6. INSPECTIONS AND TESTING .................................................................................................................. 46 6.1 General .............................................................................................................. 46

6.2 Emergency Generator Testing ........................................................................... 46

6.3 Automatic Transfer Switch Inspection ................................................................ 48

6.4 Electrical Inspection ........................................................................................... 49

6.5 Grounding Inspection ......................................................................................... 49

6.6 Site Inspection ................................................................................................... 53

6.7 Performance Testing .......................................................................................... 53

6.8 Substantial Completion ...................................................................................... 54

6.9 Single Manufacturer ........................................................................................... 54

6.10 Training .............................................................................................................. 55

6.11 Service and Support .......................................................................................... 55

6.12 Warranty ............................................................................................................ 55

APPENDIX A BIG PINE KEY FDOT REQUIREMENTS……………….……...…A1

APPENDIX B SPARE EQUIPMENT…………………………..……………….…..B1

Page 4: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 3 of 56

1. PROJECT SCOPE

1.1 General

The Florida Department of Transportation (FDOT) operates remote microwave sites

throughout the state. The FDOT desires to install an emergency standby generator

power system at the Big Pine Key FDOT Site.

This Technical Specification delineates the requirements for the design, design

documentation, delivery, installation, and verification and/or testing of the emergency

generator to support communications equipment. These technical specifications include

the complete installation of the emergency generator power system, Automatic Transfer

Switch (ATS), and new AC surge protective devices (SPDs).

Appendix A of this document provides the specific requirements of this project. Appendix

B provides a list of spare equipment to be provided by the Vendor.

THIS MAIN DOCUMENT CONTAINS GENERAL SPECIFICATIONS FOR EQUIPMENT

THAT MAY NOT BE APPLICABLE TO THE APPENDIX. THE VENDOR SHALL

PERFORM THE WORK BASED UPON THE REQUIREMENTS OF THE SITE AS

DELINEATED IN THE APPENDIX. THE VENDOR SHALL USE THE GENERAL

SPECIFICATIONS DOCUMENT FOR EQUIPMENT SPECIFICATIONS AND

INSTALLATION REQUIREMENTS.

1.2 Conduct of the Work

The Vendor shall schedule with FDOT for access to the site and work area. The Vendor

shall provide security for equipment as required by FDOT, and shall conduct operations

so as to avoid interference with FDOT's normal operations.

The Vendor shall verify all dimensions at the site and shall be responsible for the

correctness before ordering materials or performing work that is dependent on proper

size or installation requiring coordination with site conditions. No consideration shall be

given to any claim based on the difference between the actual dimensions and those

indicated on the drawings. Any discrepancies between the drawings and/or

specifications and the existing conditions shall be referred to the FDOT’s Project

Manager for adjustment before any work affected thereby is begun.

Work to be performed outside these Technical Specifications shall be referred to as "By

others", or if by the State of Florida's designated representative then "By FDOT". The

Page 5: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 4 of 56

Vendor shall be responsible for coordinating work with that of "others" or FDOT

wherever an interface is required.

1.3 Drawings and Project Plans

The drawings and project plans are typically diagrammatic. They are as accurate as

scale permits and the Vendor shall follow them as closely as possible. Any field

conditions that change the required installation shall be reported to FDOT. The Vendor

shall verify all conditions and measurements relating to the work in the field prior to

proceeding with installation. The Vendor shall verify all walls, rack profiles, cable trays,

and conduit lengths at the existing facilities and include all conditions required to install

equipment and systems as described herein and as shown on the drawings. All offsets

required for installation of conduit and wiring systems shall be included in this project at

no additional cost to FDOT. The Vendor shall coordinate any modifications required by

existing conditions to avoid conflicts of building systems and other building components.

The drawings, project plans, and specifications are complementary, and any work

required by one and not the other shall be considered to be required by both. The FDOT

Project Manager shall be the sole interpreter of the drawings and specifications.

The Vendor shall note that all drawings and details are diagrammatic in general and

indicate the character of the work included. Work intended, but having minor details

obviously omitted or not shown, shall be furnished and installed complete to perform the

functions desired.

1.4 Definitions

FDOT: State of Florida

Florida Department of Transportation (FDOT)

in Tallahassee, Florida.

FDOT Project Manager

and/or Engineer:

Randy Pierce

FDOT Traffic Engineering and Operations – ITS Section

605 Suwannee Street, MS 90

Tallahassee, Florida 32399-0450

V: (850) 410-5608, F: (850) 410-5501

[email protected]

Page 6: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 5 of 56

Proposer: The individual, firm, partnership, corporation, company,

association, or other legal entity permitted by law to

construct projects, or portions of projects, in the State of

Florida to whom this specification is submitted and from

whom a sealed proposal is received.

Vendor: The individual, firm, partnership, corporation, company,

association, or other legal entity to whom

the contract is awarded by FDOT and who is subject to

the terms thereof.

Vendor Project Manager: The Vendor’s project contact person who has the project

responsibility.

Local Contact Person: Sean Kane

FDOT Traffic Engineering and Operations – ITS Section

605 Suwannee Street, MS 90

Tallahassee, Florida 32399-0450

V: (850) 410-5612, F: (850) 410-5501

[email protected]

1.5 Acronyms and Abbreviations

A Ampere

AIA American Institute of Architects

ANSI American National Standards Institute

APT Advanced Protection Technologies

ASTM American Society for Testing and Materials

ATS Automatic Transfer Switch

AWG American Wire Gauge

DIM Digital In/Out Module

EIA Electronic Industries Alliance

EMT Electrical Metallic Tubing

FCC Federal Communications Commission

FDOT Florida Department of Transportation

H-1 Standard Potential Rating for Magnesium Anodes

Hz Hertz

IEC International Electrotechnical Committee

Page 7: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 6 of 56

IEEE Institute of Electrical and Electronics Engineers

ISO International Organization for Standardization

kA Kiloamp

kHz Kilohertz

kW Kilowatt

kWh Kilowatt hour

LPG Liquid Propane Gas

MDF Main Distribution Frame

MB Main Breaker

MG Motors and Generators (Used by NEMA for Standards)

MHz Megahertz

MOV Metal Oxide Varistor

MTS Manual Transfer Switch

NAD83 North American Datum of 1983

NEC National Electrical Code

NEMA National Electrical Manufacturers Association

NFPA National Fire Protection Association

NO/NC Normally Open/ Normally Closed

NPGA National Propane Gas Association

OSHA Occupational Safety and Health Administration

PMG Permanent Magnet Generator

PVC Polyvinyl Chloride (Conduit)

Psi Pounds per Square Inch

RMC Rigid Metal Conduit

RPM Revolutions Per Minute

SAD Silicon Avalanche Diode

SCCR Short Circuit Current Rating

SPD Surge Protection Device

TW Thermoplastic Moisture Resistance Wiring Insulation

UL Underwriters Laboratory

UV Ultra Violet

VAC Volts, Alternating Current

VDC Volts, Direct Current

Page 8: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 7 of 56

1.6 Applicable Publications, Standards and Codes

The following publications and standards shall be of the latest issue on the date of the

request for proposal, unless otherwise specified, and shall be part of this specification.

In the event of inconsistencies between this specification and these publications and

standards, the requirements of this specification shall take precedence.

1.6.1 General Standards and Codes

A. ASCE-7: Structural and Wind Loading Standards (Applicable in Some Florida

Counties).

B. ASTM A123: Standard Specification for: Zinc (Hot Galvanized) coatings on

products fabricated from rolled, pressed, and forged steel shapes, plates, bars,

and strip.

C. ASTM A153: Standard Specification for: Zinc coating (hot-dip) on iron and steel

hardware.

D. EIA-81: Measuring Ground Resistance and Potential Gradients in the Earth.

E. IEEE C62.33-1982 (Reaff 1994): Standard Test Specifications for Varistor Surge-

Protective Devices (ANSI).

F. IEEE C62.35-1987: Standard Test Specifications for Avalanche Junction

Semiconductor Surge-Protective Devices (ANSI).

G. IEEE C62.41-1994: Recommended Practice on Surge Voltages in Low-Voltage

Data, Communications, and Signaling Circuits.

H. National Electrical Code (NFPA 70).

I. UL 1561: Dry Type General Purpose and Power Transformers.

J. UL 752: Standard for bullet-resistive surfaces.

K. Applicable Manufacturer's Instructions and Standard Practices.

L. Florida Department of Transportation 2010 Design Standards.

M. Florida Department of Transportation 2010 Standard Specifications for Road and

Bridge Construction, Divisions II and III.

Page 9: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 8 of 56

N. American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel

Code ASME certification.

O. Occupational Safety and Health Administration (OSHA).

1.6.2 Engine Generator Standards and Codes

The generator set installation and on-site testing shall conform to the requirements of the

following codes and standards, as applicable. The generator set shall include necessary

features to meet the requirements of the following standards:

CSA 282, 1989 Emergency Electrical Power Supply for Buildings.

IEEE 446 Recommended Practice for Emergency and Standby Power Systems

for Commercial and Industrial Applications.

ISO 9001 2000 Quality Management System Requirements.

NFPA 70 National Electrical Code. Equipment shall be suitable for use in

systems in compliance to Article 700, 701, and 702.

NFPA110 Emergency and Standby Power Systems (the generator set shall meet

all requirements for Level 1 systems. Level 1 prototype tests required by this

standard shall have been performed on a complete and functional unit,

component level type tests shall not substitute for this requirement).

NEMA MG1-1998 part 32. Alternator shall comply with the requirements of this

standard.

UL 58 Standard for Safety for Steel Underground Tanks for Flammable and

Combustible Liquids.

UL 1236 – Battery Chargers.

UL 2200. The generator set shall be listed to UL 2200 or submit to an

independent third party certification process to verify compliance as installed.

CSA C22.2, No. 14 – M91 Industrial Control Equipment.

EN 50082-2, Electromagnetic Compatibility – Generic Immunity Requirements,

Part 2: Industrial.

EN55011, Limits and Methods of Measurement of Radio Interference

Characteristics of Industrial, Scientific and Medical Equipment.

FCC Part 15, Subpart B.

IEC 8528 part 4. Control Systems for Generator Sets.

Page 10: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 9 of 56

IEC Std 801.2, 801.3, and 801.5 for susceptibility, conducted, and radiated

electromagnetic emissions.

UL 508 (Industrial Control Equipment). The entire control system of the

generator set shall be UL508 listed and labeled.

UL 1236 – Battery Chargers.

The generator set manufacturer shall be certified to ISO 9001 International Quality

Standard and shall have third party certification verifying quality assurance in

design/development, production, installation, and service, in accordance with ISO 9001.

1.6.3 Automatic Transfer Switch Standards and Codes

The ATS shall conform to the requirements of the following codes and standards:

UL1008. The transfer switch shall be UL listed and labeled.

CSA C22.2, No. 14 – M91 Industrial Control Equipment.

CSA 282, Emergency Electrical Power Supply for Buildings.

IEEE Standard C62.41 and C62.45.

NFPA70 – National Electrical Code. Equipment shall be suitable for use in

systems in compliance to Article 700, 701, and 702.

NFPA99 – Essential Electrical Systems for Health Care Facilities.

NFPA110 – Emergency and Standby Power Systems. The transfer switch shall

meet all requirements for Level 1 systems.

IEEE446 – Recommended Practice for Emergency and Standby Power Systems

for Commercial and Industrial Applications.

NEMA ICS10-1993 – Alternating Current (AC) ATS.

UL 508 Industrial Control Panels Suppliers.

UL 891 Standard for Safety Switchboards.

The transfer switch manufacturer shall be certified to ISO 9001 International

Quality Standard and shall have third party certification verifying quality

assurance in design/development, production, installation, and service, in

accordance with ISO 9001.

Page 11: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 10 of 56

1.7 Vendor’s Responsibility

It is understood, and the Vendor hereby agrees, that the Vendor is solely responsible for

all equipment, materials, and services proposed. Notwithstanding the details presented

in these specifications, the Vendor is responsible for verifying the completeness of the

materials required and suitability of devices to meet these specifications. The Vendor

shall provide and install, without claim, any additional equipment required for operation

in accordance with these specifications.

1.8 Authority to Suspend Vendor’s Operations

FDOT has the authority to suspend the Vendor’s operations, wholly or in part. FDOT

shall order such suspension in writing, giving in detail the reasons for the suspension.

Contract time shall be charged during all suspensions of the Vendor’s operations. FDOT

may grant an extension of contract time when determined appropriate in FDOT’s sole

judgment.

No time extension shall be granted to the Vendor when the operations are suspended

for, including but not limited to, the following reasons:

The Vendor fails to comply with the contract documents.

The Vendor fails to carry out orders given by FDOT.

The Vendor causes conditions considered unfavorable for continuing the work.

The Vendor shall immediately comply with any suspension order. The Vendor shall not

resume operations until authorized to do so by FDOT in writing. Any operations

performed by the Vendor after the issuance of the suspension order, and prior to

FDOT’s authorization to resume operations, shall be at no cost to FDOT, without regard

to whether otherwise installed in conformance with the provisions of the contract.

Further, failure to immediately comply with any suspension order shall also constitute an

act of default by the Vendor and is deemed sufficient basis in and of itself for FDOT to

declare the Vendor in default.

1.9 Method and Rate for Extension of Project Schedule

The Vendor shall not be entitled to any damages, of any nature or kind, for delays,

regardless of cause or responsibility. Rather, the Vendor’s sole remedy for delay shall

be time.

Page 12: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 11 of 56

1.10 Changes in Work

FDOT may at any time, by written amendment to the contract, make changes within the

general scope of the work, including, but not limited to, revisions, deletions or additions

to portions of the work; or changes in the method of shipment or packaging and place of

delivery, upon appropriate approvals as allowed by FDOT’s procurement code.

If any change order initiated by FDOT causes an increase or decrease in the cost or

time required for the performance of any part of the work under the contract, an

equitable adjustment shall be made by FDOT in the contract price or delivery schedule,

or both, and the contract shall be modified in writing accordingly. Adjustments to

contract price for labor shall be based on the actual direct labor and burden reasonably

incurred in the additional or unforeseen work, plus a mark-up not to exceed 10 percent.

Adjustments to contract price for actual equipment and supplies shall be based on the

actual cost of equipment and supplies incorporated into the work, including Vendor paid

transportation charges, reasonably incurred in the additional or unforeseen work, plus a

mark-up not to exceed 10 percent.

1.11 No Waiver of Contract

Changes made by FDOT shall not be considered to waive any of the provisions of the

contract, nor may the Vendor make any claim for loss of anticipated profits because of

the changes, or by reason of any variation between the approximate quantities and the

quantities of work actually performed. All work shall be performed as directed by FDOT

and in accordance with the contract documents.

1.12 Site Access and Security Requirements

The FDOT system addressed in this contract supports public safety applications

including Intelligent Transportation Systems, Highway Maintenance, and the Statewide

Law Enforcement Radio System. To ensure security for the system, FDOT requires that

the Vendor or Vendor employees submit to security background checks performed by

the Florida Department of Law Enforcement after award of contract. At any time that

employees of the Vendor are working at an FDOT communications site, a minimum of

one of those employees on the site shall possess this clearance.

1.13 Right to Remove Personnel from Project

FDOT has the right to remove any Vendor or Vendor personnel from the project for any

reason. FDOT shall send a written notification to the Vendor, via fax, that a particular

person shall be removed from the project. The Vendor shall remove the particular

person from the project within 24 hours of transmission of the written notice.

Page 13: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 12 of 56

1.14 Material and Workmanship

All equipment and component parts furnished shall be new, meet or exceed the

minimum requirements stated herein, and perform to manufacturer’s specifications.

All parts shall be of high quality workmanship and utilize the most current technology

available. No part or attachment shall be substituted or applied contrary to the

manufacturer's recommendations and standard practices. At the time of delivery and

installation, the most current revision model of each type of equipment meeting or

exceeding the requirements of this contract shall be provided, regardless of the model

offered in the proposal.

1.15 Software Updates and Vendor Documentation

FDOT requires that the Vendor provide the most current versions of software available if

applicable at the time of the negotiated delivery within the project schedule. FDOT

requires, at no additional charge, software releases, firmware upgrades, and associated

documentation that are intended by the Vendor as generic version updates to correct

reproducible and/or recurring defects (software bugs).

FDOT requires the Vendor to provide timely pre-release notification and documentation

of all planned system software upgrades during the project schedule.

1.16 Patents and Royalties

The Vendor warrants that the equipment and software furnished hereunder shall be

delivered free of any rightful claim of any third party for infringement of any United States

patent or copyright. If FDOT notifies the Vendor of the receipt of any claim that the

equipment or software infringes a United States patent or copyright and gives the

Vendor information, assistance, and exclusive authority to settle and defend such claim,

the Vendor at its own expense shall defend and hold harmless FDOT from, or may

settle, any suit or proceeding against FDOT so far as based on a claimed infringement

which breaches this warranty. If, in any such suit arising from such claim, the continued

use of the equipment and software for the purpose intended is enjoined by any court of

competent jurisdiction, the Vendor shall, at its expense and option, either procure for

FDOT the right to continue using the equipment and software, or modify the equipment

and software so that it becomes non-infringing, or replace the equipment and software or

portions thereof so that it becomes non-infringing.

FDOT reserves the right to be actively involved in any litigation arising hereto.

Page 14: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 13 of 56

1.17 Kickoff Meeting

A kickoff meeting shall be held on a date and location to be determined by the FDOT.

Required attendees shall be notified as to the date and time of the meeting. Minutes of

the meeting shall be prepared and distributed by the FDOT Project Manager.

1.18 Progress Reporting

The Vendor shall provide weekly progress reports on work schedules. The Vendor shall

also provide progress reports against the approved weekly work schedule.

1.19 Submittals

1.19.1 General

This section specifies administrative and procedural requirements for submittals required

for performance of the Work, including:

Vendor’s construction schedule

Design Drawings

Materials Product data

Special reports

1.19.2 Coordination

The Vendor shall coordinate the preparation and processing of submittals with

performance of construction activities. The Vendor shall transmit each submittal at least

10 days prior to related construction activities to avoid delay.

The Vendor shall coordinate each submittal with purchasing, testing, delivery, other

submittals, and related activities that require sequential activity.

The Vendor shall coordinate transmittal of different types of submittals for related

elements of the Work so processing shall not be delayed by the need to review

submittals concurrently for coordination.

FDOT reserves the right to withhold action on a submittal requiring coordination with

other submittals until related submittals are received.

1.19.3 Processing

The Vendor shall allow sufficient review time so that installation shall not be delayed as

a result of the time required to process submittals, including time for resubmittals.

Page 15: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 14 of 56

The Vendor shall allow 10 business days for initial review. The Vendor shall allow

additional time if processing shall be delayed to permit coordination with subsequent

submittals. FDOT shall promptly advise the Vendor when a submittal being processed

shall be delayed for coordination.

If an intermediate submittal is necessary, the Vendor shall process the submittal the

same as the initial submittal.

The Vendor shall allow 10 business days for reprocessing each submittal.

No extension of contract time shall be authorized because of failure to transmit

submittals to FDOT sufficiently in advance of the work to permit processing.

1.19.4 Submittal Preparation

The Vendor shall place a permanent label or title block on each submittal for

identification. The Vendor shall indicate the name of the entity that prepared each

submittal on the label or title block.

The Vendor shall provide a space approximately 4" x 5" on the label or beside the title

block on design drawings to record the Vendor’s review and approval markings and the

action taken.

Include the following information on the label for processing and recording action taken:

Project name

Date

Name and address of Vendor

Name and address of SubVendor

Name and address of supplier

Name of manufacturer

Number and title of appropriate specification section

Drawing number and detail references, as appropriate

1.19.5 Submittal Transmittal

The Vendor shall package each submittal appropriately for transmittal and handling.

The Vendor shall transmit each submittal to FDOT using a transmittal form. Submittals

received from sources other than the Vendor shall be returned without action.

The Vendor shall record relevant information and requests for data on the transmittal.

The Vendor shall record deviations from contract document requirements, including all

variations and limitations on the transmittal or on a separate sheet. The Vendor shall

Page 16: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 15 of 56

include the Vendor’s certification that information complies with contract document

requirements.

1.19.6 Vendor’s Construction Schedule

1.19.6.1 General

The Vendor shall prepare a fully developed construction schedule. The Vendor shall

submit its initial schedule within 10 days of receipt of Notice to Proceed.

The Vendor shall secure time commitments for performing critical elements of the work

from all parties involved. The Vendor shall coordinate each element on the schedule

with other construction activities; include minor elements involved in the sequence of the

work. The Vendor shall show each activity in proper sequence.

The Vendor shall coordinate the construction schedule with SubVendors, submittal

schedule, payment requests and other schedules.

1.19.6.2 Distribution

The Vendor shall submit copies to FDOT, SubVendors, and other parties required to

comply with scheduled dates.

When revisions are made, the Vendor shall distribute the updated schedule to the same

parties. The Vendor shall remove parties from distribution when they have completed

their assigned portion of the work and are no longer involved in construction activities.

1.19.6.3 Schedule Updating

The Vendor shall revise the schedule after each meeting or activity, where revisions

have been recognized or made. The Vendor shall issue the updated schedule

concurrently with report of each meeting.

1.19.7 Design Documentation

The Vendor shall submit design documentation for approval by the FDOT prior to

installation.

Design Documentation shall include site plans, fence details, grounding plan, electrical

one line diagrams, generator pad foundation design, LP tank pad foundation design and

generator wall enclosure design.

Page 17: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 16 of 56

The Vendor shall submit electronic design drawings to the FDOT for review and

approval.

1.19.8 Product Data

The Vendor shall collect product data into a single submittal for each element of

construction for the system. The product data shall include printed information such as

manufacturer's installation instructions and performance specifications.

The Vendor shall mark each copy to show applicable choices and options. Where

printed product data includes information on several products, some of which are not

required, the Vendor shall mark copies to indicate the applicable information. The

Vendor shall include the Vendor’s certification that the product complies with contract

document requirements.

The Vendor shall submit electronic copies of each required submittal.

The Vendor shall furnish copies of the final submittal to installers, subcontractors,

suppliers, manufacturers, and others required for performance of construction activities.

The Vendor shall show the distribution on transmittal forms.

The Vendor is required to submit materials/product data for approval by the FDOT prior

to installation.

1.19.9 Submittal Actions

Except for submittals of record, information or similar purposes, where action and return

is not required or requested, FDOT shall review each submittal and return comments to

the Vendor.

The Vendor shall comply with FDOT’s review comments.

1.19.10 Special Reports

Except when otherwise indicated, the Vendor shall submit special reports directly to

FDOT within one day of occurrence requiring special report, with copies to others

affected by the occurrence.

The Vendor shall prepare and submit reports of significant accidents at the site and

anywhere else work is in progress to FDOT. The Vendor shall record and document

data and actions, and shall comply with industry standards. For this purpose, a

significant accident is defined to include events where personal injury is sustained, or

Page 18: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 17 of 56

property loss of substance is sustained, or where the event posed a significant threat of

loss or personal injury.

1.19.11 As Built Documentation

The Vendor shall submit newly prepared information and, when required, drawn to

accurate scale.

As built drawings include, but are not limited to, site plans, fence details and notes,

grounding plan, electrical one line diagram, alarm block details, underground LPG tank

details, indoor and outdoor equipment wall mount details, generator and lp tank pad

foundation details, wall enclosure details, wiring diagrams, installation drawings, and

similar drawings.

THE VENDOR SHALL SUBMIT THREE SETS OF AS BUILT DRAWINGS, TWO HARD

COPIES AND ONE SOFT COPY, FOR FDOT REVIEW.

1.20 Project Closeout

1.20.1 Substantial Completion

Substantial Completion is defined as the point at which the equipment is fully installed,

operational, has successfully passed field acceptance testing of all elements, and

inspections are completed.

Before requesting inspection for certification of Substantial Completion, the Vendor shall

complete the following:

In the application for payment that coincides with, or first follows, the date

Substantial Completion is claimed, include supporting documentation for

completion as indicated in these contract documents and a statement showing

an accounting of changes in the contract sum.

If 100 percent completion cannot be shown, include a list of incomplete items, the

value of incomplete construction, and reasons the work is not complete.

Advise FDOT of pending insurance change-over requirements.

Submit specific warranties, workmanship bonds, maintenance agreements, final

certifications and similar documents.

Page 19: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 18 of 56

Obtain and submit releases enabling FDOT unrestricted use of the work and

access to services and utilities; include operating certificates and similar

releases.

On receipt of a request for inspection for substantial completion, FDOT shall either

proceed with inspection or advise the Vendor of unfulfilled requirements. FDOT shall

prepare the Certificate of Substantial Completion following the inspection, or advise the

Vendor of construction that shall be completed or corrected before the certificate shall be

issued.

FDOT shall repeat inspection when requested and assured that the work has been

substantially completed.

1.20.2 Final Acceptance

Final Acceptance is defined as the point at which all work is completed, all as built

documentation is submitted, all closeout forms are completed and submitted, and

equipment spares, manuals, and training have been provided.

A. Before requesting inspection for Certification of Final Acceptance, the Vendor

shall complete the following: Submit as-built documentation, maintenance

manuals, final project photographs, and similar final record information.

B. Deliver spare parts and similar items.

C. Complete final clean up requirements.

D. Submit the final payment request with releases and supporting documentation

not previously submitted and accepted. Include certificates of insurance for

products and completed operations where required.

E. Submit an updated final statement, accounting for final additional changes to the

contract sum.

F. Submit a copy of FDOT's final inspection list of items to be completed or

corrected, stating that each item has been completed or otherwise resolved for

acceptance. List any and all exceptions on this list.

G. Prior to final acceptance of the work, the Vendor shall furnish to FDOT the

following executed documents:

Page 20: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 19 of 56

1. VENDOR’S AFFIDAVIT OF RELEASE OF LIENS, American Institute of

Architects (AIA) Document G706A and releases or waivers of liens from all

SubVendors and material and equipment suppliers.

2. VENDOR’S AFFIDAVIT OF DEBTS AND CLAIMS, AIA Document G706.

3. CONSENT OF SURETY COMPANY TO FINAL PAYMENT, AIA Document

G707.

H. Submit all required inspection certificates, bonds, and written guarantees.

I. Return all FDOT provided keys for access to the site. Include affidavit that

duplications of keys have not occurred.

FDOT shall re-inspect the work upon receipt of notice that all the work, including

inspection list items from earlier inspections, has been completed, except items whose

completion has been delayed because of circumstances acceptable to FDOT. Upon

completion of re-inspection, FDOT shall prepare a Certificate of Final Acceptance, or

advise the Vendor of work that is incomplete or of obligations that have not been fulfilled

but are required for Final Acceptance. If necessary, re-inspection shall be repeated.

1.20.3 Closeout Checklist

All items listed below, with the exception of the first item listed, shall be bound in

individual heavy-duty 3-ring vinyl covered binders. The Vendor shall mark appropriate

identification on front and spine of each binder.

All items shall be submitted in triplicate within fifteen days of Substantial Completion for

the project:

Application and Certification for Payment (Final). Four copies with original

signatures and seals.

Vendor’s Affidavit of Payment of Debts (AIA G706).

Vendor’s Affidavit of Release of Liens from all Vendor’s, Sub-Vendor’s and

suppliers (AIA G706A).

Power of Attorney from Surety to make Final Payment.

Consent of Surety to Final Payment (AIA G707).

Warrantees as required by the specifications, in the name of FDOT.

Page 21: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 20 of 56

Verification that FDOT’s personnel has been trained in the use of their new

equipment. Submit a sign-in sheet signed by personnel receiving the training.

As-built documentation of maintenance and operation manuals.

Equipment Inventory List including manufacturer and serial numbers.

Notarized affidavit of all SubVendor payrolls, bills for materials/equipment and

other indebtedness paid and satisfied.

2. EQUIPMENT INSTALLATIONS AND CONFIGURATIONS

2.1 General

This section establishes the minimum requirements for the installation of the emergency

generator power system, fuel tank, automatic transfer switch (ATS), and surge protective

devices (SPD), as required, to be located at the Big Pine Key FDOT site listed below and in

Appendix A.

IN ADDITION, THE APPENDIX MAY CONTAIN SPECIFICATIONS THAT ADD TO OR

DIFFER FROM THE MAIN DOCUMENT. THE SPECIFICATIONS IN THE APPENDIX

SHALL TAKE PRECEDENCE OVER THE MAIN DOCUMENT.

All equipment supplied as part of this project shall be in compliance, unless otherwise

stated, with FDOT 2014 Standard Specifications for Road and Bridge Construction, and the

FDOT 2015 Design Standards.

The Vendor shall remove the existing generator, ATS, at the site and dispose of properly.

The Vendor shall install the new generator in the existing generator room and new ATS

within the equipment room at the Big Pine Key FDOT shelter once the existing generator

and ATS has been removed and disposed of properly.

2.2 Site Address

Big Pine Key FDOT Site, 450 Key Deer Boulevard, Big Pine Key, FL 33034

Lat: 24°40-30 N (NAD 83), Long. 81°21-39 W

Page 22: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 21 of 56

2.3 Emergency Generator Power System

The emergency generator power system shall be provided at the Big Pine Key FDOT

site as required by Appendix A. The generator shall be a Cummins 20 kW C20 N6, 60

Hz emergency power system configured for 120/240V single-phase AC power system.

The generator shall be configured for indoor installation and be furnished with all

accessories and equipment needed for the proper operation of the units. The

accessories and equipment for the generator shall include, but not be limited to, starting

battery, battery rack, battery charger, battery cable, cooling system, residential grade

exhaust silencer with exhaust pipe and rain cap, automatic frequency regulator,

vibration isolator, fuel line, fuel regulator, fuel storage tank, conduit, junction boxes,

wiring, instrument panel, local power duplex receptacle, remote alarm panel (mounted

inside the shelter) and mounting base.

The generator shall develop the minimum required power utilizing LPG (liquid propane

gas) fuel. The generator shall be installed per the manufacturer’s recommendations at

a location approved by the FDOT Project Manager and shall comply with the NEC

(National Electrical Code) and all applicable local codes.

All fuel, water, and exhaust system plumbing shall be flexible to meet vibration design

criteria and any applicable safety codes. The generator mounting base shall also be

installed to meet vibration design criteria. Both the generator and the mounting base

shall be connected to the site grounding system.

2.3.1 Vendor Engine Status Monitoring

The following information shall be available from a digital status panel on the generator

set controls:

Engine oil pressure (psi or kPA)

Engine coolant temperature (°F or °C)

Engine oil temperature (°F or °C)

Engine speed (RPM)

Number of hours of operation (hours)

Number of start attempts

Battery voltage (VDC)

Page 23: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 22 of 56

The control system shall also incorporate a data logging and display provision to allow

logging of the last 10 warning or shutdown indications on the generator set, as well as

total time of operation at various loads, as a percent of the standby rating of the

generator set.

2.3.2 Outdoor Protective Housing

This section does not apply to the Big Pine Key Site. The engine-generator shall be

provided with factory installed outdoor aluminum weather protective housing that will

withstand wind loading of 150 miles per hour rating or that required by the local building

code if higher. The outside weatherproof enclosure shall include a silencer per

Cummins standards for audible noise reduction. Easy access to the engine-generator

shall be provided by removable panels on each side of the housing. A rear-hinged door

shall be provided to allow access to the instrument panel.

2.4 Automatic Load Transfer Controls

2.4.1 General Requirements

An ATS (Automatic Transfer Switch) Cummins Model OTEC 125 configured for

120/240VAC, single-phase electric service shall be provided to transfer the AC load

between commercial power and the standby emergency generator power specified

herein.

The transfer switch shall comply with UL, NEMA, NEC, ANSI and NFPA standards. The

unit shall be completely factory-assembled and wired so that only external circuit

connections are required in the field.

The automatic load transfer control unit shall be installed indoors and contained in a

NEMA Type 1 enclosure. The control unit shall be furnished with all necessary relays,

component parts, and circuits, together with U.L. listed and tested electrical and

mechanical interlock contactor or circuit breakers to provide the following functions:

A. Time delayed automatic start of, and transfer to, the emergency generator

power system for any of the following conditions:

1. Commercial power failure.

2. Under voltage condition for any and all phases.

3. Overvoltage condition for any and all phases.

4. Over/under frequency condition for any and all phases.

Page 24: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 23 of 56

B. Upon return or stabilization of commercial power for a period of

approximately ten minutes, the load shall be transferred back to commercial

power. The generator shall continue to run in an unloaded condition (engine

cool-down) for a period of approximately five minutes after retransfer to

commercial power and then automatically shut down.

C. Automatic operation or stopping, checking or provisioning for manual

cranking/starting and transfer/retransfer of the emergency generator system

by means of a control selector switch.

2.4.2 Automatic Transfer Switch

A. The unit shall include a battery charger capable of producing 15 Amps at

12VDC. It shall also have an auxiliary relay switch in emergency position,

minus (-) 12 VDC, an auxiliary relay switch in normal position, minus (-)

12 VDC, a gen-set starting battery, minus (-) 12 VDC and a 30 point terminal

block. POSITIVE (+) GROUND IS REQUIRED.

B. The Cummins Model OTEC 125 shall be a 125 Amp, three-pole unit listed

with UL 1008. It shall be a three-phase, four-wire system rated for

120/240VAC at 60 Hz.

C. The Vendor shall connect the ATS ahead of the Manual Transfer Switch

(MTS) so that the ATS is ahead of the MTS in the power service feed as

shown in Figure 2.3.2.1 (20 kW generator to be used).

Page 25: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 24 of 56

Figure 2.3.2.1: Automatic Transfer Switch and Manual Transfer Switch Power Configuration

2.4.3 Construction

A. The automatic load transfer control unit shall be installed indoors and

contained in a NEMA Type 1 enclosure suitable for mounting indoors.

B. The enclosure shall be UL listed. The cabinet door shall be key-locking with

No. IL0333.

C. Transfer switch equipment shall be provided in a NEMA Type 1 indoor use

enclosure.

2.4.4 Control

A. Solid-state under voltage sensors shall simultaneously monitor both sources.

Pick-up and drop-out settings shall be adjustable. Voltage sensors shall have

field calibration of actual supply voltage to nominal system voltage.

B. Automatic controls shall signal the engine/generator set to start upon a signal

from the normal source sensor. Solid-state time delay start, adjustable from

0 to 15 seconds (factory set at two seconds) shall avoid nuisance start-ups.

Battery voltage starting contacts shall be silver, dry type contacts factory

wired to a field wiring terminal block.

Page 26: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 25 of 56

C. The switch shall transfer the load when the emergency source reaches the

pre-programmed time set point, and provide a solid-state time delay on

transfer, adjustable from two to 120 seconds (factory set at three seconds).

D. The switch shall retransfer the load to the normal source after a time delay,

adjustable from six seconds to 30 minutes (factory set at five minutes).

Retransfer time delay shall be immediately bypassed if the emergency power

source fails.

E. The generator controls will transfer the power back to the utility company

after 5 minutes of stable voltage and frequency from the utility company.

F. The transfer switch shall be provided with a battery charger for the generator

set starting batteries. The battery charger shall be a float type charger rated

at 10 Amps. The battery charger shall include an ammeter for display of

charging current and shall have the proper size and type of fuses

recommended by the manufacturer at both its AC inputs and DC outputs.

The charger shall also include fault indications for high and low DC voltage,

power supply failure, and dry contacts for external indication of these fault

conditions. Supply power failure shall be displayed on the ATS control panel.

G. Provide solid state exerciser clock to set the day, time, and duration of

generator set exercise/test period. Provide a with/without load selector switch

for the exercise period.

2.4.5 Plant Exerciser

A plant exercise timer shall be provided to periodically operate the engine-generator

without onsite user presence or intervention to maintain the reliability of the unit. The

timer shall be solid-state and user programmable from 0 to 168 hours (seven day),

adjustable to day of week, time of day, and duration of exercise period for up to one hour

(minimum) or to the manufacturer’s design standard. The timer shall allow the engine-

generator to exercise the site with or without a load.

2.4.6 Wiring

The Vendor shall provide and install all electrical wiring necessary to connect the

standby emergency generator power, automatic transfer panel, dry contact for remote

monitoring, and equipment building electrical loads. Power, control, and alarms shall be

run in separate conduits.

Page 27: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 26 of 56

All wiring shall meet or exceed the manufacturer’s specifications for designated load

requirements. All wiring shall be run in conduit and comply with applicable NEC and

local codes. All electrical materials and work shall be inspected and approved by the

FDOT Project Manager.

2.5 Fuel System and Storage

The Vendor shall use the existing fuel system piping sized as required for proper fuel

flow to the engine as required by the generator manufacturer. Additionally, all supply,

return, vent, and fuel lines, conduit, gauges, valves, alarm monitoring points, fuel storage

tank, fittings, and wiring are existing at Big Pine Key for the generator fuel storage

system.

All connections and plumbing to connect the existing fuel systems to the engine, where

applicable, do not apply to Figure 2.5.1, but shall be in compliance with applicable codes

and regulations.

Figure 2.5.1: Fuel System Installation

The generator set shall be provisioned with LPG fuel capabilities and connected to a the

Big Pine Key FDOT 1000 gallon existing LPG tank primary fuel source. The grade

relative to fuel source/fuel inlet shall be appropriately considered. LPG fuel tanks are

existing and shall utilize a fuel vent pressure relief valve. The relief valve vent shall be

directed away from the tank, sources of ignition, and flammable material. The fuel line

Page 28: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 27 of 56

ventilation conduit is existing and shall be ultra violet (UV) exposure rated. White PVC

(polyvinyl chloride) conduit shall not be used since it is not rated for UV exposure. Grey

PVC with designated conduit markings for UV exposure is required.

This paragraph is not applicable to this site installation since the fuel tank is existing at

this site. The Vendor shall engineer, furnish, and install all fuel storage equipment. This

includes all labor, materials, and services, including the connection of the fuel storage

equipment to the emergency generator. An approved Environmental Protection Agency

(EPA), 500 gallon LPG fuel tank for above ground installation must be used for storage.

All appropriate shut-off valves and pressure gauges must be included. The LPG tank

shall be installed per manufacturer’s recommended distance from open flames, sparks,

or other systems that can cause ignition. The LPG tank shall also be installed,

inspected, and stamped in accordance with the appropriate American Society of

Mechanical Engineers (ASME) Boiler and Pressure Vessel Code indicating that the

stamped vessel conforms to the latest edition of the ASME Boiler and Pressure Vessel

Codes safety standards and complies with the laws and regulations in all 50 US states

for pressure vessel construction.

2.5.1 Fuel Tank

Fuel storage equipment shall consist of an existing above ground 1000 gallon LPG fuel

storage tank.

The 1000 gallon tank is an above ground at the Big Pine Key FDOT site.

2.6 Grounding and Surge Protection

2.6.1 General

The installation of SPDs requires that lead lengths between the SPD and electric service

be kept to a minimum. Long lead lengths reduce performance characteristics of the

SPD necessary to adequately protect critical equipment. The SPD lead lengths shall not

exceed ten inches.

ANY VARIANCE FROM THE FDOT'S PRACTICES SHALL BE SUBMITTED IN

WRITING AND MUST BE PRE-APPROVED IN WRITING BY THE FDOT PROJECT

MANAGER OR IT WILL NOT BE ACCEPTED.

The SPDs shall be installed in accordance with NEC Article 285 titled “Surge Protective

Devices” and must comply with all related requirements of Articles 250 and 285 and with

manufacturer’s instructions for installation requirements. If any contradictions exist

within the SPD manufacturer’s installation requirements and NEC Articles 250 and 285,

Page 29: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 28 of 56

then the NEC takes precedence over the manufacturer’s installation requirements. The

SPDs shall be connected to the grounding system with no less than the minimum wire

size specified by NEC herein or the manufacturer's recommended wire size, whichever

is larger.

2.6.2 Surge Protective Devices (SPDs)

2.6.2.1 Type 1 Primary AC Power Surge Protective Device

The Vendor shall install two Type 1 Primary SPDs. One will be located at the Sheriff’s

office main breaker and the other at the FDOT communications shelter load center

breaker panel. The FDOT communications shelter Primary SPD shall be APT Model

TE01XAS30E1D-W2. The FDOT communications shelter Primary SPD shall be installed

on the load side of the breaker disconnect on the West interior wall in accordance with

Appendix A.

The Vendor shall provide a spare field replaceable MOV primary AC Power SPD unit.

For substitute product approval, the Vendor shall submit a certified, signed and sealed

statement from a Florida Registered Professional Engineer that the replacement device

meets or exceeds all requirements of this section.

The Vendor shall connect the Primary AC power SPD as designated in the Appendix

drawings of this document. The SPD shall be installed in accordance with the

manufacturer's instructions and shall be connected to the existing grounding system.

2.6.2.2 Type 1 Secondary AC Power Surge Protection Device

The Secondary AC power SPD shall be an ANSI C62.41, Category C rated, UL 1449

Third Edition, Type 1, AC power Surge Protective Device (SPD) as specified in the

Appendix. Enclosure ratings shall be the appropriate NEMA 1 listing for the SPD location

application point. The Secondary SPD shall be APT Model TE01XDS204XA-W2 and

shall be wired on the load side of a 40A-2P circuit breaker of the existing distribution

panel board within the Big Pine Key FDOT site equipment room.

The Vendor shall provide a spare field replaceable MOV secondary AC Power SPD unit.

For substitute product approval, the Vendor shall submit a certified, signed and sealed

statement from a Florida Registered Professional Engineer that the replacement device

meets or exceeds all requirements of this section.

The Vendor shall connect the Secondary AC power SPD as designated in the Appendix

A drawings of this document. The SPD shall be installed in accordance with the

manufacturer's instructions and shall be connected to the existing grounding system.

Page 30: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 29 of 56

2.6.3 Grounding and Bonding

2.6.3.1 Ground Rods

Ground Rods to not apply to this project. All new ground rods shall be copper-clad steel

with a minimum diameter of 5/8 inch and 10 feet long Harger Model 5810UPC, or

approved equivalent.

The installation and spacing of the new ground rods shall be in accordance with the

Appendix of this document.

2.6.3.2 Ground Strap

All new ground straps shall be four inch by 1/8 inch oxygen-free solid copper conductor,

Harger Model CB184XXXN, or approved equivalent and used to mount the low voltage

SPD within the site equipment room per Appendix A drawings.

2.6.3.3 Exothermic Bonds

Exothermic bonds shall be UL 467 listed and IEEE 837 approved. Exothermic bonds

shall be Erico CADWELDTM type, Harger ULTRAWELDTM, or approved equivalent and

appropriate for the application. Exothermic bonds between ground conductors and

ground rods shall be performed using “one-shot” style exothermic bonds (Erico One

Shot, Harger Uni-Shot, or approved equivalent).

Welding or other forms of exothermic bonding shall not be used unless approved in

writing by the FDOT Project Manager.

2.6.3.4 Mechanical Bonds (Compression Connections)

Mechanical compression bonds shall be made using either C-type compression taps or

a combination of bolts, washers, lock washers, and nuts, as appropriate. All cable to lug

connections shall be compression type to a minimum of 12 tons of pressure, or as

otherwise required by the specific component manufacturer. All irreversible

compression connections for use on external grounding applications shall be UL 467

listed and IEEE 837 approved. Copper connectors shall maintain maximum conductivity

with a minimum conductivity rating of 88 percent. Compression systems shall include

crimped die index and company logo for purposes of inspection. Aluminum shall not be

used for connection purposes. Split bolts and other mechanical connection methods

shall not be used.

Page 31: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 30 of 56

The Vendor shall use a Harger Model HT131LC or B131LCA compression tool, or

equivalent to make compression-type connections. Compression lugs shall be Harger

Model GECLB series two-hole long barrel compression lugs, or approved equivalent.

Bonds between a round conductor interior shelter halo and ground wires shall be made

using a parallel tap type connection using C-type compression taps (Harger Heavy Duty

Compression Tap series, or approved equivalent). Bonds between a flat conductor

interior shelter halo and ground conductors shall be made using two-hole long barrel

compression lugs consisting of bolts, washers, lock washers, and nuts. Bolts shall be

stainless steel hex head, Harger CS series, or approved equivalent. Washers shall be

stainless steel flat washers, Harger WxS series, or approved equivalent. Lock washers

shall be stainless steel lock washers, LWxS series, or approved equivalent. Nuts shall

be stainless steel nuts, NxxxS series, or approved equivalent. All mechanical

connections shall be coated with an anti-oxidant compound. (See NFPA 70, Article 250-

70).

2.6.3.5 Conductor Types

All ground conductors for below ground installations shall be tinned solid copper wire or

solid copper strap, where indicated. All ground conductors for above ground

installations within shelters shall be tinned solid copper wire, or stranded green jacketed

copper wire, solid copper strap, or black insulated welding cable where indicated.

Page 32: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 31 of 56

2.6.3.6 Conductor Sizes and Connections

A. Below Ground:

1. #2 AWG minimum tinned solid copper wire.

2. All below ground connections shall be exothermic bonds (CADWELDTM or

approved equivalent).

3. The Vendor shall not backfill the openings where the underground exothermic

bonds are made until the FDOT has inspected and approved the grounding

system and all associated connections.

B. Above Ground:

1. Conductors: All above ground connections shall be compression type, including

all bonds, between ground conductors and the interior shelter ground halo. Split

bolt or crimp connections shall not be used.

2. Grounding of equipment and specific metal objects: #6 AWG minimum solid

copper wire or #6 AWG green jacketed stranded wire, as appropriate. Four inch

by 1/8 inch oxygen-free solid copper strap where indicated. Connection of ground

conductors to equipment shall use lugs or clamps appropriate to the size and

type of wire and requirements of the equipment being grounded. Wires

connected to lugs or clamps shall be crimped for good electrical connection.

3. Fence grounding: #2 AWG tinned copper wire is required for all above ground

installations of ground wire. All fence gate ground conductors shall be 2/0 AWG

stranded welding cable with black insulation.

All non-conducting surface coatings shall be removed before each connection is made.

Application of an anti-oxidant compound is required ("NO-OX" or equivalent). Star

washers, or some other means appropriate to the fastener used, shall be installed to

ensure good continuity.

Ground conductors (wire and straps) shall be downward coursing and vertical, in the

direction of the ground field and shall be as short and straight as practical. The

minimum bending radius for generator system grounds shall be eight inches in

accordance with NFPA 780. Sharp bends and multiple bends in conductors shall be

avoided in all cases. Any deviation shall be submitted in writing and pre-approved in

writing by the FDOT Project Manager.

Page 33: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 32 of 56

2.6.4 Fence Grounding

This section does not apply at this site since the existing LPG tank is enclosed within the

compound fenced area. All generator fuel tank enclosed fencing shall be bonded to the

site grounding electrode system. A minimum #2 AWG bare tinned solid or stranded

tinned copper conductors shall be brought from the site building ground ring or earth

ground electrode system. Each lead shall be bonded to its respective corner fence post.

Grounding electrode system connections to the commercial-grade fencing and gates

shall be made using the mechanical bonds in accordance with Section 2.6.3. All welded

connections shall be coated with zinc-enriched paint for prevention of rusting. All gates

shall be bonded to the gate-supporting fence post with #2 AWG minimum stranded

copper wire using exothermic bonding.

The new fencing and posts for the fuel tank shall be grounded to the site grounding

electrode system using with a #2 AWG tinned solid copper wire. The fence perimeter

ground wire shall be buried a minimum of two feet below finished grade. Ground rods

shall be installed in accordance with the drawings in the appendix. The gate and

gatepost shall be bonded together with a 2/0 AWG flexible ground wire or strap. All

connections shall be bonded in accordance with Section 2.6.3.

Metallic fencing surrounding the generator installation shall be bonded to the external

site grounding electrode system using #2 AWG minimum bare tinned copper conductor.

2.7 Remote Alarm Monitoring

2.7.1 General

The Vendor shall install an annunciator and use the existing fuel sensor to monitor the

generator and fuel tank remotely with the FDOTs Network Management System (NMS).

The annunciator and fuel sensor will be configured to have specified alarms alert the

status of the equipment to the FDOT. The FDOT will be responsible for cross connecting

the alarms to the appropriate remote alarm terminal unit.

2.7.2 Annunciator

A 20-light LED type remote alarm annunciator panel Model LonWorks System

Annunciator panel (or approved equivalent) with horn shall be provided for local site and

remote annunciation/notification. LED lamps shall be replaceable, and indicating lamp

color shall be capable of changes needed for specific application requirements. A DIM

(Digital In/Out Module) within the automatic transfer switch (ATS) provides the remote

monitoring contact point for the generator. The DIM provides eight output and four input

Page 34: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 33 of 56

dry contacts for remote monitoring. The DIM alarms will be wired to a 66 Type Punch

Block.

The Vendor shall configure the first seven (7) DIM output Form-C dry contacts, with their

annunciator LED color designation as specified below:

Not in Auto (Red)

Generator Running (Green)

Low Oil Pressure (Red)

High Temperature (Red)

Low Coolant Level (Red)

Overcrank (Red) (failure to start)

Overspeed (Red)

Refer to the Appendix B for location of (66 block) terminal(s), diagrams and instructions

for interfacing to the annunciator panel on the DIM.

Alarm silence and lamp test switches shall also be provided on the annunciator panel.

The alarm-condition horn shall be switchable for all annunciation points.

The Vendor shall install a cable between the DIM residing within the ATS and the

annunciator panel for communications. The required cable is a Level IV twisted pair

stranded wire for communications between the DIM and the annunciator. The

communications cable pair #22 AWG will run in 1/2 inch EMT (Electrical Metallic Tubing)

between the annunciator and the DIM module. In addition, a pair of #20 AWG wires will

be required to power the annunciator from the gen-set batteries. The wires will be

installed in 1/2 inch EMT within the shelter and 1/2 inch stainless steel RMC (Rigid Metal

Conduit) running outside the shelter to the gen-set battery source.

The Vendor shall install SPDs between the remote alarm panel and the Vendor-provided

punch block within the MDF (Main Distribution Frame) unless otherwise specified in the

site specific appendix. All alarms shall be set to ‘Normally Closed’, unless otherwise

specified in the site specific appendices. The SPD shall be Atlantic Scientific Zone

Barrier Series, Model 91265, or approved equivalent.

The SPDs for the cables shall meet the following specifications:

Table 2.7.2: Atlantic Scientific Zone Barrier Series Model 91625 specifications

Page 35: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 34 of 56

Connector Type: Screw or push terminal

Frequency Response: Up to 4 kHz

Maximum Surge Current

(8x20us):

>=500 A per Line

Maximum Continuous

Operating Voltage:

>=60 V

Let-Through Voltage (500A

8x20us) (Pins 1

through 4)

<= 90 V

For SPD product approval, the Vendor shall submit a written request to the FDOT

project manager with an attached data sheet of the proposed substitution.

2.7.3 Fuel Sensor

This section does not apply to the installation. The fuel level sensor exist at this site.

The sensing device shall be Squibb Taylor, Inc. Stationary Tank Monitor, or approved

equivalent. A fuel level sensing device shall be installed on the main fuel tank. The

sensing device shall provide an analog voltage alarm monitoring point. The sensing

device shall be adjusted to activate a low fuel level alarm when the tank contains one

eighth (1/8) of the full volume. The sensing device shall also provide a visual indication

(bar graph, meter reading, other, etc.) depicting the fuel level and shall provide an

analog output that provides a voltage level proportional to the fuel level. An SPD device

shall be installed on the fuel sensing probe cable as it enters/exits the equipment

building. The SPD shall be Advanced Protection Technologies, Model D60 401 005 S,

or approved equivalent. The SPD device shall meet the following specifications:

Table 2.7.3: Atlantic Scientific Zone Barrier Series Model 91266 specifications

Connector Type: Screw or push terminal

Frequency Response: Up to 600 kilohertz (kHz)

I (Nominal) (8x20us): >=10 kA

Maximum Continuous Operating Voltage: >=7 VDC

Let-Through Voltage (500A 8x20us)

(Pins 1 through 4)

<12 VDC

For SPD product approval, the Vendor shall submit a written request to the FDOT

Project Manager, to substitute a different SPD, with an attached data sheet.

Page 36: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 35 of 56

All storage and day tanks shall comply with NFPA 30. Mechanical permits shall be

obtained and all fuel lines shall be tested by the Vendor and witnessed by the FDOT

prior to being put into service.

The Vendor shall fill the fuel tank prior to the completion of the project to no less than 80

percent of rated volume. For details, see NPGA #412-94 NATIONAL PROPANE GAS

ASSOCIATION.

Page 37: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 36 of 56

2. PRE-CONSTRUCTION SUBMITTAL REQUIREMENTS

3.1 Design Documentation Submittal

These submittals are in addition to any documentation submittal that may be required by

the local building official.

CONSTRUCTION SHALL NOT BEGIN UNTIL THE DESIGN SUBMITTALS ARE

APPROVED BY THE FDOT PROJECT MANAGER.

The Vendor shall supply sufficient information regarding the proposed equipment to

allow the FDOT to fully determine compliance with the specifications set forth in this

document. The Vendor shall furnish the following minimum requirements:

A. Specification sheets, manufacturer warranty information, and any other information

that would assist the FDOT in the equipment’s evaluation

B. Foundation designs for LPG tank and emergency generator set signed and sealed

by a Florida Registered Professional Engineer

3.2 Site Plan Requirements

The Vendor shall submit site plans for the sites to be used for permitting. The site plans

shall include, but not be limited to, staging areas and the location and installation

requirements of the generator, fuel tank, ATS, SPD, grounding, cabling, conduits,

fencing, and fuel lines.

CONSTRUCTION SHALL NOT BEGIN UNTIL SITE PLAN SUBMITTALS HAVE BEEN

APPROVED BY THE FDOT PROJECT MANAGER.

3.3 Maintenance of Traffic

Not applicable to this project. As the communications sites may be located along the

Interstate Highway or other major highway Systems, it may be necessary for the Vendor

to initiate maintenance of traffic plan to allow work and delivery vehicles to safely exit

and re-enter the highways or interstates. In the event that the FDOT determines the

maintenance of traffic plan is required, the Vendor shall develop and submit a plan for

each associated site to the FDOT for approval. The Vendor is required to implement the

approved plan and adhere to it during construction.

Page 38: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 37 of 56

3.4 Engine Generator Submittals

A. Shop Drawings:

1. Sufficient information, clearly presented, shall be included to determine

compliance with drawings and specifications.

2. Data shall be submitted in the following form:

a. Technical data sheets (TDS): These include published performance, rating

and derating curves, published ratings, catalog cuts, pictures, manufacturer's

specifications, material composition, and gauge thickness.

b. Description of operation (DO): Manufacturer's literatures and, if suitable,

diagrams.

c. Calculations (CALC): Detailed engineering calculations with all equations,

graphs, assumptions, and approximations shown, and data sources

referenced.

d. Certification (CERT): Written confirmation as to the document's accuracy,

and genuineness.

e. Shop Drawings (SD): Scaled drawings showing plan views, side views,

elevations and cross sections.

f. Diagrams (DGM): These include control system diagrams, elementary

diagrams, control sequence diagrams or table, wiring diagrams,

interconnections diagrams (between local control cubicles, remote

annunciator panels, remote derangement panels, remote monitoring panels,

remote exercising panel and underground fuel storage tank), wireless

connection diagrams, illustrative diagrams, flow diagrams, and other like

items.

3. Prior to fabrication, submit for approval the following data for the engine-

generator set, transfer device and control and supervisory equipment that are

applicable:

a. Engine generator set: TDS, SD including sub transient reactance and short-

circuit current capacity.

b. engine jacket water heaters: TDS

Page 39: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 38 of 56

c. muffler assembly: TDS, SD

d. motor-operated damper assembly: TDS

e. day tank and pumps or integral sub-base fuel tank: TDS, CALC

f. batteries, racks and charger: TDS, CALC

g. Torsional Vibration: CERT

h. Control and Supervisory Equipment: TDS, DGM, DO, SD

i. performance:

(1) voltage regulating equipment: TDS

(2) frequency regulating equipment: TDS

(3) voltage and frequency dips and recovery times due to specified motor

loading: CALC

(4) anti-freeze derating: TDS

(5) ambient derating: TDS

j. remote radiator: TDS, SD

k. fuel oil system: DGM

l. cooling system: DGM

m. vibration isolators: TDS, CALC

n. Sound power level data for the packaged outdoor generator.

o. Vibration isolation system performance data from no-load to full-load.

B. Certifications:

1. Prior to fabrication of the engine-generator set, submit the following for approval

to the FDOT Project Manager:

a. A certification in writing that a Spark-Ignited Generator Set of the same model

and configuration, with the same bore, stroke, number of cylinders, and equal

or higher break mean effective pressure and RPM ratings as the proposed

Page 40: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 39 of 56

engine has been operating satisfactorily, with connected loads of not less

than 75 percent of the specified kW/kVA rating, for not less than 2,000 hours

without any failure of a crankshaft, camshaft, piston, valve, injector or

governor system.

b. A certification in writing that devices and circuits will be incorporated to

protect the voltage regulator and other components of the auxiliary electrical

power system during operation of the Spark-Ignited Generator Set at speeds

other than the rated RPM while performing maintenance. Include thorough

descriptions with submittal of any precautions, which will be necessary to

protect the voltage regulator and other components of the system during

operation of the Spark-Ignited Generator Set at speeds other than the rated

RPM.

2. Prior to installation of the engine-generator set at the job site, submit four copies

of the following to the FDOT Project Manager:

a. Certified test data, alternator temperature rise test and strip chart recordings,

and photographs showing test setup and equipment.

3.5 Automatic Transfer Switch Submittals

A. Shop Drawings:

1. Sufficient information, clearly presented, shall be included to determine

compliance with drawings and specifications.

2. Include electrical ratings (including withstand), dimensions, weights, mounting

details, conduit entry provisions front view, side view, equipment and device

arrangement, elementary and interconnection wiring diagrams, and accessories.

3. Complete nameplate data, including manufacturer's name and catalog number.

4. A copy of the markings that are to appear on the ATS and associated equipment

when installed.

B. Certifications:

1. Submit, simultaneously with the shop drawings, a certified test report from a

recognized independent testing laboratory that a representative sample has

passed UL 1008 Standard for Safety of Transfer Switch Equipment.

Page 41: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 40 of 56

2. Two weeks prior to final inspection, submit four copies of the following to the

FDOT Project Manager:

i. Certification that no design changes have been made to the switch or its

components since last certified by UL or as tested by an independent

laboratory.

ii. Certification by the manufacturer that the equipment conforms to the

requirements of the drawings and specifications.

iii. Certification by the Vendor that the equipment has been properly installed,

adjusted, and tested.

iv. A certified test report from an independent laboratory that a representative

sample has passed the ANSI (American National Standards Institute) surges

withstand test for transfer switches which incorporate solid-state components.

4. SITE WORK

4.1 General

The FDOT will provide site space for the equipment installations. The Vendor shall

install the equipment in the provided space and make all necessary electrical and

mechanical connections. Routing of wires and cables shall be neat and orderly.

Electrical connectors shall be the responsibility of the Vendor. General site preparation

and landscaping shall be the responsibility of the Vendor. All environmental protection

requirements shall be met. The Vendor must contact the local FDOT district contact

person and FDOT Project Manager for specific information regarding site. The Vendor

shall provide gravel ground covering in the fenced-in compound area unless otherwise

specified.

Installation shall meet or exceed the design requirements of this specification and

standards of good engineering practice.

4.2 Permits

The Vendor is responsible for obtaining any permits and meeting building code

requirements, including associated fees. It is the Vendor’s responsibility to contact

applicable building department officials for permit applications and submit them to the

FDOT for signature(s).

Page 42: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 41 of 56

The Vendor is required to obtain all permits which may be required, filling out required

applications, obtaining appropriate signature(s) from FDOT, and then submitting these

applications to the appropriate regulating agency.

CONTACT WITH LOCAL AGENCIES MUST BE PRE-APPROVED BY THE FDOT PROJECT MANAGER.

4.3 Existing Communications System

The local point of contact shall be notified a minimum of 48 hours in advance of any

scheduled interruptions during cutover. The Vendor shall install the equipment in such a

manner that it shall not cause any harmful disruption to the overall communications

system. In addition to the 48 hour advance notification for scheduled interruptions, the

Vendor shall notify the local point of contact at least two hours in advance with an

anticipated outage time if communication system disruption is necessary.

The Vendor is responsible for filing any necessary notifications of construction with the

Federal Aviation Administration if disruption, modification or replacement if the tower

lighting system is necessary.

4.4 Clearing of Land

Clearing of brush, trees, or any other obstructions, including the removal of asphalt or

concrete, is the responsibility of the Vendor. The Vendor shall coordinate with the FDOT

Project Manager as to the extent and schedule for such work to ensure that there is no

interference to concurrent operations at the site. Any tree stumps resulting from clearing

shall be grubbed. All environmental protection requirements shall be met.

ANY SITE CLEARING AND TREE TRIMMING MUST BE APPROVED IN WRITING

AND IN ADVANCE BY THE FDOT.

4.5 Weed Prevention Material

Weed prevention material shall be 6-mm (minimum) plastic sheet.

4.6 Compound Gravel

The gravel or crushed rock shall be obtained locally and shall not exceed three inches in

diameter, so that foot traffic is not difficult.

Page 43: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 42 of 56

4.7 Excavations

The Vendor shall field locate all buried grounding, conduits, structures and utilities in and

around the work area prior to commencing any excavations. THE USE OF HEAVY

EXCAVATING MACHINERY IS NOT PERMITTED INSIDE THE FENCED AREA.

All digging and excavating inside of the communications site compound shall be

performed in a manner consistent with best engineering practices. Prior to any

excavation, the Vendor shall contact Sunshine State One Call of Florida (phone: 811) for

the location of all existing underground utilities and facilities. The Vendor shall keep all

excavated/disturbed gravel, dirt, and weed prevention materials separated in order to

return the sites to their original state. Failure to do so will compromise the integrity of

each materials’ designed functionality, and shall be remedied by the Vendor at no

additional cost to the Department.

All disturbed asphalt inside the existing communications site compound shall be

replaced in its original condition by the Vendor at no additional cost to the Department.

4.8 Wall Penetrations

Not applicable to this project. All new wall penetrations shall be core drilled. All wall

penetrations shall be sealed using Sonneborn Primer #46-733 and Sonneborn Urethane

Sealant NP1, or pre-approved equivalent. In the event that filler is necessary, the

Vendor shall utilize Sonneborn Soft Backer-Rod, or pre-approved equivalent. Under no

circumstances shall the Vendor use a hammer drill for wall penetrations.

4.9 Compound Treatment and Fencing

Not applicable to this project. The Vendor shall furnish and install metal fencing to

provide complete fuel tank security. The fence shall be Type B (chain-link) as specified

in Section 550 of the FDOT's Standard Specifications for Road and Bridge Construction.

These sections are delineated in the referenced FDOT's specification and Index Number

802 of the FDOT's Roadway and Traffic Design Standards.

The basic fence height shall be a minimum of six feet, and shall be topped with barbed

wire in accordance Index Number 802 of the FDOT's Roadway and Traffic Design

Standard. IN ADDITION, THE FENCE FABRIC SHALL BE FASTENED TO THE TOP

RAIL.

The fence shall include a gate made of the same material as the fence. The gate shall

have a minimum width of five feet and include a gate closing arrangement that is

Page 44: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 43 of 56

anchored to the ground with concrete (e.g. with a female pipe receptacle anchored in

concrete). A hardened, four-digit combination gate lock (Medeco or approved

equivalent) shall be provided by the Vendor, and the combination set to FDOT

specifications.

The fence shall be installed around the fuel tank enclosure with a minimum separation of

three feet from the fuel tank edge to the fence along each side. Sufficient space shall be

left to permit routine inspection and maintenance. The Vendor shall furnish and install

weed prevention material covering the newly fenced area.

4.10 Sanitary Provisions

The Vendor shall provide and maintain portable toilet facilities onsite for the use of

his/her employees. The Vendor shall keep these facilities in a neat and sanitary

condition and shall comply with local regulations pertaining to their use as articulated by

the (local) County Health Department where the facility is placed, or the State

Department of Health and Rehabilitative Services. No nuisance conditions shall be

permitted. The Vendor shall remove these facilities in a safe and sanitary manner when

the work is completed, and restore its particular location to original condition. The

Vendor shall report to the Project Manager when this has been accomplished.

4.11 Debris Removal

At the completion of the installations specified herein, the Vendor shall remove all debris

that is a result of such installations, backfill and compact all excavations after inspection

and approval is performed by the end user and return the grounds to their original

condition. All work shall comply with applicable environmental protection requirements.

4.12 Excess Garbage and Clutter

The trash generated from the installation, including lunch bags and drinks, must be

stored in a neat manner until disposed of properly. The Vendor shall be responsible for

removing and legally disposing of trash in a timely manner. Trash shall not be allowed

to accumulate at or near any construction site.

5. POST INSTALLATION SUBMITTAL REQUIREMENTS

5.1 As-Built Survey and Drawings

The Vendor shall submit three sets of detailed as-built surveys and drawings depicting

the location of the components of the communications site with respect to local features

Page 45: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 44 of 56

and benchmarks. As-built drawings depicting any necessary field changes to the

communications site shall also be provided by the Vendor. As- built drawings shall

illustrate all details of the installation of any equipment. As-built documentation shall be

provided by the Vendor in both ‘soft’ form (Microsoft Visio), as well as hard copy.

5.2 Engine Generator Documentation

A. Documentation:

1. Submit, simultaneously with the shop drawings, companion copies of complete

maintenance and operating manuals of the engine generator set and auxiliaries

including technical data sheets, wiring diagrams, and information, such as

telephone numbers, fax numbers, and URLs for ordering replacement parts.

2. Two weeks prior to the final inspection, submit four copies of the updated

maintenance and operating manual to the FDOT Project Manager.

3. Include complete “As installed” diagrams, which indicate all items of equipment

and their interconnecting wiring.

4. Include complete diagrams of the internal wiring for each piece of equipment,

including “As installed” revisions of the diagrams.

5. The wiring diagrams shall identify the terminals to facilitate installation,

maintenance, operation and testing.

6. Also include a complete list of spare parts and special tools recommended for

two years of normal operation of the system.

B. Two weeks prior to the final inspection, submit four copies of the following to the

FDOT Project Manager:

1. A certified test report by the manufacturer of the engine generator set that the

auxiliary electrical power system conforms to the requirements and drawings of

the specifications.

2. A certified report of field tests from the Vendor that the engine generator set and

major auxiliaries have been properly installed, adjusted, and tested.

5.3 Automatic Transfer Switch Documentation

A. Documentation:

Page 46: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 45 of 56

1. Submit, simultaneously with the shop drawings, companion copies of complete

maintenance and operating manuals including technical data sheets, wiring

diagrams and information, such as telephone/fax numbers and URLs for ordering

replacement parts.

2. Two (2) weeks prior to final inspection, submit four (4) copies of a final updated

maintenance and operating manual to the FDOT Project Manager.

3. Include complete ‘As installed’ diagrams, which indicate all items of equipment

and their interconnecting wiring.

4. Include complete diagrams of the internal wiring for each piece of equipment,

including ‘As installed’ revisions of the diagrams.

5. The wiring diagrams shall identify the terminals to facilitate installation,

maintenance, operation and testing.

B. Certifications:

1. Two (2) weeks prior to final inspection, submit four copies of the following to the

FDOT Project Manager:

a. Certification that no design changes have been made to the switch or its

components since last certified by UL or as tested by an independent

laboratory.

b. Certification by the Vendor that the equipment conforms to the requirements

of the drawings and specifications.

c. Certification by the Vendor that the equipment has been properly installed,

adjusted and tested.

d. A certified test report from an independent laboratory that a representative

sample has passed the ANSI ‘surges withstand capability’ test for transfer

switches which incorporate solid-state components.

Page 47: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 46 of 56

6. INSPECTIONS AND TESTING

6.1 General

All inspections shall be performed by the Vendor and witnessed by the FDOT Project

Manager or a designated representative.

The Vendor shall notify the FDOT Project Manager and the FDOT's local personnel at

least 10 days prior to completion of the installation. The Vendor, in conjunction with the

FDOT's Project Manager or designated personnel, shall verify that all equipment is

correctly installed and functional.

For ground system inspections, the Vendor shall notify the FDOT Project Manager and

the FDOT’s local personnel at least two days prior to completion of the installation.

Below grade ground installations and ground connections shall not be backfilled until

inspected and approved by the FDOT.

All test results shall be recorded in a standardized format compatible with these

technical requirements. The format to be used for the recording of the test report data

shall be submitted to the FDOT for approval prior to testing. All recorded test data shall

be dated, witnessed, and signed by at least one representative of the FDOT and the

Vendor.

The Vendor shall remedy all deficiencies at no cost to the FDOT.

6.2 Emergency Generator Testing

The emergency generator shall be inspected for proper electrical and

mechanical/physical installation. The Vendor shall demonstrate that the generator is

functioning properly by running the generator for a minimum of one hour under full load

(100% rating) conditions. The Vendor shall demonstrate that the generator operates at

the proper voltage, current, and frequency output. The Vendor shall demonstrate that

the generator alarms operate properly. If the test fails, the Vendor shall correct the

problem and repeat the test. The Vendor shall demonstrate that the fuel level is full prior

to the acceptance of the site.

The Vendor shall test the generator at 100% of nameplate kVA to validate the

generator’s capacity. The Vendor shall provide the necessary load bank and equipment

to perform the load test on site.

Page 48: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 47 of 56

The Vendor shall provide the services of a factory-authorized, factory-trained

representative of the LPG engine-generator set manufacturer to inspect field-assembled

components, equipment installation and supervise the field tests. If a complete auxiliary

electrical power system is installed, prior to the final inspection, all components of the

system shall be tested in the presence of the FDOT Project Manager for proper

operation of the individual components and the complete system and to eliminate

electrical and mechanical defects. The Vendor shall furnish fuel, lubricating oil,

anti-freeze liquid, water treatment/rust inhibitor and a resistive load bank for testing of

the LPG engine-generator set.

The engine-generator set will be tested for four (4) hours of continuous operation as

follows:

100 percent of its specified kilowatt rating for the first four (4) hours of operation

If the LPG engine shuts down, or the full kilowatt rating of the load bank is not

achieved during the first four (4) hours of operation, the test is null and void. The

test(s) shall be repeated until satisfactory results are obtained.

The Vendor or Vendor’s representative shall bear the full cost of repeating these

tests if necessary to obtain satisfactory results; including the cost of additional

material and man-hours.

The following test data will be recorded at 30 minute intervals:

Time of day.

Reading of running time indicator.

KW

Voltage on each phase

Amperes on each phase

Engine RPM

Frequency

Engine water temperature

Fuel pressure

Oil pressure

Outdoor temperature

Average ambient temperature in the vicinity of the LPG engine.

Average ambient temperature in the vicinity of the starting batteries

The Vendor shall demonstrate that the engine-generator set will reach proper voltage

and frequency, and will accept 100 percent block load within 10 seconds of a cold start

after the closing of a single contact.

Page 49: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 48 of 56

The Vendor shall furnish a resistance type load for the testing of the generator. When

approved in writing by the FDOT Project Manager prior to the testing, the Vendor may

use connected loads in the building including resistive, inductive and non-linear loads

(i.e. AC/DC rectification) as part of the test load provided by the Vendor. Test loads shall

always include adequate resistance to insure stability of the loads and equipment during

all of the testing operations. The test load kilowatt rating shall not be less than 100

percent of the specified kilowatt rating.

The Vendor shall demonstrate that the batteries and cranking motor are capable of five

(5) starting attempts. Each attempt shall include a 10-second cranking interval, with a

10-second interval between starting attempts. During these tests and intervals between,

the battery charger shall be turned off.

The Vendor shall test the local and remote panels. The Vendor shall simulate engine

failures while checking for proper operation of each indicating lamp, alarm device and

reset button. It is recommended that one inspector be located in the generator room and

another at the site of remote panels. By means of telephone or walkie-talkies, the

inspectors should be assured of proper operation and coordination of these panels.

At the completion of the field tests, the Vendor shall fill the storage tank with fuel of

grade and quality as recommended by the manufacturer of the engine. When any

defects are detected during the tests, the Vendor shall correct deficiencies and repeat all

or part of the four hour continuous test as requested by the FDOT Project Manager, and

do so at no additional cost to the FDOT. The Vendor shall provide test and inspection

results in writing to the FDOT Project Manager within a two week work period.

6.3 Automatic Transfer Switch Inspection

The ATS shall be inspected for proper electrical and mechanical installation, and

properly secured to the shelter wall. The ATS must meet the testing requirements of UL

1008 ‘Transfer Switch Equipment’. After the complete system has been installed, and

before it’s energized, the Vendor shall check all components of the system, including

insulation dielectric strength, phase to phase and phase to ground voltages, and

complete electrical circuitry safety features according to the manufacturer’s

documentation. The Vendor shall demonstrate the proper operation of the ATS’s

functions and exercise time. After energizing circuits, the Vendor shall test the

interlocking sequence and operation of the complete system, including time delays of

transfer from normal source to emergency power and back to normal source, pick-up

and voltage drop, and function of the bypass/isolation switch. These tests will be

conducted in the presence of the FDOT Project Manager prior to the final inspection. If

Page 50: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 49 of 56

any test fails, the Vendor shall correct the problem and repeat the test. Alarms and

controls shall be tested for proper operation. The Vendor shall correct any and all

defects detected and repeat the test of that feature or function as requested by the

FDOT Project Manager, at no additional cost to the FDOT.

6.4 Electrical Inspection

The generator and all of its associated system equipment shall be verified for proper

operation and for proper connections to the electrical panel. Circuits shall have properly

sized breakers and be clearly labeled.

The Vendor shall remedy all deficiencies, at no additional cost to the FDOT.

6.5 Grounding Inspection

The grounding system shall be inspected for proper connection types, tightness,

workmanship, conformance with the approved design, NEC 250 and all local code

requirements. Any compression or exothermic bonds that are deemed unsatisfactory

shall be repaired with new bonds at no additional cost to FDOT. The additional new

ground rod installation will be tested and witnessed as described elsewhere in this

section.

6.5.1 Earth Ground Electrode System Resistance Testing

Not applicable to this project. A four ohm or less earth ground resistance reading is the

target earth ground resistance for FDOT communications sites. The Vendor shall

provide before and after earth ground resistance testing of the site grounding system.

Before bonding the generator to the existing communications site grounding electrode

system, earth ground testing shall be required while isolated/disconnected from the

electric utility grounding electrode.

6.5.2 Isolating the Utility Grounded Service from the Communications Site Grounded

System

Not applicable to this site. The neutral (utility earth grounded system) must be

temporarily disconnected in order to measure the earth ground electrode resistance. The

site power is to be shut off to conduct the test. This can be done by shutting off all load

circuit breakers to all communications site equipment. These circuit breakers shall be

located at the communications site load distribution panel within the shelter. Once all

loads have been removed, the main disconnect switch shall be opened to ensure that

the test is conducted in a de-energized state. Once the main disconnect is opened, the

Page 51: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 50 of 56

Vendor will disconnect the neutral conductor at the AC main disconnect within the

communications shelter. The line side neutral conductor coming from the electric utility

is to be disconnected, taped and safely isolated during the test.

The Vendor shall check for current on the grounding electrode conductor before

disconnecting. Never disconnect the ground of a live circuit. Disconnecting the ground

of a live circuit could cause death or severe injury. The disconnection must be done by

a licensed and qualified electrician and according to OSHA requirements.

6.5.3 Three Point/Fall of Potential Earth Ground Testing Procedure

Not applicable to this site. The Three-Point/Fall-of-Potential test is the most widely

accepted and recommended test method. This procedure is documented in ANSI/IEEE

STD 81. This standard should be consulted for more details.

Required test equipment and supplies:

Three-Point/Fall-of-Potential Ground Resistance Tester (with supplied test leads, test clips, and probes)

Small sledgehammer

Tape measure

Safety glasses

Gloves

The Vendor shall perform a three point earth ground test for measuring the resistance of

the site’s earth ground electrode system to validate the earth ground resistance. This

test is also known as the 62 percent Fall of Potential Method. The earth ground test

method evaluates the resistance of the site ground resistance by circulating a test

current through the soil, test leads (ground stakes), grounding electrode under test and

test instrument. This method uses two ground stakes driven into the surrounding soil at

the site a specified distance from the electrode under test. At one ground stake,

measure the voltage drop across the soil between the electrode under test and the

closest ground stake driven 62 percent of the distance to the second driven ground

stake. The grounding conductor leads of the tester are connected to the electrode under

test (frame of the generator) and the two-ground stakes. Once these connections have

been completed, the earth ground resistance measurement is made by pressing a

switch on the test instrument. This causes a current to circulate through the ground

loop created between the test instrument, furthest ground stake and electrode under

test. The instrument will then provide an earth-ground resistance based on the voltage

drop read through the soil between the driven stakes.

Page 52: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 51 of 56

Figure 6.5.3-1 provides the recommended distances for spacing the Y and Z ground

stakes to conduct the 62 percent Fall of Potential Test. The ground stakes are to be

spaced based on the 10 foot depth of the electrode under test.

For a multi-bonded/multi-grounding electrode system, the distance of the reference Z

probe shall be between 5 and 10 times the diagonal distance of the grounding electrode

system (i.e. the diagonal distance of the fenced area). For three-point testing distance

measurements, the planar center of a multi-bonded/multi-grounded electrode system is

the extreme edge of the system in the direction of where the test probes are inserted. In

Figure 6.5.3-1, one of three rods connected to the tower ground ring has been selected

as the electrode under test, since this ground rod is the outermost rod of the earth

grounding electrode system for the illustrated communications site. Since the diagonal

distance for the communications site is 47 feet, the Z probe ground stake is calculated at

five times the diagonal site distance or 235 feet. This is the point at which the Z probe

stake is spaced away from the X probe (electrode under test). The Y probe is then

staked 62 percent the Z probe distance or 146 feet from the X probe.

When conducting the earth ground fall of potential test, the Vendor shall ensure that the

ground stakes are run directly away from the grounding electrode system being tested.

In Figure 6.5.3-1, the X probe to be tested has been selected as one of the ground rods

connected to the tower ground ring. The ground stakes shall not run in parallel to any

overhead or underground power lines whose magnetic field can adversely affect the test

instrument readings. If power lines are present, try placing the test ground stakes at 90

degree angles to power lines in the surrounding test area. The earth ground resistance

testing shall be performed by a calibrated tester. The earth ground tester calibration

date shall be current (within 12 months of the test date).

Sample listing of 3-point Grounding Electrode Testers:

www.extechproducts.com Extech Tester

www.fluke.com Fluke Saturn Geo X

www.duncaninstr.com Duncan Instruments Model 2124

www.aemc.com AEMC Model 3620 or 3640

www.amprobe.com Ground Resistance Tester

The above list is a representative sample of ground resistance test equipment

manufacturers and is by no means exhaustive or complete.

Page 53: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 52 of 56

Figure 6.5.3-1: Ground Test Probe Staking Distances

6.5.4 Site Grounding Electrode System Continuity Testing

Not applicable to this site. Upon completion of the three-point earth ground testing,

continuity of all site ground bonding shall be verified to ensure there is no differential

resistance between any two metallic points within the site. A well bonded electrical

grounding system ensures that there is close to zero ohms of resistance between any

two points. The three-point tester can be configured to read continuity (resistance

between two points) by connecting the X and Y terminal on the instrument. Figure 6.5.3-

1 shows a three point earth ground resistance tester configured in both three-point and

two-point configuration.

Configure the instrument for two-point continuity testing in accordance with the

equipment’s operating instructions and measure various points throughout the

communications site to ensure that all grounded systems are at the same earth ground

potential. The X-Y jumpered terminal leads are then connected to one of the ground

points to be tested for continuity. The Z terminal lead is connected to the second ground

point to be tested. For a well bonded electrical grounding system, the resistance value

should be measured as close to zero ohms as practical. Readings of 0.1 ohms or

greater should be investigated.

SHELTERTOWER

PERIMETER COMPOUND FENCE

# 2 TINNED

SOLID COPPER

GROUNDING

CONDUCTOR

Site Dimensions

Width 25'-0"

Length 40'-0"

Diagonal Site 47'-0"

Location of Y and Z Probes

5 times Diagonal (Z Probe) 235'-0"

62% of Z Probe Distance 146'-0"

5 times Site Diagonal (235'-0")

62% (146'-0")

X Y Z

Page 54: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 53 of 56

Continuity at communications sites should be verified between all of the following using

a three-point earth ground tester, configured for a 2-point test:

Each fence corner point to the communications tower ground ring

Communications tower ground ring to the shelter site ground ring

Communications tower ground ring to ice bridge cable support

Ice bridge cable support to shelter ground ring

All metal frames at site to shelter ground and communications tower ground ring

Any metal tanks or other metal structures to shelter and tower ground ring

All measurements must be witnessed by the FDOT Project Manager or his/her

appointed designee. Once the communications site’s earth ground and continuity

measurements have been performed, the Vendor shall proceed to install the engine

generator earth ground electrode system and bond it to the site’s existing grounding

electrode system.

After the generator earth ground electrode system is bonded to the communications

site’s earth grounding electrode system, the Vendor shall make an earth ground

measurement to determine the new earth ground resistance for the site with the engine

generator driven earth grounds in parallel with the communications site’s earth ground

electrode system. This earth ground resistance measurement shall be taken with the

utility neutral temporarily disconnected at the main disconnect panel to isolate the site's

readings from any potential influence from the utility earth ground electrode system.

If the new earth ground resistance readings for the site are found to be higher than four

ohms with all existing and new electrodes connected, the Vendor shall review the

readings with the FDOT Project Manager or his/her designee to identify what additional

ground rod augmentation is necessary to improve the ground resistance readings to four

ohms or less.

6.6 Site Inspection

Upon inspection, the site shall be free of debris and any excavations shall be backfilled

and restored. Any unique site requirements will be delineated in the site specific

Appendix.

6.7 Performance Testing

Following the completion of all acceptance inspections and testing, the installed

generator systems shall be subjected to a minimum 20-day performance period.

Page 55: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 54 of 56

A 20 consecutive calendar day period of successful operation shall constitute a

successful performance period.

For the purpose of the successful performance period, failure of operation is defined as

the failure of a major component of the generator system (emergency generator, ATS,

etc.). Degradation of performance is not a failure if function and proper operation is

maintained.

The performance verification shall be accomplished and witnessed by the FDOT Project

Manager or designated personnel. Upon acceptance test criteria by the FDOT Project

Manager, the 20 day performance period shall begin. This requirement shall be

accomplished during a period of time no later than 45 consecutive calendar days after

equipment installation, inspection and testing.

The Vendor shall configure the generator to run for 30 minutes under load, every day of

the 20 day performance period.

If a successful performance period cannot be accomplished within 45 consecutive

calendar days after the equipment is installed, inspected and tested, the FDOT reserves

the right to deem the Vendor in default and enforce the provisions set forth in the

contract.

6.8 Substantial Completion

After system cutover, the 20 day performance test will begin. Upon successful

completion of the 20 day performance test, the FDOT will consider the project to have

reached substantial completion.

When all as-built documentation has been received and approved by the FDOT and all

punch-list items have been resolved, the FDOT will approve the installed emergency

generator power system(s). Final acceptance will not constitute any waiver of the

FDOT's rights to warranty and/or warranty maintenance provided by the equipment's

manufacturers.

6.9 Single Manufacturer

The generator set equipment, including engine, alternator, exciter, and voltage regulator,

shall be designed and manufactured by Cummins. The emergency generator power

systems described herein, including specific components, shall be factory built and

tested, and shipped by this single source manufacturer, so there is one source of supply

and responsibility for warranty claims, documentation, parts, and service.

Page 56: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 55 of 56

This manufacturer shall have local representation to provide factory-trained servicemen,

required stock of replacement parts, and technical assistance.

6.10 Training

The Vendor shall provide training by the manufacturer or certified manufacturer’s

representative for the facility’s operating personnel covering operation and maintenance

of the equipment provided. The training program shall be no less than four hours in

duration and the class size shall be limited to five persons. The training date shall be

coordinated with the FDOT Project Manager and held at the newly installed emergency

generator system communications site.

6.11 Service and Support

The Vendor shall maintain service parts inventory for the generator, automatic transfer

switch, fuel tank, and SPDs at a central location which is accessible to the service

location 24 hours per day, 365 days per year over the warranty period.

The manufacturer shall maintain model and serial number records of each generator and

transfer switch provided for at least 20 years.

6.12 Warranty

The emergency generator power system, automatic transfer switch, and associated

equipment shall be warranted by the manufacturer for a period of not less than five years

from the date of commissioning against defects in materials and workmanship. The

Vendor shall transfer the warranty and ownership to the FDOT before final payment is

made.

The surge protective devices shall be warranted by the manufacturer for a period of not

less than one year from the date of commissioning against defects in materials and

workmanship. The Vendor shall transfer the Manufacturer’s warranty for the fuel tank,

fuel sensors, and surge protective devices to the FDOT.

The Vendor warranty period shall be a period of at least 12 months from the date of final

systems acceptance. Claims under any of the warranties are valid if made within 30

days after termination of the warranty period. In addition, the following specific

requirements apply to the Vendor’s warranty:

All equipment furnished by the Vendor hereunder shall be new and of current

manufacture.

Page 57: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

Page 56 of 56

FDOT shall notify the Vendor within a reasonable time after the discovery of any failure

or defect occurring within the warranty period. All equipment, software, and services

furnished by the Vendor as part of this project shall conform to this contract and be

warranted to be free from defects in material and workmanship. In the event any such

defects in equipment, software, or services become evident within the warranty period,

the Vendor shall correct the defect by either (1) repairing any defective component of the

equipment; (2) furnishing and installing necessary replacement parts; (3) otherwise

correcting any reproducible and/or recurring software defects; or (4) redoing the faulty

services. The Vendor is responsible for all charges incurred in returning defective parts

to the Vendor’s, Vendor’s, or suppliers' plants, and in shipping repaired or replacement

parts to FDOT. The Vendor shall provide labor to perform warranty services at no

charge to FDOT during the warranty period.

The Vendor further warrants that during the warranty period the equipment and software

furnished under this contract shall operate under normal use and service as a complete

system, which shall perform in accordance with this contract.

Should the Vendor fail to remedy any failure or defect within 30 consecutive days after

receipt of notice thereof, or within time specified in the notice, FDOT shall have the right

to replace, repair, or otherwise remedy such failure or defect at the Vendor’s expense.

The Vendor shall obtain any warranties which Sub-Vendors or suppliers to the Vendor

give in the regular course of commercial practice, and shall apply the same to the benefit

of FDOT.

The Vendor shall be liable to FDOT for supply of information, materials, and labor

necessary for mandatory revisions determined by the manufacturer for the duration of

the warranty period, at no cost to FDOT.

The warranty shall be comprehensive. No deductibles shall be allowed for travel time,

service hours, replacement parts cost, etc.

Under this warranty, the Vendor shall remedy at its own expense any failure to conform

to the general contract terms, system requirements, or any other document included by

reference into this contract. The Vendor also agrees to remedy at its own expense any

defect in materials or workmanship.

The "acceptance" of systems/equipment by FDOT shall not limit FDOT's warranty rights, as set forth above with respect to defects in materials or workmanship.

Page 58: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FLORIDA DEPARTMENT OF TRANSPORTATION

EMERGENCY GENERATOR AT BIG PINE KEY FDOT

APPENDIX A

EMERGENCY GENERATOR POWER SYSTEM

AT BIG PINE KEY FDOT

PLAN DRAWINGS

November 5, 2015

FILE:\\dotscoteoserver\Traffic_Ops_Data\Public\ITS\Telecommunications\Facilities\

Generators_BigPineKeyFDOT\BigPineKeyFDOT_Appendix_A_2015 11 05 REV 0.0.docx

Page 59: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

IT-1

SHEET NO.BIG PINE KEY

KEY SHEET

STATE OF FLORIDADEPARTMENT OF TRANSPORTATION

BIG PINE KEY

SITE NAME FINANCIAL PROJECT IDCOUNTY

MONROET:\Public\ITS\Telecommunications\Facilities\Generator_BigPineKey\BIG PINE KEY CONTRACT PLANS REV1_20151105.vsd

STATE OF FLORIDA

DEPARTMENT OF TRANSPORTATION

PENSACOLA

TALLAHASSEEJACKSONVILLE

TAMPA

NAPLESFT LAUDERDALE

MIAMI

KEY WEST

ORLANDO

LAKECITY

Contract plans

FINANCIAL PROJECT ID ____________________MONROE COUNTY

BIG PINE KEY (6-6361) GENERATOR REPLACEMENT

FDOT SHELTER SITE GENERATOR PLANS

NOTE: THE SCALE OF THESE PLANS MAY

HAVE CHANGED DUE TO REPRODUCTION.

GOVERNING STANDARDS AND SPECIFICATIONS:

FLORIDA DEPARTMENT OF TRANSPORTATION,

DESIGN STANDARDS DATED 2015,

AND STANDARD SPECIFICATIONS FOR ROAD AND

BRIDGE CONSTRUCTION DATED 2015,

AS AMENDED BY CONTRACT DOCUMENTS. FDOT PROJECT MANAGER: RANDY PIERCE

N

TOWER SITE ADDRESS:

450 KEY DEER BLVD.BIG PINE KEY, FL 33034 Monroe County

Site Number: 6-6361

GPS COORDINATES:

LATITUDE: 24-40-30 N (NAD 83)LONGITUDE: 81-21-39 W

LOCATION OF PROJECT

0 30 60

miles

0 500 FT. 1000 FT.

BIG PINE KEY GENERATOR

REPLACEMENT PROJECT

BIG PINE KEY TOWER SITE

FLORIDA DEPARTMENT OF TRANSPORTATION605 SUWANNEE ST. MS 90TALLAHASSEE, FL 32399-0450PH.(850)-410-5600FAX.(850)-410-5501

CONTRACT PLANS RECORDREV.DATE DESCRIPTION REV.DATE DESCRIPTION

INDEX OF PLANS

SHEET NO. SHEET DESCRIPTION

IT-1 KEY SHEET

IT-2 PROJECT NOTES

IT-3 SITE LAYOUT PLAN

IT-4 HAND RAIL REMOVAL PLAN RAIL

IT-5 HAND RAIL INSTALLATION PLAN RAIL

IT-6 ELECTRICAL RISER AND COMMUNICATIONS DIAGRAM

IT-7 GENERATOR REMOVAL PLAN

IT-8 GENERATOR INSTALLATION PLAN

IT-9 GENERATOR ROOM WALL INSTALLATION PLAN

IT-10 EXTERIOR SOUTH WALL INSTALLATION PLAN

IT-11 EQUIPMENT ROOM REMOVAL PLAN

IT-12 - IT-13 EQUIPMENT ROOM INSTALLATION PLAN

ENGINEER OF RECORD:

P.E. NO.:

TERRY A. POSEY, P.E.

36151

Page 60: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

T:\Public\ITS\Telecommunications\Facilities\Generator_BigPineKey\BIG PINE KEY CONTRACT PLANS REV1_20151105.vsd

IT-2

SHEET NO.BIG PINE KEY

PROJECT NOTES

STATE OF FLORIDADEPARTMENT OF TRANSPORTATION

BIG PINE KEY

SITE NAME FINANCIAL PROJECT IDCOUNTY

MONROE

CONTRACT PLANS RECORDREV.DATE DESCRIPTION REV.DATE DESCRIPTION

FLORIDA DEPARTMENT OF TRANSPORTATION605 SUWANNEE ST. MS 90TALLAHASSEE, FL 32399-0450PH.(850)-410-5600FAX.(850)-410-5501

GENERAL NOTES:

1. THE VENDOR SHALL BE RESPONSIBLE FOR VERIFYING ALL CONDITIONS AND MEASUREMENTS RELATING TO THE WORK IN THE FIELD

PRIOR TO PROCEEDING WITH INSTALLATION, REMOVAL, AND DISPOSAL ACTIVITIES. THE VENDOR SHALL COORDINATE ANY

MODIFICATIONS REQUIRED WITH FDOT.

2. THE VENDOR IS RESPONSIBLE FOR ALL EQUIPMENT, MATERIALS, AND SERVICES REQUIRED TO COMPLETE THIS PROJECT. THE VENDOR

IS RESPONSIBLE FOR VERIFYING THE COMPLETENESS OF MATERIALS REQUIRED AND SUITABILITY OF DEVICES TO MEET THESE PLANS.

THE VENDOR SHALL PROVIDE AND INSTALL, WITHOUT CLAIM, ANY ADDITIONAL EQUIPMENT AND SERVICES REQUIRED FOR OPERATION

PER THESE PLANS.

3. THE VENDOR SHALL BE RESPONSIBLE FOR DETERMINING LOCAL FACILITIES FOR DELIVERING, STORING, AND LEGALLY DISPOSING OF

POST-INSTALLATION MATERIALS.

4. THE VENDOR SHALL PROTECT AND PRESERVE ALL EXISTING UTILITIES, EXCLUDING THOSE REQUIRING UPGRADES OR RELOCATION IN

THESE PLANS, LOCATED WITHIN THE INSTALLATION LIMITS OF THE PROJECT.

5. THE VENDOR IS RESPONSIBLE FOR OBTAINING ANY PERMITS (DEP, SOUTH FLORIDA WATER MANAGEMENT DISTRICT, ETC.) AND

MEETING BUILDING OFFICIAL REQUIREMENTS, INCLUDING ASSOCIATED FEES. THE VENDOR IS RESPONSIBLE FOR CONTACTING

APPLICABLE BUILDING OFFICIALS FOR PERMIT APPLICATIONS AND SUBMITTING TO THE FDOT FOR SIGNATURE.

6. THE VENDOR SHALL SUBMIT AN INSTALLATION SCHEDULE TO FDOT FOR REVIEW AND APPROVAL.

7. THE VENDOR MUST COORDINATE ALL SITE WORK WITH FDOT. THE CONTACT PERSON IS RANDY PIERCE, 850-410-5608.

8. THE VENDOR SHALL COORDINATE EACH ELEMENT ON THE SCHEDULE WITH OTHER INSTALLATION ACTIVITIES AND SHOW EACH

ACTIVITY IN PROPER SEQUENCE.

9. THE FDOT SHALL BE NOTIFIED 72 HOURS IN ADVANCE OF ANY SCHEDULED INTERRUPTIONS DURING CUT-OVER FOR SAFETY

PRECAUTIONS. IN ADDITION TO THE 72 HOUR ADVANCE NOTIFICATION FOR SCHEDULED INTERRUPTIONS, THE VENDOR SHALL NOTIFY

FDOT AT LEAST TWO HOURS IN ADVANCE OF ALL NECESSARY COMMUNICATIONS DISRUPTIONS AND SUCH PLANNED OUTAGE WITH THE

ANTICIPATED OUTAGE TIME.

10. THE VENDOR SHALL RESTRICT PERSONNEL, THE USE OF EQUIPMENT, AND THE STORAGE OF MATERIALS TO AREAS WITHIN THE LIMITS

OF INSTALLATION. ANY OFF-SITE STORAGE AREA IS THE RESPONSIBILITY OF THE VENDOR.

11. THE VENDOR SHALL PROVIDE SECURITY FOR HIS/HER EQUIPMENT AND SHALL CONDUCT HIS/HER OPERATIONS SO AS TO AVOID

INTERFERENCE WITH FDOT'S NORMAL OPERATIONS.

12. ALL EXISTING DRIVEWAYS, EASEMENTS, AND GROUNDS SHALL BE PROTECTED OR RESTORED TO INITIAL CONDITION IF DAMAGED OR

DISTURBED AS A RESULT OF INSTALLATION.

13. THE VENDOR SHALL PROVIDE AND MAINTAIN IN A NEAT AND SANITARY CONDITION SUCH ACCOMMODATIONS FOR THE USE OF HIS/HER

EMPLOYEES AS MAY BE NECESSARY TO COMPLY WITH REGULATIONS OF THE COUNTY OR THE DEPARTMENT OF HEALTH AND

REHABILITATIVE SERVICES. NO NUISANCE WILL BE PERMITTED.

14. THE VENDOR SHALL BE RESPONSIBLE FOR REMOVING AND LEGALLY DISPOSING OF TRASH IN A TIMELY MANNER.

15. ALL EQUIPMENT AND SERVICES FURNISHED BY THE VENDOR AS PART OF THIS PROJECT SHALL BE WARRANTED TO BE FREE FROM

DEFECTS IN MATERIAL AND WORKMANSHIP. IN THE EVENT ANY SUCH DEFECTS IN EQUIPMENT OR SERVICES BECOME EVIDENT WITHIN

THE WARRANTY PERIOD, THE VENDOR SHALL CORRECT THE DEFECT BY REPAIRING OR REPLACING THE DEFECTIVE COMPONENT OR

EQUIPMENT AT NO COST TO FDOT DURING THE WARRANTY PERIOD. THE WARRANTY PERIOD SHALL BE A MINIMUM OF 12 MONTHS

FROM DATE OF FINAL ACCEPTANCE. CLAIMS UNDER ANY OF THE WARRANTIES HEREIN ARE VALID IF MADE WITHIN 30 DAYS AFTER

TERMINATION OF THE WARRANTY PERIOD.

16. THE VENDOR SHALL COLLECT PRODUCT DATA INTO A SINGLE SUBMITTAL FOR EACH ELEMENT OF INSTALLATION OR SYSTEM. PRODUCT

DATA SHALL INCLUDE PRINTED INFORMATION SUCH AS MANUFACTURER'S INSTALLATION INSTRUCTIONS AND PERFORMANCE

SPECIFICATIONS.

17. THE VENDOR SHALL SUBMIT (2) SETS OF AS-BUILT DRAWINGS DEPICTING THE LOCATION OF THE COMPONENTS OF THE

COMMUNICATIONS FACILITIES WITH RESPECT TO LOCAL FEATURES AND BENCHMARKS. AS-BUILT DRAWINGS DEPICTING ANY FIELD

CHANGES TO THE FACILITIES SHALL ALSO BE SUBMITTED. AS-BUILT DOCUMENTATION SHALL BE SUBMITTED IN ELECTRONIC FORMAT,

AS WELL AS PRINTED. ALL ITS FACILITY MANAGEMENT ATTRIBUTE FORMS SHALL BE COMPLETED IN ACCORDANCE WITH THE SCOPE OF

SERVICES.

18. THE VENDOR SHALL BE RESPONSIBLE FOR ENSURING THE SITE IS SECURED BY TEMPORARY FENCING AT THE END OF EACH DAY.

INSTALLATION NOTES:

1. THE VENDOR SHALL SUBMIT A DETAILED INSTALLATION PLAN FOR APPROVAL BY FDOT. THE PLAN SHALL INCLUDE A DETAILED

SCHEDULE OF EVENTS DETAILING EACH PHASE OF INSTALLATION, INCLUDING A PROJECTED TIMELINE.

2. ALL EQUIPMENT AND COMPONENT PARTS FURNISHED SHALL BE NEW, MEET OR EXCEED THE MINIMUM REQUIREMENTS STATED

HEREIN, AND PERFORM TO MANUFACTURER’S SPECIFICATIONS. NO PART OR ATTACHMENT SHALL BE SUBSTITUTED OR APPLIED

CONTRARY TO THE MANUFACTURER'S RECOMMENDATIONS AND STANDARD PRACTICES.

3. THE VENDOR IS RESPONSIBLE FOR CLEARING OF BRUSH, TREES, OR ANY OTHER OBSTRUCTIONS, INCLUDING THE REMOVAL OF

FENCING, ASPHALT OR CONCRETE. ANY TREE STUMPS RESULTING FROM CLEARING SHALL BE GRUBBED. ALL ENVIRONMENTAL

PROTECTION REQUIREMENTS SHALL BE COMPLIED WITH.

4. THE VENDOR SHALL BE RESPONSIBLE FOR REMOVING AND LEGALLY DISPOSING OF THE TRASH GENERATED FROM THE INSTALLATION,

INCLUDING LUNCH BAGS AND DRINKS, DAILY. THE VENDOR SHALL NOT ALLOW TRASH TO BLOW AROUND OR AWAY FROM ANY

CONSTRUCTION SITE.

APPLICABLE PUBLICATIONS AND STANDARDS1. APPLICABLE MANUFACTURER’S INSTRUCTIONS AND STANDARD PRACTICES.

2. APPLICABLE OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (O.S.H.A.) PRACTICES.

3. ASTM A123: STANDARD SPECIFICATION FOR: ZINC (HOT GALVANIZED) COATINGS ON PRODUCTS FABRICATED FROM ROLLED, PRESSED,

AND FORGED STEEL SHAPES, PLATES, BARS, AND STRIP.

4. ASTM A153: STANDARD SPECIFICATION FOR: ZINC COATING (HOT-DIP) ON IRON AND STEEL HARDWARE.

5. EIA-81: MEASURING GROUND RESISTANCE AND POTENTAIL GRADIENTS IN THE EARTH.

6. FLORIDA BUILDING CODE, 2014 EDITION.

7. FDOT 2015 STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE DESIGN.

8. FDOT 2015 DESIGN STANDARDS.

9. IEEE 837: STANDARD FOR QUALIFYING PERMANENT CONNECTIONS USED IN SUBSTATION GROUNDING.

10. NATIONAL ELECTRICAL CODE (NEC) (NFPA 70), 2014 EDITION.

11. NEC ARTICLE 250: GROUNDING AND BONDING.

12. NIST: NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY.

13. UL 467: STANDARDS FOR GROUNDING AND BONDING EQUIPMENT.

14. NATIONAL FIRE PROTECTION ASSOCIATION (NFPA 780)

15. NFPA 54 – NATIONAL FUEL GAS CODE

16. NFPA 58 – STORAGE AND HANDLING OF LIQUIFIED PETROLEUM GASES

17. NFPA 110 – STANDARDS FOR EMERGENCY AND STANDBY POWER SYSTEMS

CUT-OVER REQUIREMENTS:

1. GENERAL

1.1 THE VENDOR SHALL SUBMIT A DETAILED GENERATOR CUT-OVER PLAN FOR APPROVAL BY FDOT. THE PLAN SHALL INCLUDE A DETAILED

ORDER OF INSTALLATIONS, REMOVALS, AND TESTING.

THE VENDOR SHALL SUBMIT A PLAN TO CUT-OVER THE NEW GENERATOR IN THE EXISTING BIG PINE KEY TOWER SITE.

1.2 THE VENDOR SHALL PROVIDE AND INSTALL SPARK GAP GENERATOR, AUTOMATIC TRANSFER SWITCH, MAIN AND LOAD CENTER SURGE

PROTECTIVE DEIVCES, LOUVER MOTOR AND EXHAUST FANS. THE VENDOR SHALL BE RESPONSIBLE FOR FURNISHING ALL OF THE

NECESSARY EQUIPMENT, HARDWARE, LABOR, AND INSTALLATION PROCEDURES TO EFFECT PROPER INSTALLATION OF THE

GENERATOR SYSTEM.

1.3 ALL OF THE FDOT RADIO SYSTEMS ARE IN SERVICE AND CARRYING CRITICAL COMMUNICATIONS TRAFFIC. SHOULD THE CUT-OVER

CAUSE DOWNTIME TO THE EXISTING SYSTEM, THE DOWNTIME MUST BE COORDINATED WITH THE FDOT PRIOR TO THE DOWNTIME

OCCURRENCE. ALL WORK CLASSIFIED AS CAUSING LESS THAN FIVE MINUTES OF DOWNTIME REQUIRES A MINIMUM OF TWO DAYS

PRIOR NOTICE. ALL WORK CLASSIFIED AS CAUSING FIVE MINUTES OR MORE DOWNTIME REQUIRES A MINIMUM OF TEN DAYS PRIOR

NOTICE AND MUST BE COORDINATED WITH THE FDOT PRIOR TO OCCURRENCE.

INSPECTION NOTES:

1. THE INSPECTION SHALL BE PERFORMED BY THE VENDOR AND WITNESSED BY FDOT. THE VENDOR SHALL NOTIFY FDOT AT LEAST

10 DAYS PRIOR TO COMPLETION OF INSTALLATION. THE VENDOR AND FDOT SHALL VERIFY JOINTLY THAT ALL INSTALLATION WORK

IS CORRECTLY INSTALLED AND FUNCTIONAL.

2. THE VENDOR SHALL NOTIFY FDOT AT LEAST TWO DAYS PRIOR TO COMPLETION OF GROUNDING INSTALLATION FOR INSPECTION.

BELOW GRADE GROUNDING INSTALLATIONS AND GROUND CONNECTIONS SHALL NOT BE BACKFILLED UNTIL INSPECTED AND

APPROVED BY THE FDOT.

GROUNDING SHALL BE INSPECTED FOR PROPER CONNECTION TYPES, TIGHTNESS, WORKMANSHIP, AND CONFORMANCE WITH THE

APPROVED DESIGN. ANY EXOTHERMIC BONDS THAT ARE DEEMED UNSATISFACTORY SHALL BE REPAIRED BY THE VENDOR WITH NEW

BONDS, WITHOUT CLAIM.

3. FDOT STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE CONSTRUCTION SECTION 455 DOES NOT APPLY FOR THIS PROJECT.

4. THE SITE SHALL BE INSPECTED TO BE FREE OF DEBRIS AND THAT EXCAVATIONS ARE BACKFILLED AND COMPOUND RESTORED.

5. FOLLOWING THE COMPLETION OF INSPECTIONS, THE INSTALLED EQUIPMENT AND FACILITIES SHALL BE SUBJECTED TO A MINIMUM

20-DAY PERFORMANCE PERIOD. FOR THE PURPOSE OF THE SUCCESSFUL PERFORMANCE PERIOD, FAILURE OF OPERATION IS

DEFINED AS THE FAILURE OF A MAJOR COMPONENT OF THE SITE. THE PERFORMANCE VERIFICATION SHALL BE ACCOMPLISHED WITH

THE FDOT. UPON ACCEPTANCE OF THE PERFORMANCE AND TEST CRITERIA BY FDOT, THE 20-DAY PERFORMANCE PERIOD SHALL

BEGIN.

Page 61: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

T:\Public\ITS\Telecommunications\Facilities\Generator_BigPineKey\BIG PINE KEY CONTRACT PLANS REV1_20151105.vsd

IT-3

SHEET NO.BIG PINE KEY

SITE LAYOUT PLAN

STATE OF FLORIDADEPARTMENT OF TRANSPORTATION

BIG PINE KEY

SITE NAME FINANCIAL PROJECT IDCOUNTY

COLLIER

CONTRACT PLANS RECORDREV.DATE DESCRIPTION REV.DATE DESCRIPTION

FLORIDA DEPARTMENT OF TRANSPORTATION605 SUWANNEE ST. MS 90TALLAHASSEE, FL 32399-0450PH.(850)-410-5600FAX.(850)-410-5501

N

SCALE: 1" = 10' - 0"

FACILITIES PLAN:

1. EXISTING 1000 GALLON LPG TANK

2. EXISTING FUEL AND FUEL LEVEL SENSOR LINES

FDOT SHELTER

AND GENERATOR

ROOM ON 12 FT. PIER

SLERS EQUIPMENT BLDG ON

12 FT. PIERS THIS AREA

INCLUDES PIERS AND STAIRS

(6-6361)1

2

GUYED TOWER

EXISTING LPG TANK

104 deg

Page 62: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

IT-4

SHEET NO.BIG PINE KEY

FACILITIES REMOVAL

PLAN

STATE OF FLORIDADEPARTMENT OF TRANSPORTATION

BIG PINE KEY

SITE NAME FINANCIAL PROJECT IDCOUNTY

MONROET:\Public\ITS\Telecommunications\Facilities\Generator_BigPineKey\BIG PINE KEY CONTRACT PLANS REV1_20151105.vsd

CONTRACT PLANS RECORDREV.DATE DESCRIPTION REV.DATE DESCRIPTION

FLORIDA DEPARTMENT OF TRANSPORTATION605 SUWANNEE ST. MS 90TALLAHASSEE, FL 32399-0450PH.(850)-410-5600FAX.(850)-410-5501

14'-0"

4'-0"

3'-6

"

5'-0"

12'-0"

LIGHT

GROUND STRAP

POWER

ENTRY

1

HAND RAIL REMOVAL PLAN:

1. THE VENDOR SHALL SUBMIT A DETAILED REMOVAL PLAN FOR

APPROVAL BY FDOT. THE PLAN SHALL INCLUDE A DETAILED

SCHEDULE OF EVENTS DETAILING EACH PHASE OF

REMOVAL; A SAFETY PLAN DETAILING THE ACTIVITIES AND

THE ACTIONS TO BE TAKEN TO MITIGATE HAZARDS; AND AN

EMERGENCY PLAN.

2. THE VENDOR SHALL REMOVE THE PORTION OF THE EXISTING

RAIL SHOWN ON THE ADJACENT DRAWINGS TO FACILITATE

THE INSTALLATION OF THE GENERATOR OF THE ELEVATED

SHELTER GENERATOR ROOM.

3. IF PERMISSIBLE WITH SAFETY AS A PRIORITY AND THE

GENERATOR CAN BE INSTALLED WITH LESS RAIL REMOVAL

DETERMINE BY THE VENDOR, THIS SHALL BE ALLOWABLE.

4. THE GENERATOR TO BE INSTALLED WITHIN THE GENERATOR

ROOM IS A CUMMIN'S GENERATOR MODEL C20 N6 WHICH IS

34 INCHES WIDE AND 66 INCHES IN LENGTH.

5. MAKE ANY ADJUSTMENT WITH CUMMINS TO PREVENT

MODIFICATIONS TO THE DOOR OPENING.

WEST WALL

EXTERIOR ELEVATION

EXISTING INSTALLATION

TO BE REMOVED

LEGEND:

SHELTER EXTERIOR

PLAN VIEW

SHELTER EXTERIOR

NORTH ELEVATION VIEW

11

'-2

"

COLUMN

FIE

LD

VE

RIF

Y

FIE

LD

VE

RIF

Y

12

' -

0"

SH

EL

TE

R

17

' -

4"

5' -

5"

5' -

7"

5' -

7"

5' -

0"

SL

AB

9"

5' - 0"

8"

TY

P.

EXISTING RAILING

EXISTING SHELTER

COLUMN

SCALE: 1" = 5' - 0"

Page 63: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

IT-5

SHEET NO.BIG PINE KEY

FACILITIES

INSTALLATION PLAN

STATE OF FLORIDADEPARTMENT OF TRANSPORTATION

BIG PINE KEY

SITE NAME FINANCIAL PROJECT IDCOUNTY

MONROET:\Public\ITS\Telecommunications\Facilities\Generator_BigPineKey\BIG PINE KEY CONTRACT PLANS REV1_20151105.vsd

CONTRACT PLANS RECORDREV.DATE DESCRIPTION REV.DATE DESCRIPTION

FLORIDA DEPARTMENT OF TRANSPORTATION605 SUWANNEE ST. MS 90TALLAHASSEE, FL 32399-0450PH.(850)-410-5600FAX.(850)-410-5501

EXISTING INSTALLATION

TO BE INSTALLED

LEGEND:

14'-0"

4'-0

"

3'-6

"

5'-0"

12'-0"

LIGHT

GROUND STRAP

POWER

ENTRY

1 1

WEST WALL

EXTERIOR ELEVATION

SCALE: 1" = 5' - 0"

SHELTER EXTERIOR

PLAN VIEW

SHELTER EXTERIOR

NORTH ELEVATION VIEW

11

'-2

"

COLUMN

FIE

LD

VE

RIF

Y

FIE

LD

VE

RIF

Y

12

' -

0"

SH

EL

TE

R

17

' -

4"

5' -

5"

5' -

7"

5' -

7"

5' -

0"

SL

AB

9"

5' - 0"

8"

TY

P.

EXISTING RAILING

EXISTING SHELTER

COLUMN

HAND RAIL INSTALLATION PLAN:1. THE VENDOR SHALL SUBMIT A DETAILED INSTALLATION PLAN

FOR APPROVAL BY FDOT. THE PLAN SHALL INCLUDE A

DETAILED SCHEDULE OF EVENTS DETAILING EACH PHASE OF

THE INSTALLATION; A SAFETY PLAN DETAILING THE

ACTIVITIES AND THE ACTIONS TO BE TAKEN TO MITIGATE

HAZARDS; AND AN EMERGENCY PLAN.

2. THE VENDOR SHALL RE-INSTALL THE PORTION OF THE

EXISTING REMOVED RAIL ONCE THE GENERATOR HAS BEEN

INSTALLED IN THE ELEVATED SHELTER GENERATOR ROOM.

3. THE RE-INSTALLED RAIL MUST BE BROUGHT BACK TO ITS

STRUCTURAL INTEGRITY.

4. ALL FIELD WELDS AND CUTS SHALL BE GIVEN TWO (2) BRUSH

COATS Z.R.C. LIQUID, TO TOTAL A MINIMUM 8 MILS DRY FILM

THICKNESS. PREPARE SURFACES AND APPLY IN

ACCORDANCE WITH THE MANUFACTURER’S INSTRUCTIONS.

SPRAY PAINT MAY NOT BE USED. AFTER 24 TO 48 HOURS, A

TOP COAT OF HIGH UV RESISTANCE ACRYLIC PAINT SHALL BE

APPLIED OVER THE ZRC.

Page 64: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

FACILITIES REMOVAL PLAN:1. 75 KVA, 120/240VAC, 1-PHASE POLE MOUNTED POWER

COMPANY TRANSFORMER

2. 120/240V, 100A NEMA 1, MAIN DISCONNECT FUSE

SWITCH, 100 AMPERE, TO REMAIN

3. EXISTING AUTOMATIC TRANSFER SWITCH, NEMA 1,

WITH ANNUNCIATOR PANEL, TO BE REMOVED

4. EXISTING 100 AMPERE, 120/240V MANUAL TRANSFER

SWITCH, NEMA 1, TO REMAIN

5. EXISTING OUTDOOR PORTABLE GENERATOR PLUG. TO

REMAIN.

6. EXISTING 120/240V, 1-PHASE, 30 POLE DISTRIBUTION

PANEL BOARD, NEMA 1, TO REMAIN

7. EXISTING 100 AMPERE, 120/240VAC, BREAKER

DISCONNECT, NEMA 1, TO REMAIN

8. EXISTING 120/240V, 20 KW GENERAC LPG GENERATOR

WITH OUTPUT LOAD BREAKER, TO BE REMOVED

9. EXISTING GENERATOR CONTROL PANEL, TO BE

REMOVED

10. EXISTING ABOVE GROUND LPG TANK AND ENCLOSURE,

TO REMAIN.

11. EXISTING PUNCH BLOCK TO REMAIN

12. EXISTING FUEL LEVEL MONITOR, TO REMAIN

13. EXISTING I/O DATA MODULE, TO BE REMOVED

1 2 3 4 6 7

8

9

EQUIPMENT ROOM

1

2

3

5

FACILITIES INSTALLATION PLAN:1. NEW AUTOMATIC TRANSFER SWITCH, NEMA 1, CUMMINS

MODEL OTEC 125, TO BE INSTALLED WITH EXTERNAL

ANNUNCIATOR PANEL

2. NEW 120/240V, 20 KW CUMMINS LPG GENERATOR WITH

OUTPUT LOAD BREAKER, MODEL C20 N6.

3. NEW CUMMINS GENERATOR CONTROL PANEL

4. NEW I/O DATA MODULE, TO BE INSTALLED

5. NEW PRIMARY SPD APT MODEL TE01XAS30E1XD-W2

6. NEW SECONDARY SPD APT MODEL NO. TE01XDS204XA-

W2 CONNECT TO SPACE 27 AND 29 WITH 40A-2 POLE

BREAKER

A

5

6

GENERATOR ROOM

EQUIPMENT ROOM GENERATOR ROOM

IT-6

SHEET NO.BIG PINE KEY

electrical riser and

comm diagram

STATE OF FLORIDADEPARTMENT OF TRANSPORTATION

BIG PINE KEY

SITE NAME FINANCIAL PROJECT IDCOUNTY

MONROET:\Public\ITS\Telecommunications\Facilities\Generator_BigPineKey\BIG PINE KEY CONTRACT PLANS REV1_20151105.vsd

CONTRACT PLANS RECORDREV.DATE DESCRIPTION REV.DATE DESCRIPTION

FLORIDA DEPARTMENT OF TRANSPORTATION605 SUWANNEE ST. MS 90TALLAHASSEE, FL 32399-0450PH.(850)-410-5600FAX.(850)-410-5501

EXISTING ELECTRICAL RISER

AND COMMUNICATIONS DIAGRAM

EXISTING INSTALLATION

TO BE REMOVED

TO BE INSTALLED

LEGEND:

1312

11

10

10

4

POWER CO. 120/240V, 1-PH

SITE AC WIRING 120/240V, 1-PH

LPG FUEL LINE

GENERATOR ALARM AND 12VDC BATTERY

CAT 5 WIRING TO PUNCH BLOCK

FUEL LEVEL MONITOR LINE

PROPOSED ELECTRICAL RISER

AND COMMUNICATIONS DIAGRAM

Page 65: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

IT-7

SHEET NO.BIG PINE KEY

GENERATOR

REMOVAL PLAN

STATE OF FLORIDADEPARTMENT OF TRANSPORTATION

BIG PINE KEY

SITE NAME FINANCIAL PROJECT IDCOUNTY

MONROET:\Public\ITS\Telecommunications\Facilities\Generator_BigPineKey\BIG PINE KEY CONTRACT PLANS REV1_20151105.vsd

CONTRACT PLANS RECORDREV.DATE DESCRIPTION REV.DATE DESCRIPTION

FLORIDA DEPARTMENT OF TRANSPORTATION605 SUWANNEE ST. MS 90TALLAHASSEE, FL 32399-0450PH.(850)-410-5600FAX.(850)-410-5501

EXISTING INSTALLATION

TO BE REMOVED

LEGEND:

GENERATOR REMOVAL PLAN:

1. REMOVE AND DISPOSE OF EXISTING 20 KW GENERAC

GENERATOR PER LOCAL COUNTY CODE REQUIREMENTS

2. REMOVE AND REPLACE MUFFLER AND EXHAUST PIPE.

3. REMOVE AND REPLACE WITH NEW RADIATOR COOLING AIR

EXHAUST AS PER NEW GENERATOR REQUIREMENTS

4. REMOVE SCREEN ON OUTSIDE HOOD OF ROOM EXHAUST FAN

5. REMOVE SCREEN ON OUTSIDE GENERATOR EXHAUST LOUVER

6. GENERATOR OUTPUT BREAKER, TO REMAIN

7. OUTPUT WIRING TO ATS TO REMAIN IF SERVICEABLE

8. GENERATOR OUTPUT CONDUIT. REPLACE WIRING WITH SAME

SIZE IF REQUIRED BY NEW CONDUIT ROUTING

9. MOTORIZED LOUVER ASSEMBLY, TO BE REMOVED AND

REPLACED.

10. EXISTING PROPANE GAS FUEL LINE CONDUIT TO BE

REINSTALLED ON NEW GENERATOR

1'-9

5/1

6"

EXISTING 20 KW

GENERAC GENERATOR

2'-3/4"

5'-11 13/16"

POSITIVE PRESSURE

MOTORIZED INTAKE

DAMPER W/HOOD

2'-10"

FE

GENERATOR

100A-2P

CKT BKR

W/ENCL.

CONDUIT INTO

MICROWAVE SHELTER

INPUT TO GENERAC ATS

RADIATOR COOLING

AIR EXHAUST

WITH 3/8" STEEL

PLATE SHROUD

REMOVE SCREEN

ENGINE ROOM HOT

AIR LOUVER AND

EXHAUST FAN

REMOVE SCREEN

HP

S

GENERATOR OUTPUT

POWER CONDUIT TO

WALL MOUNTED CKT BKR

SCALE: 1" = 1' - 6"

1

34

5

6

7

8

8

1'-1

3/8

"

9

10

2

3'-0

"

N

1'-8

5/1

6"

Page 66: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

IT-8

SHEET NO.BIG PINE KEY

GENERATOR

INSTALLATION PLAN

STATE OF FLORIDADEPARTMENT OF TRANSPORTATION

BIG PINE KEY

SITE NAME FINANCIAL PROJECT IDCOUNTY

MONROET:\Public\ITS\Telecommunications\Facilities\Generator_BigPineKey\BIG PINE KEY CONTRACT PLANS REV1_20151105.vsd

CONTRACT PLANS RECORDREV.DATE DESCRIPTION REV.DATE DESCRIPTION

FLORIDA DEPARTMENT OF TRANSPORTATION605 SUWANNEE ST. MS 90TALLAHASSEE, FL 32399-0450PH.(850)-410-5600FAX.(850)-410-5501

EXISTING INSTALLATION

TO BE INSTALLED

LEGEND:

GENERATOR INSTALLATION PLAN:

1. INSTALL NEW C20 N6, CUMMINS 25 KVA / 20 KW GENERATOR

2. INSTALL INSULATED MUFFLER AND EXHAUST PIPE SYSTEM.

3. REPLACE WITH NEW RADIATOR COOLING AIR EXHAUST AS PER

NEW GENERATOR REQUIREMENTS

4. REPLACE SCREEN ON OUTSIDE HOOD OF EXHAUST FAN

5. REPLACE SCREEN ON OUTSIDE GENERATOR EXHAUST LOUVER

6. REUSE EXISTING GENERATOR OUTPUT BREAKER

7. REPLACE EXISTING GENERATOR OUTPUT WIRING TO NEW ATS AS

REQUIRED BY WIRING RUN

8. REPLACE GENERATOR OUTPUT CONDUIT AND REPLACE WIRING

WITH SAME SIZE IF REQUIRED TO NEW GEN POWER ENTRY

9. REPLACE MOTORIZED LOUVER ASSEMBLY

10. EXTEND EXISTING PROPANE GAS FUEL LINE CONDUIT TO

ACCOMMODATE TO NEW GENERATOR

11. INSTALL NEW CUMMINS GENERATOR THROUGH EXISTING 36” WIDE

DOOR. IF GENERATOR IS TO BIG TO BE PLACED THROUGH THE

DOOR, COORDINATD WITH MANUFACTURER TO DISASSEMBLE

GENERATOR AS NECESSARY. GENERATOR TO BE BROUGHT IN

WITH CRANE AND OUTDOOR RAILS MAY NEED TO BE REMOVED

AND REINSTALLED TO FACILITATE INSTALLATION

12. INSTALL THE GENERATOR IN ACCORDANCE TO THE

MANUFACTURERS INSTALLATION MANUAL

SCALE: 1" = 1' - 6"

1'-9

5/1

6"

2'-3/4"

6'-9 5/16"

POSITIVE PRESSURE

MOTORIZED INTAKE

DAMPER W/HOOD

2'-10"

FE

GENERATOR

100A-2P

CKT BKR

W/ENCL.

CONDUIT INTO

MICROWAVE SHELTER

INPUT TO GENERAC ATS

HP

S

GENERATOR OUTPUT

POWER CONDUIT TO

WALL MOUNTED CKT BKR 1 34

5

6

7

8

1'-1

3/8

"

9

10

1

1'-8

5/1

6"

11

ENGINE ROOM

HOT AIR LOUVER

AND EXHAUST

FAN

RADIATOR COOLING

AIR EXHAUST

WITH 3/8" STEEL

PLATE SHROUD

3'-0

"

2

N

Page 67: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

IT-9

SHEET NO.BIG PINE KEY GEN.

ROOM WALL

INSTALLATION PLAN

STATE OF FLORIDADEPARTMENT OF TRANSPORTATION

BIG PINE KEY

SITE NAME FINANCIAL PROJECT IDCOUNTY

MONROET:\Public\ITS\Telecommunications\Facilities\Generator_BigPineKey\BIG PINE KEY CONTRACT PLANS REV1_20151105.vsd

CONTRACT PLANS RECORDREV.DATE DESCRIPTION REV.DATE DESCRIPTION

FLORIDA DEPARTMENT OF TRANSPORTATION605 SUWANNEE ST. MS 90TALLAHASSEE, FL 32399-0450PH.(850)-410-5600FAX.(850)-410-5501

EXISTING INSTALLATION

TO BE INSTALLED

LEGEND:

2'-10"

6"

3'-1

0"

5'-8"

1'-11 1/2"

1'-3

"

2'-7"

5'-6"

2'-10"

9'-1

1/2

"11'-2"

9'-1

1/2

"

11'-2"

QUADRUPLEX

PULL BOX

PULL BOX

10

PULL BOX

2 ft.- 0.5 in.

6 ft. 2 in.

4 ft. 5.75 in.

3'-1

1 1

/2"

INTERIOR WEST WALL

GENERATOR ROOM

INTERIOR EAST WALL

GENERATOR ROOM

INTERIOR SOUTH WALL

GENERATOR ROOM

GEN

EXHAUST

RADIATOR

COOLING

AIR EXHAUST

LOUVER

5' -

2"

1'-6"

2'-4"

EXHAUST

FAN

9 11/16"

7"

RADIUS - 5 “

4' -

0"

FAN

THERMOSTAT

FACILITIES INSTALLATION PLAN:

1. REPACE ENTIRE MOTORIZED LOUVER ASSEMBLY – MOTOR, ARM AND LOUVER ASSEMBLY.

2. REPLACE SCREEN ON OUTSIDE HOOD OF EXHAUST FAN

3. REPLACE SCREEN ON OUTSIDE HOOD OF AIR INTAKE VENT

4. REPLACE EXHAUST FAN

5. MODIFY OPENING OF GENERATOR RADIATOR COOLING AIR EXHAUST LOUVER IF NECESSARY TO ACCOMMODATE NEW

CUMMINS 25 KVA GENERATOR RADIATOR EXHAUST

6. INSTALL NEW INSULATED GENERATOR MUFFLER AND EXHAUST PIPE AT EXISTING GENERATOR EXHAUST PIPE LOCATION,

MODIFY AS NECESSARY.

7. REUSE EXISTING CONDUITS WHERE APPLICABLE AND SERVICABLE

10. 100A-2P GENERATOR OUTPUT BREAKER TO REMAIN

11. CONDUIT / WIRING TO GENERATOR, MODIFY AND RECONNECT TO NEW CUMMINS C20 N6

12. ALARM CONDUIT TO GENERATOR, MODIFY TO NEW ALARM WIRING

13. 120VAC CIRCUIT TO GENERATOR COOLANT HEATER, MODIFY AND ADJUST TO NEW COOLANT HEATER

14. ALARM CONDUIT FROM ATS,MODIFY WITH NEW GENERATOR DATA CONTROL WIRING

15. CONDUIT / WIRING TO ATS, ADJUST TO NEW ATS

11

12

13

14

15

1

7

6

SCALE: 1" = 2' - 0"

4

5

5

AIR INTAKE

VENT

2

Page 68: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

IT-10

SHEET NO.BIG PINE KEY

EXTERIOR s. wALL

INSTALLATION PLAN

STATE OF FLORIDADEPARTMENT OF TRANSPORTATION

BIG PINE KEY

SITE NAME FINANCIAL PROJECT IDCOUNTY

MONROET:\Public\ITS\Telecommunications\Facilities\Generator_BigPineKey\BIG PINE KEY CONTRACT PLANS REV1_20151105.vsd

CONTRACT PLANS RECORDREV.DATE DESCRIPTION REV.DATE DESCRIPTION

FLORIDA DEPARTMENT OF TRANSPORTATION605 SUWANNEE ST. MS 90TALLAHASSEE, FL 32399-0450PH.(850)-410-5600FAX.(850)-410-5501

EXISTING INSTALLATION

TO BE INSTALLED

LEGEND:

3 / 4 “ CONDUIT

FOR FUEL LEVEL

MONITOR

PROPANE GAS

LINE ENTRY

PULL BOX ENTRY

4 1 / 2 “

GROUND STRAP

ENTRY FROM

GROUND RING

8"

1

POWER ENTRY

3

2

4

5

COAX

ANTENNA

ENTRY

SCALE: 1" = 2' - 0"

FACILITIES INSTALLATION PLAN:

1. REPLACE SCREEN ON OUTSIDE HOOD OF EXHAUST FAN

2. REPLACE SCREEN ON OUTSIDE HOOD OF GENERATOR EXHAUST LOUVER

3. INSTALL NEW GENERATOR EXHAUST PIPE AT EXISTING GENERATOR

EXHAUST PIPE. MODIFY AS NECESSARY.

4. REUSE EXISTING FUEL PIPE FOR NEW GENERATOR FUEL PIPE

5. REUSE EXISTING POWER ENTRY SERVICE. TO REMAIN AS IS.

EXTERIOR SOUTH WALL

Page 69: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

IT-11

SHEET NO.BIG PINE KEY

EQUIPMENT ROOM

REMOVAL PLAN

STATE OF FLORIDADEPARTMENT OF TRANSPORTATION

BIG PINE KEY

SITE NAME FINANCIAL PROJECT IDCOUNTY

MONROET:\Public\ITS\Telecommunications\Facilities\Generator_BigPineKey\BIG PINE KEY CONTRACT PLANS REV1_20151105.vsd

CONTRACT PLANS RECORDREV.DATE DESCRIPTION REV.DATE DESCRIPTION

FLORIDA DEPARTMENT OF TRANSPORTATION605 SUWANNEE ST. MS 90TALLAHASSEE, FL 32399-0450PH.(850)-410-5600FAX.(850)-410-5501

EQUIPMENT ROOM REMOVAL PLAN:

1. EXISTING MAIN BREAKER DISCONNECT, 100A-2P, TO REMAIN

2. EXISTING GENERAC ATS AND ANNUNCIATOR PANEL TO BE REMOVED

AND REPLACED WITH CUMMINS OTEC 125 AND ANNUNCIATOR

3. EXISTING 100A-2P, MTS TO REMAIN

4. EXISTING 120/240V, 100A, 30-POLE DISTRIBUTION PANEL TO

REMAIN.REMOVE ALL SINGLE POLE SPD CONNECTED TO PANEL

BOARD

5. EXISTING FUEL LEVEL MONITOR TO BE REMAIN

EXISTING INSTALLATION

TO BE REMOVED

LEGEND:

INTERIOR WEST WALL

EQUIPMENT ROOM

EXISTING

GENERAC ATS

107 in.

11 in.

48 in.

8 in.

8 in.

Exist.

Annunc.

ALARM WIRING

CONDUIT TO

GENERATOR ALARM

PHONE BLOCK ON

SOUTH WALL

REMOVE FUEL

LEVEL SPD

FUEL

LEVEL

CONDUIT

1

2

3

4

5

REWIRE

FUEL

LEVEL

WIRING

TO NEW

SPD

REWIRE

FUEL

LEVEL

WIRINGCONDUIT

FROM

GENERATOR

SCALE: 1" = 1' - 6"

Page 70: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

IT-12

SHEET NO.BIG PINE KEY

equipment room

installation PLAN

STATE OF FLORIDADEPARTMENT OF TRANSPORTATION

BIG PINE KEY

SITE NAME FINANCIAL PROJECT IDCOUNTY

MONROET:\Public\ITS\Telecommunications\Facilities\Generator_BigPineKey\BIG PINE KEY CONTRACT PLANS REV1_20151105.vsd

CONTRACT PLANS RECORDREV.DATE DESCRIPTION REV.DATE DESCRIPTION

FLORIDA DEPARTMENT OF TRANSPORTATION605 SUWANNEE ST. MS 90TALLAHASSEE, FL 32399-0450PH.(850)-410-5600FAX.(850)-410-5501

EXISTING INSTALLATION

TO BE INSTALLED

LEGEND:

EQUIPMENT ROOM INSTALLATION PLAN:1. EXISTING MAIN BREAKER DISCONNECT, 100A-2P, TO REMAIN

2. NEW CUMMINS OTEC 125 ATS

3. EXISTING 100A-2P, MTS TO REMAIN

4. EXISTING 120/240V, 100A, 30-POLE DISTRIBUTION PANEL TO REMAIN.

5. EXISTING FUEL LEVEL MONITOR TO REMAIN

6. NEW ANNUNCIATOR PANEL PER CUMMINS

7. PRIMARY APT SPD MODEL NO. TE01XAS30E1XD-W2

8. SECONDARY APT MODEL NO. TE01XDS204XA-W2 WIRED TO A 40A

BREAKER IN THE DISTRIBUTION PANEL BOARD

9. NEW LOW VOLTAGE SPD AND MOUNTED ON GROUND STRAP AND

BONDED TO EQUIPMENT ROOM GROUND STRAP

10. ADJUST ALL CONDUITS SHADED IN BLUE TO NEW EQUIPMENT

11. MOUNT THE TRANSFER SWITCH PER THE INSTRUCTION OF CUMMINS

TRANSFER SWITCH INSTALLATION MANUAL

SCALE: 1" = 1' - 6"

COPPER GROUND STRAP

CABLE RACK

8 in.12 in.

11 in.

ALARM WIRING

CONDUIT TO PUNCH

BLOCK ON SOUTH WALL

FUEL

LEVEL

SENSOR

CONDUIT

2

34

51

6

7

8

9

INTERIOR WEST WALL

EQUIPMENT ROOM

REWIRE

FUEL

LEVEL

WIRING

TO NEW

SPD

Page 71: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

IT-13

SHEET NO.BIG PINE KEY

equipment room

installation PLAN

STATE OF FLORIDADEPARTMENT OF TRANSPORTATION

BIG PINE KEY

SITE NAME FINANCIAL PROJECT IDCOUNTY

MONROET:\Public\ITS\Telecommunications\Facilities\Generator_BigPineKey\BIG PINE KEY CONTRACT PLANS REV1_20151105.vsd

CONTRACT PLANS RECORDREV.DATE DESCRIPTION REV.DATE DESCRIPTION

FLORIDA DEPARTMENT OF TRANSPORTATION605 SUWANNEE ST. MS 90TALLAHASSEE, FL 32399-0450PH.(850)-410-5600FAX.(850)-410-5501

EXISTING INSTALLATION

TO BE USED AS PART OF

THIS PROJECT

LEGEND:

EQUIPMENT ROOM INSTALLATION PLAN:

1. GENERATOR ALARM PUNCH BLOCK TO REMAIN AND

BE INTEGRATED TO NEW GENERATOR ALARMS

PHONE

BOXES

PHONE

BOXES GR

OU

ND

ST

RA

P

GR

OU

ND

ST

RA

P

GROUND STRAP

CABLE ENTRY PORT

QUADRUPLEXQUADRUPLEX

CABLE TRAY

SUPPORT

CABLE TRAY

SUPPORT

1

PHONE

BOXESG

RO

UN

D S

TR

AP

PUNCH BLOCKS

PUNCH BLOCKS

INTERIOR SOUTH WALL

EQUIPMENT ROOM

SCALE: 1" = 1' - 6 "

Page 72: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

APPENDIX B

EMERGENCY GENERATOR POWER SYSTEM

AT BIG PINE KEY FDOT

PUNCH BLOCK DETAILS

AND MAJOR ITEM LIST

November 5, 2015

FILE:\\dotscoteoserver\Traffic_Ops_Data\Public\ITS\Telecommunications\Facilities\Generators_BigPineKeyFDOT\BigPineKeyFDOT_Appendix_B_2015 11 05 REV 0.0.docx

Page 73: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

B1. GENERATOR ALARM DETAILS

Equipment 2 Punch Block

Per Engine Generator Manufacturer Model

Page 74: FURNISH AND INSTALL EMERGENCY … A TECHNICAL SPECIFICATIONS TO FURNISH AND INSTALL EMERGENCY GENERATOR POWER SYSTEM AT BIG PINE KEY FDOT November 5, 2015 FILE: \\dotscoteoserver\Traffic_Ops_Data\Public\ITS

THIS TABLE DOES NOT INCLUDE ALL PARTS AND PIECES REQUIRED BY THE

CONTRACT AND SHALL BE USED FOR INFORMATIONAL PURPOSES ONLY.

Table B.2: Major Items to be Furnished and/or Installed by the Vendor

ITEM QUANTITY

20 kW Emergency Generator (Cummins C20 N6) 1

Automatic Transfer Switch (Cummins OTEC 125) 1

Generator Alarm SPD (4 pins each) 5

Annunciator (LonWorks) 1

Main Disconnect AC Power Primary SPD with Spare Modules 1

Load Center AC Power Secondary SPD with Spare Modules 1

Required conduits and wires as per plan drawings *