futurehouse training manualoptimised
TRANSCRIPT
-
7/27/2019 Futurehouse Training Manualoptimised
1/26
TRAINING MANUAL
CONTENTS
TOOLS REQUIRED
BUILDING PROCEDURES
1. FOUNDATIONS2. WALL START UP
3. WALL CONSTRUCTION4. WINDOW AND DOOR FITTING
5. PLASTERING6. ROOFING
7. PLUMBING AND ELECTRICAL FITTING8. FORMWORK APPLICATION
-
7/27/2019 Futurehouse Training Manualoptimised
2/26
FUTUREHOUSE WALL SYSTEM TRAINING MANUAL
1.Tools required Foundations are as traditional so require conventional concrete mixing and
set up equipment.
For Futurehouse wall panels require:- Parallel sided timber or metal template the width of the FH panel to mark the
position of the wall panels on the foundations and the spacing of the starter
bar holes.
- Conventional wall profiles to ensure wall templates are straight and cornersare correct.
- Electric drilland extension cord with concrete drill bits (6 or 8mm) for drillingholes for the starter bars. These are either Y5,6 or Y8s.
- Tape measure to ensure correct spacing of starter bars.- Soft wire for tying the panels together.- Pliers for wire tying.- Levels and or plumb lines to ensure panels are plumb and straight.- Heavy duty wire cutters to cut the FH panel mesh where required.
Alternatively an angle grinder can be used.
- Hacksaw blade or stiff blade saw to cut the expanded polystyrene (EPS).- Hand held blow torch to melt the EPS where have to insert electrical or
plumbing conduit behind the FH panel wire mesh.
- Wall bracing system to brace panels from one side whilst plastering. (These areavailable from Futurehouse).
- Plaster thickness guides to control plaster thickness and make straight edgingeasier. (Also available from Futurehouse).
- Plastering is conventional so traditional plastering tools are required.- Plastering options include; Terylene machines to apply first coat spatter
plaster and for rough finishing coats and plaster spray equipment (Available
from Futurehouse).
- All other building processes using the Futurehouse panels are conventionalusing standard equipment.
-
7/27/2019 Futurehouse Training Manualoptimised
3/26
-
7/27/2019 Futurehouse Training Manualoptimised
4/26
3.
- Once starter bars are in position place the Futurehouse panels between thestarter bars starting from a corner. If needed use timber wedges under thepanels to keep the panel edges perfectly vertical. Wire tie the starter bars to
the panel mesh and the panels to each other at about 300mm centres.
Drill 100mm deep holes for
starter bars along panel wall
lines in zig zag pattern at
600mm centres on either side
Futurehouse panels wire tied
to starter bar at panel join.
Next starter bars at 600mm
centres on other side of the
panels
-
7/27/2019 Futurehouse Training Manualoptimised
5/26
4.
Wall construction
- All corners and wall joins must be reinforced with right angled wire mesh tothe full height of the walls.
Starter bars 900 mm above
foundation level tied to mesh
of the panels. Panels need to
be plumb and level
Wire overlap at panel joins.
EPS of joining panels tight fits
with no gaps. Wire of
adjoining panels should be
parallel.
-
7/27/2019 Futurehouse Training Manualoptimised
6/26
5.
Internal wall corner reinforcedwith right angled wire mesh
+- 250mm x 250mm. Cornermesh is wire tied to mesh of
wall panels
External corners reinforced
with right angled wire mesh
-
7/27/2019 Futurehouse Training Manualoptimised
7/26
6.
- To cut panels to fit and for door and window openings the wire must first becut with a wire cutter or angle grinder. Measure and mark the cut lines before
starting to cut.
- After the wire mesh has been cut the EPS is cut with a hacksaw blade or stiffblade hand saw.
To cut panels to fit walldimensions and for windows
and door openings the cutlines must first be clearly
marked and then the wire on
both sides cut with a wirecutter or angle grinder
After cutting the wire mesh
the EPS is cut with a hacksaw
blade or hand saw. Panels arecut for door and window
openings and to fit floor plans
-
7/27/2019 Futurehouse Training Manualoptimised
8/26
7.
- Reinforcement around wall openings. Added steel mesh reinforcement isneeded around window and door openings to ensure no plaster cracks form in
these areas. Mesh reinforcement strips of +- 250 x 500mm must be wire tied
diagonally around openings before plastering.
- Wall bracing. Once wall panels are in place and tied together they need to bebraced to hold them vertical and plumb before plastering. This needs to bedone only on one side of the panels. There are a number of methods of doing
this but Futurehouse have an adjustable, easy to install system for this
purpose.
Wire mesh strips must be wire
tied diagonallyaround all
window and door openings
Adjustable wall brace to hold
panels vertical and plumb
whilst plastering
-
7/27/2019 Futurehouse Training Manualoptimised
9/26
8.
- Once the panels are plastered on one side the wall braces can be removed 24hours later. The panels are now sufficiently stiff that plastering on the otherside can be done without bracing.
Panels are braced on one side
only to hold them plumb
whilst plastering from the
other side
To make sure that the wallbraces do not slip they need to
be anchored to the ground orfloor slab
-
7/27/2019 Futurehouse Training Manualoptimised
10/26
9.
- Window and door fitting. This can be done several ways.Method 1.
Before plastering metal cliscoe type window and door frames (which shouldbe sized to the width of the Futurehouse panels) can be fitted into the pre-cut
panels.
Metal cliscoe type window
frame fitted into the
Futurehouse panels before
plastering
Metal lugs from the back ofmetal frames must be wire tied
to the panel mesh to keep theframes in position
-
7/27/2019 Futurehouse Training Manualoptimised
11/26
10.
Method 2.
Fully plaster the door or window opening reveals and then fit and secure
frames into the plaster with screw and screw plug systems. This is a common
method of fitting timber and aluminium frames to the Futurehouse panels.
An option to secure metal
window and door frames is to
spot weld short pices of Y5,6
rebar to the frames and wiretie these to the panel mesh.
The common method of
fitting timber and aluminium
window and door frames is tofully plaster the window and
door reveals and then fix theframes in position with screws
and screw plugs
-
7/27/2019 Futurehouse Training Manualoptimised
12/26
11.
Method 3.
Fix a metal angle iron or hollow tube sub frame into the openings before
plastering. Fix and plaster these in place and then secure the frames to the sub
frameUseful tip: To secure heavy door/window frames it is advisable to burn or cut
away the EPS where the fixing bolts are to be secured to the wall and to fill
this space with mortar or concrete to hold the bolts.
Plastering.
Plastering can be done by machine or hand.
Standard plaster mix for the Futurehouse panel is a 4:1 building sand to
cement mix.
To prevent plaster crack formation it is recommended that 12mm long
polypropylene fibre is added to the plaster mix. (Available from Futurehouse)
Adding fibre
The simple mix ratio is a handful of fibre (100gm) per pocket of cement used.
The fibre should be pre dispersed in a bucket of water and then added to the
mix. Alternatively thoroughly mix the fibre into the dry plaster mix before
adding water
It is advisable to slush the panels with the plaster mix first. This can be done
using a hard bristle brush, Terylene machine or spray equipment.
The slush coat should be left to dry overnight.The purpose of the slush coat is to prevent the plaster slipping on the EPS
and it speeds up the drying of the finishing plaster coat by absorbing water.
EPS burned or cut away and
space filled with mortar to takedoor or window frame support
bolts
-
7/27/2019 Futurehouse Training Manualoptimised
13/26
12.
Plaster thickness guides.
To control the final plaster thickness it is recommended that plaster thickness
guides are attached to the wire mesh of the panels before plastering.
These are available from Futurehouse and can be reused.
These thickness guides control the plaster thickness above the panel wire mesh
either at 12 or 25 mm.
The guides have the advantage of making straight edging easier.
They must be removed as soon as the plaster sets up and the spaces filled in
and smoothed over before the plaster dries.If this is not done cracks will appear where the guides have been removed.
Apply a plaster slush coat tothe panels first. This stops
plaster slippage and speeds up
the drying of the final plaster
coat
-
7/27/2019 Futurehouse Training Manualoptimised
14/26
13.
Plaster finishing is as conventional with steel or wooden floats used depending
on the finish required.
25mm plaster thickness guidesattached to the wire mesh of
the Futurehouse panels.
These are used to control
plaster thickness and act as
guides for straight edging
-
7/27/2019 Futurehouse Training Manualoptimised
15/26
14.
Plaster straight edging using
plaster thickness guides to
control plaster thickness and
act as guide rails for thestraight edge
-
7/27/2019 Futurehouse Training Manualoptimised
16/26
15.
Spray plastering
Spray plastering is recommended as this contributes to the speed of building
with the Futurehouse panel.
1) The simplest method is to use a Tyrolean spatter plaster machine.2) Use a plaster spray gun attached to an air compressor. Normally need 4-6
bar pressure and compressor tank capacity of 100-150 litres.
3) For large projects it is recommended that large, automatic, mixing andspray equipment is usedTypically these could be the PFT G4 and ZP XXL machines. (These are
available from Futurehouse).
Spray application should also be done in two passes with a slush coat
being applied on day 1 and the finishing coat 24 hours + later.
Plaster thickness guides should still be used and finishing with straight
edges and plaster floats. Another advantage of using these machines isthat waste plaster can be fed back into the machine hoppers.
Spray plastering with hopper
gun and air compressor
-
7/27/2019 Futurehouse Training Manualoptimised
17/26
16.
Pre formulated plaster mixes to the Futurehouse specifications can be
supplied for these machines in bulk silos.
Spray plastering slush coat
with PFT automatic plaster
mixing and spraying
equipment.Plaster guides secured before
plastering begins
-
7/27/2019 Futurehouse Training Manualoptimised
18/26
17.
Plaster finishing.
Futurehouse offer a resin based product Futurehouse Skimplast for wall
finishing.
Skimplast is supplied as a clear with the plaster taking on the colour of the
plaster sand used. It can also be pigmented to achieve a range of natural
and earth tones in combination with the plaster sand used. To match thecolour required Futurehouse need a sample of the plaster sand to be used
plus a sample of the final colour required.
Skimplast provides a natural, resilient, maintenance free wall coating that
will significantly outlast paint finishes as the coating is millimetres as
opposed to microns thick. Skimplast also has the benefit of filling and
masking plaster cracks and can be used on conventional brick plastered
walls as well as the Futurehouse panel.
Skimplast is suitable for both external and internal use.
Futurehouse Skimplast is mixed in a ratio a 1 part resin to 3 parts plaster
sand and applied as a 2-3 mm finishing plaster coat.
Plastering with a PFT G4
plastering machine
-
7/27/2019 Futurehouse Training Manualoptimised
19/26
18.
Internal plastering
Futurehouse recommend the use of Knaufs MP75L for internal wall and
ceiling finishing to provide walls with a high quality, smooth finish.
MP75L can be applied by the following methods:
1. Spray applied directly onto the Futurehouse panel and finished with ametal or plastic float2. Spray or hand applied onto a spatter coat conventional plaster and
finished as above.
3. Applied as a 3-4 mm skimcoat on top of a smooth, conventionallyplastered surface
The benefits of using MP75 are:
It can be reworked for up to 24 hours to ensure an absolutelysmooth surface.
No need for an adhesion promoting primer coat and as it is a purewhite product eliminates undercoat application.
Yellow ochre Futurehouse
Skimplast plaster finsihingcoat.
Provides a maintenance free,
long life, non cracking finish
-
7/27/2019 Futurehouse Training Manualoptimised
20/26
19.
Roofing.
Roof trusses
Conventional roof trusses can be fixed to the top of Futurehouse walls by
the following methods:
1. Directly onto the top of plastered panels. Hoop iron or tying wireis secured to and behind the wire mesh of the panels before
plastering about 150mm from the top of the panel and left
protruding from the wall until the trusses are tied down.
2-3mm thick MP75
application over over
conventional smooth finished
plaster
-
7/27/2019 Futurehouse Training Manualoptimised
21/26
20.
2. A wall plate the width of the panel can be fixed to the top of the panels beforeplastering. This is secured by wire or hoop iron tying the wall plate to the
panel wire mesh.
3. A ring beam can be cast onto the top of the panel before plastering the wall.The ring beam cage to engineers design is tied to the panel mesh and then the
beam shuttering placed to cast the ring beam. Before casting the beam the
wire or hoop iron to secure the trusses is tied to the reinforcing of the ring
beam.
Hoop iron to secure rooftrusses tied to the wire mesh
+- 150mm from the top of the
wall before plastering.
Twist hoop iron with pliers
just above panel wire so wraps
flat around the trusses.
-
7/27/2019 Futurehouse Training Manualoptimised
22/26
21.
20.
Ring beam steelwork fixed totop of Futurehouse panels
Timber ring beam shuttering
-
7/27/2019 Futurehouse Training Manualoptimised
23/26
22.
Roof trusses and gable walls
Gable walls can be made up from prime FH panels and/or panel cut outs fromdoors and windows.
Panel shapes inclusive of roof pitch lines should be marked with a straight edge
and felt tip pen and then the steel mesh cut with and angle grinder or wire
clippers along the guide lines. The EPS can be cut with a stiff saw.
Once the cut panels are placed they should be wire tied in position with +-
150mm rectangular wire mesh pieces along the join lines, inside and out.
Slots for the brandering can be cut into the EPS at the top surface of the gable
walls with a hacksaw blade or stiff bladed saw.
Timber roof trusses fixed onto
a ring beam on Futurehousewalls with brandering flush
with top of gable walls
-
7/27/2019 Futurehouse Training Manualoptimised
24/26
23.
Beam filling
Trusses and brandering can be fitted: 1) into slots cut into the Futurehousepanels, 2) rest directly onto the top of plastered walls or 3) fixed to a wall plate .
Filling the gaps between trusses can be done with FH panels cut to the size of the
openings between the trusses, the top of the wall and the underside of the roof ,
wire tied using strips of mesh to hold the cut pieces in position and plastered.
Alternatively the gap can be bricked in and plastered. It is advisable to V notch
the plaster at the interface of the brick and the FH panel to control any likely
crack formation.
Filling above wall plate and
between trusses with
conventional brickwork
V notch plaster at the interfaceof FH panels and brickwork to
control cracking
-
7/27/2019 Futurehouse Training Manualoptimised
25/26
24.
Plumbing and electrical fitting.
Plumbing and electrical conduiting must be run behind the panel wire mesh
before plastering.To open up space behind the wire mesh a blow torch should be used to partially
melt the EPS along the lines of the conduiting.
As the EPS used in the panels is fire retardant it will melt under the flame but
not burn.
The wire mesh must be cut with wire clippers to make space for DB boards,
switch and plug boxes.
It is useful to wedge and wire tie these boxes to the wire mesh to align and hold
them in place.
Plumbing (and electrical)
conduiting must be placed
behind the panel wire mesh.
To create space for theconduiting the EPS must be
melted with a blow torch
along the lines of the
conduitin .
-
7/27/2019 Futurehouse Training Manualoptimised
26/26
25.
Retrofitting of electrical and plumbing conduit.
If conduiting has to be installed after plastering the space required will need to
be cut with an angle grinder through the plaster and the wire mesh into the EPS.The EPS can be removed with a hacksaw blade or a blow torch.
The conduit is then placed into the space and held in position with nails or wire .
It is advisable to mix polypropylene fibre into the plaster mix used to finish the
wall and/or use chicken wire over the conduit to stop cracking of the plaster.
Staircase formwork
The Futurehouse panels can be used as permanent formwork for casting
concrete stairs.Place and support the FH panels at the angle required, position the stair
shuttering and then cast the concrete.
The rigidity and lightweight of the FH panels makes this a quick and easy
formwork method.
IFHS contact details: Tel: (012)6530095, Email: [email protected]
Website: www.futurehouse.co.za
October 2010
FH panels used as formwork
for a concrete staircase