fx energy 2013 reserve report for poland

Upload: stan-holland

Post on 03-Jun-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    1/105

    CAUTIONARYNOTETO INVESTORS

    Proved, Pr obable and Possibl e Reserves

    Proved (P90) reserves are estimated quantities of oil and gas that, by analysis of geoscience and

    engineering data, can be estimated with reasonable certainty to be economically producible from a given date

    forward and recoverable in future years from known reservoirs and under existing economic conditions, operating

    methods, and governmental regulations, prior to the expiration of the contracts providing the right to operate, unless

    evidence indicates that renewal is reasonably certain. Proved developed reserves are reserves that can be expected

    to be recovered through existing wells with existing equipment and operating methods, or in which the cost of the

    required equipment is relatively minor compared to the cost of a new well, and through installed extraction

    equipment and infrastructure operational at the time of the reserves estimate if the extraction is by means not

    involving a well. Proved undeveloped reserves are reserves that are expected to be recovered from new wells onundrilled acreage or from existing wells where a relatively major expenditure is required for recompletion. Proved

    undeveloped reserves on undrilled acreage are limited to: (i) those directly offsetting development spacing areas that

    are reasonably certain of production when drilled, unless evidence using reliable technology exists that establishes

    reasonable certainty of economic producibility at greater distances; and (ii) other undrilled locations if a

    development plan has been adopted indicating that they are scheduled to be drilled within five years, unless the

    specific circumstances justify a longer time.

    Probable (P50) and possible (P10) reserves are those additional reserves that are less certain to be

    recovered than proved reserves but which, together with proved reserves, are as likely as not to be recovered. Whendeterministic methods are used, it is as likely as not that actual remaining quantities recovered will exceed the sum

    of estimated proved plus probable reserves. When probabilistic methods are used, there should be at least a 50%

    probability that the actual quantities recovered will equal or exceed the P50 reserves estimates, and a 10%

    probability that the actual quantities recovered will equal or exceed the P10 reserves estimates. Probable and

    possible reserves may be assigned to areas of a reservoir adjacent to proved reserves where data control or

    interpretations of available data are less certain, even if the interpreted reservoir continuity of structure or

    productivity does not meet the reasonable certainty criterion. Probable and possible reserves may be assigned to

    areas that are structurally higher than the proved area if these areas are in communication with the proved reservoir.

    Probable and possible reserves estimates also include potential incremental quantities associated with a greater

    t f th h d b i l th d f d

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    2/105

    t f th h d b i l th d f d

    The DirectorsFX Energy Inc.3006 Highland Drive 206Salt Lake City,Utah 84106United States of America

    BNP Paribas (Suisse)Place de Hollande 2Ch-1204 GenevaSwitzerland

    ING Bank N.VBijlmerplein 8881102 MG

    AmsterdamThe Netherlands

    ECV2060

    25thFebruary 2014

    Dear Sirs,

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    3/105

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    4/105

    Qualifications

    RPS is an independent consultancy specialising in petroleum reservoir evaluation and economicanalysis. The provision of professional services has been solely on a fee basis. Mr GordonTaylor, Director, Geoscience for RPS Energy, has supervised the evaluation. Mr. Taylor attendedthe University of Birmingham and graduated with a Bachelor of Science degree in GeologicalSciences in 1978 and a Master of Science degree in Foundation Engineering in 1979. Mr. Tayloris a Chartered Geologist and Chartered Engineer in the UK and an AAPG Certified PetroleumGeologist (No 5932); he has in excess of 35 years experience in the hydrocarbon exploration andproduction industry including the conduct of evaluation studies relating to oil and gas fields. Mr.Taylor has not, directly or indirectly, received an interest, and he does not expect to receive aninterest, direct or indirect, in FX Energy, or any associate or affiliate of the company.

    M T l i Ch t d G l i t d Ch t d E i ith 30 i i

    Gas Price Royalty OPEX

    $/Mscf $/Mscf MM $ p.a.

    Grabowka 1.61 n/a n/a

    Komorze 6.37 0.043 0.140Kromolice-1 6.93 0.043 0.350

    Kromolice-South 6.93 0.043 0.350

    Lisewo 6.74 0.043 0.561

    Roszkow 7.61 0.043 0.808

    Sroda 7.29 0.043 0.358

    Szymanowice 5.95 0.043 0.140

    Winna Gora 6.94 0.043 0.486

    Zaniemysl 5.77 0.043 0.602

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    5/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    EVALUATION OF POLISH GAS ASSETS

    Prepared for

    FX Energy Incorporated

    And

    BNP P ib (S i )

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    6/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    Table of Contents

    1. EXECUTIVE SUMMARY ...........................................................................................1

    2. TECHNICAL EVALUATION ......................................................................................4

    2.1 Overview and Evaluation Methodology...........................................................4

    2.1.1 Geological Setting ...............................................................................4

    2.1.2 GIIP and Reserves Estimation Methodology .......................................5

    2.1.3 Parameter Inputs to Static GIIP Estimates ..........................................5

    2.1.4 Material Balance Calculations .............................................................8

    2.2 Zaniemysl Field ..............................................................................................9

    2.2.1 Field Description and Static GIIP Estimate..........................................9

    2.2.2 Production History ............................................................................ 10

    2.2.3 Gas Reserves Estimation ................................................................. 11

    2.3 Roszkow Field .............................................................................................. 122.3.1 Field Description and Static GIIP Estimate........................................ 12

    2.3.2 Production History ............................................................................ 13

    2.3.3 Gas Reserves Estimation ................................................................. 14

    2.4 Kromolice-Sroda Field .................................................................................. 14

    2.4.1 Field Description and Static GIIP Estimate........................................ 14

    2 4 2 P d ti Hi t 15

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    7/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    2.9.2 Gas Reserves Estimation ................................................................. 26

    2.10 Grabowka Fields .......................................................................................... 27

    2.10.1 Field Description and Static GIIP Estimate........................................ 27

    2.10.2 Production History ............................................................................ 28

    2.10.3 Gas Reserves Estimation ................................................................. 29

    3. ECONOMIC ANALYSIS .......................................................................................... 32

    3.1 Assumptions................................................................................................. 32

    3.2 Costing ......................................................................................................... 32

    3.3 Results ......................................................................................................... 33

    4. RESERVES EVOLUTION 2013-2014 ...................................................................... 35

    4.1 Proved Gas Reserves .................................................................................. 35

    4.2 Proved plus Probable Gas Reserves ............................................................ 35

    4.3 Proved plus Probable plus Possible Gas Reserves ...................................... 36

    APPENDIX 1: PRODUCTION FORECASTS AND CASHFLOW ANALYSIS FORZANIEMYSL FIELD ............................................................................... 37

    APPENDIX 2: PRODUCTION FORECASTS AND CASHFLOW ANALYSIS FORTHE ROSZKOW FIELD ......................................................................... 44

    APPENDIX 3: PRODUCTION FORECASTS AND CASHFLOW ANALYSIS FORSRODA-KROMOLICE FIELD ............................................................... 51

    APPENDIX 4: PRODUCTION FORECASTS AND CASHFLOW ANALYSIS FOR

    THE KROMOLICE SOUTH FIELD 58

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    8/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    List of Figures

    Figure 2.1: FX Energy Licence Areas ...............................................................................4

    Figure 2.2: Fences Concession: Rotliegend Gas Accumulations ......................................5

    Figure 2.3: Lisewo-1: Sw-Height Function ........................................................................7

    Figure 2.4: Zaniemysl Field: Top Rotliegend Depth Structure ........................................ 10

    Figure 2.5: Zaniemysl Production History and Forecast ................................................. 11

    Figure 2.6: Zaniemysl Pressure Match ........................................................................... 12

    Figure 2.7: Roszkow Field - Top Rotliegend Depth Structure ......................................... 13

    Figure 2.8: Roszkow Production History and Forecast ................................................... 13

    Figure 2.9: Roszkow Pressure Match ............................................................................. 14

    Figure 2.10: Kromolice-Sroda Field - Top Rotliegend Depth Structure ............................. 15

    Figure 2.11: Sroda-4 Production History and Forecast ..................................................... 16

    Figure 2.12: Kromolice-1 Production History and Forecast ............................................... 16

    Figure 2.13: Sroda - 4 Pressure Match............................................................................. 17

    Figure 2.14: Kromolice1 Pressure Match ..................................................................... 17

    Figure 2.15: Kromolice South Field: Original & Current Maps .......................................... 18

    Figure 2.16: Kromolice South Production History and Forecast ....................................... 19

    Fi 2 17 K li S th P M t h 20

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    9/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    List of Tables

    Table 1.1: Gas Reserves attributable to the FX Energy interest (MMscf), as of 31stDecember 2013 ..............................................................................................1

    Table 1.2: Reserves Changes from 1/1/2013 to 1/1/2014, 100% Basis ...........................2

    Table 1.3: Reserves Changes from 1/1/2013 to 1/1/2014, Net interest ...........................3

    Table 2.1: REP Input Parameters ...................................................................................6

    Table 2.2: Comparison of Log and volumetric Average Sw .............................................7Table 2.3: Gas Reserves (MMscf) for the Zaniemysl Field at 31st December 2013,

    100% Basis .................................................................................................. 12

    Table 2.4: Reserves (MMscf) for the Roszkow Field at 31st December 2013, 100%Basis ............................................................................................................ 14

    Table 2.5: Gas Reserves (MMscf) for the Kromolice - Sroda Field at 31st December2013 100% Basis ......................................................................................... 18

    Table 2.6: Gas Reserves (MMscf) for the Kromolice South Field at 31st December2013, (100% basis) ...................................................................................... 20

    Table 2.7: Reserves (MMscf) for the Winna Gora Field at 31st December 2013100% Basis .................................................................................................. 22

    Table 2.8: Gas Reserves (MMscf) for the Lisewo Field at 31st December 2013 100%Basis ............................................................................................................ 23

    Table 2.9: Gas Reserves (MMscf) for Komorze Field at 31st December 2013 100%B i 25

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    10/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    1. EXECUTIVE SUMMARY

    RPS Energy has performed a technical and economic evaluation of FX Energys assets in

    Poland. This is an update of a similar evaluation performed by RPS Energy at the end of2012 but accommodating changes that have occurred during 2013.Principally these includeadditional production from the Zaniemysl, Roszkow, Kromolice-Sroda, Kromolice South,Winna Gora, Lisewo and Grabowka fields, and the new discovery Szymanowice. 2013pressure surveys in Zaniemysl, Roszkow, and Kromolice-Sroda provide further data forevaluating GIIP estimates for these fields.

    All producing fields and new discoveries were evaluated, including Komorze-3 andSzymanowice. Revised product prices and operating and development costs have been

    included in determining asset values as of 31st December 2013.

    Our evaluation of Remaining Reserves at 31stDecember 2013 is given inTable 1.1.

    Field

    Proved Proved +

    Probable

    Proved + Probable +

    Possible Proved

    Proved +

    Probable

    Proved + Probable +

    Possible

    Grabowka 100.0% 292 1,168 2,081

    Zaniemysl 24.5% 793 1,454 2,179Roszkow 49.0% 4,789 6,539 11,272

    Sroda-Kromolice 49.0% 12,099 16,878 26,325

    Kromolice South 49.0% 1,551 2,629 3,982

    Winna Gora 49.0% 4,075 6,869 11,208

    Lisewo 49.0% 12,079 19,723 31,620

    Komorze 49.0% 2,385 4,135 6,878

    Szymanowice 49.0% 3,947 7,275 12,984

    Total 41,219 65,216 106,350 793 1,454 2,179

    FX Energy Gas Reserves (MMscf)

    UndevelopedFX Energy

    Interest

    Developed

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    11/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    ECV 2060 2 February 2014

    Table 1.2: Reserves Changes from 1/1/2013 to 1/1/2014, 100% Basis

    Reserves at 1/1/2013 Production Additions Revisions Reserves at 1/1/2014

    Zaniemysl Proved 4,512 370 (904) 3,238

    Proved + Probable 9,161 370 (2,858) 5,933Proved + Probable + Possible 14,545 370 (5,281) 8,895

    Sroda-Kromolice Proved 26,152 2,838 1 ,379 24,693

    Proved + Probable 45,440 2,838 (8,157) 34,445

    Proved + Probable + Possible 55,255 2,838 1 ,309 53,725

    Winna Gora Proved 10,324 643 (1,363) 8,317

    Proved + Probable 17,009 643 (2,347) 14,018

    Proved + Probable + Possible 27,495 643 (3,979) 22,873

    Roszkow Proved 13,420 3,262 384- 9,773

    Proved + Probable 16,984 3,262 (378) 13,345

    Proved + Probable + Possible 31,761 3,262 (5,495) 23,004

    Grabowka Proved 1,413 99 (1,022) 292

    Proved + Probable 7,569 99 (6,302) 1,168Proved + Probable + Possible 19,724 99 (17,545) 2,081

    Kromolice South Proved 3,775 1,245 636 3,166

    Proved + Probable 5,015 1,245 1,594 5,365

    Proved + Probable + Possible 9,421 1,245 (48) 8,128

    Lisewo Proved 26,512 88 (1,772) 24,652

    Proved + Probable 43,158 88 (2,818) 40,252

    Proved + Probable + Possible 69,200 88 (4,581) 64,532

    Komorze Proved 4,721 - 147 4,868

    Proved + Probable 7,153 - 1,286 8,439

    Proved + Probable + Possible 11,146 - 2,891 14,037

    Szymanowice Proved - - 8,055 - 8,055

    Proved + Probable - - 14,847 - 14,847Proved + Probable + Possible - - 26,497 - 26,497

    Totals Proved 90,828 8,545 8,055 (3,285) 87,054

    Proved + Probable 151,489 8,545 14,847 (19,980) 137,812

    Proved + Probable + Possible 238,548 8,545 26,497 (32,730) 223,770

    FX -ENERGY: POLISH INTEREST

    RESERVE CHANGES FROM 1/1/2013 TO 1/1/2014

    100 % INTEREST

    GAS (MMSCF)

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    12/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    ECV 2060 3 February 2014

    Table 1.3: Reserves Changes from 1/1/2013 to 1/1/2014, Net interest

    Reserves Production Additions Revisions Reserves

    at 1/1/2013 at 1/1/2014

    Zaniemysl Proved 1,105 91 (221) 793

    Probable 1,139 - - (479) 660

    Proved + Probable 2,244 91 (700) 1,454

    Proved + Probable + Possible 3,564 91 (1,294) 2,179

    Sroda-Kromolice Proved 12,815 1,391 676 12,099

    Probable 9,451 - - (4,673) 4,778

    Proved + Probable 22,266 1,391 (3,997) 16,878

    Proved + Probable + Possible 27,075 1,391 641 26,325

    Winna Gora Proved 5,059 315 (668) 4,075

    Probable 3,276 - - (482) 2,794

    Proved + Probable 8,334 315 (1,150) 6,869

    Proved + Probable + Possible 13,473 315 (1,950) 11,208

    Roszkow Proved 6,576 1,598 188- 4,789

    Probable 1,747 - - 3 1,750

    Proved + Probable 8,322 1,598 (185) 6,539

    Proved + Probable + Possible 15,563 1,598 (2,693) 11,272

    Grabowka Proved 1,413 99 (1,022) 292

    Probable 6,156 - - (5,280) 876

    Proved + Probable 7,569 99 (6,302) 1,168

    Proved + Probable + Possible 19,724 99 (17,545) 2,081

    Kromolice South Proved 1,850 610 311 1,551

    Probable 608 - - 470 1,077

    Proved + Probable 2,458 610 781 2,629

    Proved + Probable + Possible 4,616 610 (24) 3,982

    Lisewo Proved 12,991 43 (868) 12,079

    Probable 8,157 - - (513) 7,644

    Proved + Probable 21,148 43 (1,381) 19,723

    Proved + Probable + Possible 33,908 43 (2,245) 31,620

    Komorze Proved 2,313 - 72 2,385

    Probable 1,192 - 558 1,750

    Proved + Probable 3,505 - 630 4,135

    Proved + Probable + Possible 5,462 - 1,417 6,878

    Szymanowice Proved - - 3,947 - 3,947

    Probable - - 3,328 - 3,328

    Proved + Probable - - 7,275 - 7,275Proved + Probable + Possible - - 12,984 - 12,984

    Totals Proved 44,121 4,147 3,947 (1,909) 42,012

    Probable 31,724 - 3,328 (10,395) 24,658

    Proved + Probable 75,845 4,147 7,275 (12,304) 66,670

    Proved + Probable + Possible 123,384 4,147 12,984 (23,692) 108,529

    FX -ENERGY: POLISH INTEREST

    RESERVE CHANGES FROM 1/1/2013 TO 1/1/2014

    NET INTEREST

    GAS (MMSCF)

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    13/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    2. TECHNICAL EVALUATION

    2.1 Overview and Evaluation Methodology

    2.1.1 Geological Setting

    The Zaniemysl, Roszkow, Winna Gora, Kromolice-Sroda, Kromolice South, Lisewo, Komorzeand Szymanowice gas accumulations are located in the Fences concession area (Figure2.1)where the Rotliegend sandstone is the reservoir unit; the Grabowka fields are located25km to the southwest in Block 287, in Zechstein dolomites and limestones.

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    14/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    Figure 2.2: Fences Concession: Rotliegend Gas Accumulations

    2.1.2 GIIP and Reserves Estimation Methodology

    RPS has reviewed all aspects of the geology, geophysics, petrophysics and structuralmapping of each accumulation in order to define a range of input parameters for aprobabilistic (static) calculation of GIIP.

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    15/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    ECV 2003 6 February 2014

    FIELD DIMENSIONS REP INPUT PARAMETERS REP OUTPUT

    Name ReservoirSegmen

    tArea(km2)

    Vert.Relief(m)

    Area Uncertainty (%) Gas-Water-Contact (m TVDSS) Net-to-gross (%) Porosity (%) Sw (%) FVF (1/Bg) GIIP (bcf)

    Distr. P90 P50 P10 Distr. P90 P50 P10 Distr. P90 P50 P10 Distr. P90 P50 P10 Distr. P90 P50 P10Sw

    Vol AvDistr. P90 P50 P10 P90 P50 P10 Mean P10:P90

    Grabowka

    Zechstein West 3.9 50 N 85 100 115 Single 1565 1565 1565 Single 100.0 100.0 100.0 TR 1.0 4.3 7.0 TR 20.0 43.3 70.0 48.3 TR 150 152 154 3.6 12.6 25.2 13.6 7.00

    Zechstein East 1.9 45 N 85 100 115 Single 1550 1550 1550 Single 100.0 100.0 100.0 TR 3.0 5.0 7.0 TR 20.0 43.3 70.0 47.8 TR 141 143 145 1.0 2.2 3.9 2.4 3.90

    4.6 14.8 29.1 16.0 6.33

    Zaniemysl Rotliegend 2.8 54 LN 70 102 150 Single 2889 2889 2889 Single 1000 1000 1000 N 19.0 21.0 23.0 Single 41.0 41.0 41.0 41.0 N 259 262 265 29.8 44.9 68.1 30.3 2.29

    Roszkow Rotliegend 2.4 47 LN 70 102 150 N 2826 2829 2832 Single 100.0 100.0 100.0 N 17.0 20.0 23.0 Sw-Height Function 52.3 N 259 262 265 30.2 46.6 71.9 49.2 2.38

    KromoliceSroda

    Rotliegend Kr-1 4.3 55 LN 80 110 150 N 3518 3521 3525 N 80.0 84.0 88.0 N 12.0 15.0 18.0 Sw-Height Function 54.6 N 252 257 262 30.5 46.1 69.4 48.4 2.28

    RotliegendCentralHorst

    1.1 43 LN 80 110 150 N 3518 3521 3525 N 80.0 90.0 100.0 N 12.0 17.0 22.0 Sw-Height Function 57.4 N 252 257 262 7.4 12.3 19.7 13.1 2.65

    Rotliegend Sr-4 1.4 53 LN 80 110 150 N 3518 3521 3525 N 95.0 97.3 99.6 N 15.0 18.5 22.0 Sw-Height Function 59.9 N 252 257 262 19.9 29.4 43.6 30.8 2.19

    RotliegendSr-4North

    0.7 13 LN 80 110 150 N 3518 3521 3525 N 95.0 97.3 99.6 N 15.0 18.5 22.0 Sw-Height Function 65.8 N 252 257 262 2.5 4.2 7.0 4.5 2.87

    60.3 92.0 139.7 96.8 2.32

    KromoliceSouth

    Rotliegend 1.0 41 LN 80 110 150 Single 3496 3496 3496 N 88.0 93.7 99.4 N 11.0 14.0 16.9 Sw-Height Function 57.2 N 252 257 262 5.1 7.6 11.3 8.0 2.22

    WinnaGora

    Rotliegend 1.1 64 LN 80 110 150 Single 3486 3486 3486 Single 100.0 100.0 100.0 N 14.0 16.0 18.0 Sw-Height Function 44.6 N 259 262 265 16.1 22.7 32.1 23.5 1.99

    Lisewo Rotliegend 2.3 87 LN 80 110 150 Single 3637 3637 3637 N 94.0 97.0 100.0 N 13.0 14.5 16.0 Sw-Height Function 42.0 Single 252 252 252 44.1 61.5 86.3 63.6 1.96

    Komorze Rotliegend 1.5 75 LN 80 110 150 Single 3760 3760 3760 N 78.0 83.0 88.0 N 13.0 15.0 17.0 Sw-Height Function 61.4 N 252 257 262 10.7 15.3 21.8 15.9 2.04

    Szymanowice

    Rotliegend

    (lowporosity

    1.8 87 LN 55.3 78 110 N 3604 3607 3610 N 24.0 52.0 80.0 N 7.0 11.0 15.0 Sw-Height Function 53.2 N 225 230 235

    17.8 26.9 40.9 21.6 2.42Rotliegend

    (highporosity

    1.8 87 LN 55.3 78 110 N 3604 3607 3610 N 95.0 97.0 99.0 N 14.0 16.0 18.0 Sw-Height Function 63.3 N 225 230 235

    Table 2.1: REP Input Parameters

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    16/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    Sw Parameters

    A review of log data suggests that the previous use of a range of Sw values centred on theaverage well Sw from the pay interval is not a true reflection of the volumetric average valueof Sw. The reservoir interval in most of the fields has a distinctive Sw-Height profile due tolow structural relief and moderate permeability. In such cases, a Sw-Height function shouldbe used in REP to ensure that the varying Sw is correctly weighted in a volumetric sense.

    RPS has undertaken a review of the log data from Kromolice-1, Lisewo-1, and Komorze-3. ASw-Height function has been derived from Lisewo-1 (Figure 2.3)which closely matches theSw log profiles in Kromolice-1 and Komorze-3 when using the deepest GWC in each well.These generic Sw-Height functions are also considered to be representative of the Sw log

    profiles in Sroda-4, Roszkow-1, Winna Gora-1 and Kromolice South. Another height functionhas been derived from the Szymanowice-1 well, and provides a volumetrically representativeSw profile for the Szymanowice field. Sw-Height functions have been used in REP inpreference to Sw distributions on all fields, with the exception of Zaniemysl (see Section2.3.1 below).The volume averaged Sw values associated with Sw-Height function and thecorresponding log calculated Sws are shown inTable 2.2.

    FIELD/WELL Sw COMPARISON

    Vol Av. Sw-Height Fn. Log Calculation

    Roszkow 52.3 39.9

    Kr-1 54.6 42.0

    Sr-4 59.9 51.3

    Kr-2 57.2 41.0

    Winna Gora 44.6 47.5

    Lisewo 42.0 45.0

    K 61 4 47 0

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    17/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    GRV Parameters

    The use of a Sw-Height function in REP requires GRV input in the form of area-depth pairs,rather than the previous three parameter GRV distributions. As noted above, volumetricestimates are sensitive to the velocity model used for depth conversion, and GRV uncertaintyin REP can be captured by inputting an area uncertainty distribution.

    Previous RPS work has evaluated the volumetric uncertainty resulting from different velocitymodels, particularly over the Kromolice-Sroda field. A review of this work demonstrates thatGRV uncertainty can be modelled by a log-normal area distribution (P90 80% P10 150%,see Table 2.1). This distribution has been used for all fields mapped on 3D seismic data,where the volumetric uncertainty is primarily velocity-related; for fields mapped on 2D

    seismic data (Zaniemysl and Roszkow) the P90 value is reduced to account for additionalmapping uncertainty.

    2.1.4 Material Balance Calculations

    Based on the available data by field (PVT, well test and production history data) we haveused a material balance program (Mbal) to get the producing estimation of Gas in place(GIIP) and compare it with the volumetric GIIP results using traditional p/z analysistechniques. The Mbal program was also used to predict the future reservoir performance and

    well production forecast for a given production schedule and matched well inflow and liftperformance where available. FX Energy has also specified some reservoir managementrate constraints, as advised by Operator, for the forecast by field.

    RPS has created various cases based on either single or multiple tanks with transmissibilityconnections between the tanks to reflect potential compartmentalization or later contributionfrom tight pay. These models were used to establish a range of scenarios which aresummarized below for the producing fields:

    P90 minimum case- generally based on the P90 volumetric GIIP or less where the p/zd t d t t d ll t d GIIP I if i fl d ll d

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    18/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    require the inclusion of compression at some stage in a number of the fields to gain entry tothe main export pipeline operating at c.900 psi. The tubing curves should allow the impact ofany future water production to be modelled. A number of the forecast profiles terminate

    relatively rapidly as a result of water loading in the tubing.

    For those models with aquifers, the gas leg pore volume water influx was modelled using theassumption of vertical equilibrium, where the gas-water contact will rise uniformly across thefield and water production would commence when it is at the bottom perforation. Thisattempts to model the encroachment of potential aquifer water to the gas leg and allows Mbalto reflect the impact of water production on the lift curves. It is anticipated this will provide auseful history matching tool in the event of more of the fields starting to produce water in thefuture.

    Well performances were forecast including the production and downtime constraintsspecified by FX Energy. The models will allow for better integration of the future flowing wellperformance data and any WGR trends. Individual well target rates are as follows:

    Zaniemysl 3: Well on production 1/1/2015 after sidetrack at initial rate of 2.2MMscf/d.

    Sroda 4: 2.5 MMscf/d.

    Kromolice 1: 5.4 MMscf/d.Kromolice 2: 3.2 MMscf/d.

    Roszkow: 7.6 MMscf/d.

    Winna Gora: 2.1 MMscf/d.

    Lisewo 1: 5.4 MMscf/d.

    Lisewo 2: 3.5 MMscf/d from 1/10/2014 when placed on production.

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    19/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    Figure 2.4: Zaniemysl Field: Top Rotliegend Depth Structure

    Zaniemysl-3 was drilled in a near-crestal location and encountered a 38m gas column with aclear GWC at -2888.8m TVDSS. Zaniemysl is the only Rotliegend field where the genericSw-Height function does not reasonably model the log Sw profile, and so for volumetricestimates a single value Sw of 41% (from the Operators field report) was used.The current

    G 2 1

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    20/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    0

    40

    80

    120

    160

    200

    0

    4

    8

    12

    16

    20

    Oct-06

    Feb-07

    Jun-07

    Oct-07

    Feb-08

    Jun-08

    Oct-08

    Feb-09

    Jun-09

    Oct-09

    Feb-10

    Jun-10

    Oct-10

    Feb-11

    Jun-11

    Oct-11

    Feb-12

    Jun-12

    Oct-12

    Feb-13

    Jun-13

    Oct-13

    WGR(bbl/MMscf)

    Ga

    srate(MMscfd)

    Zaniemysl Production data

    Daily prod. WGR

    2000

    2500

    3000

    3500

    2.0

    2.5

    3.0

    3.5

    (MMscfd)

    Z3ST Production data

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    21/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    Figure 2.6: Zaniemysl Pressure Match

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    22/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    Figure 2.7: Roszkow Field - Top Rotliegend Depth Structure

    Roszkow-1 is located down flank from the crest of the structure and encountered a 29.5mgas column to a depth of -2825.8m TVDSS, with a possible deeper contact (WUT) at -2831.9m TVDSS. A range of possible GWCs has been used in the volumetric assessment.The current Volumetric GIIP estimates are given in Table 2.1.

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    23/105

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    24/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    conversion uncertainties, this is still feasible, though the possibility of separate and hencedisconnected closures cannot be dismissed.

    As a result of RPS investigation of the Sw-Height issue, a potentially deeper GWC has beenrecognized in Kromolice-1 (-3540.1m TVDSS). It is difficult to reconcile this with the spillpoints on the current mapping, or on earlier versions of the Top Rotliegend depth map.However, a potentially deeper spill to -3525m TVDSS could be accommodated on thecurrent mapping and this has been used to provide a depth range for GWC uncertainty.

    For this exercise, GIIP has been estimated for each anticlinal segment, and the P90 P50 andP10 values summed arithmetically (seeTable 2.1) to give a total GIIP range for the entirefield.Table 2.1 shows the GIIP by individual segments.

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    25/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    Figure 2.11: Sroda-4 Production History and Forecast

    Kromolice-1

    Production started in June 2011, produced intermittently until October 2011, and has beenon continuous production since that time; seeFigure 2.12.

    In 2013 the well commenced producing at a rate of 6.7MMscf/d to mid-August when the ratewas reduced to 5.4MMscf/d in response to an increase in produced water salinity. However,water production has remained at condensed water levels, < 2Bbls/MMscf, through to end of

    0

    1000

    2000

    3000

    4000

    5000

    0

    1

    2

    3

    4

    5

    Dec-10

    Dec-13

    Dec-16

    Dec-19

    Dec-22

    Dec-25

    Dec-28

    Dec-31

    Dec-34

    Dec-37

    Dec-40

    Dec-43

    Dec-46

    Dec-49

    Dec-52

    Dec-55

    Dec-58

    WHP(Psia)

    Gasrate(MMscfd)

    Sroda 4 Production data

    Daily prod. P90 Prediction P50 Prediction P10 Prediction FWHP P50 Prediction FWHP

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    26/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    Figure 2.13: Sroda - 4 Pressure Match

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    27/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    The recovery factor derived from the P50 Mbal model is 48% of volumetric GIIP. Figure 2.13andFigure 2.14 show the Pressure Match for the Mbal analysis. The remaining gas reservesas of 31st December 2013 for this field, based on the existing wells are summarized inTable

    2.5.The gas production forecasts are shown inFigure 2.11 andFigure 2.12 and in Appendix3.

    Table 2.5: Gas Reserves (MMscf) for the Kromolice - Sroda Field at 31st December 2013100% Basis

    2.5 Kromolice South Field

    2.5.1 Field Description and Static GIIP Estimate

    The Kromolice South structure was tested by the Kromolice-2 well. The well was located in a

    near-crestal location and encountered a 35m gas column with a clear GWC identified at -3496m TVDSS.

    RPS evaluation of Kromolice South is based on the current Top Rotliegend depth map(Figure 2.15). The current Volumetric GIIP estimates are given Table 2.1.

    Remaining Reserves (MMscf) Evaluation Production Remaining Economic Limit Evaluation

    1stJan 2013 during 2013 31stDec 2013 in year 1stJan 2013

    Proven 26,152 2,838 23,314 2031 24,693

    Proven+Probable 45,440 2,838 42,602 2090 34,445

    Proven+Probable+Possible 55,255 2,838 52,416 2090 53,725

    2013 2014

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    28/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    2.5.2 Production History

    The Kromolice South field was brought on production on July 6th 2011 (Figure 2.16). In 2013the well commenced production at 3.5 MMscf/d to early Sept when the rate was reduced to

    3.2 MMscf/d in response to an increase in produced water salinity. Observation oftubing/casing annulus pressure indicated a leak to tubing of high salinity annulus fluid. Aworkover is scheduled to repair the tubing leak in 2014. However, water production hasremained at condensed water levels, < 2Bbls/MMscf, through to end December. The well hasa total gas cumulative production of 2.38 Bscf at 31stDecember 2013.

    0

    1000

    2000

    3000

    4000

    5000

    0

    1

    2

    3

    4

    5

    Jul-11

    Mar-12

    Nov-12

    Jul-13

    Mar-14

    Nov-14

    Jul-15

    Mar-16

    Nov-16

    Jul-17

    Mar-18

    Nov-18

    Jul-19

    Mar-20

    Nov-20

    Jul-21

    Mar-22

    Nov-22

    Jul-23

    Mar-24

    Nov-24

    Jul-25

    WHP(Psia)

    Gas

    rate(MMscfd)

    Kromolice South Production data

    Daily prod. P90 Prediction P50 Prediction P10 Prediction FWHP P50 Prediction FWHP

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    29/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    Figure 2.17: Kromolice South Pressure Match

    2013 2014

    Remaining Reserves (MMscf) Evaluation Production Remaining Economic Limit Evaluation

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    30/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    Figure 2.18: Winna Gora: Top Rotliegend Depth Structure

    The current Volumetric GIIP estimates are given in Table 2.1.

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    31/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    2.6.3 Gas Reserves Estimation

    The first static pressure measurement was carried out in Winna Gora in June 2013; it wasincluded in the Mbal model to establish the dynamic GIIP. However, it is too early to establish

    the trend from p/z plot. No aquifer has been included in the Mbal model analysis for this field.The Winna Gora forecast estimated a recovery factor of 71% of the volumetric GIIP for theP50 case.

    The remaining gas Reserves, at 31st December 2013 for this field are summarized inTable2.7.The gas production forecasts are shown inFigure 2.19 and in Appendix 5.

    Table 2.7: Reserves (MMscf) for the Winna Gora Field at 31st December 2013 100% Basis

    2.7 Lisewo Field

    2.7.1 Field Description and Static GIIP Estimate

    Lisewo-1 was drilled as a deviated well to a TD of 3946m MD in late January 2011 to test afault and dip controlled anticlinal structure mapped at Top Rotliegend. The well encounteredthe Top Rotliegend sands at 3814m MD, and a gross, gas-bearing Rotliegend interval of69m. The current depth map is shown inFigure 2.20.

    A second well Lisewo-2 was drilled last year which was tested. No pressure gauges were runbut a final gradient survey was made at end of clean up. Preliminary results from the Lisewo-

    Remaining Reserves (MMscf) Evaluation Production Remaining Economic Limit Evaluation

    1st

    Jan 2013 during 2013 31st

    Dec 2013 in year 1st

    Jan 2014Proven 10,324 643.4 9,680 2043 8,317

    Proven+Probable 17,009 643.4 16,365 2062 14,018

    Proven+Probable+Possible 27,495 643.4 26,852 2090 22,873

    2013 2014

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    32/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    Log analysis indicates possible GWCs at either -3617.5m TVDSS or -3636.7m TVDSS.Previous evaluations have favoured the deeper contact, as it coincides with the spill point onone of the main controlling faults (Fault A), and in the absence of additional data, the deeper

    contact has been retained in this years GIIP estimate.The current Volumetric GIIP estimatesare given in Table 2.1.

    2.7.2 Production History

    Lisewo 1 commenced production in Dec 2013. The average rate for the month was 4.2MMscf/d. Water production has remained at condensed water levels, < 2Bbls/MMscf, at endyear. The well has a total gas cumulative production of 88.1 MMscf at 31 stDecember 2013.Figure 2.17 shows the Production Forecast.

    0

    1250

    2500

    3750

    5000

    0

    3

    5

    8

    10

    Dec-13

    Dec-14

    Dec-15

    Dec-16

    Dec-17

    Dec-18

    Dec-19

    Dec-20

    Dec-21

    Dec-22

    Dec-23

    Dec-24

    Dec-25

    Dec-26

    Dec-27

    Dec-28

    Dec-29

    Dec-30

    Dec-31

    Dec-32

    Dec-33

    Dec-34

    Dec-35

    WHP(Psia)

    Gasrate(MMscfd)

    Lisewo Production data

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    33/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    TVDSS. RPS analysis of the log data indicates a likely GWC at -3751.4m TVDSS, but with apossible deeper contact at -3759.6m TVDSS.

    RPS generated two alternative depth maps for comparison:

    Residual correction applied (gridded) to pre-drill depth structure map

    Update of RPS 2-layer model with additional velocity control (a simplified version of theOperators 11-layer velocity model developed from a previous evaluation of the Lisewoarea)

    The resulting depth maps are similar and generate identical GIIP distributions. The depthmap from the 2-layer model is shown inFigure 2.22.

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    34/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    Table 2.9: Gas Reserves (MMscf) for Komorze Field at 31st December 2013 100% Basis

    Remaining Reserves (MMscf) Evaluation Economic Limit Evaluation

    1stJan 2013 in year 1stJan 2014

    Proven 4,721 2029 4,868Proven+Probable 7,153 2047 8,439

    Proven+Probable+Possible 11,146 2085 14,037

    20142013

    0

    500

    1000

    1500

    2000

    2500

    0.00

    0.50

    1.00

    1.50

    2.00

    2.50

    Jan-14

    Jan-17

    Jan-20

    Jan-23

    Jan-26

    Jan-29

    Jan-32

    Jan-35

    Jan-38

    Jan-41

    Jan-44

    Jan-47

    Jan-50

    Jan-53

    Jan-56

    Jan-59

    Jan-62

    Jan-65

    Jan-68

    Jan-71

    Jan-74

    Jan-77

    Jan-80

    Jan-83

    Jan-86

    WHP(Psia)

    Gasrate(MMscfd)

    Komorze Production data

    Daily prod. P90 Prediction P50 Prediction P10 Prediction P50 Prediction FWHP

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    35/105

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    36/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    P10 GIIPsbecause of the relatively low relief structure. The forecast assumption for the P10case considers an extra well, which would be on stream in 2018 producing at the same rate1.3 MMscf/d to accelerate the production.

    Figure 2.25: Szymanowice Production Forecast

    The total Szymanowice Gas Reserves are summarised in Table 2.10. The gas productionforecasts are shown in Error! Reference source not found.and in Appendix 8.

    0

    500

    1000

    1500

    2000

    2500

    0.00

    0.50

    1.00

    1.50

    2.00

    2.50

    Dec-15

    Dec-17

    Dec-19

    Dec-21

    Dec-23

    Dec-25

    Dec-27

    Dec-29

    Dec-31

    Dec-33

    Dec-35

    Dec-37

    Dec-39

    Dec-41

    Dec-43

    Dec-45

    Dec-47

    Dec-49

    Dec-51

    Dec-53

    Dec-55

    Dec-57

    Dec-59

    Dec-61

    Dec-63

    Dec-65

    Dec-67

    Dec-69

    WHP(Psia)

    Gasrate(MMscfd)

    Szymanowice Production data

    P90 Prediction P50 Prediction P10 Prediction P50 Prediction FWHP

    P10 case , considering an

    extra well in 2018

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    37/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    Figure 2.26: Grabowka Fields: Zechstein Ca1 Depth Structure

    Due to poor quality log data, a GWC could not be determined for either field. In GrabowkaWest, structural spill is estimated at 1565m TVDSS, consistent with test data from the G-5and G-7 wells. Similarly, on Grabowka East, a structural spill point of 1550m TVDSS isestimated from mapping rather than from log analysis.

    No changes to previous years GIIP estimates have been evaluated which are given in Table2.1. Most of the volume is located in the Grabowka West structure which commencedproduction in 2013 from G-6. The initial production results from G-6 and G-8 suggest asignificant reduction in Grabowka Reserves and a preliminary examination of the prior

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    38/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    Figure 2.27: Grabowka Fields - Production Data

    0

    500

    1000

    1500

    2000

    0.0

    0.5

    1.0

    1.5

    2.0

    Jul-09

    Sep-09

    Nov-09

    Jan-10

    Mar-10

    May-10

    Jul-10

    Sep-10

    Nov-10

    Jan-11

    Mar-11

    May-11

    Jul-11

    Sep-11

    Nov-11

    Jan-12

    Mar-12

    May-12

    Jul-12

    Sep-12

    Nov-12

    Jan-13

    Mar-13

    May-13

    Jul-13

    Sep-13

    Nov-13

    WGR(bbl/MMscf)/WHP(Ps

    ia)

    G

    asrate(MMscfd)

    Grabowka Production data

    Daily prod. FWHP WGR

    25002.5

    Grabowka Production data (Forecast)

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    39/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    assumption, NTG and possibly the level of the GWC, all contributing to a significantly smallerGIIP.

    y = -40x + 2501.50

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    4500

    010

    20

    30

    40

    50

    60

    70

    P/z(psia)

    Gp (MMscf)

    Flowing Material Balance Grabowka

    Pi/Zi

    Flowing P/z

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    40/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    Figure 2.30: Grabowka Fields Flowing Material Balance

    0.000

    0.001

    0.001

    0.002

    0.002

    0.0

    5.0

    10.0

    15.0

    20.0

    25.0

    30.0

    35.0

    Productivit

    yIndex

    Gp (mmscf)

    Flowing Material Balance Grabowka-6

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    41/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    3. ECONOMIC ANALYSIS

    3.1 Assumptions

    An economic analysis of the Polish Assets of FX Energy was undertaken based on thefollowing price and royalty assumptions (seeTable 3.1). These data have been supplied byFX Energy in US Dollars and are based on Polish Zloty gas prices and exchange rates,taken as the average of the 1stday of the month values throughout 2013.

    Notes:1. FX receives $1.61 for gas produced but incurs no costs. For the purpose of forecasting the

    economic limit, FX advises that it believes that the field's operator receives a price $6.50/ Mscf (netof royalty) and incurs annual opex of $0.300 MM.

    2. Opex value excludes an assumed additional $1.20 MM workover to occur in 2014.3. Opex is for all years after 2014; in 2014 it is assumed to be $0.456 MM.4. Opex is for all years after 2015; in 2015 it is assumed to be $0.129 MM.

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    42/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    Roszkow For all three volumetric cases (i.e., the Proved, Proved plus Probable, andProved plus Probable plus Possible), compression capex of US $1.45 MM has beenassumed to be incurred in 2014.

    Szymanowice In all three volumetric cases, a $2.70 MM cost to tie-in to the Lisewofacilities is assumed to be incurred in 2014. In the Proved plus Probable plus Possiblecase, costs of $9.00 MM for a second well and $2.00 MM for a tie-in are assumed to beincurred in 2018. Compression costs of $3.00 MM are assumed to be incurred 2018 inthe Proved case, and in 2021 in the Proved plus Probable and Proved plus Probable plusPossible cases.

    Winna GoraFor all three volumetric cases, compression capex of US $3.50 MM hasbeen assumed, to be incurred in 2016 in the Proved case, in 2019 in the Proved plusProbable case, and in 2022 in the Proved plus Probable plus Possible case,

    Zaniemysl Sidetrack costs of $3.60 MM are assumed to be incurred in 2014. Nocompression is assumed to be required at Zaniemysl due to pressure maintenance fromwater influx.

    Operating and Abandonment Costs

    Normal operating costs per well have been provided for all the fields and are tabulated in

    Table 3.1.In addition to basic operating costs, there is an additional $0.015/mcf additional compressionopex per license, once compression is required.

    Assumed abandonment costs of 0.385 MM per well and $0.250 MM per facility have beenprovided by FX Energy.

    3.3 Results

    The results of our analysis are shown below inTable 3.2. The Net Present Values are stated

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    43/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    Table 3.3: Effect of Gas Price Sensitivities on FX Net Reserves (MMscf)

    Table 3.4: Effect of Gas Price Sensitivities on NPV10 (Net to FX Energy) in Million USD

    1P 2P 3P 1P 2P 3P 1P 2P 3P

    Roszkow 4,789 6,483 11,047 4,789 6,539 11,272 4,842 6,590 11,272

    Winna Gora 4,002 6,757 11,131 4,075 6,869 11,208 4,141 7,003 11,208

    Kromolice South 1,551 2,629 3,982 1,551 2,629 3,982 1,551 2,629 4,006Zaniemysl 793 1,454 2,177 793 1,454 2,177 793 1,454 2,177

    Sroda-Kromolice 12,099 16,878 26,325 12,099 16,878 26,325 12,123 16,878 26,325

    Grabowka 292 1,168 2,081 292 1,168 2,081 292 1,168 2,081

    Lisewo 12,079 19,723 31,620 12,079 19,723 31,620 12,079 19,723 31,620

    Komorze 2,385 4,135 6,878 2,385 4,135 6,878 2,385 4,135 6,878

    Szymanowice 3,947 7,275 12,984 3,947 7,275 12,984 3,947 7,275 12,984

    Total 41,939 66,502 108,225 42,012 66,670 108,527 42,154 66,855 108,551

    FieldsNet Reserves 90% Price Net Reserves 110% PriceNet Reserves Base Price

    1P 2P 3P 1P 2P 3P 1P 2P 3P

    Roszkow 21.67 27.01 34.05 24.55 30.57 38.48 27.44 34.13 42.92

    Winna Gora 9.45 13.39 16.64 10.95 15.30 18.89 12.45 17.21 21.13

    Kromolice South 7.03 11.12 14.56 7.97 12.57 16.45 8.91 14.02 18.35

    Zaniemysl 1.48 3.05 4.22 1.83 3.59 4.91 2.17 4.13 5.60Sroda-Kromolice 43.44 46.94 56.09 48.89 52.83 63.01 54.35 58.72 69.94

    Grabowka 0.41 1.30 1.87 0.41 1.30 1.87 0.41 1.30 1.87

    Lisewo 38.24 52.72 66.35 43.30 59.38 74.49 48.36 66.04 82.64

    Komorze 6.00 7.81 9.13 6.89 8.89 10.35 7.77 9.98 11.57

    Szymanowice 5.11 7.03 10 6.02 8.13 12.08 6.93 9.23 13.94

    Total 132.83 170.37 213.13 150.81 192.56 240.53 168.79 214.76 267.96

    FieldsNPV10 110% PriceNPV10 Base PriceNPV10 90% Price

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    44/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    4. RESERVES EVOLUTION 2013-2014

    4.1 Proved Gas Reserves

    Table 4.1: Gas Proved Reserves (MMscf) 100% Basis

    Table 4.1 shows the Proved Reserves evolution. In general there are modest reserveschanges (+/- 10-20 %) apart from Grabowka. The inclusion of reserves for the new discoverySzymanowice gives an additional reserves of 8.1 Bscf leading to a net 4.8 Bscf, a 6 %increase in the 2014 evaluation, after 2013 production.

    2014Field Evaluation Production Remaining Evaluation MMscf (%)

    01-Jan-13 during 2013 31-Dec-13 01-Jan-14

    Zaniemysl 4,512 370 4,142 3,238 -904 -22%

    Sroda-Kromolice 26,152 2,838 23,314 24,693 1,379 6%

    Roszkow 13,420 3,262 10,158 9,773 -384 -4%

    Winna Gora 10,324 643 9,680 8,317 -1,363 -14%

    Kromolice South 3,775 1,245 2,530 3,166 636 25%

    Grabowka 1,413 99 1,314 292 -1,022 -78%

    Lisewo 26,512 88 26,424 24,652 -1,772 -7%

    Komorze 4,721 0 4,721 4,868 147 3%

    Szymanowice 8,055 8,055 0%

    Total 90,828 8,545 82,283 87,054 4,771 6%

    2013 Variation

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    45/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    4.3 Proved plus Probable plus Possible Gas Reserves

    Table 4.3: Gas Proved plus Probable plus Possible Reserves (MMscf) 100% Basis

    Table 4.3 shows the Proved plus Probable plus Possible Reserves evolution. For theproducing fields there is a general downward revision of reserves, mainly due to theconstraints imposed on GIIP estimates from reservoir pressure data. These downwardrevisions and the inclusion of reserves from the new discovery Szymanowice result in 3%less reserves (6.2 Bscf), in the 2014 evaluation, after 2013 production .

    2014Field Evaluation Production Remaining Evaluation MMscf (%)01-Jan-13 during 2013 31-Dec-13 01-Jan-14

    Zaniemysl 14,545 370 14,176 8,895 -5,281 -37%

    Sroda-Kromolice 55,255 2,838 52,416 53,725 1,309 2%

    Roszkow 31,761 3,262 28,499 23,004 -5,495 -19%

    Winna Gora 27,495 643 26,852 22,873 -3,979 -15%

    Kromolice South 9,421 1,245 8,176 8,128 -48 -1%

    Grabowka 19,724 99 19,625 2,081 -17,545 -89%

    Lisewo 69,200 88 69,112 64,532 -4,581 -7%

    Komorze 11,146 0 11,146 14,037 2,891 26%

    Szymanowice 26,497 26,497 0%

    Total 238,548 8,545 230,003 223,770 -6,233 -3%

    2013 Variation

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    46/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    APPENDIX 1: PRODUCTION FORECASTS AND CASHFLOW ANALYSIS FORZANIEMYSL FIELD

    Table A1.1: Gas Production Forecasts for the Zaniemysl Field

    Year Gas Rate

    (MMscfd)

    Cumulative

    Production (Bscf)

    Gas Rate

    (MMscfd)

    Cumulative

    Production (Bscf)

    Gas Rate

    (MMscfd)

    Cumulative

    Production (Bscf)

    2015 2.1 21.57 2.1 21.57 2.1 21.57

    2016 2.1 22.34 2.1 22.34 2.1 22.342017 2.1 23.11 2.1 23.11 2.1 23.11

    2018 2.1 23.88 2.1 23.88 2.1 23.88

    2019 0.4 24.04 2.1 24.65 2.1 24.65

    2020 2.1 25.42 2.1 25.42

    2021 2.1 26.19 2.1 26.19

    2022 1.5 26.74 2.1 26.96

    2023 2.1 27.73

    2024 2.1 28.502025 2.1 29.27

    2026 1.1 29.69

    Zaniemysl

    Proved Proved+Probable Proved +Probable+Possible

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    47/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    ECV 2003 38 February 2014

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    48/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    ECV 2003 39 February 2014

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    49/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    ECV 2003 40 February 2014

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    50/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    ECV 2003 41 February 2014

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    51/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    ECV 2003 42 February 2014

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    52/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    ECV 2003 43 February 2014

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    53/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    APPENDIX 2: PRODUCTION FORECASTS AND CASHFLOW ANALYSIS FORTHE ROSZKOW FIELD

    Year Gas Rate

    (MMscfd)Cumulative

    Production (Bscf)Gas Rate(MMscfd)

    CumulativeProduction (Bscf)

    Gas Rate(MMscfd)

    CumulativeProduction (Bscf)

    2014 7.27 21.53 7.27 21.53 7.27 21.532015 6.27 23.81 6.93 24.05 7.21 24.16

    2016 4.20 25.35 5.17 25.95 5.88 26.312017 2.78 26.37 3.78 27.33 4.56 27.972018 1.87 27.05 2.76 28.33 3.63 29.302019 1.32 27.53 2.06 29.09 2.93 30.372020 0.96 27.89 1.59 29.67 2.42 31.262021 0.73 28.15 1.27 30.13 2.07 32.012022 0.56 28.36 1.03 30.51 1.81 32.672023 0.45 28.52 0.86 30.82 1.61 33.262024 0.36 28.65 0.73 31.09 1.45 33.79

    2025 0.30 28.76 0.63 31.32 1.33 34.272026 0.25 28.85 0.54 31.52 1.22 34.722027 0.21 28.92 0.48 31.69 1.14 35.132028 0.18 28.99 0.42 31.85 1.06 35.522029 0.15 29.04 0.38 31.99 1.00 35.882030 0.13 29.09 0.34 32.11 0.94 36.232031 0.11 29.13 0.31 32.23 0.89 36.552032 0.10 29.17 0.29 32.33 0.84 36.862033 0.09 29.20 0.26 32.43 0.80 37.15

    Roszkow

    Proved Proved+Probable P roved +Probable+Possible

    RPS E FX E I E l ti f P li h G A t

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    54/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    ECV 2003 45 February 2014

    RPS Energy FX Energy Inc Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    55/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    ECV 2003 46 February 2014

    RPS Energy FX Energy Inc Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    56/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    ECV 2003 47 February 2014

    RPS Energy FX Energy Inc Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    57/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    ECV 2003 48 February 2014

    RPS Energy FX Energy Inc Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    58/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    ECV 2003 49 February 2014

    RPS Energy FX Energy Inc Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    59/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    ECV 2003 50 February 2014

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    60/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    APPENDIX 3: PRODUCTION FORECASTS AND CASHFLOW ANALYSIS FORSRODA-KROMOLICE FIELD

    YearGas Rate

    (MMscfd)

    Cumulative

    Production (Bscf)

    Gas Rate

    (MMscfd)

    Cumulative

    Production (Bscf)

    Gas Rate

    (MMscfd)

    Cumulative

    Production

    (Bscf)

    2014 7.55 9.78 7.55 11.96 7.55 11.96

    2015 7.58 12.55 7.58 14.72 7.58 14.72

    2016 7.58 15.32 7.58 17.50 7.58 17.50

    2017 7.58 18.08 7.58 20.26 7.58 20.26

    2018 7.03 20.65 7.31 22.93 7.58 23.03

    2019 5.39 22.62 5.78 25.04 6.86 25.53

    2020 4.35 24.21 4.70 26.76 5.60 27.58

    2021 3.74 25.58 4.04 28.23 4.84 29.352022 3.35 26.80 3.65 29.57 4.38 30.94

    2023 3.06 27.91 3.39 30.80 4.08 32.43

    2024 2.47 28.82 3.20 31.97 3.90 33.86

    2025 2.39 29.69 3.05 33.09 3.77 35.24

    2026 1.85 30.37 2.89 34.14 3.68 36.58

    2027 1.26 30.83 2.16 34.93 3.61 37.90

    2028 0.90 31.15 1.63 35.53 3.56 39.20

    2029 0.67 31.40 1.34 36.02 3.51 40.48

    2030 0.51 31.59 1.14 36.43 3.48 41.75

    2031 0.40 31.73 1.03 36.81 3.45 43.01

    2032 0.13 31.78 0.93 37.15 3.42 44.26

    2033 0.78 37.43 3.40 45.50

    2034 0.67 37.68 3.30 46.71

    2035 0.57 37.89 2.89 47.76

    2036 0.33 38.01 2.61 48.722037 0.33 38.13 2.43 49.60

    2038 0.33 38.25 2.18 50.40

    2039 0.33 38.37 2.07 51.15

    2040 0.31 38.49 1.92 51.85

    2041 0.33 38.61 1.27 52.32

    2042 0.31 38.72 0.85 52.63

    2043 0.33 38.84 0.84 52.93

    2044 0.32 38.96 0.82 53.23

    2045 0.31 39.07 0.81 53.53

    2046 0.31 39.19 0.80 53.82

    2047 0.31 39.30 0.78 54.11

    2048 0.31 39.42 0.77 54.39

    2049 0.30 39.53 0.75 54.66

    2050 0 31 39 64 0 74 54 93

    Sroda Kromolice

    Proved Proved+Probable Proved

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    61/105

    gy gy,

    ECV 2003 52 February 2014

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    62/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    63/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    64/105

    ECV 2003 55 February 2014

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    65/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    66/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    67/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    APPENDIX 4: PRODUCTION FORECASTS AND CASHFLOW ANALYSIS FORTHE KROMOLICE SOUTH FIELD

    Year Gas Rate

    (MMscfd)

    Cumulative

    Production(Bscf)

    Gas Rate

    (MMscfd)

    Cumulative

    Production(Bscf)

    Gas Rate

    (MMscfd)

    Cumulative

    Production(Bscf)

    2014 3.06 3.50 3.06 3.50 3.06 3.502015 3.07 4.62 3.07 4.62 3.07 4.62

    2016 2.55 5.55 3.07 5.74 3.07 5.74

    2017 2.84 6.78 3.05 6.852018 1.58 7.35 2.39 7.73

    2019 0.82 7.65 1.75 8.36

    2020 0.26 7.75 1.34 8.85

    2021 1.05 9.242022 0.84 9.54

    2023 0.69 9.792024 0.56 10.00

    2025 0.47 10.17

    2026 0.39 10.312027 0.32 10.43

    Kromolice_South

    Proved Proved+Probable Proved

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    68/105

    ECV 2003 59 February 2014

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    69/105

    ECV 2003 60 February 2014

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    70/105

    ECV 2003 61 February 2014

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    71/105

    ECV 2003 62 February 2014

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    72/105

    ECV 2003 63 February 2014

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    73/105

    ECV 2003 64 February 2014

    RPS E FX E I E l ti f P li h G A t

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    74/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    APPENDIX 5: PRODUCTION FORECASTS AND CASHFLOW ANALYSIS FORTHE WINNA GORA FIELD

    YearGas Rate

    (MMscfd)

    Cumulative

    Production (Bscf)

    Gas Rate

    (MMscfd)

    Cumulative

    Production (Bscf)

    Gas Rate

    (MMscfd)

    Cumulative

    Production (Bscf)

    2014 2.01 1.37 2.01 1.37 2.01 1.37

    2015 2.01 2.11 2.01 2.11 2.01 2.11

    2016 2.01 2.84 2.01 2.84 2.01 2.84

    2017 1.91 3.54 2.01 3.58 2.01 3.58

    2018 1.62 4.13 2.01 4.31 2.01 4.31

    2019 1.38 4.64 2.01 5.05 2.01 5.05

    2020 1.20 5.08 1.88 5.74 2.01 5.79

    2021 1.05 5.46 1.69 6.35 2.01 6.522022 0.94 5.80 1.53 6.91 2.01 7.26

    2023 0.84 6.11 1.39 7.42 2.01 7.99

    2024 0.75 6.38 1.27 7.89 1.95 8.71

    2025 0.68 6.63 1.17 8.31 1.82 9.37

    2026 0.62 6.86 1.08 8.71 1.71 9.99

    2027 0.57 7.06 1.01 9.08 1.60 10.58

    2028 0.52 7.26 0.94 9.42 1.51 11.13

    2029 0.48 7.43 0.87 9.74 1.42 11.65

    2030 0.44 7.59 0.82 10.04 1.35 12.14

    2031 0.41 7.74 0.77 10.32 1.28 12.61

    2032 0.38 7.88 0.72 10.58 1.21 13.05

    2033 0.36 8.02 0.68 10.83 1.15 13.47

    2034 0.34 8.14 0.64 11.06 1.10 13.87

    2035 0.31 8.25 0.61 11.28 1.05 14.262036 0.29 8.36 0.57 11.50 1.00 14.62

    2037 0.28 8.46 0.55 11.69 0.96 14.97

    2038 0.26 8.56 0.52 11.88 0.92 15.31

    2039 0.25 8.65 0.49 12.06 0.88 15.63

    2040 0.23 8.73 0.47 12.24 0.84 15.93

    2041 0.22 8.81 0.45 12.40 0.81 16.23

    2042 0.21 8.89 0.43 12.56 0.78 16.51

    2043 0.20 8.96 0.41 12.71 0.75 16.79

    2044 0.19 9.03 0.39 12.85 0.72 17.05

    2045 0.18 9.10 0.38 12.99 0.69 17.30

    2046 0.17 9.16 0.36 13.12 0.67 17.55

    2047 0.16 9.22 0.35 13.24 0.65 17.78

    2048 0 16 9 28 0 33 13 36 0 62 18 01

    Winna Gora

    Proved Proved+Probable Proved +Probable+Possible

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    75/105

    RPS Energ FX Energ Inc E al ation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    76/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    RPS Energy FX Energy Inc Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    77/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    78/105

    ECV 2003 69 February 2014

    RPS Energy FX Energy Inc Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    79/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    RPS Energy FX Energy Inc Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    80/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    RPS Energy FX Energy Inc Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    81/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

    APPENDIX 6: PRODUCTION FORECASTS AND CASHFLOW ANALYSIS FORLISEWO FIELD

    YearGas Rate

    (MMscfd)

    Cumulative

    Production (Bscf)

    Gas Rate

    (MMscfd)

    Cumulative

    Production (Bscf)

    Gas Rate

    (MMscfd)

    Cumulative

    Production (Bscf)

    2014 6.00 2.28 6.00 2.28 6.00 2.28

    2015 8.53 5.40 8.53 5.40 8.53 5.40

    2016 8.52 8.51 8.53 8.52 8.53 8.52

    2017 7.92 11.40 8.53 11.63 8.53 11.63

    2018 6.47 13.76 8.43 14.71 8.53 14.75

    2019 5.06 15.61 7.93 17.60 8.53 17.86

    2020 4.09 17.11 7.18 20.23 8.53 20.99

    2021 3.38 18.34 6.09 22.45 8.31 24.02

    2022 2.83 19.37 5.25 24.37 7.97 26.93

    2023 2.38 20.24 4.58 26.04 7.65 29.72

    2024 2.03 20.98 4.04 27.52 6.99 32.28

    2025 1.74 21.62 3.59 28.83 6.30 34.58

    2026 1.49 22.16 3.21 30.00 5.73 36.67

    2027 0.98 22.52 2.88 31.05 5.23 38.58

    2028 0.89 22.85 2.58 32.00 4.79 40.33

    2029 0.81 23.14 2.33 32.85 4.42 41.94

    2030 0.81 23.44 2.11 33.62 4.09 43.44

    2031 0.75 23.71 1.92 34.32 3.80 44.82

    2032 0.69 23.97 1.75 34.96 3.54 46.12

    2033 0.63 24.19 1.60 35.54 3.30 47.32

    2034 0.57 24.40 1.45 36.07 3.08 48.442035 0.51 24.59 0.99 36.43 2.87 49.49

    2036 0.46 24.76 0.94 36.78 2.68 50.47

    2037 0.15 24.81 0.89 37.10 2.51 51.39

    2038 0.06 24.84 0.84 37.41 2.36 52.25

    2039 0.03 24.85 0.80 37.70 2.22 53.06

    2040 0.82 38.00 2.09 53.82

    2041 0.79 38.29 1.97 54.54

    2042 0.74 38.56 1.85 55.22

    2043 0.70 38.82 1.75 55.85

    2044 0.67 39.06 1.65 56.46

    2045 0.63 39.29 1.56 57.03

    2046 0.60 39.51 1.48 57.57

    2047 0 56 39 71 1 19 58 01

    Lisewo

    Proved Proved+Probable Proved +Probable+Possible

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    82/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    83/105

    ECV 2003 74 February 2014

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    84/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    85/105

    ECV 2003 76 February 2014

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    86/105

    ECV 2003 77 February 2014

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    87/105

    gy gy

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    88/105

    APPENDIX 7: PRODUCTION FORECASTS AND CASHFLOW ANALYSIS FORKOMORZE-3 FIELD

    Year Gas Rate

    (MMscfd)

    Cumulative

    Production (Bscf)

    Gas Rate

    (MMscfd)

    Cumulative

    Production (Bscf)

    Gas Rate

    (MMscfd)

    Cumulative

    Production (Bscf)

    2014 1.25 0.42 1.25 0.42 1.25 0.42

    2015 1.25 0.87 1.25 0.87 1.25 0.87

    2016 1.25 1.33 1.25 1.33 1.25 1.33

    2017 1.21 1.77 1.25 1.78 1.25 1.78

    2018 1.09 2.17 1.24 2.23 1.25 2.24

    2019 0.98 2.53 1.17 2.66 1.25 2.69

    2020 0.89 2.86 1.08 3.06 1.24 3.15

    2021 0.82 3.15 1.01 3.43 1.19 3.58

    2022 0.75 3.43 0.94 3.77 1.12 3.99

    2023 0.69 3.68 0.88 4.09 1.06 4.38

    2024 0.64 3.91 0.83 4.39 1.01 4.752025 0.60 4.13 0.78 4.67 0.96 5.10

    2026 0.56 4.33 0.73 4.94 0.92 5.43

    2027 0.52 4.52 0.69 5.19 0.88 5.75

    2028 0.49 4.70 0.66 5.44 0.84 6.06

    2029 0.46 4.87 0.62 5.66 0.80 6.35

    2030 0.59 5.88 0.77 6.63

    2031 0.56 6.08 0.74 6.90

    2032 0.54 6.28 0.71 7.16

    2033 0.51 6.47 0.68 7.41

    2034 0.49 6.65 0.66 7.65

    2035 0.47 6.82 0.63 7.89

    2036 0.45 6.99 0.61 8.11

    2037 0.43 7.15 0.59 8.332038 0.42 7.30 0.57 8.53

    2039 0.40 7.44 0.55 8.74

    2040 0.39 7.59 0.53 8.93

    2041 0.37 7.72 0.52 9.12

    2042 0.36 7.85 0.50 9.30

    2043 0.35 7.98 0.49 9.48

    2044 0.33 8.10 0.47 9.65

    2045 0.32 8.22 0.46 9.82

    2046 0.31 8.33 0.45 9.98

    2047 0.30 8.44 0.43 10.14

    2048 0.42 10.30

    2049 0.41 10.45

    Komorze

    Proved Proved+Probable Proved +Probable+Possible

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    89/105

    ECV 2003 80 February 2014

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    90/105

    ECV 2003 81 February 2014

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    91/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    92/105

    ECV 2003 83 February 2014

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    93/105

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    94/105

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    95/105

    APPENDIX 8 PRODUCTION FORECASTS AND CASHFLOW ANALYSIS FORSZYMANOWICE FIELD

    YearGas Rate

    (MMscfd)

    Cumulative

    Production (Bscf)

    Gas Rate

    (MMscfd)

    Cumulative

    Production (Bscf)

    Gas Rate

    (MMscfd)

    Cumulative

    Production (Bscf)

    2015 1.25 0.42 1.25 0.42 1.25 0.42

    2016 1.25 0.87 1.25 0.87 1.25 0.87

    2017 1.25 1.33 1.25 1.33 1.25 1.33

    2018 1.25 1.78 1.25 1.78 2.49 2.24

    2019 1.21 2.22 1.25 2.24 2.49 3.152020 1.12 2.63 1.25 2.69 2.49 4.06

    2021 1.04 3.01 1.25 3.15 2.49 4.97

    2022 0.97 3.37 1.25 3.60 2.49 5.88

    2023 0.91 3.70 1.22 4.05 2.45 6.77

    2024 0.86 4.02 1.17 4.48 2.34 7.63

    2025 0.81 4.31 1.13 4.89 2.24 8.44

    2026 0.76 4.59 1.09 5.29 2.14 9.23

    2027 0.72 4.85 1.05 5.67 2.05 9.97

    2028 0.69 5.11 1.01 6.04 1.97 10.69

    2029 0.65 5.34 0.98 6.40 1.89 11.38

    2030 0.62 5.57 0.95 6.74 1.82 12.05

    2031 0.59 5.78 0.92 7.08 1.75 12.69

    2032 0.56 5.99 0.89 7.40 1.69 13.30

    2033 0.54 6.19 0.86 7.71 1.63 13.90

    2034 0.52 6.37 0.83 8.02 1.57 14.47

    2035 0.49 6.56 0.81 8.31 1.52 15.02

    2036 0.47 6.73 0.78 8.60 1.47 15.56

    2037 0.45 6.89 0.76 8.88 1.42 16.08

    2038 0.44 7.05 0.74 9.15 1.38 16.58

    2039 0 42 7 21 0 72 9 41 1 33 17 07

    Szymanowice

    Proved Proved+Probable Proved +Probable+Possible

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    96/105

    ECV 2003 87 February 2014

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    97/105

    ECV 2003 88 February 2014

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    98/105

    ECV 2003 89 February 2014

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    99/105

    ECV 2003 90 February 2014

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    100/105

    ECV 2003 91 February 2014

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    101/105

    ECV 2003 92 February 2014

    RPS Energy

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    102/105

    APPENDIX 9 PRODUCTION FORECASTS AND CASHFLOW ANALYSIS FORGRABOWKA FIELD

    Table A8.1: Gas Production Forecasts for Grabowka

    Year Gas Rate

    (MMscfd)

    Cumulative

    Production

    (Bscf)

    Gas Rate

    (MMscfd)

    Cumulative

    Production

    (Bscf)

    Gas Rate

    (MMscfd)

    Cumulative

    Production

    (Bscf)

    2014 0.3 0.6 0.3 0.6 0.3 0.6

    2015 0.3 0.7 0.3 0.7 0.3 0.72016 0.2 0.8 0.3 0.8 0.3 0.8

    2017 0.6 1.0 0.3 0.9

    2018 0.6 1.3 0.6 1.2

    2019 0.6 1.5 0.6 1.4

    2020 0.3 1.6 0.6 1.6

    2021 0.2 1.7 0.6 1.8

    2022 0.6 2.02023 0.6 2.3

    2024 0.6 2.5

    2025 0.3 2.6

    2026 0.1 2.6

    Grabowka

    Proved Proved+Probable Proved

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    103/105

    ECV 2003 94 February 2014

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    104/105

    ECV 2003 95 February 2014

    RPS Energy FX Energy, Inc. Evaluation of Polish Gas Assets

  • 8/12/2019 FX Energy 2013 Reserve Report for Poland

    105/105