District Department of Transportation FY2017 FY2017 Performance Accountability Report The Performance Accountability Report (PAR) measures each agency's performance for the fiscal year against the agency's performance plan and includes major accomplishments, updates on initiatives, and key performance indicators (KPIs). Mission The District Department of Transportation’s (DDOT) mission is to enhance the quality of life for District residents and visitors by ensuring that people and goods move safely with minimal adverse impact on residents and the environment. Summary of Services DDOT executes its mission through the work of several divisions. - The Office of the Director is responsible for legal affairs; civil rights matters; compliance with the Americans with Disabilities Act of 1990; senior and elderly affairs; and policy and legislative affairs. - The Project Delivery Administration is responsible for design and engineering and related support; street and bridge construction project management and related material inspection and testing; project materials specification review; construction project review and coordination; construction contract execution; intermodal planning; state transportation environmental compliance; project identification and development; DC Circulator bus service; DC Streetcar service; freight and passenger rail; and mass transit policy, including WMATA matters. - The Operations Administration is responsible for tree planting and maintenance; tree inventory management; public space permits and records; investigations and inspections relating to public space regulations; asset management; bridge and street maintenance; streetlight management; traffic operations and safety; transportation systems management; traffic sign fabrication and installation; parking, carsharing, tour bus, and motor carrier regulation, permitting, and operations; and advertisements on parking meters, including the back of receipts printed out by multi-space parking meters. - The Administrative Administration is responsible for human resources; workforce development; budget and financial services; financial planning and management; and contracting and procurement - The Performance Administration is responsible for coordinating and managing transportation system data; customer service; coordinating and managing the agency's fleet, warehouses; and other technology and information services. FY17 Top Accomplishments The new process will accomplish the following: (1) uniform and consistent invoice processes and procedures Department wide; (2) real-time lifecycle chain-of-custody and approval flow from receipt to submission to the OCFO for payment; (3) minimization of late payment fees; (4) rejection of invoices in a timely manner; (5) rigorous QA/QC process; (6) elimination of processing bottlenecks by assigning backup staff; (7) reduction of complaints due to late processing and payment; and (8) better partnerships with contractors and subcontractors. DDOT's project delivery will be faster and reduce unnecessary fees, which will improve efficiency for DC's residents. ProTrack+ has enhanced coordination across internal DDOT groups, improved the contracting process with external organizations, and provides a GIS- centered view of work by DDOT as well as ProTrack+ improves project delivery and coordination between agencies and groups, which improves asset Accomplishment Impact on Agency Impact on Residents New Invoice Tracking Process and System: DDOT launched invoice process improvements on October 1, 2017. This was a year-long effort that started with a 3-month Lean Six Sigma interagency effort in response to a Federal Highway Administration Prompt Payment Review whereby DDOT was found to be non-compliant in paying contractors on time. This process improvement resulted in a Standard Operating Procedure and a new Invoice Tracking System as a part of ProTrack+ along with training of over 200 staff. Additionally, an Invoice Review Team was established to track and report performance metrics, review and resolve complaints, train staff, and modify processes and procedures to improve performance. ProTrack+ Software Roll Out for Project Coordination across DDOT and between Agencies: DDOT developed and implemented an application called ProTrack+ (E Construction) which is now the main system for the project pipeline from Call for Projects to Close Out. ProTrack+ is a cradle to grave project tracking application that allows 1 of 21

Upload: others

Post on 28-Feb-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

District Department of Transportation FY2017

FY2017 Performance Accountability ReportThe Performance Accountability Report (PAR) measures each agency's performance for the fiscal year against the agency's performance planand includes major accomplishments, updates on initiatives, and key performance indicators (KPIs).

MissionThe District Department of Transportation’s (DDOT) mission is to enhance the quality of life for District residents and visitors by ensuring thatpeople and goods move safely with minimal adverse impact on residents and the environment.

Summary of ServicesDDOT executes its mission through the work of several divisions. - The Office of the Director is responsible for legal affairs; civil rights matters;compliance with the Americans with Disabilities Act of 1990; senior and elderly affairs; and policy and legislative affairs. - The Project DeliveryAdministration is responsible for design and engineering and related support; street and bridge construction project management and relatedmaterial inspection and testing; project materials specification review; construction project review and coordination; construction contractexecution; intermodal planning; state transportation environmental compliance; project identification and development; DC Circulator busservice; DC Streetcar service; freight and passenger rail; and mass transit policy, including WMATA matters. - The Operations Administration isresponsible for tree planting and maintenance; tree inventory management; public space permits and records; investigations and inspectionsrelating to public space regulations; asset management; bridge and street maintenance; streetlight management; traffic operations and safety;transportation systems management; traffic sign fabrication and installation; parking, carsharing, tour bus, and motor carrier regulation,permitting, and operations; and advertisements on parking meters, including the back of receipts printed out by multi-space parking meters. -The Administrative Administration is responsible for human resources; workforce development; budget and financial services; financial planningand management; and contracting and procurement - The Performance Administration is responsible for coordinating and managingtransportation system data; customer service; coordinating and managing the agency's fleet, warehouses; and other technology andinformation services.

FY17 Top Accomplishments

The new process will accomplish thefollowing: (1) uniform and consistentinvoice processes and proceduresDepartment wide; (2) real-time lifecyclechain-of-custody and approval flow fromreceipt to submission to the OCFO forpayment; (3) minimization of latepayment fees; (4) rejection of invoices ina timely manner; (5) rigorous QA/QCprocess; (6) elimination of processingbottlenecks by assigning backup staff; (7)reduction of complaints due to lateprocessing and payment; and (8) betterpartnerships with contractors andsubcontractors.

DDOT's project deliverywill be faster and reduceunnecessary fees, whichwill improve efficiencyfor DC's residents.

ProTrack+ has enhanced coordinationacross internal DDOT groups, improvedthe contracting process with externalorganizations, and provides a GIS-centered view of work by DDOT as well as

ProTrack+ improvesproject delivery andcoordination betweenagencies and groups,which improves asset

Accomplishment Impact on Agency Impact on Residents

New Invoice Tracking Process and System: DDOT launched invoiceprocess improvements on October 1, 2017. This was a year-longeffort that started with a 3-month Lean Six Sigma interagency effortin response to a Federal Highway Administration Prompt PaymentReview whereby DDOT was found to be non-compliant in payingcontractors on time. This process improvement resulted in a StandardOperating Procedure and a new Invoice Tracking System as a part ofProTrack+ along with training of over 200 staff. Additionally, anInvoice Review Team was established to track and report performancemetrics, review and resolve complaints, train staff, and modifyprocesses and procedures to improve performance.

ProTrack+ Software Roll Out for Project Coordination across DDOTand between Agencies: DDOT developed and implemented anapplication called ProTrack+ (E Construction) which is now the mainsystem for the project pipeline from Call for Projects to Close Out.ProTrack+ is a cradle to grave project tracking application that allows

1 of 21

2017 Strategic Objectives

2017 Key Performance Indicators

utility companies. management forresidents.

This project is the largest project inDDOT’s history.

The bridge will result inimproved safety, trafficflow, and pedestrian andbicycle access connectingthe east and west sidesof the Anacostia River.The winning Design-Buildteam proposed a newsignature bridge spanwith a series of threearches across the riverthat will provide a newgateway unlike any otherriver crossing in theDistrict.

Enhance productivity utilizing a data-driven approach and technology to improve efficiency and effectiveness.

Prioritize safety in building and maintaining an environmentally sustainable, accessible, and connected transportation networkacross all modes.

Plan and deliver projects utilizing an integrated approach, developing project pipelines, and ensuring that programmatic andadministrative functions are efficiently coordinated and aligned.

Support employee performance through targeted professional development, performance management, and enhanced safetyguidelines.

As custodians of the District's public realm, develop and enforce laws and regulations designed to maintain a safe and beautifulpublic realm.

Create and maintain a highly efficient, transparent and responsive District government.**

ObjectiveNumber

Strategic Objective

1 - Enhance productivity utilizing a data-driven approach and technology to improve efficiency and effectiveness. (6Measures)

Quarterly 7 3 1 0 1 5 Unmet The goal of 7 was not achieved dueto time/effort from difficultiesexperienced in getting reliable data

Measure Freq Target Q1 Q2 Q3 Q4 FY 2017 KPIStatus

Explanation

DDOT to start from the “Call for Projects” through obligation tocontract process to construction to close out. ProTrack+ incorporatesall interaction with OCP, OCFO, FHWA and DDOT staff so it is aseamless process that allows the users to know where each project isalong this process pipeline. Training and enhancements are ongoingas are the build out of newer modules such as invoice tracking,Change Order Requests and Project Plan Reviews.

South Capitol/Frederick Douglass Memorial Bridge Contract Award:During FY17, DDOT awarded contracts for the Design-Buildconstruction and the Program Management/Construction Management(PM/CM) for Phase I of the South Capitol Street project. Phase Iincluded the replacement of the deteriorating Frederick DouglassMemorial Bridge, the construction of land-side improvements,including new open spaces and waterfront trail access, on both sidesof the Anacostia River, and reconstruction of the Suitland Parkway/I-295 highway interchange. In addition to these two contracts, DDOTadvanced the acquisition of the right-of-way necessary for theroadway improvements. In FY18, DDOT will complete right-of-wayacquisition, finalize the project design, and begin constructionactivities. Substantial completion of the project, including demolitionof the existing bridge is anticipated in FY21.

1

2

3

4

5

6

Total number ofbike/ped countersinstalled

2 of 21

from 5 installs that werecompleted.

Quarterly 80% 73.7% 76.3% 65.1% 73.9% 72.3% NearlyMet

Bus maintenance was a bigobstacle and considering the age ofthe fleet, 40 new vehicles havebeen added.

Quarterly 165 158 187 147 144 159 NearlyMet

Contract/funding issues

Quarterly 60% 91.6% 69.3% 125% 27.4% 81.8% Met

Quarterly 97% 76.6% 84.5% 86.9% 88.9% 84.2% Unmet Previous data was based onestimation from service requestsbecause not all meters werenetworked. As of 10/17/17, allmeters are networked in theDistrict, so each meter is providingfeedback when there is issues, andcontractor can now take proactiveaction.

Quarterly 20% 75% 13.5% 7.5% 4.7% 17.9% Met

2 - Prioritize safety in building and maintaining an environmentally sustainable, accessible, and connected transportationnetwork across all modes. (16 Measures)

Quarterly 2% 7.8% 17.4% 21.9% 9.5% 15.6% Met

Quarterly 0 107 137 211 236 691 Unmet The District has performed betterthan many peer vision zero citiesand the national average over thefirst two years of the Vision Zeroinitiative. Nationally, fatalities haverisen to 40,000 per year, thefastest increase the country hasseen in several decades. Likewise,the District is adding approximately1,000 residents per month, morepeople are driving as the economyhas improved and gas has becomecheaper. More unprotectedtravelers are walking a biking – DCis now second in the nation forshare of commuters biking to work(4.6%). 13.7% of people walkingto work. 36% take public transit,

Circulator on-timeperformance

Total number ofdeploymentlocations coveredfor traffic controlofficers (TCOs)

Percent of lightingsurvey issuesresolved

Average percent ofparking metersworking daily

Percent ofrequests for TrafficControl Officers(TCOs) unfulfilled

Percent change inCapital BikeshareRidership

Number of crasheswith bicyclistsinvolved

3 of 21

which makes them vulnerablepedestrians at some point in theirjourney. This all translates intomore potential for crashes, injuries,and fatalities. In the first years ofVision Zero, we’ve dramaticallyenhanced our sophistication ondata and analysis. This foundationwill eventually translate to safetygains on the street in the comingyears.

Quarterly 0 319 263 244 247 1073 Unmet The District has performed betterthan many peer vision zero citiesand the national average over thefirst two years of the Vision Zeroinitiative. Nationally, fatalities haverisen to 40,000 per year, thefastest increase the country hasseen in several decades. Likewise,the District is adding approximately1,000 residents per month, morepeople are driving as the economyhas improved and gas has becomecheaper. More unprotectedtravelers are walking a biking – DCis now second in the nation forshare of commuters biking to work(4.6%). 13.7% of people walkingto work. 36% take public transit,which makes them vulnerablepedestrians at some point in theirjourney. This all translates intomore potential for crashes, injuries,and fatalities. In the first years ofVision Zero, we’ve dramaticallyenhanced our sophistication ondata and analysis. This foundationwill eventually translate to safetygains on the street in the comingyears.

Quarterly 93 0 0 0 0 0 Unmet DDOT received approval from theFederal Transit Administration forthe $2 million grant in in August2017 and now has a programmanagement support task order inplace and are advancing corridor-level improvement plans. DDOThas been unable to secureconstruction management servicesfor the projects due to delays inthe A/E schedule procurement butexpects to greatly increaseproductivity in FY18.

Quarterly 250 8 8 8 8 32 Unmet The original projection of 250

Number of crasheswith pedestriansinvolved

Percent of "high-priority" bus stopsimproved to meetADA standards

Number of safety4 of 21

focused on all re-stripings howeverthis metric should only consider theidentified priority intersections.

Quarterly 0 6882 6208 6277 6508 25875 Unmet The District has performed betterthan many peer vision zero citiesand the national average over thefirst two years of the Vision Zeroinitiative. Nationally, fatalities haverisen to 40,000 per year, thefastest increase the country hasseen in several decades. Likewise,the District is adding approximately1,000 residents per month, morepeople are driving as the economyhas improved and gas has becomecheaper. More unprotectedtravelers are walking a biking – DCis now second in the nation forshare of commuters biking to work(4.6%). 13.7% of people walkingto work. 36% take public transit,which makes them vulnerablepedestrians at some point in theirjourney. This all translates intomore potential for crashes, injuries,and fatalities. In the first years ofVision Zero, we’ve dramaticallyenhanced our sophistication ondata and analysis. This foundationwill eventually translate to safetygains on the street in the comingyears.

Quarterly 0 3 3 5 6 17 Unmet The District has performed betterthan many peer vision zero citiesand the national average over thefirst two years of the Vision Zeroinitiative. Nationally, fatalities haverisen to 40,000 per year, thefastest increase the country hasseen in several decades. Likewise,the District is adding approximately1,000 residents per month, morepeople are driving as the economyhas improved and gas has becomecheaper. More unprotectedtravelers are walking a biking – DCis now second in the nation forshare of commuters biking to work(4.6%). 13.7% of people walkingto work. 36% take public transit,which makes them vulnerablepedestrians at some point in theirjourney. This all translates intomore potential for crashes, injuries,and fatalities. In the first years of

upgrades atpriorityintersections

Number of vehiclecrashes

Number of vehicular fatalities

5 of 21

Vision Zero, we’ve dramaticallyenhanced our sophistication ondata and analysis. This foundationwill eventually translate to safetygains on the street in the comingyears.

Quarterly 0 0 2 2 2 6 Unmet The District has performed betterthan many peer vision zero citiesand the national average over thefirst two years of the Vision Zeroinitiative. Nationally, fatalities haverisen to 40,000 per year, thefastest increase the country hasseen in several decades. Likewise,the District is adding approximately1,000 residents per month, morepeople are driving as the economyhas improved and gas has becomecheaper. More unprotectedtravelers are walking a biking – DCis now second in the nation forshare of commuters biking to work(4.6%). 13.7% of people walkingto work. 36% take public transit,which makes them vulnerablepedestrians at some point in theirjourney. This all translates intomore potential for crashes, injuries,and fatalities. In the first years ofVision Zero, we’ve dramaticallyenhanced our sophistication ondata and analysis. This foundationwill eventually translate to safetygains on the street in the comingyears.

Quarterly 0 0 0 1 1 2 Unmet The District has performed betterthan many peer vision zero citiesand the national average over thefirst two years of the Vision Zeroinitiative. Nationally, fatalities haverisen to 40,000 per year, thefastest increase the country hasseen in several decades. Likewise,the District is adding approximately1,000 residents per month, morepeople are driving as the economyhas improved and gas has becomecheaper. More unprotectedtravelers are walking a biking – DCis now second in the nation forshare of commuters biking to work(4.6%). 13.7% of people walkingto work. 36% take public transit,which makes them vulnerablepedestrians at some point in their

Number ofpedestrianfatalities

Number of bicyclistfatalities

6 of 21

journey. This all translates intomore potential for crashes, injuries,and fatalities. In the first years ofVision Zero, we’ve dramaticallyenhanced our sophistication ondata and analysis. This foundationwill eventually translate to safetygains on the street in the comingyears.

Quarterly 87% 79.2% 53.6% 69% 62.9% 64.9% Unmet In prior years a Pothole Killer wasused which was fast but oftenineffective. This year DDOT focusedon effectiveness.

Quarterly 75% 78.4% 78.6% 79.2% 79.8% 79% Met

Quarterly 3 5 5 5 5 5 Unmet All of these bridges are in thecontract pipeline.

Quarterly 9% 0.6% 0% 0.3% 0.1% 0.3% Unmet In response to a request made byCouncilmember Cheh, a partialmoratorium was put in place todiscontinue the installation of LEDlights on residential streets untilcommunity concerns regarding theprogram are resolved. This delayedthe procurement of the LEDcontract as further studies to findthe desired LED were carried out.

DDOT is proceeding with the LEDinstallations along the District’shighways and will only install withinresidential neighborhoods with theconcurrence of ANC and MPD.

Quarterly 17000 19469 21445 22261 20782 83957 Met

Quarterly 40 28 17 6 2 53 Met

Quarterly 8 3 0 2 3 8 Met

Percent ofpotholes filled andclosed out within72 hours

Percent of streetsin “Fair" to"Excellent”condition

Number ofdeficient bridges

Percent of light-emitting diodes(LEDs) installedcitywide annuallyout of 68,000qualifying lights

Number of KidsRide Free passespicked up bystudents.

Total number ofnew Level 3 andLevel 4 employersofferingtransportationprograms/benefitsto encourage non-SOV travel.

Number ofintersection/safetyimprovements forbicyclists

7 of 21

3 - Plan and deliver projects utilizing an integrated approach, developing project pipelines, and ensuring that programmaticand administrative functions are efficiently coordinated and aligned. (5 Measures)

Quarterly 10 4.29 0 0.21 2.9 6.64 Unmet Goal of 10% increase in lanes notachieved due in part to A&Eschedule evaluation staff timecommitments, high priorityprojects encountering significantcommunity engagement and/ordesign issues, unexpectedtime/complexity associated withlow-mileage projects, andcontinued difficulty awardingstandalone bikelane installationcontract. We can provide furtherdetail if necessary.

Quarterly 64 47 31 32 33 143 Met

Annually 0.7% AnnualMeasure

AnnualMeasure

AnnualMeasure

AnnualMeasure

96.3% Met

Quarterly 70 29.05 25 6.08 20.52 80.9 Met

Quarterly 15 2 12 0 0 14 NeutralMeasure

4 - Support employee performance through targeted professional development, performance management, and enhancedsafety guidelines. (7 Measures)

Quarterly 130 17 13 17 22 69 Met

Quarterly 9% 1.8% 1.3% 1.8% 2.3% 1.8% NeutralMeasure

Quarterly 100 72.17 4.76 18.75 34.51 130.97 Met

Quarterly 87 0 53.6 6.67 1.46 59.46 Unmet DDOT continues to be challengedregarding delivery times anddelivery mechanisms that fit allschedules and all locations fornon-MSS employees.

Quarterly 95% 97% 96.4% 98.6% 98.8% 97.7% Met

implemented

Percent increase inmiles of bike lanesinstalled

Number of alleysresurfaced

Percent of milescompleted in thepaving plan

Percent ofsidewalk blockscompleted in thesidewalk plan

Number of studiesrequested,prepared, orcontracted byDDOT

Number ofincidents/accidents

Percent ofreported incidentsper 100 employees

Percent of MSSemployeescompletingmandatory training

Percent of non-MSS employeesparticipating intraining

Employee8 of 21

Quarterly 32.4 0.63 5.13 0.14 0.1 5.76 Unmet The trend is for a smaller amountof employees to requests multipletrainings. Total numbers ofemployees requesting andcompleting training remains toolow for our liking.

Quarterly 1000 449.31 777.91 1031.98 239.37 2410.77 NeutralMeasure

5 - As custodians of the District's public realm, develop and enforce laws and regulations designed to maintain a safe andbeautiful public realm. (9 Measures)

Quarterly 7000 3858 3361 940 0 8159 Met

Quarterly 92% 93.6% 93.1% 95.4% 94% 94.1% Met

Quarterly 11% 19.2% 15.9% 20.8% 25.3% 20.3% Met

Quarterly 540 107 127 104 73 411 NeutralMeasure

Quarterly 0.5 0.6 0.6 0.6 0.6 0.6 Unmet There are limited futureopportunity to improve this ratio.However DDOT is exploring how todo pay by phone only, with a pilotto be tested in FY18. If it issuccessful, DDOT can startremoving assets while maintainingmetering operations.

Quarterly 35000 6842 16649 10654 8892 43037 Met

Quarterly 24 172 125 71 No dataavailable

123 Unmet Data is looking at the time it takesto open and close a ServiceRequest as opposed to the actualtime it takes to repair a meter.

Quarterly 6 84 91 43 12 58 Unmet This is the first year that DDOT hasbeen able to measure time torepair connected meters and cannow enforce its contractstipulations.

Quarterly 2 68 61 65 8 51 Unmet This is the first year that DDOT hasbeen able to measure time torepair connected meters and can

retention rate

Average Numberof Training HoursPer Employee

Average TrainingCosts PerEmployee

Number of treesplanted citywide

Percent publicspace applicationsapproved

Percent of DDOTgreeninfrastructure sitesmaintained in theright-of-way.

Number of lightingsurveys forupgrade requestedby the public

Asset to MeteredSpace ratio

Number of SignsInstalled

Mean time torepair meters -Mechanical Meters

Mean time torepair meters -Connected Meters

Mean time torepair meters -Multi-Space Meters

9 of 21

We've revisited a project to standardize District wide measures for the Objective "Create and maintain a highly efficient, transparent andresponsive District government." New measures will be tracked in FY18 and FY19 and published starting in the FY19 Performance Plan.

2017 Workload Measures

now enforce its contractstipulations.

1 - Green Infrastructure Maintenance (1 Measure)

Annually AnnualMeasure

AnnualMeasure

AnnualMeasure

AnnualMeasure

245

1 - Street Tree Maintenance (2 Measures)

Annually AnnualMeasure

AnnualMeasure

AnnualMeasure

AnnualMeasure

11047

Annually AnnualMeasure

AnnualMeasure

AnnualMeasure

AnnualMeasure

2728

2 - Circulator Operations (4 Measures)

Annually AnnualMeasure

AnnualMeasure

AnnualMeasure

AnnualMeasure

4314408

Annually AnnualMeasure

AnnualMeasure

AnnualMeasure

AnnualMeasure

$843564.7

Annually AnnualMeasure

AnnualMeasure

AnnualMeasure

AnnualMeasure

22044783

Annually AnnualMeasure

AnnualMeasure

AnnualMeasure

AnnualMeasure

4314408

2 - Streetcar operations (1 Measure)

Annually AnnualMeasure

AnnualMeasure

AnnualMeasure

AnnualMeasure

1121466

2 - Traffic Signal Maintenance (1 Measure)

Annually AnnualMeasure

AnnualMeasure

AnnualMeasure

AnnualMeasure

130

2 - Transportation demand management (1 Measure)

Annually AnnualMeasure

AnnualMeasure

AnnualMeasure

AnnualMeasure

DataForthcoming

3 - Roadway Repairs (1 Measure)

Annually AnnualMeasure

AnnualMeasure

AnnualMeasure

AnnualMeasure

7042

4 - Fleet Operations (1 Measure)

Measure Freq Q1 Q2 Q3 Q4 FY 2017

Maintaining green infrastructure

Maintaining the safety of our street treepopulation

Street Tree Removal

Number of Circulator Passengers

Total amount of Circulator fare revenuecollected

Total cost to operate Circulator

Seasonally Adjusted Annual Rate

Number of Streetcar Passengers

Traffic Safety Maintenance

Number of alternative mode placements

Number of Potholes Filled (# of ServiceRequests)

10 of 21

2017 Strategic Initiatives

Annually AnnualMeasure

AnnualMeasure

AnnualMeasure

AnnualMeasure

586908

4 - Public Engagement Training for Eligible Staff (1 Measure)

Annually AnnualMeasure

AnnualMeasure

AnnualMeasure

AnnualMeasure

0

5 - Public Space Permitting (1 Measure)

Annually AnnualMeasure

AnnualMeasure

AnnualMeasure

AnnualMeasure

61761

5 - Street Light Asset Management (1 Measure)

Annually AnnualMeasure

AnnualMeasure

AnnualMeasure

AnnualMeasure

28406

5 - Urban Forest Preservation (1 Measure)

Annually AnnualMeasure

AnnualMeasure

AnnualMeasure

AnnualMeasure

1376

CIRCULATOR (3 Strategic initiatives)

DC Circulator will take delivery of vehiclesordered in FY16. Specifications for thenext order of vehicles will be finalized inFY17 for delivery in FY18 or FY19.

75-99% The first 26 of the new vehiclesentered service in summer 2017.The final 14 new vehicles arebeing manufactured, with deliveryexpected in winter 2017/2018.

The final 14 new vehiclesare planned for delivery inwinter 2017/2018.

DDOT will assess site suitability for a futureCirculator bus maintenance facility. A newmaintenance facility is necessary toproperly maintain Circulator buses.

50-74% DDOT is working with DGS to gaincontrol of the preferred site andbegin preparations for necessaryimprovements.

This is a multi-year project.

Mid-life overhaul for 2009 Van Hool busesin the Circulator fleet. The overhaul willextend the life of the buses.

50-74% The presence of new vehicles inthe fleet has lowered the averagefleet age and reduced the numberof maintenance deficienciespresent. Maintenance audits willcontinue, though fewer criticaldefects have been found. Theprogram will continue its focus onensuring a robust preventivemaintenance program.

Maintenance has improved,but DDOT is targeting ahigher overall standard.

INFORMATION TECHNOLOGY (1 Strategic Initiative)

DDOT will work to develop a process forintegrating databases through business

Complete Protrack Plus training and roll outis ongoing but the system is

Title Description Completeto Date

Status Update Explanation

Fleet Operations

Public Engagement Training for Eligible Staff

Number of public space inspections

Street Light Maintenance

Preserving the Street Tree Canopy

Circulator BusProcurement

CirculatorOperations

CirculatorMaintenance

Integration ofDatabases for

11 of 21

intelligence tools or actual databaseintegration to ensure a method of centralreporting for the performance managementfunctions of the agency.

functional from Call for Projects toClose out. Protrack Plus is themain system for the projectpipeline. In addition DDOT hasselected a vendor to provide aupdate to our work managementsystem called Cityworks to matchwith our recent realignment to theagency and improve automation.These two system are part of thecore for DDOT’s daily effort andreporting on our progress to theEOM.

INTELLIGENT TRANSPORTATION SYSTEMS (1 Strategic Initiative)

This project is part of Washington D.C.'sgoal to improve overall traffic flow,optimize pedestrian crossing times andreduce bus delays. DDOT will continue itsprogram of systematically optimizing thetimings of all traffic signals. 1243 trafficsignals have been optimized to-date. In FY2017, DDOT will complete optimization oflast 384 traffic signals (Eastern corridor) inthe system. DDOT intends to continue thissystem-wide optimization program once inevery five years (1600+ traffic signals).

Complete New timing plans were developedand implemented for the lastnetwork (376 signals, North-Eastnetwork) in Summer, 2017. Itconcludes the Round-1 of theCitywide Signal OptimizationProgram (1650 traffic signals).

PERFORMANCE MANAGEMENT (1 Strategic Initiative)

Advance key Year 1 recommendations fromthe Multimodal Congestion ManagementStudy, including completion of an onlinevisualization tool summarizing studyperformance measure results,implementation traffic signal timingmonitoring and active management, andintegration of data and video fromoperations and monitoring systems into anAdvanced Traffic Management System(ATMS).

75-99% The annual update to ourCongestion Study has concluded.

This study is part of anongoing annual effort.

PLANNING (11 Strategic initiatives)

Construct improved lighting on the existingtrail to improve the experience for theusers.

0-24% Awaiting comments about legalsufficiency from OAG.

The construction estimate isover 1$M. Therefore thisproject needs to beapproved by the Council.Concurrently the Package iswith the OAG for legalsufficiency.

DDOT will begin the first phase ofconstruction which can include streetreconstruction efforts, improvements tosafety, utility relocation, ADA compliance

75-99% contract is awarded to PotomacConstruction, NTP by Mid-October

Delays in awarding thedesign-build contract.

PerformanceManagement

City-wide TrafficSignalOptimizationProgram

MultimodalCongestionManagementStudy

MetropolitanBranch TrailLightingEnhancements

MetropolitanBranch TrailConstruction

12 of 21

components, and storm water mitigation.

Complete design of the trail for the FortTotten to Takoma segment. Final designdevelops the preliminary designs into muchmore detailed plans, including detailsnecessary for construction such asdimensions, materials, and environmentalimpact plans. Final designs are used tosolicit construction services through theprocurement process.

25-49% Final Design is necessary before aconstruction contract can beissued for completion of the MetBranch Trail.

DDOT focused oncompleting the design-buildprocurement for theBrookland to Fort Tottensection of the trail andconducted additional publicengagement withcommunities along the FortTotten to Takoma section toaddress concerns in the30% design phase.

Complete short-term serviceimprovements. Service improvements wereidentified in the 16th Street Transit PriorityStudy and will improve Metrobus servicealong 16th Street NW.

25-49% Phase one recommendations willimprove bus transit service in thecorridor incrementally, with morelimited stop service.

Complete bus lane and stop improvementdesign. These will improve service for busriders across the city, including accessibilityimprovements.

25-49% DDOT is working with a consultantto develop bus lane configurationalternatives and completerequired environmentaldocumentation. DDOT is assessingbus stops for ADA compliance andidentifying inadequate stop zones.

This is a multi-year project

Advance Environmental Assessment andseek Finding of no Significant Impact(FONSI). This is a necessary component ofthe federal Environmental Assessmentprocess.

50-74% Technical analysis has madesubstantial progress. Additionalanalysis and maintenance andstorage facility underway withdraft to FHWA/FTA anticipated in2018 Q1.

DDOT has made significantprogress on advancing theEA. Most of the analysiswas complete in FY17 anddocumented results areexpected in FY18. A FONSIis anticipated in FY18.

Preliminary design consists of datagathering, requirements gathering, utilityassessments, land surveys, and civilengineering details such as storm waterneeds. The process incorporates the datagathering process with initial stakeholdermeetings to help inform the design processas it goes through development.

50-74% None. Ongoing project that wasnot anticipated to becomplete in FY17.

In coordination with community andgovernment partners, DDOT will site andinstall 20 new Capital Bikeshare stationsaround the city.

Complete DDOT installed 12 new CaBistations in Q4 FY17 and 31stations total in FY17.

Develop sponsorship program to allowcommunity partners to support CapitalBikeshare.

0-24% Potentially large impact, butArlington County is taking leadand we are waiting for them todevelop cooperative RFP.

Priority was on equipmentprocurement, and Arlingtonis taking lead oncooperative sponsorshipsolicitation.

The Eastern Downtown Protected Bike LaneStudy will determine the optimal locationfor a new protected bike lane in the

Complete Released study that recommendedproceeding with 30% design ontwo alternatives.

Complete DesignMetropolitanBranch TrailSegment fromFt. Totten toTakoma

16th Street NWTransit PriorityPlanning Study

16th Street NWTransit PriorityPlanning Study

Union Station toGeorgetownTransportationImprovements

Union Station toGeorgetownTransportationImprovements

Install CapitalBikeshare

CapitalBikeshareSponsorshipProgram

EasternDowntownProtected Bike

13 of 21

eastern area of Downtown DC.

Advance the Environmental ImpactStatement process for the Long Bridge overthe Potomac River.

25-49% Completion is expected in 2019 This is a multi-year projectwith an expected durationof 3 years.

POLICY DEVELOPMENT (6 Strategic initiatives)

Implement intersection improvementsthroughout the District to provide saferpassage for the users of our transportationsystem.

75-99% The new Vision Zero website willbe ready to launch in mid-October, 2017. The site willinclude the tableau dashboard andrequired reporting widgets. DDOTis also providing safety data toEOM for use in a city-widedashboard.

The website was nearlycomplete but underwent aredesign following OCTOinput. It has also beendelayed by ESRI limitations.We will move forward withbasic dashboards wherenecessary until ESRI addsfull functionality.

Complete development of risk-basedanalysis model that will assist with ourVision Zero goals and program.

75-99% DDOT has identified a firm (OpenData Nation) who will collaboratewith the Howard UniversityTransportation Reserach Center todevelop the risk analysis tool.ODN has submitted a proposal inrespose to DDOT's scope of work.DDOT and ODN are negotiatingthe terms of an agreement,particularly with regard tointelectual property and asubscription model. A notice toproceed should be issued in Q1 ofFY18.

The research programfunds to support thisproject were not availableuntil late July (due to STIPand other FHWA-causeddelays). Uncertainty aboutthe timing of fundingavailability (in flux fromFeb-July) prevented thecontracting process fromgetting substantiallyunderway before then.Upside was that thesummer intern was able tohelp put together a veryrobust scope.

In conjunction with other jurisdictions,DDOT is working to negotiate a 6-yearcapital funding agreement for WMATA withnew project prioritization and reportingrequirements.

Complete Mayor signed legislative packagefor the 1-year extensions to theCapital Funding Agreement andLocal Funding Agreement on6/30/17.

Establish an initiative to enhance safetythrough placemaking. Pilot safetyenhancements through placemaking effortsand public art in three locations. Activateand enhance amenities in poorly designedpublic spaces to maximize safety.Incorporate green infrastructure and low-impact design.

75-99% The Lincoln Rd NE site will beimplemented early in FY18. A thirdsite has not yet been identified.

OP and DDOT coordinationmay be improved throughan FY18 Vision Zero grant.

Pilot 25 MPH “Arterial Safe Zones” on twomajor streets. Pilot “Safe Neighborhoods”with 20 MPH traffic calming in tworesidential neighborhoods. Create 15 MPH“Safe Zones” around schools, parks, andhigh concentrations of seniors or youth toapply slower speed limits for expanded

75-99% DDOT plans to introduce aresolution to approve the 2ndproposed Vision Zero rulemakingas final. Meanwhile, an OAG andDDOT OGC legal opinion haveclarified that DDOT does not needto issue a rulemaking to change a

OPLA has not yet approvedthe introduction of aresolution.

Lane Study

Long BridgeEnvironmentalImpactStatement

IntersectionImprovementsfor our VisionZero Program

Vision ZeroInitiative- Risk-Based AnalysisModel

WMATA CapitalFundingAgreement

Vision ZeroInitiative:Placemaking andPublic Art

Vision ZeroInitiative: Createand pilotversions of "Safezones" intargeted areasin the District

14 of 21

hours. Support with Automated TrafficEnforcement. Evaluate safety impact.

speed limit, but instead can followthe NOI process, so long as thechange in speed limit etc. doesnot constitute a major policychange.

Establish one public location for all crashand safety data on the Vision Zero website.Data will be available in a machine-readable, open format. A datadashboard will display performance of topsafety metrics. Incorporate/emulatepublicly-sourced data such as “Struck inDC” or the Vision Zero safety map.

75-99% The new Vision Zero website willbe ready to launch in mid-October, 2017. The site willinclude the tableau dashboard andrequired reporting widgets. DDOTis also providing safety data toEOM for use in a city-widedashboard.

The website was nearlycomplete but underwent aredesign following OCTOinput. It has also beendelayed by ESRI limitations.We will move forward withbasic dashboards wherenecessary until ESRI addsfull functionality.

PROJECT DEVELOPMENT & MANAGEMENT (45 Strategic initiatives)

Preliminary design consists of datagathering, requirements gathering, utilityassessments, land surveys, and civilengineering details such as storm waterneeds. The process incorporates the datagathering process with initial stakeholdermeetings to help inform the design processas it goes through development.

Complete Now preparing task order for FinalDesign

Preliminary design consists of datagathering, requirements gathering, utilityassessments, land surveys, and civilengineering details such as storm waterneeds. The process incorporates the datagathering process with initial stakeholdermeetings to help inform the design processas it goes through development.

75-99% 90% is Complete, final is due byOctober 17

Final resolution of DDOTand community commentstook longer thananticipated.

Preliminary design consists of datagathering, requirements gathering, utilityassessments, land surveys, and civilengineering details such as storm waterneeds. The process incorporates the datagathering process with initial stakeholdermeetings to help inform the design processas it goes through development.

25-49% 30% Completed Ongoing project that wasnot anticipated to becomplete in FY17.

Preliminary design consists of datagathering, requirements gathering, utilityassessments, land surveys, and civilengineering details such as storm waterneeds. The process incorporates the datagathering process with initial stakeholdermeetings to help inform the design processas it goes through development.

75-99% DOEE stormwater permit and CFAapproval of safety fencing are stillpending.

Ongoing project that wasnot anticipated to becomplete in FY17.

Preliminary design consists of datagathering, requirements gathering, utilityassessments, land surveys, and civilengineering details such as storm water

75-99% coordinating with DC Water forconflicts. the 90% submission ison 10/18.

This is an ongoing projectthat was not anticipated tobe complete in FY17.

and evaluate thesafety impact.

Vision ZeroInitiative: Createa crash andsafety datadashboard.

Rehabilitation ofI-395 HOVBridge overPotomac River

MarylandAvenuePreliminaryDesign

Florida AvenuePreliminaryDesign

16th StreetBridge overPiney BranchParkway BridgeNo. 22

Eastern Avenue,New HampshireAvenue toWhittier Street

15 of 21

needs. The process incorporates the datagathering process with initial stakeholdermeetings to help inform the design processas it goes through development.

Final design develops the preliminarydesigns into much more detailed plans,including details necessary for constructionsuch as dimensions, materials, andenvironmental impact plans. Final designsare used to solicit construction servicesthrough the procurement process.

25-49% Ongoing. Ongoing project that wasnot anticipated to becomplete in FY17.

DDOT will begin the first phase ofconstruction which can include streetreconstruction efforts, improvements tosafety, utility relocation, ADA compliancecomponents, and storm water mitigation.

75-99% Construction in progress DDOT issued change orderto contractor to addresssome pedestrian accessissues and completeconstruction.

Preliminary design consists of datagathering, requirements gathering, utilityassessments, land surveys, and civilengineering details such as storm waterneeds. The process incorporates the datagathering process with initial stakeholdermeetings to help inform the design processas it goes through development.

75-99% Field inspection was completeafter a few months delays.Currently working on the finalreport.

Ongoing project that wasnot anticipated to becomplete in FY17.

DDOT will begin the first phase ofconstruction which can include streetreconstruction efforts, improvements tosafety, utility relocation, ADA compliancecomponents, and storm water mitigation.

0-24% The design is complete. B22-0184Financing Amendment Act of 2017was approved by Council andsigned into law by the Mayor. Thebiennial plan was submitted toPSC on July 3, 2017, and approvalis anticipated no earlier thanNovember 2017.

Approval of First BiennialPlan required prior tomoving forward.

DDOT will begin the first phase ofconstruction which can include streetreconstruction efforts, improvements tosafety, utility relocation, ADA compliancecomponents, and storm water mitigation.

25-49% Construction in progress, about40% complete

Ongoing project that wasnot anticipated to becomplete in FY17.

Preliminary design consists of datagathering, requirements gathering, utilityassessments, land surveys, and civilengineering details such as storm waterneeds. The process incorporates the datagathering process with initial stakeholdermeetings to help inform the design processas it goes through development.

75-99% Task Modification is addedfor additional work.

Ongoing project that wasnot anticipated to becomplete in FY17.

Preliminary design consists of datagathering, requirements gathering, utilityassessments, land surveys, and civilengineering details such as storm waterneeds. The process incorporates the datagathering process with initial stakeholder

75-99% R.O.W Acquisition Ongoing project that wasnot anticipated to becomplete in FY17.

NW

Broad BranchRoad, BeachDrive to LinneanAvenue NW

Kennedy StreetNWRevitalization

14th Street SWRamp Bridges(#170-1, 170-2,170-3)

PowerlineUndergroundingEngineering (DCPLUG) - Feeder308

Rehabilitation ofKey Bridge

Reconstructionof SB KenilworthAvenue NE

Rehabilitation ofKenilworthPedestrianBridges -DouglasPedestrian

16 of 21

meetings to help inform the design processas it goes through development.

DDOT will begin the first phase ofconstruction which can include streetreconstruction efforts, improvements tosafety, utility relocation, ADA compliancecomponents, and storm water mitigation.

50-74% Construction in progress Comments received areunder review by DDOT andFHWA. A FONSI isexpected shortly.

DDOT will begin the first phase ofconstruction which can include streetreconstruction efforts, improvements tosafety, utility relocation, ADA compliancecomponents, and storm water mitigation.

75-99% The construction will complete atthe end of October 2017

Planting and punch listexpected in first quarter ofFY18.

Preliminary design consists of datagathering, requirements gathering, utilityassessments, land surveys, and civilengineering details such as storm waterneeds. The process incorporates the datagathering process with initial stakeholdermeetings to help inform the design processas it goes through development.

50-74% None Ongoing project that wasnot anticipated to becomplete in FY17.

Begin the Program Management phase ofthis project that will provide consultingservices to assist with contract oversight,field reporting, outreach and qualitycontrols.

0-24% Work will not begin until BiennialPlan is approved, and thesolicitation process is initiated.Pre-Program Managementsolicitation currently with OCP.

Program ManagementSolicitation will be based offof deliverables of the Pre-Program Managementcontract, which is pendingaward.

Preliminary design consists of datagathering, requirements gathering, utilityassessments, land surveys, and civilengineering details such as storm waterneeds. The process incorporates the datagathering process with initial stakeholdermeetings to help inform the design processas it goes through development.

25-49% Stakeholder and agencyengagement is ongoing.

Ongoing project that wasnot anticipated to becomplete in FY17.

Begin the Program Management phase ofthis project that will provide consultingservices to assist with contract oversight,field reporting, outreach and qualitycontrols.

50-74% CM Services continue Ongoing project that wasnot anticipated to becomplete in FY17.

Preliminary design consists of datagathering, requirements gathering, utilityassessments, land surveys, and civilengineering details such as storm waterneeds. The process incorporates the datagathering process with initial stakeholdermeetings to help inform the design processas it goes through development.

75-99% The EA has been drafted andcirculated for public review andcomment. Received commentsare being reviewed by DDOT andFHWA. A FONSI is expected in Fall2017.

Final FHWA comments tooklonger than anticipated.

Preliminary design consists of datagathering, requirements gathering, utilityassessments, land surveys, and civilengineering details such as storm water

0-24% Consultant selection is completed Ongoing project that wasnot anticipated to becomplete in FY17.

BridgeReplacement

PennsylvaniaAvenue NWBridge over RockCreek

Oxon Run Trailfrom SouthCapitol to 13thStreet SE

SouthernAvenue Phase II

PowerlineUndergroundingEngineering (DCPLUG) - ProgramManagement

Cleveland ParkStreetscape andDrainageImprovement

PennsylvaniaAvenue NWBridge over RockCreek CM

PennsylvaniaAve./PotomacAve. Circle

H Street Bridge,NE, from NorthCap. To 3rdStreet

17 of 21

needs. The process incorporates the datagathering process with initial stakeholdermeetings to help inform the design processas it goes through development.

Preliminary design consists of datagathering, requirements gathering, utilityassessments, land surveys, and civilengineering details such as storm waterneeds. The process incorporates the datagathering process with initial stakeholdermeetings to help inform the design processas it goes through development.

75-99% Feasibility study started Dec. 7,2016., bridge layout and impact tonavigation channel revised, plan,elevation, and locations ofelements of the bridge parkrevised to reduce impact to theenvironment and utility lines.Bridge inspection and conditionassessment completed, bridgetouch down area and locations ofprogram area refined

It was not intended to becompleted in FY17; Phase Iwill be completed in FY 18.

Preliminary design consists of datagathering, requirements gathering, utilityassessments, land surveys, and civilengineering details such as storm waterneeds. The process incorporates the datagathering process with initial stakeholdermeetings to help inform the design processas it goes through development.

75-99% First 3 alleys starting construction10/20/17

Construction scheduled forFY18.

DDOT will begin the first phase ofconstruction which can include streetreconstruction efforts, improvements tosafety, utility relocation, ADA compliancecomponents, and storm water mitigation.

0-24% Effective contracting mechanismto effectively implement multiplesmall design projects.

Contract through FY19.

DDOT will begin the first phase ofconstruction which can include streetreconstruction efforts, improvements tosafety, utility relocation, ADA compliancecomponents, and storm water mitigation.

75-99% First 2 task orders nearingcompletion. 1 more task orderissued. Expecting 3 more taskorders before 1/1/18.

Contract through FY19.

Preliminary design consists of datagathering, requirements gathering, utilityassessments, land surveys, and civilengineering details such as storm waterneeds. The process incorporates the datagathering process with initial stakeholdermeetings to help inform the design processas it goes through development.

50-74% Working on the resolutions withstakeholders

Ongoing project that wasnot anticipated to becomplete in FY17.

Preliminary design consists of datagathering, requirements gathering, utilityassessments, land surveys, and civilengineering details such as storm waterneeds. The process incorporates the datagathering process with initial stakeholdermeetings to help inform the design processas it goes through development.

50-74% Ongoing. The first phase is scheduledto be completed in FY18.The second phase will becompleted in FY19.

Issue a Request for Proposal forConstruction Management services related

Complete Award planned for July 2017

11th StreetBridge Park

Green Alleys

GreenInfrastructureConstructionLocal IDIQ

GreenInfrastructureConstructionFederal IDIQ

Martin LutherKing Jr. AvenueCorridor Studyfrom SouthCapitol St. toMilwaukee Place

BloomingdaleGreenInfrastructure

SouthCapitol/Frederick

18 of 21

to the construction of the SouthCapitol/Frederick Douglass MemorialBridge.

Begin the Program Management phase ofthis project that will provide consultingservices to assist with contract oversight,field reporting, outreach and qualitycontrols.

50-74% This initiative has been meetingthe goals of the MOA betweenDDOT and CSXT.

It is an ongoing initiativewhich is driven by 3rd partyprogress.

Continue the ongoing program for PermitSupport on Mega Projects

25-49% This initiative has been meetingthe goals established by the LTCPMOU, and is ongoing.

It is an ongoing initiativewhich is driven by 3rd partyprogress.

DDOT will begin the first phase ofconstruction which can include streetreconstruction efforts, improvements tosafety, utility relocation, ADA compliancecomponents, and storm water mitigation.

25-49% Construction is underway Ongoing project that wasnot anticipated to becomplete in FY17.

Issue Request for Proposals for theconstruction of the South Capital/FrederickDouglas Memorial Bridge.

Complete Award planned for early summer

Begin the Program Management phase ofthis project that will provide consultingservices to assist with contract oversight,field reporting, outreach and qualitycontrols.

25-49% This initiative has been meetingthe needs of DDOT's AWI programand is ongoing.

This initiative is ongoingand was not intended to becompleted in FY 2017.

Final design develops the preliminarydesigns into much more detailed plans,including details necessary for constructionsuch as dimensions, materials, andenvironmental impact plans. Final designsare used to solicit construction servicesthrough the procurement process.

75-99% Final right-of-way acquisitionunderway.

Right-of-Way acquisitiontook longer than expected.

Begin the Program Management phase ofthis project that will provide consultingservices to assist with contract oversight,field reporting, outreach and qualitycontrols.

25-49% CM Services continue Ongoing project that wasnot anticipated to becomplete in FY17.

Final design develops the preliminarydesigns into much more detailed plans,including details necessary for constructionsuch as dimensions, materials, andenvironmental impact plans. Final designsare used to solicit construction servicesthrough the procurement process.

75-99% Final right-of-way acquisitionunderway.

The right-of-way acquisitiontook longer than expected.

Issue a Request for Proposal for the designof Anacostia Ave NE.

0-24% Task Order Issued for Phase I ofthe project; inspection of thebridges is 90% completed; projectcoordination with PEPCO, NPS,DOEE and DDOT planning group is

It was never intended to becompleted in FY17; Phase Iwill be completed in FY18.

DouglassMemorial Bridge

Virginia Ave.Tunnel

PermittingSupport MegaProjects

17th StreetImprovementsfrom Potomac toBenning

SouthCapitol/FrederickDouglassMemorial BridgeD/B Contract

AWI ProgramManagement

Reconstructionof OregonAvenue

Rehabilitation ofKey Bridge CM

Reconstructionof OregonAvenue

Rehabilitation ofAnacostia NEover AnacostiaRiver Outlet

19 of 21

on going.

Preliminary design consists of datagathering, requirements gathering, utilityassessments, land surveys, and civilengineering details such as storm waterneeds. The process incorporates the datagathering process with initial stakeholdermeetings to help inform the design processas it goes through development.

50-74% Ongoing Design scheduled for FY18completion and constructionfor FY19.

Final design develops the preliminarydesigns into much more detailed plans,including details necessary for constructionsuch as dimensions, materials, andenvironmental impact plans. Final designsare used to solicit construction servicesthrough the procurement process.

Complete

Begin the Program Management phase ofthis project that will provide consultingservices to assist with contract oversight,field reporting, outreach and qualitycontrols.

Complete None

Final design develops the preliminarydesigns into much more detailed plans,including details necessary for constructionsuch as dimensions, materials, andenvironmental impact plans. Final designsare used to solicit construction servicesthrough the procurement process.

75-99% Obligation of construction fundcompleted. Currently finalizingPS&E

Coordination with NationalPark Service onconstruction timeline andcanal access delayed finaldesign and constructionobligation.

DDOT will begin the first phase ofconstruction which can include streetreconstruction efforts, improvements tosafety, utility relocation, ADA compliancecomponents, and storm water mitigation.

Complete None

Final design develops the preliminarydesigns into much more detailed plans,including details necessary for constructionsuch as dimensions, materials, andenvironmental impact plans. Final designsare used to solicit construction servicesthrough the procurement process.

75-99% Obligation of construction fundcompleted. Currently finalizingPS&E

Coordination with NationalPark Service onconstruction timeline andcanal access delayed finaldesign and constructionobligation.

Begin a phased implementation of 16thStreet Bus Study's final recommendationsto help improve bus services along thecorridor.

25-49% The project will improve bus speedand reliability, improving theexperience for bus riders andreducing Metrobus operatingcosts.

It is an ongoing initiative.

This project began in FY16 to target 51high-priority bus stops that are in need ofimprovements to achieve ADA-compliance.FY17 should see the completion of theremainder of the 51 high priority locationsthat were not upgraded during FY16.

0-24% DDOT's Asset Managementdivision is upgrading high-prioritybus stops to ADA compliance

This is a multi-year project.

Oregon AvenueWatershed LID

AnacostiaFreeway overNicholson Street

Reconstructionof NB KenilworthAvenue NE

Replacement of31st Street NWBridge over C&OCanal

Reconstructionof NB KenilworthAvenue NE

Replacement of31st Street NWBridge over C&OCanal

16th Street BusLanes

ADA bus stopcompliance

20 of 21

DDOT will complete the AnacostiaRiverwalk Trail with the four-mileKenilworth Aquatic Gardens segment,linking Benning Road to the BladensburgTrail in Maryland.

75-99% Increase in trail connectivity. The trail is completed andopened to traffic sinceOctober 2016. Few punchlist items that were not yetaddressed by the contractorcould not allow closeout ofthe project.

STREET CAR (2 Strategic initiatives)

Finalize specifications for the next order ofvehicles that may be accepted for deliveryin FY18 or FY19.

0-24% Staff will await new PMC tocomplete vehicle design study.

DDOT is actively advancingits understanding ofstreetcar vehicle technologyand delivered a report toCouncil this yeardocumenting its findings.DDOT will continue to refineits approach to streetcarvehicles in FY18.

Currently under study, DDOT willbegin designs for both the Georgetown andBenning Road extensions of the DCStreetcar.

50-74% Currently conducting EA for USGTand Benning; Benning EA 95%complete and undergoing finalFHWA review; advertising SOW forBenning Design.

Both environmentalprocesses are nearingcompletion. The BenningExtension EA completedadditional noise analysisrequired by FHWA. A FONSIis anticipated in early FY18.The Union Station toGeorgetown EA has madesignificant progress. Most ofthe analysis was completein FY17 and documentedresults are expected inFY18. A FONSI isanticipated in FY18.

AnacostiaRiverwalk Trail -completeKenilworthextension

Streetcar VehicleProcurement

StreetcarExtensions