fyp 1 full
TRANSCRIPT
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 1/29
CHAPTER 1
INTRODUCTION
1.1 Introduction
Variation order (V.O) is a matter that often happened in construction
projects. Variation order is exist since early developed century. Knowledge
about variation order is important especially as an engineer and project
planner. It is very important because variation order can inuence the
additional cost of projects.
V.O is a modi!cation of contract document that agreed by contractor
and client. Variation order is a"ected by many reasons. #ll of the reason
need to be identi!ed so the problem in the project management can be
reduced. V.O is matter that related to the change that involving cost$ wor%s
and time.
&he main purpose of this project is to identify the main causes of V.O
in road construction in 'abah. ithout loo%ing for alternative to solve this
problem$ the client (government) will bear the expensive cost which could
not be estimated and could not be avoided. &he tendency for very high
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 2/29
occurrence of abandoned projects if the problem cannot be reduced. &he
losses imposed from variation order also identi!ed in this project.
*
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 3/29
'o$ an e"ectively solution can be !nd out in order to prevent or
reduce variation order in road construction in 'abah.
1.2 Defnition
&here are some important term used in this project which are
commonly used in a civil engineering road construction. +roject is the wor%
or tas%s to be underta%en. &he process of project management is used to
deliver the outcome.
# variation (sometimes referred to as a variation instruction$
variation order or change order) is an alteration to the scope of wor%s in a
construction contract in the form of an addition$ substitution or omission
from the original scope of wor%s. #nother term$ variation order is a written
order from the client,s representative authori-ing a variation under the
terms of the contract.
#ccording to O/rien (011)$ Variation Order contains a set of
instruction which allows changes or modi!cations to be made to an earlier
agreement in terms of volume or nature of tas% to be carried out. #nother
de!nition$ variation order is any modi!cation to the contractual guidance
provided to the 2ontractor by the client or the clients representative
(#rain 3 +heng$ *445). In other terms$ +ersatuan #r%ite% 6alaysia standard
form of contract (+#6 01) in clause $ de!ne variation as an alteration or
modi!cation of the design$ 7uality or 7uantity of the wor%s as shown in the
contract drawings and described by or referred to in the contract bills.
8
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 4/29
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 5/29
1.3 Background
&he road was !rst built during the reign of ;orth /orneo 2hartered
2ompany which also %nown ('yari%at /orneo >tara /ritish$ '/>/) in
'abah. &he main purpose of road during this era was to lin%ing economic
activities between the towns to the port. ?oad 2onstruction in 'abah was
developed slowly until independence during the formation of 6alaysia on
@ 'eptember 0@8. It is continue to develop until now. ;owadays$
roadway has been placed under administration of government. &here are
two types of road in 'abah which is 6alaysian Aederal ?oads 'ystem and
6alaysian 'tate ?oads 'ystem. 6alaysian Aederal ?oads 'ystem is the
main national road networ% in 6alaysia. #ll Aederal ?oads in 6alaysia are
under the purview of 6inistry of or%s (6O). #ccording to 6inister,s
Aunction #ct 0@0$ 6O responsible to plan$ build and maintain all Aederal
?oads ga-etted under the Aederal ?oad #ct 050. hile$ 6alaysian 'tate
?oads 'ystem are the secondary roads in 6alaysia. &he construction of
state roads in 6alaysia are funded by 6alaysian +ublic or%s Bepartment
(CK?) of each states.
Aederal Dovernment and 'tate Dovernment have a responsibilities
to maintain and ensure the 7uality and safety of the road in 'abah so that
it will be in good condition. ?epairs$ maintenance$ construction of road in
'abah was done on an annual basis. >sually$ the party that responsible in
this case +ublic or%s Bepartment (CK?)$ Bistrict 2ouncil or 2ity Eall. &his
wor% needs to be done so that road users can use it safely.
hen the government want to construct a road$ they will ma%e a
planning$ design$ cost estimating for the whole project. #fter that$ the
government will open tender to the contractor. #fter this process$ client
5
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 6/29
will award the project to the chosen contractor. 2lient and contractor will
ma%e an agreement of contract duration$ wor%s and value of the project
which contained in the contract document.
In road construction project in 'abah$ (V.O) is often faced by the
contractor during the road construction process. &his led to the allocation
for the construction of roads in 'abah are not !xed. &he study by
2haroenngam et al (*448) of variation orders on construction projects
found that the average cost escalation Variation Order usually occurs after
the contract is awarded.
'ometimes$ the wor%s could not be continue due to unexpected
wor%s$ which will lead to V.O. &he project that experienced variation orders
incurred more than 51F delay and cost increases when compared to those
no variation orders (Koush%i et al$ *448). #ccording to #rain 3 +heng
(*445)$ variation order do not only a"ect project performance in terms of
time and cost$ they also adversely a"ect the 7uality$ health and safety and
professional relations.
&here are another e"ects when the variation order exist in
construction projects. #ccording to O/rien (001)$ variation order in
construction project can cause productivity degradation$ interruption$
delays and redirection of wor% that are associated with variation orders
have a negative impact on labour productivity and procurement delay.
'ometimes$ rewor% and demolition also re7uired when variation order
exists (2lough and 'ears$ 001). It also can damage the !rms reputation
(Ais%$ 00G< Kumaraswamy et al.$ 001).
@
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 7/29
1. Pro!"e# $tate#ent
In this study$ the main causes of V.O along a road construction
project need to be identi!ed. Variation orders on construction projects
have the potential to unnecessarily increase the cost of construction.
'ome V.O wor%s must be carried out so that the overall wor% can be
continue to the project successful. &here are many V.Os cases happened
during the road construction project. V.O cannot be avoided completely
(6ohamed$ *44). It is important to identify the causes of V.O which may
occur during the road construction wor%. Identi!cation of their causes
might lead to their reduction$ possible elimination and subse7uent
improvement in overall project performance.
1.% O!&ecti'e(
&he objectives of this research areH
&o identify the main causes of Variation Order (V.O) for road
construction in 'abah.
&o determine the losses imposed from Variation Order (V.O).
&o determine the steps to avoid or reduce Variation Order (V.O).
1.) $co*e o+ ,ork
&he scope of this wor% generally focus on the main causes of
Variation Order of the project which has been complete. &his study also
determine the losses imposed for the Variation Order and to !nd out the
steps to avoid or reduce Variation Order. &he limitation of this study is that
G
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 8/29
it will just be conduct for the road construction in 'abah between !ve to
ten years ago$ with around *4 projects.
CHAPTER 2
-ITERATURE REIE,
2.1 Introduction
Variation in construction industry have become a common practice where
almost every project is su"ering ('segawa et al. *44*). &here are many
author also intimate that V.O are common to all types of projects (&homas$
Eorman$ Be 'au-a$ and Javs%i$ *44*< Oladapo$ *44G). &he study of Coint
1
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 9/29
Legislative #udit and ?eview 2ommission (CL#?2$ *44) on 844 road
construction project in Virginia revealed that average project change was
more than F. &here are many issues about V.O in construction industry.
&he nature and fre7uency of variations vary from one project to another
depending on various factors. (#rain and +heng$ *44@).
In this chapter$ some research is reviewed in which related with the causes
of variation order$ losses imposed due to variation order$ and steps to
avoid or reduce variation order in construction project. 6ost of the
previous research was focused on the general construction. &here are only
minority of previous research that focused on road construction.
*.* 2auses of Variation Order
&here were many causes of Variation Order in construction identi!ed
in many previous researcher. #ccording to ;diho%ubwayo ? et al.$ (*441)$
all of the causes can be categori-ed into = category which are owner
related variations$ consultant related variations$ contractor related
variation and other variation. 6oreover$ +atric% Keane et al.$ (*44) had
grouped the causes of variation order into three categories for the
contracting parties< Owner:related variations$ consultant:related variation
3 contractor:related variation where as non:contracting party:related
variation named as Mother variationN. #nother supportive statement$ #rain
3 +heng (*44@) has identi!ed four main origin agents of variation orders
which included client$ 2onsultant$ 2ontractor$ and other.
*.*. Owner ?elated Variation.
0
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 10/29
#rain and +heng (*44@) noted that the client as the project initiator
plays a major role in the construction project from the inception to the
completion. #s a result$ clients inuence the li%elihood of the occurrence of
variation orders. 2lients anticipate the needs and objectives of projects$
establish the scope of wor%s and the re7uired 7uality standards.
*.*.. 2hange of +lan or 'cope
2hange of plan or scope of the project is one of the most signi!cant causes
of variation in construction projects (2II$ 004). It is usually the result of
inade7uate or insucient planning at the project de!nition stage or
because of lac% of involvement of the owner in the design phase (#rain et
al.$ *44=). If the objectives of the project are inade7uately de!ned$ it is
common that clients will tend to change their minds along the way
(;diho%ubwayo$ *441). &his type of changes is normally costly especially if
made later in the construction process.
*.*..* 2hange of 'chedule
# change in schedule means that the contractor will either be
re7uired to provide additional resources or %eep some resources idle. In
both cases$ additional cost is incurred (Ais%$ 00G< O/rien$ 001). #
change of schedule during the project construction phase may result in
major reallocation of resources. &here are numerous causes of schedule
change such as mar%et conditions$ user re7uirements$ or lac% of funding.
*.*..8 Ainancial +roblem
&here are certain V.O was caused by Owners Ainancial +roblem. In
construction$ !nancial is one of the important thing to ma%e the project
successful. &he project cannot be implemented without !nancial. &he
4
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 11/29
owners !nancial problems can a"ect project progress. (2lough and 'ears$
00=< O/rien$ 001). Ainancial is necessary in all of wor%s such as
operation of machineries$ machineries maintenance$ payment of wor%ers$
uses of materials$ insurance$ and etc. ;evertheless$ there is also a
relationship between client !nancial and V.O. 'ometimes$ client had faced
an unexpected !nancial diculty during construction stage. &his situation
can force a client to ma%e changes in an attempt to reduce cost in order to
suite their conditions (;diho%ubwayo$ *441).
*.*..= Impediment to +rompt Becision:6a%ing +rocess
2lient or owner is the one who have the rights in decision:ma%ing.
2lient must ma%e a decision for any problem promptly. +rompt decision
ma%ing is an important factor for project success ('anvido et al.$ 00*<
Dray and Eughes$ *44). Aailure to ma%e the decision eciently may result
in the delay or waiting time which can lead to V.O due to cost increments.
It also give adverse e"ects on project performance.
*.*..5 2hange in 'peci!cations by the Owner
2hanges in speci!cation is a common phenomenon in construction
projects with inade7uate project objectives (O/rien$ 001). If these
changes in the speci!cation of the design or re7uirement are carried out$
this leads to variations in the construction phase.
*.*..@ 'ubstitution of 6aterials by the Owner
'ubstitution of material also by owner also may occur due to
inability of client to ma%e decision on the selection the appropriate type of
materials to be used in construction (;. 6ohammad et al.$ *44). &his type
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 12/29
of changes normally results in additional time and claims by the
contractor.
*.*..G Obstinate nature of owner
2onstruction projects are resulted from the combined e"orts of the
various professionals wor%ing together at various interfaces of the project
(ang$ *444< #rain et al.$ *44=) and many times approval of the owner is
re7uired. If the owner is obstinate$ it can cause hindrances in wor%ing$ and
result in variations at the later stages of a project. It has signi!cantly
a"ected time and cost performance in construction projects.
*.*.* 2onsultant ?elated Variation
;diho%ubwayo and Eaupt (*441) observed that the consultant team
includes architects$ designers$ specialist engineers$ project managers$
surveyors$ 7uantity surveyors and construction economists. 6embers of
the consultant team have power to e"ect variation orders upon delegation
by the client or on their behalf. 2onsultant ?elated Variation usually
generated during design phase. 6endelsohn (00G) observed that
probably G5F of the problems encountered on site were generated at the
design phase.
*.*.*. 2hange in Besign by 2onsultant
# change in design improvement by the consultant is a norm in
contemporary professional practice (#rain et al.$ *44=). 2hanges in design
were fre7uent in projects where construction starts before the design is
!nali-ed (Ais%$ 00G). &hese changes inuence the project from a di"erent
aspect depending the time when changes are incurred.
*
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 13/29
*.*.*.* Besign 2omplexity
If the design made by consultant is simple and clear$ it is very
helpful for labour to understand and execute the wor%. 2omplex designs
can cause misunderstanding and misinterpretation which lead to deviation
and re7uire uni7ue s%ills and construction methods to perform the wor%
(#rain et al.$ *44=). 2omplexity a"ects the ow of construction activities$
whereas simpler and linear construction wor%s are relatively easy to
handle (Ais%$ 00G). In other words$ if the complexity of the design
increases this will create more opportunities of variations in the project.
*.*.*.8 Inade7uate or%ing Brawing Betails
In achieving ecient wor%ing on the site$ it is very important to
have complete project design$ clear and concise wor%ing drawing (Deo%$
*44*). Inade7uate wor%ing drawing details can result in misinterpretation
of the actual re7uirements for the project (#rain et al.$ *44=) which
causing variations in the project.
*.*.*.= Lac% of 2oordination
#s a consultant$ coordination to a contractor especially in wor%
process is important to ma%e sure the result is following the speci!cation.
#ccording to #dnan Pnshassi et al.$ (*44)$ lac% of coordination is one of
the most important factor of V.O which under consultant related factor.
Lac% of coordination will inuence the 7uality of wor%s. Pvery scope of
wor% that need to be constructed by contractor re7uire a coordination from
a consultant. It is very important in a construction project to %eep strong
8
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 14/29
and continuous coordination to ma%e sure all wor%s following according to
plan (#l:Bubaisi$ *444).
*.*.*.5 2onicts between 2ontract Bocuments
2onict between contract documents often results in
misinterpretation of the project re7uirements (2II$ 01@). Aor successful
projects$ it is important that the contract documents are clear and precise.
&his conict may be occur because of the tender documentation is not
carried out precisely to include comprehensive tender drawings$
speci!cations$ conditions of contract$ and bills of 7uantities that are
responsive to the proposed wor%s (Oloo$ *45). &his is due to di"erent
documents are drawn by di"erent engineers or design personnel during
the design phase of the project which can cause discrepancies in contract
documents (#l:Bubaisi$ *444).
*.*.*.@ Prror and Omission in Besign
It is impossible to create a 44F error free design. Are7uently$
among the many contract documents of the project$ some of detail was
mis:referenced or an incomplete speci!cation sheet. Besign errors which
are not recti!ed during the design phase will eventually appear and faced
in the construction phase by contractor where the impact can be more
severe than in the design phase (2happell and illis 00@). Besign
omission may lead to loss of productivity and delay of the project schedule
(#l:Ea-ami 01G).
*.*.*.G &echnology 2hange
&echnology change may inuence a consultant to initiate V.O.
Jimmerman and Eart (01*) stated that it is impossible to be
=
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 15/29
%nowledgeable of all new materials and products that are constantly
entering the mar%et. 6ajority construction projects especially for the
project which have technology items might face this reason for change
especially if the time between design and construction is long. &he
technology used which speci!ed in the contract document is no longer as
same as the technology during the contractor start the construction which
may lead to V.O. Eowever$ it is not necessary to change whatever has
been speci!ed in the original design just to accommodate the new
technology$ material or product unless it gives impact to the function or
operation of the construction (Eamdan$ *4*).
*.*.*.1 Lac% of 2onsultants Knowledge of #vailable 6aterials and
P7uipment
#rain and +heng (*44@) and +atric% Keane et al.$ (*44) identi!ed that lac%
of consultants %nowledge of available materials and e7uipment is one of
the causes of V.O in which originated by consultant. Knowledge of
available materials and e7uipment is an important factor for developing a
comprehensive design (2ox and Eamilton 005< #ssaf et al.$ 00@). Buring
design stage$ consultant have an important role to choose a suitable
material for a certain design. &he lac% of construction %nowledge about
available materials and e7uipment may a"ect the project adversely
(#drian 018< #l:Ea-mi 01G).
*.*.*.0 2onsultant,s Lac% of Cudgment and Pxperience
5
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 16/29
Knowledge and experience are the important criteria to be considered for
each personnel involve in the construction industry (Eamdan$ *4*).
+rofessional experience and judgment is an important factor for successful
completion of the construction project (2lough and 'ear 00=< OQ/rien
001). &he lac% of professional experience may increases the ris% of errors
in design and also during construction progress which also lead V.O to
occur. # consultant must have sucient experience and judgement when
involving in a construction project. It is important because of a
construction project have to deals with human life and properties$ safety
and health re7uirements (Eamdan$ *4*).
*.*.8 2ontractor ?elated Variation
'weeney (001) stated that it is the contractors responsibility to
advise the consultant to issue a variation order when a technical problem
is discovered. #ccording to 'weeney (001) a contractor may propose
alternative construction methods where his experience shows that the
proposed technology will not ful!l the desired !tness and function of a
design.
*.*.8. >navailability of P7uipment
2onstruction project involves many heavy wor%s that need to be done in
order to complete the construction. In order to carry out all of the wor%s$
various e7uipment are re7uired so that the wor% can be handle in smooth
way and faster. #vailability of ade7uate and sucient number of
e7uipments plays a major role in project success. 2ontractor sometimes
have limited number of e7uipment which they swipe from one project to
other. >navailability of e7uipment is a procurement problem that can
@
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 17/29
a"ect the project completion (O/rien$ 001). &his problem also can lead
to variation order. #rain 3 +heng (*44@) indicated that unavailability of
e7uipment is one of the causes of V.O which originated by 2ontractor.
*.*.8.* +oor or%manship
+oor wor%manship is one of the problem faced to the contractor
which my lead to V.O (#rain 3 +heng$ *44@). 2ontractor must have a good
7uality wor%manship in order to ma%e a good 7uality construction. +oor
wor%manship may lead to demolition and rewor% in construction projects
(Ais%$ 00G< O/rien$ 001). >nsatisfactory wor%ing result re7uire
demolition and rewor% to repair the defect in construction which can cause
delay$ wasting material and increased cost.
*.*.8.8 Lac% of 'trategic +lanning
+roper strategic planning is an important factor for successful
completion of a building project (2lough and 'ears$ 00=). &he lac% of
strategic planning is a common cause of V.O in projects where construction
starts before the design is !nali-ed (O/rien$ 001). It imposes negative
e"ects in the project where execution wor%s are started before the design
wor% is completely !nished. &his is a common case in projects awarded
based on concurrent design and construction contracts (O/rien$ 001<
#rain$ *44=).
*.*.8.= +oor +rocurement +rocess
+oor procurement process reects the delays in procuring the
resources re7uired for the project. It exerts various adverse e"ects on the
construction cycle of activities (Ais%$ 00G). It can also result in the entire
G
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 18/29
change of plan or replacement for speci!ed materials or e7uipments of
any project (#rain$ *44=).
*.*.8.5 2ontractors Ainancial Biculties
2onstruction is a labor intensive industry. 2onstruction wor% not only
rely on machineries. It is also re7uire group of labor to wor%s. &he labor is
paid for the wor%s they have done. hether the contractor has been paid
or not$ the wages of the wor%er must still be paid (&homas and ;apolitan$
005). If a contractor experiences !nancial diculties during the course of
a project$ it may result in lac%ing of resource availability regardless s%illed
or uns%illed labor. 2onse7uently$ the progress of the project is a"ected
which may re7uire V.O.
*.*.8.@ 'hortage of '%illed 6anpower
2onstruction projects highly depend on s%illed manpower for
performing technical activities (#rain$ *44=). Lac% in s%illed manpower can
slow down the wor%s and also ma%e mista%es in wor%ing which will a"ect
the project performance (6emon$ *4< #ssaf$ *44@).
*.*.8.G Bi"ering 'ite 2ondition
6any time$ contractor will encounter the di"ering site conditions.
'amantha (*44*) stated that during the construction of a project$
contractors often encounter subsurface or hidden conditions which were
not anticipated and which may have a major impact on the time and cost
of performing their wor%. Pxample of case that fre7uently occur$ a
contractor encounter roc% instead of soft soil which not indicated in the
1
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 19/29
tender document. &his situation re7uire extra wor% for excavation need to
be perform by a contractor and the contractor have a right to claim a
compensation for the extra wor%s.
#ccording to 'teven and Baniel (*441)$ it is an owners obligation to
provide complete and accurate information to the contractor regarding
conditions at the construction site such as unanticipated geological
conditions$ water intrusion$ underground pipe or cable$ and other types of
impediments to the clearing$ grubbing and grading of the site. It also
might be owners do not learn as much about the site conditions as
possible before entering into the contract (Oloo$ *45). V.O can be claimed
by the contractor due to this problem.
*.*.= Other Variation
&here are also other variation that not related to participants neither
client$ consultant$ nor contractor. #rain and +heng (*44@) observed that
situations beyond the control of the contractual parties may give rise to
variation orders$ these include< weather conditions$ and safety
considerations$ change in government regulations$ change in economic
condition$ and unforeseen problems.
*.*.=. eather 2ondition
#dverse weather conditions can a"ect outside activities in
construction project (Ais% 00G< O/rian 001). eather 2ondition problem
is often faced during the construction which can lead to Variation Order in
2onstruction. 'ome of weather condition can be predicted in aspect time
of occurrence$ period of occurrence$ or type of weather condition. eather
0
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 20/29
condition problem that commonly happened in construction such as hot
season$ high wind$ rainy season$ cold season and etc. 'ometimes$ the
contractor is forced to alter his wor% schedule due to weather conditions
such as high temperature or high winds (#l:Bubaisi$ *444). #ccording to
6ar% (*4*)$ the timing or se7uence of wor% in construction project can be
varied in order attempting to avoid inclement weather condition where the
weather pattern can be predicted. 'o that$ the contractor may claim the
VO for compensation according to contract terms.
*.*.=.* 'afety 2onsideration
If some safety aspects were overloo%ed during the design phase$
the owner or consultant may initiate a change to install additional safety
features in the facility (#l:Bubaisi$ *444). &his can not be di"erent from
any other design oversight$ except for the fact that safety is usually un:
compromised.
*.*.=.8 2hange in Dovernment ?egulation
&his type of causes is rarely happened in construction project but it
have possibility to occur. Local authorities may have speci!c codes and
regulations that must be adhered to. ;ormally the designer insures that
his design is in compliance with these codes. Eowever$ new regulations
may be issued between design and construction and may force some
changes to the original plan (#l:Bubaisi$ *444). 2odes such as
environmental or labor codes are revised periodically and the contractor or
facility owners are re7uested to comply.
*.*.=.= 2hange in Pconomic 2ondition
*4
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 21/29
+rice ination9uctuation of construction materials commonly occur
from time to time especially the materials imported from foreign country.
&he non:!xed currency will cause price ination9uctuation of the material.
Pconomy related with supply and demand in the construction mar%et is
unpredictable (Eamdan$ *4*). Pconomic conditions are one of the
inuential factors that may a"ect a construction project (Ais% 00G).
*.*.=.5 >nforeseen +roblem
'ometimes$ there are unforeseen problem that beyond the control
of sta%eholder that can lead to variation order. &here are many unexpected
tragedy such natural disaster$ war$ riot and other in which can inuence
the construction project.
?eferring to clause 5G.* in 2ondition of 2ontract$ +B Aorm *48#
(?ev. 9*44)$ an MPvent of Aorce 6ajeureQ is an event beyond the control
of both parties which are<
a) war (whether declared or not)$ hostilities$ invasion$ act of foreign
enemies<
b) insurrection$ revolution$ rebellion$ military or usurped power$ civil
war$ terrorism<
c) natural catastrophe including but not limited to earth7ua%es$ ood$
subterranean spontaneous combustion or any operation of the forces of
nature against which and experienced contractor could not reasonably
have been expected to ta%e precaution.
d) ;uclear explosion$ radioactive or chemical contamination or
radiation (unless caused by negligen act$ omission or default of the
contractor$ its agents or personnel)<
*
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 22/29
e) +ressure waves caused by aircraft of other aerial devices travelling a
sonic or supersonic speeds< and
f) ?iot$ commotion or disorder$ unless solely restricted to employees of
the 2ontractor or its personnel$ servants or agent.
In view of the above and if there are any damages leads to rewor%$
contractor are eligible for the variation order.
*.8 Losses Imposed due to Variation Order
#rain and +heng (*445) di"erentiate two types of VO$ namely Mbene!cialN
and MdetrimentalN variation orders. # bene!cial variation order is one
issued to improve the 7uality standard$ reduce cost$ schedule$ or degree of
diculty in a project (#rain and +heng$ *445). hile a detrimental
variation order is one that negatively impacts the client,s value or project
performance (#rain and +heng$ *445). Betrimental variation order are
focused in this research which are related to losses impact.
&here are two major losses imposed due to VO based on previous research
which are time and cost aspect. /oth of the aspects are related to the all
causes of VO. #ccording to 6ohamed (*44)$ the more variation orders on
a project$ the greater the li%elihood that they become time consuming and
costly elements in construction projects. Eanna et al. (*44*) also found
that as a number of variation orders increases the more signi!cant
productivity losses become.
**
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 23/29
*.8. 2ost
Losses are imposed in terms of cost in various ways when the VO
exist in construction project. #lmost all of V.O that exist in construction
project are related to cost aspect. Increment in the project cost is one of
the main e"ects observed of V.O (#rain and +heng$ *445). Eanna and
Dundu- (*44=) estimate that the >nited 'tates construction industry spent
>'B 8:*@ billion in year for construction V.O. 2II (004)< Esieh et al.
(*44=)< 6ohamed (*44)< ?anda et al. (*440)< Jeiton 3 Oberlender (008)
agreed that variation orders contribute to @:GF cost overruns in
construction projects. #ccording to #mirruddin et. #l$ (*4*)$ increase in
project cost is one of the most e"ect in roadway construction projects in
south of Iran.
&he increase in the project cost is caused by any major additions or
modi!cations to the design (2lough and 'ears$ 00=). Bemolition and
rewor% are example of e"ect of V.O in construction project where it re7uire
additional cost to be implemented (#l:Bubaisi$ *444). 'ome V.O will force
for demolition and rewor% to be done if any addition$ modi!cation or
change on design that have been constructed. Bemolition and rewor%
re7uire machineries and wor%er in which both of this need additional
payment. #dditional payment that exist to implement the demolition and
rewor% will cause cost overrun. 'ometimes$ the V.O exist in the
construction project$ new materials$ tools and e7uipment which not stated
in original contract are needed to implement wor%s that stated in V.O. and
it also re7uire additional cost.
*8
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 24/29
V.O also can cause increasing in overhead cost. V.O re7uire
processing procedures$ paper wor% and reviews before they can even be
implemented (O,/rien $001). &he process and implementation of
variations in construction projects would increase the overhead expenses
for all the participants concerned. ;ormally these overhead charges are
provided for from the contingency fund allocated for the construction
project.
*.8.* &ime
6ost of the researcher found that V.O can cause the delay or time
overrun in construction process. &here are several authors agreed that
variation orders present as one of the reasons for project time overruns
(2han and Reong$ 005< 6ohamed$ *44). V.O always disrupt the project
progress which leading to delay in achieving the targeted time of
completion (2II$ 005$ Ibbs$ 00G). V.O are the reason why most
contractors dont meet up with the time speci!ed for completion of most
contract wor%s (+ourrostam and Ismail$ *4< #mu et al$. *445). #ccording
to Jeiton and Oberlender (008)$ V.O may delay the projects about 0F of
the original scheduled time duration.
# study conducted by 'ambasivan and 'oon (*44G) showed that in *445
about G.5F (of government contract projects in 6alaysia) were
considered as sic% which is more than 8 month delay or abandoned. &he
losses in term of time was exist when the construction project encountered
a delay problem. &here are 54F construction project in Eong Kong were
delayed because of VO (Kumaraswamy et al.$ 001).
*=
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 25/29
&here are several reason how VO can inuence the additional time in
construction such as rewor%$ material delivery and local authority
approval. V.O in construction often results in rewor% and demolition
(2lough and 'ears$ 00=). #dditional time was re7uired in rewor% and
demolition which must be done.
#nother e"ect of V.O in construction project is logistic delays. Logistic
delays are among the signi!cant e"ects of V.O in construction projects
(Eester et al.$ 00). V.O may cause the existence of new re7uirement or
additional amount of material and e7uipment which results in logistic
delays (Ais%$ 00G). &his additional amount of material and tools that
re7uired to carry out a certain activity sometimes need a period of time for
delivery or transportion to site construction. &he losses in term of time also
exist during the period of material transportation which can lead to
extension of time in construction project.
#ll V.O needs approval from local authorities before it can be implemented.
Local authority have a responsible to approve the V.O in construction
project and to ensure all developments comply with the laws and
regulations relates to the construction project. &he process of V.O approval
sometimes prolonged and may cause delays to the project (Eamdan$
*4*). Aactor of delay in local authority approval may be due to changes in
ocer in:charge and also 2hange of Dovernment policy.
*.= 'tep to #void or ?educe Variation Order.
*.=. 'elect 2ompetent 2onsultant 2ompany
2onsultant are the important parties which has a role as advisor to
the client in construction project. 2onsultant will give a technical advise to
the client about the whole construction project. Jou et al.$ (*445)$ studied
*5
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 26/29
the %ey ris%s in construction project and found that incomplete or
inaccurate cost estimate is directly related to the designer9consultantsQ
%nowledge and experience. 'o that$ selection of competent and
experience consultant company is very important. It is advisable to the
client to appoint those consultant based on their expertise and experience
to suit the type of projects to be implemented. /y choosing experienced
consultant could minimi-e the inaccuracy and also might avoid V.O.
*.=.* Pnhance 2ommunication and 2oordination
2ommunication and coordination is a management tool in construction
management which are important element and must be enhanced by all
parties involved in the project implementation. 2oordination and direct
communication will abolish design discrepancies$ errors and omissions in
design. It also provide an opportunity for professionals to review the
contract documents thoroughly which can help in eliminating the
variations arising because of conicts in contract documents (;or Eayati
Ibrahim$ *44@).
#ccording to Ea-rin Eamdan (*4*)$ +oor communication and coordination
will cause lost of data or information collection due to this should be a
teamwor% based. #ccording to Caspal et al.$ (*44)$ good coordination and
involvement of all professional parties and even the client is important in
developing creative and practical ideas which can minimi-e discrepancies
and resulting in V.O reduction. &he consultant has to update the contractor
of any concern he might have with the scheduled wor%. Other than that$
the ways to improve coordination can be done by carry out coordination
meetings$ progress reports$ and conference calls among others (#l:Bubaisi$
*444).
*@
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 27/29
*.=.8 2lear and &horough /rief 'cope of or%
2lear and thorough project brief would be given to all participants involved
in the project especially to a consultant. # consultant will design the scope
of wor% included in the construction project based of clients re7uirement.
&hus$ 2lient should aware with what they want and the constraint they
might faced. >yun (*44G) remar%ed that it is sometimes very dicult to
determine the exact re7uirements of the client. &hat is the reason the
client should properly de!ne and brief to consultant on what are the
important re7uirements to be incorporated.
2lient should set a boundaries about the scope of wor%s$ established the
re7uirements$ !nancial constraints and de!ne the function of the projects
in order for the consultant to digest the information prior to the design
commencement process. 'o that$ consultant can give an advice about all
the clients re7uirement. 2lear and thorough project brief will assist in
eliminating V.O that may arise when the project had started and it may
assist in developing a clear scope of wor% for the parties that involved on
the project (#ftab et al.$ *4=)
*.=.= ?easonable Buration for +lanning and Besign
2onsultant need time to implement the tas% that should be done. #s a
consultant$ they need sucient time for planning and design stage. If
there are only short time given to consultant$ it is high probability of
mista%e that they will ma%e. &ime limitation may occasionally force the
designer to wrap up the necessary design wor% at lower 7uality (#l:
6ansouri 011). &he client should allocate the reasonable or practical
duration for the for planning and design stage$ in order to avoid design
*G
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 28/29
fault$ to produce a 7uality tender document before the tender stage
(Ea-rin Eamdan$ *4*).
#ccording to Jou et al.$ (*445)$ client should prepare a practical
schedule which is sucient but not redundant time to accommodate all
design and construction activities to avoid Mtight project scheduleQ. &ime
and cost are always correlated in project. &he more period of the schelude$
the more cost will be utili-ed. # lengthy schedule will decrease the project
cost bene!t. &he client and consultant should not be in a hurry about
contract documentation and ensure the detailed architectural and
engineering drawing are made available to the 7uantity surveyor for
detailed bill of 7uantities before tender (#yodele Plijah Olusegun$ *44).
*.=.5 +roper Investigation 3 +lanning Buring +re:&ender
+roper investigation and ade7uate planning must be carried out
properly at the initial stage (in pre:tender period) in order to reduce V.O
(?anasinghe$ *4*). &he involvement of 7uali!ed profesional sta"$ such as
profesional engineers$ specialist and experts are important in early stage
in order to explain and provide solutions to technical circumstance.
#ccording to #ftab Eameed 6emon et al. (*4=)$ professionals should
participate from design phase to assist in clarifying the project objectives
and in identifying the noncompliance with their re7uirements at early
stages in order minimi-ing the occurrence of V.O in CK? projects.
Initial survey and site investigation such as visual inspection to site$ des%
study$ determining the standard to be used$ %nowing the history of the
site$ land surveying and soil investigation is a part of designing procedure
which need to be done in early stage which must be carry out properly.
Inade7uate or insucient site information such as soil report and survey
*1
8/17/2019 FYP 1 FULL
http://slidepdf.com/reader/full/fyp-1-full 29/29
report can a"ect the construction. +rior to any design scheme$ all relevant
test and survey with the government agencies and nearby buildings
should be conducted to ascertain the site conditions and reduce
unexpected ris%s (+atric% S.. Jou et al.$ *445).