gannabosch vlakte 51 mining rights application - umvoto · gannabosch vlakte 51 mining rights...
TRANSCRIPT
Gannabosch Vlakte 51 Mining Rights Application
NAME OF APPLICANT: GANNABOSCH CLAY MINE (Pty ) Ltd.
DMR REFERENCE NUMBER: WC30/5/1/2/2/10082MR
UMVOTO REFERENCE NUMBER: 856/05/01/2016
FARM NAMES: Gannabosch Vlakte 51
PROVINCE: Western Cape
DATE: April 2016
AS REQUIRED IN TERMS OF REGULATION 49 OF THE MINERAL AND PETROLEUM
RESOURCES DEVELOPMENT ACT (ACT 28 of 2002), AND IN ACCORDANCE WITH THE STANDARD DIRECTIVE FOR THE COMPILATION THEREOF AS PUBLISHED ON THE
OFFICIAL WEBSITE OF THE DEPARTMENT OF MINERAL RESOURCES.
SCOPING REPORT
Prepared for: Prepared by:
Gannabosch Clay Mine (Pty) Ltd
Final Draft
April 2016
Umvoto Africa (Pty) Ltd. Earth. Water. Science. Life
P.O. Box 61 Muizenberg 7950. Telephone: (021) 709 6700. Fax: 086 685 5725
E-mail: [email protected] Internet: www.umvoto.com
Reg. No.: 2001/013609/07
Directors: E R Hay, C J H Hartnady Associates: K Riemann, R T Wonnacott, F S Botha, W J Gouws
REPORT TITLE : Scoping Report
CLIENT : Gannabosch Clay Mine (Pty) Ltd PROJECT : Gannabosch Vlakte 51: Mining Rights
Application AUTHORS : Greg Molzen
Paul Lee Luke Towers Eddie Wise
REPORT STATUS : Final Draft REPORT NUMBER : 856/03/01/2016 DATE : April 2016 APPROVED BY :
Gannabosch Clay Mine (Pty) Ltd Umvoto Africa (Pty) Ltd Director Project Manager Morne Swanepoel Paul Lee
This report is to be referred to in bibliographies as: Umvoto Africa. (2016). Gannabosch Vlakte 51: Mining Rights Application – Scoping Report. Prepared by G. Molzen, P. Lee, L. Towers and E. Wise of Umvoto Africa (Pty) Ltd for Gannabosch Clay Mine (Pty) Ltd. Report No. 856/03/01/2016, April 2016, 45pp.
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 2
TABLE OF CONTENTS
Chapter Description Page
TABLE OF CONTENTS 2
LIST OF TABLES 3
LIST OF FIGURES 3
DEFINITIONS 4
DMR STANDARD DIRECTIVE 5
DESCRIPTION OF EIA PROCESS 5
BACKGROUND 6
1. SCOPING 7
2. DESCRIPTION OF EXISTING ENVIRONMENT 11
3. IDENTIFICATION OF THE ANTICIPATED ENVIRONMENTAL,
SOCIAL OR CULTURAL IMPACTS, INCLUDING THE
CUMULATIVE IMPACTS, WHERE APPLICABLE. 26
4. LAND USE OR DEVELOPMENT ALTERNATIVES, ALTERNATIVE
MEANS OF CARRYING OUT THE PROPOSED OPERATION AND
THE CONSEQUENCES OF NOT PROCEEDING WITH THE
PROPOSED OPERATION. 35
5. A DESCRIPTION OF THE PROCESS OF ENGAGEMENT OF
IDENTIFIED INTERESTED AND AFFECTED PARTIES,
INCLUDING THEIR VIEWS AND CONCERNS 38
6. DESCRIBE THE NATURE AND EXTENT OF FURTHER
INVESTIGATIONS REQUIRED IN THE ENVIRONMENTAL IMPACT
ASSESSMENT REPORT INCLUDING ANY SPECIALIST
REPORTS THAT MAY BE REQUIRED 42
7. ADDITIONAL INFORMATION 44
8. REFERENCES 45
APPENDIX A – MAPS I
APPENDIX B- INTERESTED AND AFFECTED PARTIES REGISTER I
APPENDIX C: INTERESTED AND AFFECTED PARTY RESPONSES VIII
APPENDIX D: CIPRO (GANNABOSCH CLAY MINE (PTY) LTD. XXVIII
APPENDIX E: TITLE DEED ( GANNABOSCH VLAKTE 51) XXIX
APPENDIX F: LAND AFFAIRS RESPONSE XXX
APPENDIX G: NEWSPAPER ADVERTISEMENT XXXII
ANNEXURE A: BACKGROUND INFORMATION DOCUMENTS XXXV
ANNEXURE B: CLAY ANALYSIS XXXVI
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 3
LIST OF TABLES
Table 1: Listed affected parties 8
Table 2 : Noise limits per sector 15
Table 3: Stratigraphy 17
Table 4: Wind speeds (km/h) between January 2014-December 2015 (saexplorer,
2015). 21
Table 5: Wind direction summary table 23
Table 6 : Listing Notice 1 (No. R. 983) Triggers in terms of 24 (2) and 24D 27
Table 7 : Listing Notice 2 (No. R. 984) Triggers in terms of 24 (2) and 24D 27
Table 8 : Listing Notice 2 (No. R. 985) Triggers in terms of 24 (2) and 24D 27
Table 9 : Heritage impacts 28
Table 10 : Socio-economic impacts 28
Table 11 : Community impacts 29
Table 12 : Biophysical impacts 31
Table 13 : Land Use 35
LIST OF FIGURES
Figure 1: Composite climate diagram of the Robertson region. Blue bars show the
median monthly precipitation. The upper and lower red lines show the mean
daily maximum and minimum temperatures respectively (After Mucina and
Rutherford, 2006). 19
Figure 2 : Average, maximum and minimum daily temperatures throughout the day, with
the horizontal axis representing months of the year, starting with January (1)
and ending with December (12). 20
Figure 3 : Predominant Wind Direction January 2014 - December 2015 (weatheronline,
2015) 21
Figure 4 : Wind rose of the Worcester/Robertson region 22
Figure 5: Regional Topographic Map II
Figure 6: Locality Map III
Figure 7: Geology Map IV
Figure 8: Land type/soil cover Map V
Figure 9: Vegetation Map VI
Figure 10: Biodiversity Map VII
Figure 11: Mine Layout Map VIII
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 4
Acronyms
DRDLR - Department of Rural Development and Land Reform
SANBI - South African National Biodiversity Institute
CBA - Critical Biodiversity Area
BID - Background Information Document
BP - Before Present
DMR - Department of Minerals and Resources
DWA - Department of Water Affairs
EIR - Environmental Impact Report
EMPr - Environmental Management Program
EMP - Environmental Management Plan
Ha - Hectares
IAP - Interested and Affected Parties
IDP - Integrated Development Plan
IDZ - Industrial Development Zone
Ma - Million Years
Mt - Million Tons
NEMA - National Environmental Management Act
NID -
WCDM - West Coast District Municipality
DEFINITIONS
Consultation – A two-way communication process between the applicant and the
community or interested and affected party wherein the former is seeking, listening to
and considering the letters response which allows openness in the decision making
process.
Community – A group of historically disadvantaged persons with interests or rights in a
particular area of land on which the members have or exercise communal rights in terms
of an agreement, custom or law: Provided that, where as a consequence of provisions of
the Act negotiations or consultations with the community are required, the community
shall include members or part of the community, directly affected by prospecting or
mining, on land occupied by such members or part of the community.
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 5
Interested and affected parties’ include but are not limited to:
1. Host communities
2. Land owners (traditional and title deeds owners)
3. Traditional authorities
4. Land claimants
5. Lawful land occupier
6. The department of land affairs
7. Any person (including on adjacent and non-adjacent parties) whose socio-economic
conditions may be directly affected by the proposed prospecting or mining operation
8. The Local Municipality
9. The relevant Government Departments, agencies and institutions responsible for the
various aspects of the environment and for infrastructure which may be affected by
the proposed project
DMR STANDARD DIRECTIVE
All applicants for mining rights in terms of the provisions of Section 29(a) and in terms of
Regulation 49(4) of the Mineral and Petroleum Resources Development Act are directed
to submit a report in strict accordance with the following format and subject headings, as
informed by the guidelines posted on the Department’s Official Website within 30 days of
notification by the regional manager of the acceptance of such application.
DESCRIPTION OF EIA PROCESS
Phase 1: Scoping Report and Consultation with Authorities
Phase 2: Stakeholder Engagement
Phase 3: Specialist Studies
Phase 4: Impact Assessment
Phase 5: Compilation and Review of Draft EIR / EMP
Phase 6: Authority Decision
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 6
BACKGROUND
Umvoto Africa (Pty) Ltd has been appointed by GANNABOSCH CLAY MINE (Pty.) Ltd.
(Enterprise No. K2015446995/07) (See Appendix D: Cipro (Gannabosch Clay Mine
(Pty) Ltd.) for the application of a Mining Right with the Department of Mineral
Resources for the abstraction of shale/brick clay from the Gannabosch Vlakte 51
property (see APPENDIX B- Interested and Affected Parties Register) after being
identified to be overlying the natural resource of sufficient grade (See Annexure B: Clay
Analysis). Umvoto was identified as an independent consultant to perform the
Environmental Impact Assessment
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 7
1. SCOPING
NAME THE COMMUNITIES AS DEFINED IN THE GUIDELINE, OR EXPLAIN WHY NO
SUCH COMMUNITY WAS IDENTIFIED
There are no HDSA communities, or occupants on the proposed mining site of
Gannabosch Vlakte No. 51 within Ward 6 of the Langeberg Local Municipality of the
Cape Winelands District Municipality, approximately 15.5 km west outside of Robertson
on the R60 and ~ 130km ENE from Cape Town, Western Cape. The nearest dwellings
are on a neighbouring property ~2km away, along the banks of the Noree River to the
SE of the proposed mining property and consist of farm houses and labourer cottages.
The nearest town is Robertson, located ~15 km to the SE of the property (Appendix A –
Maps: Local Map).
STATE WHETHER OR NOT THE COMMUNITY IS ALSO THE LANDOWNER
The land is privately owned by the H R Grobbelaar Family Trust (Refer to Appendix E:
Title Deed)
STATE WHETHER OR NOT THE DEPARTMENT OF LAND AFFAIRS HAS BEEN
IDENTIFIED AS AN INTERESTED AND AFFECTED PARTY
The Department of Rural Development and Land Reform (DRDLR) has been identified
as one of the Interested and Affected Parties. A letter has been sent informing them of
the intended application (see APPENDIX B- Interested and Affected Parties Register).
STATE SPECIFICALLY WHETHER OR NOT A LAND CLAIM IS INVOLVED
No land claim is involved. An enquiry was made on 30 November 2015 to the
Commission on Restitution of Land Rights within the Department of Rural Development
and Land Reform (DRDLR) concerning any possible restitution claims against the
property of Gannabosch Vlakte No. 51. The department confirmed that there are no
current claims on this property (Appendix F: Land Affairs Response).
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 8
NAME THE TRADITIONAL AUTHORITY IDENTIFIED BY THE APPLICANT
Traditional Authorities are recognised in terms of section 211 of the 1996 Constitution of
South Africa. The Robertson office of the Langeberg Local Municipality has been
contacted telephonically to confirm that no Traditional Authority is present in the area.
LIST THE LANDOWNERS IDENTIFIED BY THE APPLICANT. (TRADITIONAL AND
TITLE DEED OWNERS)
The portion of Gannabosch Vlakte No. 51 in question is lawfully owned by the H R
Grobbelaar Family Trust (Tittle Deed Reference Number: T 41359-95 issued on the 22nd
of March 1995) (Appendix E: Title Deed).
LIST THE LAWFUL OCCUPIERS OF THE LAND CONCERNED
Site visits which occurred on the 30th and 31st of October and 5th of November 2015
revealed no individuals occupying the land, and no dwellings (formal or informal)
constructed within the property boundary. The surface landowner H R Grobbelaar
Family Trust confirmed via telephonic communications that as of November 2015 no
persons occupy the land, permanently or temporarily.
OTHER PARTIES THAT MAY BE DIRECTLY AFFECTED
Other parties that may be directly affected include the landowners on the adjacent and non-
adjacent properties (as listed in the table below) and the associated land tenants and farm
workers. It is noted that this list could be expanded upon up to and including the 7th of April 2016,
the termination date for closure of IAP registration.
Table 1: Listed affected parties
Property Description Surface Owner Note in Relation to Project
Infrastructure
Middelburg Portion 9, No.10 Hennie Retief Neighbour
Middelberg Portion RE, No.10 Johan Fourie Neighbour
Alwynbos Vlakte No.299 Nellis Grobbelaar Neighbour
Noree No.300 Nellis Grobbelaar Neighbour
De Hex Rivier Portion 18, No.50 Ernst Botha Neighbour
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 9
Property Description Surface Owner Note in Relation to Project
Infrastructure
Lange Vallei Portion 5, No.52 Nellis Grobbelaar Neighbour
THE LOCAL MUNICIPALITY IDENTIFIED BY THE APPLICANT
The proposed Mine Right application site is located within Ward 6 of the Langeberg
Local Municipality, Robertson Magisterial / Administrative District in the Western Cape
Province. They have been included as Registered Interested and Affected Parties and
have been alerted to the application by email and registered post. Ward Councillors of
Ward 6 have also been individually contacted by email and registered letter. The Local
Municipality has been contacted and an application submitted for land use change as
per requirements of Land Use Planning Ordinance (LUPO).
OTHER STAKEHOLDER
Departments, agencies and institutions that may be affected by the proposal have been
identified among the Interested and Affected Parties list (See APPENDIX B- Interested
and Affected Parties Register). The listed parties in the table may be expanded upon up
to and including the 7th April 2016.
The relevant government departments, agencies and institutions responsible for the
various aspects of the environment, land and infrastructure that may be affected by the
project are listed below:
Regulatory authorities:
Department of Mineral Resources (DMR)
Department of Economic Development, Tourism and Environmental Affairs
(DEDTEA)
Department of Water and Sanitation (DWS)
Heritage Western Cape
Department of Rural Development and Land Reform (DRDLR)
Regional Land Claims Commission: Western Cape
Cape Nature
Department of Transport
Local authorities:
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 10
Cape Winelands District Municipality
Langeberg Local Municipality (Utrecht)
Ward councillor: Ward 6
Transnet
Parastatals:
Eskom
PRASA
Other:
Cape Lime
CONFIRM WITH EVIDENCE THAT THE LANDOWNER OR LAWFUL OCCUPIER OF
THE LAND IN QUESTION, AND ANY OTHER INTERESTED AND AFFECTED PARTIES
INCLUDING ALL THOSE LISTED ABOVE, WERE NOTIFIED.
Proof that the landowners, lawful occupiers and IAP’s were notified of the project is
provided in APPENDIX B- Interested and Affected Parties Register. The description of
the Public Participation Process (PPP) (including the notification of the various IAPs) is
provided in Section 5.
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 11
2. DESCRIPTION OF EXISTING ENVIRONMENT
This section has been compiled by means of a desktop baseline study using sources
from various specialists, site visits and available information. Further input and/or
amendments will be included once the public participation process has taken place with
identifies IAP’s. The baseline information is aimed at giving the reader perspective on
the existing status.
AGREEMENT ON EXISTING STATUS OF ENVIRONMENT
IAP’s have been sent letters and information on the existing status of the environment in
the form of a Background Information Document (BID) (See Annexure a: Background
Information Documents for BID and APPENDIX B- Interested and Affected Parties
Register for proof of sending). The BID will both inform and elicit comments from IAP’s.
All identified IAP’s were asked if they could identify and provide contact details for any
other parties which should specifically be consulted and whom may be affected by the
proposed clay mine.
EXISTING STATUS OF THE CULTURAL ENVIRONMENT THAT MAY BE AFFECTED
A site visit on 30th, 31st October 2015 and 6 November 2015 proved there is no cultural
environment on the land unit or within the immediate surrounds. The land unit is
undeveloped, uninhabited and currently not utilised for any agricultural purpose. It may
be concluded therefore that there is no visible evidence of any cultural environment
which may be affected by the proposed mining operation.
DESCRIBE THE EXISTING STATUS OF ANY HERITAGE ENVIRONMENT
Similarly to Section 2.2, site visit on the above mentioned dates showed no visible
heritage environment. However a Professional Heritage Practitioner will be sub-
contracted to undertake further investigation into the heritage environment of the site
and to submit a report for inclusion into the Environmental Impact Assessment report.
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 12
DESCRIBE THE EXISTING STATUS OF ANY CURRENT LAND USES AND THE
SOCIO-ECONOMIC ENVIRONMENT THAT MAY BE AFFECTED
Current on Site Land Use
The land in the mine zone (See Appendix A – Maps: Land Types) is still in its original
state consisting of indigenous karroid vegetation (Breede Alluvium Renosterveld).
Multiple site visits on 30th, 31st October 2015 and 6 November 2015 confirmed that there
are no cultivated fields, no stock farming and grazing on the land.
Surrounding Land Use
Located along ~500 metres from the well trafficked R60 national road, which runs
through the Cape Winelands district, Gannabosch Vlakte No.51 is situated within a rural
farming area. As such, the primary land usage consists of cultivation of wine grapes,
minor stone fruit (peaches), as well as small scale grain cultivation to supply fodder for
the minor non-intensive livestock farming occurring on adjacent and non-adjacent
properties.
Located at the foothills of the Langeberg Mountain, the farm property lies at its closest,
~3 km from the Langeberg-West Mountain Catchment conservation area which forms
part of the Mountain Catchment Conservation. The smaller Dooringkloof Private Nature
Reserve is located ~4 km to the north.
On a non-adjacent property, ~2km to the North, a limestone quarry (Cape Lime)
operates to supply the limestone to the processing plant on the adjacent property, just to
the south of Gannabosch No.51. property.
Socio-economic Environment
i) On Site Use and Immediate Surrounding Areas
As there is no current on-site land use and there are no residents living
on the current proposed mining area the land has no socio-economic
sensitivity to the proposed mining.
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 13
Utilising the GIS tool “Cape Farm Mapper
http://gis.elsenburg.com/apps/cfm/), a ~5 km search radius was
implemented to, within which 19 dwellings were located. These dwellings
were primarily located along the banks of the Noree River, ~3 km to the
east of the proposed mine property, and further SE of the confluence of
the Noree and Vink River (See Appendix A – Maps: Land Types) and
serve as dwellings for individuals living/working on the respective
properties.
As described in Section 2.4.2, the nearby neighbouring land use is that
of rural agricultural practices, with low population densities. The majority
of the individuals living in the surrounding areas are farm labourers who
generally work on the farm on which they live. The socio-economic
environment revolving around the agricultural sector in the Western Cape
is that of a relatively marginal income and poor housing facilities for the
average farm labourer. While access to education is on average poor, the
immediate surrounding area is above the norm for its rural setting given
the proximity to Robertson.
ii) Nearby businesses/ tourist places
The economic activity in the area consists mainly of the limestone quarry
mining and the Cape Lime processing plant. The proposed mining site
falls within the Breede River Valley wine route, and is a feeder road into
the R66 Klein Karoo tourist route which serves as an alternative to the
highly popular N2 Garden Route. Viticulture and related tourist interest is
a noted activity in the region.
iii) Nearby residential communities
The closest residential settlements to the proposed mining site are found
in the town of Robertson, which includes the town suburbs and the
outlying Nkqubela Settlement. The primary employment provider is that of
the grape and wine production industry, with the smaller proportion
working in industrial portion of Robertson. The proposed mining operation
will encourage employment opportunities, with likely positive socio-
economic impact. This is further addressed in detail in the Social and
Labour Plan (Umvoto, 2016).
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 14
DESCRIBE THE EXISTING STATUS OF ANY INFRASTRUCTURE THAT MAY BE
AFFECTED
The proposed mine property has no current infrastructure on it that could be affected by
mining activities.
DESCRIBE THE EXISTING STATUS OF THE BIOPHYSICAL ENVIRONMENT THAT
WILL BE AFFECTED, INCLUDING THE MAIN ASPECTS SUCH AS WATER
RESOURCES, FLORA, FAUNA, AIR, SOIL, TOPOGRAPHY ETC.
Topography & Drainage
2.6.1.1. Topography
The project site is situated in the low lying shrub lands which slope gently toward the
Buitenstekloof River south of the site.
The proposed mine property is located within the Cape Winelands district (previously
known as the Boland region). This area is located in the middle-upper courses of the
Berg and Breede Rivers, situated within the central Cape Fold Belt Mountains and within
the Breede Valley, situated between the ~1400 mamsl tall Langeberg and ~ 1300 mamsl
Riviersonderend Mountain ranges to the north and south respectively. Locally the
property is situated on slightly southward sloping, lower lying and level shrub lands, with
an elevation of ~265 to 275 mamsl.
2.6.1.2. Drainage
The property is located within the H40H quaternary catchment of the Breede-Gouritz
Catchment Management Area (CMA). The Breede River is the most significant
perennial river in the region. The perennial Vink River is located south of the property
and feeds the Breede River. Due to the low permeability of the clay soils, the property
experiences a significant amount of surface water run-off, which drains into the non-
perennial stream on the property and/or feeds into the Vink River.
Noise and Air Quality
The proposed mining property is located in a rural setting with no on-site producers of
noise or sound pollution. Located ~2 km to the north is the Cape Lime open cast quarry
which extracts lime which is sent to the processing plant ~200 m to the south on the
immediate southern bordering property..
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 15
Ambient noise levels are expected to be within the range of 0dBA and 45dBA/ 35dBA
during the daytime and nighttime respectively. In accordance with SANS-10103:2003
(South African National Standards)
Table 2 : Noise limits per sector
Type of District
Equivalent Continuous Rating Leven For Noise (dBA)
Outdoors Indoors with open windows
Daytime Night-time Daytime Night-time
RESIDENTIAL DISTRICTS
Rural Districts 45 35 35 25
Suburban districts
(little road traffic) 50 40 40 30
Urban districts 55 45 45 35
NON-RESIDENTIAL DISTRICTS
Urban districts
(workshops,
business premises
and main roads)
60 50 50 40
Central business
districts 65 55 55 45
Industrial districts 70 60 60 50
Soil
The region consists of soils derived from transported material which includes the sandy
and loamy alluvial soil, as well as the red clay loam and clay Karoo soils. As well as
residual soils which include the shale soils of the Malmesbury and Bokkeveld soil
families. The red clay loam and clay Karoo soils are the most dominant soil types in the
area of interest and are often very calcareous.
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 16
The proposed mining property overlies soils of a Eutric Brunisol (EB) nature, as
classified by the Canadian System of Soil Classification, with an approximate depth of <
450 mm (CFM, 2016). These soils exhibit minimal development and are usual of
shallow soils overlying on hard or weathering rock. Lime is generally present in part or
most of the landscape as is shown by the relatively high degree of base saturation as
indicated by their pH and lack a well-developed mineral-organic surface horizon. These
soils are common of parent material of high base status (clay/lime) and under forest or
shrub vegetation in a wide range of climates.
Further classification via the ENPAT broad soil classification shows soils of Fc718
category. The Glenrosa soil form have a strong structure and high clay content subsoil
and are not suitable for irrigation, being host to short shrub and bush. The Mispah form
is indicative of soil horizons overlying hard rock formed in alluvium, derived from mixed
rocks over residuum that has weathered from siltstone. These soils are generally very
shallow, have a variable fertility and water holding capacity, depending on the rock type
from which they are derived (P. le Roux, 2012; CFM, 2016).
Geology
The resistant to weathering rocks of the Table Mountain Group (TMG) sandstones of the
Cape Supergroup define and form the peaks of the Cape Fold Belt Mountains.
To the north of the proposed mining property, the south-westerly dipping normal
Worcester Fault has downthrown the southern, younger, Karoo Supergroup rocks
juxtapose those of the older basement Malmesbury Group and intrusive Robertson
Granite Suite, upon which the rocks of the unconformable overlying TMG form the
~1400 mamsl Langeberg Mountain range. To the south of the property, the steep (~50
°) northward steeply dipping Karoo Supergroup sediments transition into the
conformable and older stratigraphically underlying rocks of the Cape Supergroup, which
rise up to form the ~1300 mamsl elevation Riviersonderend Mountain Range.
On site, the property is underlain by Quaternary sediments deposited in the flood plains
of river courses controlled by the bounding mountain ranges of the Riviersonderend and
Langeberg Mountain ranges, which form the Breede Valley (see, Appendix A – Maps :
Geology). Rock units of the Ecca Group of the Karoo Supergroup underlay the
overlying Quaternary sediments and can be seen outcropping throughout the
surrounding landscape and in nearby diggings. The proposed mining will be
concentrating on these underlying clay sediments. The clays contain high amounts of
Quartz and smaller amounts of mica and feldspar. The feldspar is present in the form of
plagioclase series which is a group of related feldspar minerals that essentially have the
same formula but vary in their percentage of sodium and calcium content. Also present
are traces of Kaolinite and Smectite clay minerals. The stratigraphy in the region is as
follows:
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 17
Table 3: Stratigraphy
Age Supergroup Group Subgroup Formation Lithology
Quaternary
(~2.5-0 Ma) Undifferentiated sediments Alluvium
Early to Mid-
Permian
(~299-270 Ma) Karoo
Ecca
Waterford Feldspathic sandstone,
siltstone, shale
Tierberg Shale, mudstone, siltstone
Collingham Shale, Mudstone/tuff,
siltstone, chert
Whitehill Carbonaceous shales
cherty siltstone layers
Prince
Albert Shale, siltstone
Carboniferous
(~359-299 Ma) Dwyka Tillite, Diamictite, shale
Cambrian-
Ordovician
(~510-350 Ma
Cape Super
Group
Table
Mountain
Group
Skurweber
g
Quartzitic sandstone,
pebble stringers
Peninsula Quartzitic sandstone
Late
Precambrian
(~575-540 Ma)
Malmesbur
y
Greywacke, sandstone,
slate
Late
Neoproterozoi
c
(~600-540 Ma)
Cape Granite
Suite Granite
Prince Albert Formation
Outcrops of this formation are generally poor. It consists mainly of thinly laminated, dark
bluish-grey shale which weathers to an olive or red brown colour. In the cold Bokkeveld
and Ceres-Karoo thin (3-5 cm), silty to cherty layers occur intermittently. On exposure
they disintegrate into small yellow-brown angular chips.
Between Worcester and Robertson the formation is only intermittently exposed, with
good, fairly accessible outcrops occurring along the flanks of Aasvoelberg, north of
Eiland. According to De Villiers et al. (1964) the formation attains a thickness of
approximately 200 m south of Worcester, but more recently 120 m was measured just
east of the mine site on farm Scherpen Heuvel no.481. As elsewhere, a transitional
contact exists between the Prince Albert Formation and the overlying Whitehill
Formation.
Whitehill Formation
The Whitehill formation consists of thinly laminated, pyritic, carbon-bearing black shale
and measures about 30 m in thickness. The formation weathers characteristically to a
conspicuous greyish-white, gypsiferous to lime rich zone. Thin, grey to yellow-coloured
cherty lenses are often also apparent.
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 18
Collingham Formation
The Collingham formation, which concordantly overlies the Whitehill shales, is poorly
exposed in the Ceres-Karoo but in the Worcester-Robertson outlier, it is exposed in the
above-mentioned quarry sites as well as in road cutting. Here it is about 45 m thick,
compared to the generally accepted thickness of 30 m to the north. The Collingham
formation here consists of a rhythmically interbedded sequence of thin tabular beds of
dark grey shale, yellowish-coloured soft claystone, siltstone and cherty mudstone.
Bedding thickness varies from 20 to 40 mm, with some of the siltstone horizons
somewhat thicker in places. Parallel lamination is dominant. No trace fossils have been
found as yet.
A yellow weathering, illite-rich claystone (K-bentonite) typifies the Collingham Formation
and has a wide distribution throughout the Karoo Basin. These claystones and chertified
beds contain devitrified and replace glass shards, and have been interpreted as air fall
tuffs (Lock and Wilson 1975). Analyses have shown the potassium content of these ash
beds to vary from 4 to 10 % K2O (Verwoerd et al. 1990).
Tierberg Formation
The conformably overlying Tierberg Formation consists of grey-black (fresh) to olive-
green (weathered), well laminated shale, mudstone and siltstone. The formation is
extensively weathered and poorly exposed in the Ceres-Karoo. Occasional thin, silty
horizons are sometimes ripple marked and biogenic trails occur on Witte Wal 171, along
the Groot River.
Outcrops are somewhat in the Worcester-Robertson outlier, where the most complete
section across the Tierberg Formation in this area occurs between Aasvoelberg and
Mowershoogte, west of the Worcester-Robertson divisional boundary. From the
Tierberg-Collingham contact up to Mowers Siding the sequence is mainly composed of
mudstone, shale and siltstone. North of the railway line however, there is a gradually
increasing number of arenaceous layers. This latter succession is tentatively connected
with the Waterford Formation, the uppermost unit of the Ecca Group.
Waterford Formation
In the low range of hills, Mowershoogte, between Worcester and Robertson, numerous
fine-to medium grained sandstone beds are intercalated with politic units. These
arenaceous beds are generally massive or sometimes parallel laminated, and wave
ripple marks, clay-pellet conglomerate and brownish lime-rich lenses occur.
Climate
The mine area falls within the Mediterranean climate zone of the south-western region of
South Africa but is also influenced by the temperate interior climate zones of the Klein
Karoo. Winter rainfall dominates the area but the added impact of inland summer rainfall
over the Karoo and the eastern regions of the Cape generate a more even monthly
rainfall distribution than the Western Cape. Mean annual precipitation (MAP) is
recorded as 265 mm (Mucina & Rutherford, 2006), while monthly rainfall can vary from 8
mm in summer up to 35 mm in winter (See Figure 1).
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 19
Figure 1: Composite climate diagram of the Robertson region. Blue bars show the median
monthly precipitation. The upper and lower red lines show the mean daily maximum and
minimum temperatures respectively (After Mucina and Rutherford, 2006).
High interior temperatures are moderated by proximity to the Cape Fold mountain
system which induces lower temperatures due to adiabatic cooling (0.60 C per 100m) as
well as the occasional influx of cooler maritime air from south of the mountain divide.
Mean annual temperature (MAT) for the region is recorded as 16.80 C (Mucina &
Rutherford, 2006). Mean daily maximums and minimums are 29.80 C and 4.70 C in
summer and winter respectively (see Figure 1). It is noted that the MAP is only 12 % of
the Mean Annual Potential Evaporation (MAPE) which is 2192 mm, leading to a high
Soil Moisture Stress Index (MASMS) of 76% which renders surface clays dry.
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 20
Figure 2 : Average, maximum and minimum daily temperatures throughout the day, with
the horizontal axis representing months of the year, starting with January (1) and ending
with December (12).
Wind data was obtained from the Agricultural Resource Council (ARC) for the period
2000 to 2015, as shown in the wind rose in Figure 4, with supporting data in Table 5.
Information was then reinforced with research on the internet for a shorter time period of
two years from January 2014 to December 2015 as shown in Table 4. The influence of
the South Atlantic and South Indian High Pressure Systems, promotes a predominant
regional wind direction from the east/south-east and from the west. The ARC data is
more robust than the internet research data, as it ranges over a 15 year average, and
shows equal axis wind directions of approximately 15% duration from the east and the
west. Wind speeds are notably stronger from the west, in the 4 to 7 m/s category while
the easterly winds are generally lighter in the 1 to 3 m/s category. The two year period
internet data shows that east and south east winds dominate for 40% of the time while
the second influential wind direction from the west makes up 18 % of the total wind
direction duration. The average two year, January 2014 to December 2015, wind speed
is observed as 7.3 km/h (2 m/s) (See Table 5). Also important is to note that calms
account for approximately 40% of the time duration as recorded by the ARC.
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 21
Figure 3 : Predominant Wind Direction January 2014 - December 2015 (weatheronline,
2015)
Table 4: Wind speeds (km/h) between January 2014-December 2015 (saexplorer, 2015).
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 22
Figure 4 : Wind rose of the Worcester/Robertson region
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 24
Biodiversity, Flora & Fauna
The proposed mine site falls within an area with vegetation that is listed as Endangered
(EN), as defined by the South African National Botanical Institute (SANBI) (Appendix A
– Maps: Vegetation). The vegetation in the proposed mining area consists of Breede
Alluvium Renosterveld which consists of a species poor, short, open shrub land with
dwarf succulent shrubs and grasses in the gaps, dominated by Renosterbos, Athanasia
trifurcata, Pentzia incana, Ruschia caroli and Aspalathus spinosa, amongst others. The
grasses are represented by Ehrharta longiflora, E. villosa and Themeda triandra whilst
Crassula expansa is the most commonly encountered succulent shrublet (Jacobs and
Jangle, 2008).
The proposed mine further falls within an area defined as a Critical Biodiversity Area,
which is described as an area required to meet biodiversity targets for ecosystems,
species and ecological processes, as identified in a systematic biodiversity plan as per
the National Environmental Management: Biodiversity Act (No. 10 of 2004).
The Western Cape has a relatively low concentration of large terrestrial mammals.
However, the smaller fauna such as rodents, reptiles, insectivores and birds are prolific
in the mine zone. In summary, the area is home to a variety of insects, rodents, reptiles,
birds and mammals that naturally reside in this type of habitat.
Surface water
Surface runoff in the proposed mine site potentially occurs; this is due to the low
permeability of the clays. The surface water generated on site as runoff will continue to
feed the stream south west of the area. See Section 2.6.1.2
Groundwater
The fractured Table Mountain Superaquifer forms the dominant aquifer in the greater
Western Cape region, specifically the Peninsula and Nardouw (Skurweberg and Rietvlei)
Aquifers within it. These two Table Mountain Group (TMG) aquifers are separated by
the Winterhoek Mega-aquitard (Pakhuis, Cederberg and Goudini Aquitards) which totally
isolate them from one another. The upper Nardouw Aquifer is targeted by private
Schedule 1 users and farmers because of its accessibility and shallower drilling depth
which reduces drilling costs. The Peninsula Aquifer is mainly used for large scale
municipal groundwater developments (Oudtshoorn Groundwater Project, Hermanus
Wellfield, Stanford Wellfield and Cape Town’s TMG Feasibility Study) because of its
large quantity and good quality groundwater. In general, groundwater quality of both the
Peninsula and Nardouw Aquifers is good (i.e. fresh and potable), with low electrical
conductivity (EC), low solute content, acidic pH, however high iron and manganese
concentrations are characteristic.
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 25
The Bokkeveld Group is made up of fine grained shales, mudstones and siltstones
which have low hydraulic potential. For this reason the Bokkeveld Group is known as the
Gydo Mega-aquitard. The high residence time of groundwater within the clay rich shales
and low transmissivity parent rock usually results in relatively poor groundwater quality
(e.g. high electrical conductivities and high metal concentrations) due to its marine
depositional environment.
The Witteberg Group consists of alternating units of micaceous shale/siltstone and
quartzitic sandstone. The hard, fractured sandstone units (Blinkberg, Witpoort and
Floriskraal Formations) form the aquifers of the Witteberg Group which are separated
from one another by the shale rich (low hydraulic permeability) aquitards (Wagen Drift,
Swartruggen, Kweekvlei, Waaipoort Formations). The three fractured sandstone
aquifers form relatively good yielding aquifers provided the right structure is targeted,
with yields of between 2-5 l/s. The Witpoort Aquifer is the thickest and most likely the
highest yielding aquifer within the Witteberg Group. Groundwater quality is likely to be
relatively good (electrical conductivities of <100 milliSiemens/metre [mS/m]), although
high iron and manganese concentrations are possible. The proposed mining site is
directly above Karoo sequence rocks (see Section 2.6.4) which are of little significance
with regard to groundwater in the area.
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 26
3. IDENTIFICATION OF THE ANTICIPATED ENVIRONMENTAL,
SOCIAL OR CULTURAL IMPACTS, INCLUDING THE
CUMULATIVE IMPACTS, WHERE APPLICABLE.
PROVIDE A DESCRIPTION OF THE PROPOSED PROJECT INCLUDING A MAP
SHOWING THE SPATIAL LOCALITY OF INFRASTRUCTURE, EXTRACTION AREA,
AND ANY ASSOCIATED ACTIVITIES
The spatial locality of the proposed project and the locality of infrastructure may be seen
in the Mine Layout Map in Appendix A – Maps: Mine Layout. Access to the proposed
mining property will make use of existing infrastructure namely the secondary road
(Lanvlei Road) off the R60 National road.
A small vehicle parking area of ~25 by 30 meteres at the entrance to the property will be
fenced off for the parking of the escavator during periods of non-use and visiting
vehicles to the minig property. The proposed mining method (open pit mining) will
require the use of a front-end loader and tipper truck to mine the clay deposits. The
process starts with the removal and safe storage of the overburden and topsoil to
expose the economic material, which is then moved to a central point by front end loader
and transported by tipper trucks to the nearby purchaser. A 19 ton excavator will be
rented from the sole consumer and buyer of the raw clay materials, Robertson Bakstene
(Pty) Ltd, for the stripping top soils from the land surface and for abstraction of raw clay
material. Robertson Bakstene shall collect the raw clay for transport to their nearby brick
production facility by making use of a single 5 ton tip truck. The storage area for
overburden can be seen in Appendix A – Maps: Mine Layout. There is no electrical
use on site. Due to the limited human presence on site during operations, a single on
site toilet will be installed. No on site office will be located on the mining property.
Minor bookkeeping and administrative tasks will be undertaken off site by
Gannabosch Clay Mine (Pty) Ltd.
DESCRIBE ANY LISTED ACTIVITIES (IN TERMS OF THE NEMA EIA
REGULATIONS) WHICH WILL BE OCCURRING WITHIN THE PROPOSED PROJECT.
The following activities represent listed activities from the National Environmental
Management Act, 1998 (Act No. 107 of 1998), which are likely to be triggered
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 27
Government Notice No.R982 National Environmental Management Act (107/1998):
Environmental Impact Assessment Regulations, 2014.
Table 6 : Listing Notice 1 (No. R. 983) Triggers in terms of 24 (2) and 24D
Activity Number
Activity description Identification of Competent Authority
22 The decommissioning of any activity requiring- A closure certificate in terms of section 43 of the Mineral and Petroleum Resources Development Act, 2002 (Act No. 28 of 2002): The closure of the mine at the endo of the mines life: ~10-15 years
Minister responsible DMR
27 The clearance of an area of 1 hectare or more, but less than 20 hectares of indigenous vegetation,
Minister responsible DMR
Table 7 : Listing Notice 2 (No. R. 984) Triggers in terms of 24 (2) and 24D
Activity Number
Activity description Identification of Competent Authority
17 Activity which requires a mining right as contemplated in section 22 of the Mineral and Petroleum Resources Development Act, 2002: The abstraction of shale/brick clay.
Minister responsible DMR
Table 8 : Listing Notice 2 (No. R. 985) Triggers in terms of 24 (2) and 24D
Activity Number
Activity description Identification of Competent Authority
None*
SPECIFICALLY CONFIRM THAT THE COMMUNITY AND IDENTIFIED INTERESTED
AND AFFECTED PARTIES HAVE BEEN CONSULTED AND THAT THEY AGREE THAT
THE POTENTIAL IMPACTS IDENTIFIED INCLUDE THOSE IDENTIFIED BY THEM.
Contact letters and a Background Information Document (BID) (Annexure a:
Background Information Documents) have been sent to the Interested and Affected
Parties and Communities (IAP&C) as listed in APPENDIX B- Interested and Affected
Parties Register. The process awaits any comments that they might have. Comments
and feedback from the IAP & C will inform the Environmental Impact Assessment
process and Mine Works Program.
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 28
IMPACTS
Provide a list and description of potential impacts identified on the
heritage environment, if applicable.
During the Scoping phase, potential impacts are identified for later and further
analysis during the EMP phase. This will require consultation with specialists
within respective fields of expertise. Compilation of specialist reports will be
performed and used during the EMP phase.
Table 9 : Heritage impacts
Potential impacts on heritage
environment Description
Paleontological
Positive:
Any fossils or artefacts present might be unearthed
by the mining operation if not identified by the site
visit for the planned specialist study.
.
Negative:
Machinery excavation may damage artefacts that
may be in place
Provide a list and description of potential impacts identified on the
socio-economic conditions of any person on the property and on any
adjacent or non-adjacent property who may be affected by the
proposed prospecting or mining operation.
Socio-economic impacts refer to the change in social behaviour and status due to the
economic impact of the mine. Site visit and discussions with the applicant indicates that
there are no existing residents / occupants on the portion of land. Current scoping
research has not identified any persons on adjacent and or non-adjacent property that
may be affected by the proposed mining operation.
Table 10 : Socio-economic impacts
Potential impacts on socio-
Economic conditions
Description
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 29
Economic Local labour from adjacent farm communities or
Robertson will be employed by the mine. This will
have a positive impact on the wellbeing of employees
with a multiplier effect on households of the
employed.
Provide a list of potential impacts (positive & negative) on:
employment opportunities, community health, community proximity,
and links to the Social Labour Plan.
Table 11 : Community impacts
Potential impacts
employment, health,
Description
Employment Positive:
The establishment of a mine would create
employment of some residents living in the
neighbouring communities. Allowing for a much
needed income into the area.
Negative:
No negative employment issues can be attributed to
the local community from the proposed mining
operation on Gannabosch Vlakte 51.
Health Positive:
Employment of staff and training thereof in health
and safety protocol, will improve health and wellbeing
of staff and their immediate households. The SLP
can provide ABET to the workers which should
spread down through the families and ultimately to
improve awareness of health issues among staff
employees and their associated households.
Negative:
No negative health issues can be attributed to the
local community from the proposed mining operation
on Gannabosch Vlakte 51.
Community proximity Due to the distance of any communities and towns
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 30
from the mine, there are no foreseeable positive or
negative issues that may impact on communities.
Transport and Infrastructure Minimal to no impact on national roads should occur
due to the fact that the clay is planned to be
transported to the neighbouring property and location
for manufacture of clay bricks.
3.4.3.1. Links to the Social and Labour Plan
The Social and Labour Plan (Umvoto, 2016) consists of the following implementation
plans for the single employee of the company.
1) Skills development programmes
2) Bursary programme for employee’s dependants
3) Career progression plan
4) Mentorship programme
The implementation of these initiatives focuses on the upliftment of the worker’s family,
which leads to further opportunities for their children, giving them improved
access/standard of education and thus better chance for skilled.
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 31
Provide a list and description of potential impacts identified on the
biophysical environment including but not limited to impacts on:
flora, fauna, water resources, air, noise, soil etc.
Table 12 : Biophysical impacts
Potential biophysical
impacts
Description
Flora Breede Sand Fynbos and Breede Alluvium
Renosterveld are the two predominant vegetation
types residing in Gannabosch Farm. Both are ranked
in the Vulnerable Status (VU) group as classified by
SANBI. Open trench mining will impact such
vegetation in the 14.5 ha for which Gannabosch Clay
Mine plans to extract clay from. The risk of influx of
invasive alien species due to surface disturbance and
increased vehicular access to the area will further
exacerbate the predicament (Refer to Appendix A –
Maps: Vegetation).
Fauna Large natural fauna is not present on the property.
Livestock from neighbouring properties will be actively
managed so as not to be directly affected by the mine.
Small feral mammals, insects and reptiles would be
disturbed during the mine process.
Water resource Pit mining will be utilised to mine the clay layer which
will not be mined past a depth of 10 mbgl. This is
above the ground water level and all indications point
towards a dry mining process, which will not affect the
ground water. The exposed pit from which the clay is to
be extracted will pose a water capture area from
surface runoff, implementation of necessary measures
will take place to ensure water is drained from the open
pit There is the possibility of surface water erosion
occurring due to vegetation removal and increased
sediment load / contamination runoff into nearby
streams.
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 32
Air Small scale trench mining will have minimal impact on
air quality and the proposed mining area is not in
proximity to an inhabited area This parameter is
therefore not considered to have an impact on people.
Dust Small scale trench mining may pose small impact of
dust load of air, though the cumulative impact is
considered low due to the presence of Cape Lime
processing facility on the neighbouring property.
Noise The operation of single excavator will increase noise
pollution in the area during daylight working hours on
the mine minimally. The impact to the area would be
low due to there being no inhabitants in the adjacent
farm.
Soil With the removal of vegetation from the mining area,
increased chance of soil erosion is probable unless
mitigating steps are followed. The usage of light and
heavy haulage machinery will compact the surface.
Soil compaction is the process in which a stress
applied to soil causes densification as air is displaced
from the pores between the soil grains causing soils to
become less able to absorb rainfall, and increasing
runoff and erosion. Plants and burrowing animals may
have difficulty in compacted soil because the mineral
grains are pressed together, leaving little space for air
and water, which are essential for root growth. This will
create, in general a hostile environment, as the denser
soil becomes more difficult to penetrate. Potential for
hydrocarbon spillages in the form of oil, hydraulic fluid
or diesel are possible due to the use of machinery for
mining. This can be integrated in an EMP.
Topography
The open pit mining techniques in order to access the
clay deposits will alter the surface topography by
creating trenches and stockpiles. Rehabilitation will
ensure that the pit caused as a result of mining is not
of danger to fauna or humans
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 33
Visual The proposed mining site is situated a distance away
from any road, structure or public area and is
sufficiently isolated that it will not negatively impact on
the surrounding areas.
Waste (solid, biodegradable,
mine dump)
Numerous waste products will be generated which will
include: Waste dumps, refuse, (bio and non-
biodegradable), human waste and sewage. The
impact of the diverse waste types will impact differently
on the biophysical, chemical and visual environment
and will have to be managed and mitigated.
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 34
Provide a description of potential cumulative impacts that the
proposed operation may contribute to considering other identified
land uses which may have potential environmental linkages to the
land concerned.
Identified potential cumulative impacts include an expected low negative cumulative
impact of noise, dust and visual, at sufficiently low cumulative level to not impact
surrounding tourism activities that are on the Breede River Wine route and on nearby
Cape Lime quarry and processing plant. The individual impacts of noise, dust,
groundwater and visual will be further assessed in the EIA in order to formulate a more
informed and qualified impact statement on potential impact on ecology, land value and
tourism activities. As mentioned earlier such cumulative impact will also consider the
positive impact of the presence of business activity in the Langeberg region. It will also
consider the threshold impact of both the lime and mine.
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 35
4. LAND USE OR DEVELOPMENT ALTERNATIVES,
ALTERNATIVE MEANS OF CARRYING OUT THE
PROPOSED OPERATION AND THE CONSEQUENCES OF
NOT PROCEEDING WITH THE PROPOSED OPERATION.
PROVIDE A LIST OF AND DESCRIBE ANY ALTERNATIVE LAND USES THAT EXIST
ON THE PROPERTY OR ON ADJACENT OR NON-ADJACENT PROPERTIES THAT
MAY BE AFFECTED BY THE PROPOSED MINING OPERATION.
Primary use of the land surrounding the site is used for agrarian purposes, in the form of
vineyards. The only mining in the area around is limestone quarry mining north of the
proposed site. Adjacent to the site is the processing plant for the limestone being
mined. The following adjacent land units are noted along with land uses that are in
progress and that may be affected by proposed mining.
Table 13 : Land Use
Farm Portion Land Use Activities
Middelburg
9/10 Thicket / Dense bush & Shrubland Fynbos – Land Cover (DEA, 2014)
Middelberg
RE/10 Enterprises: Fruit - Wine grapes (Crop Census, 2013)
Alwynbos Vlakte
No.299 Shrubland Fynbos – Land Cover (DEA, 2014)
Noree No.300 Shrubland Fynbos – Land Cover (DEA, 2014)
De Hex Rivier
18/50 Enterprises: Fruit - Wine grapes (Crop Census, 2013)
Lange Vallei
5/52
Enterprises:Fruit – Mostly wine grapes and some peach (Crop Census,
2013)
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 36
PROVIDE A LIST OF AND DESCRIBE ANY LAND DEVELOPMENTS IDENTIFIED BY
THE COMMUNITY OR INTERESTED AND AFFECTED PARTIES THAT ARE IN
PROGRESS AND WHICH MAY BE AFFECTED BY THE PROPOSED MINING
OPERATION.
No land developments were identified or are currently taking place that would be
affected by the proposed mining operation.
PROVIDE A LIST OF AND DESCRIBE PROPOSALS MADE IN THE CONSULTATION
PROCESS TO ADJUST THE OPERATIONAL PLANS OF THE MINE TO
ACCOMMODATE THE NEEDS OF THE COMMUNITY, LANDOWNERS AND
INTERESTED AND AFFECTED PARTIES.
No proposals by the landowners or IAPs to adjust the operational plans of the mine have
been made at the time of preparing the draft Scoping Report and comments from the
IAP’s will address this.
PROVIDE INFORMATION IN RELATION TO THE CONSEQUENCES OF NOT
PROCEEDING WITH THE PROPOSED OPERATION.
If the proposed operation were not to proceed, the land may or may not be utilized for
grazing of livestock in the future. As much as the no go option may result in the
protection of the environment in situ; the consequences of not proceeding with the
proposed operation will include the forfeiture of a mining opportunity and therefore the
loss of support towards the Langeberg Municipality. It would further suggest that no new
employment opportunities would be created as well as any resultant community
upliftment and development programs would likely take place in the surrounding
communities of Robertson
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 37
A DESCRIPTION OF THE MOST APPROPRIATE PROCEDURE TO PLAN AND
DEVELOP THE PROPOSED MINING OPERATION THE APPLICANT MUST:
Provide information on its response to the findings of the
consultation process and the possible options to adjust the mining
project proposal to avoid potential impacts identified in the
consultation process.
Responses to the findings of the consultation process will be noted and discussed.
Appropriate adjustments to the mining proposal will be implemented to avoid any
stakeholder and IAP identified impacts.
Describe accordingly the most appropriate procedure to plan and
develop the proposed mining operation with due consideration of the
issues raised in the consultation process.
Appropriate planning and development of the mine and alternative procedures can only
be addressed after feedback from stakeholders and specialists have been received.
These considerations will inform the Scoping and EIA reports.
The remainder of the public participation process consists of the following phases:
1. Distribution of Scoping report to State departments (by DMR) and registered
I&AP’s
2. Tasking of specialists to conduct any further studies
3. Receipt of specialist studies
4. Preparation of draft EMP for distribution
5. Receipt of comments in respect of draft
6. Compilation of EMP for delivery to DMR before approval
The process outlined above will provide opportunity for all parties to give their input into
a document which will therefore consider all aspects and issues and adjust the proposed
mining project as may be appropriate.
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 38
5. A DESCRIPTION OF THE PROCESS OF ENGAGEMENT OF
IDENTIFIED INTERESTED AND AFFECTED PARTIES,
INCLUDING THEIR VIEWS AND CONCERNS
PROVIDE A DESCRIPTION OF THE INFORMATION PROVIDED TO THE
COMMUNITY, LANDOWNERS, AND INTERESTED AND AFFECTED PARTIES TO
INFORM THEM IN SUFFICIENT DETAIL OF WHAT THE PROSPECTING OR MINING
OPERATION WILL ENTAIL ON THE LAND, IN ORDER FOR THEM TO ASSESS WHAT
IMPACT THE PROSPECTING WILL HAVE ON THEM OR ON THE USE OF THEIR
LAND.
Background Information Documents (BID), Annexure a: Background Information
Documents and supporting letters will be sent via email and registered letters to all
Stakeholders and IAP’S. Advertisements notices will be placed in regional and local
newspaper to inform the general public of the proposed mining activity and invite public
comment, (See APPENDIX B- Interested and Affected Parties Register),provides a list
of which of the identified communities, landowners, lawful occupiers and other interested
and affected parties that were consulted.
PROVIDE A LIST OF THEIR VIEWS IN REGARD TO THE EXISTING CULTURAL,
SOCIO-ECONOMIC OR BIOPHYSICAL ENVIRONMENT, AS THE CASE MAY BE.
Existing Cultural Environment
No comments, concerns or views were raised from any of the IAP’s
pertaining to the existing cultural environment of the proposed mine site.
Existing Socio-Economic Environment
The application site is zoned Agricultural Zone 1 in terms of the Section 8
Zoning Scheme Regulations. The primary use permitted is Agriculture, which
means “(a) the cultivation of land or (b) the breeding of animals, or (c) natural
veld, and comprises only of those activities and buildings that directly relate
to the main farming activities on the farm”. The proposed mining activities do
not fall within the above definition and application must be made to the
Langeberg Municipality in terms of the Langeberg Land Use Planning Bylaws
PN 264/2-15, for a temporary departure from the zoning provisions.
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 39
Refer to comments received from stakeholders and IAP’s as found in
Appendix C: Interested and Affected Party Responses.
Existing Biophysical Environment
Listed below is a summary of the comments raised by the Stakeholders and IAP’s:
The area of interest forms part of an important ecological corridor that contributes
towards an upland-lowland link between the Breede and Riviersonderend
Mountains.
The area of interest is mostly classified as a Critical Biodiversity Area.
The area of interest is Priority Botanical Hotspot.
The area of interest is Threatened Plant Hotspot Priority Botanical Hotspot.
The area of interest is classified as top priority property by the Succulent Karoo
Ecosystem Programme (SKEP) (Central Breede River Valley), Lesley Hill
Succulent Karoo Trust (LHSKT), and the National Protected Area Expansion
Strategy (NPAES).
Threatened species that have been recorded within close proximity to the site:
Drosanthemum micans [EN], Freesia marginata [EN], Euphorbia nesemannii
[NT], Eriospermum bowieanum [VU], and Brianhuntleya intrusa [NT].
The vegetation on the land is very close to qualifying as Endangered and has
hardly any formal protection.
Concerns were raised regarding the botanical survey and whether the survey
included different season observations as there are endemic species and Red
list species that only appear at specific seasons.
Watercourses on the site are classified as Ecological Support Areas (ESAs) and
should be protected from activities which may cause degradation.
Refer to comments received from stakeholders and IAP’s as found in Appendix C:
Interested and Affected Party Responses.
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 40
PROVIDE A LIST OF THEIR VIEWS RAISED ON HOW THEIR EXISTING CULTURAL,
SOCIO-ECONOMIC OR BIOPHYSICAL ENVIRONMENT POTENTIALLY WILL BE
IMPACTED ON BY THE PROPOSED PROSPECTING OR MINING OPERATION.
Cultural Environment Impacts
No comments or responses were received from any of the IAP’s pertaining to
the potential impact that the proposed mining site and operation will have on
the existing cultural environment.
Socio-Economic Environment Impacts
While direct impacts on the socio-economic environment were not explicitly
relayed by any of the IAP’s, the potential impact may be inferred to, based on
the views of the IAP’s raised in Section Error! Reference source not found..
he impact would be the loss of zoned agricultural land.
Biophysical Environment Impacts
The seedbank in the topsoil should not be stored for longer than three months as
it will no longer be viable. Rehabilitation on its own is not considered adequate
mitigation as mining areas do not return to the same condition and level of
species diversity that were present before mining commenced.
Main concern is that the general area is an area of critical biodiversity. Therefore
the proposed mining area should be carefully assessed by especially botanists,
as most geophytes are dormant during summer, flowering in autumn, winter and
spring
Even if topsoil is rehabilitated, removal of the clay from the subsoil will
substantially change the drainage and this affects topsoil microclimate adversely
Refer to comments received from stakeholders and IAP’s as found in Appendix C:
Interested and Affected Party Responses.
PROVIDE A LIST OF ANY OTHER CONCERNS RAISED BY THE AFORE SAID
PARTIES
To date, the concerns and views raised by the stakeholders and IAP’s are all accounted
for under Sections Error! Reference source not found. and Section Error! Reference
urce not found. (Refer to: Appendix C: Interested and Affected Party Responses). This
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 41
will be tabulated when the timeline for registration and comments passes on 7th April
2016.
PROVIDE INFORMATION WITH REGARDS TO ANY OBJECTIONS RECEIVED
To date no objections have been received pertaining to the proposed mining
site and activity. If any objections are received prior to 7 April 2016, they will
be included in this section.
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 42
6. DESCRIBE THE NATURE AND EXTENT OF FURTHER
INVESTIGATIONS REQUIRED IN THE ENVIRONMENTAL
IMPACT ASSESSMENT REPORT INCLUDING ANY
SPECIALIST REPORTS THAT MAY BE REQUIRED
SCOPE OF WORK FOR EIA
The following specialist studies will be completed for the EIA/EMP phase:
Botanical assessment of flora and rehabilitation plan
Heritage assessment (Cultural and Paleontological)
Due to the mining techniques proposed as well as well as initial impact identification,
studies of the hydrogeological, botanical and heritage environments will be the focus of
specialist studies.
Hydrogeological
The hydrogeological assessment will provide a baseline study of the geology, hydrology,
geochemistry, potential contamination at the proposed site and the impact of proposed
mining operation on the local aquifer systems and existing groundwater users.
• Desktop study for conceptual hydrogeological model and water quality
• Environmental risk assessment
• Field investigation
• Reporting of data, conceptual models and analysis of potential risks and
proposed mitigating measures to be implemented.
Botanical
Due to the conservation statuses of the endemic vegetation types in the mining
area, a more detailed baseline assessment regarding specific plant species, their
densities and conservation value need to be assessed. Issues that need to be
addressed include:
Vegetation loss during mine implementation and operation phases
Habitat fragmentation
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 43
Cumulative effects of similar proposed operations in the area
Suggested mitigation and rehabilitation procedures
Conservation opportunities identified to formally conserve areas of natural
habitat within the mine property
Heritage
The heritage assessment of the area will focus on both the paleontological and
archaeological significance of the area and assess the cumulative (positive and
negative) impacts within and around the proposed mine property
Identifying heritage resources affected by the mine and associated
infrastructural development.
Assess the significance of any identified resources within the affected area.
Consult with the affected and other interested parties in regard to the
impact on the heritage resources in the project’s receiving environment.
Identify possible mitigating measures with the view to reduce negative
impacts and enhance positive impacts on the heritage resources.
PUBLIC PARTICIPATION PROCESS
The method for current and future public-participation-processes has been discussed in
detail under Section 5. This will abide by and follow the required MPRDA & NEMA
process.
IMPACT ASSESSMENT AND MANAGEMENT OF IMPACTS
The impact assessment for the EIA report will be conducted as above. Any impacts
identified through the PPP process and through specialists studies will be included
within an assessment table which shall look at the significance of potential impacts, their
extent, duration, as well as mitigating procedures to reduce possible negative impacts.
This table will be utilized as the basis for the Environmental Management Plan (EMP).
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 44
7. ADDITIONAL INFORMATION
OTHER MINING OCCURRING IN THE AREA
Cape Lime currently operates an open cast pit mine for the abstraction of limestone in a
quarry ~2 km to the NE, and processes it on the neighbouring property Lange Vallei
5/52.
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page 45
8. REFERENCES
Elsenberg GIS: ArcGIS Services Directory, Western Cape Government: Agriculture
[accessed 2015 Dec 05]. http://gis.elsenburg.com/app/cfm.
Mucina, L., & Rutherford, M.C. (eds). 2006. The Vegetation of South Africa, Lesotho and
Swaziland. Strelitzia 19. South African Biodiversity Institute, Pretoria. ISBN: 978-
1919976-21-1
Jacobs, K. & Jangle, R. 2008. Renosterveld Ecosystem Management Plan: Western Cape.
Unpublished, The Nature Conservation Corporation, Cape Town
P. le Roux, 2012, Report on a Soil Survey as part of an Environmental Impact Assessment
of the development of a Solar Farm on the soils of Valleydora Solar Farm Springfontein,
CSIR, pp10.
SA Explorer: Information by Location [assessed 2015 Nov 25] www.saexplorer.co.za/south-
africa/climate/robertson 2000-2014
Umvoto Africa. (2016). Gannabosch Vlakte 51: Mining Rights Application – Social and
Labour Plan. Prepared by P. Lee, L. Nolakana and J. Rust of Umvoto Africa (Pty) Ltd for
Gannabosch Clay Mine (Pty) Ltd. Report No. 856/05/01/2016, February 2016, 21pp.
WeatherOnline: Weather Online Ltd. [accessed 2015 Dec 03],
www.weatheronline.co.uk/weather/maps/city, 1999-2016
GANNABOSCH CLAY MINE (Pty) Ltd.
Scoping Report Page I
APPENDIX A – MAPS
Figure 5 Regional Topographic Map
Figure 6 Local Map
Figure 7 Local Geology Map
Figure 8 Land/Soil Type Map
Figure 9 Vegetation Map
Figure 10 Critical Biodiversity Status Map
Figure 11 Mine Layout/ Infrastructure Location Map