GANTT CHART Yr./Sec: 4 – D Date of Exposure: January 6 – January 29, 2011 Concept: Community Health Nursing Utilizing COPAR Area: Purok 3, Barangay Lubogan, Toril, Davao City Activities January 6 7 8 Remark s 1 3 1 4 1 5 Remark s 2 0 2 1 2 2 Remark s 2 7 2 8 29 Remarks Courtesy Call to Main Health Center Courtesy Call to Barangay Health Center Courtesy Call to Purok Leader Ocular Survey Area Assignment General Orientation GANTT Chart Making Preparation

Upload: ciena-mae

Post on 13-Apr-2015

64 views

Category:

Documents


2 download

DESCRIPTION

gannt

TRANSCRIPT

Page 1: Gantt Chart 4d

GANTT CHARTYr./Sec: 4 – DDate of Exposure: January 6 – January 29, 2011Concept: Community Health Nursing Utilizing COPARArea: Purok 3, Barangay Lubogan, Toril, Davao City

Activities January

6 7 8 Remarks 13 14 15 Remarks 20 21 22 Remarks 27 28 29 Remarks

Courtesy Call to Main Health Center

Courtesy Call to Barangay Health Center

█ █ █

Courtesy Call to Purok Leader

█ █ █

Ocular Survey █

Area Assignment █

General Orientation █

GANTT Chart Making

Preparation of Survey Forms

Actual Survey █ █

BP Taking █ █

Weight Taking █ █

Identification of Core Group

█ █

Meeting with the Core Group

Page 2: Gantt Chart 4d

Documentation █ █ █ █ █ █ █ █ █

Spot Map/Miniature Making

█ █ █

Tabulation of Initial Data Gathered

Bag Technique █

Finalization of Tabulation of Survey Results

Identification of Community Problems

Formulation of Community Diagnosis

Planning of Activities

Implementation of Programs

█ █

Submission of Initial Manuscript

School Case Presentation

Community Case Presentation

Culmination Program

Corrections/Editing of Manuscript

Submitted to: Helen S. Odchimar R.N.,M.N