gantt2

9

Click here to load reader

Upload: eduardo-aranguiz-olea

Post on 05-Sep-2015

216 views

Category:

Documents


2 download

DESCRIPTION

ujhhjk

TRANSCRIPT

  • ID Task

    Mode

    Task Name Duration Start Finish

    1 Proyecto de Virtualizacin

    43 days Thu 01/01/15 Mon 02/03/15

    2 Reunion Inicial Clientes 1 day Thu 01/01/15 Thu 01/01/15

    3 Definir Objetivos y Alcances

    6 days Fri 02/01/15 Fri 09/01/15

    4 Recopilacin datos de Infraestructura

    8 days Mon 12/01/15 Wed 21/01/15

    5

    6 Realizar Estudio de Sitio

    2 days Mon 12/01/15 Tue 13/01/15

    7 Realizar Inventario Equipos , Aplicacines Y Almacenamiento

    2 days Wed 14/01/15 Thu 15/01/15

    8 Analisis de requerimientos en base a perfomance

    2 days Fri 16/01/15 Sat 17/01/15

    9 Analisis de historicos en base al Almacenamiento

    3 days Mon 19/01/15 Wed 21/01/15

    10 Planificacin de Diseo 6 days Mon 19/01/15 Mon 26/01/15

    W S T M F T S W S T M F

    13 Oct '14 27 Oct '14 10 Nov '14 24 Nov '14

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 1

    Project: Project1

    Date: Sun 19/10/14

  • ID Task

    Mode

    Task Name Duration Start Finish

    11 Analisis de Arquitectura propuesta

    3 days Mon 19/01/15 Wed 21/01/15

    12 Desarrollo de plan detrabajo

    3 days Thu 22/01/15 Sat 24/01/15

    13 Reunion Gerencia Proyectos

    1 day Mon 26/01/15 Mon 26/01/15

    14 Implementacin proyecto

    10 days Tue 27/01/15 Sat 07/02/15

    15 Inicio migracion de servicios

    5 days Tue 27/01/15 Sat 31/01/15

    16 Implementacion servidor Virtualizacin

    2 days Tue 03/02/15 Thu 05/02/15

    17 Marcha Blanca 11 days Mon 09/02/15 Sat 21/02/15

    18 Analsis de comportamiento servicios

    5 days Mon 09/02/15 Fri 13/02/15

    19 Analisis y Respuesta de Incidencias

    7 days Sat 14/02/15 Sat 21/02/15

    20 Capacitacin 5 days Mon 23/02/15 Fri 27/02/15

    W S T M F T S W S T M F

    13 Oct '14 27 Oct '14 10 Nov '14 24 Nov '14

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 2

    Project: Project1

    Date: Sun 19/10/14

  • ID Task

    Mode

    Task Name Duration Start Finish

    21 Entrega 1 day Mon 02/03/15 Mon 02/03/15W S T M F T S W S T M F

    13 Oct '14 27 Oct '14 10 Nov '14 24 Nov '14

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 3

    Project: Project1

    Date: Sun 19/10/14

  • F T S W S T M F T S W S T M F T S W S T M F T S W

    24 Nov '14 08 Dec '14 22 Dec '14 05 Jan '15 19 Jan '15 02 Feb '15 16 Feb '15 02 Mar '15

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 4

    Project: Project1

    Date: Sun 19/10/14

  • F T S W S T M F T S W S T M F T S W S T M F T S W

    24 Nov '14 08 Dec '14 22 Dec '14 05 Jan '15 19 Jan '15 02 Feb '15 16 Feb '15 02 Mar '15

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 5

    Project: Project1

    Date: Sun 19/10/14

  • F T S W S T M F T S W S T M F T S W S T M F T S W

    24 Nov '14 08 Dec '14 22 Dec '14 05 Jan '15 19 Jan '15 02 Feb '15 16 Feb '15 02 Mar '15

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 6

    Project: Project1

    Date: Sun 19/10/14

  • W S T M F T S W S T M F T S W S T M F T S W S T M

    02 Mar '15 16 Mar '15 30 Mar '15 13 Apr '15 27 Apr '15 11 May '15 25 May '15 08 Jun '15

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 7

    Project: Project1

    Date: Sun 19/10/14

  • W S T M F T S W S T M F T S W S T M F T S W S T M

    02 Mar '15 16 Mar '15 30 Mar '15 13 Apr '15 27 Apr '15 11 May '15 25 May '15 08 Jun '15

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 8

    Project: Project1

    Date: Sun 19/10/14

  • W S T M F T S W S T M F T S W S T M F T S W S T M

    02 Mar '15 16 Mar '15 30 Mar '15 13 Apr '15 27 Apr '15 11 May '15 25 May '15 08 Jun '15

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 9

    Project: Project1

    Date: Sun 19/10/14