gasco-uae

Upload: megha-rawat

Post on 06-Jul-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/17/2019 Gasco-UAE

    1/3

     Abu Dhabi Gas Industries Ltd, known as

    GASCO, is part of the ADNOC group and is the

    operating company in Abu Dhabi responsible for

    processing non-associated gas from standalone

    gas reservoirs and associated gas from onshore

    oil production. Abu Dhabi ranks fifth in the world

    in terms of its gas reserves.

    We have played a key role in three interlinked

    projects, Habshan-3, Ruwais NGL Train-3

    and Habshan-4, which are integral to

    GASCO’s multi-billion-dollar gas expansion.

     Habshan-4 will process incremental 

     associated gas resulting from ADNOC’s expansion of its

    crude production.

     At full capacity the new train will 

     handle up to 24,400 tpd of natural  gas liquids to provide 6,400 tpd of 

     raw ethane, 6,000 tpd each of  propane and butane and 5,800 tpd 

    of paraffinic naphtha.

     Habshan is one of the world’s

     largest gas processing plants. The new Habshan-3 facilities have

     a processing capacity of1,300 million scfd of condensate-

     rich gas to produce 130,000 bpd 

    of condensate and 11,800 tpdof natural gas liquids.

    GASCO’smulti-billion-dollar upstream expansion

    Playing a key role inHabshan-3 Ruwais NGL Train-3 Habshan-4

     Ruwais NGL Train-3 utilities with new storage and jetty in background.

    This article waspublished in FW NewSummer 2010. Formore informationplease contact us [email protected]

    © 2013 Foster Wheeler All rights reserved

    NEWS

  • 8/17/2019 Gasco-UAE

    2/3

     A trusted teamOur involvement in the GASCO projects started

    in early 2002 when, as PMC, we began the

    evaluation of the FEED tenders for the suite of

    projects. This was followed by support to the

    GASCO team in the management of the FEED

    phase and then bidding support and evaluation

    of the EPC tenders in Abu Dhabi through much of

    2004. We have been project managing the EPC

    phases on behalf of GASCO since the start of

    2005. All three projects are now at, near, or past

    the finishing post.

    ‘Right first time’A feature of the suite of GASCO projects has been

    regular multi-project workshops where project

    status and lessons learned have been shared

    between the GASCO and PMC teams throughout

    the EPC home office phase.

    A particular theme has been a focus on ‘right first

    time start-up’ (RFTSU). The EPC contractors were

    required to develop and implement detailed RFTSU

    programmes for a trouble-free start-up. RFTSU is

    a proactive methodology where risks and likely

    problems, which may later result in commissioning

    and start-up problems or delays, are identified and

    mitigation action plans put in place.

    Habshan-3GASCO’s Habshan complex is one of the world’slargest gas processing plants producing condensate

    and natural gas liquids (NGL). Habshan-3 is the

    latest phase of the Habshan development to

    come on-line.

    The Habshan-3 facilities have a processing

    capacity of 1,300 million standard cubic feet

    per day (scfd) of condensate-rich gas to produce

    130,000 barrels per day (bpd) of condensate

    and 11,800 tonnes per day (tpd) of NGL.

    The two-train facility includes process units

    for gas/condensate separation, condensate

    stabilisation, gas treating, gas dehydration and

    NGL recovery, and condensate and NGL storage,

    along with a full complement of utilities. Reservoir

    pressure is maintained through the reinjection

    (at over 350 bar) of a n equal volume of gas withmake-up gas supplied by the national sales gas

    network. The compression facilities required

    for this element of the facility consist of eight

    compressors each driven by 22MW GE Frame-5

    gas turbines.

    The NGL from Habshan-3 is pumped to the new

    Ruwais third NGL fractionation train via a new

    24” pipeline and the condensate is pumped to

    the TAKREER refinery in Ruwais. The acid gas

    waste stream is sent to the new sulphur recovery

    plant that is part o f the Habshan-4 facilities.

    Habshan-3 has over 700 major equipment items,

    of which 24 are major process compressors, with

    all manner of drives: gas turbines, steam turbines,

    fixed-speed electric motors and variable-speed

    electric motors. There are some very large process

    vessels with two 635-tonne de-methanisers and

    two 850-tonne high pressure amine absorbers. At

    peak, the EPC workforce at site was over 7,000.

    The project revenue streams of condensate and

    NGL are now flowing to specification with only

    plant performance test runs and project close-out

    to complete.

    KEY: FW’s PMC scope for:

     Arabian Gulf

    Oman

    UAE

    Oman

     Abu Dhabi

    Dubai

    Ruwais

    Habshan

     Asab

    GASCORuwais NGL Train-3

    New Fractionation TrainNew JettyStorage FacilitiesO&U

    GASCOHabshan-4

    1 x Gas Compression Train1 x Acid Gas Enrichment2 x Sulphur Recovery1 x Sour Water Stripper1 x Condensate Stabilisation

     ADCOHabshan/Bab

    Gas Gathering & Injection

    GASCO Asab-2

    2 x Gas Treatment2 x NGL Recovery1 x NGL PipelineO&U

    TAKREERRuwais Expansion

    Condensate Storage &Shipping Facilities

    GASCOHabshan-3

    2 x Condensate Separation/Stabilisation2 x Gas Treatment2 x NGL Recovery4 x Reinjection Trains1 x NGL PipelineO&UCondensate + NGL Storage

    “This has been a major project management undertaking for

    Foster Wheeler. Our involvement started from the pre-award stage

    of the FEED contract and continued right through to start-up.

    We are proud to have been associated with this world-class venture.”

    Graeme Lang

    Project Sponsor and Director, Projects

    Foster Wheeler Energy Limited

     Habshan-4 acid gas enrichment. Ruwais NGL Train-3 main compressor shelter.

    Overview of Habshan-3 facilities.

    FEED Phase

    FEED & EPC Phases

    This article waspublished in FW NewSummer 2010. Formore informationplease contact us [email protected]

    © 2013 Foster Wheeler All rights reserved

    NEWS

  • 8/17/2019 Gasco-UAE

    3/3

    Ruwais NGL Train-3The new third processing train is designed to

    handle up to 24,400 tpd of NGL produced by the

    Habshan-3, Asab-2 and other upstream projects.

    The single-train NGL fractionation facility is currently

    amongst the largest facilities of its kind in the world.

    At full capacity the new train will provide 6,400 tpd

    of raw ethane as feedstock to the Borouge-2 facility,

    for which Foster Wheeler is also providing PMC

    support. The remaining product streams, 6,000 tpd

    each of propane and butane and 5,800 tpd of

    paraffinic naphtha, will be exported by tanker.

    The main process columns were fabricated locally

    and the de-ethaniser, weighing in at 1,077 tonnes

    and 53 metres tan-to-tan, is, we believe, the largest

    vessel ever fabricated within the UAE.

    In addition to the fractionation unit where the NGL

    is split into its component products, the gaseous

    ethane and liquid propane and butane are

    sweetened and dried. Product storage has been

    significantly expanded with the addition of four new

    cryogenic storage tanks plus a new floating-roof tank

    for the paraffinic naphtha. There are two additional

    marine berths capable of handling tankers up to

    125,000m3, providing flexibility and capacity for

    future expansion.

    The Train-3 facilities have been fully integrated with

    the existing plant to enhance reliability and include,

    for the first time at Ruwais, a medium-pressure

    steam system for reboiler operation. The site

    construction labour force peaked at over 7,000, and

    a strong focus on safety was diligently maintained.

    The main plant performance tests have been

    successfully completed and routine marine

    operations from the two new berths are ongoing.

    Our PMC team is resolving final documentation

    issues and is closing out the site.

    Habshan-4The objective of the Habshan-4 project is to enable

    the facility to process incremental associated gas

    resulting from ADNOC’s expansion of its crude oil

    production from 1.2 to 1.4 million bpd, increasing

    condensate production by 15,000 bpd and sulphur

    by 1,600 tpd.

    We were initially appointed as project manager

    for the FEED phase of this project. This contract

    was extended in October 2005 to cover project

    management of the EPC phase.

    The Habshan-4 facilities are distributed both within

    and adjacent to the existing facilities. Low- and

    medium-pressure gas compression, condensate

    stabilisation, sour water stripping and utilities are at

    multiple locations within the existing facilities whilst

    feed gas compression, acid gas enrichment and

    sulphur recovery are on an adjacent plot.

    The many interfaces with the existing plant were

    a key feature of the project. In addition to numerous

    piping tie-ins, a major upgrade of the existing control

    system was undertaken both to improve the operation

    of the existing facilities and expand the system to

    accommodate the new plant. The requirement to

    maintain ongoing operations and minimise shutdowns

    presented a significant challenge to the project.

    Commissioning is now well advanced and parts

    of the Habshan-4 plant have been operational for

    several months. The compression train, condensate

    stabilisation, acid gas enrichment, sulphur recovery

    and most of the utilities are in operation. Much of

    the plant is being operated by the client’s operations

    personnel under the responsibility of the EPC

    contractor, pending completion of test runs and

    handover. Acid gas feedstock has been received

    from Habshan-3, enabling the acid gas enrichment

    unit test run to proceed.

    With construction work completed in late 2009, the

    PMC team has reduced in size and is focused on final

    commissioning and handover activities, which are

    expected to complete by the third quarter of 2010.

    Rising to the challengeOverall it has been a remarkable achievement

    bringing these parallel projects to life from the start

    of the FEEDs to production.

    The success to date has been a real testament to

    the focus of the client and Foster Wheeler team on

    managing the plethora of interfaces, within each

    project, between projects, and with other related

    projects ongoing around the same time.

    In addition, the EPC phases spanned very challenging

    times for project execution, with a troubled global

    economy and very stretched supplier and sub-

    contractor markets.

    We are proud to be reaching the finish line, having

    proved once again that dealing with technical and

    logistical complexity is something at which we excel!

     Main picture: Ruwais NGL Train-3 butane storage with jetty in background.

     Inset: Berth 3 looking west.

    This article waspublished in FW NewSummer 2010. Formore informationplease contact us [email protected]

    © 2013 Foster Wheeler All rights reserved

    NEWS