Geographical Presence (Offices)
Solihul, West Midland
ISPRA
Madrid
Paris
Spain (Valence Headquarters) Avda. Cortes Valencianas,58 Sorolla Center local 10 46015 Valencia España Phone: +34 963 540 300
Spain (Madrid Offices)
Paseo de la Castellana 163
28046 Madrid (Spain)
Phone: +34 916 409 870
United Kingdom
Regus House, Central Boulevard, Blythe Valley Business Park, Solihull, West Midlands, B90 8AG (Registered office for GD Energy Services Nuclear Limited) Lythemore House, Forss Business & Technology Park, Forss, Thurso, Caithness, KW14 7UZ Phone: 01847 808100
Aggregate sales: € 95 million
Number of employees: 1.700
Marseille
Valence
Thurso
2
Global Foot Print
Brazil
Singapore
United Kingdom
Mexico Italy
Spain
France
Qatar
United States
United Arab Emirates
Eastern Europe
Panama
3
GDES offers services for several sectors.
Nuclear Services
SERVICES:
• Decontamination
• Dismantling of nuclear installations
• Radiation protection
• Training and technical advice
• Chemical cleaning
• Maintenance Cleaning
• Surfaces treatments
• Radiation emergencies
• Logistic outsourcing
5
GDES Innovation
Chemical engineering laboratory
Robotics and control process laboratory.
Design and development laboratory
Innovation Center (R&D&i)
6
UK
GDES provides decommissioning operatives across the Dounreay (UK - NDA) site including PFR (Na) and DFR (NaK). We also provide Professional Services to DSRL which includes providing Engineers and conducting studies. Additionally, we have worked on other sites handling Na and NaK from reactor projects including JRC-Ispra and JRC-Karlsruhe Typical scope of work includes:
Technical studies Risk assessments Radiological assessments Method Statements Implementation / Operations Disposal
Dounreay (UK - NDA)
9
Image © DSRL & NDA
DSRL Decommissioning Framework
10
UK
• In 2013 NDSL (now GDES) was awarded a framework by DSRL to provide decommissioning services following a similar framework which was held from August 2010 building upon an even earlier framework for operatives in 2007. The scope of the new framework potentially includes:
o Full turnkey decommissioning projects
o FEED studies
o Provision of Decommissioning Teams
• The framework operates through ‘mini – competitions’ and for the current tranche (up to 2017) NDSL is providing the largest team (~80 personnel) on the Dounreay site.
• The teams are allocated through the GDES Labour Allocation Manager (co-located with DSRL on site) across the site in Reactors (DFR & PFR) and the Fuel Cycle Area (FCA).
• As a result the teams are experienced in working in a variety of hazardous environments including Alpha (PCM), Alkali metals and Beta / Gamma.
GDES Innovation
•Disposal of Na / NaK for JRC-Ispra. This involved re-packaging of the alkali metals and incineration •Germany Decontamination of NaK whetted items Disposal of secondary Cold Trap at KNK Karlsruhe Disposal of U contaminated Na at JRC- Ispra Repackage 25Te of Na at RSRL Winfrith (UK)
11
Alkali Metals (Europe)
UK
• Serves 12 separate facilities in the Fuel Cycle Area and is connected to 17 individual active and non-active ventilation systems
• Enabled the transfer of all systems from the original centralised system in the course of a weekend with minimal disruption
• The system has a capacity of 84 m3/s
• NDSL came up with the concept design and developed that into a comprehensive scheme design
Replacement ventilation system for the Fuel Cycle Area at Dounreay
12
12
VANDELLÓS I NPP (Spain)
13
Tarragona (Spain)
Decommissioning of the activated parts
and decontamination of the singular
elements. 1999-2005.
• Preparatory activities.
• Conditioning of the site to undertake the disassembly into hotspots.
• Dismantling and removal of the site equipment and of the conventional structures.
• Implementation or modification of systems and facilities.
• Dismantling of activated components and decontamination of singular elements.
• Reactor isolation.
• Walls scarifying
• Dismantling of the Storage ATC-Silos.
• Building the Weather protection of the reactor and preparing the infrastructure for latency period.
Guadalajara (Spain)
Removal of the reactor core internals. Client:
Westinghouse.
• Cutting and removal of concrete walls between the Spent Fuel Pool and reactor cavity.
• Removal of the fuel racks from the SFP.
• Removal of upper and lower internals.
• Disassembling of demineralizers and SFP instrumentation.
• Cleaning and filtering of the SFP and reactor cavity.
• SFP Liner repair with divers and remote techniques.
• Handling and support for cutting operational waste.
• Removal concrete and steel parts from reactor cavity walls and floor
• Construction of new concrete floor in reactor cavity.
• Waterproofing Reactor cavity and SFP.
• Conditioning of 5 T Jaso Crane.
• Supply of a new bridge in SFP.
• Cutting and segmentation reactor vessel head CRDM tubes.
• Planning and assistance to the internals segmentation.
• Lifting, handling, and radiological control of NCS 45 container
JOSÉ CABRERA NPP (Spain)
14
CIEMAT (Spain)
15
Nuclear Research Centre Madrid (Spain)
Decontamination and
Decommissioning of nuclear and
radioactive facilities (1985-to date).
• Decontamination and
decommissioning of more than 20
radioactive and nuclear facilities.
• Decommissioning of the Pu-Glove
Boxes, Hot Cells, underground
storage tanks for high and
intermediate level liquid waste.
• Refurbishment of the nuclear
facilities (PIMIC – Integrated Plan
for the Facilities Improvement).
EUROPEAN COMMISSION JRC - ISPRA (Italy)
16
Italy
Radiation Protection Assistance to the
Decommissioning activities. Framework
contract: 2006-2010; Client : Iberdrola
Ingenieria y Construcción.
• Supply and maintenance of specific
instruments
• Characterisation of facility
• Planning of activities
• Expected exposure evaluation
• Assistance during planned activities
• Decontamination
• Confinement/conditioning
• Organisation of waste
• Radiological survey/routine checks
17
Italy
Transferring of radioactive sludge and
further decontamination of a tank. 2010-
2012. Client: EUROPEAN COMMISSION.
• Design of sludge transfer system.
• Design of ventilation system.
• Radiological environmental impact
studies.
• Project management.
• Transfer system Implementation
• Decommissioning tasks
implementation.
• Decontamination of tank L1.
• Waste Management.
EUROPEAN COMMISSION JRC - ISPRA (Italy)
“GALILEO GALILEI” CISAM – PISA - (Italy)
18
Italy
Dismantling of Nuclear «Galileo Galilei»
RTS-1 Reactor
• Treatment of 750 m3 of water
• Definition of Controlled water release
• Cut , decontamination, contidiotning0f
25 tons of solid wastes
• Environmental Surveillance Plan
• Project Planning
• Health and Security
• Radioprotection Plan
• Quality Plan
DECOMMISSIONING OF ARBI REACTOR (Italy)
19
Italy
Tank located in a European Scientific and
Technical Research Centre.
JRC/CCR Ispra (VA) – Italy. May 2012/July 2012
Execution:
• 4.062 hours man. 400 metal components. 618
concrete blocks. 411 graphite blocks.
• Monitoring of materials for its declassification:
98.000 radiation dose rate and contamination.
Waste Management:
• Inert and recycled solid waste: concrete blocks
and metals. Evacuation by managing company.
• Dangerous waste (graphite, Cd, paraffin)
• Wiring waste and electronic components.
Radioactive waste management. ENRESA.