general specification for the civil sub-03-017 … · the guidance drawings listed below are...

15
GENERAL SPECIFICATION FOR THE CIVIL ENGINEERING AND BUILDING DESIGN AND CONSTRUCTION OF SECONDARY SUBSTATIONS SUB-03-017 Appendix 1 10/07/2018 _________________________________________________________________________________ © SP Power Systems Limited APPENDIX 1: DRAWINGS The guidance drawings listed below are typical layout and construction details deemed to satisfy SPEN’s functional civil and building requirements for Secondary Substations. Constructors shall note that where provided such typical details may be generic and may not reflect exact on-site requirements on a project/site-specific basis. Where applicable and considered appropriate by SPEN, additional typical deemed to satisfy construction detail drawings may be issued on a project-specific basis. Variations or changes to the ‘deemed to satisfy guidance drawings’ shall be submitted to SPEN for audit and agreement prior to any work starting on-site. Drawing No. Drawing Title Revision SP2022244 Typical 11kV GRP Plinth (No Metering) 5 SP2103445 Typical 11kV GRP Plinth (With Metering) 5 SP2142493 Typical 11kV RMU GRP Plinth (With Metering) 5 SP3020357 Typical 11kV Brick Built Substation (Close Coupled Gear) 6 SP4000542 Typical Z Vent Louvered Ventilation Unit For Brick Built Substation 5 SP4000543 Typical Hardwood Doors for 11kV Substations 4 SP4000545 Typical 11kV Brick Built Substation (X or Y Type Separate Gear) 5 SP4008870 Typical 11kV Brick Built Substation (3 Panel Board With Metering) 6 SP4049060 Typical 11kV Brick Built Substation (D or G Type RMU With Metering) 10 SP4053389 Typical 11kV Brick Built Substation (Double Side by Side) 3 SP4058664 Typical 11kV Brick Built Substation (Double Square) 3 SP4102117 Typical 11kV GRP Plinth D Type RMU with MU Single Plinth 2 SP4105959 Typical 11kV Brick Built (LV Generation Substation 3 SP4132847 Typical 11kV GRP Plinth G or D Type RMU (indoor Kit) 2

Upload: others

Post on 22-Mar-2020

25 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: GENERAL SPECIFICATION FOR THE CIVIL SUB-03-017 … · The guidance drawings listed below are typical layout and construction details deemed to satisfy SPEN’s ... This drawing is

GENERAL SPECIFICATION FOR THE CIVIL

ENGINEERING AND BUILDING DESIGN AND CONSTRUCTION OF SECONDARY

SUBSTATIONS

SUB-03-017 Appendix 1 10/07/2018

_________________________________________________________________________________

© SP Power Systems Limited

APPENDIX 1: DRAWINGS

The guidance drawings listed below are typical layout and construction details deemed to satisfy SPEN’s functional civil and building requirements for Secondary Substations.

Constructors shall note that where provided such typical details may be generic and may not reflect exact on-site requirements on a project/site-specific basis.

Where applicable and considered appropriate by SPEN, additional typical deemed to satisfy construction detail drawings may be issued on a project-specific basis.

Variations or changes to the ‘deemed to satisfy guidance drawings’ shall be submitted to SPEN for audit and agreement prior to any work starting on-site.

Drawing No. Drawing Title Revision

SP2022244 Typical 11kV GRP Plinth (No Metering) 5

SP2103445 Typical 11kV GRP Plinth (With Metering) 5

SP2142493 Typical 11kV RMU GRP Plinth (With Metering) 5

SP3020357 Typical 11kV Brick Built Substation (Close Coupled Gear) 6

SP4000542 Typical Z Vent Louvered Ventilation Unit For Brick Built Substation 5

SP4000543 Typical Hardwood Doors for 11kV Substations 4

SP4000545 Typical 11kV Brick Built Substation (X or Y Type Separate Gear) 5

SP4008870 Typical 11kV Brick Built Substation (3 Panel Board With Metering) 6

SP4049060 Typical 11kV Brick Built Substation (D or G Type RMU With Metering)

10

SP4053389 Typical 11kV Brick Built Substation (Double Side by Side) 3

SP4058664 Typical 11kV Brick Built Substation (Double Square) 3

SP4102117 Typical 11kV GRP Plinth D Type RMU with MU Single Plinth 2

SP4105959 Typical 11kV Brick Built (LV Generation Substation 3

SP4132847 Typical 11kV GRP Plinth G or D Type RMU (indoor Kit) 2

Page 2: GENERAL SPECIFICATION FOR THE CIVIL SUB-03-017 … · The guidance drawings listed below are typical layout and construction details deemed to satisfy SPEN’s ... This drawing is
Page 3: GENERAL SPECIFICATION FOR THE CIVIL SUB-03-017 … · The guidance drawings listed below are typical layout and construction details deemed to satisfy SPEN’s ... This drawing is
Page 4: GENERAL SPECIFICATION FOR THE CIVIL SUB-03-017 … · The guidance drawings listed below are typical layout and construction details deemed to satisfy SPEN’s ... This drawing is
Page 5: GENERAL SPECIFICATION FOR THE CIVIL SUB-03-017 … · The guidance drawings listed below are typical layout and construction details deemed to satisfy SPEN’s ... This drawing is

11

15

79

8

21

52

15

3590 Ext.

665 798 798 665

31

60

In

t.

SIDE ELEVATION

REAR ELEVATION

FRONT ELEVATION

PLAN

35

90

E

xt.

floor slab

cable slots - below

to trench sides &

215mm Brickwork

SECTION B-B

SECTION A-A

Trench

Cable

Slot

68

5

2035 ==

AA

B

B

G.L.

F.F.L.

24

10

15

0

25

06

75

21

85

D

oo

r o

pe

nin

g

30

0 S

lo

t

82

5

22

53

85

38

5

75

Cable

Slot

Galvanised steel ventilators

Cable

Slot

to top, on Visqueen or similar

(anti-crack) fabric with 20mm cover

concrete reinforced with A142

Floor slab to be min. 150mm thk.

NOTE

It is essential that EnergyNetworks

personnel can access

& properly secure on egress

Facing brick to finish

DETAIL AT DOORWAY

suit door spec.

Threshold detail to

F.F.L.

1 course below G.L.

G.L.

40mm cover

1 sheet top, 1 sheet bottom,

2 sheets of A252 fabric -

to be reinforced with

Concrete floor over cable slots

min. 100mm bearing

cable slots

R.C. lintels over

over open trench area

to u/s to prevent movement)

plywood covers (with battens fitted

Provide 19mm thk. temporary

over cable slots

Reinforced floor slab

approved dpm, on sand blinding

DETAIL

SEE

metal lintel

Proprietary corrosion resistant

DETAIL

SEE

150mm thickness of rounded

sand filled, trench topped with

Cable trench & slots to be

50

15

0

(or similar approved)

with 2 layers of Visqueen

level and smooth, topped

10mm Thk. cured bed joint,

Scale 1:10

15

0

10

0

3690

3790 Slab o/a

36

90

10

0

37

90

S

la

b o

/a

ROOF SECTION

ROOF PLAN

FOUNDATION

PLAN OF BRICKWORK BELOW FLOOR SLAB

Concrete slab, reinforced with

min. A393 fabric with 40mm cover

to sides, top and bottom.

Laps to be min. 400mm

25

0

11

15

= =

C

L

778778

665665

18

00

21

5

910 909

21

5

21

5

FallFall

215

Cable

Slot

Cable

Slot

2260 B.O.

2035

2465

25mm Galvd. M.S. bar

A252 Fabric reinft.

900 X 900mm sheet

Haulage

eye (see

detail)

HAULGE EYE DETAIL Scale 1:20

C

L

13

0

10

0

30

0

18

0

12

5 C

ove

r

15

01

50

R

5

0

100 Cover

all doors at all times. Any

hardwood, metalwork or GRP

construction doors that may

shrink, warp, wind, distort,

corrode or bind will not be

acceptable

L.H. leaf to open first

SECTION

Min

.

Min

.

Min

.

(min. 150mm end bearing)

laps to be 400mm

20mm cover to bottom,

75mm cover to sides and

Roof reinft. min. A393 mesh with

ventilator openings

R.C. lintels over

(see detail)

For plant installation:

Weak mix concrete

or graded stone infill

with suitable polysulphide

Rake out and point

movement joint sealant

Drip

LINTOL TO VENT OPENING SCALE 1:20

Min. 2 No. 6mm dia. m.s. bars at 45mm centres

(shape code 21 bar length 1040mm 'A'=940mm)

1000 103

14

0

25mm Cover

to bars

D.P.C.

where graded stone infill is used

(top to be level with F.F.L.)

gravel chippings

Additional foundation and/or

ground improvement works

to constructors design

to suit site-specific conditions

60

0

600mm rad.

100mm I/D

cable duct

NOTES

cScale

A2Size

Status

Location

Drawn

Title

Drg. No.

CheckedDate Date

Rev.

DateApproved

Drawn

CheckedApproved

Rev. Date

SP PowerSystems LtdSystem Design, Drawing Office3 Prenton Way , Prenton , CH43 3ETTelephone 0151 6092491

ISSUED SP3020357

TYPICAL TRADITIONAL BUILDING DETAILS FOR11kV BRICKBUILT SUBSTATION

(CLOSE COUPLED GEAR)

1:50

TYPICAL

M.T. JAN.07 C.W. JAN.07 A.J.R. JAN.07

C.B.27/11/17

GRGR

GENERAL UPDATES TO REFLECT CHANGESTO CIVIL POLICY DOCUMENTS

GeneralThis drawing is to be read in conjunction with document SUB-03-017 GeneralSpecification for the Civil Engineering and Building Design and Construction ofSecondary Substations. It is the constructor's responsibility to confirm, beforeconstruction, that the details on this drawing are correct as per SUB-03-017.

This is a generic guidance drawing that is deemed suitable for construction. Howeverthe constructor should consider all site specific risk that will affect the design andoperation of the substation. Proposed substation details are to be submitted foracceptance before installation.

Details shown on this drawing are typical for this type of substation building but maynot be suitable for substations housing alternative equipment. The constructor shallsatisfy themselves that the appropriate details shown are correct depending on thetype of substation being constructed.

ConcreteGeneralThe concrete shall be in accordance with the specification and attain the relevant cubcrushing strength at 28 days.

Foundations (Concrete 40N/mm² 28-Day Cube Strength)Foundations are to be set on undisturbed inorganic strata that provide the requiredminimum design safe ground bearing capacity. Minimum bearing capacity to be75kN/m².

Floor (Concrete 40N/mm² 28-Day Cube Strength)A flat, level and smooth floor surface is essential for installation of plant. Tolerancesto finished level expressed as a maximum permissible deviation beneath a straightedge with feet placed anywhere on the floor shall not exceed 1mm in 1m or 3mm in3m. Floors to be cured, prepared & painted with 2 No. Coats of non-slip floor paint oncompletion.

BrickworkGeneralAll brickwork below D.P.C. to be H.D. category 1 min. 75N/mm² mean compressivestrength and max 7% M.A. and durability designation F2 S2 (Ex Engineering BrickworkClass B) in English bond except for exposed faces.External facing brickwork to be H.D. category 1 min. 30N/mm² mean compressivestrength and max 12% M.A. and durability designation F1 S1 or better.Internal facing brickwork to fair faced smooth textured solid concrete bricks, sized tomatch external facing bricks and with a mean compressive strength of not less than20N/mm².Class iii mortar.

WallsWalls shall be 215mm English garden wall bond or Collar jointed stretcher bond.Leaves of collar jointed double stretcher walls to be tied together by means of type 1or type 2 stainless steel ties laid in every fourth course at 375mm centres and set back38mm from outer face, ties are to be staggered.

DoorsDetails of proposed doors shall be submitted to SPEN for comment, before workcommences.Proprietary GRP faced aluminium or steel security doors are the preferred option,unless stated otherwise.An alternative option for hardwood doors (see Drg SP4000543 for details) or GRPdoors is also available.

Cable Trench & SlotsOn completion of cabling, cable trench and slots to be filled with dry sand topped witha minimum 150mm depth of rounded gravel chippings (top to be level with FFL).

RoofStandard Concrete Roofs (Concrete 40N/mm² 28-Day Cube Strength)Wherever practicable, roofs should be cast in situ reinforced concrete constructionwith a soffit finish. Slip joints shall be incorporated at wall bearings, polysulphidesealed externally. Internal / External faces of concrete to be fair faced. All externalfaces to be cured, prepared, primed and finished with a two coat high performance(Aliphatic) polyurethane waterproofing system (flat roof grade) with glass fibre matreinforcement to initial coat, e.g.

1No. Coat of LPL bonding primer then2No. Coats of LPL Decothane.

Obtainable from Liquid Plastics Tel. 01772 259 781 or Equal System

All finishes are to be in accordance with the manufacturers recommendations.

Where permanent structural metal soffit shutters are used as part of a compositeroof system these shall be corrosion resistant and the Constructor's proposals forscreening or tagging for earthing purposes shall be expressly agreed with SPEN priorto construction.

VentilationVentilation shown is typical for a single 500kVA transformer substation.The typical ventilation indicated may not be adequate in certain supply conditionswhich might require additional or alternative ventilation arrangements.

Related Typical Deemed to Satisfy DrawingsHardwood Doors SP4000543Meter Cupboards SP4078901Vent for Brickbuilt substation SP4000542

Page 6: GENERAL SPECIFICATION FOR THE CIVIL SUB-03-017 … · The guidance drawings listed below are typical layout and construction details deemed to satisfy SPEN’s ... This drawing is
Page 7: GENERAL SPECIFICATION FOR THE CIVIL SUB-03-017 … · The guidance drawings listed below are typical layout and construction details deemed to satisfy SPEN’s ... This drawing is
Page 8: GENERAL SPECIFICATION FOR THE CIVIL SUB-03-017 … · The guidance drawings listed below are typical layout and construction details deemed to satisfy SPEN’s ... This drawing is

13

0

23

10

280

B.O

.

79

88

90

1003

215

40

50

36

20

21

5

215

1002

21

5

14

00

15

0

B.O

.

150

B.O.

75

MIN

. 2

50

82

5M

IN

. 2

41

0

3590

3160

112

345

75

3690

41

50

400

75

15

00

15

00

75

75

3590

MIN

. 2

50

215

21

5

40

50

215

21

52

31

0

457

215 215

280

14

00

21

52

15

MIN

. 1

00

MIN

. 1

00

MIN

. 1

50

1115798

38

53

85

B.O

.

1585 B.O.

*

*

150

150

100

125

R

5

0

100

1000

25 25 103

140

2525

25

180

100

300

50

75

NOTES

cScale

A1Size

Status

Location

Drawn

Drg. No.

CheckedDate Date

Rev.

DateApproved

Location

Title

SP PowerSystems LtdSystem Design, Drawing Office3 Prenton Way , Prenton , CH43 3ET

Drawn

Checked

Approved

Rev. Date

Telephone 0151 6092491

ISSUED SP40005451:50

TYPICAL

L.A. 12/4/06 M.T. 12/4/06 A.J.R. 12/4/06

TYPICAL TRADITIONAL BUILDING DETAILS FOR11kV BRICKBUILT SUBSTATION

(X OR Y TYPE SEPARATE SWITCHGEAR)

C.B.27/11/17

GRGR

GENERAL UPDATES TO REFLECT CHANGES TOCIVILS POLICY DOCUMENT

GeneralThis drawing is to be read in conjunction with document SUB-03-017 General Specification forthe Civil Engineering and Building Design and Construction of Secondary Substations. It is theconstructor's responsibility to confirm, before construction, that the details on this drawing arecorrect as per SUB-03-017.

This is a generic guidance drawing that is deemed suitable for construction. However theconstructor should consider all site specific risk that will affect the design and operation of thesubstation. Proposed substation details are to be submitted for acceptance before installation.

Details shown on this drawing are typical for this type of substation building but may not besuitable for substations housing alternative equipment. The constructor shall satisfythemselves that the appropriate details shown are correct depending on the type of substationbeing constructed.

ConcreteGeneralThe concrete shall be in accordance with the specification and attain the relevant cub crushingstrength at 28 days.

Foundations (Concrete 40N/mm² 28-Day Cube Strength)Foundations are to be set on undisturbed inorganic strata that provide the required minimumdesign safe ground bearing capacity. Minimum bearing capacity to be 75kN/m².

Floor (Concrete 40N/mm² 28-Day Cube Strength)Floors of substations housing indoor switchgear shall have a visqueen damp proof membraneinstalled where graded stone infill is used.A flat, level and smooth floor surface is essential for installation of plant. Tolerances to finishedlevel expressed as a maximum permissible deviation beneath a straight edge with feet placedanywhere on the floor shall not exceed 1mm in 1m or 3mm in 3m. Floors to be cured, prepared& painted with 2 No. Coats of non-slip floor paint on completion.

BrickworkGeneralAll brickwork below D.P.C. to be H.D. category 1 min. 75N/mm² mean compressive strengthand max 7% M.A. and durability designation F2 S2 (Ex Engineering Brickwork Class B) in Englishbond except for exposed faces.External facing brickwork to be H.D. category 1 min. 30N/mm² mean compressive strength andmax 12% M.A. and durability designation F1 S1 or better.Internal facing brickwork to fair faced smooth textured solid concrete bricks, sized to matchexternal facing bricks and with a mean compressive strength of not less than 20N/mm².Class iii mortar.

WallsWalls shall be 215mm English garden wall bond or Collar jointed stretcher bond.Leaves of collar jointed double stretcher walls to be tied together by means of type 1 or type 2stainless steel ties laid in every fourth course at 375mm centres and set back 38mm from outerface, ties are to be staggered.

DoorsDetails of proposed doors shall be submitted to SPEN for comment, before work commences.Proprietary GRP faced aluminium or steel security doors are the preferred option, unless statedotherwise.An alternative option for hardwood doors (see Drg SP4000543 for details) or GRP doors is alsoavailable.

Cable Trench & Slots/RampOn completion of cabling, cable trench to be filled with dry sand and skimmed with minimum50mm depth of sand/cement screed over a visqueen membrane (top to be level with FFL).

RoofStandard Concrete Roofs (Concrete 40N/mm² 28-Day Cube Strength)Wherever practicable, roofs should be cast in situ reinforced concrete construction with asoffit finish. Slip joints shall be incorporated at wall bearings, polysulphide sealed externally.Internal / External faces of concrete to be fair faced. All external faces to be cured, prepared,primed and finished with a two coat high performance (Aliphatic) polyurethane waterproofingsystem (flat roof grade) with glass fibre mat reinforcement to initial coat, e.g.

1No. Coat of LPL bonding primer then2No. Coats of LPL Decothane.

Obtainable from Liquid Plastics Tel. 01772 259 781 or Equal System

All finishes are to be in accordance with the manufacturers recommendations.

Where permanent structural metal soffit shutters are used as part of a composite roof systemthese shall be corrosion resistant and the Constructor's proposals for screening or tagging forearthing purposes shall be expressly agreed with SPEN prior to construction.

VentilationVentilation shown is typical for a single 500kVA transformer substation.The typical ventilation indicated may not be adequate in certain supply conditions which mightrequire additional or alternative ventilation arrangements.

Related Typical Deemed to Satisfy DrawingsHardwood Doors SP4000543Meter Cupboards SP4078901Vent for Brickbuilt substation SP4000542

Page 9: GENERAL SPECIFICATION FOR THE CIVIL SUB-03-017 … · The guidance drawings listed below are typical layout and construction details deemed to satisfy SPEN’s ... This drawing is

150

910 X 2185 HIGH

440

267

267

215

215

2785

900

1050 500 500

150

3620

4378

379379

4378

1050 500 500

1135

2485

1750675

600

100

500 500

4578

4378

3620379

100

379

100

3028

4578

100

4378

1135

2270

215

100

1185

1340

665

1585 x 2485 HIGH

890

250

400

750

225

225

750

3620

379

379

3600

4050

614

1083

450

2185

1135

2485

665

1400

450

NOTES

cScale

A1Size

Status

Location

Drawn

Drg. No.

CheckedDate Date

Rev.

DateApproved

Location

Title

SP PowerSystems LtdSystem Design, Drawing Office3 Prenton Way , Prenton , CH43 3ET

Drawn

Checked

Approved

Rev. Date

Telephone 0151 6092491

ISSUED SP40088701:50

TYPICAL

M.T. DEC.06 C.W. DEC.06 A.J.R. DEC.06

TYPICAL TRADITIONAL BUILDING DETAILS FOR11kV BRICKBUILT SUBSTATION

(3 PANEL BOARD WITH METERING)

C.B.27/11/17

G.R.G.R.

GENERAL UPDATES TO REFLECT CHANGES TOCIVILS POLICY DOCUMENT

GeneralThis drawing is to be read in conjunction with document SUB-03-017 General Specification for the CivilEngineering and Building Design and Construction of Secondary Substations. It is the constructor'sresponsibility to confirm, before construction, that the details on this drawing are correct as perSUB-03-017.

This is a generic guidance drawing that is deemed suitable for construction. However the constructorshould consider all site specific risk that will affect the design and operation of the substation.Proposed substation details are to be submitted for acceptance before installation.

Details shown on this drawing are typical for this type of substation building but may not be suitablefor substations housing alternative equipment. The constructor shall satisfy themselves that theappropriate details shown are correct depending on the type of substation being constructed.

ConcreteGeneralThe concrete shall be in accordance with the specification and attain the relevant cub crushingstrength at 28 days.

Foundations (Concrete 40N/mm² 28-Day Cube Strength)Foundations are to be set on undisturbed inorganic strata that provide the required minimum designsafe ground bearing capacity. Minimum bearing capacity to be 75kN/m².

Floor (Concrete 40N/mm² 28-Day Cube Strength)Floors of substations housing indoor switchgear shall have a visqueen damp proof membrane installedwhere graded stone infill is used.A flat, level and smooth floor surface is essential for installation of plant. Tolerances to finished levelexpressed as a maximum permissible deviation beneath a straight edge with feet placed anywhere onthe floor shall not exceed 1mm in 1m or 3mm in 3m. Floors to be cured, prepared & painted with 2No. Coats of non-slip floor paint on completion.

BrickworkGeneralAll brickwork below D.P.C. to be H.D. category 1 min. 75N/mm² mean compressive strength and max7% M.A. and durability designation F2 S2 (Ex Engineering Brickwork Class B) in English bond except forexposed faces.External facing brickwork to be H.D. category 1 min. 30N/mm² mean compressive strength and max12% M.A. and durability designation F1 S1 or better.Internal facing brickwork to fair faced smooth textured solid concrete bricks, sized to match externalfacing bricks and with a mean compressive strength of not less than 20N/mm².Class iii mortar.

WallsExternal walls to enclosures housing Indoor Equipment shall be cavity construction that provides, as aminimum, standard thermal insulation values in accordance with the table below. The internal leafshall be solid brickwork construction minimum 215mm overall thickness. Walls shall be fair-facedplumb and smooth to the interior.Leaves of walls to be tied together by means of type 1 or type 2 stainless steel ties laid in every fourthcourse at 375mm centres and set back 38mm from outer face, ties are to be staggered.

DoorsDetails of proposed doors shall be submitted to SPEN for comment, before work commences.Proprietary GRP faced aluminium or steel security doors are the preferred option, unless statedotherwise.An alternative option for hardwood doors (see Drg SP4000543 for details) or GRP doors is alsoavailable.

Cable Trench & Slots/RampOn completion of cabling, cable trench to be filled with dry sand and skimmed with minimum 50mmdepth of sand/cement screed over a visqueen membrane (top to be level with FFL).

RoofRoofs shall provide a minimum standard thermal insulation values as detailed in the table below.

Roof shall be proprietary precast pre-stressed beam and in situ concrete screed topping systems witha fair-faced soffit finish, sealed joints and with reinforcement to screed where applicable with waterproofing as shown in the Typical Detail above.

VentilationNominal trickle ventilation is to be provided to reduce the risk of condensation.

InsulationSubstations housing indoor switchgear require insulation. U values for wall and roof shall meet thosedetailed in the table below:

Related Typical Deemed to Satisfy DrawingsHardwood Doors SP4000543Meter Cupboards SP4078901

SCOTLAND

REGION

ENGLAND & WALES

0.2

ROOF

0.25

U (W/m2k)WALLS

U (W/m2k)

0.27

0.35

Page 10: GENERAL SPECIFICATION FOR THE CIVIL SUB-03-017 … · The guidance drawings listed below are typical layout and construction details deemed to satisfy SPEN’s ... This drawing is

cScale

A2Size

Status

Location

Drawn

Title

Drg. No.

CheckedDate Date

Rev.

DateApproved

Drawn

CheckedApproved

Rev. Date

SP PowerSystems LtdSystem Design, Drawing Office, Gateway House,Old Hall Road, Bromborough, CH62 3NX.Telephone 0141 614 7143.

ISSUED SP4049060

TYPICAL TRADITIONAL BUILDING DETAILS FOR11kV BRICKBUILT SUBSTATION

('D' OR 'G' TYPE RMU WITH METERING)

1:50

11kV SUBSTATIONS

MT OCT 08 C.O.B OCT 08 C.W OCT 08

C.B.27/11/17

G.R.G.R.

GENERAL UPDATES TO REFLECT CHANGES TOCIVILS POLICY DOCUMENT

GeneralThis drawing is to be read in conjunction with document SUB-03-017General Specification for the Civil Engineering and Building Design andConstruction of Secondary Substations. It is the constructor'sresponsibility to confirm, before construction, that the details on thisdrawing are correct as per SUB-03-017.

This is a generic guidance drawing that is deemed suitable forconstruction. However the constructor should consider all site specificrisk that will affect the design and operation of the substation. Proposedsubstation details are to be submitted for acceptance before installation.

Details shown on this drawing are typical for this type of substationbuilding but may not be suitable for substations housing alternativeequipment. The constructor shall satisfy themselves that the appropriatedetails shown are correct depending on the type of substation beingconstructed.

ConcreteGeneralThe concrete shall be in accordance with the specification and attain therelevant cub crushing strength at 28 days.

Foundations (Concrete 40N/mm² 28-Day Cube Strength)Foundations are to be set on undisturbed inorganic strata that providethe required minimum design safe ground bearing capacity. Minimumbearing capacity to be 75kN/m².

Floor (Concrete 40N/mm² 28-Day Cube Strength)Floors of substations housing indoor switchgear shall have a visqueendamp proof membrane installed where graded stone infill is used.A flat, level and smooth floor surface is essential for installation of plant.Tolerances to finished level expressed as a maximum permissibledeviation beneath a straight edge with feet placed anywhere on the floorshall not exceed 1mm in 1m or 3mm in 3m. Floors to be cured, prepared& painted with 2 No. Coats of non-slip floor paint on completion.

BrickworkGeneralAll brickwork below D.P.C. to be H.D. category 1 min. 75N/mm² meancompressive strength and max 7% M.A. and durability designation F2 S2(Ex Engineering Brickwork Class B) in English bond except for exposedfaces.External facing brickwork to be H.D. category 1 min. 30N/mm² meancompressive strength and max 12% M.A. and durability designation F1 S1or better.Internal facing brickwork to fair faced smooth textured solid concretebricks, sized to match external facing bricks and with a mean compressivestrength of not less than 20N/mm².Class iii mortar.

WallsExternal walls to enclosures housing Indoor Equipment shall be cavityconstruction that provides, as a minimum, standard thermal insulationvalues in accordance with the table below. The internal leaf shall be solidbrickwork construction minimum 215mm overall thickness. Walls shall befair-faced plumb and smooth to the interior.Leaves of walls to be tied together by means of type 1 or type 2 stainlesssteel ties laid in every fourth course at 375mm centres and set back38mm from outer face, ties are to be staggered.

DoorsDetails of proposed doors shall be submitted to SPEN for comment,before work commences.Proprietary GRP faced aluminium or steel security doors are the preferredoption, unless stated otherwise.An alternative option for hardwood doors (see Drg SP4000543 for details)or GRP doors is also available.

Cable Trench & Slots/RampOn completion of cabling, cable trench to be filled with dry sand andskimmed with minimum 50mm depth of sand/cement screed over avisqueen membrane (top to be level with FFL).

RoofRoofs shall provide a minimum standard thermal insulation values asdetailed in the table below.

Roof shall be proprietary precast pre-stressed beam and in situ concretescreed topping systems with a fair-faced soffit finish, sealed joints andwith reinforcement to screed where applicable with water proofing shallbe that as shown in the Typical Detail above.

VentilationNominal trickle ventilation is to be provided to reduce the risk ofcondensation.

InsulationSubstations housing indoor switchgear require insulation. U values forwall and roof shall meet those detailed in the table below:

Related Typical Deemed to Satisfy DrawingsHardwood Doors SP4000543Meter Cupboards SP4078901

SCOTLAND

REGION

ENGLAND & WALES

0.2

ROOF

0.25

U (W/m2k)WALLS

U (W/m2k)

0.27

0.35

Page 11: GENERAL SPECIFICATION FOR THE CIVIL SUB-03-017 … · The guidance drawings listed below are typical layout and construction details deemed to satisfy SPEN’s ... This drawing is

cScale

A1Size

Status

Location

Drawn

Drg. No.

CheckedDate Date

Rev.

DateApproved

Location

Title

SP PowerSystems LtdSystem Design, Drawing Office3 Prenton Way , Prenton , CH43 3ET

Drawn

Checked

Approved

Rev. Date

Telephone 0151 6092491

ISSUED SP40533891:50

STANDARDS

M.T. JAN.09 A.J.R. JAN.09 C.W JAN.09

TYPICAL TRADITIONAL BUILDING DETAILS FOR11kV BRICK BUILT SUBSTATION

(DOUBLE SIDE BY SIDE)

C.B.27/11/17

G.R.G.R.

GENERAL UPDATES TO REFLECT CHANGES TOCIVILS POLICY DOCUMENT

NOTES

GeneralThis drawing is to be read in conjunction with document SUB-03-017 General Specification for theCivil Engineering and Building Design and Construction of Secondary Substations. It is theconstructor's responsibility to confirm, before construction, that the details on this drawing arecorrect as per SUB-03-017.

This is a generic guidance drawing that is deemed suitable for construction. However theconstructor should consider all site specific risk that will affect the design and operation of thesubstation. Proposed substation details are to be submitted for acceptance before installation.

Details shown on this drawing are typical for this type of substation building but may not besuitable for substations housing alternative equipment. The constructor shall satisfy themselvesthat the appropriate details shown are correct depending on the type of substation beingconstructed.

ConcreteGeneralThe concrete shall be in accordance with the specification and attain the relevant cub crushingstrength at 28 days.

Foundations (Concrete 40N/mm² 28-Day Cube Strength)Foundations are to be set on undisturbed inorganic strata that provide the required minimumdesign safe ground bearing capacity. Minimum bearing capacity to be 75kN/m².

Floor (Concrete 40N/mm² 28-Day Cube Strength)Floors of substations housing indoor switchgear shall have a visqueen damp proof membraneinstalled where graded stone infill is used.A flat, level and smooth floor surface is essential for installation of plant. Tolerances to finished levelexpressed as a maximum permissible deviation beneath a straight edge with feet placed anywhereon the floor shall not exceed 1mm in 1m or 3mm in 3m. Floors to be cured, prepared & paintedwith 2 No. Coats of non-slip floor paint on completion.

BrickworkGeneralAll brickwork below D.P.C. to be H.D. category 1 min. 75N/mm² mean compressive strength andmax 7% M.A. and durability designation F2 S2 (Ex Engineering Brickwork Class B) in English bondexcept for exposed faces.External facing brickwork to be H.D. category 1 min. 30N/mm² mean compressive strength and max12% M.A. and durability designation F1 S1 or better.Internal facing brickwork to fair faced smooth textured solid concrete bricks, sized to matchexternal facing bricks and with a mean compressive strength of not less than 20N/mm².Class iii mortar.

WallsWalls shall be 215mm English garden wall bond or Collar jointed stretcher bond.Leaves of collar jointed double stretcher walls to be tied together by means of type 1 or type 2stainless steel ties laid in every fourth course at 375mm centres and set back 38mm from outerface, ties are to be staggered.

SHS windposts shall be installed on the front and rear wall panels.

DoorsDetails of proposed doors shall be submitted to SPEN for comment, before work commences.Proprietary GRP faced aluminium or steel security doors are the preferred option, unless statedotherwise.An alternative option for hardwood doors (see Drg SP4000543 for details) or GRP doors is alsoavailable.

Cable Trench & Slots/RampOn completion of cabling, cable trench to be filled with dry sand and skimmed with minimum 50mmdepth of sand/cement screed over a visqueen membrane (top to be level with FFL).

RoofStandard Concrete Roofs (Concrete 40N/mm² 28-Day Cube Strength)Wherever practicable, roofs should be cast in situ reinforced concrete construction with a soffitfinish. Slip joints shall be incorporated at wall bearings, polysulphide sealed externally. Internal /External faces of concrete to be fair faced. All external faces to be cured, prepared, primed andfinished with a two coat high performance (Aliphatic) polyurethane waterproofing system (flat roofgrade) with glass fibre mat reinforcement to initial coat, e.g.

1No. Coat of LPL bonding primer then2No. Coats of LPL Decothane.

Obtainable from Liquid Plastics Tel. 01772 259 781 or Equal System

All finishes are to be in accordance with the manufacturers recommendations.

Where permanent structural metal soffit shutters are used as part of a composite roof system theseshall be corrosion resistant and the Constructor's proposals for screening or tagging for earthingpurposes shall be expressly agreed with SPEN prior to construction.

VentilationVentilation shown is typical for a double 500kVA transformer substation.Ventilation unit opening sizes for 1000kVA transformers shall be a minimum 1002 x 450mm. Thetypical ventilation indicated may not be adequate in certain supply conditions which might requireadditional or alternative ventilation arrangements.

SteelworkAll steelwork is to be hot dipped galvanised in accordance with the specification and shall providefixings for earthing.

Related Typical Deemed to Satisfy DrawingsHardwood Doors SP4000543Meter Cupboards SP4078901Vent for Brickbuilt substation SP4000542

Page 12: GENERAL SPECIFICATION FOR THE CIVIL SUB-03-017 … · The guidance drawings listed below are typical layout and construction details deemed to satisfy SPEN’s ... This drawing is

cScale

A1Size

Status

Location

Drawn

Drg. No.

CheckedDate Date

Rev.

DateApproved

Location

Title

SP PowerSystems LtdSystem Design, Drawing Office3 Prenton Way , Prenton , CH43 3ET

Drawn

Checked

Approved

Rev. Date

Telephone 0151 6092491

ISSUED SP4058664AS SHOWN

STANDARDS

M.T. MARCH 09 C.W. MARCH 09 A.J.R. MARCH 09

TYPICAL TRADITIONAL BUILDING DETAILS FOR11kV BRICK BUILT SUBSTATION

(DOUBLE SQUARE TYPE)

C.B.27/11/17

G.R.G.R.

GENERAL UPDATES TO REFLECT DETAILS TOCIVILS POLICY DOCUMENT

NOTES

GeneralThis drawing is to be read in conjunction with document SUB-03-017 General Specification for theCivil Engineering and Building Design and Construction of Secondary Substations. It is theconstructor's responsibility to confirm, before construction, that the details on this drawing arecorrect as per SUB-03-017.

This is a generic guidance drawing that is deemed suitable for construction. However theconstructor should consider all site specific risk that will affect the design and operation of thesubstation. Proposed substation details are to be submitted for acceptance before installation.

Details shown on this drawing are typical for this type of substation building but may not besuitable for substations housing alternative equipment. The constructor shall satisfy themselvesthat the appropriate details shown are correct depending on the type of substation beingconstructed.

ConcreteGeneralThe concrete shall be in accordance with the specification and attain the relevant cub crushingstrength at 28 days.

Foundations (Concrete 40N/mm² 28-Day Cube Strength)Foundations are to be set on undisturbed inorganic strata that provide the required minimumdesign safe ground bearing capacity. Minimum bearing capacity to be 75kN/m².

Floor (Concrete 40N/mm² 28-Day Cube Strength)Floors of substations housing indoor switchgear shall have a visqueen damp proof membraneinstalled where graded stone infill is used.A flat, level and smooth floor surface is essential for installation of plant. Tolerances to finishedlevel expressed as a maximum permissible deviation beneath a straight edge with feet placedanywhere on the floor shall not exceed 1mm in 1m or 3mm in 3m. Floors to be cured, prepared &painted with 2 No. Coats of non-slip floor paint on completion.

BrickworkGeneralAll brickwork below D.P.C. to be H.D. category 1 min. 75N/mm² mean compressive strength andmax 7% M.A. and durability designation F2 S2 (Ex Engineering Brickwork Class B) in English bondexcept for exposed faces.External facing brickwork to be H.D. category 1 min. 30N/mm² mean compressive strength andmax 12% M.A. and durability designation F1 S1 or better.Internal facing brickwork to fair faced smooth textured solid concrete bricks, sized to matchexternal facing bricks and with a mean compressive strength of not less than 20N/mm².Class iii mortar.

WallsWalls shall be 215mm English garden wall bond or Collar jointed stretcher bond.Leaves of collar jointed double stretcher walls to be tied together by means of type 1 or type 2stainless steel ties laid in every fourth course at 375mm centres and set back 38mm from outerface, ties are to be staggered.

SHS windposts shall be installed on the front and rear wall panels.

DoorsDetails of proposed doors shall be submitted to SPEN for comment, before work commences.Proprietary GRP faced aluminium or steel security doors are the preferred option, unless statedotherwise.An alternative option for hardwood doors (see Drg SP4000543 for details) or GRP doors is alsoavailable.

Cable Trench & Slots/RampOn completion of cabling, cable trench to be filled with dry sand and skimmed with minimum50mm depth of sand/cement screed over a visqueen membrane (top to be level with FFL).

RoofStandard Concrete Roofs (Concrete 40N/mm² 28-Day Cube Strength)Wherever practicable, roofs should be cast in situ reinforced concrete construction with a soffitfinish. Slip joints shall be incorporated at wall bearings, polysulphide sealed externally. Internal /External faces of concrete to be fair faced. All external faces to be cured, prepared, primed andfinished with a two coat high performance (Aliphatic) polyurethane waterproofing system (flatroof grade) with glass fibre mat reinforcement to initial coat, e.g.

1No. Coat of LPL bonding primer then2No. Coats of LPL Decothane.

Obtainable from Liquid Plastics Tel. 01772 259 781 or Equal System

All finishes are to be in accordance with the manufacturers recommendations.

Where permanent structural metal soffit shutters are used as part of a composite roof systemthese shall be corrosion resistant and the Constructor's proposals for screening or tagging forearthing purposes shall be expressly agreed with SPEN prior to construction.

VentilationVentilation shown is typical for a double 500kVA transformer substation.The typical ventilation indicated may not be adequate in certain supply conditions which mightrequire additional or alternative ventilation arrangements.

SteelworkAll steelwork is to be hot dipped galvanised in accordance with the specification and shall providefixings for earthing.

Related Typical Deemed to Satisfy DrawingsHardwood Doors SP4000543Meter Cupboards SP4078901Vent for Brickbuilt substation SP4000542

Page 13: GENERAL SPECIFICATION FOR THE CIVIL SUB-03-017 … · The guidance drawings listed below are typical layout and construction details deemed to satisfy SPEN’s ... This drawing is
Page 14: GENERAL SPECIFICATION FOR THE CIVIL SUB-03-017 … · The guidance drawings listed below are typical layout and construction details deemed to satisfy SPEN’s ... This drawing is

Blinding Concrete

50mm

G.L.

Switchgear Leg

(Typical)

RLK-L-10100

M10x100 Sleeve Anchor Rawplug

Top flange and support to be drilled

on site to take fixing for switchgear

Packer

RMU STEEL SUPPORT DETAIL

Scale 1:20

REAR ELEVATIONFRONT ELEVATION

SECTION A-A

to top, on Visqueen or similar

(anti-crack) fabric with 20mm cover

concrete reinforced with A142

Floor slab to be min. 150mm thk.

NOTE

It is essential that EnergyNetworks

personnel can access

& properly secure on egress

Facing brick to finish

DETAIL AT DOORWAY

suit door spec.

Threshold detail to

F.F.L.

1 course below G.L.

G.L.

approved dpm, on sand blinding

metal lintel

Proprietary corrosion resistant

50

15

0

(or similar approved)

with 2 layers of Visqueen

level and smooth, topped

10mm Thk. cured bed joint,

Scale 1:10

15

0

10

0

5490 Conc.Roof

10

0

ROOF SECTION

ROOF PLAN

FOUNDATION SECTION

PLAN OF BRICKWORK BELOW FLOOR SLAB

Concrete slab, reinforced with

min. A252 fabric with 40mm cover

to sides, top and bottom.

Laps to be min. 400mm

FallFall

all doors at all times. Any

hardwood, metalwork or GRP

construction doors that may

shrink, warp, wind, distort,

corrode or bind will not be

acceptable

L.H. leaf to open first

Min

.

Min

.

Min

.

(min. 150mm end bearing)

laps to be 400mm

20mm cover to bottom,

with 75mm cover to sides and

Roof reinft. min. A393 mesh

D.Tp. Type 1 graded

stone (class 'A') infill,

75mm to dust, or

weak-mix mass concrete infill

with suitable polysulphide

Rake out and point

movement joint sealant

Drip

where graded stone infill is used

Additional foundation and/or

ground improvement works

to constructors design to

suit site-specific conditions

brickwork below D.P.C.

215mm Engineering

F.F.L.

G.L.

conduits (1 on 2)

vitreous clay

plain ended

3No. 150mm i/d

250

F.F.L.

A

B

G.L.

D.P.C.

SECTION B-B

910

1892

12

50

46

0

Galvanised

steel ventilators

F.F.L.

G.L.

21

85

24

10

150

67

5

82

5

250

225

conduits

vitreous clay

plain ended

3No. 150mm i/d

See doorway detail

R.C. lintels over

ventilator openings

(see vent detail drg.)

5490 Found. slab

5390 Brickwork

conduit (600 rad.)

vitreous clay

plain ended

1No. 150mm i/d

Double doors

(see doors detail drg.)

customer design

Sw.room to

cu

sto

me

r d

esig

n

Sw

.ro

om

to

552

89

0

1340

A

215

4960

215

B

42

35

46

65

1003 4405721115 2260

5390

A

(or similar approved)

with 2 layers of Visqueen

PLAN

Cable slot

767 910

1677

46

01

46

5

Cable slot

450 5221851

800

347

65

05

40

25

0

14

78

915

32

3

1230

880

800

450

10

80

65

0

68

0

250

11

03

22

93

129

307

PLANT LAYOUT

45

0

450

'G' Type

Sw.gear

Unit T/X

Sw.gear

(1000kVA)

(Schneider)

Consumer

unit

Socket

Thermostatic

controlled heater

Unswitched

spur box

for B.S.U.

Ba

tte

ry

pa

ne

l

Electrical installation to comply with

SPEN document SUB-03-029

450

Light

switch

150

45

0

45

0

75

conduit (600 rad.)

vitreous clay

plain ended

2No. 150mm i/d

Socket

See RMU Steel Support Detail

cScale

A2Size

Status

Location

Drawn

Title

Drg. No.

CheckedDate Date

Rev.

DateApproved

Drawn

CheckedApproved

Rev. Date

SP PowerSystems LtdSystem Design, Drawing Office, Gateway House,Old Hall Road, Bromborough, CH62 3NX.Telephone 0141 614 7143.

ISSUED SP4105959

TYPICAL TRADITIONAL BUILDING DETAIL FOR11kV BRICK BUILT SUBSTATION

(LV GENERATION)

1:50

11kV SUBSTATIONS

M.T. SEPT. 13 S.H. OCT.13 A.J.R. OCT.13

C.B.27/11/17

G.R.G.R.

TO SWITCHGEAR ARRANGEMENT

GENERAL UPDATES TO REFLECT CHANGES TOCIVIL POLICY DOCUMENTS AND AMENDMENTS

NOTES

GeneralThis drawing is to be read in conjunction with document SUB-03-017 General Specificationfor the Civil Engineering and Building Design and Construction of Secondary Substations. Itis the constructor's responsibility to confirm, before construction, that the details on thisdrawing are correct as per SUB-03-017.

This is a generic guidance drawing that is deemed suitable for construction. However theconstructor should consider all site specific risk that will affect the design and operation ofthe substation. Proposed substation details are to be submitted for acceptance beforeinstallation.

Details shown on this drawing are typical for this type of substation building but may not besuitable for substations housing alternative equipment. The constructor shall satisfythemselves that the appropriate details shown are correct depending on the type ofsubstation being constructed.

ConcreteGeneralThe concrete shall be in accordance with the specification and attain the relevant cubcrushing strength at 28 days.

Foundations (Concrete 40N/mm² 28-Day Cube Strength)Foundations are to be set on undisturbed inorganic strata that provide the requiredminimum design safe ground bearing capacity. Minimum bearing capacity to be 75kN/m².

Floor (Concrete 40N/mm² 28-Day Cube Strength)A flat, level and smooth floor surface is essential for installation of plant. Tolerances tofinished level expressed as a maximum permissible deviation beneath a straight edge withfeet placed anywhere on the floor shall not exceed 1mm in 1m or 3mm in 3m. Floors to becured, prepared & painted with 2 No. Coats of non-slip floor paint on completion.

BrickworkGeneralAll brickwork below D.P.C. to be H.D. category 1 min. 75N/mm² mean compressive strengthand max 7% M.A. and durability designation F2 S2 (Ex Engineering Brickwork Class B) inEnglish bond except for exposed faces.External facing brickwork to be H.D. category 1 min. 30N/mm² mean compressive strengthand max 12% M.A. and durability designation F1 S1 or better.Internal facing brickwork to fair faced smooth textured solid concrete bricks, sized to matchexternal facing bricks and with a mean compressive strength of not less than 20N/mm².Class iii mortar.

WallsWalls shall be 215mm English garden wall bond or Collar jointed stretcher bond.Leaves of collar jointed double stretcher walls to be tied together by means of type 1 ortype 2 stainless steel ties laid in every fourth course at 375mm centres and set back 38mmfrom outer face, ties are to be staggered.

DoorsDetails of proposed doors shall be submitted to SPEN for comment, before workcommences.Proprietary GRP faced aluminium or steel security doors are the preferred option, unlessstated otherwise.An alternative option for hardwood doors (see Drg SP4000543 for details) or GRP doors isalso available.

Cable Trench & SlotsOn completion of cabling, cable trench and slots to be filled with dry sand topped with aminimum 150mm depth of rounded gravel chippings (top to be level with FFL).

RoofStandard Concrete Roofs (Concrete 40N/mm² 28-Day Cube Strength)Wherever practicable, roofs should be cast in situ reinforced concrete construction with asoffit finish. Slip joints shall be incorporated at wall bearings, polysulphide sealed externally.Internal / External faces of concrete to be fair faced. All external faces to be cured,prepared, primed and finished with a two coat high performance (Aliphatic) polyurethanewaterproofing system (flat roof grade) with glass fibre mat reinforcement to initial coat, e.g.

1No. Coat of LPL bonding primer then2No. Coats of LPL Decothane.

Obtainable from Liquid Plastics Tel. 01772 259 781 or Equal System

All finishes are to be in accordance with the manufacturers recommendations.

Where permanent structural metal soffit shutters are used as part of a composite roofsystem these shall be corrosion resistant and the Constructor's proposals for screening ortagging for earthing purposes shall be expressly agreed with SPEN prior to construction.

VentilationVentilation shown is typical for a single 500kVA transformer substation.Ventilation unit opening sizes for 1000kVA transformers shall be a minimum 1002 x 450mm.The typical ventilation indicated may not be adequate in certain supply conditions whichmight require additional or alternative ventilation arrangements.

Related Typical Deemed to Satisfy DrawingsHardwood Doors SP4000543Meter Cupboards SP4078901Vent for Brickbuilt substation SP4000542

Page 15: GENERAL SPECIFICATION FOR THE CIVIL SUB-03-017 … · The guidance drawings listed below are typical layout and construction details deemed to satisfy SPEN’s ... This drawing is

'X' 'Y'

2486 (CABLE TRENCH)

'Y' 'X'

!

PLANT LAYOUT PLAN

FRONT ELEVATION

SECTION C - C

METRE OR GREATER FROM BOUNDARY

ERECTED AT A DISTANCE OF ONE

ENCLOSURE ONLY SUITABLE WHEN

WARNING/INFORMATION NOTICESDANGER SIGN, CONTACT NUMBERAND SF6 EQUIPMENT WITHIN

TYPICAL HOLDING DOWN DETAIL SECTION

ANTI VERMIN MESHFITTED INTERNALLY WITH S.S.

REAR ELEVATION

BOTTOM (AT FRONT) OF UNIT.EACH TO BE 150 x 100mm Min.

LOUVER

GROUND LEVEL

S.W. GEAR SECTION E - E

ABOVE FINISHEDSLAB TO BE 150mm

FOR DIAGRAMATIC

TOP OF FOUNDATION

PURPOSES ONLY

S.W. GEAR SHOWN

OF PLINTH

SIDE ELEVATION

ISOMETRIC VIEW

DOOR HEIGHT

ROOF TO BE FITTED WITH MANUFACTURERSEXPLOSION RELIEF MECHANISM

FABRICA142 REINFORCEMENT

PLINTH PLAN

SECTION A - A

25mm PERIMETER CHAMFER

ADDITIONAL FOUNDATION AND/ORGROUND IMPROVEMENT WORKSTO CONSTRUCTOR'S DESIGNTO SUIT SITE-SPECIFIC CONDITIONS

100

2486

50mm COVER TO

C

BCABLE TRENCH

C910

1923

1013

235 235

500

CHAMFERS25mm

CABLE TRENCH

CABL

E SL

OT

CABL

E SL

OT

CONDUITS

PLAIN ENDED3No. 150mm I/D

VITREOUS CLAY

CABLE ENTRY

CABL

E SL

OT

CABL

E SL

OT

ENTRYCABLE

225

450 67

5EQUI-SPACED, 50mmCOVER TO BOTTOM & SIDES

3 No T10 BARS 2800 LONG

A

A B

SECTION B - B

LOUVER

LOUVERLOUVER

E

E

PANEL

BATTERY PANEL- FOR 'G' TYPE

METER

RCD SOCKET

6 WAY

SPUR BOX

THERMOSTATICCONTROLLED HEATER

'G' TYPE

LIGHT SWITCH

SOCKET

SOCKET

UNSWITCHEDSPUR BOXFOR B.S.U.

SPUR BOXFOR HEATER

UNITCONSUMER

FOR HEATER

PROTECTIONPANEL

F.F.L.

G.L.

G.L.

G.L. G.L.G.L.

F.F.L.

LOUVERS TO BE PROVIDEDTOP (AT REAR) AND

F.F.L.G.L.

1501013

500

1923300

235235

FABRICA142 REINFORCEMENT

50mm BLINDING CONCRETE

THE REQUIRED INTERNAL FIXINGS FOR MANUFACTURERS ARE TO INCLUDE

DESIGN (SEE PLANT LAYOUT PLAN)

FABRIC

METALWORK FRAME BUILT FLOOR TO CEILING IN A BOX SECTION TO SUPPORT LOAD

REINFORCEMENT

(SCALE 1:5)

EQUI-SPACED,

BOTTOM & SIDES

3 No T10 BARS

(SEE PLANT LAYOUT PLAN)

2800 LONG

CURRENT BUILDING REGULATION STANDARDS 'U' VALUES OF ROOF AND WALLS TO BE TO

25

CHAMFER25mm

C

SECTION D -D

CABLE TRENCH

CABLE SLOT

G.L.F.F.L.

ABUS

DD

850

650CONDUITS

PLAIN ENDED3No. 150mm I/D

SECTION X-X (SCALE 1:5)

VITREOUS CLAY (450mm RADIUS)1No. 100mm DIA

CLAY CONDUIT

650

F.F.L.

1260

(INT

.)

600 (INT.)

1585(Min.) DOUBLE DOORS ==

PANELMETER

DOOR

2235

(Min

.)

F.F.L.F.F.L.

R450

SW. GEAR

REFER TO DRG. SP4090884FOR CABLE DUCT DETAILSIN METER CUPBOARD

MANUFACTURERS TO PROVIDE THE FINISH/COLOUR OF GRP UNIT TOREQUIRED GRP UNIT DESIGN

75

CUSTOMERS REQUIREMENTS

F.F.L.

50

DIMENSION TO SUIT GRP DESIGN (300mm Min.)

25

100

Y

G.L.

2500

(Min

.)

2235

(Min

.)

100

LOCK

910450

150

F.F.L.

C

25

CEILINGLIGHT

L

CEILINGLIGHT

CLA142

300 (Min.)

300

(Min

.)

100

150

CL

50100

825

2235

(Min

.)

775

825

675

GRP ENCAPSULATED WOOD VERTICAL BATTENS

L

PLINTH EXTERNAL DIMS. TO SUIT GRP UNIT DESIGN

3900 (Min. INTERNAL)

2900

(Min

. INT

ERNA

L)

PLIN

TH E

XTER

NAL

DIM

S. T

O SU

IT G

RP U

NIT

DESI

GN

BE SINGLE SKIN GRP/PLYWOOD/GRP WITHINTERNAL DIVISION WALL MAY ALTERNATIVELY

TO REAR

REQUIREMENTS ETC. IN THE GRP DESIGN. HEATERS/LIGHTS/SOCKETS ETC. CAN BEAND MANUFACTURERS ARE TO INCLUDE THE FIXING, REINFORCEMENT, 'U' VALUEALL ITEMS SHOWN BLUE ARE TO BE FITTED ON THE INTERNAL WALLS OF THE GRP

FIXED TO 18mm WEATHERPROOF PLYWOOD. BATTERY/METER PANELS TO HAVE A

CHANNEL NUT

1000

BACKING PLATE

CHANNELSKIN (INNER)

SKIN (OUTER)

SECTION Y-Y

WALL MOUNTED ITEMS IN THE GRP

(MAX 100kg)

(MAX 30kg)

CONSTRUCTION DETAILSSTANDARD GRP UNIT

(SCALE 1:5)

150

(SAFETY, SECURITY ETC.)

825

50

BUILDING REGULATION STANDARDS 'U' VALUES OF WALLS TO BE AS CURRENT

REQUIREMENT UP TO 100KG

TOP METALANGLE SUPPORT

ANGLE SUPPORTBOTTOM METAL

(BACKING PLATE)

SKIN (OUTER)

(BACKING PLATE)

x

CHANNEL

x

Y

Y

Y

STRUT

STRUT

STRUT

WEATHER BAR ATGALVANISED STEEL

BASE OF DOORS

1000

DOUBLE DOORS TO MEET

SKIN (INNER)

WITH F.F.L.)(TOP TO BE LEVEL SAND/CEMENT SCREEDAREAS FILLED WITH

(TOP TO BE LEVEL WITH F.F.L.) SAND/CEMENT SCREEDAREAS FILLED WITH

Rev Date Drawn Reviewed Approved Description of Change

1 17/12/2015 M.T. S.H. G.W. -

2 27/11/2017 CB GR GR GENERAL UPDATES TO REFLECT CHANGES TO CIVILS POLICY DOCUMENT

Size:

Drawn Rev'd App'd

Project:

Drg. No.: Rev:

All rights reserved. Total or partial reproduction of this drawing without authorisation of the proprietor is prohibited.

Scale:

Drg. Title:

Sheet:

Next:

Location:

Drawing State:

Approval Status:

43 5 6 7 8 9 1021 11 12

43 5 6 7 8 9 1021 11 12

C

B

A

D

E

F

G

H

C

B

A

D

E

F

G

H

A2

Voltage:GUIDANCE DRAWING 11kV

TYPICAL TRADITIONAL BUILDING DETAILS FOR

11kV GRP PLINTH 'D' OR 'G' TYPE RMU

(INDOOR KIT)

1:50CB GR GR SP4132847

Approved

For Issue

2

THIS DRAWING TO BE READ IN CONJUCTION WITH

SUB-03-017 'GENERAL SPECIFICATION FOR THE

CIVIL ENGINEERING AND BUILDING DESIGN AND

CONSTRUCTION OF SECONDARY SUBSTATIONS'

NOTES

THIS DRAWING IS FOR GUIDANCE ONLY.

PROPOSED SUBSTATION DETAILS ARE TO BE

SUBMITTED FOR ACCEPTANCE BEFORE

INSTALLATION.