generation reliability calculation methodology

18
A Hydro-Québec Division November 18, 2 004 Generation Reliability Generation Reliability Calculation Methodology Calculation Methodology Presentation to the NEPOOL Power Supply Presentation to the NEPOOL Power Supply Planning Committee Planning Committee

Upload: lenci

Post on 15-Jan-2016

60 views

Category:

Documents


2 download

DESCRIPTION

Generation Reliability Calculation Methodology. Presentation to the NEPOOL Power Supply Planning Committee. Presentation. Introduction Actual tool FEP - Methodology New tool FEPMC - Methodology Input Comparison Output Comparison FEPMC – Advantages Simulations Next Steps. Introduction. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Generation Reliability Calculation Methodology

A Hydro-Québec Division

November 18, 2004

Generation Reliability Generation Reliability Calculation MethodologyCalculation Methodology

Presentation to the NEPOOL Power Supply Planning Presentation to the NEPOOL Power Supply Planning CommitteeCommittee

Page 2: Generation Reliability Calculation Methodology

November 18, 200422

PresentationPresentation

IntroductionIntroduction

Actual tool FEP - MethodologyActual tool FEP - Methodology

New tool FEPMC - MethodologyNew tool FEPMC - Methodology

Input ComparisonInput Comparison

Output ComparisonOutput Comparison

FEPMC – AdvantagesFEPMC – Advantages

SimulationsSimulations

Next StepsNext Steps

Page 3: Generation Reliability Calculation Methodology

November 18, 200433

IntroductionIntroduction

In 2003, Hydro-Québec started the In 2003, Hydro-Québec started the development of a new model to better assess development of a new model to better assess its resources adequacy its resources adequacy

IncentivesIncentives Better assessment of demand and supply side Better assessment of demand and supply side

benefits benefits Introduction of transmission constraints in Introduction of transmission constraints in

reliability assessments reliability assessments Elimination of manual data entry (risk of error)Elimination of manual data entry (risk of error) Improvement of user interfaceImprovement of user interface

Page 4: Generation Reliability Calculation Methodology

November 18, 200444

Actual tool FEP - MethodologyActual tool FEP - Methodology

DescriptionDescription The program convolves a monthly load duration The program convolves a monthly load duration

curve and a probability curve of forced outages curve and a probability curve of forced outages to calculate LOLEto calculate LOLE

Installed CapacityAvailable CapacityPlanned Outage

Load Duration Curve

Lk

Tk

Ok

Pk1

Outage causing a loss of load

MW

Page 5: Generation Reliability Calculation Methodology

November 18, 200455

Actual tool FEP - MethodologyActual tool FEP - Methodology

Load ModelLoad Model Monthly load duration curve with annual peak Monthly load duration curve with annual peak

load forced in Januaryload forced in January Load forecast uncertainty (LFU)Load forecast uncertainty (LFU)

Normal distribution where the standard deviation is a Normal distribution where the standard deviation is a percentage of the load forecastpercentage of the load forecast

Structural and climatic uncertaintiesStructural and climatic uncertainties

Capacity ModelCapacity Model Forced outages probability curve Forced outages probability curve

Cumulative probability curve for total forced outagesCumulative probability curve for total forced outages

Page 6: Generation Reliability Calculation Methodology

November 18, 200466

New tool FEPMC - MethodologyNew tool FEPMC - Methodology

DescriptionDescription The new program calculates the installed The new program calculates the installed

capacity margin for all 8760 hours and derives capacity margin for all 8760 hours and derives LOLE from the hours where available LOLE from the hours where available resources are lower than firm commitments resources are lower than firm commitments plus synchronous reserve (250 MW) plus synchronous reserve (250 MW)

Load ModelLoad Model 210 chronological zonal load profiles210 chronological zonal load profiles

Load forecast applied to last 30 years weather Load forecast applied to last 30 years weather profiles profiles

Weather profile offsets of ± 3 daysWeather profile offsets of ± 3 days Structural uncertainty normally distributedStructural uncertainty normally distributed

Page 7: Generation Reliability Calculation Methodology

November 18, 200477

New tool FEPMC - MethodologyNew tool FEPMC - Methodology

Capacity ModelCapacity Model Forced outages generated using Monte-Carlo Forced outages generated using Monte-Carlo

statistical methodstatistical method Number and length of forced outages based on Number and length of forced outages based on

historical data for every unithistorical data for every unit

Tie benefitsTie benefits No tie benefits are taken into accountNo tie benefits are taken into account Only firm external sales and purchases are Only firm external sales and purchases are

consideredconsidered

ConvergenceConvergence Relatively high number of cycles required for Relatively high number of cycles required for

convergenceconvergence

Page 8: Generation Reliability Calculation Methodology

November 18, 200488

New tool FEPMC - MethodologyNew tool FEPMC - Methodology

Convergence Test - FEP MC

2,09

2,1

2,11

2,12

2,13

2,14

2,15

2,16

2,17

2,18

2,19

0 20000 40000 60000 80000 100000 120000

Number of years simulated

LO

LE

(h

ou

rs/y

ear)

Complete Execution Mid Execution Short Execution

Page 9: Generation Reliability Calculation Methodology

November 18, 200499

New tool FEPMC - MethodologyNew tool FEPMC - Methodology

Transmission System representationTransmission System representation DC load flow simulationDC load flow simulation

Page 10: Generation Reliability Calculation Methodology

November 18, 20041010

Input ComparisonInput Comparison

FEPFEP FEPMCFEPMC

Load ForecastLoad Forecast Load duration curvesLoad duration curves 210 chronological zonal load 210 chronological zonal load profilesprofiles

Forced OutagesForced Outages Probability curveProbability curve Randomly generated using Randomly generated using Monte Carlo's methodMonte Carlo's method

Planned OutagesPlanned Outages Monthly percentageMonthly percentage Unit specific maintenance Unit specific maintenance schedule (weekly basis)schedule (weekly basis)

Demand and Supply Side Demand and Supply Side Management ConstraintsManagement Constraints

Fixed deratings to account Fixed deratings to account for constraintsfor constraints

Number and duration of Number and duration of usage usage

Transmission ConstraintsTransmission Constraints Not taken into accountNot taken into account Weekly value per Weekly value per transmission pathtransmission path

Other constraintsOther constraints Not taken into accountNot taken into accountAbility to take into account Ability to take into account other constraints such as other constraints such as

ice cover formationice cover formation

Page 11: Generation Reliability Calculation Methodology

November 18, 20041111

Output ComparisonOutput Comparison

FEPFEP FEPMCFEPMC

LOLELOLE LOLELOLE

Installed reserve marginInstalled reserve margin Installed reserve marginInstalled reserve margin

Monthly capacity marginMonthly capacity margin Monthly capacity marginMonthly capacity margin

Statistics on use of demand and supply Statistics on use of demand and supply side management programsside management programs

Statistics on load shedding conditionsStatistics on load shedding conditions

Page 12: Generation Reliability Calculation Methodology

November 18, 20041212

FEPMC - AdvantagesFEPMC - Advantages

More realistic assessment of resources More realistic assessment of resources availabilityavailability

Representation of transmission constraints Representation of transmission constraints (congestion)(congestion)

Automatic data transferAutomatic data transfer

Evaluation of benefits of demand and supply Evaluation of benefits of demand and supply side management programsside management programs

Page 13: Generation Reliability Calculation Methodology

November 18, 20041313

Simulations - Simulations - IEEE Test GridIEEE Test Grid

Simplified network and loadSimplified network and load Fixed parameters (LFU, EFOR, Maintenance)Fixed parameters (LFU, EFOR, Maintenance)

FEP does not take into account the transfer of unused FEP does not take into account the transfer of unused volumes of energy from one month to the othervolumes of energy from one month to the other

SimulationSimulation FEPFEPLOLELOLE

FEPMCFEPMCLOLELOLE

IEEE Test Grid (without hydraulic IEEE Test Grid (without hydraulic constraints)constraints) 63,74 hrs63,74 hrs 59,60 hrs59,60 hrs

IEEE Test Grid (with hydraulic IEEE Test Grid (with hydraulic constraints)constraints) 98,24 hrs98,24 hrs 82,86 hrs82,86 hrs

Hydraulic constraints representationHydraulic constraints representation

(annual water inflow)(annual water inflow)Planned OutagePlanned Outage

Supply side Supply side Management Management

ProgramProgram

Page 14: Generation Reliability Calculation Methodology

November 18, 20041414

Simulations – Hydro-Québec GridSimulations – Hydro-Québec Grid

Simulation with a constrained version of FEPMC to Simulation with a constrained version of FEPMC to establish a base comparison with FEPestablish a base comparison with FEP Load duration curve built from chronological load Load duration curve built from chronological load

profilesprofiles Same load forecast uncertaintiesSame load forecast uncertainties Monthly planned outagesMonthly planned outages Fixed quantities for demand and supply side Fixed quantities for demand and supply side

managementmanagement Transmission constraints not taken into accountTransmission constraints not taken into account

The installed reserve margins obtained with FEP and The installed reserve margins obtained with FEP and FEPMC were within 5%FEPMC were within 5%

Page 15: Generation Reliability Calculation Methodology

November 18, 20041515

Simulations – Hydro-Québec GridSimulations – Hydro-Québec Grid

Simulation with the introduction of the 210 Simulation with the introduction of the 210 chronological zonal load shapes instead of chronological zonal load shapes instead of the load duration curve for FEPMCthe load duration curve for FEPMC

Results show the 210 load profiles are more Results show the 210 load profiles are more stringent than a normal distribution. stringent than a normal distribution.

Page 16: Generation Reliability Calculation Methodology

November 18, 20041616

Simulations – Hydro-Québec GridSimulations – Hydro-Québec Grid

Simulation with the introduction of all the Simulation with the introduction of all the other FEPMC features (except transmission other FEPMC features (except transmission constraints)constraints)

LOLE is slightly lowered for the following LOLE is slightly lowered for the following reasons:reasons:

By forcing the annual peak load in January, the By forcing the annual peak load in January, the FEP model artificially overestimates demandFEP model artificially overestimates demand

Better modeling of demand and production side Better modeling of demand and production side management programsmanagement programs

Page 17: Generation Reliability Calculation Methodology

November 18, 20041717

Next StepsNext Steps

Validation of the transmission modeling Validation of the transmission modeling impact on resource adequacyimpact on resource adequacy

Reduce calculation timeReduce calculation time

Page 18: Generation Reliability Calculation Methodology

November 18, 20041818

Hugo Sansoucy

[email protected]

Tél.: (514) 289-6873

Fax: (514) 289-6882