generator commissioning
TRANSCRIPT
-
7/31/2019 Generator Commissioning
1/90
Generator
Commissioning
- SUBODH KUMAR
-
7/31/2019 Generator Commissioning
2/90
GENERAL INSPECTION AND CHECKS
Ensure that erection work of the
Generator and associated equipments are
completed in all respect.
Check that no part of Generator, Exciter,
Bus-duct, CT, PT, Terminal Bushings,
Marshalling Boxes, equipment is damaged.
Ensure safe and satisfactory access to the
equipments.
-
7/31/2019 Generator Commissioning
3/90
Ensure fire protection system is
adequate.
Check that painting work is satisfactory.
Check that Name Plate Details areavailable, labeling and identification is
permanent and satisfactory.
Check that permanent and adequate
lighting arrangements are made.
-
7/31/2019 Generator Commissioning
4/90
Carefully examine the Generator Stator
core, winding, Rotor body, slip-ringsand all other associated equipment forany kind of abnormality, dents, or any
physical damage.
Ensure the quality certificate andfactory inspection and test reports areavailable.
-
7/31/2019 Generator Commissioning
5/90
Ensure that all the RTDs installed are
functioning properly.
-
7/31/2019 Generator Commissioning
6/90
TESTING OF GENERATOR
Laboratory tests and
Field tests to evaluate theinsulation condition of statorwindings of generator.
-
7/31/2019 Generator Commissioning
7/90
Laboratory tests
Laboratory tests have two functions:
The first function is to evaluate thequality of coil manufacturing to ensure
that your machine can achieveexpected service lifetime.
The second function is to examine
any faults and defects of your statorcoils to prevent catastrophic machinefailures.
-
7/31/2019 Generator Commissioning
8/90
Field tests
Field tests provide diagnostic tests andcondition assessment of machine
insulation at your plant to help you todetermine maintenance requirements toreduce maintenance cost.
-
7/31/2019 Generator Commissioning
9/90
Laboratory Diagnostic
Tests of Stator WindingInsulation
-
7/31/2019 Generator Commissioning
10/90
Laboratory tests include:
Voltage Endurance test Thermal Cycling Dissection of Coils
Insulation Failure Analysis Partial Discharge test Dissipation Factor Turn-to-Turn Multi-Factor Stress Forensic Analysis
-
7/31/2019 Generator Commissioning
11/90
voltage endurance test
A voltage endurance test is an acceleratedinsulation-aging test. The test is performedon stator bars or coils at much higher thannormal operation stress levels within a shortperiod of time to simulate insulation agingduring machine operation.
The test can predict the performance of theoverall insulation system and measure the
manufacturing quality. A number of diagnostic tests on stator
insulation can be conducted before and aftera voltage endurance test.
-
7/31/2019 Generator Commissioning
12/90
voltage endurance test Manufacturers of stator insulation could
change its design, type of materials, andthe manufacturing process.
The voltage endurance test can be done atthe prototype and production stage toensure the quality consistency duringmanufacturing. The test gives objectiveassessment of the quality of stator insulation.
If coils fail the test, a remedial action may betaken by the manufacturer to improve thequality of coil manufacturing.
-
7/31/2019 Generator Commissioning
13/90
voltage endurance test
Voltage endurance tests can be applied toboth new coils and spare coils to check
the quality and performance of theinsulation system. Spare coils have beenstored for a long period of time and need
to be tested to check their performance.
-
7/31/2019 Generator Commissioning
14/90
A set-up of the voltageendurance testing
-
7/31/2019 Generator Commissioning
15/90
Insulation failure during a voltageendurance test at 280 hours
-
7/31/2019 Generator Commissioning
16/90
Thermal Cycling Tests and
Multi-Factor Tests Large motors are exposed to
frequent start/stop operations.
Pumped-storage generators andhydro-generators have frequent loadchanges. All of those operations
cause rapid heating and cooling, i.e.thermal cycling effect on statorinsulation.
-
7/31/2019 Generator Commissioning
17/90
Thermal cycling cancause
1. Loss of bond between copper andinsulation;
2. De-lamination and degradation ofground-wall insulation;
3. Insulation failure.
-
7/31/2019 Generator Commissioning
18/90
A set-up of thermal cycling testing onstator windings
-
7/31/2019 Generator Commissioning
19/90
To assess the insulation performanceunder thermal cycling stress as themachine experiences in service, weperform thermal cycling tests on statorbars and coils according to IEEE
Standard 1310 -1996 and IECstandards.
The test insulation system is heatedand cooled at a prescribed rate for a
number of cycles (e.g. 500 cycles). Anumber of diagnostic tests on statorinsulation can be performed during
thermal cycling testing.
-
7/31/2019 Generator Commissioning
20/90
When a generator or motor is
operating, a stator bar or coil is subjectto electrical, mechanical, and thermalstresses simultaneously. Stator winding
have to test under multifactor(electrical, mechanical, and thermalstresses) stress aging simultaneously tosimulate normal service conditions orconditions as required.
-
7/31/2019 Generator Commissioning
21/90
Thermal cycling test result
-
7/31/2019 Generator Commissioning
22/90
Failure Analysis
When your stator coils or bars failed
in service, you want to know whatactually caused insulation failures toprevent future failures. You may need
expert witness to prove the causes ofinsulation failures.
-
7/31/2019 Generator Commissioning
23/90
Failure Analysis
Dissections of a bar or coil can determinethe quality of coil manufacturing and the
causes of insulation failures. The failedcoil or bar will be dissected and examinedunder a computer- controlled microscope.
The root causes of insulation failures areinvestigated
-
7/31/2019 Generator Commissioning
24/90
Failure Analysis
The following chemical tests on theinsulation system can be also conductedfor insulation failure analysis:
Resin content analysis;
Thermo-gravimetric analysis;
Thermo-mechanical analysis;
Fourier transform infraredspectroscopy
-
7/31/2019 Generator Commissioning
25/90
Insulation failure of a 13.8 kV, 44 MWhydro-generator
ac v y cause e a ove nsu a on
-
7/31/2019 Generator Commissioning
26/90
ac v y cause e a ove nsu a onfailure by dissection and microscopic
examination
P i l Di h
-
7/31/2019 Generator Commissioning
27/90
Partial DischargeMeasurements
Partial discharge (PD), corona inceptionmeasurements provide a non-intrusive indication ofthe void content and other problems, which may bepresent in a stator bar or a coil.
Partial discharge measurements can identify
insulation defects which could be caused byimproper impregnation, inadequate resin, voids,or poor consolidation of the insulation.
These measurements are normally undertaken at the
rated phase-to-ground voltage. PD specialists canassess insulation condition based on PD test data.
-
7/31/2019 Generator Commissioning
28/90
Generator insulation damage due topartial discharge activity
-
7/31/2019 Generator Commissioning
29/90
FIELD TEST
-
7/31/2019 Generator Commissioning
30/90
TEST PROCEDURE
1. Generator is disconnected from the
bus duct.2. Ground all the RTD wires coming
from the Generator.
3. Carry out the IR test on the Each
Phase to Ground separately.(note
Insulation Tester used and Ambient temp. in deg C.):
-
7/31/2019 Generator Commissioning
31/90
This test is performed injecting a stabilized high DCvoltage and measuring the current after 15seconds to calculate Insulation Resistance (IR).
We can perform this test between phases orbetween the 3 phases and the ground. IR highlydepends on temperature and must be corrected. Italso depends on the winding class and on thecuring state of the machine.
IR should be above a minimum value related withthe rated voltage of the generator.
The Polarization Index (PI) is the ratio between IRafter 10 and after 1. As a ratio, it is almost no
temperature dependant. The results indicateinsulation contamination, moisture, cracks orfissures in the insulation.
Standards indicate that this test should be carried
out before more aggressive tests like Hipot orSur e tests.
-
7/31/2019 Generator Commissioning
32/90
D.C. winding resistance:
Carry out the D.C. winding resistance
test of the Stator Winding (each
phase separately)
-
7/31/2019 Generator Commissioning
33/90
Winding Resistance (DC) [m]- The
test injects a current and measures theterminal voltage in eachphase. The resultis the pure resistance of each phase andmust be temperature corrected.
The resistance per phase should be verysimilar between them.
It gives an indication of the integrity ofthe windings and the connections,indicating shorted turns, looseconnections, wrong connections and open
circuits.
-
7/31/2019 Generator Commissioning
34/90
FEILD TEST INCLUDE:
Visual Inspection test Digital ELCID
PD Data Interpretation and Analysis
Corona Probe TEST Dissipation Factor (tan delta test)
AC and DC Hi-pot test
Wedge Tightness test Core repair, if loose
Insulation Condition Assessment
-
7/31/2019 Generator Commissioning
35/90
EL CID Test
Electromagnetic Core ImperfectionDetection (EL CID) is used to checkthe integrity of inter-laminar insulation
for stator cores of generators.A fault current occurring within the
laminated stator core results in a hot
spot and can cause a catastrophicfailure of a generator and motor inservice.
-
7/31/2019 Generator Commissioning
36/90
An EL CID test can
detect faults and defects in the statorcore;
check effectiveness of core repairs;test the stator core before and after astator rewind to check any damagescaused by rewind;
check the quality of a new statorcore;trend the stator core condition.
-
7/31/2019 Generator Commissioning
37/90
EL CID testing on 80 MW hydro-generator
-
7/31/2019 Generator Commissioning
38/90
EL CID testing on a Turbo-generator
-
7/31/2019 Generator Commissioning
39/90
-
7/31/2019 Generator Commissioning
40/90
-
7/31/2019 Generator Commissioning
41/90
-
7/31/2019 Generator Commissioning
42/90
-
7/31/2019 Generator Commissioning
43/90
-
7/31/2019 Generator Commissioning
44/90
-
7/31/2019 Generator Commissioning
45/90
ADVANTAGE OF ELCID TEST
In comparison with a traditional loop (ringflux) test, an EL CID test offers the followingbenefits:
Uses a portable excitation transformer
instead of a large excitation transformer in aloop test to considerably reduce testcost;Saves 30% of test time and labor cost of a
loop test.
Conducts low power testing (EL CID usesonly 4% of the rated magnetic flux) to
avoid further damage to fault areas;
-
7/31/2019 Generator Commissioning
46/90
Does not have safety concerns to
test personnel;Records test data by a computer
for trending of test results.
Provides an easy and in-expensivetest method to check the quality
of a core repair or a re-wedgingoperation.
-
7/31/2019 Generator Commissioning
47/90
EL CID testing requires goodknowledge of the EL CIDinstrument and stator cores togive a reliable test result.
O li / ff li PD t t d PD
-
7/31/2019 Generator Commissioning
48/90
On-line/off-line PD tests and PDdata analysis;
Partial discharge (PD) testing is a recognizedtool to diagnose stator insulationdeterioration and the other related problems.
The tests can be performed under the on-line condition (when a machine is running) orthe off-line condition (when a machine isstand still).
On-line PD testing can give early warning ofpotential machine failures and providemachine condition information for predictive
maintenance.
-
7/31/2019 Generator Commissioning
49/90
WHAT IS PARTIAL DISCHARGE
PD is a localized electrical discharge( spark) in an electrical system thatdoes not completely bridge the
electrode.
Partial discharge (PD) corresponds
to ionization of gas around or withinsolid insulation.
-
7/31/2019 Generator Commissioning
50/90
This phenomena only occurs at
higher AC voltage (specially > 3KV).
Higher the voltage, the more
destructive the activity. PD is a leading indicator of insulation
breakdown.
OFF LINE PD MEASUREMENT
-
7/31/2019 Generator Commissioning
51/90
OFF-LINE PD MEASUREMENT
-
7/31/2019 Generator Commissioning
52/90
OFF LINE PD TESTINGLIMITATION
Testing does not observe loadchanges
Testing does not occur atoperating voltage.
Equipment will not be at ratedtemperature.
-
7/31/2019 Generator Commissioning
53/90
ONLINE PD MEASUREMENT
The HV couplers are connected to themachine terminals to detect partial
discharges from the stator winding. A computer-controlled instrument
measures PD signals detected by the HV
couplers. PD specialist then analyzes thetest data to provide an insulationdiagnostics report .
-
7/31/2019 Generator Commissioning
54/90
-
7/31/2019 Generator Commissioning
55/90
RFCT
l
-
7/31/2019 Generator Commissioning
56/90
Coupling Capacitor
-
7/31/2019 Generator Commissioning
57/90
The nature, type, region, and severityof PD activity can be identified asfollows through data analysis:
Slot discharge
De-laminations
Internal partial discharge fromvoids
Grading paint discharge
Loose windings End winding discharge
PD Corona
-
7/31/2019 Generator Commissioning
58/90
PD - Corona
-
7/31/2019 Generator Commissioning
59/90
PD t ki
-
7/31/2019 Generator Commissioning
60/90
PD - tracking
-
7/31/2019 Generator Commissioning
61/90
PD- slot Discharge
-
7/31/2019 Generator Commissioning
62/90
EFECT OF PD
Rise to ozone
Nascent oxygen (strong oxidizingagent)
Power loss
Intense heat in the dischargechannel
-
7/31/2019 Generator Commissioning
63/90
PD ANALYSIS
Magnitude
Number density
Polarity
Phase angle of occurrence
Quadratic rate
-
7/31/2019 Generator Commissioning
64/90
WEDGE TIGHTNESS TEST
This test is done to check the tightness ofslot wedges of stator winding.
Looseness of wedge due to - shrinkage of slot packing material.
High mechanical stress
vibration
-
7/31/2019 Generator Commissioning
65/90
Corona probe measurements
Corona probe testing can pinpoint partialdischarge location in each slot.
It supplements on- line/off-line partialdischarge tests by precisely locating partialdischarge to a particular coil or a spot.
The corona probe can also be used as a
testing tool to measure levels of PD activity.Corona probe testing can be performed eitherwith the rotor in or out of the machine.
-
7/31/2019 Generator Commissioning
66/90
it is normally a requirement that the rotorsare removed from the stators so that the
electromagnetic probe can be inserted intothe stator frame. The stator winding isenergized at various voltages up to phase
voltage. The probe is moved along eachindividual slot and the levels of dischargecurrent are recorded from the peak milli
ammeter.
-
7/31/2019 Generator Commissioning
67/90
Corona probe testing to pinpoint theexact location of partial discharge activity
-
7/31/2019 Generator Commissioning
68/90
HI POT (DC Leakage currentmeasurement)
This test applies to the insulation a voltage for 1minute above nominal values. Maintenance testvoltage is less than the factory test voltage. Theresult is generally pass or fail. This test willinsure that the machine will supportextraordinary service conditions but because of
its aggressiveness, its usually not carried out asa predictive maintenance tool.
O ( k
-
7/31/2019 Generator Commissioning
69/90
HI POT (DC Leakage currentmeasurement)
Vdc= 1.6 x (AC test voltage)
or 1.5 Vph
(d f )
-
7/31/2019 Generator Commissioning
70/90
Dissipation factor (Tan-Delta) is one of the mostpowerful off-line nondestructive diagnostic toolto monitor the condition of solid insulation ofvarious high voltage equipment.
By measuring the electrical properties such as
capacitance and Tan-Delta regularly onperiodical basis, it is possible to ensure theoperational unexpected breakdown.
TAN DELTA (dissipation factor)TEST
-
7/31/2019 Generator Commissioning
71/90
WHAT IS TAN DELTA
It represents Di- electric losses concept ofthe insulating material.
HV
LV
INSULATIONELECTRODES
-
7/31/2019 Generator Commissioning
72/90
Perfect Insulation between the two
electrodes will act as a perfectcapacitor.
V
I
Cp
-
7/31/2019 Generator Commissioning
73/90
Tan = Ir/Ic= loss angle
= phase angle
Max allowable
Tan = 0.03For new machine Ir
Ic
V
I
T d lt t d
-
7/31/2019 Generator Commissioning
74/90
Tan delta measurement procedure
Suitable KVA rating transformer
Equipment should be disconnected
Kit to be grounded and test voltage israised in steps up to rated phase voltage.
-
7/31/2019 Generator Commissioning
75/90
Measurement Analysis:
Change in above quantities with machineage.
Statically variation of the quantities of thesimilar machine.
CORE LOOSENESS & REPAIR
-
7/31/2019 Generator Commissioning
76/90
CORE LOOSENESS & REPAIR
-
7/31/2019 Generator Commissioning
77/90
TESTING ON ROTOR
-
7/31/2019 Generator Commissioning
78/90
RSO TEST
AIR PURGE TEST
INSULATION RESISTANCE TEST
WINDING RESISTANCE IMPEDENCE TEST
CC BOLT AIR TIGHTNESS TEST
DPT & UT OF RETAINING RING
RSO TEST
-
7/31/2019 Generator Commissioning
79/90
RSO TEST
RSO test is performed to detect faults inrotor winding.
Electrical faults in the rotor fall into twomain categories:
Fault from the winding to the rotor body (Earth fault)
Fault between parts of the windings ( Inter
turn winding faults)
-
7/31/2019 Generator Commissioning
80/90
-
7/31/2019 Generator Commissioning
81/90
-
7/31/2019 Generator Commissioning
82/90
-
7/31/2019 Generator Commissioning
83/90
RSO TEST (SIMULATE EARTH FAULT ) ON
-
7/31/2019 Generator Commissioning
84/90
RSO TEST (SIMULATE EARTH FAULT ) ON
GENERATOR ROTOR UNIT 9
RSO TEST(SIMULATE INTERTURN FAULT ) IN
-
7/31/2019 Generator Commissioning
85/90
RSO TEST(SIMULATE INTERTURN FAULT ) INGENERATOR ROTOR UNIT 9
ROTOR AIR PURGE TEST
-
7/31/2019 Generator Commissioning
86/90
-
7/31/2019 Generator Commissioning
87/90
-
7/31/2019 Generator Commissioning
88/90
DPT/UT of retaining ring
These test are performed tocheck the internal cracks of the
retaining ring.
CC Bolt Air Tightness test
-
7/31/2019 Generator Commissioning
89/90
CC Bolt Air Tightness test
-
7/31/2019 Generator Commissioning
90/90
THANK YOU