EVM Made Simpleby Forrest Kovach
![Page 3: GenNext EVMS](https://reader034.vdocument.in/reader034/viewer/2022052600/557eb6add8b42ad27b8b489f/html5/thumbnails/3.jpg)
Dell ServicesConfidential3
Earned Value Management Made Simple
“Earned Value Management has proven itself to be one of the most effective performance measurement and feedback tools for managing projects.” - PMI
![Page 4: GenNext EVMS](https://reader034.vdocument.in/reader034/viewer/2022052600/557eb6add8b42ad27b8b489f/html5/thumbnails/4.jpg)
Dell ServicesConfidential4
It is called “Project Management with the Lights On” - PMI• Answers Questions:
– How effectively are we using our time?
– Are we currently over or under budget?
– What is the entire project likely to cost?
– Is the project anticipated to complete over or under budget?
• Pinpoints Difficulties
– Road Blocks
– The Magnitude of the Problem
![Page 5: GenNext EVMS](https://reader034.vdocument.in/reader034/viewer/2022052600/557eb6add8b42ad27b8b489f/html5/thumbnails/5.jpg)
Dell ServicesConfidential5
• Drives Schedule Performance
– Poor performance indices drive inquires
– Inquires identify roadblocks
– Illuminating roadblocks leads to elimination of impasse or work around
– Keeping the project moving while time and charges are burning
• Drives Cost Performance
– Poor performance indices drive inquires
– Reviewing actuals against planned value
– Unassigned charges
It is called “Project Management with the Lights On” - PMI
![Page 6: GenNext EVMS](https://reader034.vdocument.in/reader034/viewer/2022052600/557eb6add8b42ad27b8b489f/html5/thumbnails/6.jpg)
Dell ServicesConfidential6
Puts Pressure on Measurable Accomplishments
• What is measured gets done
• Quality comes first
• Performance comes next
• Plan is usually baselined against an aggregate parametric estimate
![Page 7: GenNext EVMS](https://reader034.vdocument.in/reader034/viewer/2022052600/557eb6add8b42ad27b8b489f/html5/thumbnails/7.jpg)
Dell ServicesConfidential7
• Flying without instruments is dangerous
• Managing projects with out performance measurement is disastrous.
• Do not dismiss the EV measurement as inaccurate, any gauge is better than none.
It is instrumentation for Project Management
![Page 8: GenNext EVMS](https://reader034.vdocument.in/reader034/viewer/2022052600/557eb6add8b42ad27b8b489f/html5/thumbnails/8.jpg)
Dell ServicesConfidential8
Project Actuals without EVM is Inconclusive• Actuals alone do not communicate how much work is
accomplished during the project.
• EVM is needed to measure performance objectively.
• Brief Timeline
– 1967, the Department of Defense established the Cost/Schedule Control Systems Criteria (C/SCSC).
– 1989, EVM is required for most Defense and NASA Acquisitions.› Added needed controls for cost plus contracts
– Construction industry adopts EVM.– 1999 Project Management Institute (PMI) creates the College of
Performance Management.
– 2002 EVM receives attention by publicly traded companies in response to the Sarbanes-Oxley Act.
![Page 9: GenNext EVMS](https://reader034.vdocument.in/reader034/viewer/2022052600/557eb6add8b42ad27b8b489f/html5/thumbnails/9.jpg)
Dell ServicesConfidential9
Key EVMS Terms
• Planned Value (PV)
• Earned Value (EV)
• Actual Cost (AC)
• Schedule Variance = EV – PV (to date)
• Budget at Complete (BAC)
• Schedule Performance Index (SPI) = EV / PV
– Answers what % of the planned work was completed to date
– > 1 great
– < 1 below optimal
![Page 10: GenNext EVMS](https://reader034.vdocument.in/reader034/viewer/2022052600/557eb6add8b42ad27b8b489f/html5/thumbnails/10.jpg)
Dell ServicesConfidential10
Key EMVS Terms
• Cost Performance Index (CPI) = EV / AC
– Answers how effectively are we using our resources?
– > 1 great
– < 1 below optimal
• Analytical Estimate at Complete (EAC)
– Uses CPI to forecast resource efficiency
– Uses SPI to forecast future schedule performance
– EAC = AC + ((BAC – EV) / (CPI * SPI))
![Page 11: GenNext EVMS](https://reader034.vdocument.in/reader034/viewer/2022052600/557eb6add8b42ad27b8b489f/html5/thumbnails/11.jpg)
Dell ServicesConfidential11
Putting EVMS to Work
• Baselined Microsoft Project Plan (MPP) file
Unique ID NameBaseline Work
Resource Names
16514 Firewall 280h16515 Initial Assessment 40h Network Engineer[50%]16518 Routing on DMZ/MDMZ to Reach Client Firewalls 16h Network Engineer[50%]16526 Best Practices Configuration 24h Network Engineer[50%]16519 DMZ nats IP Re-Addressing Plan (When Servers are All Up) 56h Network Engineer[50%]16520 Software Upgrade 24h Network Engineer[50%]
16521 Configure Standard Access from Firewall Leverage Team Servers (Need MPLS connection, dedicated circuit to PTC)
32h Network Engineer[50%]
16522 Add TACACS Authentication 8h Network Engineer[50%]16523 Setup Firewall Logs 16h Network Engineer[50%]16524 Add Monitoring to Firewalls (Needs OPAS) 24h Network Engineer[50%]16525 Add Firewalls to Voyence (Backup Tool) 16h Network Engineer[50%]16527 Transition FWs to Firewall Leverage Team (After Go-Live) 40h Network - Transition SME16719 End User Computing (EUC) Onsite Design and Deployment 302h16720 EUC Design 172h16802 Build machine specific drivers into image 40h POC EUC16803 Operating System patches and updates 20h POC EUC[50%]16804 Package and script additional software packages (per) 20h POC EUC[50%]16805 Desktop look and feel (EUC Design Complete) 12h POC EUC[50%]16806 Run machine consistently 20h POC EUC[50%]16807 Test driver, office apps and OS integrity 20h POC EUC[50%]16808 Open and test additional applications 20h POC EUC[50%]16809 Replicate Test Image to distribution shares 20h POC EUC[50%]16754 EUC Deployment (PC's, Displays) 130h POC EUC[25%]
![Page 12: GenNext EVMS](https://reader034.vdocument.in/reader034/viewer/2022052600/557eb6add8b42ad27b8b489f/html5/thumbnails/12.jpg)
Dell ServicesConfidential12
MPP Task Settings
• Fixed Work
• Duration increases will not increase estimated hours
• Assumes duration increases are due to delays
• Completed tasks earn baseline hours as actual hours when completed
![Page 13: GenNext EVMS](https://reader034.vdocument.in/reader034/viewer/2022052600/557eb6add8b42ad27b8b489f/html5/thumbnails/13.jpg)
Dell ServicesConfidential13
MPP Setting for Project Summary Task
![Page 14: GenNext EVMS](https://reader034.vdocument.in/reader034/viewer/2022052600/557eb6add8b42ad27b8b489f/html5/thumbnails/14.jpg)
Dell ServicesConfidential14
MPP Task Usage View
![Page 15: GenNext EVMS](https://reader034.vdocument.in/reader034/viewer/2022052600/557eb6add8b42ad27b8b489f/html5/thumbnails/15.jpg)
Dell ServicesConfidential15
MPP Time Phased Data
• Status File
• View – Task Usage – Line 0
• Set Scale to Weeks or Months as Desired
• Right Click to Display both Base and Actual Work
• Actuals are earned by completing planned work
• We are using MPP Actual Work as Earned Value (EV)
![Page 16: GenNext EVMS](https://reader034.vdocument.in/reader034/viewer/2022052600/557eb6add8b42ad27b8b489f/html5/thumbnails/16.jpg)
Dell ServicesConfidential16
Transfer Time Phased Data to Excel
Monday Week Start
28-Nov 5-Dec
12-Dec
19-Dec
26-Dec 2-Jan 9-Jan
16-Jan
23-Jan
30-Jan 6-Feb
13-Feb
20-Feb
27-Feb 5-Mar
12-Mar
19-Mar 26-Mar 2-Apr
Sunday Week End 4-Dec11-Dec
18-Dec
25-Dec 1-Jan 8-Jan
15-Jan
22-Jan
29-Jan 5-Feb
12-Feb
19-Feb
26-Feb 4-Mar
11-Mar
18-Mar
25-Mar 1-Apr 8-Apr
Base hrs 34h 57h 59h 80h h 61h 128h 199h 239h 117h 185h 327h 153h 179h 140h 162h 118h 118h 130hEV hrs 34h 57h 59h 80h 61h 128h 199h 239h 117h 185h 327h 143h 168h 130h 153h 107h 107h 119h
• Create Matching Timescale in Spreadsheet
• Replace all h units with Blank so Excel will use the values as numbers
![Page 17: GenNext EVMS](https://reader034.vdocument.in/reader034/viewer/2022052600/557eb6add8b42ad27b8b489f/html5/thumbnails/17.jpg)
Dell ServicesConfidential17
Get Actual Hours
• From PeopleSoft
• Other Sources for Offshore or Legacy Dell
• Combine Actual Hours
• From Financial Analyst
• Filter for Weekly Totals
• Team Must Record Weekly Time
![Page 18: GenNext EVMS](https://reader034.vdocument.in/reader034/viewer/2022052600/557eb6add8b42ad27b8b489f/html5/thumbnails/18.jpg)
Dell ServicesConfidential18
PeopleSoft Data
ID Name Financial Depar DeptID Rpt Dt Quantity TRC PC Bus Unit Proj/Grt ActivityID
109767 PRSER01 Q18A12A00Z 5/1/2012 8.000000 RGR CORP PERMS00100 PROJMGMT
109767 PRSER01 Q18A12A00Z 5/2/2012 8.000000 RGR CORP PERMS00100 PROJMGMT
109767 PRSER01 Q18A12A00Z 5/3/2012 8.000000 RGR CORP PERMS00100 PROJMGMT
109767 PRSER01 Q18A12A00Z 5/4/2012 8.000000 RGR CORP PERMS00100 PROJMGMT
52260 GFISS01 B5A2A0000Z 5/2/2012 2.000000 RGR CORP PERMS00100 INFOASSUR
52260 GFISS01 B5A2A0000Z 5/3/2012 1.000000 RGR CORP PERMS00100 INFOASSUR
52260 GFISS01 B5A2A0000Z 5/4/2012 0.500000 RGR CORP PERMS00100 INFOASSUR
52260 GFISS01 B5A2A0000Z 5/8/2012 0.500000 RGR CORP PERMS00100 INFOASSUR
52260 GFISS01 B5A2A0000Z 5/9/2012 0.500000 RGR CORP PERMS00100 INFOASSUR
52260 GFISS01 B5A2A0000Z 5/10/2012 2.000000 RGR CORP PERMS00100 INFOASSUR
52260 GFISS01 B5A2A0000Z 5/11/2012 2.000000 RGR CORP PERMS00100 INFOASSUR
50176 PRSER01 Q18A12C50Z 5/1/2012 1.000000 RGR CORP PERMS00100 SERVICEDESK
50176 PRSER01 Q18A12C50Z 5/2/2012 8.000000 RGR CORP PERMS00100 SERVICEDESK
50176 PRSER01 Q18A12C50Z 5/3/2012 2.000000 RGR CORP PERMS00100 SERVICEDESK
50176 PRSER01 Q18A12C50Z 5/4/2012 1.000000 RGR CORP PERMS00100 SERVICEDESK
50176 PRSER01 Q18A12C50Z 5/7/2012 1.000000 RGR CORP PERMS00100 SERVICEDESK
90337 GMEND01 Q18C9C000Z 5/1/2012 4.000000 RGR CORP PERMS00100 SERVICEDESK
90337 GMEND01 Q18C9C000Z 5/2/2012 4.000000 RGR CORP PERMS00100 SERVICEDESK
90337 GMEND01 Q18C9C000Z 5/7/2012 4.000000 RGR CORP PERMS00100 SERVICEDESK
90337 GMEND01 Q18C9C000Z 5/8/2012 4.000000 RGR CORP PERMS00100 SERVICEDESK
90337 GMEND01 Q18C9C000Z 5/9/2012 4.000000 RGR CORP PERMS00100 SERVICEDESK
90337 GMEND01 Q18C9C000Z 5/10/2012 4.000000 RGR CORP PERMS00100 SERVICEDESK
90337 GMEND01 Q18C9C000Z 5/11/2012 4.000000 RGR CORP PERMS00100 SERVICEDESK
112191 GFBUP01 QA8F00000Z 5/1/2012 4.000000 RGR CORP PERMS00100 PROJMGMT
112191 GFBUP01 QA8F00000Z 5/2/2012 4.000000 RGR CORP PERMS00100 PROJMGMT
![Page 19: GenNext EVMS](https://reader034.vdocument.in/reader034/viewer/2022052600/557eb6add8b42ad27b8b489f/html5/thumbnails/19.jpg)
Dell ServicesConfidential19
Transfer Time Phased Data to Excel
• Input Actual Hours
• May need to combine several sources
Monday Week Start
28-Nov 5-Dec
12-Dec
19-Dec
26-Dec
2-Jan 9-Jan
16-Jan
23-Jan
30-Jan 6-Feb
13-Feb
20-Feb
27-Feb 5-Mar
12-Mar
19-Mar 26-Mar 2-Apr 9-Apr 16-Apr 23-Apr
Sunday Week End 4-Dec11-Dec
18-Dec
25-Dec 1-Jan
8-Jan
15-Jan
22-Jan
29-Jan 5-Feb
12-Feb
19-Feb
26-Feb 4-Mar
11-Mar
18-Mar
25-Mar 1-Apr 8-Apr 15-Apr 22-Apr 29-Apr
Base hrs 34h 57h 59h 80h h 61h 128h 199h 239h 117h 185h 327h 153h 179h 140h 162h 118h 118h 130h 89h 145h 364hEV hrs 34h 57h 59h 80h 61h 128h 199h 239h 117h 185h 327h 143h 168h 130h 153h 107h 107h 119h 78h 125h 341hActual hrs 1,265 187 187 188 202 239 178 213 236 261Base Cum hrs 34 91 150 230 230 290 418 617 855 972 1,158 1,485 1,638 1,817 1,957 2,118 2,236 2,354 2,484 2,573 2,718 3,082EV Cum hrs 34 91 150 230 230 290 418 617 855 972 1,158 1,485 1,627 1,795 1,925 2,078 2,185 2,291 2,410 2,489 2,614 2,955Actual Cum hrs 1,265 1,452 1,639 1,827 2,029 2,268 2,446 2,659 2,895 3,156SPI 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.99 0.99 0.98 0.98 0.98 0.97 0.97 0.97 0.96 0.96CPI 1.24 1.17 1.14 1.08 1.01 0.99 0.94 0.90 0.94SV hrs. 0 0 0 0 0 0 0 0 0 0 0 0 -11 -11 -11 -9 -11 -11 -11 -11 -20 -23EAC hrs. 8,441 8,919 9,230 9,77710,44810,73411,32811,79011,377VAC hrs. +is below budget 1,895 1,417 1,106 559 -112 -398 -992 -1,453 -1,041
![Page 20: GenNext EVMS](https://reader034.vdocument.in/reader034/viewer/2022052600/557eb6add8b42ad27b8b489f/html5/thumbnails/20.jpg)
Dell ServicesConfidential20
Create Formulas for Analysis
• Base Cum = Base Cum Last Week + Base Hours Current Week
• EV Cum = EV Cum Last Week + EV Hours Current Week• Actual Cum = Actual Cum Last Week + Actual Hours Current
Week• SPI = Cum EV Hours / Cum Base Hours• CPI =Cum EV Hours / Cum Actual Hours• SV = Cum EV Hours - Cum Base Hours• EAC = Cum Actual + ((Cum Planed Hours- EV
Hours)/(SPI*CPI))• VAC = Cum Hours at Complete – EAC
Monday Week Start
28-Nov 5-Dec
12-Dec
19-Dec
26-Dec
2-Jan 9-Jan
16-Jan
23-Jan
30-Jan 6-Feb
13-Feb
20-Feb
27-Feb 5-Mar
12-Mar
19-Mar 26-Mar 2-Apr 9-Apr 16-Apr 23-Apr
Sunday Week End 4-Dec11-Dec
18-Dec
25-Dec 1-Jan
8-Jan
15-Jan
22-Jan
29-Jan 5-Feb
12-Feb
19-Feb
26-Feb 4-Mar
11-Mar
18-Mar
25-Mar 1-Apr 8-Apr 15-Apr 22-Apr 29-Apr
Base hrs 34h 57h 59h 80h h 61h 128h 199h 239h 117h 185h 327h 153h 179h 140h 162h 118h 118h 130h 89h 145h 364hEV hrs 34h 57h 59h 80h 61h 128h 199h 239h 117h 185h 327h 143h 168h 130h 153h 107h 107h 119h 78h 125h 341hActual hrs 1,265 187 187 188 202 239 178 213 236 261Base Cum hrs 34 91 150 230 230 290 418 617 855 972 1,158 1,485 1,638 1,817 1,957 2,118 2,236 2,354 2,484 2,573 2,718 3,082EV Cum hrs 34 91 150 230 230 290 418 617 855 972 1,158 1,485 1,627 1,795 1,925 2,078 2,185 2,291 2,410 2,489 2,614 2,955Actual Cum hrs 1,265 1,452 1,639 1,827 2,029 2,268 2,446 2,659 2,895 3,156SPI 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.99 0.99 0.98 0.98 0.98 0.97 0.97 0.97 0.96 0.96CPI 1.24 1.17 1.14 1.08 1.01 0.99 0.94 0.90 0.94SV hrs. 0 0 0 0 0 0 0 0 0 0 0 0 -11 -11 -11 -9 -11 -11 -11 -11 -20 -23EAC hrs. 8,441 8,919 9,230 9,77710,44810,73411,32811,79011,377VAC hrs. +is below budget 1,895 1,417 1,106 559 -112 -398 -992 -1,453 -1,041
![Page 21: GenNext EVMS](https://reader034.vdocument.in/reader034/viewer/2022052600/557eb6add8b42ad27b8b489f/html5/thumbnails/21.jpg)
Dell ServicesConfidential21
Graph Result for Analog Communication
![Page 22: GenNext EVMS](https://reader034.vdocument.in/reader034/viewer/2022052600/557eb6add8b42ad27b8b489f/html5/thumbnails/22.jpg)
Dell ServicesConfidential22
Conclusions
• Implement Weekly EVM on Projects
• Focus on Indices will Spot Concerns
• Concerns will Drive Performance
• An EVM Adherence Cycle will Increase Company:
– Performance
– Utilization
– Profits
– And crank out projects with more horsepower than ever!
![Page 23: GenNext EVMS](https://reader034.vdocument.in/reader034/viewer/2022052600/557eb6add8b42ad27b8b489f/html5/thumbnails/23.jpg)
Dell ServicesConfidential23
Why EVMs and Metric Tools
• When SPI variances occur drill into Microsoft Data for Late tasks.
– Tasks baselined in the past with Start or Finish Variances
• When CPI variances occur review labor charge details where hours are charged and not earning as much Earned Value in Microsoft Project Tasks.
• Look for a common cause or theme to Identify and take corrective action
• Data is only data if it is not acted upon.
![Page 24: GenNext EVMS](https://reader034.vdocument.in/reader034/viewer/2022052600/557eb6add8b42ad27b8b489f/html5/thumbnails/24.jpg)
Dell ServicesConfidential24
Questions?
![Page 25: GenNext EVMS](https://reader034.vdocument.in/reader034/viewer/2022052600/557eb6add8b42ad27b8b489f/html5/thumbnails/25.jpg)
Dell ServicesConfidential25
Contact Information for Inquiries or Assistance