geology map - ministry of energy of georgiaenergy.gov.ge/projects/pdf/pages/tskhenistskali 1 hesi...
TRANSCRIPT
APPENDIX 3
Geology Map
WEL ▼1780
WEL ▼1780
WEL ▼1780
WEL ▼1780
WEL ▼1780
APPENDIX 4
Geomorphology Map
WEL ▼1780
WEL ▼1780
WEL ▼1780
WEL ▼1780
WEL ▼1780
APPENDIX 5
Soils Map
WEL ▼1780
WEL ▼1780
APPENDIX 6
Preliminary Turbine – Generator Characteristics
TURBNPRO Version 3 - PELTON TURBINE SOLUTION SUMMARY
Page 1
Solution File Name: d:₩projects₩database₩turbin~1₩tsk1-4xp
TURBINE SIZING CRITERIA _______________________
Rated Discharge: 166.0 cfs / 4.70 m3/s Net Head at Rated Discharge: 841.2 feet / 256.4 meters Gross Head: 885.8 feet / 270.0 meters Efficiency Priority: 5 System Frequency: 50 Hz Minimum Net Head: 841.2 feet / 256.4 meters Maximum Net Head: 858.0 feet / 261.5 meters
PELTON TURBINE SOLUTION DATA _____________________________
Arrangement: VERTICAL WITH RUNNER ON TURBINE SHAFT Intake Type: 4 - JET Runner Pitch Diameter: 59.3 inches / 1506 mm Unit Speed: 428.6 rpm Multiplier Efficiency Modifier: 1.000 Flow Squared Efficiency Modifier: 0.0000 Specific Speed at Rated Net Head (turbine) - (US Cust.) (SI Units) At 100% Turbine Output: 11.3 43.0 At Peak Efficiency Condition: 10.3 39.3 Specific Speed at Rated Net Head (per jet) - (US Cust.) (SI Units) At 100% Turbine Output: 5.6 21.5 At Peak Efficiency Condition: 5.2 19.6
SOLUTION PERFORMANCE DATA _________________________................................................................................. At Rated Net Head of: 841.2 feet / 256.4 meters
% of Rated Discharge Output (KW) Efficiency (%) cfs m3/s ** 116.6 12267 89.0 193.6 5.48 100 10592 89.6 166.0 4.70 * 83.3 8842 89.7 138.3 3.92 75 7945 89.6 124.5 3.53 50 5235 88.6 83.0 2.35 25 2568 86.9 41.5 1.18 ** - Overcapacity * - Peak Efficiency Condition................................................................................. At Maximum Net Head of: 858.0 feet / 261.5 meters
Max. Output (KW) Efficiency (%) cfs m3/s 12636 89.0 195.5 5.54................................................................................. At Minimum Net Head of: 841.2 feet / 256.4 meters
Max. Output (KW) Efficiency (%) cfs m3/s 12273 89.0 193.6 5.48.................................................................................
TURBNPRO Version 3 - PELTON TURBINE SOLUTION SUMMARY
Page 2
Solution File Name: d:₩projects₩database₩turbin~1₩tsk1-4xp
MISCELLANEOUS DATA __________________
Maximum Runaway Speed (at Max. Net Head): 753 rpm
D/B Ratio (Runner Pitch Dia./Bucket Width): 2.87
Maximum Hydraulic Thrust (at Max. Net Head): 14054 lbs / 6388 kg Hydraulic Thrust per Jet (at Max. Net Head): 9939 lbs / 4518 kg Estimated Axial Thrust: 14859 lbs / 6754 kg
Approximate Runner and Shaft Weight: 13313 lbs / 6052 kg
DIMENSIONAL DATA ________________................................................................................. Intake Type: 4 - JET inches / mm Inlet Diameter: 33.0 838 Nozzle Diameter: 19.5 496 Jet Orifice Diameter: 6.2 158 Needle Stroke: 5.9 151 Inlet Piping Spiral Radius: 132.8 3372 Jet to Jet Included Angle: 90 Degrees................................................................................. Housing/Discharge Geometry: inches / mm Centerline to Housing Top: 41.8 1062 Housing Diameter: 198.2 5033 Discharge Width: 148.6 3775 Tailwater Depth: 32.7 830 Discharge Ceiling to T.W.: 35.6 904 Centerline to Tailwater: 97.5 2476................................................................................. Shafting Arrangement: VERTICAL WITH RUNNER ON TURBINE SHAFT inches / mm Centerline to Shaft Coupling: 89.8 2281 Turbine Shaft Diameter: 14.5 369................................................................................. Miscellaneous: inches / mm Runner Outside Diameter: 79.9 2030 Runner Bucket Width: 20.6 524.................................................................................
**** All information listed above is typical only. Detailed characteristics will vary based on turbine manufacturer's actual designs.
TURBNPRO Version 3.0 - PELTON TURBINE SOLUTION GRAPHICS
Page 1
Solution File Name: d:₩projects₩database₩turbin~1₩tsk1-4xp Intake Type: 4 - JET Runner Diameter: 1506 mm Net Head at Rated Discharge: 256.40 meters Unit Speed: 428.6 rpm
TURBNPRO Version 3.0 - PELTON TURBINE SOLUTION GRAPHICS
Page 1
Solution File Name: d:₩projects₩database₩turbin~1₩tsk1-4xp Intake Type: 4 - JET Runner Diameter: 1506 mm Net Head at Rated Discharge: 256.40 meters Unit Speed: 428.6 rpm
TURBNPRO Version 3.0 - PELTON TURBINE SOLUTION GRAPHICS
Page 1
Solution File Name: d:₩projects₩database₩turbin~1₩tsk1-4xp Intake Type: 4 - JET Runner Diameter: 1506 mm Net Head at Rated Discharge: 256.40 meters Unit Speed: 428.6 rpm
TURBNPRO Version 3.0 - PELTON TURBINE SOLUTION GRAPHICS
Page 1
Solution File Name: d:₩projects₩database₩turbin~1₩tsk1-4xp Intake Type: 4 - JET Runner Diameter: 1506 mm Net Head at Rated Discharge: 256.40 meters Unit Speed: 428.6 rpm
TURBNPRO Version 3 - PELTON TURBINE HILL CURVE
Page 1
Solution File Name: d:₩projects₩database₩turbin~1₩tsk1-4xp
Intake Type: 4 - JET Runner Pitch Diameter: 1506 mm Net Head at Rated Discharge: 256.40 meters Unit Speed: 428.6 rpm Peak Efficiency: 89.7 % Multiplier Efficiency Modifier: 1.000 Flow Squared Efficiency Modifier: 0.0000
0
1
2
3
4
5
6
7
300 400 5000%20%40%60%
Hd Limit80%
Hd Limit 346.6m80% Hd Limit 346.6m
85%
86%
87%88%
89%
At Peak Eff 3.92 m3/s
Rated 4.70 m3/s
4 jet operationMax Hd - 261.5m
Min Hd - 256.4m256.4 m
4 jet operation
ead (meters)
Discharge
Key
Constant Efficiency LinesMax Discharge LimitMin/Max Net Head LimitsNet Head Limits Entered
NOTE: Discharge is in cubic meters per second
TURBNPRO Version 3 - PELTON TURBINE HILL CURVE
Page 1
Solution File Name: d:₩projects₩database₩turbin~1₩tsk1-4xp Intake Type: 4 - JET Runner Pitch Diameter: 1506 mm Net Head at Rated Discharge: 256.40 meters Unit Speed: 428.6 rpm Multiplier Efficiency Modifier: 1.000 Flow Squared Efficiency Modifier: 0.0000
Performance Data Shown is for a Net Head of: 256.4000
Power (KW) Efficiency (%) Discharge (m3/s) Operating Jets Notes
12273 89.00 5.48 4 Max Discharge Limit
12050 89.16 5.37 4 Additional Output Capability
11820 89.29 5.26 4 Additional Output Capability
11584 89.36 5.15 4 Additional Output Capability
11347 89.44 5.04 4 Additional Output Capability
11110 89.52 4.93 4 Additional Output Capability
10869 89.56 4.82 4 Additional Output Capability
10625 89.59 4.71 4 Additional Output Capability
10592 89.59 4.70 4 Rated Flow/Head Condition
10381 89.62 4.61 4 -
10137 89.64 4.50 4 -
9892 89.66 4.39 4 -
9646 89.68 4.28 4 -
9401 89.70 4.17 4 -
9156 89.72 4.06 4 -
8910 89.74 3.95 4 -
8840 89.75 3.92 4 Best Efficiency at Net Head
8661 89.72 3.84 4 -
8409 89.68 3.73 4 -
8158 89.64 3.62 4 -
7908 89.60 3.51 4 -
7657 89.56 3.40 4 -
7407 89.52 3.29 4 -
7157 89.48 3.18 4 -
6903 89.39 3.07 4 -
6648 89.28 2.96 4 -
6564 88.85 2.94 3 Best Efficiency for 3 Jet Operation
6395 89.17 2.85 4 -
6141 89.07 2.74 4 -
5888 88.96 2.63 4 -
5631 88.77 2.52 4 -
5376 88.60 2.41 3 -
5125 88.50 2.30 3 -
4874 88.35 2.19 3 -
4622 88.21 2.08 3 -
4372 88.07 1.97 3 -
4332 87.95 1.96 2 Best Efficiency for 2 Jet Operation
4121 87.89 1.86 2 -
3875 87.81 1.75 2 -
3629 87.73 1.64 2 -
3382 87.60 1.54 2 -
3133 87.39 1.43 2 -
2885 87.18 1.32 2 -
2636 86.88 1.21 1 -
2399 86.97 1.10 1 -
2161 87.05 0.99 1 -
2144 87.06 0.98 1 Best Efficiency for 1 Jet Operation
1918 86.91 0.88 1 -
1674 86.71 0.77 1 -
1428 86.29 0.66 1 -
1179 85.48 0.55 1 -
928 84.12 0.44 1 -
676 81.75 0.33 1 -
TURBNPRO Version 3 - PELTON TURBINE HILL CURVE
Page 2
Power (KW) Efficiency (%) Discharge (m3/s) Operating Jets Notes
409 74.16 0.22 1 -
114 41.25 0.11 1 Low efficiency; not used in energy calculation
50
60
70
80
90
100
0 2 4 6 8
Rated Flow atRated Head
x - Maximum Discharge Limit
256.4m
Turbine Discharge (cubic meters/second)
%Efficiency
APPENDIX 7
Land Cover Map
WEL ▼1780
WEL ▼1780
WEL ▼1780
APPENDIX 8
Mean Annual Precipitation
WEL ▼1780
WEL ▼1780
WEL ▼1780
WEL ▼1780
APPENDIX 9
Environmental and Social Impacts, Affected Environment
1
Appendix 1: Description of Tables
This appendix presents a tabular summary of potential environmental and social receptor impacts from the development of a hydropower project. These tables are based on the “EU Strategic Environmental Assessment Principles” that uses a subset of categories developed that best fits this level of analysis (Ref: http://ec.europa.eu/environment/eia/home.htm). Sections 2 and 3 and Section 6 of this document present a description of environmental and social baseline conditions. Section 6.2 presents environmental and social impacts and mitigation practices for each impacted receptor. The tables include a range of qualitative values for impacts and recommendations for mitigation practices that are considered standards of practice today. This prefeasibility report does not go into any detail with respect to recommended mitigation practices and should be used as a guideline with respect to the types of practice to be incorporated during a feasibility study for the different phases of the project (construction or operations. Decommissioning has not been included at this time).
The table column headers are described as follows:
Column 1: Receptors
Receptors are the environmental and social category that an impact is evaluated for. For this prefeasibility report these include:
Water Resources Surface Water Resources Surface Water Quality Flood Risk
Soils, Geology, and Landscape
Air Quality
Biodiversity Terrestial Flora Terrestial Fauna Fisheries
Community, Socio-Economic, and Public Health Cultural and Historic Assets Population Recreation Public Health
Receptors are evaluated with a Sensitivity level that is defined as follows:
2
Sensitivity of receptors, based on Value and Vulnerability
Classification Sensitivity Level
Vulnerability
High (H) e.g. potential
pathways exist for environmental change in receptors as a result of project, receptor is in a declining condition, and/or dependent on a narrow range of environmental conditions
Medium (M) e.g. few
pathways exist for environmental change in receptors as a result of project, receptor is only expected to recover from disturbance over a prolonged period of time, if at all, or impact potential is high but duration is short
Low (L) e.g. limited or no pathways
exist for environmental change in receptors as a result of project, receptor is in stable or favorable condition &/ or dependent on wide range of environmental conditions
None (N) e.g. no
pathways exist between environmental changes and receptors, receptor is insensitive to disturbance
Value
High (H) – receptor is rare,
important for social or economic reasons, legally protected, of international or national designation
Low (L) – receptor is
common, of local or regional designation
Column 2: Impact This column is a description of the effect on the receptors during each of the project phases, construction followed by operations.
Column 3: Duration Duration is the expectation for the length of time an impact will occur to a given receptor. The following table displays the rating values for duration:
Guidelines for determining the period of the project lifecycle
Duration of effect
Classification Long Term (LG) Medium Term (MD) Short Term (SH) Very Short Term (VSH)
Guideline 10+ years 3-10 years 1-3 years <12 months
Project phase Operation Operation Construction (or part thereof) Part of construction period
3
Column 4: Risk Level
Risk Level qualitatively addresses the exposure and vulnerability a receptor will have from the project or in some cases how specific risks could cause the project to increase exposure and vulnerability to the receptor. An example of this is Seismic Risk as it pertains to Soils, Geology, and Landscape during each project phase. Risk level also includes whether the impact is Irreversible or Reversible and temporary or Permanent. The following displays the rating values for Risk Level:
Risk Level Rankings Definitions and Description
Risk Level Description
Very Low (VL) Rarely occurs, and/or of very low magnitude, and/or rarely causes significant loss or life or property damage
Low (L) Can occur during the life of the project, and/or can be of modest magnitude, and/or rarely causes loss of life but can cause property some damage
Medium (M) Occurs several or more times during the life of a project, and/or of significant magnitude, and/or can cause some loss of life and significant property damage
High (H) Occurs often or on a regular basis and/or of a very high magnitude, and/or causes large loss of life and major property damage
Irreversible Impact causes irreversible change to the receptor
Reversible Impact causes reversible changes to the receptor
Temporary Impact is of a temporary nature and receptor will return to original conditions after activity concludes
Permanent Impact from activity is permanent changing the original receptor conditions to a new state.
Column 5: Mitigation Practices
Mitigation practices are guidelines and recommendations for a type of prevention activity that will reduce impacts to a receptor, provide necessary data and information for decisions during a project phase, provide heath and safety guidelines, and environmental prevention practices to minimize impacts to the receptors.
4
Table - 1 Affected Environmental Impacts and Proposed Mitigation Measures Environmental Receptor Category: Water Resources
Water Resources
Receptors Vulnerability (H, M, L, N) Value (H, L)
IMPACT (Description of effect)
Duration ( construction, operation
or decommissioning LG/MD/SH/VSH term)
and frequency
Risk Level (VL, L, M, H)
Irrev./ rev.; Temp./ per
Mitigation Practices
Surface Water Resources (quantity) M/L
M/L
Construction Phase (HPP and Transmission Facility):
Altered surface runoff contribution to water courses and ditches, etc. as a result of land disturbance
Temporary Diversion of River away from Dam and intake structure
Large construction/tunnel volume debris disposal
Construction of the dam will create a small permanent reservoir changing natural river conditions.
Operation Phase:
Effects on surface water resources during facility operations
SH
SH
SH
LG
LG
VL/R/T
VL/R/T
VL/R/T
VL/IR/P
L/R/P
Very high sediment and bed load transport by upper river. Assume site preparation include in-water, bank side, and/or adjacent property. River flow and river channel may be temporarily redirected for site construction. Well understood process. Few if any uncertainties, assume runoff controls and spill prevention plans and monitoring are included in construction. Locate area for construction debris that can contribute to generation of usable land in the future.
Run of river hydropower operations returns all diverted flow used for generation to the receptor river. Long penstock facilities must meet appropriate receptor guidelines for bypass flows as required.
5
Surface Water Quality M/L
M/L
Construction Phase(HPP and Transmission Facility):
Altered surface runoff water quality to water courses and ditches, etc. as a result of land disturbance
Temporary Diversion of River away from Dam and intake structure
Operation Phase:
effects on surface water resources during facility operations
SH
SH
LG
VL/R/T
VL/R/T
L/R/T
Very high sediment and bed load transport by upper river. Assume site preparation can include in-water, bank side, and/or adjacent property. River flow and river channel may be temporarily redirected for site construction. Well understood process. Few if any uncertainties, assume runoff controls and spill prevention plans and monitoring are included during construction.
Run of river hydropower operations returns all diverted flow used for generation to the receptor river. Long penstock facilities must meet appropriate receptor guidelines for bypass flows as required.
Flooding Risk M/L
M/L
Construction Phase (HPP and Transmission Facility):
Increase to flood discharge from failure of dam during construction
Operations Phase:
Prevent failure of dam and other project components in the event of a flood that would severely increase the impact from the flooding event
VSH
VSH
L/R/T
M/R/T
Construction to adhere to all design requirements.
Dispose of large volumes of construction debris in locations that will not increase flood levels, or impact floodplain negatively
Design to address appropriate levels of Flood Risk in planning construction phase.
Monitoring of river discharge upstream on main stem and significant tributaries (flash flood warning)
Emergency Evacuation Plan developed
Emergency site shut down plan to be developed.
Insure all facilities are operating correctly including, spillway gates, trash racks, and shut off gates (tunnel and powerhouse), etc. Monitor Dam for seepage, leaks, and structural integrity. Monitor Tunnel for leaks and structural integrity Prepare Emergency operations plan that includes flooding events Prepare Emergency shut down and evacuation plan.
6
Table - 2 Affected Environmental Impacts and Proposed Mitigation Measures Environmental Receptor Category: Soils, Geology, and Landscape
Soils, Geology and Land Use
Receptors
IMPACT (Description of effect)
Duration LG/MD/SH/VS
H term)
Risk Level (VL, L, M, H, and Irreversible/
reversible; temporary/ permanent
Mitigation Practices
Soils, Geology, Landscape (Vulnerability (H, M, L, None) and Value (H, L)
M/H
M/H
Seismic Risk Construction Phase (HPP and Transmission Facility):
Impacts on infrastructure and public due to seismic activity
Operation Phase:
Impacts on infrastructure and public due to seismic activity that causes HPP to fail
VSH
VSH
H/R and IR/T and P
depending on seismic characteristics
H/R and IR/T and P
depending on seismic characteristics
Well understood process. The project structures to be built in the area have to have appropriate design specifications which are in line with the national and international standards. Severe activity can lead to failure, flooding, property damage and loss of human life. Emergency site shut down and Evacuation plans should be included in construction management planning.
Well understood process but magnitude is unknown Severe seismic activity can lead to failure, flooding, property damage and loss of human life downstream of HPP. Emergency site shut down and Evacuation plans downstream should be included in HPP Operations Plan
Soils, Geology, and Landscape (Vulnerability (H, M, L, None) and Value (H, L)
M/H
M/H
Landslides and Mudslides Construction Phase (HPP and Transmission Facility):
Improper stockpiling of materials, poor sitting, of storage and lay down areas, blasting activities and/or destruction of vegetation cover could increase receptor impacts if land slide or mud slide occurs at HPP site or upstream.
Operation Phase:
Minimize increasing the impacts from this natural occurrence from HPP operations
VSH
SH
M/R/T
L/R/T
Erosion and sediment control plan (includes issues like: proper site sitting and engineering design based on best management practices, accumulated sediment disposal plan, grading and smoothing steep slopes, re-vegetation activities etc.) at national and international standards should be developed. Emergency shut down and Evacuation plans should be developed to protect receptors, property, and human life. Early Warning Monitoring to include Weather and watershed and upslope areas from HPP site and known land slide and mud slide locations Proper scheduling of construction activities Monitoring of vibration from construction equipment (and blasting activities)
Monitoring site conditions on a regular basis; implementation of pre-prepared emergency shut down and Evacuation plans ; Monitoring of Early Warning system
7
Soils, Geology, and landscape (Vulnerability (H, M, L, None) and Value (H, L)
M/H
M/H
Visual impact on landscape Construction Phase (HPP and Transmission Facility):
Visual impact is important in this mountainous setting and impacts to this receptor are significant. Construction activities may cause visual disturbance of landscape (new project units (e.g. dam, powerhouse) will be constructed. Construction activities may cause removal of vegetation cover, changes in land use pattern. Waste generation due to construction activities may create visual impact on landscape as well as impact on land. Management and disposal of construction debris
Operation Phase:
No more additional alterations of landscape are expected during the operation phase. Water body such as impoundment may be considered to create pleasant scenery.
SH
SH
VL/R/T
VL/IR/P
Proper storage and utilization of topsoil and excavation materials. Restoration of soil cover, re-vegetation and reforestation activities to national and international standards Proper scheduling of construction activities. Develop construction management plan. Development appropriate waste management plan which includes management of solid, liquid, hazardous waste material and are in line with national and international environmental regulations. Construction debris should be disposed of according to current accepted practice, local and national laws. Where possible use construction in a sustainable manner that provides opportunities for agriculture, local industry, and does not impact local floodplain
Monitoring the landscape restoration activities.
8
Table - 3 Affected Environmental Impacts and Proposed Mitigation Measures Environmental Receptor Category: Air Quality
Air Quality
Receptor s
IMPACT (Description of effect)
Duration LG/MD/SH/VSH term)
Risk Level (VL, L, M, H, and Irreversible/ reversible; temporary/ permanent
Mitigation Practices
Air Quality (Vulnerability (H, M, L, None) and Value (H, L) L/H
L/H
Construction Phase (HPP and Transmission Facility):
Construction activities may increase the level of emission in the air and dust, especially under windy conditions.
Operation Phase:
During operation there would not be any significant emission level.
SH
VSH
L/R/T
VL/R/T
Well understood process. Air management plan should be developed, which includes activities like construction machinery maintenance scheduling, Exhaust gas quality, water spray on construction site to minimize dust, checking construction equipment and/or benzene quality etc.
Ensuring compliance with air management plan, emergency generator exhaust controls.
9
Table - 4 Affected Environmental Impacts and Proposed Mitigation Measures Environmental Receptor Category: Biodiversity
Biodiversity
Receptor s
IMPACT (Description of effect)
Duration LG/MD/SH/VSH
term)
Risk Level (VL, L, M, H, and Irreversible/
reversible; temporary/ permanent
Mitigation Practices
Terrestrial flora (Vulnerability (H, M, L, None) and Value (H, L) L/H
L/H
Construction Phase (HPP and Transmission Facility):
Project might have following primary and secondary impacts on the terrestrial flora:
Construction of HPP, new roads and/or Transmission lines may cause removal of vegetation (forests, topsoil);
Alien species invading the existing ecosystem;
Operation Phase:
There would be minor or no impact on flora during the operation phase
SH
MD
M/R/T
VL/R/P
Well understood process. Restoration and reinstatement of soil cover; re-vegetation and/or reforestation activities.
Monitoring restoration activities.
Terrestrial fauna (Vulnerability (H, M, L, None) and Value (H, L) L/H
Construction Phase (HPP and Transmission Facility):
Project might have following primary and secondary impacts on the terrestrial fauna:
Disruption of sites of breeding and sheltering;
Animal mortality due to construction activities (e.g. accidents and/or mortality of birds due to Transmission lines)
Alien species invading the existing ecosystem;
number of equipments and/or possible blasting activities may cause the increase the noise/vibration level during the construction process, which may disturb wildlife (affect species behaviour)
SH
M/R/T
Wildlife management plan should be developed. Noise management plan. Proper scheduling of construction activities; Monitoring of vibration and blasting activities from construction equipment
10
L/H
Operation Phase:
Impacts affecting fauna elements during operation are:
Ecological barrier effect (movement is disabled or hindered
Mortality of animals on roads;
Mortality of birds on power lines
LG
VL/R/P
Implementing and monitoring the wildlife management plan.
Fishery (Vulnerability (H, M, L, None) and Value (H, L) L/H
L/H
Construction Phase HPP:
Impact on fish species due to construction in the riverbed and altering the river flow through temporary diversion channel, and blasting activities.
Operation Phase:
Impacts on fish species due to diverting river flow to the powerhouse (mortality fish species in the turbines/generators). Exposure of bypass section of river to very low to no flow.
MD
MD
M/R/T
M/R/T
Installing fish protecting/screening facilities at the entrance of the HPP feeding tunnels/channels. Scheduling of construction activities. Avoiding the stock piling in the riverbed. Proper scheduling of construction activities; Monitoring of vibration and blasting activities from construction equipment
Well understood process. Permanent monitoring of sanitary water flow; compliance with environmental and in-stream flow requirements with monitoring.
11
Table - 5 Affected Environmental Impacts and Proposed Mitigation Measures Environmental Receptor Category: Cultural Resources
Cultural Resources and Recreation
Receptor s
IMPACT (Description of effect)
Duration LG/MD/SH/VSH
term)
Risk Level (VL, L, M, H, and Irreversible/ reversible; temporary/ permanent
Mitigation Practices
Cultural and historic assets (Vulnerability (H, M, L, None) and Value (H, L)
L/H
L/H
Construction Phase HPP and Transmission Facility):
There are no archaeological and/or cultural heritage sites in the vicinity of the projects. However, during construction works they might occur. Archaeological objects should be protected from damage.
Operation Phase:
No damage on archaeological/cultural resources is expected from operational phase. Small reservoir behind dam may provide new opportunities for recreational activities
VSH
VSH
VL/R/T
VL/R/P
Identifying historical and cultural assets. Development of noise and construction management plan. Proper scheduling of construction activities Monitoring of vibration from construction equipment and blasting activities.
N/A
Table-6 Affected Environmental Impacts and Proposed Mitigation Measures Environmental Receptor Category:
Community, Socio-Economic and Public Health
Community, Socio-Economic and Public Health
Receptor s
IMPACT (Description of effect)
Duration (LG/MD/S
H/VSH term)
Risk Level (VL, L, M, H, and Irreversible/
reversible; temporary/ permanent
Mitigation Practices
Agricultural Land (Vulnerability (H, M, L, None) and Value (H, L)
L/H
Construction Phase (HPP and Transmission Facility):
Impact associated with land acquisition and thereby loss of agricultural land, which may cause loss of income earning means; disposal of debris; limit access to agricultural property
SH
L/R/T
Develop compensation mechanism for occupied agricultural land.; coordinate construction activities to minimize impacts to agricultural properties, appropriate selection of disposal areas, materials storage areas;, Monitoring the implementation of compensation scheme
12
L/H
Operation Phase:
New infrastructure (e.g. access roads) may positively impact on local population, provide better access to markets for agricultural products
LG
VL/R/P
N/A
Population (Vulnerability (H, M, L, None) and Value (H, L)
N/H
N/H
Construction Phase (HPP and Transmission Facility):
Machinery and/or possible blasting activities may cause the increase the noise/vibration level during the construction process, Construction activities cause traffic delays, which affect local population within the vicinity of project. New job opportunities and economic benefits to community
Operation Phase:
The noise/vibration source during the operation will be generators and turbines located in the powerhouse. Since they are located in the closed building, it will have not any considerable nuisance.
SH
N/A
L/R/T
N/A
Well understood process. Noise management plan Blast warning plan for construction crews and local residents. Proper scheduling of construction activities Monitoring of vibration from construction equipment (and blasting activities)
N/A
Recreation (Vulnerability (H, M, L, None) and Value (H, L)
L/H
L/H
Construction Phase (HPP and Transmission Facility):
Visual impact due to construction; activities may impact recreation in the region. Waste generation due to construction activities may create visual impact. Delay or prevent access to recreational locations
Operation Phase:
New reservoir and new infrastructure (e.g. better roads) may positively impact on recreational activities
SH
LG
VL/R/T
L/IR/P
Proper scheduling of construction activities. Develop construction management plan. Development appropriate waste management plan which includes management of solid, liquid, hazardous waste management and are in line with national and international environmental regulations. Provide construction schedules and coordinate with recreational locations to minimize access issues for visitors.
Operations practice should coordinate with recreational activities so as to assure safe access (fishing), adequate water in bypass channels to support in-stream activities, and provide access to river for such activities if project limits access.
13
Roads, Infrastructure, and Communities (Vulnerability (H, M, L, None) and Value (H, L)
L/H
L/H
Construction Phase (HPP and Transmission Facility):
It is expected that during construction new access roads will be built. Loads on the existing roads will increase due to construction machinery. Traffic increase will affect Noise, Air Quality, community safety, and Public Health Receptors. Construction provides jobs and economic benefits to community
Operation Phase:
It is expected that during operational phase vehicular movement will be increased for maintenance, etc purposes. Consider community health, safety and security issues, as well as Noise and Air Quality Receptors.
SH
LG
L/R/T
VL/R/P
Develop construction management plan that addresses materials delivery, storage, noise, and air quality issues that are sensitive to local communities and meet all Georgian environmental and legal requirements. Include job training for local population where appropriate.
Develop traffic management plan with limited vehicular movement during operational phase. Ensure compliance with local and regional laws that effect the community
Public Health (Vulnerability (H, M, L, None) and Value (H, L)
L/H
L/H
Construction Phase (HPP and Transmission Facility):
Construction activities might cause health impact to the workers (e.g. construction related accidents). Also see Air Quality, Population Receptors
Operation Phase:
Operational activities might cause health impact to the workers and/or local population.
SH
LG
VL/R/T
VL/R/P
Health and safety plan should be in line with national and international standards. Occupational health and safety measures should be identified and implemented. Necessary precautionary measures should be implemented in order to avoid and minimize risk of accidents (e.g. fire, flooding etc )
Ensure compliance with health and safety plan
APPENDIX 10
Cultural Resource & Recreation Areas
WEL ▼1780
APPENDIX 11
Listed Cultural Properties in Lower Svaneti
1
Historical, Cultural and Archeological Resources in
Lentekhi and Tsageri Districts
# Name Location Dated
Lentekhi District
1 Church “Macxvar” Village Bavari Medieval
2 Tower Buleshi Village Medieval
3
Gardaphkhadze Residential Complex
1. Tower
2. Residential house
Village Tekali N/A
4 Church “Zagaloti” Tekali Village surroundings XI-XII A.D.
5 Tower Lentekhi Medieval
6 The Charkvianis’ Tower Village Leusheri Medieval
7
Larashi – Dadiani’s Residential Complex
1. Tower
2. Castle
3. Other buildings
Village Leksura Medieval
8 St. George’s Church “Jgrag” Village Luji, cemetery Medieval
9 Tower Village Mami Medieval
10 Church “Matskhovari” (Church of the
Redeemer ) Village Mami, cemetery X-XI A.D.
11 St. George’s Church “Jgrag” Village Margvishi, cemetery Medieval
12 Residential Complex “Machubi” Village Makhashi Medieval
13 Tower “Moroldirad” Village Makhashi Medieval
14 Onianis’ Tower Village Mebetsi Medieval
15 Church Village Mele, cemetery Medieval
16 Onianis’ Tower Village Mele Medieval
17 Church Tarigzeli (Church of Archangel) Village Mutsdi, cemetery Medieval
18 Church Tarigzeli (Church of Archangel) Village Natsuli, cemetery Medieval
19 Church Tarigzeli (Church of Archangel) Village Sasashi, surroundings of “Sands” Medieval
20 St. George’s Church “Jgrag” Village Sakdari Medieval
21 Tower Village Tvibi Medieval
22 Church Tarigzeli (Church of Archangel) Village Tvibi surroundings X-XI A.D.
23 Church Tarigzeli (Church of Archangel) Village Phaki Medieval
24 Church Tarigzeli (Church of Archangel) Village Ghobi,
at the Tskheniskali River embankment Medieval
25 St. Mary Church Village Ghobi, cemetery Medieval
26 Church Tarigzeli (Church of Archangel) Village Shtvili Medieval
27 St. Mary Church “Lamaria” Village Chikhareshe, cemetery XIX A.D.
28 St. Mary Church “Lamaria” Village Chikhareshe, Dabishi District Medieval
29 Church Tarigzeli (Church of Archangel) Village Chukuli, cemetery Medieval
30 Siani Tower Village Chukuli, “Nakisheri” Medieval.
31 Church Village Chukuli Medieval
32 Church “Muchpa Village Chukuli XII-XIII A.D.
33 Church Tarigzeli (Church of Archangel) Village Chukuli X-XII A.D.
34 Church Village Kheria, Lamzagora IX-X A.D.
35 St. George’s Church “Jgrag” Village Zhakhunderi XI-XII A.D.
Tsageri District
36 Church Town Tsageri Medieval
37 Remnant of the “Shkhudala” Monastry Village Alpana, near the Lajanuri and Rioni
Rivers confluence Medieval
2
38 Gveso Complex Village Gveso IX-X A.D.
39 Sosilei Tower, Charkviani Tower Village Gveso surroundings Medieval
40 Remnants of the Tower Village Gveso, R. Tsvarianis’ premises Medieval
41 Wooden House “Oda” Village Gveso, M. Chikovanis’ premises XX A. D.
42 Church “Mtavarangelozi” (Church of
Archangel) Village Upper Aghvi, cemetery Medieval
43 St. George’s Church Village Upper Sairme, cemetery XIX A. D.
44 St. Mary Church Village Zogishi Medieval
45 “Zubi” Church Village Zubi, surroundings Medieval
46 Tower-Church “Dedaghvtisa” Village Tabori, mountain Medieval
47 Church Village Tabori VI A.D.
48 Isunderi Tower Village Isunderi Medieval
49 St. Mary Church Village Isunderi, cemetery XIX A. D.
50 Synagogue Village Lailashi XIX-XX A.D.
51 Church Village Lailashi Medieval
52 St. George’s Church Village Lailashi, cemetery XIX A.D.
53 Church “Amaghleba”
(Church of the Ascension) Village Lailashi 1859
54 Church of the Holy Trinity “Sameba” Village Makhura, cemetery XIX A. D.
55 St. George’s Church Village Nakuraleshi, cemetery XVII A. D.
56 Church Village Nakuraleshi Medieval
57 St. Mary Church Village Nasperi, cemetery XIX A. D.
58 Tower Village Nasperi,
G. Murtseladze’s premises Medieval
59 Goni Church of St. George Village Orkhvi, surroundings X A. D.
60 St. George’s Church Village Orkhvi XIX A. D.
61 Tower –Fortress “Qvatsikhe”,
“Qvarianis’ Tower” Village Orkhvi Medieval
62 Remnant of the St. George’s Church Village Okureshi, surroundings Medieval
63 Wooden House Village Okureshi,
K. Arjevanidze’s premises XIX A. D.
64 Church Village Okureshi Medieval
65 St. George’s Church Village Usakhelo, cemetery XIX A. D.
66 Remnant of the Dadeshqelianis’ Fortress Village Usakhelo, surroundings Medieval
67 St. George’s Church Village Utskheri, “Gudula” location Medieval
68 Remnant of St. Mary Church Village Utskheri Medieval
69 “Utskheri” Tower-Fortress Village Utskheri Medieval
70 St. Mary Church Village Lower Aghvi, cemetery XIX
71 Remnant of St. Mary Church Village Qorenashi, cemetery Medieval
72 Qorenishi Tower Village Qorenishi, J. Asatiani premises Medieval
73 “Dedaghvtisa” Church Village Ghu, Cemetery 1880
74 Muri Church Village Chkhuteli, surroundings Medieval
Source: Ministry of Culture of Georgia: Ministerial Orders #3/133 and #3/110(2006 and 2011)
USAID Hydropower Investment Promotion Project (USAID-HIPP)
Deloitte Consulting Overseas Projects - HIPP Tiflis Business Centre, 13th Floor
11 Apakidze Street Tbilisi 0171, Georgia