georgia transmission corporation (gtc) reliability initiatives gsu presentation september 2012

42
Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Upload: barrett-notley

Post on 22-Jan-2016

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Georgia Transmission Corporation (GTC)

Reliability Initiatives

GSU Presentation

September 2012

Page 2: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Douglas O. Maddox

• Manager – System Reliability• Started as distribution & lighting engineer • Manages a department of six engineers and

coop student• (1) Power Quality / Digital Fault Recorder (DFR) • (2) Clearance Mitigation staff• (1) Outage investigator • (1) Benchmarking and results reporting • (1) Trending and programs

Page 3: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

GTC Background

• Created from Oglethorpe Power Corporation (OPC) reorganization in 1997

• New smaller Board of Directors with outside directors

• Reliability is job one• Keep improving until we say stop• Continuous feedback on reliability • Measure, report, and benchmark data• Reduce frequency and duration of outages

Page 4: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

This Presentation

• Illustrates how GTC reliability improvement is built upon the technology of remote sensing, monitoring, and control equipment

• Explains how GTC fits in to the overall utility structure in Georgia

• IS NOT about preventing widespread blackouts or new FERC/ NERC ERO standards

Page 5: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Functions and types of Georgia’s electric utilities

Georgia Utilities Function Function Function

Generation Transmission Distribution

Cooperatives - 39 Oglethorpe Power

Georgia Transmission

Individual EMCs

Municipals ~ 48 MEAGPower MEAGPower Individual Cities

Investor Owned -Georgia Power

GPC GPC GPC

Cooperatives - 3 TVA TVA TVA

Page 6: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Georgia EMC Service Areas

Page 7: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Remote Sensing Equipment

• First generation of sensors was end-user notification – power problem or outage

• Equipment had no remote monitoring or control• Relays were sensors but had no remote status or control• Fuses and reclosers were down line sensors – no remote

status• Outage notification via postcard, letter, phone call, visit,

etc.• SCADA – supervisory control and data acquisition • AMI – automated metering infrastructure • Outage management systems - call in and tie to

Geographic Information Systems (GIS)• Facebook, twitter, web sites

Page 8: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Power Circuit Breakers

Gas Oil Vacuum

Page 9: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Electromechanical Relays

Page 10: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Fuses (Southern States)

Page 11: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Recloser (Joslyn)

Page 12: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Meters

Electromechanical Meter

AMI Meter

Page 13: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

SCADA

RTU Control Panel

Page 14: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Remote sensors - continued

• Electronic relays and Digital Fault Recorders (DFRs)• Fault indicators • Fault Analysis and Lightning Location (FALLS)

lightning data & weather data • Phasor measurement units (PMUs)• Line loading and monitoring• Substation monitors• Telecommunications

1. Phone lines

2. Satellite

3. Radio signals

Page 15: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

DFR (USI)

Page 16: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

SEL Relays

SEL-551

SEL-351S

SEL-587

Page 17: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

PMU (SEL)

SEL-351A (With PMU)

Page 18: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Line Loading Device (GridSense)

Page 19: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Substation Transformer Monitor (GridSense)

Page 20: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Fault Indicator (PDP)

Page 21: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

FALLS Lightning Study Map

Page 22: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 20110

5

10

15

20

25

30

35

23.17

15.61

19.41

15.06

17.29

13.20 13.64 11.77

10.1511.37 10.57 10.26 9.49

7.51

SAIDI TrendYearly SAIDI

5 Year Average

Trend (5 Yr Avg)

Min

ute

s O

f O

uta

ge

Tim

e P

er

Cu

sto

me

r

GOOD

Page 23: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012
Page 24: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012
Page 25: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

MAIFI

• One minute definition of sustained outage vs. momentary outage is < one minute

• Lightning normalized (Georgia Integrated Transmission System {ITS} standard)

• Found our ITS lines did not live up to stated Basic Insulation Level (BIL) levels of protection vs. stroke magnitude (older approach of 115 kV survives 30 kA strike)

• Electric Power Research Institute (EPRI) T- Flash program

• GTC standard 115 kV t/l design would have 3 momentary per year

Page 26: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Wins and Losses

• Results vary based on philosophy & location• Great results Metal Oxide Varistors (MOVs) for

Homeland –Macedonia Primary (3 per structure) from 8 to <1 momentary outage per year – only strikes >100 kA flashed the line

• Terrible results for Douglas – Stump Creek (Black) – distribution pattern of 3-1-1-1 did not work, nor does 3-0-0 work

• Early fault indicator success – then false alarms• Special 115 kV FI failed lab and field tests

Page 27: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

T/L Arresters

Page 28: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Standard GTC 115 MOV approach

• Most structures are single poles • Most structures have vertically mounted

phases• T-Flash predicts “O” outages per year with 3

MOV per pole• T- Flash predicts 0.16 outages per year with 2

MOV per pole• GTC generally will save one MOV per pole to

stretch MOV funds• Installation Pattern is top and bottom phase

Page 29: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Early Benchmarking

• 2003 trip to Florida Power and Light (FPL) for Georgia Power, GTC, and our control centers

• FPL = 4 min SAIDI • GTC = 15 min SAIDI

Differences

Looped lines – two way feeds

Redundant transformers

Intelligent fault detection and location

Page 30: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Sustained Outage Programs

• GTC study found 75% of SAIDI is switching & restoring good loads; 25% is restoration

• Completed motorizing substation line switches• Completed grounding switch replacements• Nearly completed converting GTC’s pole

mounted manually operated switches to remote control

• Extensive DFR upgrades, installations, & minis• Replace obsolete switches• Replace Silicon Carbide lightning arresters

Page 31: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Sustained Outage (continued)

• Split long circuits• Modernize relaying (SEL)• Replace older breakers• Replace older transformers • Add reliability criteria to alternative selection

for capacity and voltage solving solutions• Normally Open Point analysis • Clearance mitigation efforts

Page 32: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Unfinished Sustained Outage Programs

• ITS grounding switches to be replaced• Convert pole switches from manual to remote control• One directional fault indicators to be installed • Bidirectional fault indicators – testing phase • Replacements for old technology arresters, first

generation MOVs• Replace older, obsolete switches• On line transformer monitoring • Carrier relaying, tuners, traps• Real time DTF from DFR and SELs• Supporting GPC (ITS) 46 kV enhancement program

Page 33: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Clearance Mitigation

• 2003 time frame• 25% of SAIDI and SAIFI under abnormal

conditions - clearances• Both construction & maintenance• Extended clearances• Too many clearances• Local equipment not in good condition

Page 34: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Clearance Mitigation (continued)

• Combine maintenance work with construction• Combine line, sub, and metering work• Combine ITS and EMC work• Send report to EMCs daily• Minimize abnormal time & mobile time• Check lines and subs before going abnormal• Contingency plans

Page 35: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Digital Fault Recorders (DFRs)

• Replaced old Rochester Brand Units• New USI brand units are Sequence of Events (SOE) &

DFR combination units, windows based, with data accumulator able to be connected to home office server

• New APP brand units initially bought for smaller subs and less capacity

• Allow GPC access to server & emails• Populate real time distance to fault data into SCADA• Go beyond minimal federally required locations• Tie DFRs to FALLS data server

Page 36: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Relay Data Server

• GTC hosted server similar to DFRs• Allows access to relay data• Cyber Security considerations• Does send emails

Page 37: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Power Quality Program

• Investigate transmission problems• Assist EMC customers with investigations• Temporary meters• Permanent meters• PQ data server – GTC and EMC access• Consultant on standby• AMI systems susceptible to PQ issues

Page 38: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Power Quality Meters

Temporary Permanent

Page 39: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

MAIFI Improvements

• Overhead Ground Wire (OHGW) is installed on virtually all lines serving GTC loads

• Different workshops on lightning and grounding

• T/L MOVs• FALLS acquisition• ITS policy

Page 40: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

FALLS

• Obtained our own subscription• Review momentary outages down to 46 level• Send reports to EMC• Keep up with YTD results• Keep up with MOV effectiveness• Use in T-Flash• Use for MOV pattern selection

Page 41: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Remote Sensor Issues

• Cost• Reliability• Ability to communicate• Battery life• Telecom path availability, capacity, and cost • Ability to install and maintain on energized

lines

Page 42: Georgia Transmission Corporation (GTC) Reliability Initiatives GSU Presentation September 2012

Your Questions and comments?