geotechnical characterization of foundation preparation practices

4
  Proceedings o f Indian Geo technical Con ference  December 15-1 7, 2011, K ochi (Paper No.Q-077) GEOTECHNICAL CHARACTERIZATION OF FOUNDATION PREPARATION PRACTICES IN EARTH AND ROCK FILL DAM- A CASE STUDY Praveen Kumar Yadav,  DGM (FES), KOLDAM HEPP, NTPC Ltd, E-mail: [email protected]  Rama Krishna Adhikari, Manager (Geology), KOLDAM HEPP, NTPC Ltd,E-mail: ra [email protected]  Pratik Roy,  Sr. Geologist, KOLDAM HEPP, NTPC Ltd, E-mail: [email protected] ABSTRACT:  The Kol Dam Project (800MW), NTPC’s first voyage into hydroelectric power project under construction, a 167m high Earth and Rock fill dam across Satluj River, is situated in a Karstic terrain. Geotechnical characterization of foundation mainly depends upon the type of rock, frequency of discontinuities and structure to be built on that area. Surface  preparation included excavating overburden; surface cleaning, shaping the foundation surface with dental concrete; treating faults, shears, or weak zones; filling up of joints with cement mortar etc. Besides surface treatments curtain grouting and consolidation grouting were also provided as per geological condition of the area concerned for creating seepage barrier and strengthening the strata. This paper presents the different methods adopted to achieve safety and constructional advantage in foundation preparation in the Dam body of Kol Dam project.  INTRODUCTION Kol Dam (location 31°23’N, 76°52’E) in Bilaspur District, Himachal Pradesh, NTPC’s first voyage into hydro project is an Earth and rock fill Dam across Satluj, situated about 6 km upstream of Dehar Power House (Beas Satluj link project). Main structures of Kol Dam projects are two diversion tunnels of 14m finished diameter and 900 (appx.) length each, a 108.5m wide and 0.42 km long chute spillway and a surface  power house of 800(4x200) MW capacity. The Kol Dam  project has been basically designed as a run-of-the-river hydro power development scheme with advantage of additional storage for the first 30 years. The 167 m. high (above deepest foundation level at El 481) and 500 m. long (at crest) rock and gravel fill Kol Dam with impervious central clay core to provide a live storage of 90 million cum. (9000 ha. m.) between full reservoir level (FRL at El 642) and Minimum Draw Down Level (MDDL at El 636). This paper presents the different techniques/ practices adopted to achieve safety and constructional advantage in foundation preparation in Main Dam area of Kol Dam  project. BRIEF GEOLOGY OF THE PROJECT AREA The rocks belonging to Shali, Shimla, Sundernagar Groups and Mandi Darla volcanic constitute the area. The dolomite of Tatapani, Limestone of Sorgarwari (Shali Group) and  phyllites of Basantpur formation with basic intrusive are the major lithological units exposed at the locations of major components of the Kol Dam project (Sanjiv Kumar 2005-06). In addition two generations of terrace materials are also  present in the project area one is simple river borne terrace material composed of loose river borne materials like  boulders of Quartzite including the material coming from the rocks present near the dam site and the other one is terrace material composed of boulders, pebbles and gravel, essentially made of quartzite, limestone, dolomite and basic rock (all the rock materials that present outcrops near the dam site), in a sandy and highly cemented calcareous matrix. The rock encountered at the Dam foundation is Limestone, Dolomite and Limestone-Dolomite transition zone. Detailed geological mapping of the Main Dam foundation area has been carried out in 1:100 scale. Pink limestone unit (Sorgharwari Formation), transition zone and Upper dolomite unit (Tatapani Formation) with thin (1 to 10 cm thick) shale interbeds are exposed in the Dam foundation and abutments. The general trend of bedding joint recorded is N10 0 W- S10 0 E, which is nearly 20 0 askew to Dam axis, with 70-80 0 dip due southwest direction. Due to the disposition of bedding the transition zone crosses the core foundation from left to right abutment. The Limestone-Dolomite transition zone in the Dam base foundation & abutment carries numerous open  joint networks, solution cavities, sand pockets and small sinkholes. A number of erosional cavities formed partly by solution activities and may be by churning actions has also  been observed while doing the geological mapping. Two  principal families of stress relief joints have been observed along riverbanks near the dam site; both are striking parallel to the river, the first one consists of joints parallel to the abutments slope (dipping 30 to 70° towards the river) and the second one consists of joints, dipping perpendicularly to the valley dipping joints. The rock is affected by a minor joint  pattern (in a first approach, two main joint families). Both families are striking perpendicular to the bedding; the first one is dipping approximately 50-60° NW, and the other one is 1003

Upload: pramods8

Post on 03-Jun-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

8/12/2019 Geotechnical Characterization of Foundation Preparation Practices

http://slidepdf.com/reader/full/geotechnical-characterization-of-foundation-preparation-practices 1/4

 

 Proceedings of Indian Geotechnical Conference

 December 15-17, 2011, Kochi (Paper No.Q-077)

GEOTECHNICAL CHARACTERIZATION OF FOUNDATION PREPARATION PRACTICES

IN EARTH AND ROCK FILL DAM- A CASE STUDY 

Praveen Kumar Yadav, DGM (FES), KOLDAM HEPP, NTPC Ltd, E-mail: [email protected] Rama Krishna Adhikari, Manager (Geology), KOLDAM HEPP, NTPC Ltd,E-mail: [email protected] Pratik Roy, Sr. Geologist, KOLDAM HEPP, NTPC Ltd, E-mail: [email protected]

ABSTRACT: 

The Kol Dam Project (800MW), NTPC’s first voyage into hydroelectric power project under construction, a

167m high Earth and Rock fill dam across Satluj River, is situated in a Karstic terrain. Geotechnical characterization of

foundation mainly depends upon the type of rock, frequency of discontinuities and structure to be built on that area. Surface preparation included excavating overburden; surface cleaning, shaping the foundation surface with dental concrete; treating

faults, shears, or weak zones; filling up of joints with cement mortar etc. Besides surface treatments curtain grouting and

consolidation grouting were also provided as per geological condition of the area concerned for creating seepage barrier and

strengthening the strata. This paper presents the different methods adopted to achieve safety and constructional advantage in

foundation preparation in the Dam body of Kol Dam project. 

INTRODUCTION

Kol Dam (location 31°23’N, 76°52’E) in Bilaspur District,

Himachal Pradesh, NTPC’s first voyage into hydro project is

an Earth and rock fill Dam across Satluj, situated about 6 kmupstream of Dehar Power House (Beas Satluj link project).

Main structures of Kol Dam projects are two diversion

tunnels of 14m finished diameter and 900 (appx.) length each,

a 108.5m wide and 0.42 km long chute spillway and a surface power house of 800(4x200) MW capacity. The Kol Dam

 project has been basically designed as a run-of-the-river

hydro power development scheme with advantage of

additional storage for the first 30 years.

The 167 m. high (above deepest foundation level at El 481)

and 500 m. long (at crest) rock and gravel fill Kol Dam with

impervious central clay core to provide a live storage of 90million cum. (9000 ha. m.) between full reservoir level (FRL

at El 642) and Minimum Draw Down Level (MDDL at El

636). This paper presents the different techniques/ practicesadopted to achieve safety and constructional advantage in

foundation preparation in Main Dam area of Kol Dam

 project.

BRIEF GEOLOGY OF THE PROJECT AREA

The rocks belonging to Shali, Shimla, Sundernagar Groups

and Mandi Darla volcanic constitute the area. The dolomite ofTatapani, Limestone of Sorgarwari (Shali Group) and

 phyllites of Basantpur formation with basic intrusive are themajor lithological units exposed at the locations of major

components of the Kol Dam project (Sanjiv Kumar 2005-06).

In addition two generations of terrace materials are also

 present in the project area one is simple river borne terrace

material composed of loose river borne materials like

 boulders of Quartzite including the material coming from the

rocks present near the dam site and the other one is terrace

material composed of boulders, pebbles and gravel,

essentially made of quartzite, limestone, dolomite and basicrock (all the rock materials that present outcrops near the dam

site), in a sandy and highly cemented calcareous matrix. The

rock encountered at the Dam foundation is Limestone,

Dolomite and Limestone-Dolomite transition zone.

Detailed geological mapping of the Main Dam foundation

area has been carried out in 1:100 scale. Pink limestone unit

(Sorgharwari Formation), transition zone and Upper dolomiteunit (Tatapani Formation) with thin (1 to 10 cm thick) shale

interbeds are exposed in the Dam foundation and abutments.

The general trend of bedding joint recorded is N100W- S100E,

which is nearly 200 askew to Dam axis, with 70-800 dip duesouthwest direction. Due to the disposition of bedding the

transition zone crosses the core foundation from left to right

abutment. The Limestone-Dolomite transition zone in theDam base foundation & abutment carries numerous open

 joint networks, solution cavities, sand pockets and small

sinkholes. A number of erosional cavities formed partly by

solution activities and may be by churning actions has also

 been observed while doing the geological mapping. Two

 principal families of stress relief joints have been observed

along riverbanks near the dam site; both are striking parallelto the river, the first one consists of joints parallel to the

abutments slope (dipping 30 to 70° towards the river) and thesecond one consists of joints, dipping perpendicularly to the

valley dipping joints. The rock is affected by a minor joint

 pattern (in a first approach, two main joint families). Both

families are striking perpendicular to the bedding; the first

one is dipping approximately 50-60° NW, and the other one is

1003

8/12/2019 Geotechnical Characterization of Foundation Preparation Practices

http://slidepdf.com/reader/full/geotechnical-characterization-of-foundation-preparation-practices 2/4

 

 Praveen Kumar Yadav, Rama Krishna Adhikari & Pratik Roy

dipping about 50-60° SE. The broken surfaces usually present

a certain roughness. These joints can present an extensionranging from some dozen centimeters to some meters. Some

cavities (1 to 3m diameter) have also been surveyed during

the Geological mapping on both abutments.

FOUNDATION PREPARATION AT KOL DAMThe foundation preparation practices in Kol Dam Hydro

electric power project has been characterized into three

different categories such as Slope modifications, FoundationGrouting and Surface Foundation Treatment.

Slope Modifications To allow earth fill to be compacted and maintain positive pressure on the abutments, foundation surfaces in both

abutments in Main Dam Clay Core, in particular, has been

flattened to about 0.73:1 to 1.75:1(H:V)in Left abutmentwhile 0.87:1 to 4.45:1(H:V) in the Right abutment (Clay Core

Area) by excavation (NTPC-EDF 2002)(Fig. 1).

Fig.1 Slope modification to reduce differential settlement &cracking of core (Sanjiv Kumar 2005)

Foundation GroutingThe principal purpose of grouting is to fill openings in a

foundation and render it impervious to percolating water. It is

also used to improve the strength and elastic properties of the

foundation material into which it is injected. Themethodology of grouting given to the foundation materials as

a whole has been decided depending upon the available

geological formations and features in the near vicinity of Dam

site. Grouting with normal cement grout is also doubtfulvalue in rocks where permeability value results from a great

number of fine cracks. With normal cement grout it is not

 possible to seal cracks which have width much finer than

0.2mm. In Kol Dam as the carbonate sedimentary rock like

limestone and dolomite are inherited by very fine as well asopen joint networks different fillers/accelerators/admixtures

were incorporated in both curtain and consolidation groutingwith variable C:W ratios. The grout mix for all the grouting

operations in Kol Dam has been designed depending upon the

existing site geology. The grouting operation has been carriedout with a variety of grout mixes starting C/W ratio 0.35:1 to

0.6:1 with different admixtures like bentonite, accelerators

like micro silica etc depending upon the geology encountered.The spacing and the pattern of grout holes has been designed

 based on several test sections carried out on the basis of

acceptable permeability of the foundation and the nature of

the Dam. In the test sections different grout materials with

variable C/W ratio were also analyzed for suitability byobserving the performance in terms of viscosity, decantation

and compressive strength. The grout performance in terms of

lugeon value, viscosity, decantation, compressive strengthand ground upheaval were analyzed for achieving the design

criteria. The treatments provided as per encountered geology

has been found satisfactory even during the heavy monsoon.

In addition, as a measure of foundation safety in Kol Dam, 5no. of drainage galleries are also provided to drain off the

seepage water and thus reduce the uplift pressure in the

abutments which will act after the reservoir impounding.Foundation grouting adopted in Kol Dam are mainly in two

forms:

1. Curtain Grouting  In Kol Dam two rows of grout curtain with an average depthfrom the deepest level of dam foundation has been designed

(Fig. 3). The average depth of the grout curtain is around 70-

80m from 12 grouting Galleries (Fig.2). Two rows of separategrout curtain has also been provided in the U/S part of the

Main dam left bank clay core abutment (up to 30m from the

foundation) to provide curtain to cutoff/minimize seepage.

2. Consolidation/Blanket Grouting  It is being carried out in the Main Dam clay core abutmentsand in the foundation, for filling up the joints/cracks/crevices

etc. and there by making the foundation homogeneous. It

makes upper portions of the bedrock stronger and less pervious. In Kol dam it is usually restricted to the upper 6 to

12m.

The following observations can be drawn on the basis of

Drilling-Grouting records of Dam foundation in Kol Dam:1. The intrinsic permeability of the rock in the Main Dam

foundation appears to be low as inferred from the strata

encountered, drilling record & grout intake data ofconsolidation as well as curtain grouting and from the pre &

 post grout permeability test results (Sanjiv Kumar 2005-06,

07-08).

2. The overall grouting activities in the Dam foundationdepicts that the opening along joints, fractures and fissures is

more in the left abutment as compared with the rightabutment.

3. The concentration of open joint networks/finefissures/cavities are more in the near surface condition upto

an average depth of 6-10m as compared to the deeper depth in

general in both the abutments.

1004

8/12/2019 Geotechnical Characterization of Foundation Preparation Practices

http://slidepdf.com/reader/full/geotechnical-characterization-of-foundation-preparation-practices 3/4

 

Geotechnical characterization of foundation preparation practices in Earth and Rock fill Dam- A case study.

4. In addition, only some rare and little size (2-5 cm) solution

cavities or channels have been observed during drillingoperations or core logging all along the Dam foundations and

 below the Dam foundation Galleries. In conclusion, no real

evidence of large scale Karstic phenomena has been observedat Dam site.

Fig.2 Curtain grouting through Grouting Galleries beneath the Dam foundation (NTPC-EDF 2002)

Fig.3 Typical Curtain Grouting in Kol Dam (NTPC-EDF 2002)

Surface Foundation Treatment Foundation surface preparation practices in Kol Dam includes

excavating overburden; shaping the foundation surface withdental concrete; filling surface irregularities with slush grout

(usually a cement/water mixture poured in cracks) or dental

concrete (conventional concrete used to shape surfaces, fill

irregularities, and protect poor rock); providing dentaltreatments for the exposed faults, shears zones/seams, or

weak zones as directed by the site geologist prior to caulking

and contact grouting. As the Dam is located on Limestone-

Dolomite i.e in Karstic terrain the shear seams/weatheredzones/buried channels/cavities/surface springs were common

in the foundation/abutments. These zones are susceptible to

differential settlement as the in filled material within themajor open joins (>20cm)/shear seams are of different moduli

compared to the bed rock. So, special care has been taken

while doing the dental treatment all through the Dam

abutments in the Clay core and Filter area. Very often the

faults, shear seams or shattered zones met with after

excavation extend to such depths that It is impracticable to

clean them out entirely.

Stress concentrations may occur in the dam due to the presence of such low modulus zones. To minimize the build

up of stresses in the dam, a portion of the weak zone is

replaced by concrete. The procedure for reinforcing and

consolidating such weak geological features is frequentlycalled Dental Treatment.

The dental treatments adopted in Main Dam clay core as well

as in the filter area in Kol Dam are as follows (Fig. 4):

a. For Shear Zone/Clay Band  

all the material along its length should be scooped. Theexcavation depths (d) were decided by the site geologist by

the following formula:

d=3-4w, if w (width of the shear zone/clay band) > 20 cm;

then it is backfilled by concrete and contact grouted all along

the feature cross cutting it up to a depth 3-4m

1005