geotechnical investigation phase ii final … · sewpp sedimentation basin a & b improvements...
TRANSCRIPT
GEOTECHNICAL INVESTIGATION PHASE II FINAL DESIGN FOR ENGINEERING
SEWPP SEDIMENTATION BASIN A & B IMPROVEMENTS (TM1), FLOCCULATORS REHABILITATION BASINS (TM1), REHABILITATION OF
TRANSFER AND DISTRIBUTION PUMPS & MOTORS AND ON-CALL MISCELLANEOUS ENGINEERING SERVICES
WBS NO. S-000012-0028-3
THICKENED SLUDGE PUMP STATION NO. 2 AND SPARE PARTS BUILDING
Report No. 1140187501
Reported to:
CHESTER ENGINEERS, INC.
Houston, Texas
Reported by:
GEOTEST ENGINEERING, INC.
Houston, Texas
Date: October 10, 2013
Key Map Nos. 577 R
TABLE OF CONTENTS Page EXECUTIVE SUMMARY.............................................................................................. 1
1.0 INTRODUCTION
1.1 General ..................................................................................................... 4
1.2 Project Description ................................................................................... 4
1.3 Purpose and Scope ................................................................................... 4
2.0 FIELD EXPLORATION ...................................................................................... 6
3.0 LABORATORY TESTS...................................................................................... 8
4.0 GENERAL SUBSURFACE CONDITIONS ....................................................... 9
4.1 Thickened Sludge Pump Station No. 2 (Boring GB-1) ........................... 9
4.2 Parts Building (Boring GB-2) ................................................................. 10
4.3 Faults ........................................................................................................ 10
5.0 GEOTECHNICAL ENGINEERING RECOMMENDATIONS ......................... 11
5.1 General ..................................................................................................... 11
5.2 Thickened Sludge Pump Station No. 2 ................................................... 11
5.2.1 General Parameters ........................................................................ 11
5.2.2 Excavation Stability....................................................................... 11
5.2.3 Excavation Dewatering ................................................................. 13
5.2.4 Foundation Recommendations ...................................................... 14
5.3 Parts Building ........................................................................................... 15
5.3.1 Foundation Type, Depth and Allowable Bearing Pressure ........... 15
5.3.2 Foundation Settlement ................................................................... 16
5.3.3 Site Preparation and Structural Fill Requirements ........................ 16
5.3.4 Building Pad .................................................................................. 17
5.3.5 Floor Slabs ..................................................................................... 17
5.3.6 Landscaping ................................................................................... 17
5.3.7 Surface Drainage ........................................................................... 17
6.0 CONSTRUCTION CONSIDERATIONS ........................................................... 18
7.0 PROVISIONS ...................................................................................................... 19
ILLUSTRATIONS Figure
Vicinity Map ................................................................................................................. 1
Plan of Borings ............................................................................................................. 2
Boring Log Profile ........................................................................................................ 3
Symbols and Abbreviations Used on Boring Log Profile ............................................. 4
Excavation Support Earth Pressure ............................................................................... 5.1 and 5.2
Stability of Bottom for Braced Cut ............................................................................... 6
Lateral Earth Pressure Diagram for Permanent Wall .................................................... 7.1 and 7.2
Uplift Pressure and Resistance ...................................................................................... 8
TABLE
Table Geotechnical Design Parameter Summary ............................................................ 1
APPENDIX A
Figure
Log of Borings from this study ............................................................................. A-1 and A-2
Symbols and Terms Used on Boring Logs............................................................ A-3
Piezometer Installation Report .............................................................................. A-4
APPENDIX B
Figure
Summary of Laboratory Tests ............................................................................... B-1 and B-2
Grain Size Distribution Curves ............................................................................. B-3
Geotest Engineering, Inc. Report No. 1140187501 City of Houston Southeast Water Purification Plant Improvements October 10, 2013 Thickened Sludge Pump Station No. 2 and Spare Parts Building WBS No. S-000012-0028-3, Houston, Texas
1
EXECUTIVE SUMMARY
A geotechnical investigation was conducted in connection with the design and construction
of the Thickened Sludge Pump Station (TSPS) No. 2 and parts building at Southeast Water
Purification Plant in Houston, Texas. The Thickened Sludge Pump Station No. 2 is approximately
27 feet x 27 feet in plan dimension. The bottom of the TSPS #2 will be placed at 22-foot deep (El.
9.50). The parts building is a one-story masonry or precast concrete building with an approximate
plan dimension of 50 feet x 30 feet. It is understood that a 10-ton bridge crane will be configured in
the building with an eave height of about 25 to 30 feet.
This study included drilling and sampling one (1) 45-foot deep boring (GB-1) for TSPS #2
and one (1) 25-foot deep boring (GB-2) for the parts building, performing laboratory tests,
performing engineering analyses and preparing a geotechnical report.
The principal findings and conclusions developed from this investigation are summarized
as follows:
• Based on the available information, the nearest known surface fault is Library Fault and
is located approximately 2.5 miles south of the project site.
• The boring GB-2 was drilled in the existing concrete pavement. The existing pavement
as encountered at boring GB-2 consists of 9.375 inches of concrete over 2 inches of lime
stabilized clay and gravel mix. The boring GB-1 was drilled in the grass area.
• The subsurface conditions are given below.
Thickened Sludge Pump Station No. 2 (Boring GB-1) : The subsurface soils below the
existing grade, as encountered in boring GB-1, consist of medium stiff to hard gray,
yellowish brown and reddish brown and gray Fat Clay, Lean Clay and Lean Clay with
sand to a depth of 45 feet, the termination depth of the boring. A layer of medium dense
silty sand was encountered between the depths of 16 and 18 feet. Fill material
Geotest Engineering, Inc. Report No. 1140187501 City of Houston Southeast Water Purification Plant Improvements October 10, 2013 Thickened Sludge Pump Station No. 2 and Spare Parts Building WBS No. S-000012-0028-3, Houston, Texas
2
consisting of hard dark gray lean clay with sand and grass roots was encountered to a
depth of 2 feet.
Parts Building (Boring GB-2): The subsurface soils below the existing pavement, as
encountered in boring GB-2, consist of soft to very stiff gray and yellowish brown
Sandy Lean Clay to a depth of 6 feet. The sandy lean clay is underlain by loose to
medium dense silty sand to a depth of 25 feet, the termination depth of the boring.
• Free water was first encountered at depth of 16.0 feet in boring GB-1 and 6 feet in
boring GB-2. The water level, measured 15 minutes after water was first encountered,
was at a depth of about 9.7 feet in boring GB-1 and 4 feet in boring GB-2. The
groundwater was measured at a depth of about 6.4 feet in piezometer GB-1P on August
13, 2013.
• All excavation operations should be carried out in accordance with OSHA standards and
the City of Houston Standard Specifications.
• In general, excavation and backfill for utilities should be designed and constructed in
accordance with City of Houston Standard Specification No. 02317.
• Based on the soil conditions revealed by the boring GB-1, the mat foundation for
supporting the thickened sludge pump station placed at a depth of 22 feet (El. 9.5 feet) (into
very stiff fat clay) may be designed for an allowable (net) bearing pressure of 6,000 psf for
total loads. These allowable bearing pressures include a safety factor of 2.0. The above
recommendations assume that the final bearing surfaces consist of undisturbed natural soils
and that underlying semi-transmissive zones are properly pressure-relieved and stable
undisturbed bearing surfaces are attained.
In view of soft soils encountered at shallow depth (4 to 6 feet) in boring GB-2, shallow
foundations are not recommended for supporting the parts building. The proposed parts
Geotest Engineering, Inc. Report No. 1140187501 City of Houston Southeast Water Purification Plant Improvements October 10, 2013 Thickened Sludge Pump Station No. 2 and Spare Parts Building WBS No. S-000012-0028-3, Houston, Texas
3
building foundation can be supported on (straight) drilled footings (shafts). Drilled
footings should be placed at a depth of at least 8 feet and proportioned for an allowable
bearing pressure of 3,000 psf for total dead and sustained loads or 2,000 psf for dead and
sustained live loads, whichever results in a larger footing. These allowable bearing
pressures contain safety factors of 2 for total load and 3 for sustained load conditions.
• Construction considerations are included in Section 6.0 of this report.
Geotest Engineering, Inc. Report No. 1140187501 City of Houston Southeast Water Purification Plant Improvements October 10, 2013 Thickened Sludge Pump Station No. 2 and Spare Parts Building WBS No. S-000012-0028-3, Houston, Texas
4
1.0 INTRODUCTION
1.1 General A geotechnical investigation was conducted in connection with the design and construction
of the Thickened Sludge Pump Station (TSPS) No. 2 and parts building at Southeast Water
Purification Plant in Houston, Texas.
1.2 Project Description
The Thickened Sludge Pump Station No. 2 is approximately 27 feet x 27 feet in plan
dimension. The bottom of the TSPS #2 will be placed at a depth of 22-foot deep (El. 9.50). The
parts building is a one-story masonry or precast concrete building with an approximate plan
dimension of 50 feet x 30 feet. It is understood that a 10-ton bridge crane will be configured in the
building with an eave height of about 25 to 30 feet. A Vicinity Map is shown on Figure 1.
1.3 Purpose and Scope
The purposes of this investigation were to explore the subsurface conditions at the proposed
site and to develop geotechnical recommendations pertinent to the design and construction of the
proposed thickened Sludge Pump Station No. 2 and parts building. The scope of work consists of
the following tasks:
1. drilling and sampling one (1) 45-foot boring for the TSPS location and one (1) 25-foot
boring for the parts building;
2. performing laboratory tests to determine the physical and engineering properties of the
subsurface soils;
3. performing engineering analyses to develop geotechnical recommendations for the
proposed TSPS #2 and parts building foundation, groundwater control, uplift
Geotest Engineering, Inc. Report No. 1140187501 City of Houston Southeast Water Purification Plant Improvements October 10, 2013 Thickened Sludge Pump Station No. 2 and Spare Parts Building WBS No. S-000012-0028-3, Houston, Texas
5
resistance, pavement section and subgrade stabilization and construction
considerations; and
4. preparation of a geotechnical report including field and laboratory data and engineering
recommendations.
Geotest Engineering, Inc. Report No. 1140187501 City of Houston Southeast Water Purification Plant Improvements October 10, 2013 Thickened Sludge Pump Station No. 2 and Spare Parts Building WBS No. S-000012-0028-3, Houston, Texas
6
2.0 FIELD EXPLORATION
Subsurface conditions were explored by drilling 2 soil borings, designated as GB-1 and
GB-2. Boring GB-1 was drilled for the Proposed Thickened Sludge Pump Station No. 2 to a depth
of 45 feet and boring GB-2 was drilled for the new parts building to a depth of 25 feet. All the
borings were drilled with a truck-mounted rotary drilling rig. The approximate locations of borings
are shown on Figure 2, Plan of Borings.
Samples were obtained continuously to 45 feet for boring GB-1 and 20-foot depth and at 5-
foot intervals thereafter for boring GB-2. In general, samples of cohesive soils were obtained with a
3-inch diameter thin-walled tube sampler in accordance with ASTM D1587 and samples of granular
soils were obtained with a 2-inch diameter split-barrel sampler in general accordance with ASTM
Method D 1586. Each sample was removed from the sampler in the field, carefully examined and
logged by an experienced soils technician. Suitable portions of each sample were sealed and
packaged for transportation to Geotest's laboratory. The shear strength of cohesive soil samples was
estimated by use of a calibrated pocket penetrometer in the field. Driving resistances for the split-
barrel sampler were recorded as "Blows per Foot" on the boring logs. All the borings, except the
ones converted to piezometers, were grouted with cement-bentonite grout after completion of drilling
and obtaining water level measurements.
Detailed descriptions of the soils encountered in the borings are given on the boring logs
presented on Figures A-1 and A-2 in Appendix A. A key to the symbols and terms used on the
boring logs is given on Figure A-3 in Appendix A.
During the field investigation, a piezometer was installed in the open borehole of boring
GB-1. The location of the piezometer, designated as GB-1P is shown on Figure 2, Plan of Borings.
The piezometer installation report showing the details of the construction of the piezometer is
provided on Figure A-4 in Appendix A.
Geotest Engineering, Inc. Report No. 1140187501 City of Houston Southeast Water Purification Plant Improvements October 10, 2013 Thickened Sludge Pump Station No. 2 and Spare Parts Building WBS No. S-000012-0028-3, Houston, Texas
7
Groundwater level observations were made at each boring location during field investigation.
The results of these observations are noted on the boring logs.
Geotest Engineering, Inc. Report No. 1140187501 City of Houston Southeast Water Purification Plant Improvements October 10, 2013 Thickened Sludge Pump Station No. 2 and Spare Parts Building WBS No. S-000012-0028-3, Houston, Texas
8
3.0 LABORATORY TESTS
The laboratory testing program was designed to evaluate the pertinent physical properties and
shear strength characteristics of the subsurface soils. Classification tests were performed on selected
samples to aid in soil classification. All geotechnical tests were performed in accordance with
appropriate ASTM procedures.
The undrained shear strengths of selected cohesive samples were estimated by unconsolidated
undrained (UU) triaxial compression (ASTM D2850) tests. The results of UU triaxial compression
tests are plotted on the boring logs as solid squares. Estimated shear strengths of the cohesive
samples were also evaluated in the field with a calibrated hand penetrometer and also in the
laboratory with a Torvane. The shear strength values obtained from the penetrometer and Torvane
are plotted on the boring logs as open circles and triangles, respectively.
Water content and dry unit weight of soil samples were determined as a part of the UU
triaxial compression tests. Water content determinations (ASTM D2216) were also made on all
other samples to define the moisture profile at the boring locations. Liquid and plastic limit (ASTM
D4318) tests were performed on appropriate samples. The percent passing sieve No. 200 (ASTM
D1140) were performed for selected samples. The results of all the tests are plotted or summarized
on the boring logs presented on Figures A-1 and A-2.
Geotest Engineering, Inc. Report No. 1140187501 City of Houston Southeast Water Purification Plant Improvements October 10, 2013 Thickened Sludge Pump Station No. 2 and Spare Parts Building WBS No. S-000012-0028-3, Houston, Texas
9
4.0 GENERAL SUBSURFACE CONDITIONS
As revealed by the boring logs, the subsurface soils at each proposed improvement are
described below.
4.1 Thickened Sludge Pump Station No. 2 (Boring GB-1)
Depth Below Ground Surface, ft Description
0 – 2 Fill: hard dark gray lean clay with sand calcareous
and ferrous nodules
2 – 12 Very stiff to hard gray Lean Clay (CL) with sand,
calcareous and ferrous nodules
12 – 16 Stiff brown Lean Clay (CL) with silt seams
16 – 18 Medium dense brown Silty Sand (SM)
18 – 45 Very stiff to hard reddish brown and gray Fat Clay
(CH) with ferrous nodules
The Fat Clay soils are of very high plasticity with liquid limits ranging from 74 to 98 and
plasticity indices ranging from 64 to 47. The Lean Clay and Lean Clay with sand is of medium
plasticity with liquid limits ranging from 28 to 38 and plasticity indices ranging from 10 and 20. The
fines content (passing No. 200 sieve) of Fat Clay ranged from 93 to 100 percent. The fines content
of Lean Clay and Lean Clay with sand ranged from 76 to 91 percent. The fines content of Silty Sand
is about 47 percent.
Free water was first encountered at 16 feet during drilling and measured at 7.3 feet at 15
minutes after water was first encountered. The water level measured in piezometer was measured at
depth of about 6.4 feet on August 13, 2013. However, groundwater levels can be expected to vary
seasonally with changes in precipitation, nearby subsurface construction activities, and change in
area drainage.
Geotest Engineering, Inc. Report No. 1140187501 City of Houston Southeast Water Purification Plant Improvements October 10, 2013 Thickened Sludge Pump Station No. 2 and Spare Parts Building WBS No. S-000012-0028-3, Houston, Texas
10
Piezometer was abandoned in place after taking the final water level measurements. The
piezometer abandonment report is presented in Appendix C.
4.2 Parts Building (Boring GB-2)
Depth Below Ground Surface, ft Description
0 – 6 Soft to very stiff gray Sandy Lean Clay (CL) with sand seams
6 – 25 Loose to medium dense gray Silty Sand (SM)
The Sandy Lean Clay soil is of high plasticity with liquid limits ranging from 41 to 43 and
plasticity indices ranging from 22 to 23. The fines content (percent passing No. 200 sieve) of Sandy
Lean Clay is about 61 percent. The fines content of Silty Sand ranges from 20 to 24 percent.
Free water was first encountered at 6 feet during drilling and measured at 4 feet at 15 minutes
after water was first encountered. However, groundwater levels can be expected to vary seasonally
with changes in precipitation, nearby subsurface construction activities, and change in area drainage.
4.3 Faults
The available library information consisted of U.S. Geological Survey and NASA maps, open
file reports, and information contained in our files relating to geologic faults in this area. Based on
this available information no known faults exist within the project site and the nearest known surface
fault is Library Fault and is located approximately 2.5 miles south of the project site.
Geotest Engineering, Inc. Report No. 1140187501 City of Houston Southeast Water Purification Plant Improvements October 10, 2013 Thickened Sludge Pump Station No. 2 and Spare Parts Building WBS No. S-000012-0028-3, Houston, Texas
11
5.0 GEOTECHNICAL ENGINEERING RECOMMENDATIONS
5.1 General
The Thickened Sludge Pump Station No. 2 is approximately 27 feet x 27 feet in plan
dimension. The bottom of the TSPS #2 will be placed at a depth of 22 feet (El. 9.50). The parts
building is a one-story masonry or precast concrete building with an approximate plan dimension of
50 feet x 30 feet. It is understood that a 10-ton bridge crane will be configured in the building with
an eave height of about 25 to 30 feet.
5.2 Thickened Sludge Pump Station No. 2
The Thickened Sludge Pump Station No. 2 is approximately 27 feet x 27 feet in plan
dimension. The bottom of the TSPS #2 will be placed at 22-foot deep (El. 9.50).
5.2.1 Geotechnical Parameters. Based on the soil conditions revealed by the boring GB-1,
geotechnical parameters were developed for the design of open excavation for the thickened sludge
pump station. The design parameters are provided in Table 2. For design, the groundwater level
should be assumed to exist at the ground surface.
5.2.2 Excavation Stability. The open excavation may be shored or laid back to a stable slope
or supported by some other equivalent means used to provide safety for workers and adjacent
structures, if any. The excavating operations should be in accordance with OSHA Standards, OSHA
2207, Subpart P, latest revision and the City of Houston Standard Specification.
• Excavation Shallower Than 5 Feet - Excavations that are less than 5 feet deep (critical
height) should be effectively protected when an indication of dangerous ground movement is
anticipated.
Geotest Engineering, Inc. Report No. 1140187501 City of Houston Southeast Water Purification Plant Improvements October 10, 2013 Thickened Sludge Pump Station No. 2 and Spare Parts Building WBS No. S-000012-0028-3, Houston, Texas
12
• Excavations Deeper Than 5 Feet. For the excavation deeper than 5 feet, such as 22 feet in
this case, the excavation should be shored, sheeted, braced, or supported by some other equivalent
means of protection such that workers are not exposed to moving ground or cave-ins. The shoring
should be in accordance with OSHA requirements.
A soil retention system is recommended and essential for this project. Whichever system is
used should remain in place until backfilling is within 5 feet of the ground surface. Based on the soil
conditions and proposed excavation 22-foot deep, the following alternatives can be considered for
soil retention.
1. Temporary sheet piles
2. H-piles with wooden lagging
Sheet piles may be driven or vibrated in place.
The following items provide design criteria for excavation stability.
(i) OSHA Soil Type. Based on the soil conditions revealed by the geotechnical borings,
OSHA’s soil type “C” should be used for the design of a shoring system. For shoring
deeper than 20 feet, an engineering evaluation is required.
(ii) Excavation Support Earth Pressure. Lateral earth pressure diagram was developed based
on the subsurface conditions indicated by our field and laboratory investigations. The
earth pressure diagrams developed for excavation support are presented on Figures 5.1
and 5.2. The pressure diagram can be used for the design of temporary excavation
bracing. The effects of any surcharge loads at the ground surface should be added to the
computed lateral earth pressures. A surcharge load, q, will typically result in a lateral
load equal to 0.5q. The computation of the equivalent fluid pressure assumes that
groundwater level is at ground surface, since these conditions may exist after a heavy rain
Geotest Engineering, Inc. Report No. 1140187501 City of Houston Southeast Water Purification Plant Improvements October 10, 2013 Thickened Sludge Pump Station No. 2 and Spare Parts Building WBS No. S-000012-0028-3, Houston, Texas
13
or flooding. For the design of the shoring or bracing, for resisting lateral earth pressures
can be based on an equivalent fluid pressure of 96 psf.
If H-piles with wooden lagging are planned, the piles should penetrate at least 10 feet below
the bottom of the excavation with a bracing at about 6 feet from the ground surface.
(iii) Bottom Stability. In braced cuts, if tight sheeting is terminated at the base of the cut, the
bottom of the excavation can become unstable under certain conditions. The stability of the bottom
of the excavation is governed by the shear strength of the soils and by the differential hydrostatic
head. For cuts in cohesive soils (such as lean clay and lean clay with sand), stability of the bottom
may be evaluated in accordance with the procedure outlined in Figure 6. In cohesionless soils (such
as silty sand encountered in borings between depths of 16 and 18 feet), the excavation should be
done after dewatering or installing sheet pile cut off wall to avoid bottom stability problems.
5.2.3 Excavation Dewatering. Excavations for the proposed TSPS #2 structure will
encounter groundwater seepage to varying degrees depending upon groundwater conditions at the
time of construction. In cohesive soils (such as lean clay, and sandy lean clay), groundwater may be
managed by collection in excavation bottom sumps for pumped disposal. The trench excavation up
to 22 feet will be formed in cohesive soils with water bearing sands (approximately 2-foot thick) near
the bottom of the excavation. The groundwater may be controlled by using eductor well system if
can be successfully lowered 5 feet below the excavation bottom otherwise or alternatively installing
continuous interlock (water tight) sheet piling with trench bottom sumps for pumped disposal.
It is recommended that the actual groundwater conditions be verified at the time of
construction and that groundwater control be performed in general accordance with City of Houston
Standard Specifications, Section 01578, “Control of Ground Water and Surface Water.”
Geotest Engineering, Inc. Report No. 1140187501 City of Houston Southeast Water Purification Plant Improvements October 10, 2013 Thickened Sludge Pump Station No. 2 and Spare Parts Building WBS No. S-000012-0028-3, Houston, Texas
14
5.2.4 Foundation Recommendations
5.2.4.1 Foundation Conditions. Foundation conditions were explored by boring GB-1.
Based on the soil conditions revealed by this boring, the bottom of the TSPS #2 will be in very stiff
Fat Clay.
5.2.4.2 Foundation Design Recommendations. The following items provide
recommendations and design criteria for construction of the TSPS #2 structure.
• Allowable Bearing Pressures. Based on the soil conditions, the mat foundation for
supporting the thickened sludge pump station placed at a depth of 22 feet (El. 9.5 feet)
(into very stiff fat clay) may be designed for an allowable (net) bearing pressure of
6,000 psf for total loads. These allowable bearing pressures include a safety factor of
2.0. The above recommendations assume that the final bearing surfaces consist of
undisturbed natural soils and that underlying semi-transmissive zones are properly
pressure-relieved and stable undisturbed bearing surfaces are attained
Based on mat foundation depths of 22 feet (bottom of footing into very stiff clay) the
modulus of subgrade reaction, K will be 50 pci.
• Lateral Earth Pressure. The pressure diagrams presented on Figures 5.1 and 5.2 can
be used for the design of braced excavation. The lateral earth pressure diagrams
presented on Figures 7.1 and 7.2 are applicable for the design of the permanent walls.
• Hydrostatic Uplift Resistance. Structures extending below the groundwater level
should be designed to resist uplift pressure resulting from excess piezometric head.
Design uplift pressures should be computed based on the assumption that the water
table is at ground surface. To resist the hydrostatic uplift at the bottom of the
structure, one of the following sources of resistance can be utilized in each of the
designs.
Geotest Engineering, Inc. Report No. 1140187501 City of Houston Southeast Water Purification Plant Improvements October 10, 2013 Thickened Sludge Pump Station No. 2 and Spare Parts Building WBS No. S-000012-0028-3, Houston, Texas
15
a. Dead weight of structure,
b. Weight of soil above base extensions plus weight of structure, or
c. Soil-wall friction plus dead weight of structure.
The uplift force and resistance to uplift should be computed as detailed on Figure 8.
In determining the configuration and dimensions of the structure using one of the
approaches presented on Figure 8, the following factors of safety are recommended.
a. Dead weight of concrete structure, Sf1 = 1.10,
b. Weight of soil (backfill) above base extension, Sf2 = 1.5, and
c. Soil-wall friction, Sf3 = 3.0.
Friction resistance should be discounted for the upper 5 feet, since this zone is
affected by seasonal moisture changes.
5.3 Parts Building
The parts building is a one-story masonry or precast concrete building with an approximate
plan dimension of 50 feet x 30 feet. It is understood that a 10-ton bridge crane will be configured in
the building with an eave height of about 25 to 30 feet.
5.3.1 Foundation Type, Depth and Allowable Bearing Pressure. As revealed by boring GB-2,
the surficial soils consist of soft to medium stiff Sandy Lean Clay. Hence, the slab-on-grade or
shallow foundations are not recommended for the crane and building foundation. The proposed
building can be supported on (straight) drilled footings (shaft). Drilled footings should be placed at a
depth of at least 8 feet and proportioned for an allowable bearing pressure of 3,000 psf for total dead
and sustained loads or 2,000 psf for dead and sustained live loads, whichever results in a larger
footing. These allowable bearing pressures contain safety factors of 2 for total load and 3 for
sustained load conditions.
Geotest Engineering, Inc. Report No. 1140187501 City of Houston Southeast Water Purification Plant Improvements October 10, 2013 Thickened Sludge Pump Station No. 2 and Spare Parts Building WBS No. S-000012-0028-3, Houston, Texas
16
Pier reinforcement should be checked to ensure that design provides sufficient resistance to
tensile loads imposed due to swell of near surface soils. Reinforcement should be sufficient to resist
a tensile load of 19d kips, where “d” is the diameter of the shaft, in feet.
Lateral Resistance
The lateral capacity for designing the drilled shafts (straight shafts) for a shaft depth of 8 feet are
given below.
Shaft Diameter, ft Lateral Capacity, kips
3 9
5 15
The above mentioned lateral capacity includes a factor of safety of 2. The upper 3 feet of soil is
neglected due to moisture variation zone.
5.3.2 Foundation Settlement. Depending upon the footing size and magnitude of the
sustained footing pressure, some total and differential settlements should be anticipated due to
consolidation of the foundation soils. Although detailed settlement analysis was not within the scope
of this study, it is believed that the footings designed in accordance with the above recommendations
should experience small acceptable settlements. Small differential settlement may also result from
variation in subsurface conditions across the site, loading conditions and construction procedures.
5.3.3 Site Preparation and Structural Fill Requirements. The sites should be cleared,
grubbed, and stripped of all organic material, soft soils and foreign material from the building and
paved areas.
Structural fill required to raise the grade or backfill grub holes should consist of lean clay or
sandy lean clay with a liquid limit less than 40 and a plasticity index between 10 and 20. The
Geotest Engineering, Inc. Report No. 1140187501 City of Houston Southeast Water Purification Plant Improvements October 10, 2013 Thickened Sludge Pump Station No. 2 and Spare Parts Building WBS No. S-000012-0028-3, Houston, Texas
17
structural fill material shall be placed in loose lifts not exceeding 8 inches and should be compacted
to 95 percent of the maximum dry density as determined by ASTM D 698. The moisture content of
structural fill should be one percent dry and two percent wet of the optimum moisture content as
determined by the Standard Proctor Test. The on-site sandy lean clays after removal of all foreign
material, if it meets the structural fill requirement can be used as structural fill.
5.3.4 Building Pad. Based on the plasticity characteristics and the physical state of the
subgrade soils at the sites, the shallow surface soils possess low to moderate potential for swelling and
shrinking. During construction, it is essential that the finished surface be protected from excessive
drying. Any material required to raise the grade should meet the criteria described in Section 5.3.3
“Site Preparation and Structural Fill Requirements.” The structural fill, if needed, should extend at
least 5 feet beyond the slab area.
5.3.5 Floor Slabs. Due to low to moderate potential for swelling and shrinkage of the surficial
soils, the floor slabs should be supported on 18 inches of inactive fill material. This inactive material
should be select structural fill meeting the criteria described in the previous section, “Site Preparation
and Structural Fill Requirements.” A modulus of subgrade reaction of 50 pci can be used for design
of floor slabs.
5.3.6 Landscaping. It is recommended that no large trees exist or be planted within 15 feet of
the structure and preferably within the mature drip line. Any flower beds or open lawn areas, if provided
near the structure areas, should have a good sprinkler system to minimize the moisture variations in the
subsurface soils. It is imperative that the sprinkler systems installed in the proximity of structures be
free from leaks, which could provide a continuous source of moisture and promote differential swelling
of the near surface soils.
5.3.7 Surface Drainage. The following drainage precautions should be observed during
construction and maintained at all times after the structure has been completed.
Geotest Engineering, Inc. Report No. 1140187501 City of Houston Southeast Water Purification Plant Improvements October 10, 2013 Thickened Sludge Pump Station No. 2 and Spare Parts Building WBS No. S-000012-0028-3, Houston, Texas
18
1. Backfill around the structure should be moistened and compacted to at least 90
percent of Standard Proctor Density (ASTM D 698).
2. The ground surface surrounding the exterior of the structure should be sloped to drain
away from the structure in all directions.
3. Roof downspouts and drains should discharge well beyond the limits of the
foundation backfill.
Geotest Engineering, Inc. Report No. 1140187501 City of Houston Southeast Water Purification Plant Improvements October 10, 2013 Thickened Sludge Pump Station No. 2 and Spare Parts Building WBS No. S-000012-0028-3, Houston, Texas
19
6.0 CONSTRUCTION CONSIDERATIONS
Thickened Sludge Pump Station No. 2:
It is understood that the preliminary plans call for the thickened sludge pump station to be
constructed by cast-in-place method.
Excavation of Pump Station after Dewatering (Dry Method). Instability of the excavation
bottom can be attenuated by dewatering the transmissive silty sand. An appropriate dewatering
system should be installed outside the perimeter of the excavation area. The dewatering system
should maintain the groundwater level at least 5 feet below the proposed bottom of the TSPS
throughout the period of the excavation and construction of the structural slab.
Parts Building:
It is recommended that the footing excavation be inspected by a geotechnical engineer or
experienced engineering technician or an architect's or owner's representative prior to placing steel
and concrete. The excavation should be checked to verify that (a) the footing has been constructed to
the specified dimensions and is placed at the correct depth and into the appropriate stratum with
adequate bearing capacity as recommended in this report, (b) the loose cuttings, and any soft-
compressible materials have been removed from the bottom of the excavation, and (c) placement of
concrete should be accomplished as soon as possible to prevent changes in the state of stress and
caving of the foundation soils. A seal slab of lean concrete should be placed, if concrete placement
is delayed for more than 6 hours after excavation or sooner if rain is forecasted. No footing concrete
should be placed without the prior approval of the Project's Engineer, Architect or Owner's
Representative.
Geotest Engineering, Inc. Report No. 1140187501 City of Houston Southeast Water Purification Plant Improvements October 10, 2013 Thickened Sludge Pump Station No. 2 and Spare Parts Building WBS No. S-000012-0028-3, Houston, Texas
20
7.0 PROVISIONS
The subsurface conditions and the design information contained in this report are based on
the test borings made at the time of drilling at specific locations. However, some variation in soil
conditions may occur between the boring locations. Should any subsurface conditions other than
those described in our boring logs be encountered, Geotest should be immediately notified so that
further investigation and supplemental recommendations can be provided. The depth of the
groundwater level can be expected to vary with environmental variations such as frequency and
magnitude of rainfall.
The analysis and recommendations submitted in this report are based upon the data obtained
from subsurface explorations made at the time test borings were drilled at specific locations and the
results of laboratory tests on selected soil samples from the test borings. The stratification lines on
the log of borings represent the approximate boundaries between soil types, however, the transition
between soil types may be more gradual than depicted.
This report has been prepared for the exclusive use of Chester Engineers, Inc. specifically for
the Phase II final design and construction of Southeast Water Purification Plant in Houston, Texas.
This report shall not be reproduced in whole or part without written permission of Geotest
Engineering, Inc., or Chester Engineers, Inc. or City of Houston.