gerald j. carey gardens brooklyn, ny · carey gardens $ 86,711,000 total # 4 682 1,681 8.37 8 46 23...

2
GERALD J. CAREY GARDENS Brooklyn, NY 2 1 3 W 24TH STREET W 23RD STREET W 22ND STREET MERMAID AVENUE SURF AVENUE NORTH PROPOSED ELEVATED CENTRAL HEATING PLANT BUILDING, WITH PARKING BELOW NEW GENERATOR ADDITION AT BUILDING 3 SITE BOUNDARY SITE BOUNDARY SITE BOUNDARY EXISTING PARKING EXISTING BALL COURT EXISTING BALL COURT EXISTING PARKING EXISTING PARKING PROPOSED EMERGENCY GENERATORS EXISTING BUILDINGS PROPOSED BOILER HALL PROPOSED MECHANICAL ADDITIONS PROPOSED MECHANICAL ADDITION AT BUILDING 2 EXISTING COMMUNITY CENTER IMAGE “A” IMAGE “C” IMAGE “A” - PROPOSED ELEVATED CENTRAL HEATING PLANT BUILDING CONCEPTUAL - NOT FINAL IMAGE “C” - RENOVATED LOBBY AND NEW PLANTED FLOOD BARRIER IMAGE “B” - TYPICAL PLAN OF LOBBY RENOVATION AND NEW PLANTED FLOOD BARRIER NEW PLANTED FLOOD BARRIER “LEVEE”, WITH INTEGRATED SEATING AUTOMATIC FLOOD BARRIER NEW STAIR OVER TOP OF “LEVEE” NEW ENTRANCE DOORS, WINDOWS, AND FINISHES AT RENOVATED LOBBY IMAGE “B” IMAGE “B” IMAGE “B”

Upload: others

Post on 20-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: GERALD J. CAREY GARDENS Brooklyn, NY · CAREY GARDENS $ 86,711,000 Total # 4 682 1,681 8.37 8 46 23 47 Est. Construction Start* Q2-16 # of Damaged Bldgs. ... Installation of stand-by

GERALD J. CAREY GARDENSBrooklyn, NY

2

13

W 24TH STREET

W 23RD STREET

W 22ND STREET

MERM

AID AVENU

E

SURF AVEN

UE

NORTH

PROPOSED ELEVATED CENTRAL HEATING PLANT BUILDING, WITH PARKING BELOWNEW GENERATOR

ADDITION AT BUILDING 3SITE BOUNDARY

SITE BOUNDARY

SITE BOUNDARY

EXISTING PARKING

EXISTING BALL COURT

EXISTING BALL COURT

EXISTING PARKING

EXISTING PARKING PROPOSED EMERGENCY GENERATORS

EXISTING BUILDINGS PROPOSED BOILER HALL

PROPOSED MECHANICAL ADDITIONS

PROPOSED MECHANICAL ADDITION AT BUILDING 2

EXISTING COMMUNITY

CENTER

IMAGE “A”IMAGE “C”

IMAGE “A” - PROPOSED ELEVATED CENTRAL HEATING PLANT BUILDING CONCEPTUAL - NOT FINAL

IMAGE “C” - RENOVATED LOBBY AND NEW PLANTED FLOOD BARRIER

IMAGE “B” - TYPICAL PLAN OF LOBBY RENOVATION AND NEW PLANTED FLOOD BARRIER

NEW PLANTED FLOOD BARRIER “LEVEE”, WITH INTEGRATED SEATING

AUTOMATIC FLOOD BARRIER

NEW STAIR OVER TOP OF “LEVEE”

NEW ENTRANCE DOORS, WINDOWS, AND FINISHES AT RENOVATED LOBBY

IMAGE “B”IMAGE “B”

IMAGE “B”

Page 2: GERALD J. CAREY GARDENS Brooklyn, NY · CAREY GARDENS $ 86,711,000 Total # 4 682 1,681 8.37 8 46 23 47 Est. Construction Start* Q2-16 # of Damaged Bldgs. ... Installation of stand-by

NEW YORK CITY HOUSING AUTHORITYSANDY RECOVERY PROGRAM MANAGEMENT OFFICE

Sandy Recovery ProgramPermanent Repairs

Districts

Development

Current estimated allocation necessary for FEMA scope

Residential Buildings Apartments Population Acreage Congressional

State Assembly

State Senate

City Council

CAREY GARDENS 86,711,000$   Total # 4 682                1,681           8.37 8 46 23 47Est. Construction Start*

Q2-16# of Damaged Bldgs. funded by FEMA**

All Residential Buildings 

Site Restoration (sidewalks, fencing and ground fill to positive drain, etc.) of Sandy damaged areas as well as any areas that may be affected by construction

Site Restoration - (Asphalt resurfacing) of Sandy damaged areas as well as any areas that may be affected by construction

Repair and restore architectural features (walls, floors) of common areas damaged by flooding. Replace doors, frame & hardware damaged by flooding

Remove underground fuel oil storage tank(s) as required.

Installation of stairwell lighting

Restoration of Sandy damaged portions of mechanical, electrical and plumbing systems

New building to house boiler equipment above the DFE

Dry flood proofing above DFE to protect building envelope in flood prone areas

Contents damaged as a result of Sandy (i.e. equipment and supplies)

Restoration of play ground surface areas and play structures damaged by Sandy

Replacement of underground conduits & site lighting (in Sandy flooded areas)

CCTV and Layered Access Systems

Installation of stand-by generators to provide full back-up power

Abate & restore building crawl spaces

New electrical annexes to be located above the Design Flood Elevation (DFE) to house new C/T cabinets

Full roof replacement

FEMA 428 Scope

DFE ‐ Design Flood Elevation* These are estimated dates and are subject to change**The determination of whether a building was damaged by Sandy and eligible for funding was made by FEMA