Key activities to prepare the detailed design (January to August 2012)• Fieldinvestigationsincludingsurveyofutilitylocations,soiltestinganddrainageassessments.
• Discussionswithaffectedlandownersaboutgeotechnicalandsurveyinvestigations,propertyadjustmentsandaccessduringconstruction.
• ConsultationwiththeAboriginalcommunitytodeterminethesignificanceofAboriginalobjectsand/orplaceswithintheprojectareatoprepareaculturalheritageassessmentreport.
• FinalisingthealignmentofthePrincesHighwayandtheaccessroaddesigndetails.
• Designofbridges,retainingwalls,drainagestructures,streetfurniture,lighting,noisewalls,pavementsandlandscaping.
Mount Pleasant to Toolijooa Road - detailed design in progress
ThedetaileddesignfortheGerringongupgradebetweenMountPleasantandToolijooaRoadhasbeenpreparedforyourcomment.Thisdesigninvolvesfinalisingtheupgradedroadalignment,theurbandesign,landscapingandthedevelopmentofvariousplanstosupportconstructionandminimiseimpactsonthelocalcommunity.
• Developmentofplansformanagingconstructionstaging,community/stakeholdercommunicationsandparticipation,environment,traffic,safetyandheritage.
Community advocate appointed
RMSispleasedtoannouncetheappointmentofRowenaLenningsasthecommunityadvocatefortheGerringongupgrade.
Rowena’srolewillbeto:
• Provideyouwithadvice,independentoftheprojectteam.
• Providesupporttocommunitymembersifrequired,inexplainingtheirproblemsorissuestotheprojectteam.
• AssistyouwithunderstandingtechnicalinformationprovidedbyRMS.
• LookintohowyourcomplaintstoRMSortheprojectteamhavebeendealtwithifyoubelievetherehasnotbeenasufficientresponsetoyourissueorconcern.
RowenawillreporttoseniormanagersatRMS.WeencourageyoutotakeadvantageofRowena’sservicesascommunityadvocatetohelpensureclearandconsistentinformationisdeliveredtothecommunity,theprojectteamandtoRMS.
ContactRowenabyphone:0418490376or02 94847881oremail:[email protected]
Rowenawillassesshowshecanbesthelpyou,usuallywithin24hours.
Community display
Youareinvitedtoacommunitydisplaytomeetwiththeprojectteamandfindoutmoreaboutthedetaileddesign.Wewillprovideinformationontheproposedalignment,theurbandesignandlandscapeplans.
Youcanvisitthedisplayon:
Friday 25 and Saturday 26 May 2012 at Gerringong Town Hall 106 Fern Street, Gerringong 10am – 4pm each day
MAY 2012COMMUNITY UPDATE
Gerringong upgradePrinces Highway
I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I II
II
II
II
II
II
II
I
I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I
I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I II
II
II
II
II
II
II
I
I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I
I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I II
II
II
II
II
II
II
I
I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I
I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I II
II
II
II
II
II
II
I
I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I
I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I II
II
II
II
II
II
II
I
I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I
I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I II
II
II
II
II
II
II
I
I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I
North of Pottery access road
Belinda Street interchange and Sims Road access road Rose Valley interchange and access road
Omega Lane access road
Toolijooa Road interchange detailToolijooa Road intersection
Toolijooa
Road
Willow
vale R
oad
Belinda
Street
Crooked R
iver
South Coast Railway
Rose V
alley Road
Ooaree Creek
South Coast Railway
Will
owva
le R
oad
South Coast Railway
Toolijooa
Road
Baileys
Road
Crooked R
iver
Alne Bank
Lane
Burnett Avenue
Upgraded
Princes Highway
GERRINGONG
Sim
s Road
Rowlins Road
Victoria
Street
Belinda
Street
Campbell
Street
Omega Flat
Ooaree Creek
Werri Lagoon
Aerial photo - 2007
Rose Valley R
oad
Om
ega Lane
ROSE VALLEY
Mount Pleasant
Ridge
New Fern Street railway overbridge
WILLOW VALE
Removal of climbing lane to provide right turn lanes via road marking.
Connection to existing
Kiama bends
Fern Street
Proposed extent of noise wall
0 200 400 600 800m
N
Key features of the upgraded highway
N500m0m 250m
LEGENDProposed upgrade
Existing highway
Other roads
Railway
Watercourse
I I I
LEGEND
UpgradedPrincesHighway
Newsharedaccessroads
ExistingPrincesHighway
Otherroads
SouthCoastRailway
Waterways
Newbridges
Existingbridges
Climbinglane
Figtreeretained
Noisewall
DEVELOPMENT OF ROUTE OPTIONS 2007
SELECTION OF PREFERRED OPTION INCLUDING IDENTIFICATION OF STAGING OPPORTUNITIES 2008
FURTHER INVESTIGATIONS AND REFINEMENT OF PREFERRED OPTION 2008
GERRINGONG UPGRADE REVIEW OF ENVIRONMENTAL
FACTORS 2010
NEW SHARED ACCESS ROADS DESIGN 2011
GERRINGONG UPGRADE CONCEPT DESIGN 2010
PREFERRED OPTION AND PREFERRED ACCESS
OPTIONS ANNOUNCED 2009
DETAILED DESIGN, LAND ACQUISITION AND INITIAL
UTILITY RELOCATIONS 2012
CONSTRUCTION 2012 - 2015 KEY CONSTRUCTION STAGING PLAN CURRENTLY UNDER DEVELOPMENT
ON
GO
ING
CO
MM
UN
ITY
PA
RT
ICIP
AT
ION
WE ARE
HERE
Have your say forms will also be
available at the public
display days
RoadsandMaritimeServices(“RMS”)issubjecttothePrivacyandPersonalInformationProtectionAct1998(“PPIPAct”)whichrequiresthatwecomplywiththeInformationProtectionPrinciplessetoutinthePPIPAct.
Allinformationincorrespondenceiscollectedforthesolepurposeof assistingintheassessmentof thisproposal.Theinformationreceived,includingnamesandaddressesof respondents,maybepublishedinsubsequentdocumentsunlessaclearindicationisgiveninthecorrespondencethatallorpartof thatinformationisnotpublished.OtherwisetheRMSwillonlydiscloseyourpersonalinformation,withoutyourconsent,if authorisedbythelaw.YourpersonalinformationwillbeheldbytheRMSatRoadsandMaritimeServices,90CrownStreet,Wollongong2500.Youhavetherighttoaccessandcorrecttheinformationif youbelievethatitisincorrect.
Roads and Maritime Services RMS12.125
For more information
Email: [email protected]: www.rta.nsw.gov.au/guPhone: 1800506976(freecall)projectinformationline. 1300762343forSafetyandEnvironmentalEmergenciesPost: Gerringongupgrade,POBox364GerringongNSW2534Information: Berry project office,BroughtonCourt,Shop3/113QueenStreet,BerryNSW2535 generallyopenFridays10am-5pm Gerringong Newsagency displaywindow,131FernStreet,GerringongSiteoffice: 446PrincesHighway,Gerringong2534
Construction
RoadsandMaritimeServices(RMS)hascontractedFultonHogantodesignandconstructthe$310millionupgrade.Thenewhighwaywillprovideapproximately7.5kilometresofnewroad,whichwillgenerallyfollowtheexistingroadalignment.Therewillbeaposted100km/hspeedlimitalongmostoftheupgrade.
Constructionworkisexpectedtostartinthesecondhalfof2012,withcompletionexpectedinthefirsthalfof2015,weatherpermitting.Howconstructionactivitieswillbestagedisbeingthoughtthrough.WebelievethatwewillbeabletoundertaketheworkwithonlyshortperiodsofclosingFernStreetorBelindaStreet.Weareseekingyourfeedbackonwhatyouconsidertobeacceptablelengthsoftimeforanytemporaryclosures,aswellasgivingusyouropinionontheurbandesignandlandscapeplansandsomeoftheconstructionelementssuchasbridgesandembankmenttreatments.
Have your say
FultonHoganandRMSinviteyourcommentsonthedetaileddesign.Yourfeedbackwillbeconsideredaswefinalisethisdesign.PleasefillintheHaveYourSayformattachedandsendtothefollowingaddressbyFriday 22 June 2012:
REPLY PAID 86040 Gerringong upgrade PO Box 364 Gerringong NSW 2534