Page 1: Gerrit Zenner. Sarens UK Ltd. 29th January

1 Presentation title - edit in the Master slide

 

Range of available Heavy Transportation & Heavy Lifting Techniques

Gerrit Zenner - Global Area Sales Manager – Sarens Group Nuclear & Thermal Plants

Page 2: Gerrit Zenner. Sarens UK Ltd. 29th January

Modular or Stick Built Solutions

• Partially or entirely constructed in factory

• Transport to site for assembly and installation

• Needs depend of technology provider

• There are some copy / paste systems (e.g. AP1000)

• Equipment build on frames (skid) or tailor made

Page 3: Gerrit Zenner. Sarens UK Ltd. 29th January

Modular or Stick Built Solutions

• Primary circuit equipment is tested prior to arrival – in one piece – example reactor & steam generators

• Need for good supply chain

• Plenty of modular yards on West coast of UK & Scotland

Page 4: Gerrit Zenner. Sarens UK Ltd. 29th January

Options for Transportation• Moorside Sellafield & Wylfa : will have

interface between Sea & Land

• Inventive solutions:River transportBeach landing

Page 5: Gerrit Zenner. Sarens UK Ltd. 29th January

Building a Jetty (temporary)

• Building jetty (for maintenance afterwards)

• Port facilities

• Semi Submersible ships

• Geared ships

• Barges (different sizes) – draft - roro

Page 6: Gerrit Zenner. Sarens UK Ltd. 29th January

Internal Transportation on Site

Companies with available equipment in UK :

•ALE

•Mammoet

•Sarens

Page 7: Gerrit Zenner. Sarens UK Ltd. 29th January

Super Heavy Lifting Equipment

• Up to 200,000 M/T is available

• Capacity up to 5.000 ton @ 40m radius

• Global experience:ALE – Mammoet – Sarens

• OPEN TOP for installations of equipment or …..

Page 8: Gerrit Zenner. Sarens UK Ltd. 29th January

Availability of Techniques

• Skidding & Jacking in via Hatch

• Bringing in equipment after Polar Crane & Dome is installed

• Reactor & Steam generators

Our advise : early engineering & involvement

Why : Different concepts with feasibility study