ges 400 h selected topics in geography: computer aided negotiation economic issues in river basins

36
Made with OpenOffice.org 1 GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins John J. Boland, Ph.D., P.E. Professor Emeritus The Johns Hopkins University 24 Sep 08

Upload: amil

Post on 04-Jan-2016

26 views

Category:

Documents


1 download

DESCRIPTION

GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins John J. Boland, Ph.D., P.E. Professor Emeritus The Johns Hopkins University 24 Sep 08. Objectives. At the end of this lecture, you should: - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 1

GES 400 H Selected Topics in Geography:

Computer Aided Negotiation

Economic Issues in River Basins

John J. Boland, Ph.D., P.E.Professor Emeritus

The Johns Hopkins University

24 Sep 08

Page 2: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 2

Objectives

At the end of this lecture, you should:At the end of this lecture, you should:

Recognize some economic issues associated with recreational uses of rivers

Be able to articulate the difference between market and non-market values, and to recognize the non-market values associated with recreation

Be able to list the principal advantages and weaknesses of methods used to measure non-market recreation benefits

0:10

Page 3: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 3

Example Problem

A state is considering a capital project for the A state is considering a capital project for the next fiscal year. The project is described as next fiscal year. The project is described as follows:follows:

“Fish populations in several tributary streams have been depleted because of past pollution (now corrected). At the present time, fishing is banned in the affected stream reaches to avoid extinction of harvestable species. The state proposes to stock the streams with immature fish raised in a state hatchery. It is expected that the program, conducted in the summer of 2010, will permit sport fishing to resume in the summer of 2013, and to continue indefinitely thereafter.”

1:05

Page 4: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 4

Benefits and Costs

What are the costs of carrying out this What are the costs of carrying out this project?project?

How can we measure the costs?How can we measure the costs?

What are the benefits that will result if this What are the benefits that will result if this project is successfully implemented?project is successfully implemented?

How can we measure the benefits?How can we measure the benefits?

From the point of view of society as a whole, From the point of view of society as a whole, why do we care about benefits and costs?why do we care about benefits and costs?

2:15

Page 5: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 5

More InformationUp to a point, the larger numbers of immature fish restocked, the larger the resulting population and the more fishing-days can be sustained.

The more fish placed in the stream, the greater the cost of restocking and the risk of overstocking

The more fishing-days each year, the greater the benefit from the state's investment.

The state proposes limiting the number of annual fishing days to a sustainable level by issuing a fixed number of no-cost licenses, assuming each licensee will fish for an average of 25 days/year.

The state wishes to design the project so that the benefits are at least equal to the costs. 5:05

Page 6: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 6

Sustainability

What does it mean for this project to be What does it mean for this project to be sustainable?sustainable?

With respect to ---fish population

social welfare (economics)

anything else?

8:00

Page 7: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 7

The Question

How many licenses should the state issue each year (so that the benefits are at least equal to the costs)?

Issuing too few licenses will deprive some of the opportunity to fish and will result in lower benefits, possibly less than the project costs (no economic sustainability)

Issuing too many licenses may result in depleting the restocked fish population (no fish population sustainability)

The state wishes to find the optimum number of licenses, considering all of these factors

9:00

Page 8: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 8

The AnalysisThis problem requires economic analysis This problem requires economic analysis because:because:

We need to know the cost of restocking the streams as a function of the anticipated fishing pressure, resulting from the number of licensees

We need to know the economic benefits obtained from fishing each year, as a function of the number of licensees

In order to evaluate benefits, we must measure the value of a non-market good – fishing

Costs and benefits must be adjusted to reflect the same monetary measure (e.g., 2008 dollars)

Future benefits must be reduced to present value for comparison to costs 9:20

Page 9: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 9

What's Next

We will learn how economists measure costs We will learn how economists measure costs and benefitsand benefits

In particular, we will learn how non-market In particular, we will learn how non-market benefits are measuredbenefits are measured

Several methods will be discussed

They all have pros and cons

We will see how costs and benefits occurring We will see how costs and benefits occurring at different times are adjusted and comparedat different times are adjusted and compared

The result will be the optimum number of The result will be the optimum number of licenses that the state should issuelicenses that the state should issue

11:00

Page 10: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 10

Measuring Costs

The costs of implementing a project generally The costs of implementing a project generally consist of construction costs, operating costs, consist of construction costs, operating costs, maintenance costs, and possibly future maintenance costs, and possibly future removal costs. These costs are typically removal costs. These costs are typically engineering estimates and relatively engineering estimates and relatively uncontroversial (compared to benefits).uncontroversial (compared to benefits).

But there may be external effects (either But there may be external effects (either positive or negative) associated with positive or negative) associated with constructing and operating a project. These constructing and operating a project. These are measured using methods similar to those are measured using methods similar to those described for benefits.described for benefits.

11:10

Page 11: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 11

Measuring Benefits

Measuring the benefits of public sector Measuring the benefits of public sector projects, especially water resource projects, projects, especially water resource projects, presents many challenges. Resulting presents many challenges. Resulting measurements often prove controversial, measurements often prove controversial, making this a particularly difficult area for making this a particularly difficult area for planners.planners.

What is sought is a monetary measure of What is sought is a monetary measure of benefits, even though many water resource benefits, even though many water resource benefits are not associated with a cash flow. benefits are not associated with a cash flow. Even where there is a cash flow, it may not Even where there is a cash flow, it may not properly represent the value of the output to properly represent the value of the output to society.society. 11:55

Page 12: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 12

Market vs. Non-Market Goods

Market goodMarket good

Can be bought and sold in a market – the good has a price – consumption of the good involves a cash flow (consumers pay producers)

Examples – bread, cable TV, computers

Non-market goodNon-market good

Is not offered in the market – no price – consumers may use the good but they don't pay for it, so there is no cash flow

Examples – clean air, visual amenity, fishing

12:40

Page 13: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 13

Market-Based Valuation

Some benefits can be measured by means of Some benefits can be measured by means of market-based methods:market-based methods:

The project output may consist of market goods, which are sold to beneficiaries at observable prices. (hydroelectric energy)

The project output may not be itself a market good, but its provision may affect the demand for an existing market good. (canoeing affects the demand for canoe rentals)

The project output may not be itself a market good, but its provision may affect the cost of producing an existing market good. (flood control may reduce the cost of downstream activities) 14:00

Page 14: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 14

Market-Based Valuation

Market goods, or goods with links to market Market goods, or goods with links to market goods, are relatively easy to valuegoods, are relatively easy to value

For a market good, the value is consumers' willingness to pay for the good, calculated from the price and the quantity consumed

For goods related to market goods, the value is at least the increment in value created for the market goods, but it might be more

17:00

Page 15: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 15

Non-Market Goods

Some outputs may be non-market goods Some outputs may be non-market goods without any close connection to market without any close connection to market transactions:transactions:

Some can be measured indirectly by revealed preference methods (measurement derived from market behavior involving other weakly complementary goods).

Some can be measured directly by stated preference methods (measurement obtained directly from consumers using survey methods).

17:10

Page 16: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 16

Kinds of Value

For certain non-market goods, there may be For certain non-market goods, there may be more than one kind of value:more than one kind of value:

Use value—experienced by persons who actually use the good

Intrinsic value—experienced by persons who do not necessarily use the good

Option value is experienced by non-users who do not know whether they will use the good in the future, but prefer to retain the option

Existence value is experienced by non-users who do not plan to use the good in the future, but prefer that it be available for others

Bequest value is experienced by non-users who do not plan to use the good in the future, but prefer that it be available for future generations 18:45

Page 17: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 17

Non-Market Good Valuation

Indirect methods – Revealed PreferenceIndirect methods – Revealed Preference

People's behavior reveals the value that they place on the good

Direct methods – Stated PreferenceDirect methods – Stated Preference

People are asked to state what value they place on the good

24:40

Page 18: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 18

Revealed Preference Methods

Appraisal Method: Expert opinion as to what Appraisal Method: Expert opinion as to what a good would be worth if it could be traded in a good would be worth if it could be traded in the market (based on comparable sales)the market (based on comparable sales)

Travel Cost Method: Measures value of an Travel Cost Method: Measures value of an in situ resource (e.g., national parks) as in situ resource (e.g., national parks) as demonstrated by willingness of individuals to demonstrated by willingness of individuals to incur travel expenses.incur travel expenses.

Hedonic Price Analysis: Value of an Hedonic Price Analysis: Value of an environmental good can be deduced from its environmental good can be deduced from its effect on the value of a weakly effect on the value of a weakly complementary market good, such as real complementary market good, such as real estate.estate. 25:20

Page 19: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 19

Stated Preference Methods

All Stated Preference Methods use some All Stated Preference Methods use some type of survey, which may be administered in type of survey, which may be administered in person, by telephone, by mail, or by internet. person, by telephone, by mail, or by internet. The survey has the following elements:The survey has the following elements:

Description of the good that is to be valued and the choice situation (hypothetical market) that is to be assumed.

The elicitation (choice) question. This may take a number of forms: “how much would you pay for ____?” “would you pay $____ for ____?” “how would you rank ___ alternatives?” “given a change in the level of the non-market good, how would your behavior change?” 31:15

Page 20: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 20

Stated Preference (cont.)

Questions about the respondent: age, gender, socio-economic data, attitudes, beliefs, etc.

33:30

Page 21: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 21

Contingent Valuation

Contingent Valuation Method (CVM)Contingent Valuation Method (CVM)Typical elicitation question: “how much would you pay for ____?”

Results can be extrapolated from sample to population and transformed, in a number of steps, to a population demand curve for the non-market good.

The value of a change in the quantity of a non-market good is the change in the area under the demand curve (change in willingness to pay).

35:00

Page 22: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 22

Contingent Referendum

Contingent Referendum MethodContingent Referendum MethodTypical elicitation question: “would you be willing to pay $_____ for _____? Yes or No?”

Sample results can be extrapolated to the population.

Using econometric techniques, results can be used to estimate a demand curve.

By comparison to CVM, respondents usually find the elicitation question easier to answer. However, the method requires a larger sample.

35:35

Page 23: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 23

Contingent Ranking

Contingent Ranking MethodContingent Ranking MethodElicitation question asks respondents to rank a number of alternative bundles of goods, including the non-market good.

Results can be extrapolated from the sample to the population.

Respondents find this relatively easy; it does not require the assumption of a hypothetical market. Accordingly, this method avoids some kinds of biases.

This method requires a large sample.

37:10

Page 24: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 24

Contingent Activity

Contingent Activity MethodContingent Activity MethodTypical elicitation question: “if ___ amount of the non-market good were supplied, how would that affect the number of days you spend _____?”

If the contingent activities can be valued in monetary terms, it is possible to impute the value of the non-market good, to the extent that it enables some valuable activity.

Sample results can be extrapolated to the population.

Limited applicability (e.g., water quality improvement may induce additional recreational activity).

37:45

Page 25: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 25

Other Stated Preference

Combinations of these methods can be used Combinations of these methods can be used (e.g., a contingent referendum question with (e.g., a contingent referendum question with a contingent valuation follow-up)a contingent valuation follow-up)

Method can be varied to suit circumstancesMethod can be varied to suit circumstances

Conjoint Analysis, e.g., is a variant of the Conjoint Analysis, e.g., is a variant of the Contingent Ranking Method.Contingent Ranking Method.

NOTE: all survey methods, including all of NOTE: all survey methods, including all of the Stated Preference methods discussed the Stated Preference methods discussed here, are subject to a variety of biases. here, are subject to a variety of biases. Every application should be carefully Every application should be carefully designed to minimize bias.designed to minimize bias.

38:20

Page 26: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 26

Biases in Survey Research

Bias is not the same as error, or as Bias is not the same as error, or as uncertainty. In the case of error or uncertainty. In the case of error or uncertainty, there is usually no presumption uncertainty, there is usually no presumption as to the direction of the error. Biases, as to the direction of the error. Biases, however, usually shift results in a particular however, usually shift results in a particular and predictable direction.and predictable direction.

Strategic Bias: Respondents may answer Strategic Bias: Respondents may answer questions so as to increase the likelihood questions so as to increase the likelihood that some valuable good will be provided to that some valuable good will be provided to them.them.

38:35

Page 27: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 27

Biases (cont.)

Protest Bids: Some respondents may Protest Bids: Some respondents may provide zero or non-zero valuations for provide zero or non-zero valuations for reasons other than their actual valuation. reasons other than their actual valuation. This may reflect objections to placing a value This may reflect objections to placing a value on a good that respondents expect to receive on a good that respondents expect to receive without cost. Or some may report a high without cost. Or some may report a high value in order to “send a message” or for value in order to “send a message” or for other reasons unrelated to their personal other reasons unrelated to their personal valuation.valuation.

Value Cue Bias: Instead of reaching their Value Cue Bias: Instead of reaching their own valuation, respondents may react to own valuation, respondents may react to some cue given in the course of the survey. some cue given in the course of the survey.

39:15

Page 28: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 28

Biases (cont.)

Information Bias: Too much or too little Information Bias: Too much or too little information on the good may have been information on the good may have been given in the survey instrument. This is a given in the survey instrument. This is a particular problem where some respondents particular problem where some respondents have access to information from other have access to information from other sources (e.g., newspaper accounts).sources (e.g., newspaper accounts).

Payment Vehicle Bias: The respondent may Payment Vehicle Bias: The respondent may react to the method proposed for recovering react to the method proposed for recovering the cost of the non-market good, or to their the cost of the non-market good, or to their assumptions when no method is stated. assumptions when no method is stated. Possible methods include broad-based Possible methods include broad-based taxes, local benefit taxes, user fees, etc.taxes, local benefit taxes, user fees, etc.

40:55

Page 29: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 29

Biases (cont.)

Hypothetical Bias: The hypothetical nature of Hypothetical Bias: The hypothetical nature of the survey questions may prompt a the survey questions may prompt a respondent to answer carelessly. This effect respondent to answer carelessly. This effect is typically called a “bias” but it is probably is typically called a “bias” but it is probably better described as a source of “error,” since better described as a source of “error,” since the direction of the discrepancy cannot the direction of the discrepancy cannot usually be predicted.usually be predicted.

Sample Bias: The sample of respondents Sample Bias: The sample of respondents may be non-random, or the sample may be may be non-random, or the sample may be biased by refusals and/or incomplete biased by refusals and/or incomplete responses.responses.

41:40

Page 30: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 30

Biases (cont.)

Non-Response Bias: Those who do not Non-Response Bias: Those who do not respond to the survey, or who decline to be respond to the survey, or who decline to be interviewed, are not a random sample of the interviewed, are not a random sample of the population. They may include those who population. They may include those who place the lowest value on the good. Their place the lowest value on the good. Their exclusion can bias the results.exclusion can bias the results.

42:10

Page 31: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 31

Fishery Problem

Back to the problem posed at the beginning Back to the problem posed at the beginning of the lecture --of the lecture --

A consultant has estimated the cost of stocking the streams (including hatchery costs) as a function of the expected fishing pressure:

Where: TC = total cost of stocking (2005 $)

P = no. of licenses

Q = fishing-days/year/license (25)

This must be restated in 2008 $, using the Consumer Price Index (why?)

TC=1,100,00050 P⋅Q 1.0303

TC=1,199,6935.53 P⋅Q 1.030343:10

Page 32: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 32

Fishery Problem (cont.)

A previous study estimated the willingness-to-pay (benefit) of anglers on a similar stream, under similar conditions. A sample of anglers were interviewed, using a contingent valuation method. The results were then extrapolated to the larger population of anglers and fitted to a mathematical form, giving the following expression

Where: W = total willingness-to-pay/year

But this result is in 2003 $, so it is escalated to:

W=45 Q1 −0.5⋅P⋅Q 0.90

W=52.09 Q1 −0.5⋅P⋅Q 0.9044:45

Page 33: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 33

Fishery Problem (cont.)

Notice that the cost is a single item, incurred in 2010 and stated in 2008 $, but the benefits are annual amounts, starting in 2013 and continuing indefinitely (stated in 2008 $).

Calculate the equivalent present value of the benefit stream, as of 2010 (same year that costs are incurred).

Both benefits and costs can be stated in 2008 $, or in dollars for any other year, as long as the same year is used for both

Using an inflation free discount rate of 3.0%, the 2010 present value of the benefits is:

TB=1,589 Q1−0.5⋅P⋅Q 0.90

46:00

Page 34: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 34

Fishery Problem (cont.)

Now we have expressions for total costs and total benefits, both as functions of P and Q.

If Q is assumed to equal 25 days/year, the expressions can be rewritten as functions of P

The decision criterion (benefits at least equal to costs) is satisfied by setting TC = TB

Solving the resulting expression for P gives the optimal number of licenses

Note that this cannot be solved analytically. But the expressions can be set up on a spreadsheet and solved with a solver, or by manual iteration

Solution: optimal number of licenses = 1,380

TC=1,199,6931,503 P 1.0303

TB=5,647 P 0.90

47:20

Page 35: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 35

Fishery Problem (cont.)

Review --Review --

Solution required:Mathematical modeling of the cost of restocking the streams

Non-market valuation of fishing (using contingent valuation in this case), allowing mathematical modeling of annual benefits

Both costs and benefits were stated at 2010 present value, but in 2008 $

Results included -The minimum cost ($3,781,800) at which the project could be feasible

The number of permits which could be distributed consistent with maintaining sustainable fisheries on these streams

48:20

Page 36: GES 400 H Selected Topics in Geography: Computer Aided Negotiation Economic Issues in River Basins

Made with OpenOffice.org 36

What did we learn?