The Norwegian Public Roads AdministrationGetting there safely, together
17/06/2018
Photo: Knut Opeide
![Page 2: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/2.jpg)
A modern transport system is safe to use and accessible to all, while safeguarding the environment both locally and globally.
17/06/2018
Photo: Knut Opeide
Terje Moe Gustavsen Director General
Norwegian Public Roads Administration
![Page 3: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/3.jpg)
NPRA Organisation Chart
The structure of our organisation
17/06/2018
![Page 4: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/4.jpg)
Organised by regionNational organisation
17/06/2018
● The Directorate of Public Roads
● Five Regions
● 72 Driver and Vehicle LicensingOffices
● 7,600 employees
![Page 5: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/5.jpg)
From a builder of roads to a competence-based organisation
We have changed a lot in 150 years
17/06/2018
Photo: Knut OpeideUnknown photographer, from the archives of The Norwegian Road Museum, dated around 1930
![Page 6: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/6.jpg)
Four main focus areas
● Mobility
● Road safety
● The environment
National objectives for Norwegian transport policy
17/06/2018
Photo
:: K
nut
Opeid
e
Photo
:: H
enri
ett
e E
. B
uste
rud
Photo
: K
nut
Opeid
e
Photo
: K
nut
Opeid
e
![Page 7: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/7.jpg)
Our budget breaks down as follows:
Operation, maintenance and development is expensive
17.06.2018
30.2billion
5.1billion
2018 ANNUAL BUDGET
The total budget comprises approx. NOK 35,3 billion, 30.2 bn is government funding and 5.1 bn comes from external funds (road tolls and advance allocations) In addition, NPRA administrate construction work on county roads for around NOK 20 billion.
![Page 8: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/8.jpg)
Our governing documentsInterchangeable transport policy priorities
17/06/2018
![Page 9: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/9.jpg)
New structure 2020
17.06.2018
19 Counties today 10 Counties in 2020
NPRA are administration onbehalf of the counties
Counties administrate themselves
![Page 10: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/10.jpg)
Different Project Modelsused in Norwegian Road Projects
17.06.2018
Photo: Håkon Aurlien
BB (Bid – Build) dominates
DB (Design – Build)
DBO (Design – Build – Operate)
DBFO – PPP: Design-Build-Finance-Operate, Private Public Partnership
![Page 11: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/11.jpg)
Contract portfolio
Contracts (building) 2017
17.06.2018
Feilkilde:Not all contractsbelow 2 millNOK areincluded
26
6775 73
50
2917
11
Under 2 mill kr 2-5 mill kr 5 - 10 mill kr 10-25 mill kr 25-50 mill kr 50- 100 mill kr 100-250 mill kr 250 mill +
Contract size Number Value mill NOK
Below 2 mill NOK 26 35
2-5 mill NOK 67 219
5 -10 mill NOK 75 536
10-25 mill NOK 73 1 153
25-50 mill NOK 50 1 803
50-100 mill NOK 29 2 203
100-250 mill NOK 17 2 729
250 mill + 11 4 470
SUM 348 13 149
![Page 12: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/12.jpg)
Operations and maintenance, 104 contracts
~ NOK 6 billions
![Page 13: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/13.jpg)
Location of ongoing PPP contracts
Oslo
Trondheim
2006: Lyngdal –
Flekkefjord
2005: Klett - Orkanger
2009: Grimstad – Krisisansand
![Page 14: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/14.jpg)
Ongoing PPP contacts, 25 years operation period
● “Orkdalsvegen” (E39 Klett - Orkanger )Length ~27 kmConstruction completion-handing back: 2005 – 2030
● “Allfarveg” (E39 Lyngdal – Flekkefjord)Length ~ 38 kmConstruction completion – handing back : 2006 – 2031
● “Agder OPS Vegselskap” (E18 Grimstad – Krisisansand)Length, 4-lane motorway ~38 kmConstruction completion - handing back: 2009 – 2034
![Page 15: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/15.jpg)
Experience from the ongoing PPP contracts
● The current contract documents have worked well in the ongoingcontracts.
● Payment mechanisms have generally worked well.
● Long operation and maintenance periods stimulate focus onoperation and maintenance also during the construction period.
● Important:Focus on safety and occupational health.
● Important: Clearly defined road condition at the end of the operation and maintenance period.
● Important: Provisions are required in the Contract for large and unexpectedwork that may be necessary in the operation period.
![Page 16: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/16.jpg)
Location, upcoming PPP projects
Oslo
Løten - Elverum
Hålogalandsvegen
(Tjeldsund-Gullesfjordbotn-Langvassbukt)
Sotrasambandet
NOK 9500 mill. project cost
~ 9 km lengthNOK 5100 mill. project cost
~ 26 km length
NOK 8500 mill. project (PPP) cost
~ 80 km length
![Page 17: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/17.jpg)
Upcoming PPP projects
● Rv.3/rv.25 Løten-Elverum, Hedmark County ~ 26 km Approximately NOK 5100 mill. project costFinancial close 30 May 2018.
● Rv.555 Sotrasambandet, Hordaland County ~ 9 kmApproximately NOK 9500 mill. project cost
Approved by the Parliament/Stortinget 15. May 2018
● E10/rv.85 Tjeldsund-Gullesfjordbotn-Langvassbukt, Nordland and Troms Counties ~ 80 kmApproximately NOK 8500 mill. project cost
NPRA are preparing the project
![Page 18: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/18.jpg)
Location Rv.3/rv.25 Løten- Elverum
NIB
18
Oslo
Trondheim
![Page 19: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/19.jpg)
Location Rv.3/rv.25 Løten- Elverum
NIB
19
Objectives:
● The major freight transport between Oslo and Trondheim
● The region Hamar/Elverumis a joint residential and labour market.
● Continuous pedestrian and cycle lane between Hamarand Elverum
● Improved: mobility, traffic safety, public safety, residential environment
Project cost NOK 5100 mill
![Page 20: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/20.jpg)
Location Rv. 555 Sotrasambandet
Bergen Oslo
![Page 21: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/21.jpg)
Kolltveit
Storavatnet
Bergen
city
centre
Project cost NOK 9500 mill
Location Rv. 555 Sotrasambandet
Objectives:- Connection between Bergen
and the island municipalities Fjell, Sund and Øygarden (36,500 inhabitants).
- The project objectives include improved mobility, increased traffic safety and regularity.
- AADT at 26,000 on the current two lane road gives high accident rates. (also challenging for the traffic management during construction)
- Improvements for public transport, pedestrians and cyclists.
![Page 22: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/22.jpg)
New mainroad – tunnels, bridges, intersections(not so much regular road building)
KryssStraume
KryssBildøy
KryssValen
KryssDrotningsvik
KryssStoravatnet
KryssKolltveit
Kolltveit
Straume
Storavatnet
Tunnel
Bridge
Intersection
intersections
![Page 23: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/23.jpg)
Illustrations – new and old Sotra Bridge
Rv.555 Sotrasambandet
![Page 24: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/24.jpg)
Main elementsRv.555 Sotrasambandet
9 km 4-lane road, which includes:
4 bridges (Sotra bridge 875 m plus totally 550 m of smaller bridges
4 tunnels, tunnels totally 4,6 km (double-tube)
4 major junctions
Pedestrian and cycle lanes, 14 km. Upgrading the local road network, partially with new public transport lanes. 2 km of high-voltage tunnels, re-routing of major power line.
![Page 25: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/25.jpg)
New main road. Profile Straume - Storavatnet
Kryss i fjell
StoravatnetNew Sotra-bridge DrotningsviktunnelArefjordtunnel Valen
2 km
Svært krevende prosjekt helt i «ytterkant» av regelverket
• Tunnelsikkerhet • Stigning• Kryss i fjell• Drift og vedlikehold (tunnel)• Beredskap (tunnel)• Bru (600m)
Very demanding project on the very edge of current regulations
• Safety in tunnels• Inclanation• Junction in tunnels• Operate and maintainace (tunnel)• Bridge (600m)
25
![Page 26: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/26.jpg)
New Sotra-bridge
KolltveitBildøy
Straume
Knarrevik
Drotningsvik
Storavatnet
Suspension bridge
26
![Page 27: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/27.jpg)
The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered a maximum traffic of over 32,000 vehicles crossing the bridge in one day.
The narrow road makes it impossible to prioritize public transport.
The very narrow road-shoulders makes it nearly impossible to cycle or walk across the bridge.
The bridge represents the only connection between Bergen and Sotra / Øygarden.
This makes it very vulnerable to storms, accidents and emergency situations.
A new bridge and a new road are crucial for the region's continual growth.
Outdated and overloaded road
27
![Page 28: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/28.jpg)
Location and objectives Hålogalandsvegen
Oslo
Narvik
Trondheim
Objectives:
• Reduce travel time for the freight
• Reduced travel time to Evenes airport
• Improved regularity
![Page 29: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/29.jpg)
European/National road no. E10/Rv85 Hålogalandsvegen
![Page 30: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/30.jpg)
The scope of the PPP projectE10/ rv. 85 Tjeldsund-Gullesfjordbotn-Langvassbukt
![Page 31: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/31.jpg)
E10/rv. 85 Tjeldsund –Gullesfjordbotn–Langvassbukt
80 km 2-lane highway
28 km tunnels, in total
![Page 32: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/32.jpg)
National Tourist Routes
Yesterday’s transport, today’s tourist attraction
17/06/2018
Photo: Jarle Wæhler
![Page 33: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/33.jpg)
A film about the NPRA
Getting there safely, togehter
17/06/2018
![Page 34: Getting there safely, together The Norwegian Public Roads … · 2018. 6. 19. · The existing Sotra-bridge is dimensioned for 12,000 cars, but at the most there has been registered](https://reader036.vdocument.in/reader036/viewer/2022063012/5fca20e946371c50442cdd59/html5/thumbnails/34.jpg)
Thank you for your attention!