glast large area telescope: electronics, data acquisition & instrument flight software
DESCRIPTION
Gamma-ray Large Area Space Telescope. GLAST Large Area Telescope: Electronics, Data Acquisition & Instrument Flight Software Peer Critical Design Review March 19-20, 2003 Gunther Haller Stanford Linear Accelerator Center Manager, Electronics, DAQ & FSW LAT Chief Electronics Engineer - PowerPoint PPT PresentationTRANSCRIPT
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 1
GLAST Large Area Telescope:GLAST Large Area Telescope:
Electronics, Data Acquisition & Instrument Flight Software Peer Critical Design Review March 19-20, 2003
Gunther HallerStanford Linear Accelerator CenterManager, Electronics, DAQ & FSWLAT Chief Electronics Engineer
[email protected](650) 926-4257
Gamma-ray Large Gamma-ray Large Area Space Area Space TelescopeTelescope
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 2
CDR AgendaCDR Agenda
Day 1 - March 19 (all times PST)Section 1: Electronics, DAQ, FSW Overview 8:00 – 8:40
Section 2: Management 8:40 – 9:20
Section 3: System Engineering 9:20 – 10:30
BREAK 10:30 – 10:45
Section 4: Electronics 10:45 – 12:00
LUNCH 12:00 – 13:00
Section 5: Instrument Software Overview 13:00 – 13:30
Section 6: Instrument Software I 13:30 – 14:45
BREAK 14:45 – 15:00
Section 7: Instrument Software II 15:00 – 15:30
Section 8: Instrument Software III 15:30 – 16:15
Discussion 16:15 – 17:00
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 3
CDR Agenda (Con’t)CDR Agenda (Con’t)
Day 2 - March 20
Section 9: Mechanical & Thermal 8:00 – 9:00
Section 10: Power - EMI 9:00 – 9:30
Section 11: Monitoring & Thermal Control 9:30 – 10:00
BREAK 10:00 – 10:10
Section 12: EEE Parts 10:10 – 10:40
Section 13: Manufacturing 10:40 – 11:10
Section 14: Summary 11:10 – 11:20
Discussion/Closeout 11:20 – 12:00
Adjourn 12:00
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 4
Review Board TeamReview Board Team
• Hartmut Sadrozinski/UCSC Chairman • Al Vernacchio/GSFC Co-Chairman - GLAST
Deputy Project Manager• Fred Huegel /GSFC Electrical Engineering• John Fox/SLAC Electrical Engineering -
Applied Physics• Steve Smith/SLAC Electrical Engineering –
System Engineering • Bob Jackobsen/LBL Software• Rick Schnurr/GSFC Software • Lowell Klaisner/SLAC LAT Chief Engineer• Steve Scott/GSFC Systems Engineering• Ron Zellar/GSFC Software
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 5
GLAST Large Area Telescope:GLAST Large Area Telescope:
Electronics, Data Acquisition & Flight Software Overview
Gunther HallerStanford Linear Accelerator CenterManager, Electronics, DAQ & FSWLAT Chief Electronics Engineer
[email protected](650) 926-4257
Gamma-ray Large Gamma-ray Large Area Space Area Space TelescopeTelescope
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 6
Overview OutlineOverview Outline
• Overview of LAT and Electronics• Level III Requirements Summary• Meeting Key Requirements• Flowdown – Requirements to Design• Design Evolution• Optimization• Technical Heritage• Status of July PDR Recommendation Items
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 7
e+ e–
Overview of LATOverview of LAT
• Precision Si-strip Tracker (TKR) Precision Si-strip Tracker (TKR) 18 XY tracking planes. Single-sided silicon strip detectors (228 m pitch) Measure the photon direction; gamma ID, ~880,000 channels.
• Hodoscopic CsI Calorimeter(CAL)Hodoscopic CsI Calorimeter(CAL) Array of 1536 CsI(Tl) crystals in 8 layers. Measure the photon energy; image the shower.
• Segmented Anticoincidence Detector Segmented Anticoincidence Detector (ACD)(ACD) 89 plastic scintillator tiles. Reject background of charged cosmic rays; segmentation removes self-veto effects at high energy.
• Electronics System Electronics System Includes flexible, robust hardware trigger and software filters.
Systems work together to identify and measure the flux of cosmic gamma Systems work together to identify and measure the flux of cosmic gamma rays with energy 20 MeV - >300 GeV.rays with energy 20 MeV - >300 GeV.
Calorimeter
Tracker
ACD [surrounds 4x4 array of TKR towers] DAQ Electronics
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 8
LAT ElectronicsLAT Electronics
16 Tower Electronics Modules– DAQ electronics module (DAQ-EM)– Power-supplies for tower electronics
* Primary & Secondary Units shown in one chassis
ACD
spare
EPU-3
EPU-2EPU-1
spare spare
Pwr Dist. Box
GASU
spare
spare
SIU-P SIU-R
3 Event-Processor Units (2+1 spare) – Event processing CPU– LAT Communication Board– SIBSpacecraft Interface Unit
– Spacecraft Interface Board (SIB): Spacecraft interface, control & data
– LAT control CPU– LAT Communication
Board (LCB): LAT command and data interface
Power-Distribution Unit (PDU)*– Spacecraft interface, power– LAT power distribution– LAT health monitoring
Global-Trigger/ACD-EM/Signal-Distribution Unit*
TKR
CAL
TKR Front-End Electronics (MCM)ACD Front-End Electronics (FREE)
CAL Front-End Electronics (AFEE)
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 9
Specification TreeSpecification Tree
Mission SystemSpecification
ScienceRequirem ents
Docum ent
LAT-SC InterfaceRequirem ents
Docum ent
LAT P erform anceSpecification
LA T-SS-00010
LATEnvironm entalSpecification
LA T-SS-00778
LAT IOCPerform anceSpecification
LA T-SS-00015
ACD SubsystemSpecification
LAT-SS-00016
TKR SubsystemSpecification
LAT-SS-00017
CAL SubsystemSpecification
LAT-SS-00018
Trigger & DataflowSubsystem
SpecificationLAT-SS-00019
SASSubsystem
SpecificationLAT-SS -00020
LO FSubsystem
SpecificationLA T-SS-00021
PowerSubsystem
SpecificationLAT-SS-00136
MechanicalSubsystem
SpecificationLA T-SS-00115
Mission
LAT
LATSubsystem
ScienceRqm ts
Miss ionRqm ts
G round System Rqm ts
Interface Rqm ts
Interface Rqm ts
TCS Perform anceSpecification
LAT-SS-00715
SAS DesignSpecification
LAT-SS -00505
CAL DesignSpecification
LAT-SS-00210
LAT TriggerSpecification
LAT-SS -00284
LAT TK R DesignSpecification
LA T-SS-00134
LA T O perationsFacility
SpecificationLA T-SS-01783
Tower PowerSupplies
SpecificationLAT-SS-01537
ACD DesignSpecification
LAT-SS-00352
DesignSpecification
LA T DataflowSpecification
LAT-SS-00285
LAT Flight SWSpecification
LAT-SS-00399
LAT ReadoutElectronic
SpecificationLA T-SS-00152
LAT IOC/MOC/SSC Interface
ControlDocum ents
Radiator DesignSpecification
LAT-SS-00394
X-LAT P lateDesign
SpecificationLAT-SS-01240
Grid Box DesignSpecification
LAT-SS-00775
LAT-SC InterfaceControl
Docum ents
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 10
Level III Key Requirements SummaryLevel III Key Requirements Summary
Adjust Input timing resolution <100 ns Test 50 nsTrigger acknowledge output Test/Demonstration Meet Requirement
TACK latency < 1.3 s Test < 1.3 usecTiming Jitter < +/- 50 ns Test < 50nsDead-time contribution < 5 s Test < 200 nsec
Acknowledge blocking Test/Demonstration Meet RequirementDead time cause Test/Demonstration Meet Requirement
Event Deadtime Report < 500 ns Test < 500 nsEvent Data Contribution Test/Demonstration Meet RequirementDiagnostics Mode Test/Demonstration Meet Requirement
Control SystemVerify commanding interface Test/Demonstration Meet RequirementGRB response Test/Demonstration Meet Requirement
Event DataReadout and overwrite protection Test/Demonstration Meet RequirementFiltering functions Test/Demonstration Meet RequirementPointing & coordinate system Test/Demonstration Meet RequirementDead-time for average orbit condition < 5% Test/Demonstration < 5% for T&DF
Monitoring & calibration Test/Demonstration Meet RequirementVolume < 0.25 m3 Inspection < 0.25 m3
< 188 kg Inspection < 188 kg
Power < 142 W (dayly average) Test < 142 W (daily average)< 330 W (peak, average over 1 sec) Test < 330 W (average over 1 sec)
Mass
ElectronicsRef: LAT-SS-00019
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 11
Level III Key Requirements Summary (2)Level III Key Requirements Summary (2)
Parameter Requirement Verification Expected Performance
28 VDC +6/- 6V Test 22 V to 37 V DC< 1000 Watts peak Test/Analysis < 750 W< 650 Watts (daily average) Test/Analysis < 650 WImpedance Analysis tbdPrimary/Redundant input power source Analysis Meet RequirementSwitching Test Meet Requirement8 primary power circuits of 14 A Analysis 2 to 5 circuitsControl Test Meet Requirement
Telemetry Telemetry monitoring internal voltage, current, and temperature
Test Meet Requirement
Output Power Supply power to Tower Electronics Test Meet RequirementSupply power to EPU Test Meet RequirementSupply power to SIU Test Meet RequirementSupply power to GASU Test Meet Requirement
Input Power
Power SystemRef: LAT-SS-00136
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 12
Flowdown – Requirements to DesignFlowdown – Requirements to Design
Parameter Requirement Constraint Characteristics Needed Design
Trigger
Adjust Input timing resolution
<100 ns Power Hardware/Firmware system Central Trigger
TACK latency < 1.3 us Mass Decision BlockTiming Jitter < +/- 50 ns Volume (Global Trigger,Dead-time contribution < 5 us Complexity located in GASEvent Deadtime Report < 500 ns Reliability Unit)
DataflowReadout and overwrite protection Power Event buffering in Front-end
electronics, TEM, GASUCentral Event Builder
Efficient Event Assembly Mass (Hardware, locatedFiltering functions Volume Hardware event assembly in GAS Unit)Dead-time for average orbit condition < 5%
Complexity of hardware versus software
Buffering for burst up to 20,000 photon events
Reliability Processor for filtering PowerPC Processor Farm
Error Recovery
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 13
Evolution of DAQ DesignEvolution of DAQ Design
Proposal Design:• No global trigger, ability to reduce hardware trigger rate from tracker marginal • Data router to move partial event fragments into central processor• Event building in software• 16 processors, one on each tower to process data • Communication to TKR/CAL/ACD systems very unique
Current Design:• Global trigger, ability to reduce hardware trigger rate from tracker• Event building in hardware• Data switch to move complete event fragments from hardware event builder to
processor• 2 processors for event processing• Communication to TKR/CAL/ACD systems unified
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 14
Optimization – SummaryOptimization – Summary
• Serial LVDS (Low-Voltage-Differential-Swing) protocol with Data, Clock, Reset, Return-Data to each front-end system and between DAQ modules (see LAT-TD-00606)
• Buffering of event data fragments at each module stage to meet dead-time requirements– TKR front-end -> TEM -> Event-Builder -> LAT
Communication Board -> CPU -> Spacecraft Solid-State Recorder
• Flow-control between buffer stages to meet non-overwriting and data consistency requirements
• Utilization of ASIC’s to meet volume, power, and cost constraints
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 15
HeritageHeritage
• Similar data-acquisition system was used on balloon flight (TEM, one event-processing CPU, one spacecraft-interface-equivalent control CPU)
• Electronics components: mostly components with flight-heritage (FPGA’s, LVDS converters, memories)
• ASIC technology same as for tracker, calorimeter, ACD systems
• Trigger, dataflow, event assembly, and event filter processing very similar to past high-energy physics experiments
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 16
Summary of July Delta-PDR ReviewSummary of July Delta-PDR Review
• “The electronics including software was already baselined at the January PDR review”
• “Work with GSFC branch to qualify poly-switches for use in the LAT electronics”– Approved
• “Ensure that FPGA design practices adhere to GSFC guidelines and recommendations for space-flight applications”– Working with Rich Katz at GSFC to review LAT FPGA
designs. In process of sending designs to GSFC for review
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 17
Summary of July Delta-PDR Review (Con’t)Summary of July Delta-PDR Review (Con’t)
• “Determine the need date for processor down-select based on software design impact”– Have selected BAE RAD750
• “Finalize the flight-software management plan and test plan”– Flight software management plan (LAT-MD-00104-02)
entered into cyberdocs 6 November 2002– Flight software test plan (LAT-TD-00786-01) entered into
cyberdocs 10 June 2002
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 18
Summary of July Delta-PDR Review (Con’t)Summary of July Delta-PDR Review (Con’t)
• “Identify solution path to replace the functionality that would have been provided by SCL COTS tool in the flight software. Coordinate with I&T and mission operations”– I&T has adopted a low level toolset (Python, Qt, XML,
MySQL) to implement the EGSE side of the I&T test environment. FSW provides the hardware drivers for the embedded system. Code already exists and is running on test stands to replace the SCL register manipulation model. FSW has adopted the I&T low level toolkit for its Test Executive.
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 19
GLAST Large Area Telescope:GLAST Large Area Telescope:
Electronics, Data Acquisition & Flight Software Management
Gunther HallerStanford Linear Accelerator CenterManager, Electronics, DAQ & FSWLAT Chief Electronics Engineer
[email protected](650) 926-4257
Gamma-ray Large Gamma-ray Large Area Space Area Space TelescopeTelescope
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 20
Management OutlineManagement Outline
• Team Leads• Team Partners• Contingency (Mass, Power, Cost)• Organization Chart• Work Flow• Testing Overview• Fabrication Plan• Schedule & Critical Path• Cost• Procurements• Configuration Management• Issues and Concerns• Summary
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 21
Team LeadsTeam Leads
• Gunther Haller– Project Manager Electronics, DAQ, Instrument Software– Chief Electronics Engineer– PCMS Schedule & Cost Lead
• JJ Russell– Instrument (Flight) Software Lead
• Mike Huffer– Data-Acquisition System Lead
• Dave Nelson– Mechanical & Thermal Engineering Lead– I&T Lead– Power/EMI System Lead
• Jobe Noriel– Packaging Engineering Lead
• Jerry Clinton– Manufacturing Lead
• Nick Virmani/Darren Marsh– Mission/Quality Assurance
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 22
Team PartnersTeam Partners
• Naval Research Lab– Spacecraft interface board (Silver Engineering)– Instrument flight software (Boot Code, SC Interface)– CAL front-end electronics
• University of Santa-Cruz– Tracker front-end electronics
• Goddard Space Flight Center– ACD front-end electronics
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 23
Contingency HandlingContingency Handling
• All contingency (Power, Mass, Cost) is held at LAT project level• Change requests to LAT Change Control Board are required to
account for variance• 4.1.7 Changes which required increase in cost, mass, power:
Change Request # Description StatusLAT-XR-01242 Flight Software
Labor Increase (SLAC)
Approved
LAT-XR-01753 Flight Software Labor Increase (NRL)
Approved
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 24
Organization ChartsOrganization Charts
Section 7.4 Elec, DAQ, Flt SW Overview
ReliabilityD. NelsonSU-SLAC
WBS 4.1.7.2
Quality AssuranceD. Marsh/N. Virmani
SU-SLAC/NRLWBS 4.1.7.2
DAQM. HufferSU-SLAC
WBS 4.1.7.4/4.1.7.5
Enclosures/HarnessM .FreytagSU-SLAC
WBS 4.1.7.7/4.1.7.8
Power SystemD. NelsonSU-SLAC
WBS 4.1.7.6
Instrument SoftwareJ. RussellSU-SLAC
WBS 4.1.7.9
GSE & OperationM. HufferSU-SLAC
WBS 4.1.7.A
Instrument I&TG. HallerSU-SLAC
WBS 4.1.7.C
Tracker ElexWBS 4.1.4
CAL ElexWBS 4.1.5
ACD ElexWBS 4.1.6
Front-End ElexG. HallerSU-SLAC
Electronics, DAQ & Flight SoftwareG. HallerSU-SLACWBS 4.1.7
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 25
Development Testing LAT SystemDevelopment Testing LAT System
• Processor: Motorola Power-PC• Flight Software• LAT COM engineering modules for
– LAT Communcation– Trigger
• TEM DAQ Assembly• TEM Power-Supply Assembly• 28-V Supply• LAT-TD-00861
Tower Power Supply Assembly
(1.5V/2.5V/3.3V/ 0-100V/0-150V)
TEM DAQ Assembly
COM-card 1: LAT Communication Module
COM-card 2: Trigger Module
28-V Power Supply
Power-PC Processor
Flight Software
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 26
Testing PlanTesting Plan
• ASIC’s are 100% acceptance tested before assembly on boards– Radiation performance is lot
tested for single event effects and total ionizing radiation.
• Function/Performance is tested at the board level
• Qualification and acceptance tests including performance, vibration, EMI/EMC, and thermal vacuum are performed at the component sub-assembly (box) level.
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 27
Fabrication PlanFabrication Plan• ASIC’s
– Design: SLAC– Fabrication: Agilent– Packaging: ASAT
• Printer-Circuit Boards– Design:
• Spacecraft Interface Board: Silver Engineering
• All other DAQ custom modules: SLAC– Fabrication: qualified vendor– Parts procurements: SLAC– Assembly: qualified vendor
• Enclosures– Design: SLAC– Fabrication: qualified vendor
• Module Assembly (PCB’s/cables/enclosure)– Design: SLAC– Assembly: qualified vendor
• Tower Power Supplies– Circuit & board design, fabrication,
assembly: qualified vendor– Enclosure design: SLAC– Assembly: qualified vendor
• Harness– Design: SLAC– Assembly: qualified vendor
• Installation at SLAC
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 28
Work FlowWork Flow
TEM DAQ Assembly
TEM DAQ BoardGCCC, GTCC ASICs TEM DAQ Enclosure
TEM PS Assembly
TEM PS Board
TEM Power Supply Enclosure
GASU Assembly
GASU DAQ BoardGLTC ASIC
GASU Enclosure
PDU Assembly
PDU DAQ BoardGLTC ASIC
PDU Enclosure
SIU Assembly
SIB Board
Crate Enclosure
LCB Board
CPU Board
PS Board
EPU Assembly
Harness
TEM Assembly
LAT Integration 1st stage
Acceptance Test
Acceptance Test
Acceptance Test
Acceptance Test
Acceptance Test
Acceptance Test
GLTC ASIC
Acceptance Test
LAT Integration 2nd stage
LAT Integration 3rd stage
First layer DAQ modules
Second layer DAQ modules
Add Harness
Software Acceptance Test
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 29
Key MilestonesKey Milestones
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 30
Key Milestones
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 31
Critical PathCritical Path
• TEM DAQ Assembly– Flight TEM DAQ PC Board fab and loading Feb 04
• Requires flight TEM ASICs • Tower Power Supplies
– Flight assemblies by March 04• Is out for RFP, expected back March 25
– Depends on vendor response
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 32
Cost by Fiscal YearCost by Fiscal Year
FY00in K$
FY01in K$
FY02in K$
FY03in K$
FY04in K$
FY05in K$
Totalin K$
692 930 1,727 7,013 4,097 1,281 15,737
• W.B.S. 4.1.7 without contingency
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 33
Cost Contingency and ScheduleCost Contingency and Schedule
Item In k$
Budget at Complete (a) 15,737
Contingency at Start* 2,830 18% of (a)
Budgeted Cost for Work Scheduled (b) 4,206
Budgeted Cost for Work Performed 4,148
Actual Cost for Work Performed 4,238
Cost Variance -90 -2.1% of (b)
Schedule Variance -48 -1.1% of (b)
• Status below is as of Jan 31-03
*contingency is held at project level
• Software-specific contingency: see Instrument Software presentation
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 34
Manpower PlanManpower PlanFT
Es
4.1.7 Electronics
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 35
ProcurementsProcurements
• Long-Lead Procurements– Tower power supplies (RFP close March 25)– Processor (RFP in April)– Voltage regulators (after CDR)
• Major Upcoming Procurements Near-Term (< 4 months)– FPGA’s– Connectors– MOS Transistors– DC/DC Converters & Filters– ASIC’s
• Major Upcoming Procurements Long-Term (>4 months)– Enclosures– Harness
• Minor Upcoming Procurements– Miscellaneous electrical components
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 36
Configuration Management and Information Configuration Management and Information TechnologyTechnology
• SLAC CM System– Cyberdocs (web-based document storage): Electronically
stored documents, drawings, procedures, Work-Order-Authorization (WOA’s)
– Risk Item Database– Document Library
• Electronics, DAQ, Flight Software web-site– http://www-glast.slac.stanford.edu– Website is used to share information and store draft
documents, – Directly access CM documents stored in cyberdocs
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 37
Issues and ConcernsIssues and Concerns
• Schedule is very tight– Critical path has little room for delay
• Dependency on delivery of procured items
GLAST LAT Project DOE/NASA Peer Critical Design Review, March 19-20, 2003
G. Haller 4.1.7 Elex Overview-Management V6 38
SummarySummary
• Technically the electronics and instrument software are on track
• Schedule and budget plan are fully in PCMS down to level 7 since PDR, both are on track
• Critical path and contingency analyzed• No unusual risks besides risks of any high-energy physics
experiment and space flight instrument• Testing, fabriation, and workflow plans in place• Experienced management and technical team