gmp binder for northboro elementary modernization / … board meeting on tuesday... · takeoff...
TRANSCRIPT
BUILDING QUALITY THROUGH TEAMWORK
2200 Centrepark West Drive, Suite 100 West Palm Beach, FL 33409 Main: 561-689-8880 Fax: 561-689-8860 www.hedrickbrothers.com
GMP BINDER for Northboro Elementary Modernization / Phase 2
Table of Contents SECTION 0:
1. Transmittals 2. Table of Contents
SECTION 1:
3. GMP 4. Qualifications & Clarifications
SECTION 2:
5. GMP Summary (Spreadsheet) 6. General Conditions Summary (Spreadsheet) 7. Construction Phase Fee Summary (Spreadsheet)
SECTION 3:
8. Exhibit B: GMP Summary 9. Exhibit D: HBC Personnel Assigned During Construction 10. Exhibit E: Const. Manager’s Staff Per Diem Rates (for time extensions) 11. Exhibit F: Construction Team Assigned Representatives 12. Exhibit I: Builder’s Risk Questionnaire
SECTION 4 13. Drawing Log 14. Specifications
SECTION 5:
15. Exhibit S1: Subcontractor’s Participation (by Division) 16. Exhibit S2: List of Major Subcontractors (by Trade) 17. APPENDIX C: Construction Vendors MWBE Letters of Intent 18. M/WBE Confirmation Letters
SECTION 6:
19. Project Schedule
SECTION 7: 20. Beneficial Interest & Disclosure of Ownership Affidavit
BRINGING VISIONS TO REALITY
2200 Centrepark West Drive, Suite 100, West Palm Beach, FL 33409 Main: 561-689-8880 Fax: 561-689-8860 www.hedrickbrothers.com
Northboro Elementary School
Guaranteed Maximum Price (GMP) Phase II
Qualifications & Clarifications
October 29, 2008
Phase II Construction costs totals $23,528,427.00
DIV 02 SITEWORK
1. A $275,000 ALLOWANCE for the Playground Equipment and Playground Surfacing is included. A
$10,000 ALLOWANCE for FPL pole relocation is also included.
DIV 09 FINISHES
1. Acoustical ceilings exclude hurricane, hold down, or retention clips as called for in the specifications, as
the drawings do not specify where this is required. This can be added to the project if requested.
Acoustical wall panels are included at the multi-purpose room and music room.
DIV 10 SPECIALTIES
1. Floor Mats are excluded.
DIV 11 EQUIPMENT
1. Safe at Administration area is excluded.
DIV 16 ELECTRICAL
1. A Class A “Dual Pipe” Fire Alarm system with 2 conduits per panel is included.
2. A $10,000 ALLOWANCE to remove / relocate FPL power lines & utility poles, phone lines, and cable
lines, at the „to be removed‟ road, is included.
HEDRICK BROTHERS GMP SUMMARY Page 1
NORTHBORO ELEMENTARY - PHASE II - GMP 10/29/2008 5:33 PM
Division DescriptionTakeoff
Quantity
Labor
Amount
Material
Amount
Sub
Amount
Total
Amount
1000.000 GENERAL REQUIREMENTS
Scheduling
Schedule Preparation 4,000.00 ls - - 4,000 4,000
Schedule Updates 18.00 mo - - 6,300 6,300
Scheduling 10,300 10,300
Temp: Supplies
Blue Prints 300.00 sets - 31,950 - 31,950
Temp: Supplies 31,950 31,950
Temp: Traffic Control
Security Guard 65.00 wk - - 39,000 39,000
traffic control barricades signs 7.00 mo - 3,728 - 3,728
Temp: Traffic Control 3,728 39,000 42,728
Temp: Protection
Temporary Protection 7,500.00 ls - - 7,500 7,500
Hurricane Prep 5,000.00 ls - - 5,000 5,000
Temporary Fence w/ screen & Removal 1,200.00 lf - - 10,362 10,362
Temp: Protection 22,862 22,862
Controls: Erosion
Maintain Erosion Control 14.00 mo - - 7,000 7,000
Dust Control 360,000.00 sf - - 10,800 10,800
Controls: Erosion 17,800 17,800
Layout
Layout (Own Forces) 17.33 wk 12,911 9,228 - 22,139
Layout 12,911 9,228 22,139
Clean Up
Final Cleanup 48,525.00 ls - - 48,525 48,525
Current Cleanup 90.00 wk 60,346 1,438 - 61,783
Haul Dumpster 133.00 ea - 46,035 - 46,035
Clean Up 60,346 47,473 48,525 156,343
Project Closeout
Project Closeout 1.00 ea 4,098 2,929 - 7,026
Project Closeout 4,098 2,929 7,026
GENERAL REQUIREMENTS
77,354 95,307 138,487 311,148
2000.000 SITE CONSTRUCTION
Surveying
Surveying - Sitework & Buildings 38,885.00 ls - - 38,885 38,885
Utility line locator at conc. demo/util install 2,500.00 ls - - 2,500 2,500
Surveying 41,385 41,385
Demo: Site
Demo Curb & Concrete 10,075.00 ls - - 10,075 10,075
Demo Utilities Sheet C-106 4,670.00 ls - - 4,670 4,670
Demo Utilities 1,820.00 ls - - 1,820 1,820
Demo Utilities @ Phase 1 -1,820.00 ls - - (1,820) (1,820)
Demo: Site 14,745 14,745
Clearing: Site
Clear & Grubbing 2,695.00 ls - - 2,695 2,695
HEDRICK BROTHERS GMP SUMMARY Page 2
NORTHBORO ELEMENTARY - PHASE II - GMP 10/29/2008 5:33 PM
Division DescriptionTakeoff
Quantity
Labor
Amount
Material
Amount
Sub
Amount
Total
Amount
Clearing: Site 2,695 2,695
Earthwk: Site Grading
Crane Access Road 6,910.00 ls - - 6,910 6,910
Earthwork 184,040.00 ls - - 184,040 184,040
Earthwork @ Phase 1 -74,115.00 ls - - (74,115) (74,115)
Grading & Paving as-builts 8,555.00 ls - - 8,555 8,555
Grading & Paving as-builts @ Phase 1 -1,815.00 ls - - (1,815) (1,815)
P & P Bond 8,954.00 ls - - 8,954 8,954
P & P Bond @ Phase 1 -1,965.00 ls - - (1,965) (1,965)
Earthwk: Site Grading 130,564 130,564
Erosion & Sediment Contrl
Maintain Erosion Control & Street Sweeping 17,635.00 ls - - 17,635 17,635
Erosion & Sediment Contrl 17,635 17,635
Water Distribution
Domestic Water Distribution 44,270.00 ls - - 44,270 44,270
Utility stake w/ asbuilts 9,945.00 ls - - 9,945 9,945
Utility stake w/ asbuilts @ Phase 1 -1,300.00 ls - - (1,300) (1,300)
Water Distribution 52,915 52,915
Sanitary Sewer
Sanitary Sewage 36,085.00 ls - - 36,085 36,085
Sanitary Sewer 36,085 36,085
Fire Main
Fire Line Distribution 133,615.00 ls - - 133,615 133,615
4' Dia Check Valve Manhole - 4 ea 8,360.00 ls - - 8,360 8,360
6" Stub-ups @ Bldgs 5,150.00 ls - - 5,150 5,150
Fire Main 147,125 147,125
Storm Drainage
Storm Drainage 247,060.00 ls - - 247,060 247,060
Storm Drainage @ Phase 1 -120,955.00 ls - - (120,955) (120,955)
Storm Drain Condensate 5,765.00 ls - - 5,765 5,765
Storm Drainage 131,870 131,870
Asphalt Paving
Off-site Asphalt Paving turn lane 20,495.00 ls - - 20,495 20,495
Off-site Asphalt Mill & Overlay 38th street 17,100.00 ls - - 17,100 17,100
Turnlane Revision 2,935.00 ls - - 2,935 2,935
Asphalt Paving 40,530 40,530
Sidewalks
Off-site Sidewalks, Demo, HC Ramps 66,735.00 ls - - 66,735 66,735
Sidewalks 66,735 66,735
Parking Lines
Stripage, Signage, & Wheelstops 19,670.00 ls - - 19,670 19,670
Parking Lines 19,670 19,670
Paving: Curbs & Gutters
Type D & F Curbs 38,615.00 ls - - 38,615 38,615
Valley Gutters @ Entrances 3,180.00 ls - - 3,180 3,180
Paving: Curbs & Gutters 41,795 41,795
Athletic/Recreate Surface
Plexicoat Surface & Striping 25,225.00 ls - - 25,225 25,225
Athletic/Recreate Surface 25,225 25,225
Irrigation System
HEDRICK BROTHERS GMP SUMMARY Page 3
NORTHBORO ELEMENTARY - PHASE II - GMP 10/29/2008 5:33 PM
Division DescriptionTakeoff
Quantity
Labor
Amount
Material
Amount
Sub
Amount
Total
Amount
Irrigation System
Irrigation System 116,348.00 ls - - 116,348 116,348
Irrigation System 116,348 116,348
Fencing
Perimeter Fence 138,847.00 ls - - 138,847 138,847
Demo Existing Perimeter Fencing 3,000.00 ls - - 3,000 3,000
Card Reader Prep @ Entry Gates 3.00 ea - - 750 750
Motorized Operators @ Entry Gates 3.00 ea - - 4,500 4,500
Food Service Compressor Enclosure 2,000.00 ls - - 2,000 2,000
Fencing 149,097 149,097
Site Equip: PlayingFields
Basketball Goals-fixed exterior 6,900.00 ls 0 0 6,900 6,900
Playground:Equipment,Surface, & Turf - SEEALLOWANCES
0.00 ls - - 0 0
Site Equip: PlayingFields 6,900 6,900
Landscape
Landscaping 98,299.00 ls - - 98,299 98,299
Sodding 134,700.00 sf - - 28,287 28,287
Roof Barier 500.00 lf - - 6,000 6,000
sodding @ perimeter of site 6,000.00 sf - - 2,100 2,100
Maintenance of perimeter/interior site 82.00 wK - - 10,250 10,250
Landscape 144,936 144,936
SITE CONSTRUCTION 1,186,255 1,186,255
3000.000 CONCRETE
Concrete Work
Soil Treatment 55,000.00 sf - - 4,300 4,300
Concrete Paving 94,314.00 sf - - 334,900 334,900
On-site Sidewalks, w/ Turn Down Curb @
Parent Drop Off
23,669.00 sf - - 143,880 143,880
Sawcut & Demo Driveways 3,500.00 ls - - 3,500 3,500
Off-site Sidewalk 2,095.00 sf - - 6,800 6,800
Site Wall, Sign, Play Yard, Chiller & FPL
Pads
78,500.00 ls - - 78,500 78,500
Picture Frame Finsih @ Courtyard 4,600.00 ls - - 4,600 4,600
Bldg #1 Entry Sturcture inc/ CMU & Brick 26,950.00 ls - - 26,950 26,950
Add Columns w/ Brick Veneer @ Courtyard
Gates, A504, Detail #4
7.00 ea - - 12,600 12,600
Delete 4" Conc Base @ Bldg #3 Courtyard -30,200.00 ls - - (30,200) (30,200)
Site Monument Sign Foundation 2 ea 2.00 ea - - 4,920 4,920
6' 'Backless' & 'Art' Bench Seats (no backs) 22.00 ea - - 7,550 7,550
Building Concrete 99,000.00 sf - - 915,400 915,400
Add Haunch @ CMU Infill Walls,
R266A001504, Detail #3 & #4
105.00 lf - - 7,400 7,400
Bond on Total Scope 1.58% 40,004.00 ls - - 40,004 40,004
MEP Trades concrete flr replace. bldg #2 3,700.00 ls - - 3,700 3,700
Surface Dewatering @ Foundations 1,500.00 ls - - 1,500 1,500
Concrete Grout @ Below grade utility
penetrations
1,000.00 ls - - 1,000 1,000
Arched/reg beams (missing in ctyd/bldg #2)
- 80 cy
58.05 cy - - 73,314 73,314
HEDRICK BROTHERS GMP SUMMARY Page 4
NORTHBORO ELEMENTARY - PHASE II - GMP 10/29/2008 5:33 PM
Division DescriptionTakeoff
Quantity
Labor
Amount
Material
Amount
Sub
Amount
Total
Amount
Concrete Work
Perimeter protection 1,200.00 lf - - 4,500 4,500
Asphalt coating @ HM Frames @ CMU
Walls
75.00 ea - - 4,000 4,000
Brick Veneer 15,500.00 sf - - 221,500 221,500
F & I Brick Lintels (Releaving Angles) 550.00 lf - - 10,040 10,040
CMU Masonry, Rebar, Filled Cells 60,000.00 sf - - 761,500 761,500
Furnish Precast Window Sills 10,350.00 ls - - 10,350 10,350
Install Precast Window Sills 6,400.00 ls - - 6,400 6,400
CMU bullnose adder 1,000.00 ls - - 1,000 1,000
CMU dovetail anchors supply/instl bldg #3 2,400.00 ls - - 2,400 2,400
Concrete Work 2,662,308 2,662,308
Deck: Insulating ConcRoof
Lt Wt Concrete Roof @ Main Areas 100,000.00 ls - - 100,000 100,000
Lt Wt Concrete Roof @ Below Mansards 30,000.00 ls - - 30,000 30,000
Deck: Insulating ConcRoof 130,000 130,000
CONCRETE 2,792,308 2,792,308
5000.000 STEEL
Structural Steel
Pipe Bollard 2.00 ea - - 700 700
Bike Rack 20.00 ea - - 3,450 3,450
Structural Steel - 2 story w/ stairs 1,276,895.00 ls - - 1,276,895 1,276,895
Structural Steel Support @ Roof Hatches 3.00 ea - - 1,500 1,500
Kitchen Hood Support Frame 1.00 ea - - 3,500 3,500
Angle Iron Drywall Bracing 1,800.00 ls - - 1,800 1,800
Grout Column Bases 31.00 ea - - 465 465
Add Pipe Columns @ Mansard Girder
Trusses
31.00 ea - - 7,750 7,750
Stage Curtaqin Support Frame 22.00 lf - - 4,400 4,400
Add Supports for Classroom Projectors 65.00 ea - - 6,500 6,500
Expansion Joints & Misc Angle Iron 30,000.00 ls - - 30,000 30,000
Refurbish Existing Fence @ NE Corner 6,900.00 ls - - 6,900 6,900
Structural Steel 1,343,860 1,343,860
Metal Framing Systems
Lt Gauge Girder & Mansard Trusses, 20 ga
G-90 Metal Deck, 5/8" Plywood, 2x & 1x
Fascia
15,465.00 ls - - 319,028 319,028
Lt Gauge Framing, Plywood, @ Copper
Roofing
585.00 sf - - 8,775 8,775
Metal Framing Systems 327,803 327,803
Metal Fabrications
Metal Fabrication - Alum Railings, Alum
Fencing
286,872.00 ls - - 286,872 286,872
Alum Fencing @ East & West Site
Perimeters
100.00 lf - - 10,000 10,000
5' Alum Gates @ East & West Site
Perimeters
2.00 ea - - 1,500 1,500
4' Alum Gates @ East & West Site
Perimeters
2.00 ea - - 1,300 1,300
Metal Fabrications 299,672 299,672
HEDRICK BROTHERS GMP SUMMARY Page 5
NORTHBORO ELEMENTARY - PHASE II - GMP 10/29/2008 5:33 PM
Division DescriptionTakeoff
Quantity
Labor
Amount
Material
Amount
Sub
Amount
Total
Amount
STEEL 1,971,335 1,971,335
6000.000 CARPENTRY
Rough Carpentry
Rough Carpentry 66,160.00 ls 49,290 35,230 0 84,520
Rough Carpentry 49,290 35,230 84,520
CARPENTRY 49,290 35,230 84,520
7000.000 THERMAL/MOISTURE
Waterproofng
Waterproofing & Brick Seal 43,462.00 ls - - 43,462 43,462
Waterproof CMU @ Brick Veneer 5,351.00 sf - - 13,378 13,378
Waterproofng 56,840 56,840
Foam Insulation
Foam Insulation @ Exterior CMU walls 23,377.00 ls - - 23,377 23,377
Foam Insulation 23,377 23,377
Shingles: Metal
Metal Shingles, Flashing, Underlayments,
Gutter & Downspouts
29,185.00 sf - - 424,500 424,500
Shingles: Metal 424,500 424,500
Metal Roof Panels
Standing Seam Copper, Flashing,
Underlayments, Gutters & Downspouts
585.00 sf - - 28,500 28,500
Metal Roof Panels 28,500 28,500
Roofing Demo
Tear Off Bldg #2 Roof Membrane &
Flashings
37,460.00 ls - - 37,460 37,460
Roofing Demo 37,460 37,460
Membrane: BUR Bitumen
Modified Bituminous Roof w/ Roof Hatches 289,541.00 ls - - 289,541 289,541
Roofing Material 205,000.00 ls - - 205,000 205,000
Material Escalation 29,600.00 ls - - 29,600 29,600
Repair existing bldg #2 lghtwgt deck 5% 565.00 sf - - 5,650 5,650
Lt Wt Concrete Supervision & Mgmt 24,670.00 ls - - 24,670 24,670
Membrane: BUR Bitumen 554,461 554,461
Firestopping
Firestopping / Fire caulking 56,853.00 ls - - 56,853 56,853
Firestopping 56,853 56,853
Joint Sealants
Caulking & Sealants 68,986.00 ls - - 68,986 68,986
Joint Sealants 68,986 68,986
THERMAL/MOISTURE 1,250,977 1,250,977
8000.000 WINDOWS AND DOORS
Frames, Doors & Hardware
HM Frames & HM Doors 145,880.00 ls - - 145,880 145,880
FSC Wood Doors 109,570.00 ls - - 109,570 109,570
Door Hardware 297,330.00 ls - - 297,330 297,330
New Door Slabs @ Bldg #2 22,653.00 ls - - 22,653 22,653
Asphalt Coating @ HM Frames @ CMU
Walls
5,426.00 ls - - 5,426 5,426
HEDRICK BROTHERS GMP SUMMARY Page 6
NORTHBORO ELEMENTARY - PHASE II - GMP 10/29/2008 5:33 PM
Division DescriptionTakeoff
Quantity
Labor
Amount
Material
Amount
Sub
Amount
Total
Amount
Frames, Doors & Hardware
Grey Tint Impact Glass @ Ext HM Doors 13,275.00 ls - - 13,275 13,275
Glass @ Interior Wood Doors 9,894.00 ls - - 9,894 9,894
Frames, Doors & Hardware Installation 79,095.00 ls - - 79,095 79,095
New Door Slabs @ Bldg #2 Installation 59.00 ea - - 6,608 6,608
Frames, Doors & Hardware 689,731 689,731
Doors: Access
Access Doors - 9,000.00 ls 6,705 4,793 0 11,498
Doors: Access 6,705 4,793 11,498
Doors: Coiling
Coiling Door 6,770.00 ls - - 6,770 6,770
Add Door Insulation @ Ext Doors 850.00 ls - - 850 850
Doors: Coiling 7,620 7,620
Windows: Metal
Windows, Door Lites, Storefront, & Curtain
Wall
525,000.00 ls - - 525,000 525,000
Firelite Door Glass @ Bldg #2 25,000.00 ls - - 25,000 25,000
Window Testing 15,000.00 ls - - 15,000 15,000
Windows: Metal 565,000 565,000
WINDOWS AND DOORS 6,705 4,793 1,262,351 1,273,849
9000.000 FINISHES
Stucco
Stucco Repair @ Bldg 2 Windows 1,840.00 lf - - 18,400 18,400
Stucco 18,400 18,400
Drywall & Metal Framing
Metal Framing, Ext Sheathing, Int Drywall, &
Stucco
1,297,800.00 ls - - 1,297,800 1,297,800
Metal Framing @ Ext Soffit @ Mansard 1,460.00 lf - - 7,300 7,300
Drywall & Metal Framing 1,305,100 1,305,100
Acoustic Ceiling
Acoustical Ceiling and Acoustic Panels 172,596.00 ls - - 172,596 172,596
Acoustic Ceiling 172,596 172,596
Flooring
VCT, Carpet, Sht Vinyl, Stairs & Rubber
Base
322,114.00 ls - - 322,114 322,114
Ceramic Tile & Quarry Tile 53,832.00 ls - - 53,832 53,832
Epoxy Grout @ Quarry Tile 4,158.00 sf - - 13,064 13,064
Mud Set @ Quarry Tile 4,158.00 sf - - 13,285 13,285
Bond @ 2% 8,046.00 ls - - 8,046 8,046
Quarry Wall Tile 3,130.00 sf - - 20,439 20,439
Crack Suppression 6,871.00 ls - - 6,871 6,871
Add VCT @ Stage 1,030.00 sf - - 2,575 2,575
8 Coats of Wax @ VCT 67,581.00 sf - - 16,895 16,895
Flooring 457,121 457,121
Flooring Epoxy
Epoxy Flooring w/ Shotblast Prep 7,000.00 unit - - 44,275 44,275
Adjust Quanity 300.00 unit - - 1,898 1,898
Waterproof Membrane 7,975.00 ls - - 7,975 7,975
Flooring Epoxy 54,148 54,148
Flooring Preparition
HEDRICK BROTHERS GMP SUMMARY Page 7
NORTHBORO ELEMENTARY - PHASE II - GMP 10/29/2008 5:33 PM
Division DescriptionTakeoff
Quantity
Labor
Amount
Material
Amount
Sub
Amount
Total
Amount
Flooring Preparition
Flooring Prep @ VCT @ Bldg #2 30,821.00 sf - - 57,000 57,000
Flooring Prep @ VCT @ Bldg #2 Additional
Qty
714.00 sf - - 1,320 1,320
Flooring Prep @ Bldgs #1 & #3 100,000.00 sf - - 10,000 10,000
Flooring Preparition 68,320 68,320
Paints & Coatings
Painting 274,197.00 ls - - 274,197 274,197
Stucco @ Back of Mansard 8,000.00 sf - - 7,600 7,600
Paints & Coatings 281,797 281,797
FINISHES 2,357,482 2,357,482
10000.000 SPECIALTIES
Visual Display Boards
Visual Display Boards 64,793.00 ls - - 64,793 64,793
Visual Display Boards 64,793 64,793
Toilet Compartments
Toilet Compartment & Toilet Accessories 100,410.00 ls - - 100,410 100,410
Electric Hand Dryers @ Gang Bathroom 4.00 ea - - 3,000 3,000
Toilet Compartments 103,410 103,410
Louvers and Vents
Louvers - 15,000.00 ls - - 15,000 15,000
Louvers and Vents 15,000 15,000
Wall & Corner Guards
Corner Guards - 25,000.00 ls - - 25,000 25,000
Wall & Corner Guards 25,000 25,000
Flagpoles
Flagpole 30' hgt page 12 ed spec 4,293.00 ls - - 4,293 4,293
Flagpole Concrete 500.00 ls - - 500 500
Flagpoles 4,793 4,793
Signs and Letters
Signage 69,505.00 ls - - 69,505 69,505
Signage @ Monument Sign (add 1) 1.00 ea - - 2,600 2,600
Signs and Letters 72,105 72,105
Fire Extinguishers Etc
Fire Extinguisher & Cabinet 24,523.00 ls - - 24,523 24,523
Fire blanket 3.00 ea - - 197 197
Fiist Aid kit 3.00 ea - - 189 189
Fire Extinguishers Etc 24,909 24,909
Walkway Covers
Walkway Canopy w/ Bond 195,636.00 ls - - 195,636 195,636
Walkway Covers 195,636 195,636
Partitions
Wire Mesh Partitions 17,213.00 ls - - 17,213 17,213
Partitions 17,213 17,213
Storage Cabinets & Shelving
Metal Lockers 16.00 ea - - 4,984 4,984
Metal Cabinets & Metal Utility Shelving 51,661.00 ls - - 51,661 51,661
Key Cabinet 1.00 ea - - 250 250
HEDRICK BROTHERS GMP SUMMARY Page 8
NORTHBORO ELEMENTARY - PHASE II - GMP 10/29/2008 5:33 PM
Division DescriptionTakeoff
Quantity
Labor
Amount
Material
Amount
Sub
Amount
Total
Amount
Storage Cabinets & Shelving
Lockable Narcotics Cabinet 24"w x 30"hx
10"d @ Clinic
1.00 ea - - 250 250
Lockable Storage Cabinet @ Clinic 1.00 ea - - 250 250
Storage Cabinets & Shelving 57,395 57,395
Misc Specialties
Clock - INSTALLATION 56.00 ea 459 0 0 459
Clock - INSTALLATION 14.00 ea 115 - 115
Clock - INSTALLATION 19.00 ea 156 - 156
Misc Specialties 729 729
SPECIALTIES 729 580,254 580,983
11000.000 EQUIPMENT
Equip: Bank & Vault
Knox box 4.00 ea - - 2,000 2,000
Drop Safe 2.00 ea - - 850 850
Equip: Bank & Vault 2,850 2,850
Equip: Curtains & Window
Treatrment
Cubicle Curtain Track Ceilinf Mounted @
Clinic
1,060.00 ls - - 1,060 1,060
Curtain track assembly @ CCTV room 40.00 lf 167 275 0 442
Curtain @ CCTV room 360.00 sf 499 709 0 1,208
Pipe rail to hang lights @ CCTV room 140.00 lf 586 962 0 1,548
Stage Curtains 9,063.00 ls - - 9,063 9,063
Window Treatment 16,747.00 ls - - 16,747 16,747
Equip: Curtains & Window
Treatrment
1,253 1,946 26,870 30,068
Equip: Audio Visual
(62) 80" x 60" Manual and (1) 10' x 12'
Motorized Projector Screens
12,662.00 ls - - 12,662 12,662
Additional Projection Screens 80" x 60" 5.00 ea - - 875 875
Motorized Projection Screens 12' x 5' 1.00 ea - - 1,275 1,275
Motorized Projection Screens Supports 2.00 ea - - 600 600
Equip: Audio Visual 15,412 15,412
Equip: Commercial Food
Kitchen Equipment, Commercial Washer &
Dryer
452,880.00 ls - - 452,880 452,880
Equip: Commercial Food 452,880 452,880
Equip: Residental Food
Kitchen Appliance 10,367.00 ls - - 10,367 10,367
Equip: Residental Food 10,367 10,367
Equip: Educational
Educational Equipment Sub(lsum)
ls - -
Equip: Industrial/Process
Kiln 1.00 EA 0 0 5,500 5,500
Equip: Industrial/Process 5,500 5,500
EQUIPMENT 1,253 1,946 513,879 517,077
12000.000 FURNISHINGS
HEDRICK BROTHERS GMP SUMMARY Page 9
NORTHBORO ELEMENTARY - PHASE II - GMP 10/29/2008 5:33 PM
Division DescriptionTakeoff
Quantity
Labor
Amount
Material
Amount
Sub
Amount
Total
Amount
Manufactured Casework
Manufact. Casework-recessed display case 883,789.00 ls - - 883,789 883,789
Delete Metal Cabinets -219,059.00 ls - - (219,059) (219,059)
Bond @ 2.5% 16,618.00 ls - - 16,618 16,618
Adjust Plastic Laminate Qtys 60,411.00 ls - - 60,411 60,411
Bond on HB Add @ 2.5% 1,510.00 ls - - 1,510 1,510
Manufactured Casework 743,269 743,269
FURNISHINGS 743,269 743,269
14000.000 ELEVATOR
Hydraulic Elevators
Hydraulic Elevator 53,897.00 ls - - 53,897 53,897
Hydraulic Elevators 53,897 53,897
ELEVATOR 53,897 53,897
15000.000 MECHANICAL
Fire Sprinkler
Fire Sprinkler 281,604.00 ls - - 281,604 281,604
Fire Penetrations Safing 1,527.00 ls - - 1,527 1,527
Fire Sprinkler 283,131 283,131
Plumbing
Plumbing inc Bond 734,905.00 ls - - 734,905 734,905
Grease Traps inc Bond 22,440.00 ls - - 22,440 22,440
Plumbing 757,345 757,345
HVAC Systems
TEMPORARY HVAC (mo) 8.00 mo - 42,600 0 42,600
HVAC Sub (lsum) 2,475,000.00 ls - - 2,475,000 2,475,000
HVAC Systems 42,600 2,475,000 2,517,600
MECHANICAL 42,600 3,515,476 3,558,076
16000.000 ELECTRICAL
Electrical
ELECTRICAL inc Bond 2,726,000.00 ls - - 2,726,000 2,726,000
Fire Alarm @ PIV 24,300.00 ls - - 24,300 24,300
Lutron Lighting Ctl Sys & Piperail @ CCTV
Prod Rm
6,300.00 ls - - 6,300 6,300
Intercom 3" Riser System 14,000.00 ls - - 14,000 14,000
120v Heat Detector & Contactor @ Kilns 2,800.00 ls - - 2,800 2,800
Heat Detector @ Elev Landing 2,700.00 ls - - 2,700 2,700
Class 'A' "Dual Pipe" Fire Alarm System 18,000.00 ls - 18,000 18,000
Additional Fire Alarm Devices 10,000.00 ls - 10,000 10,000
Replace Bldg #2 Devices & Wiring 21,800.00 ls - 21,800 21,800
Emergency Panel Coordination Study &
Panel Upgrade
10,000.00 ls - 10,000 10,000
Lightning Detection & Warning System 1,750.00 ls - - 1,750 1,750
Add 13 GPS Clocks 2,500.00 ls - - 2,500 2,500
Concrete @ Tranformer Pad 5,000.00 ls - 5,325 5,325
PA & Intercom Systems 79,800.00 ls - - 79,800 79,800
Art-Tronics Wireless Speakers @ Stage 10,000.00 ls - - 10,000 10,000
Electrical 5,325 2,929,950 2,935,275
Power Generation
Fuel / auto transfer switch / exhaust /
controls systems
34,865.00 INC - 37,131 0 37,131
HEDRICK BROTHERS GMP SUMMARY Page 10
NORTHBORO ELEMENTARY - PHASE II - GMP 10/29/2008 5:33 PM
Division DescriptionTakeoff
Quantity
Labor
Amount
Material
Amount
Sub
Amount
Total
Amount
Power Generation 37,131 37,131
High Voltage Distribution
Relocate FPL Power Poleswithin easements - SEEALLOWANCES
0.00 ls - - 0 0
ELECTRICAL 42,456 2,929,950 2,972,406
HEDRICK BROTHERS GMP SUMMARY Page 11
NORTHBORO ELEMENTARY - PHASE II - GMP 10/29/2008 5:33 PM
Estimate Totals
Description Amount Totals Rate
Labor 135,331
Material 222,332
Subcontract 19,295,919
TOTAL DIVISIONS 1-16 19,653,582
INSURANCE & BOND 468,589
CONSTRUCTION PHASE FEE 1,422,424
GENERAL CONDITIONS 335,748
CONSTRUCTION MANAGER'S FEE 1,109,405
OWNER'S CONST CONTINGENCY 491,340
OWNER'S ALLOWANCE 285,000
SUB-TOTAL 23,766,088
DEDUCT: SALES TAX RECOVERY (237,661)
TOTAL GMP PHASE II 23,528,427
TOTAL GMP PHASE I 2,002,889
PRECONSTRUCTION PHASE FEE 179,971
TOTAL CONSTRUCTION COST 25,711,287
HEDRICK BROTHERS GENERAL CONDITIONS SUMMARY Page 1
NORTHBORO ELEMENTARY - PHASE II - GC'S 10/29/2008 11:34 AM
Phase DescriptionTakeoff
Quantity
Labor
Amount
Material
Amount
Sub
Amount
Equip
Amount
Total
Amount
GENERAL CONDITIONS
1300.010 Personnel: Supervision
Superintendent Vehicle Expense 71.00 wk - 11,342 - 8,696 20,038
Asst. Superintendent Vehicle Expense 71.00 wk - 11,342 - 7,183 18,526
Personnel: Supervision 22,685 15,879 38,564
1310.010 Personnel: Proj. Managmnt
Senior Project Manager Vehicle
Expense
71.00 wk - 6,805 - 8,696 15,501
HB Truck/Hauling 35.00 wk 4,555 - - 1,491 6,046
Personnel: Proj. Managmnt 4,555 6,805 10,187 21,547
1510.010 Utilities: Temporary
Temp Electricity 16.25 mo - 43,266 - - 43,266
Rework Temp Electricity to Job
Trailers
4,758.00 ls - 5,067 - - 5,067
Temp Phone - HB Phone & Fax 21.50 mo - 10,304 - - 10,304
Temp Phone - SD Phone & Fax 21.50 mo - 10,304 - - 10,304
Temp Phone - SD T-1 21.50 mo - 11,449 - - 11,449
Supt Phone 16.25 mo - 1,731 - - 1,731
Asst Supt Phone 16.25 mo - 1,731 - - 1,731
Senior Project Mgr Phone 16.25 mo - 1,385 - - 1,385
Asst Project Mgr Phone 16.25 mo - 1,385 - - 1,385
LEED Asst Project Mgr Phone 16.25 mo - 415 - - 415
Project Coordinator Phone 16.25 mo - 1,385 - - 1,385
Temp Water 16.25 mo - 17,306 - - 17,306
Temp Toilets (8) 16.25 mo - 15,576 - - 15,576
SD Trailer Chemical Toilet 16.50 mo - 14,058 - - 14,058
Utilities: Temporary 135,359 135,359
1520.010 Temp: Facilities
SD Office Trailer 16.50 mo - 8,786 - - 8,786
SD Office Trailer - Security System 16.50 mo - 3,515 - - 3,515
SD Office Trailer - Drinking Water
Service
16.50 mo - 2,636 - - 2,636
SD Office Trailer - Coffee Service 16.50 mo - 1,757 - - 1,757
HB Trailer #1 - Mgmt 16.50 mo - 8,786 - - 8,786
HB Trailer #2 - Supt / Conference 16.50 mo - 8,786 - - 8,786
HB Trailer #1 & #2 - Security System 16.50 mo - 3,515 - - 3,515
Office Trailer - Janitorial Service 16.50 mo - 6,590 - - 6,590
Tool Trailers - 2 ea 13.25 mo - 3,528 - - 3,528
Job Site Consumables 16.25 mo - 8,653 - - 8,653
Computer Service - HB, M.O.
Equipment
16.25 mo - 6,094 - 6,094
Computer Leasing 21.50 mo - 2,365 - 2,365
Computer Leasing 19.50 mo - 2,145 - 2,145
Software Licensing 16.25 mo - 5,281 - 5,281
Temp: Facilities 56,551 15,885 72,437
1520.020 Temp: Supplies
Cups & Ice 13.25 mo - 3,528 - - 3,528
Office Supplies 16.25 mo - 10,384 - - 10,384
Progress Photographs 3,000.00 ls - 3,195 - - 3,195
Aerial Photographs 13.25 mo - 1,764 - - 1,764
Temp: Supplies 18,870 18,870
1520.030 Temp: Office Supplies
Copy Expense 16.25 mo - 2,163 - - 2,163
Postage/FedEx 16.25 mo - 6,057 - - 6,057
HEDRICK BROTHERS GENERAL CONDITIONS SUMMARY Page 2
NORTHBORO ELEMENTARY - PHASE II - GC'S 10/29/2008 11:34 AM
Phase DescriptionTakeoff
Quantity
Labor
Amount
Material
Amount
Sub
Amount
Equip
Amount
Total
Amount
Temp: Office Supplies 8,220 8,220
1540.010 Temp: Tools & Equipment
Tools & Equipment 13.25 mo - 7,056 - - 7,056
Project Fuel Expense 13.25 mo - 21,167 - - 21,167
Temp: Tools & Equipment 28,223 28,223
1562.010 Controls: Safety
First Aid Equip 13.25 mo - 3,528 - - 3,528
Safety - Site Visits 36.00 ea - - 9,000 - 9,000
Controls: Safety 3,528 9,000 12,528
GENERAL CONDITIONS 4,555 280,242 24,885 26,066 335,748
Estimate Totals
Description Amount
Labor 4,555
Material 280,242
Subcontract 24,885
Equipment 26,066
TOTAL 335,748
HEDRICK BROTHERS PHASE FEE SUMMARY Page 1
NORTHBORO ELEMENTARY - PHASE II - PHASE FEE10/29/2008 11:36 AM
Phase DescriptionTakeoff
QuantityLabor Amount Sub Amount Total Amount
CONSTRUCTION PHASE FEE
1210.010 Teaming Mgmt
MBE Mentoring - Milton Grey 71.00 wk - 59,669 59,669
MBE Foreman - Gavin Grey 71.00 wk - 153,695 153,695
Teaming Mgmt 213,364 213,364
1300.010 Personnel: Supervision
Superintendent 71.00 wk 238,674 - 238,674
Asst. Superintendent 63.00 wk 148,252 - 148,252
Personnel: Supervision 386,925 386,925
1310.010 Personnel: Proj. Managmnt
Project Executive 65.00 wk 98,327 - 98,327
Senior Project Manager 71.00 wk 270,512 - 270,512
Assistant Project Manager 71.00 wk 179,005 - 179,005
LEED Assistant Project Manager 63.00 wk 67,768 - 67,768
Project Coordinator 71.00 wk 143,193 - 143,193
Accounting 71.00 wk 31,950 - 31,950
Executive Assistant 65.00 wk 31,379 - 31,379
Personnel: Proj. Managmnt 822,134 822,134
CONSTRUCTION PHASE
FEE
1,209,060 213,364 1,422,424
Estimate Totals
Description Amount
Labor 1,209,060
Subcontract 213,364
TOTAL 1,422,424
Name/Title % Time Hours/Week Rate/Hour
Duration in
Weeks Total
Snowden Hernandez, Senior Project Manager 100% 40 95.25 71 $270,512
Jim Kleen II, Assistant Project Manager 100% 40 63.03 71 $179,005
Berretta Davis, Project Coordinator 100% 40 50.42 71 $143,193
Rusty Boatwright, Superintendent 100% 40 84.04 71 $238,674
David Smith, Assistant Superintendent 100% 40 58.83 63 $148,252
Gavin Grey, Foreman 100% 40 54.118 71 $153,695
Name/Title % Time Hours/Week Rate/Hour
Duration in
Weeks Total
James E. Kleen, V.P. of Education 30% 12 126.06 65 $98,327
Robyn Chamberlain, Executive Asst 30% 12 40.23 65 $31,379
Cathy Longworth, Accounting 25% 10 45.00 71 $31,950
John Banting, LEED Assistant Project Manager 40% 16 67.23 63 $67,768
Milton Grey, CM Consultant 20% 8 105.05 71 $59,669
TOTAL $1,422,424
PHASE II EXHIBIT D
PERSONNEL ASSIGNED DURING CONSTRUCTION
SUMMARY OF CONSTRUCTION PHASE FEES
NORTHBORO ELEMENTARY MODERNIZATION
PROJECT NO.: 0291-7504
PHASE II EXHIBIT E CONSTRUCTION MANAGER’S STAFF PER DIEM FOR TIME EXTENSIONS
PROJECT NAME: NORTHBORO ELEMENTARY MODERNIZATION
PROJECT NO.: 0291-7504
Name/Title Hrs/Day Rate/Hr. Per Diem Rate Snowden Hernandez 8 95.25 $762.01 Sr. Project Manager Jim Kleen II 8 63.03 $504.24 Assistant Project Manager Rusty Boatwright 8 84.04 $672.32 Superintendent Berretta Davis 8 50.42 $403.36 Project Coordinator Gavin Grey 8 54.118 $432.95 Foreman Total Per Diem $ 2,774.88
PHASE II EXHIBIT F CONSTRUCTION TEAM ASSIGNED REPRESENTATIVES
PROJECT NAME: NORTHBORO ELEMENTARY MODERNIZATION
PROJECT NO.: 0291-7504 Owner: School District of Palm Beach County 3300 Summit Blvd West Palm Beach, FL 33406 Owner’s Authorized Representative: Glen Armbruster, Sr. Projects Administrator 3300 Summit Blvd West Palm Beach, FL 33406 Construction Manager: Hedrick Brothers Construction Co., Inc. 2200 Centre Park West Drive, Ste 100 West Palm Beach, FL 33409 Contact: Snowden Hernandez Architect - Engineer: BRPH ARCHITECTS, ENGINEERS,
CONSTRUCTORS 1475 Centrepark Blvd West Palm Beach, FL 33401 Contact: Leila Rouady
Northboro Elementary School Modernization Project # 07-609-01 Hedrick Brothers Construction Co., Inc.
400 40th Street West Palm Beach, FL 33407 Tel: 561-689-8880 Fax: 561-689-8860
West Palm Beach, FL 33407
COVER
Drawing Number Rev # Rev Date Title % Complete Status Category
C-000 0 6/6/2008 Cover Sheet 100 GMP Phase 2 Construction Set
GENERAL, LIFE SAFETY AND SIGNAGE
Drawing Number Rev # Rev Date Title % Complete Status Category
G-101 1 7/31/2008 Life Safety - Site Plan - Narrative 100 GMP Phase 2 Construction Set
G-102 1 7/31/2008 Life Safety - Composite Plans 100 GMP Phase 2 Construction Set
G-103 1 7/31/2008 Life Safety - Bldg 1 100 GMP Phase 2 Construction Set
G-104 1 7/31/2008 Life Safety - Bldg 2 First Floor 100 GMP Phase 2 Construction Set
G-105 1 7/31/2008 Life Safety - Bldg 2 Second Floor 100 GMP Phase 2 Construction Set
G-106 1 7/31/2008 Life Safety - Bldg 3 First Floor 100 GMP Phase 2 Construction Set
G-107 1 7/31/2008 Life Safety - Bldg 3 Second Floor 100 GMP Phase 2 Construction Set
G-108 1 7/31/2008 Signage Plan - Bldg 1 100 GMP Phase 2 Construction Set
G-109 1 7/31/2008 Signage Plan - Bldg 2 100 GMP Phase 2 Construction Set
G-110 0 6/6/2008 Signage Plan - Bldg 3 100 GMP Phase 2 Construction Set
SURVEY
Drawing Number Rev # Rev Date Title % Complete Status Category
SUR-1 0 6/6/2008 SFRN Survey 100 GMP Phase 2 Construction Set
SUR-2 0 6/6/2008 SFRN Survey 100 GMP Phase 2 Construction Set
CIVILS
Drawing Number Rev # Rev Date Title % Complete Status Category
C-100 0 6/6/2008 Cover Sheet - Civil 100 GMP Phase 2 Construction Set
C-101 1 7/31/2008 Demolition Plan 100 GMP Phase 2 Construction Set
C-102 1 7/31/2008 Stormwater Pollution Prevention Plan 100 GMP Phase 2 Construction Set
C-103 1 7/31/2008 Drainage Map 100 GMP Phase 2 Construction Set
C-104 1 7/31/2008 Horizontal Dimensioning Plan 100 GMP Phase 2 Construction Set
C-105 1 7/31/2008 Grading, Paving & Drainage Plan 100 GMP Phase 2 Construction Set
C-106 1 7/31/2008 Water & Wastewater Plan 100 GMP Phase 2 Construction Set
2200 CENTREPARK WEST DRIVE, SUITE 100
MAIN: 561-689-8880 FAX: 561-689-8860
CURRENT DRAWING LISTWEST PALM BEACH, FL 33409
Page 1 of 8
Northboro Elementary School Modernization Project # 07-609-01 Hedrick Brothers Construction Co., Inc.
400 40th Street West Palm Beach, FL 33407 Tel: 561-689-8880 Fax: 561-689-8860
West Palm Beach, FL 33407
2200 CENTREPARK WEST DRIVE, SUITE 100
MAIN: 561-689-8880 FAX: 561-689-8860
CURRENT DRAWING LISTWEST PALM BEACH, FL 33409
C-107 1 7/31/2008 Signage & Pavement Marking Plan 100 GMP Phase 2 Construction Set
C-108 1 7/31/2008 Grading, Paving & Drainage Details 100 GMP Phase 2 Construction Set
C-109 1 7/31/2008 Grading, Paving & Drainage Details 100 GMP Phase 2 Construction Set
C-110 0 6/6/2008 Water Details 100 GMP Phase 2 Construction Set
C-111 0 6/6/2008 Water & Wastewater Details 100 GMP Phase 2 Construction Set
C-112 1 7/31/2008 Wastewater Details & Profile 100 GMP Phase 2 Construction Set
LANDSCAPE AND IRRIGATION
Drawing Number Rev # Rev Date Title % Complete Status Category
LA-1 0 6/6/2008 Tree Alteration Plan 100 GMP Phase 2 Construction Set
LA-2 0 6/6/2008 Tree Alteration Plan 100 GMP Phase 2 Construction Set
LA-3 1 7/31/2008 Landscape Plan 100 GMP Phase 2 Construction Set
LA-4 1 7/31/2008 Landscape Plan 100 GMP Phase 2 Construction Set
LA-5 0 6/6/2008 Landscape Plan 100 GMP Phase 2 Construction Set
LA-6 1 7/31/2008 Landscape Plan 100 GMP Phase 2 Construction Set
IR-1 1 7/31/2008 Irrigation Plan 100 GMP Phase 2 Construction Set
IR-2 1 7/31/2008 Irrigation Legend & Details 100 GMP Phase 2 Construction Set
IR-3 1 7/31/2008 Rainwater Tank & Pump Details 100 GMP Phase 2 Construction Set
STRUCTURAL
Drawing Number Rev # Rev Date Title % Complete Status Category
S-001 0 6/6/2008 Design Information & General Notes 100 GMP Phase 2 Construction Set
S-101 1 7/31/2008 Foundation Layout Building 1 100 GMP Phase 2 Construction Set
S-102 1 7/31/2008 Foundation Layout Building 2 100 GMP Phase 2 Construction Set
S-103 1 7/31/2008 Foundation Layout Building 3 100 GMP Phase 2 Construction Set
S-113 1 7/31/2008 2nd Floor Framing Plan Building 3 100 GMP Phase 2 Construction Set
S-121 1 7/31/2008 Roof Framing Plan Building 1 100 GMP Phase 2 Construction Set
S-123 1 7/31/2008 Roof Framing Plan Building 3 100 GMP Phase 2 Construction Set
S-131 1 7/31/2008 Mansard Framing Plan Building 1 100 GMP Phase 2 Construction Set
S-133 1 7/31/2008 Mansard Framing Plan Building 3 100 GMP Phase 2 Construction Set
S-501 1 7/31/2008 Foundation Details 100 GMP Phase 2 Construction Set
S-502 1 7/31/2008 Foundation Details 100 GMP Phase 2 Construction Set
Page 2 of 8
Northboro Elementary School Modernization Project # 07-609-01 Hedrick Brothers Construction Co., Inc.
400 40th Street West Palm Beach, FL 33407 Tel: 561-689-8880 Fax: 561-689-8860
West Palm Beach, FL 33407
2200 CENTREPARK WEST DRIVE, SUITE 100
MAIN: 561-689-8880 FAX: 561-689-8860
CURRENT DRAWING LISTWEST PALM BEACH, FL 33409
S-511 1 7/31/2008 Floor Framing Details 100 GMP Phase 2 Construction Set
S-512 1 7/31/2008 Framing Details 100 GMP Phase 2 Construction Set
S-521 1 7/31/2008 Roof Framing Details 100 GMP Phase 2 Construction Set
ARCHITECTURAL
Drawing Number Rev # Rev Date Title % Complete Status Category
A-001 1 7/31/2008 Demolition Plan - Bldg 2 First Floor 100 GMP Phase 2 Construction Set
A-002 0 6/6/2008 Demolition Plan - Bldg 2 Second Floor 100 GMP Phase 2 Construction Set
A-003 1 7/31/2008 Site Plan - Overall 100 GMP Phase 2 Construction Set
A-004 1 7/31/2008 Site Plan - Partial 100 GMP Phase 2 Construction Set
A-005 1 7/31/2008 Site Plan - Partial 100 GMP Phase 2 Construction Set
A-102 1 7/31/2008 Floor Plan - Bldg 1 100 GMP Phase 2 Construction Set
A-103 1 7/31/2008 Floor Plan - Bldg 2 First Floor 100 GMP Phase 2 Construction Set
A-104 1 7/31/2008 Floor Plan - Bldg 2 Second Floor 100 GMP Phase 2 Construction Set
A-105 1 7/31/2008 Floor Plan - Bldg 3 First Floor 100 GMP Phase 2 Construction Set
A-106 1 7/31/2008 Floor Plan - Bldg 3 Second Floor 100 GMP Phase 2 Construction Set
A-107 1 7/31/2008 Floor Plan - Courtyard 100 GMP Phase 2 Construction Set
A-108 1 7/31/2008 RCP Plan - Bldg 1 100 GMP Phase 2 Construction Set
A-109 1 7/31/2008 RCP Plan - Bldg 2 First Floor 100 GMP Phase 2 Construction Set
A-110 1 7/31/2008 RCP Plan - Bldg 2 Ssecond Floor 100 GMP Phase 2 Construction Set
A-111 0 6/6/2008 RCP Plan - Bldg 3 First Floor 100 GMP Phase 2 Construction Set
A-112 1 7/31/2008 RCP Plan - Bldg 3 Second Floor 100 GMP Phase 2 Construction Set
A-113 1 7/31/2008 Roof Plan - Bldg 1 100 GMP Phase 2 Construction Set
A-114 1 7/31/2008 Roof Plan - Bldg 2 100 GMP Phase 2 Construction Set
A-115 1 7/31/2008 Roof Plan - Bldg 3 100 GMP Phase 2 Construction Set
A-116 1 7/31/2008 FF&E Plan - Bldg 1 100 GMP Phase 2 Construction Set
A-117 1 7/31/2008 FF&E Plan - Bldg 2 First Floor 100 GMP Phase 2 Construction Set
A-118 1 7/31/2008 FF&E Plan - Bldg 2 Second Floor 100 GMP Phase 2 Construction Set
A-119 1 7/31/2008 FF&E Plan - Bldg 3 First Floor 100 GMP Phase 2 Construction Set
A-120 1 7/31/2008 FF&E Plan - Bldg 3 Second Floor 100 GMP Phase 2 Construction Set
A-201 0 6/6/2008 Perspectives 100 GMP Phase 2 Construction Set
A-202 1 7/31/2008 Exterior Elevations 100 GMP Phase 2 Construction Set
Page 3 of 8
Northboro Elementary School Modernization Project # 07-609-01 Hedrick Brothers Construction Co., Inc.
400 40th Street West Palm Beach, FL 33407 Tel: 561-689-8880 Fax: 561-689-8860
West Palm Beach, FL 33407
2200 CENTREPARK WEST DRIVE, SUITE 100
MAIN: 561-689-8880 FAX: 561-689-8860
CURRENT DRAWING LISTWEST PALM BEACH, FL 33409
A-203 1 7/31/2008 Exterior Elevations 100 GMP Phase 2 Construction Set
A-204 1 7/31/2008 Exterior Elevations 100 GMP Phase 2 Construction Set
A-205 1 7/31/2008 Exterior Elevations 100 GMP Phase 2 Construction Set
A-206 0 6/6/2008 Exterior Elevations 100 GMP Phase 2 Construction Set
A-301 1 7/31/2008 Building Sections - Bldg 1 100 GMP Phase 2 Construction Set
A-302 0 6/6/2008 Building Sections - Bldg 3 100 GMP Phase 2 Construction Set
A-303 1 7/31/2008 Wall Sections 100 GMP Phase 2 Construction Set
A-304 1 7/31/2008 Wall Sections 100 GMP Phase 2 Construction Set
A-305 1 7/31/2008 Wall Types 100 GMP Phase 2 Construction Set
A-306 1 7/31/2008 Wall Types 100 GMP Phase 2 Construction Set
A-401 1 7/31/2008 Enlarged Interior Plans 100 GMP Phase 2 Construction Set
A-402 1 7/31/2008 Enlarged Interior Plans 100 GMP Phase 2 Construction Set
A-403 1 7/31/2008 Enlarged Plans 100 GMP Phase 2 Construction Set
A-404 1 7/31/2008 Enlarged Plans - Toilets 100 GMP Phase 2 Construction Set
A-405 0 6/6/2008 Enlarged Plans - Toilets 100 GMP Phase 2 Construction Set
A-406 1 7/31/2008 Enlarged Plans - Stairs 100 GMP Phase 2 Construction Set
A-407 1 7/31/2008 Enlarged Plans - Stairs 100 GMP Phase 2 Construction Set
A-408 1 7/31/2008 Enlarged Plans - Elevator 100 GMP Phase 2 Construction Set
A-409 0 6/6/2008 Enlarged Plans - Canopy (Site) 100 GMP Phase 2 Construction Set
A-411 1 7/31/2008 Millwork 100 GMP Phase 2 Construction Set
A-412 1 7/31/2008 Millwork 100 GMP Phase 2 Construction Set
A-501 1 7/31/2008 Site Details - Canopy Plans 100 GMP Phase 2 Construction Set
A-502 1 7/31/2008 Site Details 100 GMP Phase 2 Construction Set
A-503 1 7/31/2008 Site Details 100 GMP Phase 2 Construction Set
A-504 1 7/31/2008 Site Details - Exterior Courtyard 100 GMP Phase 2 Construction Set
A-505 1 7/31/2008 Details - Doors 100 GMP Phase 2 Construction Set
A-506 0 6/6/2008 Details - Doors 100 GMP Phase 2 Construction Set
A-507 1 7/31/2008 Details - Windows 100 GMP Phase 2 Construction Set
A-508 1 7/31/2008 Details - Roof 100 GMP Phase 2 Construction Set
A-509 1 7/31/2008 Details - Roof 100 GMP Phase 2 Construction Set
A-510 0 6/6/2008 Column Details 100 GMP Phase 2 Construction Set
A-511 0 6/6/2008 Details - Ceilings 100 GMP Phase 2 Construction Set
Page 4 of 8
Northboro Elementary School Modernization Project # 07-609-01 Hedrick Brothers Construction Co., Inc.
400 40th Street West Palm Beach, FL 33407 Tel: 561-689-8880 Fax: 561-689-8860
West Palm Beach, FL 33407
2200 CENTREPARK WEST DRIVE, SUITE 100
MAIN: 561-689-8880 FAX: 561-689-8860
CURRENT DRAWING LISTWEST PALM BEACH, FL 33409
A-512 1 7/31/2008 Details 100 GMP Phase 2 Construction Set
A-513 1 7/31/2008 Details - Play Court Stripping 100 GMP Phase 3 Construction Set
A-514 1 7/31/2008 Site Details 100 GMP Phase 4 Construction Set
A-601 1 7/31/2008 Schedule - Door 100 GMP Phase 2 Construction Set
A-602 1 7/31/2008 Schedule - Finish 100 GMP Phase 2 Construction Set
FOOD SERVICES
Drawing Number Rev # Rev Date Title % Complete Status Category
FS-001 1 7/31/2008 Food Service Equipment Layout 100 GMP Phase 2
FS-002 1 7/31/2008 Food Service Electrical Plan 100 GMP Phase 2
FS-003 1 7/31/2008 Food Service Plumbing Plan 100 GMP Phase 2
FS-004 1 7/31/2008 Food Service Special Conditions Plan 100 GMP Phase 2
FIRE PROTECTION
Drawing Number Rev # Rev Date Title % Complete Status Category
FP-001 1 7/31/2008 Notes, Abbreviations & Symbols 100 GMP Phase 2 Construction Set
FP-101 1 7/31/2008 Fire Protection Plan - Bldg 1 & 2 100 GMP Phase 2 Construction Set
FP-102 0 6/6/2008 Fire Protection Plan - Bldg 3 100 GMP Phase 2 Construction Set
PLUMBING
Drawing Number Rev # Rev Date Title % Complete Status Category
P-001 0 6/6/2008 Notes, Abbreviations & Symbols 100 GMP Phase 2 Construction Set
P-101 1 7/31/2008 Plumbing Plan - Bldg 1 100 GMP Phase 2 Construction Set
P-102 1 7/31/2008 Plumbing Demo Plan - Bldg 2 - 1st Floor 100 GMP Phase 2 Construction Set
P-103 0 6/6/2008 Plumbing Demo Plan - Bldg 2 - 2nd Floor 100 GMP Phase 2 Construction Set
P-104 1 7/31/2008 Plumbing Plan - Bldg 2 - 1st Floor 100 GMP Phase 2 Construction Set
P-105 0 6/6/2008 Plumbing Plan - Bldg 2 - 2nd Floor 100 GMP Phase 2 Construction Set
P-106 1 7/31/2008 Plumbing Plan - Bldg 3 - 1st Floor 100 GMP Phase 2 Construction Set
P-107 1 7/31/2008 Plumbing Plan - Bldg 3 - 2nd Floor 100 GMP Phase 2 Construction Set
P-401 0 6/6/2008 Kithcen Plumbing Plan 100 GMP Phase 2 Construction Set
P-501 1 7/31/2008 Plumbing Details 100 GMP Phase 2 Construction Set
P-502 1 7/31/2008 Plumbing Details 100 GMP Phase 2 Construction Set
Page 5 of 8
Northboro Elementary School Modernization Project # 07-609-01 Hedrick Brothers Construction Co., Inc.
400 40th Street West Palm Beach, FL 33407 Tel: 561-689-8880 Fax: 561-689-8860
West Palm Beach, FL 33407
2200 CENTREPARK WEST DRIVE, SUITE 100
MAIN: 561-689-8880 FAX: 561-689-8860
CURRENT DRAWING LISTWEST PALM BEACH, FL 33409
P-601 1 7/31/2008 Plumbing Schedule 100 GMP Phase 2 Construction Set
P-901 1 7/31/2008 Riser Diagrams - Building 1 100 GMP Phase 2 Construction Set
P-902 1 7/31/2008 Riser Diagrams - Building 2 100 GMP Phase 2 Construction Set
P-903 1 7/31/2008 Sanitary Riser Diagram - Building 3 100 GMP Phase 2 Construction Set
P-904 1 7/31/2008 Water Riser Diagram - Building 3 100 GMP Phase 2 Construction Set
MECHANICAL
Drawing Number Rev # Rev Date Title % Complete Status Category
M-001 0 6/6/2008 Notes, Abbreviations & Symbols 100 GMP Phase 2 Construction Set
M-003 1 7/31/2008 Mechanical Site Plan 100 GMP Phase 2 Construction Set
M-004 1 7/31/2008 Mechanical Roof Plan 100 GMP Phase 2 Construction Set
M-101 1 7/31/2008 Mechanical Plan - Bldg 1 100 GMP Phase 2 Construction Set
M-102 0 6/6/2008 Mechanical Demo Plan - Bldg 2 - 1st Floor 100 GMP Phase 2 Construction Set
M-103 0 6/6/2008 Mechanical Demo Plan - Bldg 2 - 2nd Floor 100 GMP Phase 2 Construction Set
M-104 1 7/31/2008 Mechanical Plan - Bldg 2 - 1st Floor 100 GMP Phase 2 Construction Set
M-105 1 7/31/2008 Mechanical Plan - Bldg 2 - 2nd Floor 100 GMP Phase 2 Construction Set
M-106 1 7/31/2008 Mechanical Plan - Bldg 3 - 1st Floor 100 GMP Phase 2 Construction Set
M-107 1 7/31/2008 Mechanical Plan - Bldg 3 - 2nd Floor 100 GMP Phase 2 Construction Set
M-401 1 7/31/2008 Enlarged Mechanical Room Plans 100 GMP Phase 2 Construction Set
M-402 0 6/6/2008 Enlarged Mechanical Room Plans 100 GMP Phase 2 Construction Set
M-403 0 6/6/2008 Enlarged Mechanical Room Plans 100 GMP Phase 2 Construction Set
M-404 0 6/6/2008 Enlarged Mechanical Room Plans 100 GMP Phase 2 Construction Set
M-501 1 7/31/2008 Mechanical Details 100 GMP Phase 2 Construction Set
M-502 1 7/31/2008 Mechanical Details 100 GMP Phase 2 Construction Set
M-503 1 7/31/2008 Mechanical Details 100 GMP Phase 2 Construction Set
M-601 1 7/31/2008 Mechanical Schedules 100 GMP Phase 2 Construction Set
M-602 1 7/31/2008 Mechanical Schedules 100 GMP Phase 2 Construction Set
M-603 1 7/31/2008 Mechanical Schedules 100 GMP Phase 2 Construction Set
M-604 0 6/6/2008 Chilled Water Flow Diagram 100 GMP Phase 2 Construction Set
M-701 0 6/6/2008 Mechanical Controls 100 GMP Phase 2 Construction Set
M-702 1 7/31/2008 Mechanical Controls 100 GMP Phase 2 Construction Set
M-703 1 7/31/2008 Mechanical Controls 100 GMP Phase 2 Construction Set
Page 6 of 8
Northboro Elementary School Modernization Project # 07-609-01 Hedrick Brothers Construction Co., Inc.
400 40th Street West Palm Beach, FL 33407 Tel: 561-689-8880 Fax: 561-689-8860
West Palm Beach, FL 33407
2200 CENTREPARK WEST DRIVE, SUITE 100
MAIN: 561-689-8880 FAX: 561-689-8860
CURRENT DRAWING LISTWEST PALM BEACH, FL 33409
ELECTRICAL
Drawing Number Rev # Rev Date Title % Complete Status Category
E-001 1 7/31/2008 Legend & Abbreviations 100 GMP Phase 2 Construction Set
E-002 0 6/6/2008 General Notes 100 GMP Phase 2 Construction Set
E-101 1 7/31/2008 Site Lighting & Photometric Plan 100 GMP Phase 2 Construction Set
E-102 1 7/31/2008 Site Power & Systems 100 GMP Phase 2 Construction Set
E-103 0 6/6/2008 Site Canopy Plan 100 GMP Phase 2 Construction Set
E-104 1 7/31/2008 Building 1 Lighting Plan 100 GMP Phase 2 Construction Set
E-105 1 7/31/2008 Building 1 Power Plan 100 GMP Phase 2 Construction Set
E-106 1 7/31/2008 Building 1 Systems Plan 100 GMP Phase 2 Construction Set
E-107 0 6/6/2008 Building 2 First Demo 100 GMP Phase 2 Construction Set
E-108 1 7/31/2008 Building 2 First Floor Lighting Plan 100 GMP Phase 2 Construction Set
E-109 1 7/31/2008 Building 2 First Floor Power Plan 100 GMP Phase 2 Construction Set
E-110 1 7/31/2008 Building 2 First Floor Systems Plan 100 GMP Phase 2 Construction Set
E-111 0 6/6/2008 Building 2 Second Floor Demo 100 GMP Phase 2 Construction Set
E-112 0 6/6/2008 Building 2 Second Floor Lighting Plan 100 GMP Phase 2 Construction Set
E-113 0 6/6/2008 Building 2 Second Floor Power Plan 100 GMP Phase 2 Construction Set
E-114 1 7/31/2008 Building 2 Second Floor Systems Plan 100 GMP Phase 2 Construction Set
E-115 1 7/31/2008 Building 3 First Floor Lighting Plan 100 GMP Phase 2 Construction Set
E-116 1 7/31/2008 Building 3 First Floor Power Plan 100 GMP Phase 2 Construction Set
E-117 1 7/31/2008 Building 3 First Floor Systems Plan 100 GMP Phase 2 Construction Set
E-118 1 7/31/2008 Building 3 Second Floor Lighting Plan 100 GMP Phase 2 Construction Set
E-119 1 7/31/2008 Building 3 Second Floor Power Plan 100 GMP Phase 2 Construction Set
E-120 1 7/31/2008 Building 3 Second Floor Systems Plan 100 GMP Phase 2 Construction Set
E-501 0 6/6/2008 Enlargements 100 GMP Phase 2 Construction Set
E-502 1 7/31/2008 Enlargements 100 GMP Phase 2 Construction Set
E-503 0 6/6/2008 Enlargements 100 GMP Phase 2 Construction Set
E-504 1 7/31/2008 Enlargements 100 GMP Phase 2 Construction Set
E-601 1 7/31/2008 Partial Electrical One-Line Diagram 100 GMP Phase 2 Construction Set
E-602 0 6/6/2008 Partial Electrical One Line Diagram 100 GMP Phase 2 Construction Set
E-701 1 7/31/2008 Intercom Riser Diagram 100 GMP Phase 2 Construction Set
Page 7 of 8
Northboro Elementary School Modernization Project # 07-609-01 Hedrick Brothers Construction Co., Inc.
400 40th Street West Palm Beach, FL 33407 Tel: 561-689-8880 Fax: 561-689-8860
West Palm Beach, FL 33407
2200 CENTREPARK WEST DRIVE, SUITE 100
MAIN: 561-689-8880 FAX: 561-689-8860
CURRENT DRAWING LISTWEST PALM BEACH, FL 33409
E-702 1 7/31/2008 TV & Data Riser Diaagram 100 GMP Phase 2 Construction Set
E-703 1 7/31/2008 Security Riser Diagram 100 GMP Phase 2 Construction Set
E-704 0 6/6/2008 Fire Alarm Riser Diagram 100 GMP Phase 2 Construction Set
E-705 0 6/6/2008 EMCS Riser Diagram 100 GMP Phase 2 Construction Set
E-801 1 7/31/2008 Voice Data & Card Access Details 100 GMP Phase 2 Construction Set
E-802 0 6/6/2008 Details 100 GMP Phase 2 Construction Set
E-803 1 7/31/2008 Video Surveillance Systems Details 100 GMP Phase 2 Construction Set
E-804 0 6/6/2008 Details 100 GMP Phase 2 Construction Set
E-805 0 6/6/2008 Classroom Projector Wiring Detail 100 GMP Phase 2 Construction Set
E-806 0 6/6/2008 Cafeteria-Media Projector Wiring Detail 100 GMP Phase 2 Construction Set
E-807 0 6/6/2008 Details 100 GMP Phase 2 Construction Set
E-901 1 7/31/2008 Schedules 100 GMP Phase 2 Construction Set
E-902 1 7/31/2008 Schedules 100 GMP Phase 2 Construction Set
E-903 1 7/31/2008 Schedules 100 GMP Phase 2 Construction Set
E-904 1 7/31/2008 Schedules 100 GMP Phase 2 Construction Set
E-905 1 7/31/2008 Schedules 100 GMP Phase 2 Construction Set
E-906 1 7/31/2008 Schedules 100 GMP Phase 2 Construction Set
Page 8 of 8
NORTHBORO ELEMENTARY SCHOOL
BRPH ARCHITECTS/ENGINEERS, INC.TABLE OF CONTENTS
DIVISION 1 - GENERAL REQUIREMENTS
Section 01010 Summary of Work 06.16.08
Section 01027 Applications for Payment 06.09.08
Section 01028 Modification Requirements 06.09.08
Section 01039 Coordination and Meetings 06.16.08
Section 01045 Cutting and Patching 06.09.08
Section 01060 Regulatory Requirements 06.16.08
Section 01120 Alteration Project Procedures 06.09.08
Section 01300 Submittals Procedures 06.16.08
Section 01311 Network Analysis Schedules 06.09.08
Section 01351 Construction Waste Management 06.09.08
Section 01353 Noise and Acoustics Management 06.09.08
Section 01354 Environmental Management 06.16.08
Section 01400 Quality Control 06.16.08
Section 01410 Testing Laboratory Services 06.09.08
Section 01421 References 06.16.08
Section 01500 Construction Facilities and Temporary Controls 06.09.08
Section 01540 Security 06.09.08
Section 01560 Temporary Controls 06.09.08
Section 01600 Material, Equipment, and Approved Equals 06.16.08
Section 01611 Environmental Requirements for Products 06.16.08
Section 01650 Starting of Systems 06.09.08
Section 01700 Contract Closeout 06.16.08
Section 01730 Operation and Maintenance Data 06.16.08
Section 01740 Warranties 06.16.08
Section 01810 Commissioning 06.09.08
Section 01811 Sustainable Design Requirements 06.09.08
TECHNICAL SPECIFICATIONS
5859.01 1
NORTHBORO ELEMENTARY SCHOOL
BRPH ARCHITECTS/ENGINEERS, INC.TABLE OF CONTENTS
DIVISION 2 - SITE WORK
Section 02060 Building Demoliton 06.09.08
Section 02070 Selective Demolition 06.09.08
Section 02110 Site Clearing 06.09.08
Section 02200 Earth Moving 06.09.08
Section 02400 Asphalt Paving 06.09.08
Section 02520 Concrete Paving 06.09.08
Section 02580 Pavement Marking 06.09.08
Section 02660 Water Distribution System 06.09.08
Section 02700 Storm Drainage Utilities 06.09.08
Section 02730 Sanitary Sewerage Utilities 06.09.08
Section 02810 Underground Irrigation System 06.09.08
Section 02853 Parking Bumpers 06.09.08
Section 02938 Grass Sodding 06.09.08
Section 02950 Trees, Plants, and Ground Cover 06.09.08
5859.01 2
NORTHBORO ELEMENTARY SCHOOL
BRPH ARCHITECTS/ENGINEERS, INC.TABLE OF CONTENTS
DIVISION 3 – CONCRETE
Section 03100 Concrete Formwork 06.09.08
Section 03200 Concrete Reinforcement 06.09.08
Section 03300 Cast-in-Place Concrete 06.09.08
Section 03341 Fibrous Concrete Reinforcing 06.09.08
Section 03346 Concrete Floor Finishing 06.09.08
Section 03521 Lightweight Insulating Concrete 06.09.08
DIVISION 4 – MASONRY
Section 04100 Masonry Mortar and Grout 06.09.08
Section 04300 Masonry Unit 06.09.08
Section 04340 Reinforced Masony Unit 06.09.08
DIVISION 5 – METALS
Section 05120 Structural Steel 06.09.08
Section 05210 Steel Joists and Joist Girders 06.09.08
Section 05310 Steel Deck 06.09.08
Section 05400 Cold Formed Metal Framing 06.09.08
Section 05500 Metal Fabrications 06.09.08
Section 05510 Metal Stairs 06.09.08
Section 05520 Metal Railings 06.09.08
5859.01 3
NORTHBORO ELEMENTARY SCHOOL
BRPH ARCHITECTS/ENGINEERS, INC.TABLE OF CONTENTS
DIVISION 6 – WOOD AND PLASTICS
Section 06100 Rough Carpentry 06.09.08
Section 06410 Custom Casework 06.16.08
DIVISION 7 – THERMAL AND MOISTURE PROTECTION
Section 07120 Fluid Applied Waterproofing 06.16.08
Section 07160 Bituminous Dampproofing 06.16.08
Section 07170 Bentonite Waterproofing 06.09.08
Section 07181 Water Repellent Penetrant 06.16.08
Section 07191 Vapor Retarders 06.16.08
Section 07212 Extruded Polystyrene Board Insulation 06.16.08
Section 07213 Batt Insulation 06.16.08
Section 07214 Foamed-in-Place Insulation 06.09.08
Section 07255 Cementitious Fireproofing 06.09.08
Section 07270 Firestopping 06.09.08
Section 07341 Metal Shake Roof SystemADDED REV. 1
(7/31/08)
Section 07536 Modified Bitumen Roofing System 06.09.08
Section 07610 Standing Seam Roof and Wall Panels 06.16.08
Section 07615 Metal Roof PanelsADDED REV. 1
(7/31/08)
Section 07620 Flashing, Gutters, Downspouts, and Other Accessories 06.16.08
Section 07724 Roof Hatches 06.09.08
Section 07900 Joint Sealants 06.16.08
DIVISION 8 – DOORS AND WINDOWS
Section 08110 Metal Doors and Frames 06.16.08
Section 08210 Solid Core Wood Doors 06.16.08
Section 08305 Access Doors/Hatches 06.16.08
Section 08331 Rolling Service Doors 06.16.08
Section 08520 Aluminum Windows 06.16.08
Section 08710 Door Hardware 06.16.08
Section 08800 Glazing 06.09.08
DIVISION 9 – FINISHES
Section 09111 Metal Stud Framing System 06.16.08
Section 09220 Portland Cement Plaster 06.16.08
Section 09250 Gypsum Board Systems 06.16.08
Section 09311 Ceramic Tile 06.16.08
Section 09330 Quarry Tile 06.16.08
Section 09511 Suspended Acoustical Ceiling System 06.16.08
Section 09520 Acoustical Wall Panels 06.16.08
Section 09610 Stain Finishing for Concrete Floors 06.09.08
Section 09650 Resilient Flooring 06.16.08
Section 09656 Resilient Terrazzo Tile 06.09.08
Section 09682 Carpet Modular 06.16.08
Section 09705 Epoxy Resin Composition Flooring 06.09.08
Section 09840 Acoustical Wall Treatment 06.09.08
Section 09900 Painting 06.19.08
Section 09963 Interior Acrylic Texture Coating 06.16.08
5859.01 4
NORTHBORO ELEMENTARY SCHOOL
BRPH ARCHITECTS/ENGINEERS, INC.TABLE OF CONTENTS
DIVISION 10 – SPECIALTIES
Section 10100 Marker Boards, Tack Boards, and Walk-off Logo Mats 06.16.08
Section 10171 Toilet Compartments, Urinal Screens, Shower Cubicles 06.16.08
Section 10196 Cubicle Curtains 06.09.08
Section 10211 Fixed Metal Wall Louvers 06.16.08
Section 10250 Door and Wall Protection 06.09.08
Section 10260 Wall Protection Systems 06.09.08
Section 10350 Flagpoles 06.09.08
Section 10415 Display Cases 06.09.08
Section 10420 Plaque 06.16.08
Section 10441 Signage 06.09.08
Section 10508 General/Corridor Lockers 06.09.08
Section 10522 Fire Extinguishers, Cabinets, and Accessories 06.09.08
Section 10532 Aluminum Walkway Covers 06.16.08
Section 10605 Wire Mesh Partitions 06.16.08
Section 10675 Metal Shelving 06.16.08
Section 10700 Window Solar ShadeDELETED REV. 1
(7/31/08)
Section 10800 Toilet and Bath Accessories 06.16.08
Section 10900 Synthetic TurfADDED REV. 1
(7/31/08)
DIVISION 11 – EQUIPMENT
Section 11026 Safe 06.09.08
Section 11050 Library Steel Bookstack Shelving 06.09.08
Section 11062 Stage Curtains - Cotton 06.09.08
Section 11063 Stage Curtains - Polyester 06.09.08
Section 11131 Projection Screens 06.16.08
Section 11400 Foodservice Equipment 06.09.08
Section 11450 Residential Appliances 06.16.08
Section 11480 Athletic Equipment REV. 1 (7/31/08)
Section 11515 Kilns 06.09.08
DIVISION 12 – FURNISHINGS
Section 12345 Laboratory Casework and Equipment 06.09.08
Section 12500 Window Veritcal Blinds 06.16.08
DIVISION 13 - SPECIAL CONSTRUCTION
NOT USED
DIVISION 14 - CONVEYING SYSTEMS
Section 14245 Hydraulic Elevators - Passenger REV. 1 (7/31/08)
5859.01 5
NORTHBORO ELEMENTARY SCHOOL
BRPH ARCHITECTS/ENGINEERS, INC.TABLE OF CONTENTS
DIVISION 15 – MECHANICAL
Section 15000 Basic Mechanical Requirements 06.09.08
Section 15073 Minor HVAC Demolition 06.09.08
Section 15075 Minor Plumbing Demolition 06.09.08
Section 15135 Meters, Gages, and Thermometers for HVAC Piping 06.09.08
Section 15140 Hangers and Supports for Plumbing Piping 06.09.08
Section 15145 Hangers and Supports for HVAC Piping 06.09.08
Section 15170 Motor Requirements for HVAC 06.09.08
Section 15190 Identification for HVAC Piping and Equipment 06.09.08
Section 15242 HVAC Vibration Isolation 06.09.08
Section 15260 Plumbing Piping Insulation 06.09.08
Section 15280 HVAC Equipment Insulation 06.09.08
Section 15290 Ductwork Insulation 06.09.08
Section 15411 Facility Water Distribution 06.09.08
Section 15412 Facility Sanitary Distribution 06.09.08
Section 15413 Facility Storm Drainage 06.09.08
Section 15420 Plumbing Piping 06.09.08
Section 15430 Plumbing Specialties 06.09.08
Section 15440 Plumbing Fixtures 06.09.08
Section 15450 Plumbing Equipment 06.09.08
Section 15500 Fire Suppression 06.09.08
Section 15510 Hydronic Piping 06.09.08
Section 15515 Hydronic Specialties 06.09.08
Section 15535 Refrigeration Piping 06.09.08
Section 15540 HVAC Pumps 06.09.08
Section 15671 Air-Cooled Refrigerant Condensers 06.09.08
Section 15682 Air Cooled Water Chillers 06.09.08
Section 15765 Variable Frequency Motor Controls 06.09.08
Section 15801 HVAC Water Treatment 06.09.08
Section 15817 Electric Resistance Duct Heaters 06.09.08
Section 15855 Air Handling Units 06.09.08
Section 15870 HVAC Power Ventilators 06.09.08
Section 15885 HVAC Air Filters 06.09.08
Section 15890 Ductwork 06.09.08
Section 15895 Air Duct Accessories 06.09.08
Section 15900 Energy Management and Control System 06.09.08
Section 15930 Variable Air Volume Units 06.09.08
Section 15936 Grilles, Registers, Diffusers 06.09.08
Section 15990 Commissioning of HVAC Systems 06.09.08
Section 15991 HVAC Testing, Adjusting and Balancing 06.09.08
Section 15992 Tests – Plumbing Piping Systems 06.09.08
Section 15993 Tests – HVAC Piping Systems 06.09.08
5859.01 6
NORTHBORO ELEMENTARY SCHOOL
BRPH ARCHITECTS/ENGINEERS, INC.TABLE OF CONTENTS
DIVISION 16 – ELECTRICAL
Section 16010 Basic Electrical Requirements 06.09.08
Section 16020 Work Included 06.09.08
Section 16025 Codes, Fees, and Standards 06.09.08
Section 16050 Basic Materials and Methods 06.09.08
Section 16111 Conduit 06.09.08
Section 16112 Cable Trays 06.09.08
Section 16117 Manholes 06.09.08
Section 16123 Building Wire and Cable 06.09.08
Section 16130 Boxes 06.09.08
Section 16141 Wiring Devices 06.09.08
Section 16160 Cabinets and Enclosures 06.09.08
Section 16180 Equipment Wiring Systems 06.09.08
Section 16190 Supporting Devices 06.09.08
Section 16195 Electrical Identification 06.09.08
Section 16420 Service Entrance 06.09.08
Section 16425 Switchboards REV. 2 (9/15/08)
Section 16440 Disconnect Switches 06.09.08
Section 16450 Grounding 06.09.08
Section 16461 Dry Type Transformers 06.09.08
Section 16470 Panelboards 06.09.08
Section 16476 Enclosed Circuit Breakers 06.09.08
Section 16477 Fuses (600-Volt and Below) 06.09.08
Section 16480 Motor Control 06.09.08
Section 16485 Contactors 06.09.08
Section 16495 Transfer Switch 06.09.08
Section 16510 Interior Luminaries 06.09.08
Section 16530 Site Lighting 06.09.08
Section 16535 Emergency Lighting Equipment 06.09.08
Section 16610 Transient Voltage Surge Suppression 06.09.08
Section 16622 Packaged Engine Generator Systems 06.09.08
Section 16650 Energy Management and Control System 06.09.08
Section 16670 Lightning Protection Systems 06.09.08
Section 16721 Fire Alarm and Smoke Detection Systems 06.09.08
Section 16722 Intrusion Detection and Security Access System 06.09.08
Section 16723 Video Surveillance System 06.09.08
Section 16724 Emergency Radio Communications Systems 06.09.08
Section 16725 Access System 06.09.08
Section 16730 GPS Wireless Clock Systems 06.09.08
Section 16765 Intercom Systems 06.09.08
Section 16770 Public Address Systems 06.09.08
Section 16781 Master Television Antenna System (MTAS) 06.09.08
Section 16902 Electric Controls and Relays 06.09.08
Section 16905 Communications System (Data and Voice) 06.09.08
Section 16906 Ceiling Projector System REV. 1 (7/31/08)
Section 16995 Electrical Commissioning 06.09.08
5859.01 7
PHASE II EXHIBIT S LIST OF MAJOR SUBCONTRACTORS
PROJECT NAME: NORTHBORO ELEMENTARY MODERNIZATION
PROJECT NO.: 0291-7504
DIVISION OF WORK
Sitework Concrete
Metals Thermal & Moisture Protection Doors & Windows Doors & Windows Finishes
CORPORATE NAME & ADDRESS AMERICAN ENGINEERING & DEVELOPING 11765 W Okeechobee Rd. Hialeah Gardens, FL 33018 EAGLE METAL FABRICATORS, INC. 4300 SW 59th Ave Davie, FL 33460 STEEL FABRICATORS 3801 Dawes Ave West Palm Beach, FL 33460 HI-TECH ROOFING & SHEET METAL, INC. 2266 4th Ave North Lake Worth, 33461 STUART PAINT & SUPPLY 657 NE Dixie Highway Jensen Beach, FL 34957 SUNRYSE CONSTRUCTION 44575 SE Commerce Avenue, Stuart, FL 34997 D&D QUALITY 1409 Forsythe Road West Palm Beach, FL 33405
PRINCIPAL OR OFFICER’S NAME
Thomas McDonough Patricia A. Fye Michael Daley Robert F. Johnston David Walter Blanka Diamond
LICENSE NO. CGC 020569 U-20235 CCC 058213 CBC 025081 CGC 1511260 CGC 010017
PHASE II EXHIBIT S LIST OF MAJOR SUBCONTRACTORS
PROJECT NAME: NORTHBORO ELEMENTARY MODERNIZATION
PROJECT NO.: 0291-7504
DIVISION OF WORK
Finishes Finishes Finishes Specialties Equipment Furnishings Mechanical Mechanical Mechanical
Electrical
CORPORATE NAME & ADDRESS PHOENIX PAINTING CO. 6303 N. Powerline Rd. Ft. Lauderdale, FL 33309 SUPERIOR INTEROR SYSTEMS, INC. 959 Shotgun Rd. Sunrise, FL 33326 ZAHARION’S FLOORING 1338 South Killian Drive Suite 11 Lake Park, FL 33403 DWYER INDUSTRIES 7025 CR 46A Suite 1071-513 Lake Mary, FL 32746 DESIGN FURNISHINGS 889 Brentwood Drive, Daytona Beach, FL 32117 NEW RIVER CABINETS 700 NW 57th Court Ft. Lauderdale, FL 33309 DODEC 3140 W 84th Street #2 Hialeah, FL 33018 FRANCIS ENGINEERING 1232 SW 31st Avenue Ft. Lauderdale, FL 33312 HPI PLUMBING CONTRACTORS, INC. 2545 Old Okeechobee Rd. West Palm Beach, FL 33409 FASTRAC ELECTRIC CORP 810 Saturn St. #25 Jupiter, FL 33477
PRINCIPAL OR OFFICER’S NAME Richard Gardella
Mary Cooper
Rebecca Zaharion David W. Dwyer Mike McKernan Keith Mosley Trevor Pantry Orrett Francis Glenroy Hessing Shawn Bly
LICENSE NO. U-12253 U-17723 U-17022 PSL08-9486 85012290 2700002665 CMC 03464 6005000011990 CFC 021473 EC 002876
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
Total
Float
PHASE 1
COMMENCEMENT
01000.00 ABATEMENT CLEARANCE LETTER RECEIVED 1 09JUN08 09JUN08 0
01010.00 NOTICE TO PROCEED 1 10JUN08 10JUN08 0
01020.00 DISTRICT MOVE & SALVAGE 5 10JUN08 16JUN08 1
01030.00 PRE-CONSTRUCTION MEETING 1 11JUN08 11JUN08 0
01050.00 MOBILIZATION 4 12JUN08 17JUN08 0
LEED DOCUMENTATION
01120.00 DEMOLITION PROGRESS PHOTOS 56 09JUN08 25AUG08 12
01110.00 SALVAGE PHOTOS, REUSE 46 09JUN08 11AUG08 22
01130.00 MEP RECOVERY DOCUMENTATION 10 09JUN08 20JUN08 58
01100.00 EROSION CONTROL PHOTOS 4 09JUN08 12JUN08 64
SITEWORK
TREE, ROOT PRUNING
02000.99 ROOT PRUNING 20 17JUN08 14JUL08 17
02010.99 TREE RELOCATION 25 15JUL08 18AUG08 17
TEMPORARY PARKING (COMPOUND)
02520.99 TEMPORARY PARKING (COMPOUND) 3 27JUN08 01JUL08 51
SITE DEMOLITION
02020.99 PAVING & CONCRETE FLATWORK REMOVAL 5 18JUN08 24JUN08 0
02030.99 UTILITY DEMOLITION 5 25JUN08 01JUL08 0
02040.99 CHILLER PLANT 4 26JUN08 01JUL08 0
02050.99 ITV TOWER 2 27JUN08 30JUN08 0
02060.99 CUT & STOCKPILE BASE MATERIAL 2 01JUL08 02JUL08 0
02061.99 AUTHORIZATION TO DEMO INTERIOR ROADS 9 15AUG08 27AUG08 0
02062.99 DEMO INTERIOR ROADS ON-SITE 12 28AUG08 10SEP08 0
SITE UTILITIES
02720.99 STORM DRAINAGE SYSTEM - SITE 20 11SEP08 08OCT08 0
02210.99 BACKFILL & COMPACT UTILITIES - SITE 10 09OCT08 22OCT08 0
02730.99 SEWER LINE - SITE 20 09OCT08 05NOV08 0
02220.99 BUILDING PADS 16 23OCT08 13NOV08 0
02660.99 WATER DISTRIBUTION - SITE 20 06NOV08 04DEC08 0
02540.99 U/G CISTERNS/TANKS - SITE 10 02DEC08 15DEC08 0
16101.99 ELECTRICAL U\G R-I - SITE 20 05DEC08 05JAN09 164
2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL
ABATEMENT CLEARANCE LETTER RECEIVED
NOTICE TO PROCEED
DISTRICT MOVE & SALVAGE
PRE-CONSTRUCTION MEETING
MOBILIZATION
DEMOLITION PROGRESS PHOTOS
SALVAGE PHOTOS, REUSE
MEP RECOVERY DOCUMENTATION
EROSION CONTROL PHOTOS
ROOT PRUNING
TREE RELOCATION
TEMPORARY PARKING (COMPOUND)
PAVING & CONCRETE FLATWORK REMOVAL
UTILITY DEMOLITION
CHILLER PLANT
ITV TOWER
CUT & STOCKPILE BASE MATERIAL
AUTHORIZATION TO DEMO INTERIOR ROADS
DEMO INTERIOR ROADS ON-SITE
STORM DRAINAGE SYSTEM - SITE
BACKFILL & COMPACT UTILITIES - SITE
SEWER LINE - SITE
BUILDING PADS
WATER DISTRIBUTION - SITE
U/G CISTERNS/TANKS - SITE
ELECTRICAL U\G R-I - SITE
© Primavera Systems, Inc.
Start Date 09JUN08
Finish Date 07JUN10
Data Date 09JUN08
Run Date 08OCT08 08:10
Early Bar
Progress Bar
Critical Activity
BASZ
HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL
Sheet 1 of 16
ORGANIZED BY AREA
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
Total
Float
PORTABLE CLASSROOM DEMOLITION
02000.70 UTILITY DISCONNECT & CAP 2 18JUN08 19JUN08 0
02010.70 DEMOLITION & REMOVAL 5 20JUN08 26JUN08 0
MAIN BUILDIINGS DEMOLITION
CAFETERIA - EXISTING
02080.99 EXISTING - CAFETERIA DEMOLITION 5 25JUN08 01JUL08 0
BUILDING #1 - EXISTING
02090.99 EXISTING - BUILDING #1 SELECTIVE DEMOLITION 30 02JUL08 12AUG08 0
02091.99 HISTORICAL RESTORATION WEST WALL 10 30JUL08 12AUG08 0
02092.99 COMPLETE DEBRIS REMOVAL 15 06AUG08 26AUG08 0
FINAL SITE PREP
02200.99 GRADE SITE & BALANCE 11 27AUG08 10SEP08 0
BUILDING #3 - EXISTING
02095.99 SELECTIVE DEMOLITION - 1ST FLR - BLDG 3 - EXISTI 15 11SEP08 01OCT08 0
02096.99 SELECTIVE DEMOLITION - 2ND FLR - BLDG 3 - EXISTI 15 29SEP08 17OCT08 0
COMPLETION
17000.01 SUBSTANTIAL COMPLETION - PHASE 1 19 20OCT08 13NOV08 0
PHASE 2
COMMENCEMENT
01000.02 NOTICE TO PROCEED - PHASE 2 11 14NOV08 01DEC08 0
FOUNDATIONS
NEW BUILDING 3
15400.03 INSTALL U/G WATER/SEWER - BLDG 3 - NEW 7 02DEC08 10DEC08 0
15410.03 INSTALL PLUMB R-I - U/G - BLDG 3 - NEW 7 02DEC08 10DEC08 0
15420.03 INSTALL CHILLED WATER R-I U/G- BLDG 3 - NEW 7 02DEC08 10DEC08 0
16110.03 INSTALL ELECT R-I - U/G - BLDG 3 - NEW 7 02DEC08 10DEC08 0
16111.03 INSTALL ELEC U/G DUCTBANK - BLDG 3 - NEW 7 02DEC08 10DEC08 0
01601.03 INSPECT - U/G - BLDG 3 - NEW 3 11DEC08 15DEC08 0
03000.03 LAYOUT FTGS - BLDG 3 - NEW 1 16DEC08 16DEC08 0
03002.03 EXCAVATE INTERIOR FTGS - BLDG 3 - NEW 4 17DEC08 22DEC08 0
03003.03 FORM INTERIOR FTGS - BLDG 3 - NEW 5 19DEC08 26DEC08 2
03005.03 EXCAVATE PERIMETER FTGS - BLDG 3 - NEW 5 23DEC08 30DEC08 0
03200.03 PLACE REBAR INTERIOR FTGS - BLDG 3 - NEW 4 24DEC08 30DEC08 2
2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL
UTILITY DISCONNECT & CAP
DEMOLITION & REMOVAL
EXISTING - CAFETERIA DEMOLITION
EXISTING - BUILDING #1 SELECTIVE DEMOLITION
HISTORICAL RESTORATION WEST WALL
COMPLETE DEBRIS REMOVAL
GRADE SITE & BALANCE
SELECTIVE DEMOLITION - 1ST FLR - BLDG 3 - EXISTI
SELECTIVE DEMOLITION - 2ND FLR - BLDG 3 - EXISTI
SUBSTANTIAL COMPLETION - PHASE 1
NOTICE TO PROCEED - PHASE 2
INSTALL U/G WATER/SEWER - BLDG 3 - NEW
INSTALL PLUMB R-I - U/G - BLDG 3 - NEW
INSTALL CHILLED WATER R-I U/G- BLDG 3 - NEW
INSTALL ELECT R-I - U/G - BLDG 3 - NEW
INSTALL ELEC U/G DUCTBANK - BLDG 3 - NEW
INSPECT - U/G - BLDG 3 - NEW
LAYOUT FTGS - BLDG 3 - NEW
EXCAVATE INTERIOR FTGS - BLDG 3 - NEW
FORM INTERIOR FTGS - BLDG 3 - NEW
EXCAVATE PERIMETER FTGS - BLDG 3 - NEW
PLACE REBAR INTERIOR FTGS - BLDG 3 - NEW
© Primavera Systems, Inc.
Start Date 09JUN08
Finish Date 07JUN10
Data Date 09JUN08
Run Date 08OCT08 08:10
Early Bar
Progress Bar
Critical Activity
BASZ
HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL
Sheet 2 of 16
ORGANIZED BY AREA
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
Total
Float
03006.03 FORM PERIMETER FTGS - BLDG 3 - NEW 5 29DEC08 05JAN09 0
03201.03 PLACE REBAR PERIMETER FTGS - BLDG 3 - NEW 5 31DEC08 07JAN09 0
01630.03 INSPECT - INTERIOR FDNS - BLDG 3 - NEW 2 31DEC08 02JAN09 2
03300.03 POUR INTERIOR FTGS - BLDG 3 - NEW 3 05JAN09 07JAN09 2
01631.03 INSPECT - PERIMETER FDNS - BLDG 3 - NEW 2 08JAN09 09JAN09 0
03301.03 POUR PERIMETER FTGS - BLDG 3 - NEW 4 12JAN09 15JAN09 0
04200.03 MASONRY STEM WALL - BLDG 3 - NEW 1 16JAN09 16JAN09 0
04201.03 SET CMU'S - BLDG 3 - NEW 3 19JAN09 21JAN09 0
03331.03 GROUT CMU'S - BLDG 3 - NEW 1 22JAN09 22JAN09 0
03332.03 TIE COLS - STEM WALL - BLDG 3 - NEW 2 23JAN09 26JAN09 0
02215.03 TERMITE CONTROL - BLDG 3 - NEW 1 27JAN09 27JAN09 0
15411.03 PLUMBING ROUGH-IN - S.O.G. - BLDG 3 - NEW 10 28JAN09 10FEB09 0
16112.03 ELECTRICAL ROUGH-IN - S.O.G. - BLDG 3 - NEW 10 28JAN09 10FEB09 0
02210.03 ROUGH GRADE - S.O.G. - BLDG 3 - NEW 3 11FEB09 13FEB09 0
02211.03 FINE GRADE - S.O.G. - BLDG 3 - NEW 5 16FEB09 20FEB09 0
03100.03 WIRE MESH - S.O.G - BLDG 3 - NEW 2 23FEB09 24FEB09 0
01632.03 INSPECT - SOG - BLDG 3 - NEW 2 25FEB09 26FEB09 0
03310.03 POUR SOG - BLDG 3 - NEW 1 27FEB09 27FEB09 0
NEW BUILDING 1
15400.01 INSTALL U/G WATER/SEWER - BLDG 1 - NEW 7 09DEC08 17DEC08 38
15410.01 INSTALL PLUMB R-I - U/G - BLDG 1 - NEW 7 09DEC08 17DEC08 38
15420.01 INSTALL CHILLED WATER R-I U/G- BLDG 1 - NEW 7 09DEC08 17DEC08 38
16110.01 INSTALL ELECT R-I - U/G - BLDG 1 - NEW 7 09DEC08 17DEC08 38
16111.01 INSTALL ELEC U/G DUCTBANK - BLDG 1 - NEW 7 09DEC08 17DEC08 38
01601.01 INSPECT - U/G - BLDG 1 - NEW 3 18DEC08 22DEC08 38
03000.01 LAYOUT FTGS - BLDG 1 - NEW 1 23DEC08 23DEC08 38
03002.01 EXCAVATE INTERIOR FTGS - BLDG 1 - NEW 4 24DEC08 30DEC08 38
03003.01 FORM INTERIOR FTGS - BLDG 1 - NEW 5 29DEC08 05JAN09 40
03005.01 EXCAVATE PERIMETER FTGS - BLDG 1 - NEW 5 31DEC08 07JAN09 38
03200.01 PLACE REBAR INTERIOR FTGS - BLDG 1 - NEW 4 02JAN09 07JAN09 40
03006.01 FORM PERIMETER FTGS - BLDG 1 - NEW 5 05JAN09 09JAN09 38
03201.01 PLACE REBAR PERIMETER FTGS - BLDG 1 - NEW 5 08JAN09 14JAN09 38
01630.01 INSPECT - INTERIOR FDNS - BLDG 1 - NEW 2 08JAN09 09JAN09 40
03300.01 POUR INTERIOR FTGS - BLDG 1 - NEW 3 12JAN09 14JAN09 40
01631.01 INSPECT - PERIMETER FDNS - BLDG 1 - NEW 2 15JAN09 16JAN09 38
03301.01 POUR PERIMETER FTGS - BLDG 1 - NEW 4 19JAN09 22JAN09 38
04200.01 MASONRY STEM WALL - BLDG 1 - NEW 1 23JAN09 23JAN09 38
2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL
FORM PERIMETER FTGS - BLDG 3 - NEW
PLACE REBAR PERIMETER FTGS - BLDG 3 - NEW
INSPECT - INTERIOR FDNS - BLDG 3 - NEW
POUR INTERIOR FTGS - BLDG 3 - NEW
INSPECT - PERIMETER FDNS - BLDG 3 - NEW
POUR PERIMETER FTGS - BLDG 3 - NEW
MASONRY STEM WALL - BLDG 3 - NEW
SET CMU'S - BLDG 3 - NEW
GROUT CMU'S - BLDG 3 - NEW
TIE COLS - STEM WALL - BLDG 3 - NEW
TERMITE CONTROL - BLDG 3 - NEW
PLUMBING ROUGH-IN - S.O.G. - BLDG 3 - NEW
ELECTRICAL ROUGH-IN - S.O.G. - BLDG 3 - NEW
ROUGH GRADE - S.O.G. - BLDG 3 - NEW
FINE GRADE - S.O.G. - BLDG 3 - NEW
WIRE MESH - S.O.G - BLDG 3 - NEW
INSPECT - SOG - BLDG 3 - NEW
POUR SOG - BLDG 3 - NEW
INSTALL U/G WATER/SEWER - BLDG 1 - NEW
INSTALL PLUMB R-I - U/G - BLDG 1 - NEW
INSTALL CHILLED WATER R-I U/G- BLDG 1 - NEW
INSTALL ELECT R-I - U/G - BLDG 1 - NEW
INSTALL ELEC U/G DUCTBANK - BLDG 1 - NEW
INSPECT - U/G - BLDG 1 - NEW
LAYOUT FTGS - BLDG 1 - NEW
EXCAVATE INTERIOR FTGS - BLDG 1 - NEW
FORM INTERIOR FTGS - BLDG 1 - NEW
EXCAVATE PERIMETER FTGS - BLDG 1 - NEW
PLACE REBAR INTERIOR FTGS - BLDG 1 - NEW
FORM PERIMETER FTGS - BLDG 1 - NEW
PLACE REBAR PERIMETER FTGS - BLDG 1 - NEW
INSPECT - INTERIOR FDNS - BLDG 1 - NEW
POUR INTERIOR FTGS - BLDG 1 - NEW
INSPECT - PERIMETER FDNS - BLDG 1 - NEW
POUR PERIMETER FTGS - BLDG 1 - NEW
MASONRY STEM WALL - BLDG 1 - NEW
© Primavera Systems, Inc.
Start Date 09JUN08
Finish Date 07JUN10
Data Date 09JUN08
Run Date 08OCT08 08:10
Early Bar
Progress Bar
Critical Activity
BASZ
HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL
Sheet 3 of 16
ORGANIZED BY AREA
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
Total
Float
04201.01 SET CMU'S - BLDG 1 - NEW 3 26JAN09 28JAN09 38
03331.01 GROUT CMU'S - BLDG 1 - NEW 1 29JAN09 29JAN09 38
03332.01 TIE COLS - STEM WALL - BLDG 1 - NEW 2 30JAN09 02FEB09 38
02215.01 TERMITE CONTROL - BLDG 1 - NEW 1 03FEB09 03FEB09 38
15411.01 PLUMBING ROUGH-IN - S.O.G. - BLDG 1 - NEW 10 04FEB09 17FEB09 38
16112.01 ELECTRICAL ROUGH-IN - S.O.G. - BLDG 1 - NEW 10 04FEB09 17FEB09 38
02210.01 ROUGH GRADE - S.O.G. - BLDG 1 - NEW 3 18FEB09 20FEB09 38
02211.01 FINE GRADE - S.O.G. - BLDG 1 - NEW 5 23FEB09 27FEB09 38
03100.01 WIRE MESH - S.O.G - BLDG 1 - NEW 2 02MAR09 03MAR09 38
01632.01 INSPECT - SOG - BLDG 1 - NEW 2 04MAR09 05MAR09 38
03310.01 POUR SOG - BLDG 1 - NEW 1 06MAR09 06MAR09 38
NEW BUILDING 3
1ST FLOOR
04200.0301 ERECT MASONRY WALLS TO BEAM - 1ST FLR - BLDG 3 - 20 02MAR09 27MAR09 0
03330.0301 FORM/POUR TIE COLS/BEAMS - 1ST FLR - BLDG 3 - NE 15 12MAR09 01APR09 0
03331.0301 INSTALL EMBEDS - 1ST FLR - BLDG 3 - NEW 5 02APR09 08APR09 0
05100.0301 ERECT STRUCTURAL STEEL/JOISTS - 2ND FLR - BLDG 3 10 09APR09 22APR09 0
09231.0301 METAL FRAMING - TOP TRACK - BLDG 3 - 1ST FLR - N 5 11MAY09 15MAY09 53
08500.0301 WINDOWS - BLDG 3 - 1ST FLR - NEW 10 11MAY09 22MAY09 87
15890.0301 INSTALL DUCTWORK - BLDG 3 - 1ST FLR - NEW 20 18MAY09 15JUN09 53
09230.0301 INSTALL METAL FRAMING - BLDG 3 - 1ST FLR - NEW 20 26MAY09 22JUN09 53
15530.0301 INSTALL HVAC PIPING - BLDG 3 - 1ST FLR - NEW 17 29MAY09 22JUN09 63
15300.0301 INSTALL FIRE SPRKLR ROUGH - BLDG 3 - 1ST FLR - N 20 02JUN09 29JUN09 102
15415.0301 INSTALL PLUMBING ROUGH - BLDG 3 - 1ST FLR - NEW 20 04JUN09 01JUL09 56
15655.0301 INSTALL HVAC EQUIP - BLDG 3 - 1ST FLR - NEW 17 05JUN09 29JUN09 90
16115.0301 INSTALL ELECTRIC ROUGH - BLDG 3 - 1ST FLR - NEW 20 09JUN09 07JUL09 53
13100.0301 INSTALL INTERCOM BACKBOXES - BLDG 3 - 1ST FLR - 15 16JUN09 07JUL09 53
15895.0301 INSTALL DUCTWORK INSULATION - BLDG 3 - 1ST FLR - 20 16JUN09 14JUL09 94
15656.0301 HVAC DUCT CONNECT/HOOK-UP - BLDG 3 - 1ST FLR - N 7 30JUN09 09JUL09 90
01618.0301 INSPECT FIRE SPRINKLER ABOVE CLG - BLDG 3 - 1ST 2 30JUN09 01JUL09 102
01614.0301 INSPECT PLUMBING - BLDG 3 - 1ST FLR - NEW 2 02JUL09 06JUL09 56
01616.0301 INSPECT ELECTRICAL ROUGH - BLDG 3 - 1ST FLR - NE 2 08JUL09 09JUL09 53
01617.0301 INSPECT FRAMING - BLDG 3 - 1ST FLR - NEW 2 10JUL09 13JUL09 53
15657.0301 HVAC PIPING CONNECT/HOOK-UP - BLDG 3 - 1ST FLR - 7 10JUL09 20JUL09 90
01615.0301 INSPECT HVAC - BLDG 3 - 1ST FLR - NEW 2 13JUL09 14JUL09 94
09250.0301 HANG DRYWALL - BLDG 3 - 1ST FLR - NEW 15 14JUL09 03AUG09 53
14102.0301 ELEVATOR RAILS - BLDG 3 - NEW 20 24JUL09 20AUG09 63
2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL
SET CMU'S - BLDG 1 - NEW
GROUT CMU'S - BLDG 1 - NEW
TIE COLS - STEM WALL - BLDG 1 - NEW
TERMITE CONTROL - BLDG 1 - NEW
PLUMBING ROUGH-IN - S.O.G. - BLDG 1 - NEW
ELECTRICAL ROUGH-IN - S.O.G. - BLDG 1 - NEW
ROUGH GRADE - S.O.G. - BLDG 1 - NEW
FINE GRADE - S.O.G. - BLDG 1 - NEW
WIRE MESH - S.O.G - BLDG 1 - NEW
INSPECT - SOG - BLDG 1 - NEW
POUR SOG - BLDG 1 - NEW
ERECT MASONRY WALLS TO BEAM - 1ST FLR - BLDG 3 -
FORM/POUR TIE COLS/BEAMS - 1ST FLR - BLDG 3 - NE
INSTALL EMBEDS - 1ST FLR - BLDG 3 - NEW
ERECT STRUCTURAL STEEL/JOISTS - 2ND FLR - BLDG
METAL FRAMING - TOP TRACK - BLDG 3 - 1ST FLR -
WINDOWS - BLDG 3 - 1ST FLR - NEW
INSTALL DUCTWORK - BLDG 3 - 1ST FLR - NEW
INSTALL METAL FRAMING - BLDG 3 - 1ST FLR -
INSTALL HVAC PIPING - BLDG 3 - 1ST FLR - NEW
INSTALL FIRE SPRKLR ROUGH - BLDG 3 - 1ST
INSTALL PLUMBING ROUGH - BLDG 3 - 1ST FL
INSTALL HVAC EQUIP - BLDG 3 - 1ST FLR - NEW
INSTALL ELECTRIC ROUGH - BLDG 3 - 1ST FL
INSTALL INTERCOM BACKBOXES - BLDG 3 - 1
INSTALL DUCTWORK INSULATION - BLDG 3 -
HVAC DUCT CONNECT/HOOK-UP - BLDG 3 - 1
INSPECT FIRE SPRINKLER ABOVE CLG - BLDG
INSPECT PLUMBING - BLDG 3 - 1ST FLR - NEW
INSPECT ELECTRICAL ROUGH - BLDG 3 - 1ST
INSPECT FRAMING - BLDG 3 - 1ST FLR - NEW
HVAC PIPING CONNECT/HOOK-UP - BLDG 3
INSPECT HVAC - BLDG 3 - 1ST FLR - NEW
HANG DRYWALL - BLDG 3 - 1ST FLR - NEW
ELEVATOR RAILS - BLDG 3 - NEW
© Primavera Systems, Inc.
Start Date 09JUN08
Finish Date 07JUN10
Data Date 09JUN08
Run Date 08OCT08 08:10
Early Bar
Progress Bar
Critical Activity
BASZ
HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL
Sheet 4 of 16
ORGANIZED BY AREA
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
Total
Float
09251.0301 FINISH DRYWALL - BLDG 3 - 1ST FLR - NEW 15 27JUL09 14AUG09 53
09900.0301 PAINT INTERIOR PRIME COAT - BLDG 3 - 1ST FLR - N 8 17AUG09 26AUG09 53
09310.0301 INSTALL CERAMIC TILE - BLDG 3 - 1ST FLR - NEW 15 17AUG09 04SEP09 56
14104.0301 INSTL ELEV. FRAMES/EQ/CABS - BLDG 3 - NEW 40 21AUG09 16OCT09 63
09901.0301 PAINT INTERIOR FINISH COAT - BLDG 3 - 1ST FLR - 15 27AUG09 17SEP09 53
06410.0301 INSTALL CABINETS - BLDG 3 - 1ST FLR - NEW 17 08SEP09 30SEP09 56
09510.0301 INSTALL ACOUSTICAL CLG GRID - BLDG 3 - 1ST FLR - 15 11SEP09 01OCT09 53
08100.0301 HANG DOORS - BLDG 3 - 1ST FLR - NEW 12 18SEP09 05OCT09 75
10100.0301 INSTALL CHALK/TACKBOARD - BLDG 3 - 1ST FLR - NEW 8 18SEP09 29SEP09 82
15940.0301 INSTALL HVAC GRILLS/TRIM - BLDG 3 - 1ST FLR - NE 15 21SEP09 09OCT09 53
16500.0301 INSTALL ELEC FIXTURES - BLDG 3 - 1ST FLR - NEW 20 21SEP09 16OCT09 58
15440.0301 INSTALL PLUMB FIXTURES - BLDG 3 - 1ST FLR - NEW 20 01OCT09 28OCT09 56
13129.0301 INTERCOM INSTALLATION - BLDG 3 - 1ST FLR - NEW 15 02OCT09 22OCT09 62
11132.0301 INSTALL PROJECTION SCREENS - BLDG 3 - 1ST FLR - 5 02OCT09 08OCT09 72
08710.0301 INSTALL FINISH HARDWARE - BLDG 3 - 1ST FLR - NEW 10 06OCT09 19OCT09 75
15980.0301 START-UP HVAC SYSTEM - BLDG 3 - 1ST FLR - NEW 10 12OCT09 23OCT09 53
14106.0301 INTERIOR ELEVATOR FINISHES - BLDG 3 - NEW 15 19OCT09 06NOV09 63
09515.0301 INSTALL ACOUSTICAL CLG TILE - BLDG 3 - 1ST FLR - 8 26OCT09 04NOV09 53
15990.0301 PERFORM TEST & BALANCE - BLDG 3 - 1ST FLR - NEW 5 26OCT09 30OCT09 66
16505.0301 INSTALL ELEC TRIM - BLDG 3 - 1ST FLR - NEW 10 29OCT09 11NOV09 53
16710.0301 INSTALL SYSTEMS TRIM/DEVICES - BLDG 3 - 1ST FLR 10 29OCT09 11NOV09 53
10801.0301 INSTALL TOILET PARTITIONS - BLDG 3 - 1ST FLR - 7 29OCT09 06NOV09 56
08800.0301 INSTALL INTERIOR GLAZING - BLDG 3 - 1ST FLR - NE 5 29OCT09 04NOV09 63
15310.0301 INSTALL FIRE SPRKLR HEADS/TRIM - BLDG 3 - 1ST FL 7 02NOV09 10NOV09 54
09680.0301 INSTALL CARPET/FLOORING - BLDG 3 - 1ST FLR - NEW 10 05NOV09 18NOV09 53
10600.0301 METAL SHELVING/LOCKERS - BLDG 3 - 1ST FLR - NEW 7 05NOV09 13NOV09 56
10024.0301 INSTALL FIRE EXTINGUISHERS - BLDG 3 - 1ST FLR - 5 05NOV09 11NOV09 58
10800.0301 INSTALL BATH ACCESSORIES - BLDG 3 - 1ST FLR - NE 5 09NOV09 13NOV09 56
01690.0301 INSPECT - FINISHES - BLDG 3 - 1ST FLR - NEW 2 19NOV09 20NOV09 53
17000.0301 CONTRACTOR COMPLETION - BLDG 3 - 1ST FLR - NEW 0 20NOV09 53
2ND FLOOR
05200.0302 ERECT METAL DECK - 2ND FLR - BLDG 3 - NEW 5 23APR09 29APR09 0
01611.0302 INSPECT WELDS - METAL DECK - 2ND FLR - BLDG 3 - 2 30APR09 01MAY09 0
03310.0302 FORM/POUR 2ND FLR DECK - BLDG 3 - NEW 5 04MAY09 08MAY09 0
01612.0302 INSPECT REBAR - 2ND FLR - BLDG 3 - NEW 2 07MAY09 08MAY09 0
04200.0302 ERECT MASONRY WALLS TO BEAMS - 2ND FLR - BLDG 3 20 11MAY09 08JUN09 0
03330.0302 FORM/POUR TIE COLS/BEAMS - 2ND FLR - BLDG 3 - NE 15 21MAY09 11JUN09 0
2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL
FINISH DRYWALL - BLDG 3 - 1ST FLR - NEW
PAINT INTERIOR PRIME COAT - BLDG 3 - 1ST FLR - N
INSTALL CERAMIC TILE - BLDG 3 - 1ST FLR - NEW
INSTL ELEV. FRAMES/EQ/CABS - BLDG 3 - NEW
PAINT INTERIOR FINISH COAT - BLDG 3 - 1ST FLR -
INSTALL CABINETS - BLDG 3 - 1ST FLR - NEW
INSTALL ACOUSTICAL CLG GRID - BLDG 3 - 1ST FLR -
HANG DOORS - BLDG 3 - 1ST FLR - NEW
INSTALL CHALK/TACKBOARD - BLDG 3 - 1ST FLR - NEW
INSTALL HVAC GRILLS/TRIM - BLDG 3 - 1ST FLR - NE
INSTALL ELEC FIXTURES - BLDG 3 - 1ST FLR - NEW
INSTALL PLUMB FIXTURES - BLDG 3 - 1ST FLR - NEW
INTERCOM INSTALLATION - BLDG 3 - 1ST FLR - NEW
INSTALL PROJECTION SCREENS - BLDG 3 - 1ST FLR -
INSTALL FINISH HARDWARE - BLDG 3 - 1ST FLR - NEW
START-UP HVAC SYSTEM - BLDG 3 - 1ST FLR - NEW
INTERIOR ELEVATOR FINISHES - BLDG 3 - NEW
INSTALL ACOUSTICAL CLG TILE - BLDG 3 - 1ST FLR -
PERFORM TEST & BALANCE - BLDG 3 - 1ST FLR - NEW
INSTALL ELEC TRIM - BLDG 3 - 1ST FLR - NEW
INSTALL SYSTEMS TRIM/DEVICES - BLDG 3 - 1ST FLR
INSTALL TOILET PARTITIONS - BLDG 3 - 1ST FLR -
INSTALL INTERIOR GLAZING - BLDG 3 - 1ST FLR - NE
INSTALL FIRE SPRKLR HEADS/TRIM - BLDG 3 - 1ST FL
INSTALL CARPET/FLOORING - BLDG 3 - 1ST FLR - NEW
METAL SHELVING/LOCKERS - BLDG 3 - 1ST FLR - NEW
INSTALL FIRE EXTINGUISHERS - BLDG 3 - 1ST FLR -
INSTALL BATH ACCESSORIES - BLDG 3 - 1ST FLR - NE
INSPECT - FINISHES - BLDG 3 - 1ST FLR - NEW
CONTRACTOR COMPLETION - BLDG 3 - 1ST FLR - NEW
ERECT METAL DECK - 2ND FLR - BLDG 3 - NEW
INSPECT WELDS - METAL DECK - 2ND FLR - BLDG 3 -
FORM/POUR 2ND FLR DECK - BLDG 3 - NEW
INSPECT REBAR - 2ND FLR - BLDG 3 - NEW
ERECT MASONRY WALLS TO BEAMS - 2ND FLR -
FORM/POUR TIE COLS/BEAMS - 2ND FLR - BLDG
© Primavera Systems, Inc.
Start Date 09JUN08
Finish Date 07JUN10
Data Date 09JUN08
Run Date 08OCT08 08:10
Early Bar
Progress Bar
Critical Activity
BASZ
HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL
Sheet 5 of 16
ORGANIZED BY AREA
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
Total
Float
03331.0302 INSTALL EMBEDS - 2ND FLR - BLDG 3 - NEW 5 12JUN09 18JUN09 0
01613.0302 INSPECT BEAMS - 2ND FLR - BLDG 3 - NEW 2 19JUN09 22JUN09 0
05100.0302 ERECT STRUCTURAL STEEL/JOISTS - ROOF - BLDG 3 - 10 23JUN09 07JUL09 0
09231.0302 METAL FRAMING - TOP TRACK - BLDG 3 - 2ND FLR - N 5 24JUL09 30JUL09 0
08500.0302 WINDOWS - BLDG 3 - 2ND FLR - NEW 10 29JUL09 11AUG09 31
15890.0302 INSTALL DUCTWORK - BLDG 3 - 2ND FLR - NEW 20 31JUL09 27AUG09 0
09230.0302 INSTALL METAL FRAMING - BLDG 3 - 2ND FLR - NEW 20 07AUG09 03SEP09 0
15530.0302 INSTALL HVAC PIPING - BLDG 3 - 2ND FLR - NEW 17 12AUG09 03SEP09 10
15300.0302 INSTALL FIRE SPRKLR ROUGH - BLDG 3 - 2ND FLR - N 17 14AUG09 08SEP09 53
15415.0302 INSTALL PLUMBING ROUGH - BLDG 3 - 2ND FLR - NEW 20 18AUG09 15SEP09 3
15655.0302 INSTALL HVAC EQUIP - BLDG 3 - 2ND FLR - NEW 17 19AUG09 11SEP09 35
16115.0302 INSTALL ELECTRIC ROUGH - BLDG 3 - 2ND FLR - NEW 20 21AUG09 18SEP09 0
13100.0302 INSTALL INTERCOM BACKBOXES - BLDG 3 - 2ND FLR - 15 28AUG09 18SEP09 0
15895.0302 INSTALL DUCTWORK INSULATION - BLDG 3 - 2ND FLR - 20 28AUG09 25SEP09 42
01618.0302 INSPECT FIRE SPRINKLER ABOVE CLG - 2ND FLR - B 3 2 09SEP09 10SEP09 53
15656.0302 HVAC DUCT CONNECT/HOOK-UP - BLDG 3 - 2ND FLR - N 10 14SEP09 25SEP09 35
01614.0302 INSPECT PLUMBING - BLDG 3 - 2ND FLR - NEW 2 16SEP09 17SEP09 3
01616.0302 INSPECT ELECTRICAL ROUGH - BLDG 3 - 2ND FLR - NE 2 21SEP09 22SEP09 0
01617.0302 INSPECT FRAMING - 2ND FLR - BLDG 3 - NEW 2 23SEP09 24SEP09 0
01615.0302 INSPECT HVAC - BLDG 3 - 2ND FLR - NEW 2 24SEP09 25SEP09 42
09250.0302 HANG DRYWALL - BLDG 3 - 2ND FLR - NEW 15 25SEP09 15OCT09 0
15657.0302 HVAC PIPING CONNECT/HOOK-UP - BLDG 3 - 2ND FLR - 7 28SEP09 06OCT09 35
09251.0302 FINISH DRYWALL - BLDG 3 - 2ND FLR - NEW 15 08OCT09 28OCT09 0
09310.0302 INSTALL CERAMIC TILE - BLDG 3 - 2ND FLR - NEW 15 29OCT09 18NOV09 0
09900.0302 PAINT INTERIOR PRIME COAT - BLDG 3 - 2ND FLR - N 8 29OCT09 09NOV09 1
09901.0302 PAINT INTERIOR FINISH COAT - BLDG 3 - 2ND FLR - 15 10NOV09 01DEC09 1
06410.0302 INSTALL CABINETS - BLDG 3 - 2ND FLR - NEW 17 19NOV09 14DEC09 0
09510.0302 INSTALL ACOUSTICAL CLG GRID - BLDG 3 - 2ND FLR - 15 24NOV09 15DEC09 1
08100.0302 HANG DOORS - BLDG 3 - 2ND FLR - NEW 12 02DEC09 17DEC09 15
10100.0302 INSTALL CHALK/TACKBOARD - BLDG 3 - 2ND FLR - NEW 10 02DEC09 15DEC09 22
15940.0302 INSTALL HVAC GRILLS/TRIM - BLDG 3 - 2ND FLR - NE 12 03DEC09 18DEC09 1
16500.0302 INSTALL ELEC FIXTURES - BLDG 3 - 2ND FLR - NEW 17 03DEC09 28DEC09 1
15440.0302 INSTALL PLUMB FIXTURES - BLDG 3 - 2ND FLR - NEW 13 15DEC09 04JAN10 0
13129.0302 INTERCOM INSTALLATION - BLDG 3 - 2ND FLR - NEW 15 16DEC09 07JAN10 2
11132.0302 INSTALL PROJECTION SCREENS - BLDG 3 - 2ND FLR - 5 16DEC09 22DEC09 12
08710.0302 INSTALL FINISH HARDWARE - BLDG 3 - 2ND FLR - NEW 10 18DEC09 04JAN10 15
15980.0302 START-UP HVAC SYSTEM - BLDG 3 - 2ND FLR - NEW 5 21DEC09 28DEC09 1
09515.0302 INSTALL ACOUSTICAL CLG TILE - BLDG 3 - 2ND FLR - 8 29DEC09 08JAN10 1
2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL
INSTALL EMBEDS - 2ND FLR - BLDG 3 - NEW
INSPECT BEAMS - 2ND FLR - BLDG 3 - NEW
ERECT STRUCTURAL STEEL/JOISTS - ROOF -
METAL FRAMING - TOP TRACK - BLDG 3 - 2
WINDOWS - BLDG 3 - 2ND FLR - NEW
INSTALL DUCTWORK - BLDG 3 - 2ND FLR - NEW
INSTALL METAL FRAMING - BLDG 3 - 2
INSTALL HVAC PIPING - BLDG 3 - 2ND FLR - NEW
INSTALL FIRE SPRKLR ROUGH - BLDG
INSTALL PLUMBING ROUGH - BLDG 3
INSTALL HVAC EQUIP - BLDG 3 - 2ND FLR - NEW
INSTALL ELECTRIC ROUGH - BLDG 3
INSTALL INTERCOM BACKBOXES - BLDG 3 - 2ND FLR -
INSTALL DUCTWORK INSULATION -
INSPECT FIRE SPRINKLER ABOVE CLG - 2ND FLR - B 3
HVAC DUCT CONNECT/HOOK-UP - BLDG 3 - 2ND FLR - N
INSPECT PLUMBING - BLDG 3 - 2ND FLR - NEW
INSPECT ELECTRICAL ROUGH - BLDG 3 - 2ND FLR - NE
INSPECT FRAMING - 2ND FLR - BLDG 3 - NEW
INSPECT HVAC - BLDG 3 - 2ND FLR - NEW
HANG DRYWALL - BLDG 3 - 2ND FLR - NEW
HVAC PIPING CONNECT/HOOK-UP - BLDG 3 - 2ND FLR -
FINISH DRYWALL - BLDG 3 - 2ND FLR - NEW
INSTALL CERAMIC TILE - BLDG 3 - 2ND FLR - NEW
PAINT INTERIOR PRIME COAT - BLDG 3 - 2ND FLR - N
PAINT INTERIOR FINISH COAT - BLDG 3 - 2ND FLR -
INSTALL CABINETS - BLDG 3 - 2ND FLR - NEW
INSTALL ACOUSTICAL CLG GRID - BLDG 3 - 2ND FLR -
HANG DOORS - BLDG 3 - 2ND FLR - NEW
INSTALL CHALK/TACKBOARD - BLDG 3 - 2ND FLR - NEW
INSTALL HVAC GRILLS/TRIM - BLDG 3 - 2ND FLR - NE
INSTALL ELEC FIXTURES - BLDG 3 - 2ND FLR - NEW
INSTALL PLUMB FIXTURES - BLDG 3 - 2ND FLR - NEW
INTERCOM INSTALLATION - BLDG 3 - 2ND FLR - NEW
INSTALL PROJECTION SCREENS - BLDG 3 - 2ND FLR -
INSTALL FINISH HARDWARE - BLDG 3 - 2ND FLR - NEW
START-UP HVAC SYSTEM - BLDG 3 - 2ND FLR - NEW
INSTALL ACOUSTICAL CLG TILE - BLDG 3 - 2ND FLR -
© Primavera Systems, Inc.
Start Date 09JUN08
Finish Date 07JUN10
Data Date 09JUN08
Run Date 08OCT08 08:10
Early Bar
Progress Bar
Critical Activity
BASZ
HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL
Sheet 6 of 16
ORGANIZED BY AREA
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
Total
Float
15990.0302 PERFORM TEST & BALANCE - BLDG 3 - 2ND FLR - NEW 5 29DEC09 05JAN10 14
16505.0302 INSTALL ELEC TRIM - BLDG 3 - 2ND FLR - NEW 10 04JAN10 15JAN10 1
16710.0302 INSTALL SYSTEMS TRIM/DEVICES - BLDG 3 - 2ND FLR 10 04JAN10 15JAN10 1
10801.0302 INSTALL TOILET PARTITIONS - BLDG 3 - 2ND FLR - 10 05JAN10 18JAN10 0
08800.0302 INSTALL INTERIOR GLAZING - BLDG 3 - 2ND FLR - NE 5 05JAN10 11JAN10 10
15310.0302 INSTALL FIRE SPRKLR HEADS/TRIM - BLDG 3 - 2ND FL 7 06JAN10 14JAN10 2
09680.0302 INSTALL CARPET/FLOORING - BLDG 3 - 2ND FLR - NEW 10 11JAN10 22JAN10 1
10600.0302 METAL SHELVING/LOCKERS - BLDG 3 - 2ND FLR - NEW 7 11JAN10 19JAN10 4
10024.0302 INSTALL FIRE EXTINGUISHERS - BLDG 3 - 2ND FLR - 5 11JAN10 15JAN10 6
10800.0302 INSTALL BATH ACCESSORIES - BLDG 3 - 2ND FLR - NE 5 19JAN10 25JAN10 0
01690.0302 FINAL INSPECTIONS - BLDG 3 - NEW 10 26JAN10 08FEB10 0
17000.0302 CONTRACTOR COMPLETION - BLDG 3 - 2ND FLR - NEW 0 08FEB10 0
ROOF & EXTERIOR
05200.0303 ERECT METAL DECK - ROOF - BLDG 3 - NEW 5 08JUL09 14JUL09 0
01610.0303 INSPECT WELDS - METAL DECK - ROOF - BLDG 3 - NEW 2 15JUL09 16JUL09 0
03310.0303 FORM/REBAR ROOF DECK - BLDG 3 - NEW 5 17JUL09 23JUL09 0
01611.0303 INSPECT REBAR - ROOF - BLDG 3 - NEW 2 24JUL09 27JUL09 31
03311.0303 POUR ROOF DECK - BLDG 3 - NEW 1 28JUL09 28JUL09 31
04200.0303 PARAPET WALL - BLDG 3 - ROOF - NEW 5 29JUL09 04AUG09 62
07450.0303 1ST LAYOUT ROOFING - BLDG 3 - NEW 1 05AUG09 05AUG09 62
07400.0303 TRUSSES - BLDG 3 - NEW 15 06AUG09 26AUG09 62
07500.0303 ROOFING - BLDG 3 - NEW 10 27AUG09 10SEP09 62
01620.0303 ROOFING FINAL - BLDG 3 - NEW 2 11SEP09 14SEP09 62
04400.0303 BRICK VENEER - BLDG 3 - NEW 10 15SEP09 28SEP09 62
09100.0303 EXTERIOR STUCCO - BLDG 3 - NEW 15 29SEP09 19OCT09 62
09950.0303 EXTERIOR PAINTING - BLDG 3 - NEW 15 20OCT09 09NOV09 62
NEW BUILDING 1
1ST FLOOR
04200.0101 ERECT MASONRY WALLS - BLDG 1 - NEW 20 09MAR09 03APR09 38
03330.0101 FORM/POUR TIE COLS/BEAMS - BLDG 1 - NEW 15 19MAR09 08APR09 38
03331.0101 INSTALL EMBEDS - BLDG 1 - NEW 5 09APR09 15APR09 38
05100.0101 ERECT STRUCTURAL STEEL/JOISTS - BLDG 1 - NEW 7 16APR09 24APR09 38
09231.0101 METAL FRAMING - TOP TRACK - BLDG 1 - NEW 5 13MAY09 19MAY09 40
15890.0101 INSTALL DUCTWORK - BLDG 1 - NEW 20 20MAY09 17JUN09 40
09230.0101 INSTALL METAL FRAMING - BLDG 1 - NEW 20 28MAY09 24JUN09 40
15530.0101 INSTALL HVAC PIPING - BLDG 1 - NEW 17 02JUN09 24JUN09 50
15300.0101 INSTALL FIRE SPRKLR ROUGH - BLDG 1 - NEW 17 04JUN09 26JUN09 94
2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL
PERFORM TEST & BALANCE - BLDG 3 - 2ND FLR - NEW
INSTALL ELEC TRIM - BLDG 3 - 2ND FLR - NEW
INSTALL SYSTEMS TRIM/DEVICES - BLDG 3 - 2ND FLR
INSTALL TOILET PARTITIONS - BLDG 3 - 2ND FLR -
INSTALL INTERIOR GLAZING - BLDG 3 - 2ND FLR - NE
INSTALL FIRE SPRKLR HEADS/TRIM - BLDG 3 - 2ND FL
INSTALL CARPET/FLOORING - BLDG 3 - 2ND FLR - NEW
METAL SHELVING/LOCKERS - BLDG 3 - 2ND FLR - NEW
INSTALL FIRE EXTINGUISHERS - BLDG 3 - 2ND FLR -
INSTALL BATH ACCESSORIES - BLDG 3 - 2ND FLR - NE
FINAL INSPECTIONS - BLDG 3 - NEW
CONTRACTOR COMPLETION - BLDG 3 - 2ND FLR - NEW
ERECT METAL DECK - ROOF - BLDG 3 - NEW
INSPECT WELDS - METAL DECK - ROOF - BL
FORM/REBAR ROOF DECK - BLDG 3 - NEW
INSPECT REBAR - ROOF - BLDG 3 - NEW
POUR ROOF DECK - BLDG 3 - NEW
PARAPET WALL - BLDG 3 - ROOF - NEW
1ST LAYOUT ROOFING - BLDG 3 - NEW
TRUSSES - BLDG 3 - NEW
ROOFING - BLDG 3 - NEW
ROOFING FINAL - BLDG 3 - NEW
BRICK VENEER - BLDG 3 - NEW
EXTERIOR STUCCO - BLDG 3 - NEW
EXTERIOR PAINTING - BLDG 3 - NEW
ERECT MASONRY WALLS - BLDG 1 - NEW
FORM/POUR TIE COLS/BEAMS - BLDG 1 - NEW
INSTALL EMBEDS - BLDG 1 - NEW
ERECT STRUCTURAL STEEL/JOISTS - BLDG 1 - NEW
METAL FRAMING - TOP TRACK - BLDG 1 - NEW
INSTALL DUCTWORK - BLDG 1 - NEW
INSTALL METAL FRAMING - BLDG 1 - NEW
INSTALL HVAC PIPING - BLDG 1 - NEW
INSTALL FIRE SPRKLR ROUGH - BLDG 1 - NEW
© Primavera Systems, Inc.
Start Date 09JUN08
Finish Date 07JUN10
Data Date 09JUN08
Run Date 08OCT08 08:10
Early Bar
Progress Bar
Critical Activity
BASZ
HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL
Sheet 7 of 16
ORGANIZED BY AREA
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
Total
Float
15415.0101 INSTALL PLUMBING ROUGH - BLDG 1 - NEW 20 08JUN09 06JUL09 43
15655.0101 INSTALL HVAC EQUIP - BLDG 1 - NEW 17 09JUN09 01JUL09 78
16115.0101 INSTALL ELECTRIC ROUGH - BLDG 1 - NEW 20 11JUN09 09JUL09 40
13100.0101 INSTALL INTERCOM BACKBOXES - BLDG 1 - NEW 15 18JUN09 09JUL09 40
15895.0101 INSTALL DUCTWORK INSULATION - BLDG 1 - NEW 20 18JUN09 16JUL09 82
01619.0101 INSPECT FIRE SPRINKLER ABOVE CLG - 1ST FLR - B 1 1 29JUN09 29JUN09 94
15656.0101 HVAC DUCT CONNECT/HOOK-UP - BLDG 1 - NEW 7 02JUL09 13JUL09 78
01614.0101 INSPECT PLUMBING - BLDG 1 - NEW 2 07JUL09 08JUL09 43
01616.0101 INSPECT ELECTRICAL ROUGH - BLDG 1 - NEW 2 10JUL09 13JUL09 40
01617.0101 INSPECT FRAMING - 1ST FLR - BLDG 1 - NEW 2 14JUL09 15JUL09 40
15657.0101 HVAC PIPING CONNECT/HOOK-UP - BLDG 1 - NEW 7 14JUL09 22JUL09 78
01618.0101 EXT. INSULATION INSPECTION - 1ST FLR - BLDG 1 - 1 16JUL09 16JUL09 40
01615.0101 INSPECT HVAC - BLDG 1 - NEW 1 16JUL09 16JUL09 82
09250.0101 HANG DRYWALL - BLDG 1 - NEW 15 17JUL09 06AUG09 40
09251.0101 FINISH DRYWALL - BLDG 1 - NEW 15 30JUL09 19AUG09 40
09900.0101 PAINT INTERIOR PRIME COAT - BLDG 1 - NEW 8 20AUG09 31AUG09 40
09310.0101 INSTALL QUARRY/CERAMIC TILE - BLDG 1 - NEW 20 20AUG09 17SEP09 43
09901.0101 PAINT INTERIOR FINISH COAT - BLDG 1 - NEW 15 01SEP09 22SEP09 40
09510.0101 INSTALL ACOUSTICAL CLG GRID - BLDG 1 - NEW 15 16SEP09 06OCT09 40
06410.0101 INSTALL CABINETS - BLDG 1 - NEW 17 18SEP09 12OCT09 43
11400.0101 INSTALL FOOD SERVICE EQUIPMENT - BLDG 1 - NEW 30 18SEP09 29OCT09 59
08200.0101 HANG DOORS - BLDG 1 - NEW 12 23SEP09 08OCT09 64
15940.0101 INSTALL HVAC GRILLS/TRIM - BLDG 1 - NEW 12 24SEP09 09OCT09 40
16500.0101 INSTALL ELEC FIXTURES - BLDG 1 - NEW 17 24SEP09 16OCT09 40
13129.0101 INTERCOM INSTALLATION - BLDG 1 - NEW 15 07OCT09 27OCT09 46
08710.0101 INSTALL FINISH HARDWARE - BLDG 1 - NEW 10 09OCT09 22OCT09 64
15980.0101 START-UP HVAC SYSTEM - BLDG 1 - NEW 5 12OCT09 16OCT09 40
15440.0101 INSTALL PLUMB FIXTURES - BLDG 1 - NEW 17 13OCT09 04NOV09 43
09515.0101 INSTALL ACOUSTICAL CLG TILE - BLDG 1 - NEW 8 19OCT09 28OCT09 40
15990.0101 PERFORM TEST & BALANCE - BLDG 1 - NEW 5 19OCT09 23OCT09 63
16505.0101 INSTALL ELEC TRIM - BLDG 1 - NEW 10 22OCT09 04NOV09 40
16710.0101 INSTALL SYSTEMS TRIM/DEVICES - BLDG 1 - NEW 10 22OCT09 04NOV09 40
15310.0101 INSTALL FIRE SPRKLR HEADS/TRIM - BLDG 1 - NEW 7 26OCT09 03NOV09 41
10600.0101 METAL SHELVING/LOCKERS - BLDG 1 - NEW 7 29OCT09 06NOV09 53
10024.0101 INSTALL FIRE EXTINGUISHERS - BLDG 1 - NEW 5 29OCT09 04NOV09 55
15450.0101 HOOK-UP PLUMBING - FOOD SERV EQ - BLDG 1 - NEW 10 30OCT09 12NOV09 59
16490.0101 HOOK-UP ELECTRICAL - FOOD SERV EQ - BLDG 1 - NEW 10 30OCT09 12NOV09 59
09680.0101 INSTALL FLOORING - BLDG 1 - NEW 15 05NOV09 25NOV09 40
2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL
INSTALL PLUMBING ROUGH - BLDG 1 - NEW
INSTALL HVAC EQUIP - BLDG 1 - NEW
INSTALL ELECTRIC ROUGH - BLDG 1 - NEW
INSTALL INTERCOM BACKBOXES - BLDG 1 - N
INSTALL DUCTWORK INSULATION - BLDG 1
INSPECT FIRE SPRINKLER ABOVE CLG - 1ST F
HVAC DUCT CONNECT/HOOK-UP - BLDG 1 - N
INSPECT PLUMBING - BLDG 1 - NEW
INSPECT ELECTRICAL ROUGH - BLDG 1 - NEW
INSPECT FRAMING - 1ST FLR - BLDG 1 - NEW
HVAC PIPING CONNECT/HOOK-UP - BLDG 1
EXT. INSULATION INSPECTION - 1ST FLR - B
INSPECT HVAC - BLDG 1 - NEW
HANG DRYWALL - BLDG 1 - NEW
FINISH DRYWALL - BLDG 1 - NEW
PAINT INTERIOR PRIME COAT - BLDG 1 - NEW
INSTALL QUARRY/CERAMIC TILE - BLDG 1 - NEW
PAINT INTERIOR FINISH COAT - BLDG 1 - NEW
INSTALL ACOUSTICAL CLG GRID - BLDG 1 - NEW
INSTALL CABINETS - BLDG 1 - NEW
INSTALL FOOD SERVICE EQUIPMENT - BLDG 1 - NEW
HANG DOORS - BLDG 1 - NEW
INSTALL HVAC GRILLS/TRIM - BLDG 1 - NEW
INSTALL ELEC FIXTURES - BLDG 1 - NEW
INTERCOM INSTALLATION - BLDG 1 - NEW
INSTALL FINISH HARDWARE - BLDG 1 - NEW
START-UP HVAC SYSTEM - BLDG 1 - NEW
INSTALL PLUMB FIXTURES - BLDG 1 - NEW
INSTALL ACOUSTICAL CLG TILE - BLDG 1 - NEW
PERFORM TEST & BALANCE - BLDG 1 - NEW
INSTALL ELEC TRIM - BLDG 1 - NEW
INSTALL SYSTEMS TRIM/DEVICES - BLDG 1 - NEW
INSTALL FIRE SPRKLR HEADS/TRIM - BLDG 1 - NEW
METAL SHELVING/LOCKERS - BLDG 1 - NEW
INSTALL FIRE EXTINGUISHERS - BLDG 1 - NEW
HOOK-UP PLUMBING - FOOD SERV EQ - BLDG 1 - NEW
HOOK-UP ELECTRICAL - FOOD SERV EQ - BLDG 1 - NEW
INSTALL FLOORING - BLDG 1 - NEW
© Primavera Systems, Inc.
Start Date 09JUN08
Finish Date 07JUN10
Data Date 09JUN08
Run Date 08OCT08 08:10
Early Bar
Progress Bar
Critical Activity
BASZ
HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL
Sheet 8 of 16
ORGANIZED BY AREA
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
Total
Float
10801.0101 INSTALL TOILET PARTITIONS - BLDG 1 - NEW 7 05NOV09 13NOV09 43
08800.0101 INSTALL INTERIOR GLAZING - BLDG 1 - NEW 5 05NOV09 11NOV09 50
10800.0101 INSTALL BATH ACCESSORIES - BLDG 1 - NEW 5 16NOV09 20NOV09 43
01690.0101 FINAL INSPECTIONS - BLDG 1 - NEW 10 27NOV09 10DEC09 40
17000.0101 CONTRACTOR COMPLETION - BLDG 1 - NEW 0 10DEC09 40
ROOF & EXTERIOR
05200.0102 ERECT METAL DECK - ROOF - BLDG 1 - NEW 5 27APR09 01MAY09 38
01620.0102 INSPECT WELDS - ROOF DECK - BLDG 1 - NEW 2 04MAY09 05MAY09 38
03310.0102 FORM/REBAR ROOF DECK - BLDG 1 - NEW 5 06MAY09 12MAY09 38
01621.0102 INSPECT REBAR - ROOF DECK - BLDG 1 - NEW 2 13MAY09 14MAY09 38
03311.0102 POUR ROOF DECK - BLDG 1 - NEW 1 15MAY09 15MAY09 38
04200.0102 PARAPET WALL - BLDG 1 - ROOF - NEW 5 18MAY09 22MAY09 38
07450.0102 1ST LAYOUT ROOFING - BLDG 1 - NEW 1 26MAY09 26MAY09 38
07400.0102 TRUSSES - BLDG 1 - NEW 7 27MAY09 04JUN09 38
01622.0102 INSPECT TRUSSES - BLDG 1 - NEW 2 05JUN09 08JUN09 38
03320.0102 L/W CONC ROOFING - BLDG 1 - NEW 5 09JUN09 15JUN09 38
01623.0102 INSPECT L/W CONC ROOFING - BLDG 1 - NEW 2 16JUN09 17JUN09 38
07500.0102 ROOFING - BLDG 1 - NEW 10 18JUN09 01JUL09 38
01624.0102 FINAL ROOFING - BLDG 1 - NEW 2 02JUL09 06JUL09 111
04400.0102 BRICK VENEER - BLDG 1 - NEW 10 07JUL09 20JUL09 111
09100.0102 EXTERIOR STUCCO - BLDG 1 - NEW 15 21JUL09 10AUG09 111
09950.0102 EXTERIOR PAINTING - BLDG 1 - NEW 15 11AUG09 31AUG09 111
CHILLER ENCLOSURE
03000.0104 LAYOUT FTGS - CHILLER - NEW 1 09MAR09 09MAR09 80
03002.0104 EXCAVATE FTGS - CHILLER - NEW 3 10MAR09 12MAR09 80
03003.0104 FORM FTGS - CHILLER - NEW 3 12MAR09 16MAR09 80
03200.0104 PLACE REBAR FTGS - CHILLER - NEW 3 16MAR09 18MAR09 80
01630.0104 INSPECT - FDNS - CHILLER - NEW 1 19MAR09 19MAR09 80
03300.0104 POUR FTGS - CHILLER - NEW 2 20MAR09 23MAR09 80
15100.0104 INSTALL U/G MECH R-I - CHILLER - NEW 6 24MAR09 31MAR09 80
15540.0104 U/G CHILLED PIPING - CHILLER - NEW 6 24MAR09 31MAR09 80
16100.0104 INSTALL U/G ELECT R-I - CHILLER - NEW 4 01APR09 06APR09 80
02210.0104 FINE GRADE - S.O.G. - CHILLER - NEW 4 07APR09 10APR09 80
02215.0104 TERMITE CONTROL - CHILLER - NEW 1 13APR09 13APR09 80
03100.0104 WIRE MESH - S.O.G - CHILLER - NEW 1 14APR09 14APR09 80
01632.0104 INSPECT - SOG - CHILLER - NEW 1 15APR09 15APR09 80
03310.0104 POUR SOG - CHILLER - NEW 1 16APR09 16APR09 80
2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL
INSTALL TOILET PARTITIONS - BLDG 1 - NEW
INSTALL INTERIOR GLAZING - BLDG 1 - NEW
INSTALL BATH ACCESSORIES - BLDG 1 - NEW
FINAL INSPECTIONS - BLDG 1 - NEW
CONTRACTOR COMPLETION - BLDG 1 - NEW
ERECT METAL DECK - ROOF - BLDG 1 - NEW
INSPECT WELDS - ROOF DECK - BLDG 1 - NEW
FORM/REBAR ROOF DECK - BLDG 1 - NEW
INSPECT REBAR - ROOF DECK - BLDG 1 - NEW
POUR ROOF DECK - BLDG 1 - NEW
PARAPET WALL - BLDG 1 - ROOF - NEW
1ST LAYOUT ROOFING - BLDG 1 - NEW
TRUSSES - BLDG 1 - NEW
INSPECT TRUSSES - BLDG 1 - NEW
L/W CONC ROOFING - BLDG 1 - NEW
INSPECT L/W CONC ROOFING - BLDG 1 - NEW
ROOFING - BLDG 1 - NEW
FINAL ROOFING - BLDG 1 - NEW
BRICK VENEER - BLDG 1 - NEW
EXTERIOR STUCCO - BLDG 1 - NEW
EXTERIOR PAINTING - BLDG 1 - NEW
LAYOUT FTGS - CHILLER - NEW
EXCAVATE FTGS - CHILLER - NEW
FORM FTGS - CHILLER - NEW
PLACE REBAR FTGS - CHILLER - NEW
INSPECT - FDNS - CHILLER - NEW
POUR FTGS - CHILLER - NEW
INSTALL U/G MECH R-I - CHILLER - NEW
U/G CHILLED PIPING - CHILLER - NEW
INSTALL U/G ELECT R-I - CHILLER - NEW
FINE GRADE - S.O.G. - CHILLER - NEW
TERMITE CONTROL - CHILLER - NEW
WIRE MESH - S.O.G - CHILLER - NEW
INSPECT - SOG - CHILLER - NEW
POUR SOG - CHILLER - NEW
© Primavera Systems, Inc.
Start Date 09JUN08
Finish Date 07JUN10
Data Date 09JUN08
Run Date 08OCT08 08:10
Early Bar
Progress Bar
Critical Activity
BASZ
HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL
Sheet 9 of 16
ORGANIZED BY AREA
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
Total
Float
04200.0104 MASONRY WALLS - CHILLER - NEW 5 17APR09 23APR09 80
03330.0104 FORM/POUR TIE COLS/BEAMS - CHILLER - NEW 5 22APR09 28APR09 80
15900.0104 SET CHILLERS/PUMPS,ETC. - CHILLER - NEW 20 29APR09 27MAY09 80
15910.0104 COOLING TOWER - CHILLER - NEW 20 13MAY09 10JUN09 80
15541.0104 HVAC CHILLER PIPING - CHILLER - NEW 15 11JUN09 01JUL09 80
15550.0104 INSTALL HYDRONIC SPECIALITIES - CHILLER - NEW 15 02JUL09 23JUL09 80
15901.0104 HVAC - START-UP CHILLER PLANT - NEW 10 24JUL09 06AUG09 80
NEW BUILDING 2
1ST FLOOR
09231.0201 METAL FRAMING - TOP TRACK - BLDG 2 - 1ST FLR - N 5 09MAR09 13MAR09 67
03301.0201 SAWCUT CONCRETE SLAB - 1ST FLR - BLDG 2 - NEW 2 16MAR09 17MAR09 67
15410.0201 PLUMBING ROUGH - SLAB - 1ST FLR - BLDG 2 - NEW 5 18MAR09 24MAR09 67
16110.0201 ELECTRIC ROUGH - SLAB - 1ST FLR - BLDG 2 - NEW 5 20MAR09 26MAR09 67
03310.0201 PLACE & FINISH S.O.G. - 1ST FLR - BLDG 2 - NEW 2 27MAR09 30MAR09 67
15890.0201 INSTALL DUCTWORK - BLDG 2 - 1ST FLR - NEW 20 31MAR09 27APR09 67
09230.0201 INSTALL METAL FRAMING - BLDG 2 - 1ST FLR - NEW 20 07APR09 04MAY09 67
15530.0201 INSTALL HVAC PIPING - BLDG 2 - 1ST FLR - NEW 17 10APR09 04MAY09 77
15300.0201 INSTALL FIRE SPRKLR ROUGH - BLDG 2 - 1ST FLR - N 17 14APR09 06MAY09 124
15415.0201 INSTALL PLUMBING ROUGH - BLDG 2 - 1ST FLR - NEW 20 16APR09 13MAY09 70
15655.0201 INSTALL HVAC EQUIP - BLDG 2 - 1ST FLR - NEW 17 17APR09 11MAY09 109
16115.0201 INSTALL ELECTRIC ROUGH - BLDG 2 - 1ST FLR - NEW 20 21APR09 18MAY09 67
13100.0201 INSTALL INTERCOM BACKBOXES - BLDG 2 - 1ST FLR - 15 28APR09 18MAY09 67
15895.0201 INSTALL DUCTWORK INSULATION - BLDG 2 - 1ST FLR - 20 28APR09 26MAY09 113
01618.0201 INSPECT FIRE SPRINKLER ABOVE CLG - 1ST FLR - B 2 2 07MAY09 08MAY09 124
15656.0201 HVAC DUCT CONNECT/HOOK-UP - BLDG 2 - 1ST FLR - N 7 12MAY09 20MAY09 109
01614.0201 INSPECT PLUMBING - BLDG 2 - 1ST FLR - NEW 2 14MAY09 15MAY09 70
01616.0201 INSPECT ELECTRICAL ROUGH - BLDG 2 - 1ST FLR - NE 2 19MAY09 20MAY09 67
01617.0201 INSPECT FRAMING - 1ST FLR - BLDG 2 - NEW 2 21MAY09 22MAY09 67
15657.0201 HVAC PIPING CONNECT/HOOK-UP - BLDG 2 - 1ST FLR - 7 21MAY09 01JUN09 109
01615.0201 INSPECT HVAC - BLDG 2 - 1ST FLR - NEW 2 22MAY09 26MAY09 113
09250.0201 HANG DRYWALL - BLDG 2 - 1ST FLR - NEW 15 26MAY09 15JUN09 67
09251.0201 FINISH DRYWALL - BLDG 2 - 1ST FLR - NEW 15 08JUN09 26JUN09 67
09900.0201 PAINT INTERIOR PRIME COAT - BLDG 2 - 1ST FLR - N 8 29JUN09 09JUL09 67
09310.0201 INSTALL CERAMIC TILE - BLDG 2 - 1ST FLR - NEW 15 29JUN09 20JUL09 89
09901.0201 PAINT INTERIOR FINISH COAT - BLDG 2 - 1ST FLR - 15 10JUL09 30JUL09 67
06410.0201 INSTALL CABINETS - BLDG 2 - 1ST FLR - NEW 17 21JUL09 12AUG09 89
09510.0201 INSTALL ACOUSTICAL CLG GRID - BLDG 2 - 1ST FLR - 15 31JUL09 20AUG09 67
2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL
MASONRY WALLS - CHILLER - NEW
FORM/POUR TIE COLS/BEAMS - CHILLER - NEW
SET CHILLERS/PUMPS,ETC. - CHILLER - NEW
COOLING TOWER - CHILLER - NEW
HVAC CHILLER PIPING - CHILLER - NEW
INSTALL HYDRONIC SPECIALITIES - CHILLE
HVAC - START-UP CHILLER PLANT - NEW
METAL FRAMING - TOP TRACK - BLDG 2 - 1ST FLR - N
SAWCUT CONCRETE SLAB - 1ST FLR - BLDG 2 - NEW
PLUMBING ROUGH - SLAB - 1ST FLR - BLDG 2 - NEW
ELECTRIC ROUGH - SLAB - 1ST FLR - BLDG 2 - NEW
PLACE & FINISH S.O.G. - 1ST FLR - BLDG 2 - NEW
INSTALL DUCTWORK - BLDG 2 - 1ST FLR - NEW
INSTALL METAL FRAMING - BLDG 2 - 1ST FLR - NEW
INSTALL HVAC PIPING - BLDG 2 - 1ST FLR - NEW
INSTALL FIRE SPRKLR ROUGH - BLDG 2 - 1ST FLR - N
INSTALL PLUMBING ROUGH - BLDG 2 - 1ST FLR - NE
INSTALL HVAC EQUIP - BLDG 2 - 1ST FLR - NEW
INSTALL ELECTRIC ROUGH - BLDG 2 - 1ST FLR - NE
INSTALL INTERCOM BACKBOXES - BLDG 2 - 1ST FL
INSTALL DUCTWORK INSULATION - BLDG 2 - 1ST F
INSPECT FIRE SPRINKLER ABOVE CLG - 1ST FLR - B
HVAC DUCT CONNECT/HOOK-UP - BLDG 2 - 1ST FLR
INSPECT PLUMBING - BLDG 2 - 1ST FLR - NEW
INSPECT ELECTRICAL ROUGH - BLDG 2 - 1ST FLR -
INSPECT FRAMING - 1ST FLR - BLDG 2 - NEW
HVAC PIPING CONNECT/HOOK-UP - BLDG 2 - 1ST F
INSPECT HVAC - BLDG 2 - 1ST FLR - NEW
HANG DRYWALL - BLDG 2 - 1ST FLR - NEW
FINISH DRYWALL - BLDG 2 - 1ST FLR - NEW
PAINT INTERIOR PRIME COAT - BLDG 2 - 1ST
INSTALL CERAMIC TILE - BLDG 2 - 1ST FLR
PAINT INTERIOR FINISH COAT - BLDG 2 - 1S
INSTALL CABINETS - BLDG 2 - 1ST FLR - NEW
INSTALL ACOUSTICAL CLG GRID - BLDG
© Primavera Systems, Inc.
Start Date 09JUN08
Finish Date 07JUN10
Data Date 09JUN08
Run Date 08OCT08 08:10
Early Bar
Progress Bar
Critical Activity
BASZ
HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL
Sheet 10 of 16
ORGANIZED BY AREA
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
Total
Float
08100.0201 HANG DOORS - BLDG 2 - 1ST FLR - NEW 12 31JUL09 17AUG09 101
15940.0201 INSTALL HVAC GRILLS/TRIM - BLDG 2 - 1ST FLR - NE 12 10AUG09 25AUG09 67
16500.0201 INSTALL ELEC FIXTURES - BLDG 3 - 1ST FLR - NEW 17 10AUG09 01SEP09 67
15440.0201 INSTALL PLUMB FIXTURES - BLDG 2 - 1ST FLR - NEW 13 13AUG09 31AUG09 89
08710.0201 INSTALL FINISH HARDWARE - BLDG 2 - 1ST FLR - NEW 10 18AUG09 31AUG09 101
13129.0201 INTERCOM INSTALLATION - BLDG 2 - 1ST FLR - NEW 15 21AUG09 11SEP09 78
11132.0201 INSTALL PROJECTION SCREENS - BLDG 2 - 1ST FLR - 5 21AUG09 27AUG09 88
15980.0201 START-UP HVAC SYSTEM - BLDG 2 - 1ST FLR - NEW 5 26AUG09 01SEP09 67
10801.0201 INSTALL TOILET PARTITIONS - BLDG 2 - 1ST FLR - 7 01SEP09 10SEP09 89
08800.0201 INSTALL INTERIOR GLAZING - BLDG 2 - 1ST FLR - NE 5 01SEP09 08SEP09 96
09515.0201 INSTALL ACOUSTICAL CLG TILE - BLDG 2 - 1ST FLR - 8 02SEP09 14SEP09 67
15990.0201 PERFORM TEST & BALANCE - BLDG 2 - 1ST FLR - NEW 5 02SEP09 09SEP09 95
10800.0201 INSTALL BATH ACCESSORIES - BLDG 2 - 1ST FLR - NE 5 11SEP09 17SEP09 89
16505.0201 INSTALL ELEC TRIM - BLDG 2 - 1ST FLR - NEW 10 15SEP09 28SEP09 67
16710.0201 INSTALL SYSTEMS TRIM/DEVICES - BLDG 2 - 1ST FLR 10 15SEP09 28SEP09 67
15310.0201 INSTALL FIRE SPRKLR HEADS/TRIM - BLDG 2 - 1ST FL 7 15SEP09 23SEP09 70
10100.0201 INSTALL CHALK/TACKBOARD - BLDG 2 - 1ST FLR - NEW 8 15SEP09 24SEP09 72
10600.0201 METAL SHELVING/LOCKERS - BLDG 2 - 1ST FLR - NEW 7 15SEP09 23SEP09 85
10024.0201 INSTALL FIRE EXTINGUISHERS - BLDG 2 - 1ST FLR - 5 15SEP09 21SEP09 87
09680.0201 INSTALL CARPET/FLOORING - BLDG 2 - 1ST FLR - NEW 15 29SEP09 19OCT09 67
01690.0201 FINAL INSPECTIONS - BLDG 2 - 1ST FLR - NEW 10 20OCT09 02NOV09 67
17000.0201 CONTRACTOR COMPLETION - BLDG 2 - 1ST FLR - NEW 0 02NOV09 67
2ND FLOOR
09231.0202 METAL FRAMING - TOP TRACK - BLDG 2 - 2ND FLR - N 5 16MAR09 20MAR09 73
15890.0202 INSTALL DUCTWORK - BLDG 2 - 2ND FLR - NEW 20 23MAR09 17APR09 73
09230.0202 INSTALL METAL FRAMING - BLDG 2 - 2ND FLR - NEW 20 30MAR09 24APR09 73
15530.0202 INSTALL HVAC PIPING - BLDG 2 - 2ND FLR - NEW 17 02APR09 24APR09 83
15300.0202 INSTALL FIRE SPRKLR ROUGH - BLDG 2 - 2ND FLR - N 17 06APR09 28APR09 130
15415.0202 INSTALL PLUMBING ROUGH - BLDG 2 - 2ND FLR - NEW 20 08APR09 05MAY09 80
15655.0202 INSTALL HVAC EQUIP - BLDG 2 - 2ND FLR - NEW 17 09APR09 01MAY09 115
16115.0202 INSTALL ELECTRIC ROUGH - BLDG 2 - 2ND FLR - NEW 20 13APR09 08MAY09 73
13100.0202 INSTALL INTERCOM BACKBOXES - BLDG 2 - 2ND FLR - 15 20APR09 08MAY09 73
15895.0202 INSTALL DUCTWORK INSULATION - BLDG 2 - 2ND FLR - 20 20APR09 15MAY09 119
01618.0202 INSPECT FIRE SPRINKLER ABOVE CLG - 2ND FLR - B 2 2 29APR09 30APR09 130
15656.0202 HVAC DUCT CONNECT/HOOK-UP - BLDG 2 - 2ND FLR - N 7 04MAY09 12MAY09 115
01614.0202 INSPECT PLUMBING - BLDG 2 - 2ND FLR - NEW 2 06MAY09 07MAY09 125
01616.0202 INSPECT ELECTRICAL ROUGH - BLDG 2 - 2ND FLR - NE 2 11MAY09 12MAY09 73
2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL
HANG DOORS - BLDG 2 - 1ST FLR - NEW
INSTALL HVAC GRILLS/TRIM - BLDG 2 -
INSTALL ELEC FIXTURES - BLDG 3 - 1ST FLR - NEW
INSTALL PLUMB FIXTURES - BLDG 2 - 1
INSTALL FINISH HARDWARE - BLDG 2 -
INTERCOM INSTALLATION - BLDG 2 - 1ST FLR - NEW
INSTALL PROJECTION SCREENS - BLDG 2 - 1ST FLR -
START-UP HVAC SYSTEM - BLDG 2 - 1ST FLR - NEW
INSTALL TOILET PARTITIONS - BLDG 2 - 1ST FLR -
INSTALL INTERIOR GLAZING - BLDG 2 - 1ST FLR - NE
INSTALL ACOUSTICAL CLG TILE - BLDG 2 - 1ST FLR -
PERFORM TEST & BALANCE - BLDG 2 - 1ST FLR - NEW
INSTALL BATH ACCESSORIES - BLDG 2 - 1ST FLR - NE
INSTALL ELEC TRIM - BLDG 2 - 1ST FLR - NEW
INSTALL SYSTEMS TRIM/DEVICES - BLDG 2 - 1ST FLR
INSTALL FIRE SPRKLR HEADS/TRIM - BLDG 2 - 1ST FL
INSTALL CHALK/TACKBOARD - BLDG 2 - 1ST FLR - NEW
METAL SHELVING/LOCKERS - BLDG 2 - 1ST FLR - NEW
INSTALL FIRE EXTINGUISHERS - BLDG 2 - 1ST FLR -
INSTALL CARPET/FLOORING - BLDG 2 - 1ST FLR - NEW
FINAL INSPECTIONS - BLDG 2 - 1ST FLR - NEW
CONTRACTOR COMPLETION - BLDG 2 - 1ST FLR - NEW
METAL FRAMING - TOP TRACK - BLDG 2 - 2ND FLR - N
INSTALL DUCTWORK - BLDG 2 - 2ND FLR - NEW
INSTALL METAL FRAMING - BLDG 2 - 2ND FLR - NEW
INSTALL HVAC PIPING - BLDG 2 - 2ND FLR - NEW
INSTALL FIRE SPRKLR ROUGH - BLDG 2 - 2ND FLR - N
INSTALL PLUMBING ROUGH - BLDG 2 - 2ND FLR - NEW
INSTALL HVAC EQUIP - BLDG 2 - 2ND FLR - NEW
INSTALL ELECTRIC ROUGH - BLDG 2 - 2ND FLR - NEW
INSTALL INTERCOM BACKBOXES - BLDG 2 - 2ND FLR
INSTALL DUCTWORK INSULATION - BLDG 2 - 2ND FL
INSPECT FIRE SPRINKLER ABOVE CLG - 2ND FLR - B 2
HVAC DUCT CONNECT/HOOK-UP - BLDG 2 - 2ND FLR
INSPECT PLUMBING - BLDG 2 - 2ND FLR - NEW
INSPECT ELECTRICAL ROUGH - BLDG 2 - 2ND FLR - N
© Primavera Systems, Inc.
Start Date 09JUN08
Finish Date 07JUN10
Data Date 09JUN08
Run Date 08OCT08 08:10
Early Bar
Progress Bar
Critical Activity
BASZ
HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL
Sheet 11 of 16
ORGANIZED BY AREA
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
Total
Float
01617.0202 INSPECT FRAMING - 2ND FLR - BLDG 2 - NEW 2 13MAY09 14MAY09 73
15657.0202 HVAC PIPING CONNECT/HOOK-UP - BLDG 2 - 2ND FLR - 7 13MAY09 21MAY09 115
01615.0202 INSPECT HVAC - BLDG 2 - 2ND FLR - NEW 2 14MAY09 15MAY09 119
09250.0202 HANG DRYWALL - BLDG 2 - 2ND FLR - NEW 15 15MAY09 05JUN09 73
09251.0202 FINISH DRYWALL - BLDG 2 - 2ND FLR - NEW 15 29MAY09 18JUN09 73
09900.0202 PAINT INTERIOR PRIME COAT - BLDG 2 - 2ND FLR - N 8 19JUN09 30JUN09 73
09310.0202 INSTALL CERAMIC TILE - BLDG 2 - 2ND FLR - NEW 15 19JUN09 10JUL09 95
09901.0202 PAINT INTERIOR FINISH COAT - BLDG 2 - 2ND FLR - 15 01JUL09 22JUL09 73
06410.0202 INSTALL CABINETS - BLDG 2 - 2ND FLR - NEW 17 13JUL09 04AUG09 95
09510.0202 INSTALL ACOUSTICAL CLG GRID - BLDG 2 - 2ND FLR - 15 23JUL09 12AUG09 73
08100.0202 HANG DOORS - BLDG 2 - 2ND FLR - NEW 12 23JUL09 07AUG09 107
15940.0202 INSTALL HVAC GRILLS/TRIM - BLDG 2 - 2ND FLR - NE 12 31JUL09 17AUG09 73
16500.0202 INSTALL ELEC FIXTURES - BLDG 3 - 2ND FLR - NEW 17 31JUL09 24AUG09 73
15440.0202 INSTALL PLUMB FIXTURES - BLDG 2 - 2ND FLR - NEW 13 05AUG09 21AUG09 95
08710.0202 INSTALL FINISH HARDWARE - BLDG 2 - 2ND FLR - NEW 10 10AUG09 21AUG09 107
13129.0202 INTERCOM INSTALLATION - BLDG 2 - 2ND FLR - NEW 15 13AUG09 02SEP09 84
11132.0202 INSTALL PROJECTION SCREENS - BLDG 2 - 2ND FLR - 5 13AUG09 19AUG09 94
15980.0202 START-UP HVAC SYSTEM - BLDG 2 - 2ND FLR - NEW 5 18AUG09 24AUG09 73
10801.0202 INSTALL TOILET PARTITIONS - BLDG 2 - 2ND FLR - 7 24AUG09 01SEP09 95
08800.0202 INSTALL INTERIOR GLAZING - BLDG 2 - 2ND FLR - NE 5 24AUG09 28AUG09 102
09515.0202 INSTALL ACOUSTICAL CLG TILE - BLDG 2 - 2ND FLR - 8 25AUG09 03SEP09 73
15990.0202 PERFORM TEST & BALANCE - BLDG 2 - 2ND FLR - NEW 5 25AUG09 31AUG09 101
10800.0202 INSTALL BATH ACCESSORIES - BLDG 2 - 2ND FLR - NE 5 02SEP09 09SEP09 95
16505.0202 INSTALL ELEC TRIM - BLDG 2 - 2ND FLR - NEW 10 04SEP09 18SEP09 73
16710.0202 INSTALL SYSTEMS TRIM/DEVICES - BLDG 2 - 2ND FLR 10 04SEP09 18SEP09 73
15310.0202 INSTALL FIRE SPRKLR HEADS/TRIM - BLDG 2 - 2ND FL 7 04SEP09 15SEP09 76
10100.0202 INSTALL CHALK/TACKBOARD - BLDG 2 - 2ND FLR - NEW 8 04SEP09 16SEP09 78
10600.0202 METAL SHELVING/LOCKERS - BLDG 2 - 2ND FLR - NEW 7 04SEP09 15SEP09 91
10024.0202 INSTALL FIRE EXTINGUISHERS - BLDG 2 - 2ND FLR - 5 04SEP09 11SEP09 93
09680.0202 INSTALL CARPET/FLOORING - BLDG 2 - 2ND FLR - NEW 15 21SEP09 09OCT09 73
01690.0202 FINAL INSPECTIONS - BLDG 2 - 2ND FLR - NEW 10 12OCT09 23OCT09 73
17000.0202 CONTRACTOR COMPLETION - BLDG 2 - 2ND FLR - NEW 0 23OCT09 73
PARENT DROP-OFF
02200.75 EARTHWORK - PARENT DROP OFF 10 02JUL09 16JUL09 38
03300.75 COVERED WALK FTGS - PARENT DROP OFF 15 17JUL09 06AUG09 73
02720.75 STORM DRAINAGE SYSTEM - PARENT DROP OFF 5 17JUL09 23JUL09 78
2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL
INSPECT FRAMING - 2ND FLR - BLDG 2 - NEW
HVAC PIPING CONNECT/HOOK-UP - BLDG 2 - 2ND F
INSPECT HVAC - BLDG 2 - 2ND FLR - NEW
HANG DRYWALL - BLDG 2 - 2ND FLR - NEW
FINISH DRYWALL - BLDG 2 - 2ND FLR - NEW
PAINT INTERIOR PRIME COAT - BLDG 2 - 2ND F
INSTALL CERAMIC TILE - BLDG 2 - 2ND FLR -
PAINT INTERIOR FINISH COAT - BLDG 2 - 2N
INSTALL CABINETS - BLDG 2 - 2ND FLR - NEW
INSTALL ACOUSTICAL CLG GRID - BLDG
HANG DOORS - BLDG 2 - 2ND FLR - NEW
INSTALL HVAC GRILLS/TRIM - BLDG 2 - 2
INSTALL ELEC FIXTURES - BLDG 3 - 2ND
INSTALL PLUMB FIXTURES - BLDG 2 - 2N
INSTALL FINISH HARDWARE - BLDG 2 - 2
INTERCOM INSTALLATION - BLDG 2 - 2ND FLR - NEW
INSTALL PROJECTION SCREENS - BLDG
START-UP HVAC SYSTEM - BLDG 2 - 2ND FLR - NEW
INSTALL TOILET PARTITIONS - BLDG 2 - 2ND FLR -
INSTALL INTERIOR GLAZING - BLDG 2 - 2ND FLR - NE
INSTALL ACOUSTICAL CLG TILE - BLDG 2 - 2ND FLR -
PERFORM TEST & BALANCE - BLDG 2
INSTALL BATH ACCESSORIES - BLDG 2 - 2ND FLR - NE
INSTALL ELEC TRIM - BLDG 2 - 2ND FLR - NEW
INSTALL SYSTEMS TRIM/DEVICES - BLDG 2 - 2ND FLR
INSTALL FIRE SPRKLR HEADS/TRIM - BLDG 2 - 2ND FL
INSTALL CHALK/TACKBOARD - BLDG
METAL SHELVING/LOCKERS - BLDG 2 - 2ND FLR - NEW
INSTALL FIRE EXTINGUISHERS - BLDG 2 - 2ND FLR -
INSTALL CARPET/FLOORING - BLDG 2 - 2ND FLR - NEW
FINAL INSPECTIONS - BLDG 2 - 2ND FLR - NEW
CONTRACTOR COMPLETION - BLDG 2 - 2ND FLR - NEW
EARTHWORK - PARENT DROP OFF
COVERED WALK FTGS - PARENT DROP OFF
STORM DRAINAGE SYSTEM - PARENT DROP OFF
© Primavera Systems, Inc.
Start Date 09JUN08
Finish Date 07JUN10
Data Date 09JUN08
Run Date 08OCT08 08:10
Early Bar
Progress Bar
Critical Activity
BASZ
HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL
Sheet 12 of 16
ORGANIZED BY AREA
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
Total
Float
02510.75 STABILIZE SUBGRADE - PARENT DROP OFF 10 24JUL09 06AUG09 78
03310.75 COVERED WALK STRUCTURE - PARENT DROP OFF 15 07AUG09 27AUG09 73
02520.75 CONCRETE CURBS - PARENT DROP OFF 10 07AUG09 20AUG09 78
02810.75 IRRIGATION SLEEVES - PARENT DROP OFF 5 07AUG09 13AUG09 83
02511.75 LIMEROCK BASE - PARENT DROP OFF 10 21AUG09 03SEP09 78
16530.75 INSTALL ELEC POLES/FIXTURES - PARENT DROP OFF 10 21AUG09 03SEP09 93
03330.75 SIDEWALKS - PARENT DROP OFF 10 28AUG09 11SEP09 73
02512.75 ASPHALT PAVING - PARENT DROP OFF 10 14SEP09 25SEP09 73
02811.75 IRRIGATION - PARENT DROP OFF 10 28SEP09 09OCT09 73
02830.75 CHAIN LINK FENCING - PARENT DROP OFF 5 28SEP09 02OCT09 83
02580.75 STRIPING - PARENT DROP OFF 3 28SEP09 30SEP09 90
02900.75 LANDSCAPING/GRASSING - PARENT DROP OFF 15 05OCT09 23OCT09 73
17000.75 CONTRACTOR COMPLETION - PARENT DROP OFF 0 23OCT09 73
BUS DROP-OFF
02200.76 EARTHWORK - BUS DROP-OFF 10 10JUL09 23JUL09 38
03300.76 COVERED WALK FTGS - BUS DROP-OFF 15 24JUL09 13AUG09 68
02720.76 STORM DRAINAGE SYSTEM - BUS DROP-OFF 5 24JUL09 30JUL09 73
02510.76 STABILIZE SUBGRADE - BUS DROP-OFF 10 31JUL09 13AUG09 73
03310.76 COVERED WALK STRUCTURE - BUS DROP-OFF 15 14AUG09 03SEP09 68
02520.76 CONCRETE CURBS - BUS DROP-OFF 10 14AUG09 27AUG09 73
02810.76 IRRIGATION SLEEVES - BUS DROP-OFF 5 14AUG09 20AUG09 78
02511.76 LIMEROCK BASE - BUS DROP-OFF 10 28AUG09 11SEP09 73
16530.76 INSTALL ELEC POLES/FIXTURES - BUS DROP-OFF 10 28AUG09 11SEP09 88
03330.76 SIDEWALKS - BUS DROP-OFF 10 04SEP09 18SEP09 68
02512.76 ASPHALT PAVING - BUS DROP-OFF 10 21SEP09 02OCT09 68
02811.76 IRRIGATION - BUS DROP-OFF 10 05OCT09 16OCT09 68
02830.76 CHAIN LINK FENCING - BUS DROP-OFF 5 05OCT09 09OCT09 78
02580.76 STRIPING - BUS DROP-OFF 3 05OCT09 07OCT09 85
02900.76 LANDSCAPING/GRASSING - BUS DROP-OFF 15 12OCT09 30OCT09 68
17000.76 CONTRACTOR COMPLETION - BUS DROP-OFF 0 30OCT09 68
STAFF PARKING
02200.77 EARTHWORK - STAFF PARKING 10 17JUL09 30JUL09 38
03300.77 COVERED WALK FTGS - STAFF PARKING 15 31JUL09 20AUG09 63
02720.77 STORM DRAINAGE SYSTEM - STAFF PARKING 5 31JUL09 06AUG09 68
02510.77 STABILIZE SUBGRADE - STAFF PARKING 10 07AUG09 20AUG09 68
2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL
STABILIZE SUBGRADE - PARENT DROP OFF
COVERED WALK STRUCTURE - PARENT DROP OFF
CONCRETE CURBS - PARENT DROP OFF
IRRIGATION SLEEVES - PARENT DROP OFF
LIMEROCK BASE - PARENT DROP OFF
INSTALL ELEC POLES/FIXTURES - PAR
SIDEWALKS - PARENT DROP OFF
ASPHALT PAVING - PARENT DROP OFF
IRRIGATION - PARENT DROP OFF
CHAIN LINK FENCING - PARENT DROP OFF
STRIPING - PARENT DROP OFF
LANDSCAPING/GRASSING - PARENT DROP OFF
CONTRACTOR COMPLETION - PARENT DROP OFF
EARTHWORK - BUS DROP-OFF
COVERED WALK FTGS - BUS DROP-OFF
STORM DRAINAGE SYSTEM - BUS DROP-OFF
STABILIZE SUBGRADE - BUS DROP-OFF
COVERED WALK STRUCTURE - BUS DROP-OFF
CONCRETE CURBS - BUS DROP-OFF
IRRIGATION SLEEVES - BUS DROP-OFF
LIMEROCK BASE - BUS DROP-OFF
INSTALL ELEC POLES/FIXTURES - BUS DROP-OFF
SIDEWALKS - BUS DROP-OFF
ASPHALT PAVING - BUS DROP-OFF
IRRIGATION - BUS DROP-OFF
CHAIN LINK FENCING - BUS DROP-OFF
STRIPING - BUS DROP-OFF
LANDSCAPING/GRASSING - BUS DROP-OFF
CONTRACTOR COMPLETION - BUS DROP-OFF
EARTHWORK - STAFF PARKING
COVERED WALK FTGS - STAFF PARKING
STORM DRAINAGE SYSTEM - STAFF PARKING
STABILIZE SUBGRADE - STAFF PARKING
© Primavera Systems, Inc.
Start Date 09JUN08
Finish Date 07JUN10
Data Date 09JUN08
Run Date 08OCT08 08:10
Early Bar
Progress Bar
Critical Activity
BASZ
HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL
Sheet 13 of 16
ORGANIZED BY AREA
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
Total
Float
03310.77 COVERED WALK STRUCTURE - STAFF PARKING 15 21AUG09 11SEP09 63
02520.77 CONCRETE CURBS - STAFF PARKING 10 21AUG09 03SEP09 68
02810.77 IRRIGATION SLEEVES - STAFF PARKING 5 21AUG09 27AUG09 73
02511.77 LIMEROCK BASE - STAFF PARKING 10 04SEP09 18SEP09 68
16530.77 INSTALL ELEC POLES/FIXTURES - STAFF PARKING 10 04SEP09 18SEP09 83
03330.77 SIDEWALKS - STAFF PARKING 10 14SEP09 25SEP09 63
02512.77 ASPHALT PAVING - STAFF PARKING 10 28SEP09 09OCT09 63
02811.77 IRRIGATION - STAFF PARKING 10 12OCT09 23OCT09 63
02830.77 CHAIN LINK FENCING - STAFF PARKING 5 12OCT09 16OCT09 73
02580.77 STRIPING - STAFF PARKING 3 12OCT09 14OCT09 80
02900.77 LANDSCAPING/GRASSING - STAFF PARKING 15 19OCT09 06NOV09 63
17000.77 CONTRACTOR COMPLETION - STAFF PARKING 0 06NOV09 63
VISITOR PARKING
02200.78 EARTHWORK - VISITOR PARKING 10 31JUL09 13AUG09 38
03300.78 COVERED WALK FTGS - VISITOR PARKING 15 14AUG09 03SEP09 53
02720.78 STORM DRAINAGE SYSTEM - VISITOR PARKING 5 14AUG09 20AUG09 58
02510.78 STABILIZE SUBGRADE - VISITOR PARKING 10 21AUG09 03SEP09 58
03310.78 COVERED WALK STRUCTURE - VISITOR PARKING 15 04SEP09 25SEP09 53
02520.78 CONCRETE CURBS - VISITOR PARKING 10 04SEP09 18SEP09 58
02810.78 IRRIGATION SLEEVES - VISITOR PARKING 5 04SEP09 11SEP09 63
02511.78 LIMEROCK BASE - VISITOR PARKING 10 21SEP09 02OCT09 58
16530.78 INSTALL ELEC POLES/FIXTURES - VISITOR PARKING 10 21SEP09 02OCT09 73
03330.78 SIDEWALKS - VISITOR PARKING 10 28SEP09 09OCT09 53
02512.78 ASPHALT PAVING - VISITOR PARKING 10 12OCT09 23OCT09 53
02811.78 IRRIGATION - VISITOR PARKING 10 26OCT09 06NOV09 53
02830.78 CHAIN LINK FENCING - VISITOR PARKING 5 26OCT09 30OCT09 63
02580.78 STRIPING - VISITOR PARKING 3 26OCT09 28OCT09 70
02900.78 LANDSCAPING/GRASSING - VISITOR PARKING 15 02NOV09 20NOV09 53
17000.78 CONTRACTOR COMPLETION - VISITOR PARKING 0 20NOV09 53
SERVICE YARD/STAFF PARKING
02200.79 EARTHWORK - SERVICE YARD/PARKING 10 14AUG09 27AUG09 38
02720.79 STORM DRAINAGE SYSTEM - SERVICE YARD/PARKING 5 28AUG09 03SEP09 48
02510.79 STABILIZE SUBGRADE - SERVICE YARD/PARKING 10 04SEP09 18SEP09 48
03330.79 SIDEWALKS - SERVICE YARD/PARKING 10 14SEP09 25SEP09 63
02520.79 CONCRETE CURBS - SERVICE YARD/PARKING 10 21SEP09 02OCT09 48
2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL
COVERED WALK STRUCTURE - STAFF PARKING
CONCRETE CURBS - STAFF PARKING
IRRIGATION SLEEVES - STAFF PARKING
LIMEROCK BASE - STAFF PARKING
INSTALL ELEC POLES/FIXTURES - STAFF PARKING
SIDEWALKS - STAFF PARKING
ASPHALT PAVING - STAFF PARKING
IRRIGATION - STAFF PARKING
CHAIN LINK FENCING - STAFF PARKING
STRIPING - STAFF PARKING
LANDSCAPING/GRASSING - STAFF PARKING
CONTRACTOR COMPLETION - STAFF PARKING
EARTHWORK - VISITOR PARKING
COVERED WALK FTGS - VISITOR PARKING
STORM DRAINAGE SYSTEM - VISITOR PARKING
STABILIZE SUBGRADE - VISITOR PARKING
COVERED WALK STRUCTURE - VISITOR PARKING
CONCRETE CURBS - VISITOR PARKING
IRRIGATION SLEEVES - VISITOR PARKING
LIMEROCK BASE - VISITOR PARKING
INSTALL ELEC POLES/FIXTURES - VISITOR PARKING
SIDEWALKS - VISITOR PARKING
ASPHALT PAVING - VISITOR PARKING
IRRIGATION - VISITOR PARKING
CHAIN LINK FENCING - VISITOR PARKING
STRIPING - VISITOR PARKING
LANDSCAPING/GRASSING - VISITOR PARKING
CONTRACTOR COMPLETION - VISITOR PARKING
EARTHWORK - SERVICE YARD/PARKING
STORM DRAINAGE SYSTEM - SERVICE YARD/PARKING
STABILIZE SUBGRADE - SERVICE YARD/PARKING
SIDEWALKS - SERVICE YARD/PARKING
CONCRETE CURBS - SERVICE YARD/PARKING
© Primavera Systems, Inc.
Start Date 09JUN08
Finish Date 07JUN10
Data Date 09JUN08
Run Date 08OCT08 08:10
Early Bar
Progress Bar
Critical Activity
BASZ
HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL
Sheet 14 of 16
ORGANIZED BY AREA
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
Total
Float
02810.79 IRRIGATION SLEEVES - SERVICE YARD/PARKING 5 21SEP09 25SEP09 53
02511.79 LIMEROCK BASE - SERVICE YARD/PARKING 10 05OCT09 16OCT09 48
16530.79 INSTALL ELEC POLES/FIXTURES - SERVICE YARD/PARKI 10 05OCT09 16OCT09 63
02512.79 ASPHALT PAVING - SERVICE YARD/PARKING 10 19OCT09 30OCT09 48
02811.79 IRRIGATION - SERVICE YARD/PARKING 10 02NOV09 13NOV09 48
02830.79 CHAIN LINK FENCING - SERVICE YARD/PARKING 5 02NOV09 06NOV09 58
02580.79 STRIPING - SERVICE YARD/PARKING 3 02NOV09 04NOV09 65
02900.79 LANDSCAPING/GRASSING - SERVICE YARD/PARKING 15 09NOV09 30NOV09 48
17000.79 CONTRACTOR COMPLETION - SERVICE YARD/PARKING 0 30NOV09 48
PLAYCOURTS
02200.80 DEMO/CLEARING/EARTHWORK - HARDCOURTS 10 24JUL09 06AUG09 42
16101.80 ELECTRICAL U\G R-I - HARDCOURTS 7 07AUG09 17AUG09 54
02512.80 HARDCOURT SURFACE - HARDCOURTS 10 18AUG09 31AUG09 54
16530.80 ELECTRICAL POLES/FIXTURES - HARDCOURTS 7 01SEP09 10SEP09 54
02890.80 ATHLETIC SURFACE - HARDCOURTS 10 11SEP09 24SEP09 54
02830.80 CHAIN LINK FENCING - HARDCOURTS 10 25SEP09 08OCT09 54
02811.80 IRRIGATION - HARDCOURTS 12 30SEP09 15OCT09 54
02900.80 LANDSCAPING/GRASSING - HARDCOURTS 15 16OCT09 05NOV09 54
11485.80 ATHLETIC EQUIPMENT - HARDCOURTS 10 06NOV09 19NOV09 54
17000.80 CONTRACTOR COMPLETION - HARDCOURTS 0 19NOV09 54
COURTYARDS & COVERED PLAY AREA
02200.82 EARTHWORK - COURTYARD 10 07AUG09 20AUG09 42
02720.82 STORM DRAINAGE - COURTYARD 15 21AUG09 11SEP09 42
16101.82 ELECTRICAL U\G R-I - COURTYARD 15 14SEP09 02OCT09 42
02810.82 IRRIGATION SLEEVES - COURTYARD 4 29SEP09 02OCT09 42
03310.82 CONC WALKS - COURTYARD 15 05OCT09 23OCT09 42
16140.82 ELECTRICAL WIRE/CABLE - COURTYARD 15 05OCT09 23OCT09 47
03300.82 CONC PLANTER WALLS -COURTYARD 10 05OCT09 16OCT09 52
02550.82 UNIT PAVERS - COURTYARD 15 26OCT09 13NOV09 42
02811.82 IRRIGATION - COURTYARD 10 26OCT09 06NOV09 47
16530.82 ELECTRICAL POLES/FIXTURES - COURTYARD 10 26OCT09 06NOV09 47
10005.82 INSTALL FLAG POLE - COURTYARD 5 26OCT09 30OCT09 52
03320.82 CONC BENCHES - COURTYARD 5 26OCT09 30OCT09 68
02900.82 LANDSCAPING - COURTYARD 16 16NOV09 08DEC09 42
17000.82 CONTRACTOR COMPLETION - COURTYARD 0 08DEC09 42
2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL
IRRIGATION SLEEVES - SERVICE YARD/PARKING
LIMEROCK BASE - SERVICE YARD/PARKING
INSTALL ELEC POLES/FIXTURES - SERVICE YARD/PARKI
ASPHALT PAVING - SERVICE YARD/PARKING
IRRIGATION - SERVICE YARD/PARKING
CHAIN LINK FENCING - SERVICE YARD/PARKING
STRIPING - SERVICE YARD/PARKING
LANDSCAPING/GRASSING - SERVICE YARD/PARKING
CONTRACTOR COMPLETION - SERVICE YARD/PARKING
DEMO/CLEARING/EARTHWORK - HARDCOURTS
ELECTRICAL U\G R-I - HARDCOURTS
HARDCOURT SURFACE - HARDCOURTS
ELECTRICAL POLES/FIXTURES - HARDCOURTS
ATHLETIC SURFACE - HARDCOURTS
CHAIN LINK FENCING - HARDCOURTS
IRRIGATION - HARDCOURTS
LANDSCAPING/GRASSING - HARDCOURTS
ATHLETIC EQUIPMENT - HARDCOURTS
CONTRACTOR COMPLETION - HARDCOURTS
EARTHWORK - COURTYARD
STORM DRAINAGE - COURTYARD
ELECTRICAL U\G R-I - COURTYARD
IRRIGATION SLEEVES - COURTYARD
CONC WALKS - COURTYARD
ELECTRICAL WIRE/CABLE - COURTYARD
CONC PLANTER WALLS -COURTYARD
UNIT PAVERS - COURTYARD
IRRIGATION - COURTYARD
ELECTRICAL POLES/FIXTURES - COURTYARD
INSTALL FLAG POLE - COURTYARD
CONC BENCHES - COURTYARD
LANDSCAPING - COURTYARD
CONTRACTOR COMPLETION - COURTYARD
© Primavera Systems, Inc.
Start Date 09JUN08
Finish Date 07JUN10
Data Date 09JUN08
Run Date 08OCT08 08:10
Early Bar
Progress Bar
Critical Activity
BASZ
HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL
Sheet 15 of 16
ORGANIZED BY AREA
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
Total
Float
OFF-SITE - FLAGLER
02200.81 CLEARING & EARTHWORK - OFF-SITE - FLAGLER 10 28AUG09 11SEP09 38
02720.81 STORM DRAINAGE - OFF-SITE - FLAGLER 10 14SEP09 25SEP09 38
02510.81 STABILIZATION - OFF-SITE - FLAGLER 10 28SEP09 09OCT09 38
02511.81 LIMEROCK BASE - OFF-SITE - FLAGLER 15 12OCT09 30OCT09 38
02520.81 CONCRETE CURBS - OFF-SITE - FLAGLER 15 02NOV09 20NOV09 38
02512.81 ASPHALT PAVING - OFF-SITE - FLAGLER 10 23NOV09 07DEC09 38
02580.81 STRIPING & SIGNAGE - OFF-SITE - FLAGLER 5 08DEC09 14DEC09 38
02900.81 GRASSING/SOD - OFF-SITE - FLAGLER 5 08DEC09 14DEC09 38
17000.81 CONTRACTOR COMPLETION - OFF-SITE - FLAGLER 0 14DEC09 38
COMPLETION
17000.02 SUBSTANTIAL COMPLETION - PHASE 2 0 08FEB10 0
17100.02 PUNCHLIST & CLOSEOUT 84 09FEB10 07JUN10 0
17200.02 FINAL COMPLETION 0 07JUN10 0
2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL
CLEARING & EARTHWORK - OFF-SITE - FLAGLER
STORM DRAINAGE - OFF-SITE - FLAGLER
STABILIZATION - OFF-SITE - FLAGLER
LIMEROCK BASE - OFF-SITE - FLAGLER
CONCRETE CURBS - OFF-SITE - FLAGLER
ASPHALT PAVING - OFF-SITE - FLAGLER
STRIPING & SIGNAGE - OFF-SITE - FLAGLER
GRASSING/SOD - OFF-SITE - FLAGLER
CONTRACTOR COMPLETION - OFF-SITE - FLAGLER
SUBSTANTIAL COMPLETION - PHASE 2
PUNCHLIST & CLOSEOUT
FINAL COMPLETION
© Primavera Systems, Inc.
Start Date 09JUN08
Finish Date 07JUN10
Data Date 09JUN08
Run Date 08OCT08 08:10
Early Bar
Progress Bar
Critical Activity
BASZ
HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL
Sheet 16 of 16
ORGANIZED BY AREA