gmp & process validation
Embed Size (px)
TRANSCRIPT
-
8/3/2019 GMP & Process Validation
1/60
PharmaceuticalBiotechnology
Biotechnology & GMP
Raw material, Process & Process
Validation and its Regulatory
Aspects
-
8/3/2019 GMP & Process Validation
2/60
References:
GMP for pharmaceutical products: main principles;
WHO TRS No. 908,2003 GMP for biological products; WHO TRS No.822,1992
A WHO guide to GMP requirements, part 2:validation;WHO,1997
2
-
8/3/2019 GMP & Process Validation
3/60
GMP
The good practices outlined are to be considered
general guides and they may be adapted to meet
individual needs.
3
-
8/3/2019 GMP & Process Validation
4/60
GMP-are aimed primarily at diminishing the risks
inherent in any pharmaceutical production
Cross contamination; unexpected contaminants
Mix-ups; confusion (false labels)
4
-
8/3/2019 GMP & Process Validation
5/60
Good practices in production Principle: production operations must follow
clearly defined procedures in accordance with
manufacturing and marketing authorizations, withthe objective of obtaining products of the requisitequality.
5
-
8/3/2019 GMP & Process Validation
6/60
6
Production of Vaccine
Master seed Working seed
Inoculum
Single harvest
Pool/Concentrated material
Purified/Bulk material
Final bulkFinal lot
Media/Cell culture
Excipients
Validation
- process
- method
Stability studies
GMP
-
8/3/2019 GMP & Process Validation
7/60
Good practices in
production:General All handling of materials and products;
receipt
cleaning
quarantine sampling
storage
labelling
dispensing
processing
packaging
distribution should be done in accordance with written procedures and recorded.
7
-
8/3/2019 GMP & Process Validation
8/60
Good practices in
production:General Any deviation from instructions or procedures
should be avoid as far as possible.
If deviations occur: should be done in accordance withan approved procedure
approved in writing by a designated person
8
-
8/3/2019 GMP & Process Validation
9/60
Good practices in
production:General Checks on yields and reconciliation of quantities
to ensure that there are no discrepancies outside
acceptable limits.
9
-
8/3/2019 GMP & Process Validation
10/60
Good practices in
production:General Operation on different products should not be
carried out simultaneously or consecutively in the
same room or area unless there is no risk of mix-
up or cross-contamination.
10
-
8/3/2019 GMP & Process Validation
11/60
Good practices in
production:General At all time during processing
all materials
bulk containers major items of equipment
rooms
packaging lines
being used should be labeled or identified
11
-
8/3/2019 GMP & Process Validation
12/60
Good practices in
production:General Access to production premises should be
restricted to authorized personnel.
Non-medicinal products should not be producedin areas or with equipment destined for the
production of pharmaceutical products.
12
-
8/3/2019 GMP & Process Validation
13/60
Good practices in
production:General In-process controls are usually performed within
the production area.
The performance should not have any negative effecton the quality of the product or another product.
13
-
8/3/2019 GMP & Process Validation
14/60
Good practices in production: Prevention of cross-
contamination during production
When dry materials and products are used inproduction, special precautionshould be taken toprevent the generation and dissemination of dust. proper air control e.g. supply and extraction of air of
suitable quality
14
-
8/3/2019 GMP & Process Validation
15/60
Good practices in production: Prevention of
cross-contamination during production
Contamination of a starting material or of a product by
another material or product must be avoid.
accidental cross-contamination arises from
uncontrolled release of dust, gases, particles, vapours. sprays or organismsfrom materials and products in process
residues on equipment
intruding insects
operators clothing, skin, etc.
most hazardous, highly sensitizing materials
living organisms, hormones, cytotoxic substances, and others
15
-
8/3/2019 GMP & Process Validation
16/60
Good practices in production: Prevention of
cross-contamination during production
Avoided by taking appropriate technical e.g.
carrying out production in dedicated and self-contained
areas
conducting campaign production followed by
appropriate cleaning in accordance with a validated
cleaning procedure
providing appropriately designed airlocks, pressure
differentials and air supply and extraction systems
16
-
8/3/2019 GMP & Process Validation
17/60
Good practices in production: Prevention of
cross-contamination during production
minimizing the risk of contamination caused by recirculationor re-entry of untreated or insufficiently treated air
wearing protective clothing
using cleaning and decontamination procedures of knowneffectiveness
using a closed system in production
testing for residues
using cleanliness status labels on equipment
17
-
8/3/2019 GMP & Process Validation
18/60
Good practices in production: Prevention of
cross-contamination during production
Measures to prevent cross-contamination and
their effectiveness should be checked periodically
according to SOP
Production areas periodic
environmental monitoring
18
-
8/3/2019 GMP & Process Validation
19/60
Good practices in production:
Processing operations
Before any processing operation
work area and equipment
clean and free from any starting materials, products,product residues, labels or documents not required for thecurrent operation
19
-
8/3/2019 GMP & Process Validation
20/60
Good practices in production:
Processing operations
Any necessary in-process controls and environmental
controls should be carried out and recorded
Indicate the failures of equipment or services (e.g. water,gas) to equipment
defective EQ withdrawn
after use, production EQ
cleanedwithout delay, stored underclean and dry conditions in separate area
20
-
8/3/2019 GMP & Process Validation
21/60
Good practices in production:
Processing operations Time limits for storage of EQ after cleaning and
before use
Containers for filling should be cleaned beforefilling
Any significant deviation from the expected yield
recorded and investigated
21
-
8/3/2019 GMP & Process Validation
22/60
Good practices in production:
Processing operations Checks
pipelines and other pieces of EQ used fortransportation of products
Pipe used for conveying distilled or deionizedwater sanitized and stored according to written procedures
(action limits for microbiological contamination and
measures
22
-
8/3/2019 GMP & Process Validation
23/60
Good practices in production:
Processing operations EQ and instruments
serviced and calibrated at prespecified interval
records maintained
checked daily or prior to use clearly indicated the date of calibration and servicing,
recalibration (label attached to instrument)
Repair and maintenance operations not present any hazard to the quality of the products
23
-
8/3/2019 GMP & Process Validation
24/60
GMP for biological products
:Production SOP for manufacturing operations: available, up
date
Starting material: source, origin, method ofmanufacture, QC
Media and culture shall be added to fermenter
and other vessels under carefully controlled
conditions, avoid contamination
24
-
8/3/2019 GMP & Process Validation
25/60
GMP for biological products
:Production Media should be sterilized in situ. Inline sterilizing
filters for routine addition of gases, media, acids,
alkalis, deforming agents, etc. to fermenter should be
used where possible.
Validation of sterilization.
Inactivation process: measures should be taken to
avoid risk of cross-contamination between treatedand untreated products.
25
-
8/3/2019 GMP & Process Validation
26/60
GMP for biological products
:Production A wide equipment used for chromatography
should be dedicated to purification of one product
should besterilized or sanitized between batches
define the life span of columns and the sterilization
method
26
-
8/3/2019 GMP & Process Validation
27/60
In-process controls play a specially important rolein ensuring the consistent quality of biologicalproducts because certain deficiencies may not be
revealed by testing the finished product. Tests that are crucial for quality control but that cannot
be carried out on the finished product shall beperformed at an appropriate stage of production.
27
-
8/3/2019 GMP & Process Validation
28/60
Samples of intermediate and final products shall be
retained in sufficient amount and under appropriate
storage conditions to allow the repetition or
confirmation of a batch control.
Certain operations require the continuous monitoring
of data during a production process e.g.monitoring
and recording of physical parameters during
fermentation.
28
-
8/3/2019 GMP & Process Validation
29/60
V
alidation: Definition Validation is the documented act of proving that
any procedure, process, equipment,
material,activity or system actually leads to theexpected result.
29
-
8/3/2019 GMP & Process Validation
30/60
V
alidation studies
analytical test
equipment
facility systems (air, water, steam, process;manufacturing processes, cleaning,sterilization, sterile filling, lyophilization)
30
Separate validation for
lyophilizer/ lyophilization process cleaning of
glassware/ cleaning of facility sterilizationprocess/sterility test
-
8/3/2019 GMP & Process Validation
31/60
V
alidation studies verify the system under test under the extremes
expected during the process to prove that the
system remains in control.
Critical equipment and processes are routinely
revalidated at appropriate intervals todemonstrate that the process remains in control.
31
-
8/3/2019 GMP & Process Validation
32/60
T
ype of validation Prospective
pre-planned protocol
Concurrent
base on data collected during actual performance of a process alreadyimplemented in a manufacturing facility
suit manufacturers of long standing, have well-controlled manufacturingprocess
Retrospective
for production for a long time, but has not been validated according to aprospective protocol and concurrent validation is not realistic option
is not generally accepted
32
-
8/3/2019 GMP & Process Validation
33/60
Type of validation
Laboratory-and pilot-scale validations
some production processes cannot be carried out
in production facility
33
removal of impurities by individual purification steps in process
- not acceptable to bring unacceptable impurities (endotoxin,
unwanted protein, contaminating bacteria and virus) spike intoprocess
-
8/3/2019 GMP & Process Validation
34/60
Facility systems and equipment:Stage of validation
Design qualification (DQ)
Installation Qualification (IQ)
Operational Qualification(OQ)
Performance Qualification (PQ)
34
Systems and EQ; PQ=validation
Depending on the function and operation of some EQ
-
8/3/2019 GMP & Process Validation
35/60
Facility systems and equipment
Design qualification (DQ)
necessary when planning and choosing EQ or
systems to ensure that components selected will have
adequate capacity to function for the intended
purpose, and will adequately serve the operations orfunctions of another piece of EQ or operation.
35
-
8/3/2019 GMP & Process Validation
36/60
Facility systems and equipment
Installation Qualification (IQ)
written for critical processing EQ and systems
list all the identification information, location, utilityrequirements, and any safety features of EQ
verify that the item matches the purchasespecifications
36
-
8/3/2019 GMP & Process Validation
37/60
Facility systems and equipment
Operational Qualification(OQ) outlines the information required to provide evidence that all
component of a system or of a piece of EQ operate as specified.
should provide a listing of SOPs for operation, maintenance andcalibration
define the specification and acceptance criteria
include information on EQ or system calibration, pre-operationalactivities, routine operations and their acceptance criteria
37
-
8/3/2019 GMP & Process Validation
38/60
Facility systems and equipment
Performance Qualification (PQ) performed after both IQ and OQ have been completed, reviewed
and approved
describes the procedures for demonstrating that a system or
piece of EQ can consistently perform and meet requiredspecification under routine operation and, where appropriate,under worst case situations
include description of preliminary procedures required, detailedperformance tests to be done, acceptance criteria
other supporting EQ used during qualification have been
validated.
38
-
8/3/2019 GMP & Process Validation
39/60
Facility systems and equipment
pH meter, incubator, centrifuge, freezer; IQ,OQ
39
system: air (HVAC), compressed air, pure steam,
raw steam, purified water, WFI, central vacuum; IQ,OQ, PQ
EQ: autoclave, oven, lyophilizer,continuous flowcentrifuge; IQ, OQ, PQ
-
8/3/2019 GMP & Process Validation
40/60
40
Process validation
A process is a series of interrelated functions and
activities using a variety of specified actions andEQ which is designed to produce a defined result.
-
8/3/2019 GMP & Process Validation
41/60
41
Process validationstudies examine a process under normal operating
conditions to prove that the process is in control
re-validation
modification to the process
problems occur
EQ or systems are changed
-
8/3/2019 GMP & Process Validation
42/60
42
Process validation
To validate the reproducibility and consistency of aprocess
full defined process is carried out using validated EQ
at least 3 times, under established procedure
process must successfully and consistently meet all acceptance
criteria at all steps throughout the procedure at least 3 timesconsecutively
Validated process
Worst case: to ensure that process isacceptable in the extreme case
-
8/3/2019 GMP & Process Validation
43/60
43
Process validation
Example
cleaning
sanitization
fumigation
depyrogenation sterilization
sterile filling
fermentation
bulk production
purification
inactivation
filling, capping, sealing
lyophilization
-
8/3/2019 GMP & Process Validation
44/60
44
Process validation
specific process clearly described in Master
formula or in SOP
all EQ; identity, code number, construction, operation
capacity, actual operating range
processing parameter; sufficiently detailed to permit
complete reproducibility (time period, pH, volume,
temp.etc.)
specification at each step
-
8/3/2019 GMP & Process Validation
45/60
45
Process validation
Very important
specifications for a process undergoing validation be
pre-determined
all critical processing parameters for which
specifications have been set, there must be equipment
to measure all of those parameters during thevalidation study
-
8/3/2019 GMP & Process Validation
46/60
46
Typical content requirements forprocess validations
Cleaning, Fumigation,Sanitization Process collecting liquid and swab
samples for testing of residualproduct
residual protein
endotoxin tests
microbial tests (bioburden)
chemical tests (chlorine and
phosphoric acid) residual cleaning agents
conductivity tests
pH
As relevant to thecleaning process
All analytical tests mustbe validated before
-
8/3/2019 GMP & Process Validation
47/60
47
Typical content requirements forprocess validations
Sterilization
sterilization filtration of solutions
microbial challenge
filter integrity tests
performance tests
-
8/3/2019 GMP & Process Validation
48/60
48
Typical content requirements forprocess validations
Depyrogenation process (dry heat, column
chromatography, other)
endotoxin content reduction of 3 logs
-
8/3/2019 GMP & Process Validation
49/60
49
Typical content requirements forprocess validations
Sterile filling test filling process
perform filling process with nutrient media
run at full scale for at least one fill size worst case; large volume and number of vials
filled vials incubated, observed and test for contamination byvalidated sterility test
must be sterile for 3 consecutive runs
media fill performed twice a year
size of run must be large enough to detect low levels ofcontamination e.g. contamination rate of 1/1000, 3000 units areneeded to provide 95% confidence
-
8/3/2019 GMP & Process Validation
50/60
50
Typical content requirements forprocess validations
Mock fermentation
full scale fermentation of a representative fermentation
process
to validate the parts of process involving connections,
sampling, and additions of nutrients etc.
fermentor prepared and operated in simulated process with
uninoculated nutrient media
process follow the full fermentation process 3 consecutive runs at each stage
-
8/3/2019 GMP & Process Validation
51/60
51
Typical content requirements forprocess validations
Production processes(fermentation, bulkproduction, purification, filling, lyophilization)
run according to approved Master formula including all
raw material, personnel, equipment, and facilitypreparations, in-process tests, processing, through tofinal testing of the batch lot.
all facility systems must be monitored
3 consecutive lots must be produced and all facility,EQ, support systems, product spec, and process beingvalidated must pass at all steps
-
8/3/2019 GMP & Process Validation
52/60
Validation: Type ofDocumentation
Validation master plan (VMP)
Validation protocol (VP)
Validation reports (VR) Standard operating procedures(SOPs)
52
-
8/3/2019 GMP & Process Validation
53/60
Master validation plan (MVP)
is a document pertaining to the whole facility thatdescribes which EQ, systems, methods andprocesses will be validated and when they will be
validated. provide the format required for each particular
validation document (IQ, OQ, PQ for EQ andsystems; process validation, analytical assay
validation)
53
-
8/3/2019 GMP & Process Validation
54/60
Master validation plan (MVP)
indicate what information is to be contained withineach document
indicate why and when revalidations will be
performed
who will decide what validations will be performed
order in which each part of the facility is validated
54
-
8/3/2019 GMP & Process Validation
55/60
Master validation plan (MVP)
indicate how to deal with any deviations
state the time interval permitted between eachvalidation
55
-
8/3/2019 GMP & Process Validation
56/60
-
8/3/2019 GMP & Process Validation
57/60
Validation: In summary, VMPshould containat least Validation policy
Organizational structure
Summary of facilities, systems, equipment, processes
to be validated Documentation format for protocols and reports
Planning and scheduling
Change control
Training requirements
57
-
8/3/2019 GMP & Process Validation
58/60
Validation: Protocol
Objectives of the validation and qualification study
Site of the study
Responsible personnel Description of the equipment
SOPs
Standards
Criteria for the relevant products and processes
58
-
8/3/2019 GMP & Process Validation
59/60
Validation: Report
Title
objective of the study
Refer to the protocol Details of material
Equipment
Programmes and cycles use
Details of procedures and test methods
59
-
8/3/2019 GMP & Process Validation
60/60
Validation: changes that requirerevalidation
Software changes; controllers
Site changes; operational changes
Change of source of material Change in the process
Significant equipment changes
Production area changes
Support system changes
60