gmp & process validation

Upload: ahmed-zia

Post on 06-Apr-2018

264 views

Category:

Documents


2 download

TRANSCRIPT

  • 8/3/2019 GMP & Process Validation

    1/60

    PharmaceuticalBiotechnology

    Biotechnology & GMP

    Raw material, Process & Process

    Validation and its Regulatory

    Aspects

  • 8/3/2019 GMP & Process Validation

    2/60

    References:

    GMP for pharmaceutical products: main principles;

    WHO TRS No. 908,2003 GMP for biological products; WHO TRS No.822,1992

    A WHO guide to GMP requirements, part 2:validation;WHO,1997

    2

  • 8/3/2019 GMP & Process Validation

    3/60

    GMP

    The good practices outlined are to be considered

    general guides and they may be adapted to meet

    individual needs.

    3

  • 8/3/2019 GMP & Process Validation

    4/60

    GMP-are aimed primarily at diminishing the risks

    inherent in any pharmaceutical production

    Cross contamination; unexpected contaminants

    Mix-ups; confusion (false labels)

    4

  • 8/3/2019 GMP & Process Validation

    5/60

    Good practices in production Principle: production operations must follow

    clearly defined procedures in accordance with

    manufacturing and marketing authorizations, withthe objective of obtaining products of the requisitequality.

    5

  • 8/3/2019 GMP & Process Validation

    6/60

    6

    Production of Vaccine

    Master seed Working seed

    Inoculum

    Single harvest

    Pool/Concentrated material

    Purified/Bulk material

    Final bulkFinal lot

    Media/Cell culture

    Excipients

    Validation

    - process

    - method

    Stability studies

    GMP

  • 8/3/2019 GMP & Process Validation

    7/60

    Good practices in

    production:General All handling of materials and products;

    receipt

    cleaning

    quarantine sampling

    storage

    labelling

    dispensing

    processing

    packaging

    distribution should be done in accordance with written procedures and recorded.

    7

  • 8/3/2019 GMP & Process Validation

    8/60

    Good practices in

    production:General Any deviation from instructions or procedures

    should be avoid as far as possible.

    If deviations occur: should be done in accordance withan approved procedure

    approved in writing by a designated person

    8

  • 8/3/2019 GMP & Process Validation

    9/60

    Good practices in

    production:General Checks on yields and reconciliation of quantities

    to ensure that there are no discrepancies outside

    acceptable limits.

    9

  • 8/3/2019 GMP & Process Validation

    10/60

    Good practices in

    production:General Operation on different products should not be

    carried out simultaneously or consecutively in the

    same room or area unless there is no risk of mix-

    up or cross-contamination.

    10

  • 8/3/2019 GMP & Process Validation

    11/60

    Good practices in

    production:General At all time during processing

    all materials

    bulk containers major items of equipment

    rooms

    packaging lines

    being used should be labeled or identified

    11

  • 8/3/2019 GMP & Process Validation

    12/60

    Good practices in

    production:General Access to production premises should be

    restricted to authorized personnel.

    Non-medicinal products should not be producedin areas or with equipment destined for the

    production of pharmaceutical products.

    12

  • 8/3/2019 GMP & Process Validation

    13/60

    Good practices in

    production:General In-process controls are usually performed within

    the production area.

    The performance should not have any negative effecton the quality of the product or another product.

    13

  • 8/3/2019 GMP & Process Validation

    14/60

    Good practices in production: Prevention of cross-

    contamination during production

    When dry materials and products are used inproduction, special precautionshould be taken toprevent the generation and dissemination of dust. proper air control e.g. supply and extraction of air of

    suitable quality

    14

  • 8/3/2019 GMP & Process Validation

    15/60

    Good practices in production: Prevention of

    cross-contamination during production

    Contamination of a starting material or of a product by

    another material or product must be avoid.

    accidental cross-contamination arises from

    uncontrolled release of dust, gases, particles, vapours. sprays or organismsfrom materials and products in process

    residues on equipment

    intruding insects

    operators clothing, skin, etc.

    most hazardous, highly sensitizing materials

    living organisms, hormones, cytotoxic substances, and others

    15

  • 8/3/2019 GMP & Process Validation

    16/60

    Good practices in production: Prevention of

    cross-contamination during production

    Avoided by taking appropriate technical e.g.

    carrying out production in dedicated and self-contained

    areas

    conducting campaign production followed by

    appropriate cleaning in accordance with a validated

    cleaning procedure

    providing appropriately designed airlocks, pressure

    differentials and air supply and extraction systems

    16

  • 8/3/2019 GMP & Process Validation

    17/60

    Good practices in production: Prevention of

    cross-contamination during production

    minimizing the risk of contamination caused by recirculationor re-entry of untreated or insufficiently treated air

    wearing protective clothing

    using cleaning and decontamination procedures of knowneffectiveness

    using a closed system in production

    testing for residues

    using cleanliness status labels on equipment

    17

  • 8/3/2019 GMP & Process Validation

    18/60

    Good practices in production: Prevention of

    cross-contamination during production

    Measures to prevent cross-contamination and

    their effectiveness should be checked periodically

    according to SOP

    Production areas periodic

    environmental monitoring

    18

  • 8/3/2019 GMP & Process Validation

    19/60

    Good practices in production:

    Processing operations

    Before any processing operation

    work area and equipment

    clean and free from any starting materials, products,product residues, labels or documents not required for thecurrent operation

    19

  • 8/3/2019 GMP & Process Validation

    20/60

    Good practices in production:

    Processing operations

    Any necessary in-process controls and environmental

    controls should be carried out and recorded

    Indicate the failures of equipment or services (e.g. water,gas) to equipment

    defective EQ withdrawn

    after use, production EQ

    cleanedwithout delay, stored underclean and dry conditions in separate area

    20

  • 8/3/2019 GMP & Process Validation

    21/60

    Good practices in production:

    Processing operations Time limits for storage of EQ after cleaning and

    before use

    Containers for filling should be cleaned beforefilling

    Any significant deviation from the expected yield

    recorded and investigated

    21

  • 8/3/2019 GMP & Process Validation

    22/60

    Good practices in production:

    Processing operations Checks

    pipelines and other pieces of EQ used fortransportation of products

    Pipe used for conveying distilled or deionizedwater sanitized and stored according to written procedures

    (action limits for microbiological contamination and

    measures

    22

  • 8/3/2019 GMP & Process Validation

    23/60

    Good practices in production:

    Processing operations EQ and instruments

    serviced and calibrated at prespecified interval

    records maintained

    checked daily or prior to use clearly indicated the date of calibration and servicing,

    recalibration (label attached to instrument)

    Repair and maintenance operations not present any hazard to the quality of the products

    23

  • 8/3/2019 GMP & Process Validation

    24/60

    GMP for biological products

    :Production SOP for manufacturing operations: available, up

    date

    Starting material: source, origin, method ofmanufacture, QC

    Media and culture shall be added to fermenter

    and other vessels under carefully controlled

    conditions, avoid contamination

    24

  • 8/3/2019 GMP & Process Validation

    25/60

    GMP for biological products

    :Production Media should be sterilized in situ. Inline sterilizing

    filters for routine addition of gases, media, acids,

    alkalis, deforming agents, etc. to fermenter should be

    used where possible.

    Validation of sterilization.

    Inactivation process: measures should be taken to

    avoid risk of cross-contamination between treatedand untreated products.

    25

  • 8/3/2019 GMP & Process Validation

    26/60

    GMP for biological products

    :Production A wide equipment used for chromatography

    should be dedicated to purification of one product

    should besterilized or sanitized between batches

    define the life span of columns and the sterilization

    method

    26

  • 8/3/2019 GMP & Process Validation

    27/60

    In-process controls play a specially important rolein ensuring the consistent quality of biologicalproducts because certain deficiencies may not be

    revealed by testing the finished product. Tests that are crucial for quality control but that cannot

    be carried out on the finished product shall beperformed at an appropriate stage of production.

    27

  • 8/3/2019 GMP & Process Validation

    28/60

    Samples of intermediate and final products shall be

    retained in sufficient amount and under appropriate

    storage conditions to allow the repetition or

    confirmation of a batch control.

    Certain operations require the continuous monitoring

    of data during a production process e.g.monitoring

    and recording of physical parameters during

    fermentation.

    28

  • 8/3/2019 GMP & Process Validation

    29/60

    V

    alidation: Definition Validation is the documented act of proving that

    any procedure, process, equipment,

    material,activity or system actually leads to theexpected result.

    29

  • 8/3/2019 GMP & Process Validation

    30/60

    V

    alidation studies

    analytical test

    equipment

    facility systems (air, water, steam, process;manufacturing processes, cleaning,sterilization, sterile filling, lyophilization)

    30

    Separate validation for

    lyophilizer/ lyophilization process cleaning of

    glassware/ cleaning of facility sterilizationprocess/sterility test

  • 8/3/2019 GMP & Process Validation

    31/60

    V

    alidation studies verify the system under test under the extremes

    expected during the process to prove that the

    system remains in control.

    Critical equipment and processes are routinely

    revalidated at appropriate intervals todemonstrate that the process remains in control.

    31

  • 8/3/2019 GMP & Process Validation

    32/60

    T

    ype of validation Prospective

    pre-planned protocol

    Concurrent

    base on data collected during actual performance of a process alreadyimplemented in a manufacturing facility

    suit manufacturers of long standing, have well-controlled manufacturingprocess

    Retrospective

    for production for a long time, but has not been validated according to aprospective protocol and concurrent validation is not realistic option

    is not generally accepted

    32

  • 8/3/2019 GMP & Process Validation

    33/60

    Type of validation

    Laboratory-and pilot-scale validations

    some production processes cannot be carried out

    in production facility

    33

    removal of impurities by individual purification steps in process

    - not acceptable to bring unacceptable impurities (endotoxin,

    unwanted protein, contaminating bacteria and virus) spike intoprocess

  • 8/3/2019 GMP & Process Validation

    34/60

    Facility systems and equipment:Stage of validation

    Design qualification (DQ)

    Installation Qualification (IQ)

    Operational Qualification(OQ)

    Performance Qualification (PQ)

    34

    Systems and EQ; PQ=validation

    Depending on the function and operation of some EQ

  • 8/3/2019 GMP & Process Validation

    35/60

    Facility systems and equipment

    Design qualification (DQ)

    necessary when planning and choosing EQ or

    systems to ensure that components selected will have

    adequate capacity to function for the intended

    purpose, and will adequately serve the operations orfunctions of another piece of EQ or operation.

    35

  • 8/3/2019 GMP & Process Validation

    36/60

    Facility systems and equipment

    Installation Qualification (IQ)

    written for critical processing EQ and systems

    list all the identification information, location, utilityrequirements, and any safety features of EQ

    verify that the item matches the purchasespecifications

    36

  • 8/3/2019 GMP & Process Validation

    37/60

    Facility systems and equipment

    Operational Qualification(OQ) outlines the information required to provide evidence that all

    component of a system or of a piece of EQ operate as specified.

    should provide a listing of SOPs for operation, maintenance andcalibration

    define the specification and acceptance criteria

    include information on EQ or system calibration, pre-operationalactivities, routine operations and their acceptance criteria

    37

  • 8/3/2019 GMP & Process Validation

    38/60

    Facility systems and equipment

    Performance Qualification (PQ) performed after both IQ and OQ have been completed, reviewed

    and approved

    describes the procedures for demonstrating that a system or

    piece of EQ can consistently perform and meet requiredspecification under routine operation and, where appropriate,under worst case situations

    include description of preliminary procedures required, detailedperformance tests to be done, acceptance criteria

    other supporting EQ used during qualification have been

    validated.

    38

  • 8/3/2019 GMP & Process Validation

    39/60

    Facility systems and equipment

    pH meter, incubator, centrifuge, freezer; IQ,OQ

    39

    system: air (HVAC), compressed air, pure steam,

    raw steam, purified water, WFI, central vacuum; IQ,OQ, PQ

    EQ: autoclave, oven, lyophilizer,continuous flowcentrifuge; IQ, OQ, PQ

  • 8/3/2019 GMP & Process Validation

    40/60

    40

    Process validation

    A process is a series of interrelated functions and

    activities using a variety of specified actions andEQ which is designed to produce a defined result.

  • 8/3/2019 GMP & Process Validation

    41/60

    41

    Process validationstudies examine a process under normal operating

    conditions to prove that the process is in control

    re-validation

    modification to the process

    problems occur

    EQ or systems are changed

  • 8/3/2019 GMP & Process Validation

    42/60

    42

    Process validation

    To validate the reproducibility and consistency of aprocess

    full defined process is carried out using validated EQ

    at least 3 times, under established procedure

    process must successfully and consistently meet all acceptance

    criteria at all steps throughout the procedure at least 3 timesconsecutively

    Validated process

    Worst case: to ensure that process isacceptable in the extreme case

  • 8/3/2019 GMP & Process Validation

    43/60

    43

    Process validation

    Example

    cleaning

    sanitization

    fumigation

    depyrogenation sterilization

    sterile filling

    fermentation

    bulk production

    purification

    inactivation

    filling, capping, sealing

    lyophilization

  • 8/3/2019 GMP & Process Validation

    44/60

    44

    Process validation

    specific process clearly described in Master

    formula or in SOP

    all EQ; identity, code number, construction, operation

    capacity, actual operating range

    processing parameter; sufficiently detailed to permit

    complete reproducibility (time period, pH, volume,

    temp.etc.)

    specification at each step

  • 8/3/2019 GMP & Process Validation

    45/60

    45

    Process validation

    Very important

    specifications for a process undergoing validation be

    pre-determined

    all critical processing parameters for which

    specifications have been set, there must be equipment

    to measure all of those parameters during thevalidation study

  • 8/3/2019 GMP & Process Validation

    46/60

    46

    Typical content requirements forprocess validations

    Cleaning, Fumigation,Sanitization Process collecting liquid and swab

    samples for testing of residualproduct

    residual protein

    endotoxin tests

    microbial tests (bioburden)

    chemical tests (chlorine and

    phosphoric acid) residual cleaning agents

    conductivity tests

    pH

    As relevant to thecleaning process

    All analytical tests mustbe validated before

  • 8/3/2019 GMP & Process Validation

    47/60

    47

    Typical content requirements forprocess validations

    Sterilization

    sterilization filtration of solutions

    microbial challenge

    filter integrity tests

    performance tests

  • 8/3/2019 GMP & Process Validation

    48/60

    48

    Typical content requirements forprocess validations

    Depyrogenation process (dry heat, column

    chromatography, other)

    endotoxin content reduction of 3 logs

  • 8/3/2019 GMP & Process Validation

    49/60

    49

    Typical content requirements forprocess validations

    Sterile filling test filling process

    perform filling process with nutrient media

    run at full scale for at least one fill size worst case; large volume and number of vials

    filled vials incubated, observed and test for contamination byvalidated sterility test

    must be sterile for 3 consecutive runs

    media fill performed twice a year

    size of run must be large enough to detect low levels ofcontamination e.g. contamination rate of 1/1000, 3000 units areneeded to provide 95% confidence

  • 8/3/2019 GMP & Process Validation

    50/60

    50

    Typical content requirements forprocess validations

    Mock fermentation

    full scale fermentation of a representative fermentation

    process

    to validate the parts of process involving connections,

    sampling, and additions of nutrients etc.

    fermentor prepared and operated in simulated process with

    uninoculated nutrient media

    process follow the full fermentation process 3 consecutive runs at each stage

  • 8/3/2019 GMP & Process Validation

    51/60

    51

    Typical content requirements forprocess validations

    Production processes(fermentation, bulkproduction, purification, filling, lyophilization)

    run according to approved Master formula including all

    raw material, personnel, equipment, and facilitypreparations, in-process tests, processing, through tofinal testing of the batch lot.

    all facility systems must be monitored

    3 consecutive lots must be produced and all facility,EQ, support systems, product spec, and process beingvalidated must pass at all steps

  • 8/3/2019 GMP & Process Validation

    52/60

    Validation: Type ofDocumentation

    Validation master plan (VMP)

    Validation protocol (VP)

    Validation reports (VR) Standard operating procedures(SOPs)

    52

  • 8/3/2019 GMP & Process Validation

    53/60

    Master validation plan (MVP)

    is a document pertaining to the whole facility thatdescribes which EQ, systems, methods andprocesses will be validated and when they will be

    validated. provide the format required for each particular

    validation document (IQ, OQ, PQ for EQ andsystems; process validation, analytical assay

    validation)

    53

  • 8/3/2019 GMP & Process Validation

    54/60

    Master validation plan (MVP)

    indicate what information is to be contained withineach document

    indicate why and when revalidations will be

    performed

    who will decide what validations will be performed

    order in which each part of the facility is validated

    54

  • 8/3/2019 GMP & Process Validation

    55/60

    Master validation plan (MVP)

    indicate how to deal with any deviations

    state the time interval permitted between eachvalidation

    55

  • 8/3/2019 GMP & Process Validation

    56/60

  • 8/3/2019 GMP & Process Validation

    57/60

    Validation: In summary, VMPshould containat least Validation policy

    Organizational structure

    Summary of facilities, systems, equipment, processes

    to be validated Documentation format for protocols and reports

    Planning and scheduling

    Change control

    Training requirements

    57

  • 8/3/2019 GMP & Process Validation

    58/60

    Validation: Protocol

    Objectives of the validation and qualification study

    Site of the study

    Responsible personnel Description of the equipment

    SOPs

    Standards

    Criteria for the relevant products and processes

    58

  • 8/3/2019 GMP & Process Validation

    59/60

    Validation: Report

    Title

    objective of the study

    Refer to the protocol Details of material

    Equipment

    Programmes and cycles use

    Details of procedures and test methods

    59

  • 8/3/2019 GMP & Process Validation

    60/60

    Validation: changes that requirerevalidation

    Software changes; controllers

    Site changes; operational changes

    Change of source of material Change in the process

    Significant equipment changes

    Production area changes

    Support system changes

    60