gnssn.iaea.org document… · web viewone can see that levels of exposure rates (or air kerma...
TRANSCRIPT
DRAFT 1.0
2.1.1. Chernobyl accident
2.1.1.1. General informationOrigin of the accidentThe Chernobyl NPP consisted of four power blocks. Commissioning of the first power
unit of the Chernobyl NPP took place in 1977 and of the fourth one in March 1984. Units V and VI were under construction at the time of the accident. (See Figure 5.1 -Map of the industrial site)
Figure 5.1. Map of the industrial site
Anthropogenic accident occurred on 26 April 1986 in the night from Friday to Saturday at 1 hr 23 min 40 sec during a low-power engineering test of the Unit IV. Improper, unstable operation of the reactor, which had design flaws, allowed an uncontrollable power surge to occur, resulting in successive steam explosions, which severely damaged the reactor building and completely destroyed the reactor (Figure5.2- Destroyed Unit IV)
Figure 5.2. Destroyed Unit IV
SourceUncontrollable radioactive releaseThe accident released a mixture of radionuclides into the air over a period of about 10
daysThe following stages of release may be identified I – 26 April. Release due to explosions both as fine-dispersed fuel and violent
radionuclides released from fuel at Tfuel = 1600-1800 K II – 26 April - 2 May. Release due to graphite burning at Tfuel < 1600 K III – 2 -5 May. Release due to fuel overheating up to 2500-2800 K as a result of
radioactive decay IV – Later 5 May. Release reduction and sporadic volley emissions of
radioactivity Dynamics of radioactive release is shown in Figure 5.3
Figure 5.3. Dynamics of radioactive release
Spatial balance of nuclear fuelTotal spatial distribution of nuclear fuel was as follows: >96% - inside Unit IV, <0.3%, - industrial site<1.5% - 80-km zone (excluding industrial
site), < 1.5% - rest of the USSR, <0.1% - outside of the USSR Another words, spatial balance of released nuclear fuel was follows: 9% - NPP site, 44%
- 80-km zone, 44% - rest of the USSR, 3% - outside of the USSRTotal radioactive release was amounted more than 12,000 PBq, including 6,500 PBq – inert gases, 1,800 PBq – 131I, 85 PBq – 137Cs.
NPP site area (around 1 km2) mainly was contaminated by dispersed nuclear fuel following explosions on the night of accident. So contamination of industrial area occurred immediately following explosions on the night of accident. This is the first discrepancy compared Fukushima - 1. Just that area is very interesting from point of view on radiation protection of emergency workers.
General questions of emergency response What and how should be immediately done to take emergency process under
control? What and how should be done to mitigate consequences of the accident? What is crucial issues of radiological protection of emergency workers at the early
stages following an accident?
2.1.1.2. Emergency and preparedness regulation in the USSR to the Chernobyl accident
It was held 10 thousand days in September 11, 2013 from the day (more exactly, the night) of the Chernobyl accident. Past system of occupational radiological protection in the USSR should be considered and compared with the present system of EPR
Evolution of dose limitation for planned exposure situations before Chernobyl accident is given in Table 5.1
0
5
1015
20
25
30
35
40
45
50
1 2 3 4 5 6 7 8 9 10 11
Ряд1
Table 5.1. The USSR dose limits for occupational exposure
Year No Standard Annual dose limit, mSv Permissible daily dose, mSv
1948 Т- 1031 300 11950 2413 300 11953 129-53 150 0.51957 233-57 150 0.51960 333-60 50 -1969 BSS-69 50 -1976 BSS-76 50 -
This table demonstrates that for planned exposure situation (according to the current IAEA terminology) old-timer workers remembered their routine experience to operate in a heavy radiation conditions with annual and dose limitation. However, the main part of personnel had no such experience and proper trainning in time of the Chernobyl accident.
Basic regulation requirements of the USSR Radiation Safety Standards NRB-76 for emergency situation were as follows:
Emergency plan shall be prepared in any legal person All practicable measures shall be intended for minimize external exposure and
radionuclide intake for emergency workers (EWs) Overexposure of EWs above dose limits may be justified:- for the purpose of saving life, - averting a large-scale public overexposure, and - preventing the development of catastrophic conditions Elevated planned exposure (EPE) shall be below twice dose limit for single
undertaken action and five times over dose limit for all emergency period of time (i.e. 100 and 250 mSv)
Written permission of administration and personal consent of EW to EPE is required
Work Order shall include detailed list of actions, their time limitation and safety tips
EPE not be allowed if: - EPE+E(received before accident)>Dose Limit x T(radiation experience),- worker already received elevated exposure over 250 mSv,- worker is woman younger 40These national requirements were in accordance with IAEA documents, for instance, No
50-SG-D9, IAEA, Vienna, 1985Management system of EPR to 1986 at the Chernobyl NPP includes: Plan of emergency management at the Chernobyl NPP Plans of radiation protection of the NPP personnel and public Procedure of emergency notification Emergency system of the national operator “Souzatomenergy” Special medical provision General procedure for official inquiry and liquidation of major accidents in
industryFor clear understanding actual emergency response after the accident it is necessary to remind features of state power. The USSR was a totalitarian state. So existed national EPR system had a command-and-control management style:
Strict vertical of power Secrecy order in nuclear energy and atomic industry
As a consequence:
Guaranteed financial and resource provisions of any countermeasures Inability of serious decision making at a local level Restriction on exchange emergency experience between NPPs and informing of nuclear
workers
Special judgment No 1Formally, general approach to a problem of radiation protection regulation for rescuers and emergency workers by the time of the Chernobyl accident and currently not undergoes a change.From practical application point of view, existed national EPR system had a features agreeable to that command-and-control management style and national mentality
2.1.1.3. Categories of emergency workersAccording to the USSR, Belarus, Russia, Ukraine Laws specific cohort of emergency
workers and recovery workers are defined as participants of emergency response (so called “liquidators”):
“Citizens taken part in termination of the accident and in mitigation of its consequences on the affected areas in 1986-1990”
The total number of emergency and recovery operation workers (from 1986 to 1990) was 530,000 including 150,000 liquidators worked at the NPP site area
Within this period of time the duration of emergency exposure situation assumed to be 7 months (26 April - 30 November 1986 - completion of the SHELTER construction around Unit IV).
Attributes for categorization of emergency workers Management of emergency works, including radiation protection (national
governmental and functional EPR system) - Figure 5.4 Time after accident (first responders on scene, attracted units for urgent response,
emergency workers for restoration) - Table 5.2. Type of emergency work (saving life, preventing of catastrophic conditions,
source localization, evacuation, decontamination etc) Tables 5.3, 5.4.
FRO
NT
IER
GU
AR
DS
L I Q U I D A T O R S
CIVIL MILITARY
PERSONNEL VOLUNTEER REGULAR RESERVE
MINISTRY
ENERGYOF
MINISTRYOF ATOMICINDUSTRY
MINISTRIESOTHER MINISTRY
OF DEFENCEMINISTRY OF
INTERNALAFFAIRS
CGB
ChN
PP
CO
MB
INA
T
CO
MP
EX
DIS
PA
TH
OF
KI
US-
605
CIV
IL D
EFE
NC
E
CH
EM
ICA
L T
RO
OP
S
AIR
FO
RC
E
ING
EN
EE
RIN
G T
RO
OP
S
FIR
E-B
RIG
AD
ES
PO
LIC
E
SEC
UR
ITY
INST
ITU
TE
S
EN
TE
RP
RIS
ES
SER
VIC
E
GU
AR
D
5
Figure 5.4. Governmental categories of liquidators
Table 5.2.Cohorts of liquidators (EWs) in 1986
No Cohort Number Dates1 Witnesses and first responders 1,000 April, 262 Urgent response teams 35,000 27.04 –20.052.1 Military 13,0002.2 Civil 22,0003 Emergency & Recovery workers 89,000 21.05 – 30.113.1 Military 49,0003.2 Civil 40,000Total 125,000 26.04 – 30.11
Table 5.3. Operating schedule in 1986
Category Type DurationChNPP personnel Shift work 15working days + 15days of
restEarly liquidators Single mission Till 15 daysAttached to ChNPP Shift work or single/repeated
missionsTill 30 days
US-605 personnel Single shift work 2 monthsMilitary liquidators Single frame
Single/repeated missionsShift work
3 min or E < 200mSvE < 250 mSv3/6 months
Attached into 30-km zone Shift work or single/repeated missions
3 months orE < 250 mSv
Table 5.4General activities
Measure Object DatesPreventing of release Ruined Unit IV 26.04 -10.05.1986Evacuation Pripyat town
Chernobyl town, rural settlements27.04.19863.05-7.05.1986
Decontamination Units I-III, industrial area, settlements, roads“Red” forest
1986-19901987
Construction “Shelter”Waste depositoryDampsFilter screen
21.05-30.11.19861986-198811.07-25.09.19861987
Building Shift industrial communitySlavutich town
15.05-31.10.198625.05.1986-1988
Guarding Scala-1M (10-km), 30-km zone PermanentlyRadiation monitoring Contaminated territories Permanently
Dose restrictions after the accident Evolution of occupational dose limitation was as follows:- 26 April 1986: without emergency dose constraints for personnel of the Chernobyl NPP;- 27 April: 20 May 1986 – 500 mSv for military liquidators and 250 mSv for civil
liquidators;- 21 May – 31 December 1986: 250 mSv for all categories of liquidators;- 1 January – 31 December 1987: 250 mSv the permission of the USSR Ministry of
Public Health for special works, 100 mSv – works at the Unit III and the NPP site, 50 mSv – everywhere except for the above-mentioned places.
Special judgment No 2
Liquidators were not homogeneous cohorts of professional rescuers and nuclear workers
Cohort of liquidators were composed of independent groups met certain tasks within own management and dose control
Activities of liquidators took place in emergency exposure situation, existing exposure situation and planned exposure situation
Air Air kermakerma rate, rate, mGy/ hmGy/ h. 26 April 1986. 26 April 1986
100
10
1
10001000
Pripyattown
Cooling pond3000
Chernobyl NPP area
Pripyatriver
Figure 5.6A. Air kerma rate, mGy/h. 26 April 1986One can see that levels of exposure rates (or air kerma rates) were very high in the NPP
site Gy –tens Gy/h, i.e. typical levels of exposure rate exceeded the natural background in 106 - 108 times (Fig. 5.6A). Unfortunately this fact timely has not been confirmed by measurements. Dangerous situation was outside NPP. Dose of 1 Gy which corresponded to threshold of deterministic effects was formed in the 4-km locality during 2 days (Fig. 5.6B). Annual doses of 100 and 30 mSv which required intervention for public were predicted for settlements in the 30 km territory and far from here (Fig 5.6C). Refractory radionuclides gave the big contribution to total activity in the first year after the accident (Fig 5.6D). This is the second discrepancy compared Fukushima-1.
Special judgment No 3Unfortunately emergency dose monitoring was absent during
reflex phase: The first radiation data were reported after 1 -3.5 hours later explosion Individual dose monitoring has not been carried out on April, 26. Only film
badges (the upper level of registration of 20 mGy) were present. Routine individual dose monitoring has been carried out for 4,750 ChNPP workers and attracted personnel before the accident (data on 1 January 1986)
Actual doses for witnesses were in the range of 40- 15,000 mGy Dose of 40 mGy was received only during one trip from Pripyat town to the NPP
Number of emergency workers and witnesses is given in Table 5.7 and urgent actions - in Table 5.8.
As a result of a heavy radiation conditions, lack of occupational exposure monitoring from one hand, and professional courage of workers and firemen, from other hand, overexposures were occurred (Table 5.9)Table 5.7.First responders & witnesses of accident
Contingent Number of witnessesAt the accident moment 8 hours later
Personnel of Units I-IV 176 374Builders of Units V, VI 268 -Firemen 24 69Guards 23 113Medical staff - 10Subtotal 491 566
Table 5.8.Actions of the first respondersNo Action1 Fire control2 Saving life3 Cut-off ventilation/ electricity, switching of cooling system , lube swap4 Examination of equipment5 Radiation reconnaissance#6 Water supply
# Radiation data were reported after 1 -3.5 – 8.5 -17.5 hours later explosion
Table 5.9Individual and collective doses of the first responders
Category Number Dose, mGy Collective dose, person GyMean Median
Witnesses 1,057 550 450 581Clinics patients 134 3400 2400 455
Internal exposures took a lower values compared with external doses .Average committed equivalent dose (lung) for alive 125 witnesses of accident, treated in clinics was about 400 mSv. Distribution of thyroid doses is shown in Figure 5.7
Internal thyroid doses: first respondersInternal thyroid doses: first responders
1
10
100
1000
75%
25%
min
max
Industrial area Inside Unit IV Inside Unit IVfew hrs later
Outside industrial area
HT mSv
Group of Chernobyl workers, 26 April 1986
A B C D
Figure 5.7. Internal thyroid doses: first responders
Management at the reflex phaseIn general, chaos and uncertainty are essential feature a of major nuclear accident which
characterized the following attributes:- prevalence chance over the order; - violation of information channels;- total uncertainty concerning radiation situation, exact personnel location and severity of
technology violations.These uncertainties create risks of decision making1. Decision maker under a great stress2. The more uncertainty the greater risk of decision 3. Range of alternative decision options: to do any available actions or to do nothing
excepting actions directed on reducing uncertainties 4. Breach of management hierarchy: informal leaders with a great professional
experience come to the first plan5. Simple and robust decisions are optimal in a case of great total uncertainty Management structure at the Chernobyl NPP is demonstrates in the table 5.10.
Table 5.10. Management during the first 18 hours
No Manager Arrival Operator guide1 Director NPP +45 min Emergency headquarters actions2 Main engineer NPP +3 hr Water supply, s/m measurements3 Shift man NPP: Formal
head of reflex response0 Collect witnesses, notification. Actually
transmit his duty to No 4, 74 Deputy Main engineer on
operation Unit III+Unit IV0 Actual head: call the fire, switch on
diesel generator, ventilation, switch off power supply cables, saving life, stop Unit III
5 Shift man Unit III 0 Complete and strict compliance with emergency plan & instructions
6 Shift man Unit IV 0 Translation of No 4 guides7 Deputy head of safety
department+1 hr Radiation monitoring, zoning 30
mGy/h#, switch off ventilation# Radiation zoning has not be applied on April, 26There are two alternative retrospective estimates of reflex management View I– Decision making was chain of mistakes orView II – Decision making would have been logical timely resolute actions (water supply, preventing panics, challenging data of radiation reconnaissance, switch off long-distance telephony etc) if reactor of Unit IV had not been destroyed.
Special judgment No 4Along with positive action and results, delay of reflex administrative response concerning occupational radiation protection is obvious:
“Dose Order form” did not apply during the first day for organization of any work
Forbidden and restricted working radiation zones have not be applied
Procedure of “Elevated Planned Dose Permission” did not apply during the first day
Ignoring danger of overexposure by administration and personnel excepting dosimetrists and the turbine shop workers
Urgent evacuation of unnecessary personnel
Lessons learnt from the reflex response are as follows: Transition from routine planned exposure situation to emergency
management is a crucial point of reflex response Urgent actions of the first responders corresponded with
emergency situation, purposes, plan and instructions However delay of adequate decisions was 11 -15 hours due to
great uncertainties Absence of appropriate radiometric and dose monitoring led to
serious radiological consequences among emergency workers and witnesses
Under a great stress dominant behaviour of nuclear workers to carry out their duties prevailed over personal safety, including radiation safety
2.1.1.4. Reflex Phase – 26 April 1986 Key issues in reflex phase were as follows:(1) To clarify situation and arising threats → Collection and comprehensive analysis of
witness evidence (2) To introduce emergency plan into action → Emergency management and urgent
actions directed on maintenance of the viability of the object (3) To limit the number of involved EWs → Evacuation of unnecessary witnesses,
functionality of security check-points(4) To measure exposure rate and surface radioactivity contamination → Emergency
zoning(5) To prevent radionuclide carrying over → Functionality of sanitary check-points
All of above-mentioned actions carried out in extremely heavy radiation conditions (figures 5.5, 5.6, 5.6A and table 5.5). It is nesessary to note that mostly retrospective estimation of radiological situation are presented below.
48A
83A
93A
21A2A
57A30A
7A 7A
6A 5A
7 7
6 517
1634
23A 9A
15A
42A
4 82
89A
50
42A24A
83
87
80 85
42A
27A
28A
24
19
91 3835
40
12
1315
56
10
95
2389
42 30
Coordinates in meters
Spatial distribution of exposure rate, Spatial distribution of exposure rate, mGymGy/ hr/ hr
1000
1000
300
20003000
3000
300100
30 10
1000
4000
Figure 5.5. Spatial distribution of exposure rate, mGy/hr at the NPP site
Table 5.5. Total beta-activity. 26 April 1986Sample Place of sampling Concentration, Bq m-3
Air Premises of Unit III 109 – 10 10
Pumped water# Flooded basement Up to 10 13
# 57, 700 m3 of water was pumped out of the basement to cooling pond
30 mGy
100mGy
A C
B D
1Gy
A - Kerma rate, mGy/h on April, 26 – 4 km zone C – Annual kerma – 30 km zone
B – Kerma within first 2 days – 4 km zone D – Fuel radionuclide composition with time
Relative content,%R
1000
100
10
1 1mGy/h
Fig 5.6. Gamma radiation near the Chernobyl NPP and radionuclide composition of fuel and fallout
2.1.1.5 Early Phase: 27 April -20 May 1986
Harmful working conditions at the early phase included chemical, physical, radiological and psychological factors.
Table 5.11.Chemical factor at working places
Origin Initial materials PollutantsFire at the Unit IV Graphite, building & organic
containing materials, bitumenCO, NO2, hydrocianide, phosgene, smoke, superfine aerosols
Sublimation of materials dumped on the reactor
Sand, clay, lead, dolomite, boron compounds
Depositions of lead
Dust catching for building, roof, industrial site and roads of 30-km zone
Sulphite-alcohol barda, oxalic & hydrochloric acids, formalin; resinas, oil-slime
Superfine acid aerosols, sulfer/organic–containing vapour
Physical factor was ionizing of air. Ionization levels exceeded permissible level many times (103- 105 greater near Unit IV). This factor led to oropharyngeal syndrome estimated to be 58% among liquidators in 1986 (3000 questionnaires)
Structure of radiological factor is shown in Figure 5.8.
Total exposure
External photons
External neutrons
Externalbeta-particles
-
Internal Alpha-
beta-rays
Directed to“forward-back”,
Isotropic,Rotary
Directed to“forward-back” Distant &
contactInhalated
radionuclides
Radiological factorRadiological factor
Figure 5.8. Structure of radiological factor
Neutron exposure The first wrong measurements of neutron flux were evidence of nuclear chain
reaction. This suggestion became start point in the set of early countermeasures directed to nuclear safety
Neutron exposure gave minor impact to the total dose (up to 1-2% of gamma exposure nearby Unit IV, June-July 1986)
Distant beta exposure Ratio of beta to gamma-exposure for different types of work is given in the Figure 5.8.
Distant beta exposureDistant beta exposure
Ratio
of b
eta-
to g
amm
a-ex
posu
re ra
te
Types of work
Gamma exposure, mGy
Figure 5.8. Ratio of beta to gamma-exposure
Gamma exposureEnergy dependence of different dosimeters was in a range of 0.8 – 1.7 compared with the
known good device. This uncertainty should be taken into account when analyzing dosimetric data (Table 5.12)
Table 5.12.Sources and average energy of photons at the typical working places
Eγ, MeV Source distribution/working place
~ 0.5 Local sources, surface contamination/Roof, contaminated premises
~ 0.2 Volumetric distribution activity in soil/Contaminated territory
~ 0.1 Behind light shield materials (concrete, crushed stone)
Comparison of measured external and internal exposures show that external exposure was dominant component of total dose (Figure 5.9)
Comparison of measured Comparison of measured external and internal exposuresexternal and internal exposures
External dose/ Dose limit
Inte
rnal
dose
/ALI 111
1 1000.01
1
0.01
0.0001
0.0001
1
1
Figure 5.9. Ratios of measured external and internal exposures for early liquidators
Key issues in early phase 1. To identify list of urgent actions, available means and man power according to
radiation situation and predictable threats2. To use graded approach for operational planning 3. To estimate resources for urgent measures4. To apply system of emergency management in proper manner
Management system change at that time. Governmental Commission began to manage emergency response instead of internal facility administration. Probably, excessive activity of governmental body is inevitable attribute of early response on a major accident. Twenty five years later similar process of excessive management activity was repeated in Fukushima-1
Actions of early liquidators are presented in the Table 5.13.Table 5.13Actions of early civil and military liquidators
Industrial site 4-km zone 30-km, 70-km zonesCivil liquidatorsDecontamination Construction “wall in ground” Public evacuationDrilling of wells Works in river port “Pripyat
town”Evacuation of cattle
Digging of foundation pit near Unit III
Dyking of riverside Sanitary measures
Building of tunnel under Units III, IV
Evacuation of equipment from “Jupiter” factory
Art concert activity
Freezing of soil under Unit IV
Loading sand and lead to helicopters
Domestic service
Transportation Transportation TransportationMilitary liquidatorsFire control near reactor coolant pump on 23 May
Decontamination of vehicles Public evacuation
Laying in reactor with the help of helicopters
Decontamination of Pripyat town
Evacuation of cattle
Air reconnaissance Transport examination Radiological surveyDecontamination of site, machinery hall, roof
Fire control around Pripyat town
Fire control
Building of concrete wall between Unit IV and depository of SNF
Guarding of Pripyat town, 10-km, 30-km zones
Decontamination shower facilities
Transportation Adjustment of road traffic Decontamination of settlements
Reasonability of complete urgent actions Useful actions
Maintenance of operated ChNPP technologies Evacuation of public Water pumping out bubbler-basin Removal of valuable imported equipment from the building base Investigation of the accident reasons Fire control on May, 23
Useless actions Covering the reactor with materials by helicopters Dust catching and decontamination on the industrial area and settlements Building of concrete slab (30mx30mx2.5m) with cooling system under reactor Liquid nitrogen supply into under-reactor premises
Reasonability of incomplete urgent actions Useful actions
Nuclear fuel diagnostics of under-reactor premises Radiation, fire, thermal reconnaissance Personal dose monitoring Optimized emergency management Sanitary and hygienic measures
Useless actions Construction of horizontal holes for soil freezing under reactor IV Building of underground wall around NPP
Doses and dose distribution for early civil liquidators are presented in Table 5.14..
Table 5.14. Individual and collective doses
Individual dose distribution for early civil liquidators Dose range, mSv <10 10-30 30-100 100-300 300-1000 >1000Percent 21.5 13.2 27.7 30.8 6.2 0.6
It is important to estimate part of collective dose related to useful actions. Figure 5.10 demonstrates distributions of man-power and collective dose among general actions had been carried out within first days following the accident.
Fig.5.10. Distributions of man-hours and collective doses during first 5 days after vthe accident
One can see that movement and loss of time account for ¾ of total collective dose.
Category Number Dose, mGy Collective dose, person GyMean Median
Civil liquidators 21,600 115 56 2,487
Special judgment No 4Optimization of traffic on contaminated area is important issue from occupational radiological protection point of view.
Evolution of dose monitoringDose monitoring of Chernobyl NPP workers 27 April - Regional Civil Defense unit handed condenser dosimeters DKP-50 to
the ChNPP safety engineering department 28April – Two TLD devices were deployed at the dosimeter point of industrial
camp “Skazochniy” 28April – WBC was deployed at the dosimetry point. Then WBCs were placed in
the after-work sanatorium Occupational dose monitoring of the Chernobyl personnel was satisfactory
established by 10 May 1986 Results of dose monitoring were daily reported to Governmental commission in
May-June 1986Dose monitoring of military liquidators Both instrumental and calculated techniques Application of different types of dosimeters Fabricated dose records Value of elevated planned exposure was considered 500 mSv till 20 May
Negative lessons: early phase1. Absence of adequate personal dose monitoring means and dosimeters for measurements
of high levels of air kerma rate2. Working assumption that reactor was not destroyed for water supply operation3. Working assumption that active core was placed inside reactor4. Political decision on Unit III restoration without economic justification
Link between gaps or wrong assumptions or unfounded decisions and non-justified exposure is given in Figure 5.11.
Figure 5.11. Negative lessons 1 - 4: Logical chain
Positive lessons: early phase1. Reliable system of security check-points and sanitary check points2. The ranking of the harmful factors: external gamma → external beta→ internal
exposure3. Development of retrospective dosimetry techniques4. Timely triage of victims and system of three-stage medical treatment5. Stable iodine prophylaxis
Special judgment No 5Involvement a great number of people in emergency response and
recovery operations without proper selection and training is professional and social phenomenon of the Chernobyl event
2.1.1.6. Intermediate phase: 21 May – 30 November
Strategy of emergency and recovery works has been elaborated on May 1986, less than one month after the accident. This strategy was adopted on the highest state level by Decree of Central Committee of CPSU and the USSR Council of Ministers (29 May 1986, No 634-188). Planned vs actual dates and results of works is shown in Table 5.12 Table 5.12 Strategy of works: goals and schedule Work Completion date
Planned Actual Public returning into 30-km zone
Sept -Dec 1986 Not reevaluated
Construction of the Shelter September 1986 November 1986Decontamination on-site NPP September 1986 December 1987Unit I startup July 1986 October 1986Unit II startup July 1986 October 1986Unit III startup August 1986 December 1986Recovery of Units V and VI projects
October 1986 Never
Involvement of large number of common people was needed to fulfill this strategy. Above-mentioned Decree resolved:
“To accelerate decontamination operations in the Chernobyl NPP zone, which operations are of social and political importance and the first priority
to call up reservists for 6 month-term above limits provided to Ministry of Defense by the USSR Council Ministers of 20 August 1985”.
However, targets has have been achieved with delay or other results have not been achieved at all.
Special sanitary regulation Special sanitary regulation covered all objects and aspects of emergency works. Firstly, radiation zones has been established as follows;Zone I – (so called, zone of strict control) – area between isolines 3.0 -5.0 mR/hr (30-50
µGy/h) decay-corrected on May, 10. Projected annual external dose below 50 mSv;Zone II – (including 30-km zone and excluding or prohibited 10-km zone) - area
between isolines 5.0 -20 mR/hr (50-200 µGy/h) decay-corrected on May, 10Zone III – area of prohibited 10-km zone above isoline 20 mR/hr (>200µGy/h), excluding
industrial site of NPP, Pripyat town Zone IIIA – industrial site of NPP, Pripyat town
Secondly, different regulatory and administrative documents were adopted, applied and renewed. Types of adopted documents in May and June 1986 are given in Tables 5.13, 5.14Temporal permissible levels for surfaces were used at the sanitary check-points and applied as criteria of decontamination. Primarily, values of flux density of beta-particles were identified. However gamma-exposure rate was more convenient value for large scale radiometric examination of surface contamination: 10,000 β/(cm2 min) →1 mR/hr or 1,000 β/(cm2 min) → 1 µGy/h (Table 5.15) . Change of temporal permissible levels is illustrated in Table 5.16.
Table 5.13 Sanitary regulation: May 1986
Document type Brief title Approved by IssuedTemporary permissible levels
Surface radioactive contamination
Regulatory body 7 May
Interim methodic recommendation
Management of occupational protection
Regulatory & Government bodies
27 May
Recommendation Using of cleaning agent “Z” for skin decontamination
Regulatory body 29 May
Recommendation Using of pharmaceutics for nuclides washout
Regulatory body 29 May
Statement Monitoring and records of individual doses in 30-km zone
Chair of Governmental Commission
30 May
Interim guidance Sanitary supervision of dose monitoring
Regulatory body 31 May
Table 5.14 Sanitary regulation: June 1986
Document type Brief title Approved by IssuedInstruction Decontamination of
protective clothes etc in laundries of other NPPs
Regulatory body 11 June
Temporary permissible levels
Contamination of skin, linen, clothes, protective means, vehicles
Regulatory body 12 June
Temporary Residual exposure Regulatory body 12 June
permissible levels rates after decontamination
General requirements Recommendation
Interaction between the USSR State Sanitary Inspectors and radiation safety services: dose monitoring
Regulatory & Government bodies
22 June
Table 5.15Temporary permissible levels (TPLs) of surface radioactive contamination. Adopted on May, 7, 1986
Surface Flux density, β/(cm2 min) Exposure rate, µGy/hSkin, underwear, towel, bed linen, footwear, protective device & clothes
1000 1
Dwelling, internal surface of transport facility
2000 2
External surface of transport facility
3000 3
Table 5.16Temporary permissible levels (TPLs) for surface contamination (mR/hr) Adopted on 02.06.1986 /on 14.10.1986
Contaminated objectZone I II III III-A Outside
Skin, underwear 5/ 3 10/ 7 20/ 15 20/ 15 0,1/-Bed linen, outerwear 5/ 3 10/ 7 - - 0,1/-Personal footwear 10/ 7 - - - 0,1/-Protective device & working clothes -/ 10 30/ 20 50/ 40 100/ 70 -Internal face of transport facility 10/ 10 30/ 30 50/ 50 100/
1000,2/-
External face of transport facility 15/ 10 50/ 40 200/ 150 400/ 300
0,3/-
Individual dose monitoringFormally, Chernobyl NPP administration had to provide appropriate dose monitoring of
attached liquidators both civil staff and military reservists. However it was not able because of lack of resources, equipment and operators. Management of dose monitoring of civil and military staff was carried out independently.
Quality of dose monitoring during the first year after the accident is estimated in Table 5.17.Table 5.17Quality levels of dose monitoring during the first year after the accident
Level Description Percent StaffHigh Only instrumental data.
Less than 10% of gaps and mistaken records
13 ChNPPUS-605
Satisfied Mixture of high and low quality levels
4 Attached to NPP
Low Both instrumental and calculated techniques. Incomplete or/and doubtful records
58 Attached to 30-km zone,Military men
Zero Absence of personal dose monitoring procedure and data
25 Victims &WitnessesEarly liquidators &Belarus liquidators
Positive experience of dose monitoring management connected with construction of
“Shelter” around Unit 4 from June to November 1986 (special enterprises of US-605). Heavy radiation conditions at working places were existed in that time (maximum values
are given in Table 5.18).Table 5.18.Source parameters during construction of “Shelter” around Unit IVInfluencing factors Maximum levelsGamma-radiation of fuel fragments, surfaces, soil
100Gy/h – reactor4 Gy/h –working places
Alpha-, beta-aerosols 300 permissible concentration – dusty workAlpha-, beta-contamination of surfaces 102-105 α/(cm2 min)
104-108 β/(cm2 min)Neutron radiation 4-400 µSv/h – machinery hall
Total number of involved workers was 21,500. Maximal shift of workers was 11,000, including 6,000 of military staff and 5,000 of civil workers. Monitoring procedure was the same both civil and military staff. Numerical structure of dose monitoring department was 150 - 270. System of dose monitoring management included radiation technical survey, dose monitoring, radiation protection and research function. It was delineated 12 working zones of industrial area during the US-605 activity according to radiation situation and operation technologies. Administrative daily dose of 10 mSv was established for permanent control of received dose. Also set temporary permissible levels of surface radioactive contamination were adopted and timely revised by both regulatory body and emergency operator. A noticeable dose decreasing gave using separate shuttle mobile means in different zone.
Figure 5.12. Dose distributions for civil and military liquidators of US-605 enterprises
Special study shown influence of behavior factor (both professional and psychological origins) on individual dose value. Dose distribution for group of liquidators carried out a certain operation at the same working place may be approximated by lognormal dependence with GSD = 1.75±0.20 (see Figure 5.13)
Figure 5.13. Individual doses for the same working places
In general, results of individual dose monitoring are presented in Table 5.19
Table 5.19. \Individual and collective doses: 26 April – 31 December 1986): official data
Category Number Dose, mGy Collective dose, person GyMean Median
Clinics patients 134 3400 2400 455Witnesses 1,057 550 450 581Early civil liquidators 21,600 115 56 2,484ChNPP personnel 2,358 87 48 205US-605 personnel 21,500 82 50 1,763Military liquidators 61,762 204 220 12,600Attached into 30-km zone 31,021 20 6.3 620Total 139,432 134 18,708
Efficiency of protective equipment, radiation protected mechanisms and managing
Large scale application of protective means is one of important lesson of Chernobyl, Briefly,results of this experience in heavy radiation conditions are illustrated in Tables 5.20-5.22
Table 5.20 Personal protective equipment PPE Organ /tissue Reduction factorFilter mask & respirator Lung 40 – 200 (without violation of
obturation)Lead screen 3mm Red bone marrow 1.9Lead band 3mm Gonads 1.83 ± 0.15Dust proof spectacles 2mm Eyes 36 - 200Plexiglass helmet visor 2-5mm Skin, lens of the eyeLead inner soles 1.5mm Feet 1.4Lead rubber apron Body 1.6Lead rubber gloves Hands 1.4
Table 5.21. Radiation protected mechanisms
Class Reducing factor Exposurerate, mGy/h
Mechanisms
I >1000 >1000 Bathyscaphe, heavy craneII 100-200 n 100 Heavy bulldozer, obstacle clearing
engineering machineIII 3-20 <100 Excavator, ditcher, concrete pump, motor
transport
Table 5.22. Decontamination planning and carrying outPrinciple ProcedureChoice of main source 1. To estimate exposure rate and collective dose due to
local areas2. To select area raised maximal dose on other areas
Step-by step recapture of territory 1. To start from the most contaminated part removing
sources from a back space2. To use local shield against radiation from front space
Application of unmanned techniques 1. To use building technology, robots, remote control guidance2. To equip point of control with monitors and speakerphone
The reduction of operational duration 2. To work out operations in normal radiation condition2.To analyze detailed operational time study
Positive lessons Dose management on the base of Dose Order Form Change of routine managers to the emergency managers in the field of radiation
protection Dual personal dose monitoring of external exposure: daily and cumulative Application of “Choice of main source”, “Step-by step recapture of territory” approaches,
“Optimal impact on radiation situation” concept Application of unmanned techniques the reduction of operational duration Dose distribution analysis in ALARA procedure Lead protective equipment was not optimum in the limited time conditions for intensive
manual operations Suitable and adequate personal protective equipment (including protective clothing,
respiratory equipment, protective aprons and gloves) is required from radiation protection of EWs
Specific judgment No 6 Involvement a great number of people in emergency response and recovery operations
without proper selection and training is professional and social phenomenon of Chernobyl event
Large-scaled application of Elevated Planned Exposure in excess of 50 mSv conflicts with IBSS-2011 (4.15). However justification of such decision was outside of the SRP
Conclusions to 2.1.11. Both positive and negative lessons of the Chernobyl accident
concerning radiation protection of emergency workers are still valid for international community.
2. Two issues are considered extremely important, i.e. (1) management and dose control for the first responders and (2) involvement of a great number of common people to recovery operation.
3. Chernobyl experience has demonstrated change of priorities and key issues in different phases of mitigation consequences:
Reflex phase:- To clarify situation and arising threats by forces of collection and
comprehensive analysis of witness evidence; - To introduce emergency plan into action. Emergency management and
urgent actions should be directed on maintenance of the viability of the object; - To limit the number of involved emergency workers by means of
evacuation of unnecessary witnesses, functionality of security check-points;- To measure exposure rate and surface radioactivity contamination for
delineation of emergency zones;
- To prevent radionuclide carrying over by managing and functionality of sanitary check-points.
Early phase: - To identify list of urgent actions, available means and man power
according to radiation situation and predictable threats;- To use graded approach for operational planning; - estimate resources for urgent measures;- To apply system of emergency management in proper manner.Recovery phase:- Strategy planning based on holistic approach;- Stakeholder involvement; - Transition from emergency management to management for existing
exposure situation;- Implementation of analytic ALARA procedure;- Design and application of optimized technologies and protective means4. Brief list of negative lessons are as follows: (1) Absence of adequate personal dose monitoring means and dosimeters for
measurements of high levels of air kerma rate;(2) Working assumption that reactor was not destroyed for water supply
operation;(3) Working assumption that active core was placed inside reactor;(4) Political decision on Unit III restoration without economic justification5. Positive lessons are as follows: (1) Reliable system of security check-points and sanitary check points;(2) The ranking of the harmful factors: external gamma → external beta→
internal exposure;(3) Development of retrospective dosimetry techniques;(4) Timely triage of victims and system of three-stage medical treatment;(5) Managing stable iodine prophylaxis;(6) Dose management on the base of Dose Order Form;(7) Change of routine managers to the emergency managers in the field of
radiation protection;(8) Dual personal dose monitoring of external exposure: daily and
cumulative;(9) Application of “Choice of main source”, “Step-by step recapture of
territory” approaches, “Optimal impact on radiation situation” concept;(10) Application of unmanned techniques the reduction of operational
duration;(11) Dose distribution analysis in ALARA procedure;(12) Application of suitable and adequate personal protective equipment
(including protective clothing, respiratory equipment, protective aprons and gloves). It was proved that lead protective equipment was not optimum in the limited time conditions for intensive manual operations
References1 Chernobyl’ 88. Proceedings of the Union scientific-technical Conference. Ten volumes. Edited by Ye. I. Ignatenko. Ministry of Atomic Energy. Chernobyl, 19892. R.M. Alexakhin et al. Large Radiation Accidents: Consequences and Protective Countermeasures. Edited by L.A. Ilyin, V.A. Gubanov. Moscow, IzdAT, 2004. Book was printed in Russian - 2001, in English - 2004 and in Japanese3. V.P. Kruchkov et.al. Mitigation of accident consequences at Chernobyl NPP: Radiation and dosimetry issues. Edited by V.G. Asmolov, O.A. Kochetkov. Moscow, IzdAT, 2013 Book was printed in Russian - 2011, in English - 2013