godavarru works with ssr 2013-14 revised specification 16-12-2013
TRANSCRIPT
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
1/87
Mandal : Duggirala
Estimate Cost Rs. 77.00 Lakhs
Construction of CC Drains and CC Roads in Godavarru
village of Duggirala Mandal
Estimate
Name of the work
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
2/87
Name of the Work: Construction of Side Drains and CC Roads in Godavarru Village of Duggirala Mandal
CROSS SECTION OF DRAIN & Road
70 cm Gravel Shoulders
Concrete pavement 200 mm
Gravel Shoulders
20 cm 20 cm Granular Sub base 75 mm
Grading 2nd layer 75 mm
20 cm Grading 1st layer 75 mm
45 cm
G L 0.306.900
60 cm Length of Road 1 90Length of Road 2 90
10 cm 10 CM 10 cm Length of Road 3 90
Length of Road 4 90
Sand Filling -15 cm Length of Road 5 85
Length of Road 6 81
Length of Road 7 85
35
646
for 6.00 Mtrs WIDTH ROAD
90 cm Main Road from 6th to
V
CC1
:3:6
V
CC1
:3:6
PCC 1:5:10 - 10 cm
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
3/87
Est.Rs. 41.00 Lakhs
Assistant Engineer Deputy Executive Engineer Executive Engineer
APSHCL, Duggirala APSHCL, Mangalagiri APSHCL, Guntur
Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement concrete pavement,
thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30
(Grade) design mix, coarse and fine aggregates conforming to IS : 383, maximum in a concrete mixer of not less than
0.2 cum capacity and appropeiate weigh batcher using approved mix design, laid in approved fixed side formwork (steel
channel, laying and fixing of 125 mictron thick polythene film, wedges, steel plates including levelling the formwork as
per drawing), spreading the concrete with sholvels, rakes, compacted using needle, scareed and plate vibrators and
finished in continuous operation including provision of contraction and expansion, construction joints, applying
debonding strips, primer, sealant, dowel bars, near approaches to bridge / culvert and construction joints, admixtures as
approved, curing of concrete slabs for 14- days, curing compound (where specified) and water finishing to lines and
grade as per drawing and Technical Specification Clause 1501 MORD of un-reinforced plain cement concretepavement M30 (Grade design mix ) to thick ness of 200 mm is proposed
Construction of Gravel Base / shoulders including cost, seigniorage charges and conveyance of all
materials to work site and spreading in uniform layers by approved means, on prepared surface and
compacting with vibratory roller to achieve the desired density at OMC etc., complete for finished item of
work as per MoRT&H Specification 401& 407 (4th revision) and as directed by the Engineer-in-charge.
Gravel shoulders on both sides of the road and proposed required CD works
Necessary provisions are also made for Joint filler board, VAT @ 5%, Q.C charges @ 2.50 % ,Labour cess
@ 1.00 %, Ps Charges 7.50 % , Etc.
The detailed estimate is prepared with current schedule of rates (ie 2013-14 ) and the work will be carried
out as per APDSS
Specification report to accompany the Detailed estimate for the work
The above work was proposed for sanction under under indiramma Infrastructure funds in Indiramma
Layouts where SC/STs are more than 90%. Hence detailed estimate is prepared with the following
provisions.
Removal of Unserviceable soil including excavation, loading and disposal upto 1000 m lead but excluding
compaction ground supporting embankment subgrade replacement by suitable soil, which shall be paid
separately as per Clause 303.5.2 as per Technical Specification Clause 302.3.11 MORD / 301 MORTH is
proposed to a depth of 75 mm
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand packing, rolling with three wheel 80 -100 kN
static roller in stages to proper grade and camber, applying and brooming, stone screening/binding
materials to fill-up the interstices of coarse aggregate, watering and compacting to the required density
Grading 1 as per Technical Specification Clause 404 (WBM Grading 2nd Layer to a compacted thickness
of 75mm ) for providing two grading layers of each 75 mm thick
Name of the Work: Construction of CC Roads in Godavarru Village of Duggirala Mandal
Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with
motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compactingwith vibratory roller to achieve the desired density, complete as per clause 402 MORTH Grading C
(Granular Sub-Base with Coarse Graded Material (Table:- 400- 2)) of granular sub-base is proposed to
thick ness of 75 mm
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
4/87
Estimate Cost : Rs 7700000.00
S.No Description of Item Amount
1 Construction of CC Road (Sub Estimate) 3328378.00
2 Construction of Drain (Sub Estimate) 2920009.00
Sub Total (1+2) 6248387.00
4 Provision for PS Charges 7.5% 468629.00
5 Provision for VAT at 5% 312419.00
6 Provision for 3rd Party Quality control @2.5% 156209.00
7 Provision for labour cess 1% 62484.00
8 Provision for Tender premium at 5.00% 312419.00
10 Unforceen Items 139453.00
Grand Total:- Rs 7700000.00
Assistant Engineer Deputy Executive Engineer
APSHCL, Duggirala APSHCL, Mangalagiri
Executive Engineer
APSHCL, Guntur
GENERAL ABSTRACT
Name of the Work: Construction of Side Drains and CC Roads in Godavarru Village of
Duggirala Mandal
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
5/87
Estimate cost Rs. 41.00 lakhs
SNo. Description of Item Nos. L B D Qty. Rate per Total value
1
Cross Roads 6 54.00 3.60 0.075 87.48
Cross Roads 5 40.00 3.60 0.075 54.00
141.48 74.92 10600.00
Cu.m 1 cu.m
2
Grading 1st Layer
Cross Roads 6 54.00 3.30 0.075 80.19
Cross Roads 5 40.00 3.30 0.075 49.50
129.69 2642.00 342641.00
Cu.m 1 Cum
3
Grading 2 Layer
Cross Roads 6 54.00 3.30 0.075 80.19
Cross Roads 5 40.00 3.30 0.075 49.50
129.69 2642.00 342641.00
Cu.m 1 Cum
4
Sub Base
Cross Roads 6 54.00 3.30 0.075 80.19
Cross Roads 5 40.00 3.30 0.075 49.50
129.69 1929.79 250274.00
Cu.m 1 cu.m
Providing, laying, spreading and compacting stone aggregates of specific sizes
to water bound macadam specification including spreading in uniform
thickness, hand packing, rolling with three wheel 80 -100 kN static roller in
stages to proper grade and camber, applying and brooming, stone
screening/binding materials to fill-up the interstices of coarse aggregate,
watering and compacting to the required density Grading 1 as per Technical
Specification Clause 404 (WBM Grading 2nd Layer to a compacted
thickness of 75mm )
DETAILED CUM ABSTRACT ESTIMATE
Name of the Work: Construction of CC Roads in Godavarru Village of Duggirala Mandal
Removal of Unserviceable soil including excavation, loading and disposal upto
1000 m lead but excluding compaction ground supporting embankment
subgrade replacement by suitable soil, which shall be paid separately as per
Clause 303.5.2 as per Technical Specification Clause 302.3.11 MORD / 301
MORTH
Providing, laying, spreading and compacting stone aggregates of specific sizes
to water bound macadam specification including spreading in uniform
thickness, hand packing, rolling with three wheel 80 -100 kN static roller in
stages to proper grade and camber, applying and brooming, stone
screening/binding materials to fill-up the interstices of coarse aggregate,
watering and compacting to the required density Grading 1 as per TechnicalSpecification Clause 404 (WBM Grading 2nd Layer to a compacted
thickness of 75mm )
Construction of granular sub-base by providing coarse graded material,
spreading in uniform layers with motor grader on prepared surface, mixing by
mix in place method with rotavator at OMC, and compacting with vibratory
roller to achieve the desired density, complete as per clause 402 MORTH
Grading C (Granular Sub-Base with Coarse Graded Material (Table:- 400- 2))
5 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
6/87
SNo. Description of Item Nos. L B D Qty. Rate per Total value
5
Cross Roads 6 54.00 3.30 0.20 213.84
Cross Roads 5 40.00 3.30 0.20 132.00
345.84 6021.92 2082621.00
Cu.m 1 cu.m
6
For shoulders both side
Cross Roads 6 2 54.00 0.75 0.20 97.20
Cross Roads 5 2 40.00 0.75 0.20 60.00
157.20 742.60 116737.00
Cu.m 1 cu.m
7
for Cross Roads 2 11 2.50 55.00for Cross Roads 2 11 2.50 55.00
110.00 1555.50 171105.00
8
for Cross Roads 2 11 2.50 55.00
for Cross Roads 2 11 2.50 55.00
110.00 106.90 11759.00
Total Estamate 3328378.00
Provision for PS Charges 7.5% 249628.00
Provision for VAT at 5% 166419.00
Provision for 3rd Party Quality control @2.5% 83209.00
Provision for labour cess 1% 33284.00Provision for Tender premium at 5.00% 166419.00
Unforceen Items 72663.00
Total 4100000.00
Assistant Engineer Deputy Executive Engineer Executive Engineer
APSHCL, Duggirala APSHCL, Mangalagiri APSHCL, Guntur
Supply and delivery of RCC NP3 pipes of 450 mm dia including collars and
conveyance charges etc, complete
Laying and fixing of RCC NP3 pipes of 450 mm dia including all labour
charges etc, complete
Construction of un-reinforced, dowel jointed at expansion and construction joint only,
plain cement concrete pavement, thickness as per design, over a prepared sub base, with
43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade) design mix ,
coarse and fine aggregates conforming to IS : 383, maximum in a concrete mixer of not
less than 0.2 cum capacity and appropeiate weigh batcher using approved mix design,
laid in approved fixed side formwork (steel channel, laying and fixing of 125 mictron
thick polythene film, wedges, steel plates including levelling the formwork as per
drawing), spreading the concrete with sholvels, rakes, compacted using needle, scareed
and plate vibrators and finished in continuous operation including provision of
contraction and expansion, construction joints, applying debonding strips, primer,sealant, dowel bars, near approaches to bridge / culvert and construction joints,
admixtures as approved, curing of concrete slabs for 14- days, curing compound (where
specified) and water finishing to lines and grade as per drawing and Technical
Specification Clause 1501 MORD.
Construction of Gravel Base / shoulders including cost, seigniorage charges
and conveyance of all materials to work site and spreading in uniform layers by
approved means, on prepared surface and compacting with vibratory roller to
achieve the desired density at OMC etc., complete for finished item of work as
per MoRT&H Specification 401& 407 (4th revision) and as directed by theEngineer-in-charge.
6 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
7/87
Est.Rs. 36.00 Lakhs
Assistant Engineer Deputy Executive Engineer Executive Engineer
APSHCL, Duggirala APSHCL, Mangalagiri APSHCL, Guntur
Plain cement concrete in substructure complete as per drawings and technical specification Clauses
802, 804, 805, 806, 807, 1202 and 1204 MORD and 1500, 1700 & 2200 MORTH ( M15 concrete design mix
) for Drain Wall is proposed to a length of 843.00 mts on both sides of the road is proposed.
Specification report to accompany the detailed estimate for the work
Name of the Work: Construction of Side Drains in Godavarru Village of Duggirala Mandal
The above work was proposed under indiramma Infrastructure funds. Hence detailed estimate is
prepared with the following provisions.
Providing concrete for plain concrete in open foundations using 40 mm nominal size Graded hard stone
aggregate, mechanically mixed, placed in foundation and compacted by vibration including curing for 14days complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 MORD and 1500,
1700 & 2100 MORTH. ( M10 Concrete , nominal mix 1:3:6) for Bed Concrete 0.10m depth is proposed.
Necessary provisions are also made for Joint filler board, VAT @ 5%, Q.C charges @ 2.50 % ,Labour cess
@ 1.00 %, Ps Charges 7.50 % , Etc.The detailed estimate is prepared with current schedule of rates (ie 2013-14 ) and the work will be carried out
as per APDSS
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1
including setting out, construction of shoring and bracing, removal of stumps and other deleterious material
and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated
suitable material as per Technical Specification 305 MORD / 304 MORTH
Sand filling 150 mm th for shoe wall fondation is proposed with filling Sand in foundation trenches as
per drawing and technical specification Clause 305.3.9 MORD & 304 MORTH
Plain cement concrete in substructure complete as per drawings and technical specification Clauses 802, 804,
805, 806, 807, 1202 and 1204 MORD and 1500, 1700 & 2200 MORTH Excluding Seignorage and VAT
including OH&CP (at bottom portion of drain) M20 concrete at Concreting at bottom of drain to thick ness of
100 mm is proposed
Plastering with cement mortar (1:4), 12 mm thickness as per technical specification 1300 & 2200 MORTH
for inside and top portion of drain is proposed
Certified that the above village is with in 12 Km Radious of from Tadepalli Municipality limits. Hence
20 % extra over the rates on labour component of works provision is made in this estimate
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
8/87
Estimate cost Rs. 36.00 lakhs
SNo. Description of Item Nos. L B D Qty. Rate per Total value
1
Side walls
Main Road 1 x 2 185.00 0.90 0.600 199.80 Cum
Cross Roads 7 x 2 40.00 0.90 0.600 302.40 Cum
Cross Roads 7 x 2 54.00 0.90 0.600 408.24 Cum
910.44 116.19 105784.00
Cu.m 1 cu.m
2
Main Road 1 x 2 185.00 0.90 0.150 49.95
Cross Roads 7 x 2 40.00 0.90 0.150 75.60
Cross Roads 7 x 2 54.00 0.90 0.150 102.06
227.61 512.70 116696.00
Cu.m 1 cu.m
3
Bottom
Main Road 1 x 2 185.00 0.90 0.100 33.30
Cross Roads 7 x 2 40.00 0.90 0.100 50.40
Cross Roads 7 x 2 54.00 0.90 0.100 68.04
151.74 3799.40 576521.00
Cu.m 1 cu.m
4
Side walls
Main Road 1 2 x 2 185.00 0.20 0.550 81.40
Cross Roads 7 2 x 2 40.00 0.20 0.550 123.20
Cross Roads 7 2 x 2 54.00 0.20 0.550 166.32
DETAILED CUM ABSTRACT ESTIMATE
Name of the Work: Construction of Side Drains in Godavarru Village of Duggirala
Mandal
Earthwork in excavation for structures as per drawing
and technical specifications Clause 305.1 includingsetting out, construction of shoring and bracing, removal
of stumps and other deleterious material and disposal
upto a lead of 50 m, dressing of sides and bottom and
backfilling in trenches with excavated suitable material
as per Technical Specification 305 MORD / 304 MORTH
Filling Sand in foundation trenches as per drawing and
technical specification Clause 305.3.9 MORD & 304
MORTH
Providing concrete for plain concrete in open
foundations using 40 mm nominal size Graded hardstone aggregate, mechanically mixed, placed in
foundation and compacted by vibration including curing
for 14 days complete as per drawings and technical
specifications Clause 802, 803, 1202 & 1203 MORD and
1500, 1700 & 2100 MORTH. for Bed Concrete ( M10
Concrete , nominal mix 1:3:6)
Plain cement concrete in substructure complete as per
drawings and technical specification Clauses 802, 804,
805, 806, 807, 1202 and 1204 MORD and 1500, 1700 &
2200 MORTH ( M15 concrete design mix)
8 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
9/87
SNo. Description of Item Nos. L B D Qty. Rate per Total value
370.92 4479.60 1661573.00
Cu.m 1 cu.m
5
At bottom of Drain
Main Road 1 2 185.00 0.30 0.100 11.10
Cross Roads 7 2 40.00 0.30 0.100 16.80
Cross Roads 7 2 54.00 0.30 0.100 22.68
50.58 4828.40 244220.00
Cu.m 1 cu.m
6
Total drain
Main Road 1 2 185.00 1.600 592.00
Cross Roads 7 2 40.00 1.600 896.00
Cross Roads 7 2 54.00 1.600 1209.60
2697.60 79.78 215215.00
Sq.m 1 Sq.m
Total Estamate 2920009.00
Provision for PS Charges 7.5% 219001.00
Provision for VAT at 5% 146000.00
Provision for 3rd Party Quality control @2.5% 73000.00
Provision for labour cess 1% 29200.00
Provision for Tender premium at 5.00% 146000.00
Unforceen Items 66790.00
3600000.00
Assistant Engineer Deputy Executive Engineer Executive Engineer
APSHCL, Duggirala APSHCL, Mangalagiri APSHCL, Guntur
Total amount
Plain cement concrete in substructure complete as per
drawings and technical specification Clauses 802, 804,
805, 806, 807, 1202 and 1204 MORD and 1500, 1700 &
2200 MORTH Excluding Seignorage and VAT includingOH&CP (at bottom portion of drain) M20 concrete
Plastering with cement mortar (1:4), 12 mm thickness as
per technical specification 1300 & 2200 MORTH
9 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
10/87
S.
NoQuantity Unit Description Rate Rs. per
1 2 3 4 5 6
"13-14 40.00
0% 50.00
14% 22.00
1Removal of Unserviceable Soil with Disposal upto
1000 m
RBR-EECD
Removal of Unserviceable soil including excavation,
loading and disposal upto 1000 m lead but excluding
compaction ground supporting embankment
subgrade replacement by suitable soil, which shall be
paid separately as per Clause 303.5.2 as per Technical
Specification Clause 302.3.11 MORD / 301 MORTH
Unit = cum
Taking output = 360 cuma) Labour
- day Mate
2.080 day Mazdoor (Unskilled) 280.00 1 day
b) Machinery
3.60 hour Excavator 0.90 cum bucket capacity @ 100 cum per hour 2754.50 1 hour
15.00 hour Tipper 5.5 cum capacity, 4 trips per hour 877.30 1 hour
14% c&d) Overheads & Contractors Profit 23658.10
Cost for 360 cum = a+b+c+d
Rate per cum = (a+b+c+d)/360
2Granular Sub-Base with Coarse Graded Material
(Table:- 400- 2)
Construction of granular sub-base by providing coarse
graded material, spreading in uniform layers with motor
grader on prepared surface, mixing by mix in place method
with rotavator at OMC, and compacting with vibratory
roller to achieve the desired density, complete as per clause
402 MORTH Grading C
Unit = cum
Taking output = 300 cum
a) Labour
- day Mate
2.40 day Mazdoor skilled 280.00 1 day
8.00 day Mazdoor 280.00 1 day
b) Machinery
6.00 hour Mortar Grader 110 HP @ 50 cum per hour 3216.00 1 hour
30.00 hour Three wheel Roller 80-100 KN @10cu.m/hour 1704.60 1 hour
3.00 hour Water tanker 6 KL capacity 624.00 1 hour 12.00 hour Tractor with Rotavator 25 cu.m/hour 422.00 1 hour
c) Material
For coarse graded Granular sub-base Materials per table
400-2
For Grading-C Material (CBR Value minimum 20)
134.00 cum 9.5 mm to 4.75 mm @ 35 per cent 1327.51 1 cum
48.00 cum 4.75 mm to 2.36 mm @ 12.5 per cent 987.51 2 cum
201.60 cum 2.36 mm below @ 52.5 per cent (Dust) 1015.01 1 cum
18.00 KL Cost of water 0.00 1 KL
Total Seignorage Charges 19180.00
Overheads &
Contractor's Profit
Sand
HBG Metal
Gravel/Earth
Name of the Work:
SSR
MUNICIPAL
ALLOWANCE
Seignorage Char
10 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
11/87
S.
NoQuantity Unit Description Rate Rs. per
1 2 3 4 5 6
14% Add over heads& contr.profit Exclu. Sei. Charges 491014.84
Cost for 300 cum = a+b+c+d+e
Rate per cum = (a+b+c+d)/300
3 a Grading 1Layer
Water Bound Macadam Sub-base/base With stone
screening / binding materials WBM Grading 1 Layer
100mm thick
RBR-SBBS-9
(i) Providing, laying, spreading and compacting stone
aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness,
hand packing, rolling with three wheel 80 -100 kN static
roller in stages to proper grade and camber, applying and
brooming, stone screening/binding materials to fill-up the
interstices of coarse aggregate, watering and compacting to
the required density Grading 1 as per Technical
Specification Clause 404 MORTH & 405 MORD.
For compacted thickness of 100 mm.By Manual Means (Common for rural & urban
works)
Unit = cum
Taking output = 360 cum
a) Labour
- day Mate
12.08 day Mazdoor (Skilled) 280.00 1 day
250.00 day Mazdoor (Unskilled) 280.00 1 day
b) Machinery
6.00 hour Vibratory roller 8-10 tonnes @ 60 cum per hour 2541.40 1 hour
24.00 hour Water tanker 6 kl capacity 624.00 1 hour
c) Material
Aggregate
Grading 1 90 mm to 45 mm @ 1.21 cum per 10 sqm forcompacted thickness of 100 mm
217.8 cum 75mm IRC HBG metal 906.51 1 cum
200.38 cum 63mm IRC HBG M/C metal 981.51 1 cum
17.42 cum 45 mm IRC HBG M/C metal 1190.51 1 cum
Stone Screenings
97.20 cum Type A 13.2 mm for Grading-1 @ 0.27 cum per 10sqm 1577.51 1 cum
Binding Material
28.80 cumBinding Material @ 0.08 cum per 10 sqm forgrading 1
material (Rate of 2.36mm & Below)1015.01 1 cum
144.00 kl Water 0.00 1 KL
Total Seignorage Charges 28080.00
14% Add over heads& contr.profit Exclu. Sei. Charges 672944.60
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
3 b Grading 2 LayerWBM Grading 2nd Layer 75mm thick By
Mechanical Means
Unit = cum
Taking output = 360 cum
a) Labour
12.08 day Mazdoor (Skilled) 280.00 1 day
250.00 day Mazdoor (Unskilled) 280.00 1 day
b) Machinery
36.00 hour Three wheel Roller 80-100 KN @10cu.m/hour 1704.60 1 hour
11 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
12/87
S.
NoQuantity Unit Description Rate Rs. per
1 2 3 4 5 6
24.00 hour Water tanker 6 kl capacity 624.00 1 hour
Materials
217.8 cum 60-63mm IRC HBG metal 1021.51 1 cum
200.38 cum 40-45mm IRC HBG M/C metal 1337.51 1 cum
17.42 cum 19-22.40 mm IRC HBG M/C metal 1832.51 1 cum
86.40 cum Type B 11.2 mm for Grading 2 @ 0.18 cum per 10sqm 1577.51 1 cum
Binding Material
28.80 cumBinding material @ 0.06 cum / 10sqm (Rate of 2.36mm &
Below)1015.01 1 cum
144.00 kl Water 0.00 1 KL
Seignorage Charges 27540.00
14% Add over heads& contr.profit Exclu. Sei. Charges 810130.61
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
3 c Grading 3 Layer WBM Grading 3 Layer
RBR-SBBS-9
(i) Providing, laying, spreading and compacting stone
aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness,
hand packing, rolling with smooth wheel roller 80-100 kN
in stages to proper grade and camber, applying and
brooming, stone screening to fill-up the interstices of
coarse aggregate, watering and compacting to the required
density Grading 3 as per Technical Specification Clause
405 MORD/ 404 MORTH. For compacted thickness of
75 mm.
By Manual Means
Unit = cum
Taking output = 360 cum
a) Labour
12.08 day Mazdoor (Skilled) 280.00 1 day
250.00 day Mazdoor (Unskilled) 280.00 1 day
b) Machinery
36.00 hour Three wheel Roller 80-100 KN @10cu.m/hour 1704.60 1 hour
24.00 hour Water tanker 6 kl capacity 624.00 1 hour
c) Material (Refer Tables 400.7, 8, 9 & 10 MORD/
400.6, 7, 8 & 9 MORTH)
Aggregate
cumGrading 3 53 mm to 22.4 mm @ 0.91cum per 10 sqmfor
compacted thickness of 75 mm
357.19 cum 40-45mm IRC HBG M/C metal 1337.51 1 cum
78.41 cum 19-22.40 mm IRC HBG M/C metal 1832.51 1 cum
Stone Screening
86.40 cum Type B 11.2 mm for Grading 3 @ 0.18 cum per 10sqm 1422.51 1 cum
Binding Material
28.80 cumBinding Material @ 0.06 cum per 10 sqm forGrading 2
material (Rate of 2.36mm & Below)1015.01 1 cum
144.00 kl Water 0.00 1 KL
Seignorage Charges 27540.00
Note : Type A Screening can be used in Grading 2
12 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
13/87
S.
NoQuantity Unit Description Rate Rs. per
1 2 3 4 5 6
14% Add over heads& contr.profit Exclu. Sei. Charges 895753.46
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d)/360
3 d II WBM Grading 2
RBR-SBBS-9
Providing, laying, spreading and compacting stone
aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness,
hand packing, rolling with smooth wheel roller 80-100 kN
in stages to proper grade and camber, applying and
brooming, stone screening/binding materials to fill-up the
interstices of coarse aggregate, watering and compacting to
the required density grading 2 as per Technical
Specification Clause 405 MORD / 404 MORTH. For
compacted thickness of 75 mm.
By Manual Means
Unit = cum
Taking output = 360 cum
a) Labour
day Mate 280.00 1 day
12.08 day Mazdoor (Skilled) 280.00 1 day
250.00 day Mazdoor (Unskilled) 280.00 1 day
b) Machinery
36.00 hour Three wheel 80-100 kN static roller @ 10 cum per hour for Rural Area
works1704.60 1 hour
24.00 hour Water tanker 6 kl capacity624.00 1 hour
c) Material (Refer Tables 400.7, 8, 9 and 10 MORD/ 400.6, 7,
8 & 9 MORTH)
Aggregate
435.60 cumGrading 2 63 mm to 45 mm @ 0.91 cum per 10 sqm for
compacted thickness of 75 mm1058.51 1.00 cum
Stone Screening
86.40 cum Type B 11.2 mm for Grading 2 @ 0.18 / 0.20 cum/10sqm 1422.51 1.00 cum
(OR)
57.60 cum Type B 13.2 mm for Grading 2 @ 0.12 cum per 10sqm 1577.51 1.00 cum
Binding Material
28.80 cumBinding Material @ 0.06 cum per 10 sqm for Grading 2
material1015.01 1.00 cum
144.00 kl Water 0.00 1.00 KL
Using 11.2 mm for Grading 2 :
Seignorage Charges 26100.00
14% Add over heads& contr.profit Exclu. Sei. Charges 707615.82
Cost for 360 cum = a+b+c+d+e
Note : When BT is taken up, simultaneously, avoid Binding material
13 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
14/87
S.
NoQuantity Unit Description Rate Rs. per
1 2 3 4 5 6
Rate per cum = (a+b+c+d+e)/360
Using 13.2 mm for Grading 2
Seignorage Charges 26100.00
14% Add over heads& contr.profit Exclu. Sei. Charges 704807.82
Cost for 360 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/360
4
Providing and applying track coat with bitumen
emulsion using emulsion pressure distributor at the
rate of 0.20 kg per sqm on the prepared
bituminous/granular surface cleaned with mechanical
broom as per Tech. specification No 503 MORTH
Unit = sqm
Taking output = 3500 sqm
a) Labour
2.080 day Mazdoor (Unskilled) 280.00 1 dayb) Machinery
2.800 hour Mechanical broom @ 1250 sqm per hour 357.00 1 hour
2.800 hour Air compressor 250 cfm 499.40 1 hour
2.000 hour Emulsion pressure distributor @ 1750 sqm per hour 860.00 1 hour
c) Material
0.700 t Bitumen emulsion @ 0.2 kg per sqm 37179.93 1 Mt
14% d&e) Overheads & Contractors Profit 30726.27
Rate per sq.m = (a+b+c+d)/3500 sq.m
Rate per sq.m = (a+b+c+d)/3500 sq.m
5
20mm thick Open-Graded Premix Carpet using
Bituminous (penetration grade/modified bitumen)
Binder
Providing, laying and rolling of open-graded premix carpetof 20 mm thickness composed of 13.2 mm to 5.6 mm
aggregates either using penetration grade bitumen or
emulsion to required line, grade and level to serve as
wearing course on a previously prepared base, including
mixing a suitable plant, laying and rolling with a three
wheel 0-100 kN static roller capacity, finished to required
level and grades to be followed by seal coat of either type
A or Type B or Type C as per Technical Specification
Clause 508 MORD.
Case - II By Mechanical Means
Bitumen (S-65)
Unit = sqm
Taking output = 4000 sqm (80 cum)a) Labour
10.000 day Mazdoor (Unskilled) 280.00 1 day
3.520 day Mazdoor (Skilled) 280.00 1 day
b) Machinery
6.000 hour HMP 30/40 t per hour 19120.00 1 hour
6.000 hour Electric generator set 125 KVA 1320.00 1 hour
6.000 hour Front end loader 1 cum bucket capacity 1646.00 1 hour
3.640 hour Tipper 5.5 cum - 10 t capacity 877.30 1 hour
6.000 hour Paver finisher 2249.00 1 hour
16.000 hour Three wheel 80-100 kN static roller 1283.00 1 hour
c) Material
5.840 t Bitumen (S-65) @ 14.60 kg per 10 sqm 37179.93 1 Mt
14 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
15/87
S.
NoQuantity Unit Description Rate Rs. per
1 2 3 4 5 6
108.000 cumCrushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum
per 10 sqm1422.51 1 cum
Seignorage Charges 5400.00
14% Add over heads& contr.profit Exclu. Sei. Charges 538878.84
Cost of 4000 sqm = a+b+c+d+e
Rate per 1 sq.m = (a+b+c+d)/4000 sq.m
6 Seal Coat
Providing and laying seal coat sealing the voids in a
bituminous surface laid to the specified levels, grade and
cross fall using Type A, Type B and Type C as per
Technical Specification Clause 510 MORD. (using Three
wheel 80-100 kN static roller)
By Manual Means
Bitumen (S-65)
Unit = sqm
Taking output = 1100 sqm
a) Labour
- day Mate1.000 day Bitumen Sprayer 280.00 1 day
22.000 day Mazdoor (Unskilled) 280.00 1 day
7.150 day Mazdoor (Semi-Skilled) 280.00 1 day
b) Machinery
2.200 hour Bitumen boiler oil fired, capacity 1000 litre fitted with
spray set209.00 1 hour
2.200 hour Three wheel 80-100 kN static roller 1283.00 1 hour
c) Material
1.078 t Bitumen (S-65) @ 9.80 kg per 10 sqm 37179.93 1 cum
9.900 cum
Crushed stone chipping of 6.7 mm size 100 per cent
passing 11.2 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum per 10 sqm
1232.51 1 cum
Seignorage Charges 495.00
14% Add over heads& contr.profit Exclu. Sei. Charges 63511.21
Cost of 1100 sqm = a+b+c+d+e
Rate per 1 sq.m = (a+b+c+d)/1100
7
Cost and supply of Gravel for formation of roads
Including cost and Seignorage charges and conveyance of
all materials to work site and spreading in uniform layers
by approved means, on prepared surface and compacating
with vibrating roller to achieve the desired density.
A. Gravel Roads
The rate as applicable for sub-grade construction may be
adopted.For Grading III Material (CBR Value minimum 20)
Unit = cum
Taking output = 300 cum
D&e) Overheads & Contractors Profit
2.40 day Mazdoor (Skilled) 280.00 1 day
8.00 day Mazdoor (Unskilled) 280.00 1 day
b) Machinery
36.00 hour Three wheel 80-100 kN Static Roller 1704.60 1 hour
12.00 hour Tractor with Rotavator 422.00 1 hour
12.00 hour Tractor with Grader 422.00 1 hour
3.00 hour Water tanker 6 kl capacity 624.00 1 hour
15 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
16/87
S.
NoQuantity Unit Description Rate Rs. per
1 2 3 4 5 6
c) Material
237.6 cum Gravel(9.5MM-4.75mm)66% 508.46 1 cum
122.4 cum 2.36 mm below @ 34 per cent (Dust) 1015.01 1 cum
18.00 kl Water 1 KL
Seignorage Charges 11347.20
14% Add over heads& contr.profit Exclu. Sei. Charges 309977.72
Cost for 300cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d)/300
8
Construction of Gravel shoulders including cost,
seigniorage charges and conveyance of all materials to
work site and spreading in uniform layers by approved
means, on prepared surface and compacting with
vibratory roller to achieve the desired density at OMC etc.,
complete for finished item of work as per MoRT&H
Specification 401& 407 (4th revision) and as directed by
the Engineer-in-charge.
( Payment will be made based on levels for finished
item of work )
Unit = cum
Taking output = 300 cum
(A) Labour
0.40 day Mate 280.00 1 day
2.00 day Mazdoor skilled 280.00 1 day
8.00 day Mazdoor unskilled 280.00 1 day
(B) Machinery
6.00 hr Vibratory roller 8T 2541.40 1.00 hr
3.00 hr Water tanker 6 KL 624.00 1.00 hr
(C) Material
384.00 cum Gravel 508.46 1.00 cum
Seignorage Charges 8448.00
14% Add over heads& contr.profit Exclu. Sei. Charges 206833.04
Cost for 300cum = a+b+c+d
Rate per cum = (a+b+c+d)/300
9
RBR-SBBS-12 Granular sub-base/base/surface course with local materials (Table 400.13)
by mix in place method normal Construction of granular sub-base by
providing local material spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator at once
and compacting with smooth wheel roller to achieve the desired density
complete as per Clause 401.4 as per Technical Specification Clause 408
MORD.
Using naturally occurring gravel
Unit = cum
Taking output = 300 cum
a) Labour
day Mate 280.00 1 day
2.48 day Mazdoor (Skilled) 280.00 1 day
10.00 day Mazdoor (Unskilled) 280.00 1 day
b) Machinery
6.00 hour Motor grader 110 HP 50 cum per hour 3216.00 1 hour
30.00 hour Three wheel 80-100 kN static roller @10 cum per hour 1704.60 1 hour
12.00 hour Tractor with rotavator 25 cum per hour 422.00 1 hour
16 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
17/87
S.
NoQuantity Unit Description Rate Rs. per
1 2 3 4 5 6
5.00 hour Water tanker 6 kl capacity 624.00 1 hour
c) Material
384.00 cum Naturally occurring gravel (Local materials as per Table 400.13) 508.46 1 cum
30.00 kl Water 0.00 1 kl
Basic Cost
Seignorage Charges 19200.0014% Add over heads& contr.profit Exclu. Sei. Charges 258161.04
Cost for 300cum = a+b+c+d
Rate per cum = (a+b+c+d)/300
10
RBR-CCPV-5
Unit = cum
Taking output = 75 cum (172.50 t)
(100 x 3.75 x 0.200)
a) Labour
day Mate 280.00 1.00 day
5.00 day Mason (1st class) 350.00 1.00 day
5.00 day Mason (2nd class) 320.00 1.00 day
150.00 day Mazdoor (Unskilled) 280.00 1.00 day
6.00 day Mazdoor (Skilled) 280.00 1.00 day
2.00 day Surveyor 320.00 1.00 day
6.00 day Mazdoor (Semi-Skilled) 280.00 1.00 day
1.00 dayBlacksmith for cutting of dowel bars including removal of burrs,
fabrications & fixing of dowel bars.
b) Machinery
36.00 hour Concrete mixer 0.28 / 0.4 cum capacity (6 mixers) with weigh
batcher and suitable capacity calibrated water tank417.40 1.00 Hour
9.00 hour Needle vibrator 152.20 1.00 Hour
9.00 hour Screed vibrator 0.00 1.00 Hour
9.00 hour Plate vibrator 152.20 1.00 Hour
4.00 hour Concrete joint cutting machine for initial & final cuts 0.00 1.00 Hour
5.00 hour Water tanker 6 kl capacity 624.00 1.00 Hour
2.00 hour Air Compressor (1 hour initial + 1 hour final) 499.40 1.00 Hour
c) Material
Crushed stone coarse aggregates, grading will be as per Clause
1501.2.4.1 (Table 1500.1) of specifications @ 0.90 cum/cum of
concrete (25 mm & 12.5 mm blending)
44.55 cum 20 mm HBG Metal 1832.51 1.00 Cum
22.95 cum 12 mm HBG Metal 1577.51 1.00 Cum
33.75 cumSand as per IS:383 and conforming to Clause 1500.2.4.2 @ 0.45
cum/cum of concrete467.77 1.00 Cum
26.25 t Cement @ 310 kg/cum of concrete 5.70 1.00 Cum
412.50 sqm Polythene sheet 125 micron 15.00 1.00 Sq mt
Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain
cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade
cement or any other type as per Clause 1501.2.2 M30 (Grade) design mix, coarse and fine
aggregates conforming to IS : 383, maximum in a concrete mixer of not less than 0.2 cum
capacity and appropeiate weigh batcher using approved mix design, laid in approved fixed side
formwork (steel channel, laying and fixing of 125 mictron thick polythene film, wedges, steel
plates including levelling the formwork as per drawing), spreading the concrete with sholvels,
rakes, compacted using needle, scareed and plate vibrators and finished in continuous operation
including provision of contraction and expansion, construction joints, applying debonding
strips, primer, sealant, dowel bars, near approaches to bridge / culvert and construction joints,admixtures as approved, curing of concrete slabs for 14- days, curing compound (where
specified) and water finishing to lines and grade as per drawing and Technical Specification
Clause 1501 MORD.
17 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
18/87
S.
NoQuantity Unit Description Rate Rs. per
1 2 3 4 5 6
Mild steel dowel bar 25 mm dia of grade S 240. 500 mm long20
Nos. at culvert/bridge slab and at construction joint including 5
per cent wastage.
0.118 t(4 x 20x 0.500) + 5 per cent wastage = 42 m @ 2.80 kg per m =
117.6 kg.43000.00 1.00 ton
5.00 kg Bitumen primer @ 200 ml per joint for 23 joints 37179.93 1.00 ton
19.00 litre Bituminous sealant 800 ml per joint for 23 joints 37179.93 1.00 ton90.00 m Jute rope 12 mm dia including 5 per cent wastage
90.00 m
Debonding strips 3.75 m (length) x 10 mm (width) x 5 mm
(thick) cut-out of rubber filler board or similar material including
5 per cent wastage
483.00 sqmtPolythene sheathing, covering 2/3rd dowel bars (20x23) and tight
fit including 5 per cent wastage15.00 1.00 Sq mt
122.00 litre Plasticizer 0.5 per cent by weight of cement 70.00 1.00 Ltr
131.25 litre Curing compound (if used) @ 0.33 litre per sqm
18.00 kl Water for curing 0.00 1.00 kl
3.00 sqmJoint filler board 20 mm thick as per IS:1838
(4 x 3.75 x 0.200 = 3 sqm)925.00 1.00 Ltr
3.00%(d) Formwork @ 3% on cost of material, labour and machinery
(a+b+c)385203.05
Basic rate per 75 Cum
Seignorage Charges
Sand 1350.00
Agrregate 3375.00
4725.00
14% Add over heads& contr.profit Exclu. Sei. Charges 392034.15
Add sundries
Rate per 75 Cum
Rate per Cum
11 Cost of RCC Pipes NP2
Unit = 1Rm
5.00 RM Cost and Conveyance charges of RCC Pipes 370.60 1.00 RM
1 No Cost of collars 87.00 1.00 No
Cost for 5Rm =a+b+c+d
Rate per RM is ( a+b+c+d )/5
14% Add over heads& contr.profit Exclu. Sei. Charges 388.00
Add sundries
Rate Per RM
12
Unit = 1Rm
Taking out put = 7.50 RM (3 pipes of 2.50 Mts length each )
upto 500 mm dia
a) Labour
2.51 day Mazdoor (Unskilled) 280.00 1.00 day
deduct 20% for 300mm RCC Pipes
b)Material
Cost for 5Rm =a+b
Rate per RM is ( a+b )/7.50
14% Add over heads& contr.profit Exclu. Sei. Charges 74.97
Supply and delivery of RCC NP2 pipes of 300mm dia including collars and
conveyance charges etc, complete
Laying of RCC pipes NP2
Laying and fixing of RCC NP2 pipes of300mm diaincluding all labour charges etc, complete
18 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
19/87
S.
NoQuantity Unit Description Rate Rs. per
1 2 3 4 5 6
Add sundries
Rate Per RM
13 Cost of RCC Pipes NP2
Unit = 1Rm
5.00 RM Cost and Conveyance charges of RCC Pipes 666.00 1.00 RM
1 No Cost of collars 185.00 1.00 No
Cost for 5Rm =a+b+c+d
Rate per RM is ( a+b+c+d )/5
14% Add over heads& contr.profit Exclu. Sei. Charges 703.00
Add sundries
Rate Per RM
14
Unit = 1Rm
Taking out put = 7.50 RM (3 pipes of 2.50 Mts length each )
upto 500 mm dia
a) Labour
2.51 day Mazdoor (Unskilled) 280.00 1.00 day
deduct 20% for 300mm RCC Pipes
b)Material
Cost for 5Rm =a+b
Rate per RM is ( a+b )/7.50
14% Add over heads& contr.profit Exclu. Sei. Charges 93.71
Add sundries
Rate Per RM
15 Cost of RCC Pipes NP3
Unit = 1Rm
5.00 RM Cost and Conveyance charges of RCC Pipes 845.40 1.00 RM
1 No Cost of collars 124.00 1.00 No
Cost for 5Rm =a+b+c+d
Rate per RM is ( a+b+c+d )/5
14% Add over heads& contr.profit Exclu. Sei. Charges 870.20
Add sundries
Rate Per RM
16
Unit = 1Rm
Taking out put = 7.50 RM (3 pipes of 2.50 Mts length each )
upto 500 mm dia
a) Labour
2.51 day Mazdoor (Unskilled) 280.00 1.00 day
deduct 20% for 300mm RCC Pipes
b)Material
Cost for 5Rm =a+b
Supply and delivery of RCC NP3 pipes of 300mm dia including collars and
Laying of RCC pipes NP3
Laying and fixing of RCC NP3 pipes of300mm diaincluding all labour charges etc, complete
Supply and delivery of RCC NP2 pipes of 450mm dia including collars and
conveyance charges etc, complete
Laying of RCC pipes NP2
Laying and fixing of RCC NP2 pipes of450 mm diaincluding all labour charges etc, complete
19 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
20/87
S.
NoQuantity Unit Description Rate Rs. per
1 2 3 4 5 6
Rate per RM is ( a+b )/7.50
14% Add over heads& contr.profit Exclu. Sei. Charges 74.97
Add sundries
Rate Per RM
17 Cost of RCC Pipes NP3
Unit = 1Rm
5.00 RM Cost and Conveyance charges of RCC Pipes 1317.80 1.00 RM
1 No Cost of collars 233.00 1.00 No
Cost for 5Rm =a+b+c+d
Rate per RM is ( a+b+c+d )/5
14% Add over heads& contr.profit Exclu. Sei. Charges 1364.40
Add sundries
Rate Per RM
18
Unit = 1Rm
Taking out put = 7.50 RM (3 pipes of 2.50 Mts length each )
upto 500 mm dia
a) Labour
2.51 day Mazdoor (Unskilled) 280.00 1.00 day
deduct 20% for 300mm RCC Pipes
b)Material
Cost for 5Rm =a+b
Rate per RM is ( a+b )/7.50
14% Add over heads& contr.profit Exclu. Sei. Charges 93.71
Add sundries
Rate Per RM
19
RBR-FNDN-1
(I) Ordinary soil
(A) Manual Means
(i) Upto 3 m depth
Unit = cum
Taking output = 10 cum
a) Labour
day Mate 280.00 1.00 day
3.64 day Mazdoor (Unskilled) 280.00 1.00 day
14% b&c) Overheads & Contractors Profit 1019.20 10.00 Cu.m
Add sundries
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10
20
Supply and delivery of RCC NP3 pipes of 450mm dia including collars and
Note : Classifications of Earth Work Specification are as per 302.2.1(a) of MORD and
Filling in foundation trenches as per drawing and technical specification Clause 305.3.9 MORD
& 304 MORTH
Laying and fixing of RCC NP3 pipes of450 mm diaincluding all labour charges etc, complete
Laying of RCC pipes NP3
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1
including setting out, construction of shoring and bracing, removal of stumps and other
deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and
backfilling in trenches with excavated suitable material as per Technical Specification 305
MORD / 304 MORTH
20 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
21/87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
22/87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
23/87
S.
NoQuantity Unit Description Rate Rs. per
1 2 3 4 5 6
Basic rate per 1 Cum
Seignorage Charges
Sand 19.20
Coarse aggregate 40.00
Total 59.20
14% Add over heads& contr.profit Exclu. Sei. Charges 3877.51 1.00 Cu.mAdd sundries
Rate per cum = a+b+c+d+e+f
21 d d) RBR-FNDN-5
Sub-analysis
Cement mortar 1:5 (1 cement : 5 sand)
Unit = cum
(a) Material
0.288 t Cement 5.70 1.00 Kg
1.05 cum Sand467.77 1.00 Cum
(b) Labour
day Mate 280.00 1.00 day
0.2 day Mazdoor (Unskilled) 280.00 1.00 day
Total material and labour = (a+b)
Cement mortar 1:4 (1 cement : 4 sand)
Unit = cum
(a) Material
0.360 t Cement 5.70 1.00 Kg
1.05 cum Sand 467.77 1.00 Cum
(b) Labour
day Mate 280.00 1.00 day
0.2 day Mazdoor (Unskilled) 280.00 1.00 day
Total material and labour = (a+b)
22Plastering with cement mortar (1:5), 12 mm thick on brickwork in
substructure as per technical specification
RBR-SBST-3
Unit = 10 sqm
Taking output = 10 sqm
(a) Material
0.144 cum Cement mortar 1:5 (Rate as in item 11.5 II ) 2188.76 1.00 Cum
(b) Labour
day Mate 280.00 1.00 day
0.500 day Mason 1st Class 350.00 1.00 day
0.540 day Mazdoor (Unskilled) 280.00 1.00 day
Basic rate per 1 Cum
Seignorage Charges
Sand 6.05
14% Add over heads& contr.profit Exclu. Sei. Charges 635.34 1.00 Cu.m
Add sundries
Rate per 10 sq mt
Rate per 1 sq mt
23Plastering with cement mortar (1:4), on brickwork in substructure as
per technical specification Section 1300 & 2200 MORTH
Note : Needle Vibrator is an item of minor T & P which is already included in overhead charges. Hence not added i
concrete works.
23 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
24/87
S.
NoQuantity Unit Description Rate Rs. per
1 2 3 4 5 6
Unit = 10 sqm
Taking output = 10 sqm
(a) Material
0.144 cum Cement mortar 1:4 (Rate as in item 11.5 II ) 2599.16 1.00 Cum
(b) Labour
day Mate 280.00 1.00 day
0.500 day Mason 1st Class 350.00 1.00 day
0.540 day Mazdoor (Unskilled) 280.00 1.00 day
Basic rate per 1 Cum
Seignorage Charges
Sand 6.05
14% Add over heads& contr.profit Exclu. Sei. Charges 694.43 1.00 Cu.m
Add sundries
Rate per 10 sq mt
Rate per 1 sq mt
Assistant Engineer Deputy Executive Engineer Executive
APSHCL, Duggirala APSHCL, Mangalagiri APSHCL,
24 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
25/87
Amount Rs.
7
582.40
9916.20
13159.50
3312.13
26970.23
74.92
672.00
2240.00
19296.00
51138.00
1872.005064.00
177886.34
47400.48
204626.02
0.00
510194.84
ges
25 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
26/87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
27/87
Amount Rs.
7
14976.00
222484.88
268010.25
31922.32
136296.86
29232.29
0.00
837670.61
113418.29
951088.89
2642.00
3382.40
70000.00
61365.60
14976.00
477745.20
143687.11
122904.86
29232.29
0.00
923293.46
27 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
28/87
Amount Rs.
7
125405.48
1048698.94
2913.10
0.00
3382.40
70000.00
61365.60
14976.00
461086.96
122904.86
90864.58
29232.29
0.00
733715.82
99066.21
832782.03
28 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
29/87
Amount Rs.
7
2313.28
730907.82
98673.09
829580.91
2304.39
582.40
999.60
1398.32
1720.00
26025.95
4301.68
35027.95
10.10
2800.00
985.60
114720.00
7920.00
9876.00
3193.37
13494.00
20528.00
217130.79
29 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
30/87
Amount Rs.
7
153631.08
544278.84
75443.04
619721.88
155.00
280.00
6160.00
2002.00
459.80
2822.60
40079.96
12201.85
64006.21
8891.57
72897.78
66.27
672.00
2240.00
61365.60
5064.00
5064.00
1872.00
30 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
31/87
Amount Rs.
7
120810.10
124237.22
0.00
321324.92
43396.88
364721.80
1215.80
112.00
560.00
2240.00
15248.40
1872.00
195248.64
215281.04
28956.63
244237.67
814.20
0.00
694.40
2800.00
19296.00
51138.00
5064.00
31 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
32/87
Amount Rs.
7
3120.00
195248.64
0.00
277361.04
36142.55
313503.59
1045.10
0.00
1750.00
1600.00
42000.00
1680.00
640.00
1680.00
15026.40
1369.80
0.00
1369.80
0.00
3120.00
998.80
81638.33
36203.86
15787.24
149625.00
6187.50
32 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
33/87
Amount Rs.
7
5074.00
185.90
706.42
7245.00
8540.00
0.00
2775.00
11556.10
396759.15
54884.79
0.00
451644.00
6021.92
1853.00
87.00
1940.00
388.00
54.32
0.08
442.40
702.80
140.56
562.24
74.97
10.50
33 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
34/87
Amount Rs.
7
0.03
85.50
3330.00
185.00
3515.00
703.00
98.42
0.08
801.50
702.80
702.80
93.71
13.12
0.07
106.90
4227.00
124.00
4351.00
870.20
121.83
0.07
992.10
702.80
140.56
562.24
34 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
35/87
Amount Rs.
7
74.97
10.50
0.03
85.50
6589.00
233.00
6822.00
1364.40
191.02
0.08
1555.50
702.80
702.80
93.71
13.12
0.07
106.90
0.00
1019.20
142.69
0.01
1161.90
116.19
35 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
36/87
Amount Rs.
7
0.00
86.80
367.77
454.57
58.04
0.09
512.70
0.00
145.60
508.46
654.06
88.49
0.05
742.60
1254.00
210.501203.76
0.00
0.00
35.00
389.20
166.96
81.12
36 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
37/87
Amount Rs.
7
0.00
3340.54
458.86
0.00
3799.40
1881.00
210.50
481.51
659.71
256.06
0.00
35.00
389.20
166.96
163.20
4243.14
585.22
0.04
4828.40
1567.50
224.53
642.01439.81
113.81
0.00
35.00
389.20
166.96
357.89
37 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
38/87
Amount Rs.
7
3936.71
542.860.03
4479.60
1641.60
491.16
0.00
56.00
2188.76
2052.00
491.16
0.00
56.00
2599.16
315.19
0.00
175.00
151.20
641.39
88.95
0.06
730.40
73.04
rate analysis of cement
38 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
39/87
Amount Rs.
7
374.28
0.00
175.00
151.20
700.48
97.23
0.09
797.80
79.78
ngineer
untur
39 /87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
40/87
SSR "13-14
MUNICIPAL ALLOWANCE 0%
Overheads & Contractor's Profit 14%
Initial 0%Rate Allow.
1 1st class mason I-11 350.00 0.00 350.00 per day
2 2nd class mason II-35 320.00 0.00 320.00 per day
3 1st class Brick Layer I-11 350.00 0.00 350.00 per day
4 2nd class Brick layer II-35 320.00 0.00 320.00 per day
5 1st class Painter I-35 400.00 0.00 400.00 per day
6 2nd class Painter II-37 320.00 0.00 320.00 per day
7 Head mazdoor II-10 320.00 0.00 320.00 per day
8 Man mazdoor III-3 280.00 0.00 280.00 per day
9 Woman mazdoor III-4 280.00 0.00 280.00 per day
10 skilled electrician I-5 400.00 0.00 400.00 per day
11 semiskilled electrician II-34 320.00 0.00 320.00 per day
12 helper II-34 320.00 0.00 320.00 per day
13 Cost of binding wire pno.231/1292 70.00 0.00 70.00 per Kg
A 1st - Floorper 1 sqm Rs. 8.99 Rs. 54.34 Rs.
B 2nd - Floorper 1 sqm Rs. 8.99 Rs. 77.01 Rs.
C 3rd - Floor per 1 sqm Rs. 8.99 Rs. 99.69 Rs.
D 4th - Floorper 1 sqm Rs. 8.99 Rs. 122.36 Rs.
A 1st - Floor per 1 sqm Rs. 0.90 Rs. 5.43 Rs.
B 2nd - Floorper 1 sqm Rs. 0.90 Rs. 7.70 Rs.
C 3rd - Floorper 1 sqm Rs. 0.90 Rs. 9.97 Rs.
D 4th - Floorper 1 sqm Rs. 0.90 Rs. 12.24 Rs.
A 1st - Floorper 1 sqm Rs. 2.11 Rs. 11.08 Rs.
B 2nd - Floorper 1 sqm Rs. 2.11 Rs. 15.57 Rs.
C 3rd - Floorper 1 sqm Rs. 2.11 Rs. 20.05 Rs.
HIRE CHARGES FOR ACCESS SCAFFOLDING - up to 3.66 M using Casurina Bellies, Bamboos, Woode
Runners, Wood Posts, Wall Plates etc., for BRICK MASONRY/STONE MASONRY - 1 sqm(Pno.91)
Labour & Materials
HIRE CHARGES FOR ACCESS SCAFFOLDING - up to 3.66 M using Casurina Bellies, Bamboos, Woode
Runners, Wood Posts, Wall Plates etc., for PLASTERING TO WALLS - 1 sqm(Pno-91)
Final Rate
HIRE CHARGES FOR STAGE SCAFFOLDING - up to 3.66 M using Casurina Bellies, Bamboos, Wooden
Runners, Wood Posts, Wall Plates etc., for CEILING PLASTERING - 1 sqm(Pno.92)
Name of the Work: Construction of Side Drains and CC Roads in Godavarru Villag
Duggirala Mandal
LABOUR CHARGES
UnitSl.No. Description SSR Sl.No.
Page 40 of 87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
41/87
D 4th - Floorper 1 sqm Rs. 2.11 Rs. 24.54 Rs.
Sl.
No.
SSR
Sl. No.Unit Rate
1 3 4 5
1 BMS-W.68 Kg 27.00
2 BMT.J.27 Kg 20.60
3 BMT.J.24 Kg 47.00
4 BMT.J.26 Kg 44.24
5 BMT.J.20 Ltr 40.00
6 BMT.J.21 Kg 81.00
7 BMT.J.05 Ltr 135.00
8 BMT.J.03 Ltr 121.00
9 BMT.J.01 Kg 134.00
10 BMT.J.30 Ltr 230.00
11 BMT.J.22 Ltr 244.00
12 BMT.H.01 Kg 24.00
13 CSSR-A.03 Kg 70.00
14 BMS.W.17 Sqmt. 375.00
15 BMS.W.16 Sqmt. 274.00
16 BMT.C.01 Sqmt. 447.00
17 BMT.C.06 Sqmt. 335.00
18 BMT.B.16 Sqmt. 1008.00
19 BMS.W.20 Sqmt. 925.00
20 BMS.W.21 Sqmt. 530.00
21 BMT.B.05 10Sqmt. 1544.00
22 BMT.B.07 10Sqmt. 3603.00
22 BMT-F.28 Sqmt. 16.00
23 1 No 0.00
24 1 No 0.00
25 1 No 0.00
Oil Bound Distemper POWDER
Red Oxide Primer Paint Grade-I
Mastic Pad 0.60 x 1.20 Mts, 25.4mm thick
Synthetic enamel paint 1st quality (All Shades)
White Glazed Tiles of any Size 1st. Quality
Cement Jally 50mm thick
Wood Primer
Cement Primer Grade - I
Cement Jally 40mm thick
RCC Door Frame size 0.75 X1.98 mt (NK Materials)
Rabbit wire mesh
RCC Window Frame size 0.90 X1.20 mt (NK Materials)
RCC Door Frame size 0.98 X1.98 mt (NK Materials)
Polished kadapa slabs
Mastic Pad 0.60 x 1.20 Mts, 12.7mm thick
Ceramic tiles 7.3mm thick
Vitrified floor tiles 600 x 600 mm normal colour 1 st quality
Cost of binding wire
White Cement
Polished kadapa slabs 25mm thick
Snowcem or Equv. Quality
Water proof Cement Superior Quality
Plastic emulsion paint
Oil Bound Distemper
MATERIAL RATES OF BUILDING ITEMS
Description of Item
Impervious Water proofing compound
Surya Cem or Equivalent Quality
2
Page 41 of 87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
42/87
63.33
86.00
108.68
131.35
6.33
8.60
10.87
13.14
13.19
17.68
22.16
Reapers,
Reapers,
Reapers,
e of
Page 42 of 87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
43/87
26.65
Page 43 of 87
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
44/87
SSR "13-14
Muncipal Allowancwe 0%
Contractor Profit 14%
DISTANCE
TOTAL
RATE
1 Sand for Mortor M-005 Krishna River Cu.m 425.00 3.00 22.81
2 Sand for Filling M-004 Krishna River Cu.m 325.00 3.00 22.81
3 6mm HBG Metal M-050 Lam Cu.m 750.00 50.00 482.51
4 10 mm HBG metal M-051 Lam Cu.m 940.00 50.00 482.51
5 12 mm HBG metal M-052 Lam Cu.m 1095.00 50.00 482.51
6 20 mm HBG metal M-053 Lam Cu.m 1350.00 50.00 482.51
7 40 mm HBG metal M-055 Lam Cu.m 855.00 50.00 482.51
8 FAL-G.block (290x200x140) BMT-A11 Local 1 No 16.00 0.00 3.00
9 FAL-G.block (290x150x140) BMT-A12 Local 1 No 12.00 0.00 3.00
10 FAL-G.block (290x100x140) BMT-A13 Local 1 No 10.00 0.00 3.00
11 2nd class Country brick BMT-A01 Kollipara 1000 No 3707.00 12.00 188.48
12 Cement 0 Local 1kg 5.70 0.00 0.00
13 Water 0 Local KL 0.00 0.00 0.00
14 Steel 0 Local MT 43000.00 0.00 0.00
15 Gravel M-008 Vejandla 1 Cu.m 120.00 37.00 368.50
16 Stone crusher dust M-021 Lam 1 Cum 390.00 50.00 482.51
17 Quarry Rubbish M-148 Vejandla Cu.m 267.00 37.00 368.50
18 Earth(Conveyance only) 0.00
19300 dia. RCC NP2 class Plain ended
i esTenali RM 348.00 25.00 22.60
20 450 dia. RCC NP2 class Plain endedpipes
Tenali RM 611.00 25.00 55.00
21600 dia. RCC NP2 class Plain ended
pipesTenali RM 993.00 25.00 94.20
1300 dia. RCC NP3 class Plain ended
pipesTenali RM 791.00 25.00 54.40
23450 dia. RCC NP3 class Plain ended
pipesTenali RM 1235.00 25.00 82.80
24600 dia. RCC NP3 class Plain ended
i esTenali RM 2019.00 25.00 156.00
Assistant Engineer
APSHCL, Duggirala
LEAD STATEMENT
SI.
No.Description Unit Initial CostSSR Sl.No.
Name of the Work: Construction of Side Drains and CC Roads in Godavarru Village of Duggirala Mandal
Conveyance Charges
FOR BUILDINGS-CCRoads-CCDrains
1. Certified that the above leads are corrcet and best of my knowledge.
Source of Material
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
45/87
SSR "13-14
Muncipal Allowancwe 0%
Contractor Profit 14%
DISTANCE
1 Sand for Mortor M-005 Krishna River Cu.m 425.00 3.00 2
2 Sand for Filling M-004 Krishna River Cu.m 325.00 3.00 2
3 60 to 63 mm IRC and MoRTH HBG metal Lam Cu.m 539.00 50.00 4
4 50 to 55 mm IRC and MoRTH HBG metal Lam Cu.m 576.00 50.00 4
5 40 to 45 mm IRC and MoRTH HBG metal Lam Cu.m 708.00 50.00 4
9 SS Revetment work 300mm Lam Cu.m 276.00 50.00 4
10Quarry spall (Field picked metal) Av. of rate 25mm
& 40mmLam Cu.m 165.00 50.00 4
11 150 mm soling stone HBG metal Lam Cu.m 186.00 50.00 4
12 40 to 45 mm IRC and MoRTH HBG M/C metal Lam Cu.m 855.00 50.00 4
13 25 to 27 mm IRC and MoRTH HBG M/C metal Lam Cu.m 1300.00 50.00 4
14 19 to 22 mm IRC and MoRTH HBG M/C metal Lam Cu.m 1350.00 50.00 4
15 12 to 14 mm IRC and MoRTH HBG M/C metal Lam Cu.m 1095.00 50.00 4
16 9.5 to 11.20 mm IRC and MoRTH HBG M/C metal Lam Cu.m 940.00 50.00 4
17 5 to 7 mm IRC and MoRTH HBG M/C metal Lam Cu.m 750.00 50.00 4
18 2.36 to 5 mm IRC and MoRTH HBG M/C metal Lam Cu.m 505.00 50.00 4
19 HBG Stone chips 2.36mm and below Lam Cu.m 532.50 50.00 4
20 75mm size IRC and Morth HBG metal Lam Cu.m 424.00 50.00 4
21 65mm size IRC and Morth HBG metal Lam Cu.m 499.00 50.00 4
22 FAL-G.block (290x200x140) BMT-A11 Local 1 No 16.00 0.00
23 FAL-G.block (290x150x140) BMT-A12 Local 1 No 12.00 0.00
24 FAL-G.block (290x100x140) BMT-A13 Local 1 No 10.00 0.00
25 2nd class Country brick BMT-A01 Kollipara 1000 No 3707.00 12.00 1
26 Cement 0 Local 1kg 5.70 0.00
27 Water 0 Local KL 0.00 0.00
28 Gravel M-008 Vejandla 1 Cu. 120.00 37.00 3
29 Stone crusher dust M-021 Lam 1 Cum 390.00 50.00 4
30 Mild steel Local ton 4300031 Bitumen Vishakhapatnam 1mt 35829.93 900.00 13
APSHCL, Duggirala
Name of the Work: Construction of Side Drains and CC Roads in Godavarru Village of Duggirala Mandal
FOR ROADS & Levelling Works
Conveyance Cha
Source of Material
Conveyance of Bitumen for Bulk and packed Rs.1.50 KM/MT
1. Certified that the above leads are corrcet and best of my knowledge.
Unit Initial CostSI.
No. Description SSR Sl.No.
LEAD STATEMENT
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
46/87
Seigniorage charges 50.00
Sl.
NoDescription of Metal
Initial cost
Including
stacking
Blasting
charges
A) FOR ROAD WORKS 70.00
1 60 to 63 mm IRC and MoRTH HBG metal 419.00 70.00
2 50 to 55 mm IRC and MoRTH HBG metal 456.00 70.00
3 40 to 45 mm IRC and MoRTH HBG metal 588.00 70.00
4 SS Revetment work 300mm 156.00 70.00
5
Quarry spall (Field picked metal) Av. of rate 25mm
& 40mm 45.00 70.00
6 150 mm soling stone HBG metal 66.00 70.00
4 40 to 45 mm IRC and MoRTH HBG M/C metal 588.00 70.00
5 25 to 27 mm IRC and MoRTH HBG M/C metal 944.00 70.00
6 19 to 22 mm IRC and MoRTH HBG M/C metal 984.00 70.00
7 12 to 14 mm IRC and MoRTH HBG M/C metal 780.00 70.00
9 9.5 to 11.20 mm IRC and MoRTH HBG M/C metal 656.00 70.00
10 5 to 7 mm IRC and MoRTH HBG M/C metal 504.00 70.00
11 2.36 to 5 mm IRC and MoRTH HBG M/C metal 308.00 70.00
12 HBG Stone chips 2.36mm and below 330.00 70.00
13 75mm size IRC and Morth HBG metal 304.00 70.00
13 65mm size IRC and Morth HBG metal 379.00 70.00
ROAD METAL RATES
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
47/87
Machine
crushing
charges
Seigniorage
charges
Deduct
stacking
charges for
conveyance
Toal Cost per
Cum
25%
0.00 50.00 0.00 539.00
0.00 50.00 0.00 576.00
0.00 50.00 0.00 708.00
0.00 50.00 0.00 276.00
0.00 50.00 0.00 165.00
0.00 50.00 0.00 186.00
147.00 50.00 0.00 855.00
236.00 50.00 0.00 1300.00
246.00 50.00 0.00 1350.00
195.00 50.00 0.00 1095.00
164.00 50.00 0.00 940.00
126.00 50.00 0.00 750.00
77.00 50.00 0.00 505.00
82.50 50.00 0.00 532.50
0.00 50.00 0.00 424.00
0.00 50.00 0.00 499.00
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
48/87
Hire
Charges
Fuel
Charges
Crew
Charges
Total Per
a) 456.20 280.70 140.40 877.30 Hour
b) 422.80 280.70 140.40 843.90 Hour
c) 411.00 280.70 140.40 832.10 Hour
d) 422.80 280.70 140.40 843.90 Hour
e) 422.80 280.70 140.40 843.90 Hour
f) 120.30 114.10 269.50 503.90 Hour
g) 7.80 19.00 125.40 152.20 Hour
g) 54.60 74.30 174.20 303.10 Hour
2754.50 Hour
877.30 Hour
3216.00 Hour
2541.40 Hour
624.00 Hour
357.00 Hour
860.00 Hour
19120.00 Hour
1320.00 Hour
1646.00 Hour2249.00 Hour
1283.00 Hour
209.00 Hour
417.40 Hour
499.40 Hour
422.00 Hour
1704.60 Hour
1 Minci al area allowance 0.00%
2 Industrial area allowance 0.00%
3 Agency area allowance 0.00%
4 Allowable allowance 0.00%5 Add Overhead Charges & Contractor's Profit 0.00%
A)
1 Lead up to 1 Km:
Out put = 5.00 Cum Rate Per Amount
0.15 456.20 Hour Rs. 68.43
0.15 280.70 Hour Rs. 42.11
0.15 140.40 Hour Rs. 21.06
0.00 21.06 Rs. 0.00
Rate fo 5.00 Cum Rs. 131.60
Rate fo 1.00 Cum Rs. 26.32
Hire Charges Roads & Irrigation Works Machinery
Water tanker 6KL capacity
Emulson Pressure Distributor
Hot mix plant 40 to 60 TPH Capacity
Hydraulic Excavator
Three wheel 80-100 kN Static Roller
Paver finisher Mechanical 100 TPH
Batching plant 0.5 cum
Needle vibrator 40mm
(petrol)
Electric Generator 125 KVA
Concrete mixer 300/200
(diesel) SSR hire charges
Pg.no.325, Sl. No.16
Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
Vibratory roller 8 tonnes
Mechanical Broom Hydraulic
Tractor with ripper attachment
Front End loader
Concrete Mixer 0.28 Cum
Motar Grader
Air Compressor
Bitumen boiler oil fired (Bitumen Spraying)
LEAD, LOADING & UNLOADING STATEMENT
RATES FOR CONVEYANCE BY MACHINERY
For Earth/Gravel/Sand/Morrum/Lime/Surki (per Cum):
Hrs. hire charges of Tipper 5.00 Cum @ Rs.
Penumatic Road Roller (Static Roller
Tipper 5.5 Cum
HIRE CHARGES OF MACHINERY
Hire charges of Tipper 5.00
Cum capacity
Hire charges of Tipper 10
Tonnes capacity
Hire charges of Water Tanker
8000 Ltrs capacity
Hire charges of Truck 10
Tonnes capacity
Hire charges of FE loader
1.00 Cum bucket capacity @
45 Cum
Hrs. crew charges of Tipper 5.00 Cum @ Rs.
add area allowance at 0% on Rs.
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
49/87
0.00 26.32 Rs. 0.00
Total rate for 1.00 Cum Rs. 26.32
2 Lead up to 2 Km:
Out ut = 5.00 Cum Rate Per Amount
0.21 456.20 Hour Rs. 95.80
0.21 280.70 Hour Rs. 58.95
0.21 140.40 Hour Rs. 29.48
0.00 29.48 Rs. 0.00
Rate fo 5.00 Cum Rs. 184.23Rate fo 1.00 Cum Rs. 36.85
0.00 36.85 Hour Rs. 0.00
Total rate for 1.00 Cum Rs. 36.85
3 Lead up to 3 Km:
Out put = 5.00 Cum Rate Per Amount
0.28 456.20 Hour Rs. 127.74
0.28 280.70 Hour Rs. 78.60
0.28 140.40 Hour Rs. 39.31
0.00 39.31 Rs. 0.00
Rate fo 5.00 Cum Rs. 245.65
Rate fo 1.00 Cum Rs. 49.13
0.00 49.13 Hour Rs. 0.00
Total rate for 1.00 Cum Rs. 49.13
4 Lead up to 4 Km:
Out put = 5.00 Cum Rate Per Amount
0.34 456.20 Hour Rs. 155.11
0.34 280.70 Hour Rs. 95.44
0.34 140.40 Hour Rs. 47.74
0.00 47.74 Rs. 0.00
Rate fo 5.00 Cum Rs. 298.29Rate fo 1.00 Cum Rs. 59.66
0.00 59.66 Hour Rs. 0.00
Total rate for 1.00 Cum Rs. 59.66
5 Lead up to 5 Km:
Out ut = 5.00 Cum Rate Per Amount
0.40 456.20 Hour Rs. 182.48
0.40 280.70 Hour Rs. 112.28
0.40 140.40 Hour Rs. 56.16
0.00 56.16 Rs. 0.00
Rate fo 5.00 Cum Rs. 350.92
Rate fo 1.00 Cum Rs. 70.180.00 70.18 Hour Rs. 0.00
Total rate for 1.00 Cum Rs. 70.18
6 Lead for every Km from 5 to 30 Km:
Out put = 5.00 Cum Rate Per Amount
0.06 456.20 Hour Rs. 27.37
0.06 280.70 Hour Rs. 16.84
0.06 140.40 Hour Rs. 8.42
0.00 8.42 Rs. 0.00
Rate fo 5.00 Cum Rs. 52.63
add area allowance at 0% on Rs.
add overheads and contractors profit at 0%
on Rs.
Hrs. hire charges of Tipper 5.00 Cum @ Rs.
Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
Hrs. crew charges of Tipper 5.00 Cum @ Rs.
Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
Hrs. crew charges of Tipper 5.00 Cum @ Rs.
add area allowance at 0% on Rs.
add overheads and contractors profit at 0%
on Rs.
Hrs. hire charges of Tipper 5.00 Cum @ Rs.
Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
Hrs. crew charges of Tipper 5.00 Cum @ Rs.
add area allowance at 0% on Rs.
add overheads and contractors profit at 0%
on Rs.
add area allowance at 0% on Rs.
Hrs. crew charges of Tipper 5.00 Cum @ Rs.
add area allowance at 0% on Rs.
add overheads and contractors profit at 0%
on Rs.
Hrs. hire charges of Tipper 5.00 Cum @ Rs.
add overheads and contractors profit at 0%
on Rs.
Hrs. hire charges of Tipper 5.00 Cum @ Rs.
Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
Hrs. crew charges of Tipper 5.00 Cum @ Rs.
Hrs. hire charges of Tipper 5.00 Cum @ Rs.
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
50/87
Rate fo 1.00 Cum Rs. 10.53
0.00 10.53 Hour Rs. 0.00
Total rate for 1.00 Cum Rs. 10.53
7 Lead for every Km beyond 30 Km:
Out put = 5.00 Cum Rate Per Amount
0.05 456.20 Hour Rs. 22.81
0.05 280.70 Hour Rs. 14.04
0.05 140.40 Hour Rs. 7.02
0.00 7.02 Rs. 0.00
Rate fo 5.00 Cum Rs. 43.87
Rate fo 1.00 Cum Rs. 8.77
0.00 8.77 Rs. 0.00
Total rate for 1.00 Cum Rs. 8.77
B)
1 Lead u to 1 Km:
Out put = 5.00 Cum Rate Per Amount
0.15 456.20 Hour Rs. 68.43
0.15 280.70 Hour Rs. 42.11
0.15 140.40 Hour Rs. 21.060.00 21.06 Rs. 0.00
Rate fo 5.00 Cum Rs. 131.60
Rate fo 1.00 Cum Rs. 26.32
0.00 26.32 Rs. 0.00
Total rate for 1.00 Cum Rs. 26.32
2 Lead up to 2 Km:
Out put = 5.00 Cum Rate Per Amount
0.21 456.20 Hour Rs. 95.80
0.21 280.70 Hour Rs. 58.95
0.21 140.40 Hour Rs. 29.48
0.00 29.48 Rs. 0.00
Rate fo 5.00 Cum Rs. 184.23Rate fo 1.00 Cum Rs. 36.85
0.00 36.85 Hour Rs. 0.00
Total rate for 1.00 Cum Rs. 36.85
3 Lead u to 3 Km:
Out put = 5.00 Cum Rate Per Amount
0.28 456.20 Hour Rs. 127.74
0.28 280.70 Hour Rs. 78.60
0.28 140.40 Hour Rs. 39.31
0.00 39.31 Rs. 0.00
Rate fo 5.00 Cum Rs. 245.65
Rate fo 1.00 Cum Rs. 49.130.00 49.13 Hour Rs. 0.00
Total rate for 1.00 Cum Rs. 49.13
4 Lead up to 4 Km:
Out put = 5.00 Cum Rate Per Amount
0.34 456.20 Hour Rs. 155.11
0.34 280.70 Hour Rs. 95.44
0.34 140.40 Hour Rs. 47.74
0.00 47.74 Rs. 0.00
Rate fo 5.00 Cum Rs. 298.29
add area allowance at 0% on Rs.
Hrs. crew charges of Tipper 5.00 Cum @ Rs.
add area allowance at 0% on Rs.
Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
add overheads and contractors profit at 0%
on Rs.
Hrs. hire charges of Tipper 5.00 Cum @ Rs.
Hrs. hire charges of Tipper 5.00 Cum @ Rs.
Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
Hrs. crew charges of Tipper 5.00 Cum @ Rs.
add overheads and contractors profit at 0%
on Rs.
Hrs. hire charges of Tipper 5.00 Cum @ Rs.
add area allowance at 0% on Rs.
Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
add overheads and contractors profit at 0%
on Rs.
Hrs. crew charges of Tipper 5.00 Cum @ Rs.
Hrs. crew charges of Tipper 5.00 Cum @ Rs.
Hrs. hire charges of Tipper 5.00 Cum @ Rs.
add overheads and contractors profit at 0%
on Rs.
Hrs. hire charges of Tipper 5.00 Cum @ Rs.
Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
Hrs. crew charges of Tipper 5.00 Cum @ Rs.add area allowance at 0% on Rs.
add area allowance at 0% on Rs.
add overheads and contractors profit at 0%
on Rs.
For Rubble/Size stones/Cut stones/Coarse aggregates (per Cum):
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
51/87
Rate fo 1.00 Cum Rs. 59.66
0.00 59.66 Hour Rs. 0.00
Total rate for 1.00 Cum Rs. 59.66
5 Lead up to 5 Km:
Out put = 5.00 Cum Rate Per Amount
0.40 456.20 Hour Rs. 182.48
0.40 280.70 Hour Rs. 112.28
0.40 140.40 Hour Rs. 56.16
0.00 56.16 Rs. 0.00
Rate fo 5.00 Cum Rs. 350.92
Rate fo 1.00 Cum Rs. 70.18
0.00 70.18 Hour Rs. 0.00
Total rate for 1.00 Cum Rs. 70.18
6 Lead for every Km from 5 to 30 Km:
Out put = 5.00 Cum Rate Per Amount
0.06 456.20 Hour Rs. 27.37
0.06 280.70 Hour Rs. 16.84
0.06 140.40 Hour Rs. 8.42
0.00 8.42 Rs. 0.00Rate fo 5.00 Cum Rs. 52.63
Rate fo 1.00 Cum Rs. 10.53
0.00 10.53 Hour Rs. 0.00
Total rate for 1.00 Cum Rs. 10.53
7 Lead for every Km beyond 30 Km:
Out ut = 5.00 Cum Rate Per Amount
0.05 456.20 Hour Rs. 22.81
0.05 280.70 Hour Rs. 14.04
0.05 140.40 Hour Rs. 7.02
0.00 7.02 Rs. 0.00
Rate fo 5.00 Cum Rs. 43.87Rate fo 1.00 Cum Rs. 8.77
0.00 8.77 Rs. 0.00
Total rate for 1.00 Cum Rs. 8.77
F)
1 Lead up to 1 Km:
Out put = 3000 Nos Rate Per Amount
0.15 422.80 Hour Rs. 63.42
0.15 280.70 Hour Rs. 42.11
0.15 140.40 Hour Rs. 21.06
0.00 21.06 Rs. 0.00
Rate fo 3000 Nos Rs. 126.59
Rate fo 1000 Nos Rs. 42.20
0.00 42.20 Rs. 0.00
Total rate for 1000 Nos Rs. 42.20
2 Lead up to 2 Km:
Out put = 3000 Nos Rate Per Amount
0.21 422.80 Hour Rs. 88.79
add overheads and contractors profit at 0%
on Rs.
add overheads and contractors profit at 0%
on Rs.
Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
Hrs. hire charges of Tipper 5.00 Cum @ Rs.
For Bricks (per 1000 Nos):
Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
Hrs. crew charges of Tipper 5.00 Cum @ Rs.
Hrs. hire charges of Truck 10 Tonnes capacity
@ Rs.
add area allowance at 0% on Rs.
add overheads and contractors profit at 0%
on Rs.
Hrs. hire charges of Truck 10 Tonnes capacity
@ Rs.
Hrs. fuel charges of Truck 10 Tonnes capacity
@ Rs.
Hrs. crew charges of Truck 10 Tonnescapacity @ Rs.
add area allowance at 0% on Rs.
Hrs. crew charges of Tipper 5.00 Cum @ Rs.
add area allowance at 0% on Rs.
Hrs. crew charges of Tipper 5.00 Cum @ Rs.
add area allowance at 0% on Rs.
Hrs. hire charges of Tipper 5.00 Cum @ Rs.
add overheads and contractors profit at 0%
on Rs.
add overheads and contractors profit at 0%
on Rs.
Hrs. hire charges of Tipper 5.00 Cum @ Rs.
Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
52/87
0.21 280.70 Hour Rs. 58.95
0.21 140.40 Hour Rs. 29.48
0.00 29.48 Rs. 0.00
Rate fo 3000 Nos Rs. 177.22
Rate fo 1000 Nos Rs. 59.07
0.00 59.07 Rs. 0.00
Total rate for 1000 Nos Rs. 59.07
3 Lead up to 3 Km:
Out put = 3000 Nos Rate Per Amount
0.28 422.80 Hour Rs. 118.38
0.28 280.70 Hour Rs. 78.60
0.28 140.40 Hour Rs. 39.31
0.00 39.31 Rs. 0.00
Rate fo 3000 Nos Rs. 236.29
Rate fo 1000 Nos Rs. 78.76
0.00 78.76 Rs. 0.00
Total rate for 1000 Nos Rs. 78.76
Hrs. fuel charges of Truck 10 Tonnes capacity
@ Rs.
add overheads and contractors profit at 0%
on Rs.
Hrs. fuel charges of Truck 10 Tonnes capacity
@ Rs.
Hrs. crew charges of Truck 10 Tonnes
capacity @ Rs.
Hrs. crew charges of Truck 10 Tonnes
capacity @ Rs.
add area allowance at 0% on Rs.
add area allowance at 0% on Rs.
add overheads and contractors profit at 0%
on Rs.
Hrs. hire charges of Truck 10 Tonnes capacity
@ Rs.
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
53/87
4 Lead up to 4 Km:
Out put = 3000 Nos Rate Per Amount
0.34 422.80 Hour Rs. 143.75
0.34 280.70 Hour Rs. 95.44
0.34 140.40 Hour Rs. 47.74
0.00 47.74 Rs. 0.00Rate fo 3000 Nos Rs. 286.93
Rate fo 1000 Nos Rs. 95.64
0.00 95.64 Rs. 0.00
Total rate for 1000 Nos Rs. 95.64
5 Lead up to 5 Km:
Out put = 3000 Nos Rate Per Amount
0.40 422.80 Hour Rs. 169.12
0.40 280.70 Hour Rs. 112.28
0.40 140.40 Hour Rs. 56.16
0.00 56.16 Rs. 0.00
Rate fo 3000 Nos Rs. 337.56
Rate fo 1000 Nos Rs. 112.52
0.00 112.52 Rs. 0.00
Total rate for 1000 Nos Rs. 112.52
6 Lead for every Km beyond 5 Kms up to 30 Kms:
Out ut = 3000 Nos Rate Per Amount
0.06 422.80 Hour Rs. 25.37
0.06 280.70 Hour Rs. 16.84
0.06 140.40 Hour Rs. 8.42
0.00 8.42 Rs. 0.00
Rate fo 3000 Nos Rs. 50.63
Rate fo 1000 Nos Rs. 16.88
0.00 16.88 Rs. 0.00
Total rate for 1000 Nos Rs. 16.88
7 Lead for ever Km be ond 30 Kms:
Out put = 3000 Nos Rate Per Amount
0.05 422.80 Hour Rs. 21.14
0.05 280.70 Hour Rs. 14.04
0.05 140.40 Hour Rs. 7.02
0.00 7.02 Rs. 0.00
Rate fo 3000 Nos Rs. 42.20
Rate fo 1000 Nos Rs. 14.07
0.00 14.07 Rs. 0.00
Total rate for 1000 Nos Rs. 14.07
add area allowance at 0% on Rs.
add overheads and contractors profit at 0%
on Rs.
Hrs. hire charges of Truck 10 Tonnes capacity
@ Rs.Hrs. fuel charges of Truck 10 Tonnes capacity
@ Rs.
add overheads and contractors profit at 0%
on Rs.
add area allowance at 0% on Rs.
add overheads and contractors profit at 0%
on Rs.
Hrs. hire charges of Truck 10 Tonnes capacity
@ Rs.
Hrs. crew charges of Truck 10 Tonnes
capacity @ Rs.
add area allowance at 0% on Rs.
Hrs. fuel charges of Truck 10 Tonnes capacity
@ Rs.
Hrs. crew charges of Truck 10 Tonnes
capacity @ Rs.
Hrs. fuel charges of Truck 10 Tonnes capacity
@ Rs.
Hrs. crew charges of Truck 10 Tonnescapacity @ Rs.
add area allowance at 0% on Rs.
add overheads and contractors profit at 0%
on Rs.
Hrs. hire charges of Truck 10 Tonnes capacity
@ Rs.
Hrs. fuel charges of Truck 10 Tonnes capacity
@ Rs.
Hrs. crew charges of Truck 10 Tonnes
capacity @ Rs.
Hrs. hire charges of Truck 10 Tonnes capacity
@ Rs.
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
54/87
A)
(i) Loading charges:
Out put = 5.50 Cum Rate Per Amount
a) Labour:
0.01 320.00 day Rs. 3.20
0.25 280.00 da Rs. 70.00
Rs. 73.200.00 73.20 Rs. 0.00
Total labour charges Rs. 73.20
Rate fo 5.50 Cum Rs. 73.20
Rate fo 1.00 Cum Rs. 13.31
0.00 13.31 Rs. 0.00
Total rate for 1.00 Cum Rs. 13.31
ii Unloadin char es:
Out ut = 5.50 Cum Rate Per Amount
a) Labour:
0.005 320.00 day Rs. 1.60
0.125 280.00 day Rs. 35.00
Rs. 36.60
0.00 36.60 Rs. 0.00
Total labour charges Rs. 36.60
Rate fo 5.50 Cum Rs. 36.60
Rate fo 1.00 Cum Rs. 6.65
0.00 6.65 Rs. 0.00
Total rate for 1.00 Cum Rs. 6.65
B)
(i) Loading charges:
Out put = 5.50 Cum Rate Per Amount
a) Labour:0.02 320.00 day Rs. 6.40
0.50 280.00 da Rs. 140.00
Rs. 146.40
0.00 146.40 Rs. 0.00
Total labour charges Rs. 146.40
Rate fo 5.50 Cum Rs. 146.40
Rate fo 1.00 Cum Rs. 26.62
0.00 26.62 Rs. 0.00
Total rate for 1.00 Cum Rs. 26.62
ii Unloadin char es:
Out put = 5.50 Cum Rate Per Amounta) Labour:
0.01 320.00 day Rs. 3.20
0.25 280.00 day Rs. 70.00
Rs. 73.20
0.00 73.20 Rs. 0.00
Total labour charges Rs. 73.20
Rate fo 5.50 Cum Rs. 73.20
Rate fo 1.00 Cum Rs. 13.31
0.00 13.31 Rs. 0.00
Total rate for 1.00 Cum Rs. 13.31
add overheads and contractors profit at 0%
on Rs.
day Head mazdoor
day Mazdoor
add overheads and contractors profit at 0%
on Rs.
add area allowance at 0% on Rs.
add overheads and contractors profit at 0%
on Rs.
day Mazdoor
day Head mazdoor
day Head mazdoor
add area allowance at 0% on Rs.
day Mazdoor
add area allowance at 0% on Rs.
add overheads and contractors profit at 0%
on Rs.
For Lime, Agrregate, Stone Boulder, Brick aggregate, Kankar, Building rubbish,
Crushed slag, Stone for masonry work (per Cum):
add area allowance at 0% on Rs.
LOADING & UNLOADING CHARGES BY MANUAL MEANS (EXCLUDING IDLE HIRE
CHARGES OF TRUCKS)
For Earth, Sand, Morrum, Manure, Fly Ash (per Cum):
day Head mazdoor
day Mazdoor
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
55/87
C)
(i) Loading charges:
Out put = 10.00 MT Rate Per Amount
a Labour:
0.06 320.00 day Rs. 19.20
1.50 280.00 day Rs. 420.00
Rs. 439.20
0.00 439.20 Rs. 0.00
Total labour char es Rs. 439.20
Rate fo 10.00 MT Rs. 439.20
Rate fo 1.00 MT Rs. 43.92
0.00 43.92 Rs. 0.00
Total rate for 1.00 MT Rs. 43.92
(ii) Unloading & Stacking charges:
Out put = 10.00 MT Rate Per Amount
a Labour:
0.06 320.00 day Rs. 19.20
1.50 280.00 day Rs. 420.00
Rs. 439.20
0.00 439.20 Rs. 0.00
Total labour charges Rs. 439.20
Rate fo 10.00 MT Rs. 439.20
Rate fo 1.00 MT Rs. 43.92
0.00 43.92 Rs. 0.00
Total rate for 1.00 MT Rs. 43.92
D)
i Loadin char es:
Out put = 10.00 MT Rate Per Amount
a) Labour:
0.07 320.00 day Rs. 22.40
1.80 280.00 day Rs. 504.00
Rs. 526.40
0.00 526.40 Rs. 0.00
Total labour charges Rs. 526.40
Rate fo 10.00 MT Rs. 526.40
Rate fo 1.00 MT Rs. 52.64
0.00 52.64 Rs. 0.00
Total rate for 1.00 MT Rs. 52.64
(ii) Unloading & Stacking charges:
Out ut = 10.00 MT Rate Per Amount
a) Labour:0.07 320.00 day Rs. 22.40
1.80 280.00 day Rs. 504.00
Rs. 526.40
0.00 526.40 Rs. 0.00
Total labour charges Rs. 526.40
Rate fo 10.00 MT Rs. 526.40
Rate fo 1.00 MT Rs. 52.64
0.00 52.64 Rs. 0.00
Total rate for 1.00 MT Rs. 52.64
day Mazdoor
add area allowance at 0% on Rs.
add overheads and contractors profit at 0%
on Rs.
day Head mazdoor
day Mazdoor
add area allowance at 0% on Rs.
add overheads and contractors profit at 0%
on Rs.
add overheads and contractors profit at 0%
on Rs.
day Head mazdoor
day Mazdoor
add area allowance at 0% on Rs.
add overheads and contractors profit at 0%
on Rs.
For Structural steel, Steel bars (per Tonne):
day Head mazdoor
add area allowance at 0% on Rs.
For Cement (per Tonne):
day Head mazdoor
day Mazdoor
-
8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013
56/87
E)
(i) Loading charges:
Out put = 2000.00 Nos Rate Per Amount
a) Labour:
0.01 320.00 da Rs. 3.20
0.25 280.00 day Rs. 70.00
Rs. 73.20
0.00 73.20 Rs. 0.00
Total labour charges Rs. 73.20
Rate fo 2000 Nos Rs. 73.20
Rate fo 1000 Nos Rs. 36.60
0.00 36.60 Rs. 0.00
Total rate for 1000 Nos Rs. 36.60
(ii) Unloading & Stacking charges:
Out put = 2000.00 Nos Rate Per Amount
a) Labour:
0.01 320.00 day Rs. 3.20
0.25 280.00 day Rs. 70.00
Rs. 73.20
0.00 73.20 Rs. 0.00
Total labour charges Rs. 73.20
Rate fo 2000 Nos Rs. 73.20
Rate fo 1000 Nos Rs. 36.60
0.00 36.60 Rs. 0.00
Total rate for 1000 Nos Rs. 36.60
A)
(i) Loading charges:
Out put = 5.50 Cum Rate Per Amounta Labour:
0.01 320.00 day Rs. 3.20
0.25 280.00 day Rs. 70.00
Rs. 73.20
0.00 73.20 Rs. 0.00
Total labour char es Rs. 73.20
b) Machinery:
0.50 422.80 Hour Rs. 211.40
0.50 280.70 Hour Rs. 140.35
0.50 140.40 Hour Rs. 70.20
0.00 70.20 Rs. 0.00
Total machiner char es Rs. 421.95
Total labour and machinery charges Rs. 495.15
Rate fo 5.50 Cum Rs. 495.15
Rate fo 1.00 Cum Rs. 90.03
0.00 90.03 Rs. 0.00
Total rate for 1.00 Cum Rs. 90.03
add area allowance at 0% on Rs.
Hrs. crew charges of Truck 10 Tonnes
capacity @ Rs.add area allowance at 0% on Rs.
day Mazdoor
add area allowance at 0% on Rs.
add overheads and contractors profit at 0%