godavarru works with ssr 2013-14 revised specification 16-12-2013

Upload: kandepigopi

Post on 04-Jun-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    1/87

    Mandal : Duggirala

    Estimate Cost Rs. 77.00 Lakhs

    Construction of CC Drains and CC Roads in Godavarru

    village of Duggirala Mandal

    Estimate

    Name of the work

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    2/87

    Name of the Work: Construction of Side Drains and CC Roads in Godavarru Village of Duggirala Mandal

    CROSS SECTION OF DRAIN & Road

    70 cm Gravel Shoulders

    Concrete pavement 200 mm

    Gravel Shoulders

    20 cm 20 cm Granular Sub base 75 mm

    Grading 2nd layer 75 mm

    20 cm Grading 1st layer 75 mm

    45 cm

    G L 0.306.900

    60 cm Length of Road 1 90Length of Road 2 90

    10 cm 10 CM 10 cm Length of Road 3 90

    Length of Road 4 90

    Sand Filling -15 cm Length of Road 5 85

    Length of Road 6 81

    Length of Road 7 85

    35

    646

    for 6.00 Mtrs WIDTH ROAD

    90 cm Main Road from 6th to

    V

    CC1

    :3:6

    V

    CC1

    :3:6

    PCC 1:5:10 - 10 cm

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    3/87

    Est.Rs. 41.00 Lakhs

    Assistant Engineer Deputy Executive Engineer Executive Engineer

    APSHCL, Duggirala APSHCL, Mangalagiri APSHCL, Guntur

    Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement concrete pavement,

    thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30

    (Grade) design mix, coarse and fine aggregates conforming to IS : 383, maximum in a concrete mixer of not less than

    0.2 cum capacity and appropeiate weigh batcher using approved mix design, laid in approved fixed side formwork (steel

    channel, laying and fixing of 125 mictron thick polythene film, wedges, steel plates including levelling the formwork as

    per drawing), spreading the concrete with sholvels, rakes, compacted using needle, scareed and plate vibrators and

    finished in continuous operation including provision of contraction and expansion, construction joints, applying

    debonding strips, primer, sealant, dowel bars, near approaches to bridge / culvert and construction joints, admixtures as

    approved, curing of concrete slabs for 14- days, curing compound (where specified) and water finishing to lines and

    grade as per drawing and Technical Specification Clause 1501 MORD of un-reinforced plain cement concretepavement M30 (Grade design mix ) to thick ness of 200 mm is proposed

    Construction of Gravel Base / shoulders including cost, seigniorage charges and conveyance of all

    materials to work site and spreading in uniform layers by approved means, on prepared surface and

    compacting with vibratory roller to achieve the desired density at OMC etc., complete for finished item of

    work as per MoRT&H Specification 401& 407 (4th revision) and as directed by the Engineer-in-charge.

    Gravel shoulders on both sides of the road and proposed required CD works

    Necessary provisions are also made for Joint filler board, VAT @ 5%, Q.C charges @ 2.50 % ,Labour cess

    @ 1.00 %, Ps Charges 7.50 % , Etc.

    The detailed estimate is prepared with current schedule of rates (ie 2013-14 ) and the work will be carried

    out as per APDSS

    Specification report to accompany the Detailed estimate for the work

    The above work was proposed for sanction under under indiramma Infrastructure funds in Indiramma

    Layouts where SC/STs are more than 90%. Hence detailed estimate is prepared with the following

    provisions.

    Removal of Unserviceable soil including excavation, loading and disposal upto 1000 m lead but excluding

    compaction ground supporting embankment subgrade replacement by suitable soil, which shall be paid

    separately as per Clause 303.5.2 as per Technical Specification Clause 302.3.11 MORD / 301 MORTH is

    proposed to a depth of 75 mm

    Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam

    specification including spreading in uniform thickness, hand packing, rolling with three wheel 80 -100 kN

    static roller in stages to proper grade and camber, applying and brooming, stone screening/binding

    materials to fill-up the interstices of coarse aggregate, watering and compacting to the required density

    Grading 1 as per Technical Specification Clause 404 (WBM Grading 2nd Layer to a compacted thickness

    of 75mm ) for providing two grading layers of each 75 mm thick

    Name of the Work: Construction of CC Roads in Godavarru Village of Duggirala Mandal

    Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with

    motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compactingwith vibratory roller to achieve the desired density, complete as per clause 402 MORTH Grading C

    (Granular Sub-Base with Coarse Graded Material (Table:- 400- 2)) of granular sub-base is proposed to

    thick ness of 75 mm

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    4/87

    Estimate Cost : Rs 7700000.00

    S.No Description of Item Amount

    1 Construction of CC Road (Sub Estimate) 3328378.00

    2 Construction of Drain (Sub Estimate) 2920009.00

    Sub Total (1+2) 6248387.00

    4 Provision for PS Charges 7.5% 468629.00

    5 Provision for VAT at 5% 312419.00

    6 Provision for 3rd Party Quality control @2.5% 156209.00

    7 Provision for labour cess 1% 62484.00

    8 Provision for Tender premium at 5.00% 312419.00

    10 Unforceen Items 139453.00

    Grand Total:- Rs 7700000.00

    Assistant Engineer Deputy Executive Engineer

    APSHCL, Duggirala APSHCL, Mangalagiri

    Executive Engineer

    APSHCL, Guntur

    GENERAL ABSTRACT

    Name of the Work: Construction of Side Drains and CC Roads in Godavarru Village of

    Duggirala Mandal

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    5/87

    Estimate cost Rs. 41.00 lakhs

    SNo. Description of Item Nos. L B D Qty. Rate per Total value

    1

    Cross Roads 6 54.00 3.60 0.075 87.48

    Cross Roads 5 40.00 3.60 0.075 54.00

    141.48 74.92 10600.00

    Cu.m 1 cu.m

    2

    Grading 1st Layer

    Cross Roads 6 54.00 3.30 0.075 80.19

    Cross Roads 5 40.00 3.30 0.075 49.50

    129.69 2642.00 342641.00

    Cu.m 1 Cum

    3

    Grading 2 Layer

    Cross Roads 6 54.00 3.30 0.075 80.19

    Cross Roads 5 40.00 3.30 0.075 49.50

    129.69 2642.00 342641.00

    Cu.m 1 Cum

    4

    Sub Base

    Cross Roads 6 54.00 3.30 0.075 80.19

    Cross Roads 5 40.00 3.30 0.075 49.50

    129.69 1929.79 250274.00

    Cu.m 1 cu.m

    Providing, laying, spreading and compacting stone aggregates of specific sizes

    to water bound macadam specification including spreading in uniform

    thickness, hand packing, rolling with three wheel 80 -100 kN static roller in

    stages to proper grade and camber, applying and brooming, stone

    screening/binding materials to fill-up the interstices of coarse aggregate,

    watering and compacting to the required density Grading 1 as per Technical

    Specification Clause 404 (WBM Grading 2nd Layer to a compacted

    thickness of 75mm )

    DETAILED CUM ABSTRACT ESTIMATE

    Name of the Work: Construction of CC Roads in Godavarru Village of Duggirala Mandal

    Removal of Unserviceable soil including excavation, loading and disposal upto

    1000 m lead but excluding compaction ground supporting embankment

    subgrade replacement by suitable soil, which shall be paid separately as per

    Clause 303.5.2 as per Technical Specification Clause 302.3.11 MORD / 301

    MORTH

    Providing, laying, spreading and compacting stone aggregates of specific sizes

    to water bound macadam specification including spreading in uniform

    thickness, hand packing, rolling with three wheel 80 -100 kN static roller in

    stages to proper grade and camber, applying and brooming, stone

    screening/binding materials to fill-up the interstices of coarse aggregate,

    watering and compacting to the required density Grading 1 as per TechnicalSpecification Clause 404 (WBM Grading 2nd Layer to a compacted

    thickness of 75mm )

    Construction of granular sub-base by providing coarse graded material,

    spreading in uniform layers with motor grader on prepared surface, mixing by

    mix in place method with rotavator at OMC, and compacting with vibratory

    roller to achieve the desired density, complete as per clause 402 MORTH

    Grading C (Granular Sub-Base with Coarse Graded Material (Table:- 400- 2))

    5 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    6/87

    SNo. Description of Item Nos. L B D Qty. Rate per Total value

    5

    Cross Roads 6 54.00 3.30 0.20 213.84

    Cross Roads 5 40.00 3.30 0.20 132.00

    345.84 6021.92 2082621.00

    Cu.m 1 cu.m

    6

    For shoulders both side

    Cross Roads 6 2 54.00 0.75 0.20 97.20

    Cross Roads 5 2 40.00 0.75 0.20 60.00

    157.20 742.60 116737.00

    Cu.m 1 cu.m

    7

    for Cross Roads 2 11 2.50 55.00for Cross Roads 2 11 2.50 55.00

    110.00 1555.50 171105.00

    8

    for Cross Roads 2 11 2.50 55.00

    for Cross Roads 2 11 2.50 55.00

    110.00 106.90 11759.00

    Total Estamate 3328378.00

    Provision for PS Charges 7.5% 249628.00

    Provision for VAT at 5% 166419.00

    Provision for 3rd Party Quality control @2.5% 83209.00

    Provision for labour cess 1% 33284.00Provision for Tender premium at 5.00% 166419.00

    Unforceen Items 72663.00

    Total 4100000.00

    Assistant Engineer Deputy Executive Engineer Executive Engineer

    APSHCL, Duggirala APSHCL, Mangalagiri APSHCL, Guntur

    Supply and delivery of RCC NP3 pipes of 450 mm dia including collars and

    conveyance charges etc, complete

    Laying and fixing of RCC NP3 pipes of 450 mm dia including all labour

    charges etc, complete

    Construction of un-reinforced, dowel jointed at expansion and construction joint only,

    plain cement concrete pavement, thickness as per design, over a prepared sub base, with

    43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade) design mix ,

    coarse and fine aggregates conforming to IS : 383, maximum in a concrete mixer of not

    less than 0.2 cum capacity and appropeiate weigh batcher using approved mix design,

    laid in approved fixed side formwork (steel channel, laying and fixing of 125 mictron

    thick polythene film, wedges, steel plates including levelling the formwork as per

    drawing), spreading the concrete with sholvels, rakes, compacted using needle, scareed

    and plate vibrators and finished in continuous operation including provision of

    contraction and expansion, construction joints, applying debonding strips, primer,sealant, dowel bars, near approaches to bridge / culvert and construction joints,

    admixtures as approved, curing of concrete slabs for 14- days, curing compound (where

    specified) and water finishing to lines and grade as per drawing and Technical

    Specification Clause 1501 MORD.

    Construction of Gravel Base / shoulders including cost, seigniorage charges

    and conveyance of all materials to work site and spreading in uniform layers by

    approved means, on prepared surface and compacting with vibratory roller to

    achieve the desired density at OMC etc., complete for finished item of work as

    per MoRT&H Specification 401& 407 (4th revision) and as directed by theEngineer-in-charge.

    6 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    7/87

    Est.Rs. 36.00 Lakhs

    Assistant Engineer Deputy Executive Engineer Executive Engineer

    APSHCL, Duggirala APSHCL, Mangalagiri APSHCL, Guntur

    Plain cement concrete in substructure complete as per drawings and technical specification Clauses

    802, 804, 805, 806, 807, 1202 and 1204 MORD and 1500, 1700 & 2200 MORTH ( M15 concrete design mix

    ) for Drain Wall is proposed to a length of 843.00 mts on both sides of the road is proposed.

    Specification report to accompany the detailed estimate for the work

    Name of the Work: Construction of Side Drains in Godavarru Village of Duggirala Mandal

    The above work was proposed under indiramma Infrastructure funds. Hence detailed estimate is

    prepared with the following provisions.

    Providing concrete for plain concrete in open foundations using 40 mm nominal size Graded hard stone

    aggregate, mechanically mixed, placed in foundation and compacted by vibration including curing for 14days complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 MORD and 1500,

    1700 & 2100 MORTH. ( M10 Concrete , nominal mix 1:3:6) for Bed Concrete 0.10m depth is proposed.

    Necessary provisions are also made for Joint filler board, VAT @ 5%, Q.C charges @ 2.50 % ,Labour cess

    @ 1.00 %, Ps Charges 7.50 % , Etc.The detailed estimate is prepared with current schedule of rates (ie 2013-14 ) and the work will be carried out

    as per APDSS

    Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1

    including setting out, construction of shoring and bracing, removal of stumps and other deleterious material

    and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated

    suitable material as per Technical Specification 305 MORD / 304 MORTH

    Sand filling 150 mm th for shoe wall fondation is proposed with filling Sand in foundation trenches as

    per drawing and technical specification Clause 305.3.9 MORD & 304 MORTH

    Plain cement concrete in substructure complete as per drawings and technical specification Clauses 802, 804,

    805, 806, 807, 1202 and 1204 MORD and 1500, 1700 & 2200 MORTH Excluding Seignorage and VAT

    including OH&CP (at bottom portion of drain) M20 concrete at Concreting at bottom of drain to thick ness of

    100 mm is proposed

    Plastering with cement mortar (1:4), 12 mm thickness as per technical specification 1300 & 2200 MORTH

    for inside and top portion of drain is proposed

    Certified that the above village is with in 12 Km Radious of from Tadepalli Municipality limits. Hence

    20 % extra over the rates on labour component of works provision is made in this estimate

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    8/87

    Estimate cost Rs. 36.00 lakhs

    SNo. Description of Item Nos. L B D Qty. Rate per Total value

    1

    Side walls

    Main Road 1 x 2 185.00 0.90 0.600 199.80 Cum

    Cross Roads 7 x 2 40.00 0.90 0.600 302.40 Cum

    Cross Roads 7 x 2 54.00 0.90 0.600 408.24 Cum

    910.44 116.19 105784.00

    Cu.m 1 cu.m

    2

    Main Road 1 x 2 185.00 0.90 0.150 49.95

    Cross Roads 7 x 2 40.00 0.90 0.150 75.60

    Cross Roads 7 x 2 54.00 0.90 0.150 102.06

    227.61 512.70 116696.00

    Cu.m 1 cu.m

    3

    Bottom

    Main Road 1 x 2 185.00 0.90 0.100 33.30

    Cross Roads 7 x 2 40.00 0.90 0.100 50.40

    Cross Roads 7 x 2 54.00 0.90 0.100 68.04

    151.74 3799.40 576521.00

    Cu.m 1 cu.m

    4

    Side walls

    Main Road 1 2 x 2 185.00 0.20 0.550 81.40

    Cross Roads 7 2 x 2 40.00 0.20 0.550 123.20

    Cross Roads 7 2 x 2 54.00 0.20 0.550 166.32

    DETAILED CUM ABSTRACT ESTIMATE

    Name of the Work: Construction of Side Drains in Godavarru Village of Duggirala

    Mandal

    Earthwork in excavation for structures as per drawing

    and technical specifications Clause 305.1 includingsetting out, construction of shoring and bracing, removal

    of stumps and other deleterious material and disposal

    upto a lead of 50 m, dressing of sides and bottom and

    backfilling in trenches with excavated suitable material

    as per Technical Specification 305 MORD / 304 MORTH

    Filling Sand in foundation trenches as per drawing and

    technical specification Clause 305.3.9 MORD & 304

    MORTH

    Providing concrete for plain concrete in open

    foundations using 40 mm nominal size Graded hardstone aggregate, mechanically mixed, placed in

    foundation and compacted by vibration including curing

    for 14 days complete as per drawings and technical

    specifications Clause 802, 803, 1202 & 1203 MORD and

    1500, 1700 & 2100 MORTH. for Bed Concrete ( M10

    Concrete , nominal mix 1:3:6)

    Plain cement concrete in substructure complete as per

    drawings and technical specification Clauses 802, 804,

    805, 806, 807, 1202 and 1204 MORD and 1500, 1700 &

    2200 MORTH ( M15 concrete design mix)

    8 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    9/87

    SNo. Description of Item Nos. L B D Qty. Rate per Total value

    370.92 4479.60 1661573.00

    Cu.m 1 cu.m

    5

    At bottom of Drain

    Main Road 1 2 185.00 0.30 0.100 11.10

    Cross Roads 7 2 40.00 0.30 0.100 16.80

    Cross Roads 7 2 54.00 0.30 0.100 22.68

    50.58 4828.40 244220.00

    Cu.m 1 cu.m

    6

    Total drain

    Main Road 1 2 185.00 1.600 592.00

    Cross Roads 7 2 40.00 1.600 896.00

    Cross Roads 7 2 54.00 1.600 1209.60

    2697.60 79.78 215215.00

    Sq.m 1 Sq.m

    Total Estamate 2920009.00

    Provision for PS Charges 7.5% 219001.00

    Provision for VAT at 5% 146000.00

    Provision for 3rd Party Quality control @2.5% 73000.00

    Provision for labour cess 1% 29200.00

    Provision for Tender premium at 5.00% 146000.00

    Unforceen Items 66790.00

    3600000.00

    Assistant Engineer Deputy Executive Engineer Executive Engineer

    APSHCL, Duggirala APSHCL, Mangalagiri APSHCL, Guntur

    Total amount

    Plain cement concrete in substructure complete as per

    drawings and technical specification Clauses 802, 804,

    805, 806, 807, 1202 and 1204 MORD and 1500, 1700 &

    2200 MORTH Excluding Seignorage and VAT includingOH&CP (at bottom portion of drain) M20 concrete

    Plastering with cement mortar (1:4), 12 mm thickness as

    per technical specification 1300 & 2200 MORTH

    9 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    10/87

    S.

    NoQuantity Unit Description Rate Rs. per

    1 2 3 4 5 6

    "13-14 40.00

    0% 50.00

    14% 22.00

    1Removal of Unserviceable Soil with Disposal upto

    1000 m

    RBR-EECD

    Removal of Unserviceable soil including excavation,

    loading and disposal upto 1000 m lead but excluding

    compaction ground supporting embankment

    subgrade replacement by suitable soil, which shall be

    paid separately as per Clause 303.5.2 as per Technical

    Specification Clause 302.3.11 MORD / 301 MORTH

    Unit = cum

    Taking output = 360 cuma) Labour

    - day Mate

    2.080 day Mazdoor (Unskilled) 280.00 1 day

    b) Machinery

    3.60 hour Excavator 0.90 cum bucket capacity @ 100 cum per hour 2754.50 1 hour

    15.00 hour Tipper 5.5 cum capacity, 4 trips per hour 877.30 1 hour

    14% c&d) Overheads & Contractors Profit 23658.10

    Cost for 360 cum = a+b+c+d

    Rate per cum = (a+b+c+d)/360

    2Granular Sub-Base with Coarse Graded Material

    (Table:- 400- 2)

    Construction of granular sub-base by providing coarse

    graded material, spreading in uniform layers with motor

    grader on prepared surface, mixing by mix in place method

    with rotavator at OMC, and compacting with vibratory

    roller to achieve the desired density, complete as per clause

    402 MORTH Grading C

    Unit = cum

    Taking output = 300 cum

    a) Labour

    - day Mate

    2.40 day Mazdoor skilled 280.00 1 day

    8.00 day Mazdoor 280.00 1 day

    b) Machinery

    6.00 hour Mortar Grader 110 HP @ 50 cum per hour 3216.00 1 hour

    30.00 hour Three wheel Roller 80-100 KN @10cu.m/hour 1704.60 1 hour

    3.00 hour Water tanker 6 KL capacity 624.00 1 hour 12.00 hour Tractor with Rotavator 25 cu.m/hour 422.00 1 hour

    c) Material

    For coarse graded Granular sub-base Materials per table

    400-2

    For Grading-C Material (CBR Value minimum 20)

    134.00 cum 9.5 mm to 4.75 mm @ 35 per cent 1327.51 1 cum

    48.00 cum 4.75 mm to 2.36 mm @ 12.5 per cent 987.51 2 cum

    201.60 cum 2.36 mm below @ 52.5 per cent (Dust) 1015.01 1 cum

    18.00 KL Cost of water 0.00 1 KL

    Total Seignorage Charges 19180.00

    Overheads &

    Contractor's Profit

    Sand

    HBG Metal

    Gravel/Earth

    Name of the Work:

    SSR

    MUNICIPAL

    ALLOWANCE

    Seignorage Char

    10 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    11/87

    S.

    NoQuantity Unit Description Rate Rs. per

    1 2 3 4 5 6

    14% Add over heads& contr.profit Exclu. Sei. Charges 491014.84

    Cost for 300 cum = a+b+c+d+e

    Rate per cum = (a+b+c+d)/300

    3 a Grading 1Layer

    Water Bound Macadam Sub-base/base With stone

    screening / binding materials WBM Grading 1 Layer

    100mm thick

    RBR-SBBS-9

    (i) Providing, laying, spreading and compacting stone

    aggregates of specific sizes to water bound macadam

    specification including spreading in uniform thickness,

    hand packing, rolling with three wheel 80 -100 kN static

    roller in stages to proper grade and camber, applying and

    brooming, stone screening/binding materials to fill-up the

    interstices of coarse aggregate, watering and compacting to

    the required density Grading 1 as per Technical

    Specification Clause 404 MORTH & 405 MORD.

    For compacted thickness of 100 mm.By Manual Means (Common for rural & urban

    works)

    Unit = cum

    Taking output = 360 cum

    a) Labour

    - day Mate

    12.08 day Mazdoor (Skilled) 280.00 1 day

    250.00 day Mazdoor (Unskilled) 280.00 1 day

    b) Machinery

    6.00 hour Vibratory roller 8-10 tonnes @ 60 cum per hour 2541.40 1 hour

    24.00 hour Water tanker 6 kl capacity 624.00 1 hour

    c) Material

    Aggregate

    Grading 1 90 mm to 45 mm @ 1.21 cum per 10 sqm forcompacted thickness of 100 mm

    217.8 cum 75mm IRC HBG metal 906.51 1 cum

    200.38 cum 63mm IRC HBG M/C metal 981.51 1 cum

    17.42 cum 45 mm IRC HBG M/C metal 1190.51 1 cum

    Stone Screenings

    97.20 cum Type A 13.2 mm for Grading-1 @ 0.27 cum per 10sqm 1577.51 1 cum

    Binding Material

    28.80 cumBinding Material @ 0.08 cum per 10 sqm forgrading 1

    material (Rate of 2.36mm & Below)1015.01 1 cum

    144.00 kl Water 0.00 1 KL

    Total Seignorage Charges 28080.00

    14% Add over heads& contr.profit Exclu. Sei. Charges 672944.60

    Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)

    Rate per cum = (a+b+c+d+e)/360

    3 b Grading 2 LayerWBM Grading 2nd Layer 75mm thick By

    Mechanical Means

    Unit = cum

    Taking output = 360 cum

    a) Labour

    12.08 day Mazdoor (Skilled) 280.00 1 day

    250.00 day Mazdoor (Unskilled) 280.00 1 day

    b) Machinery

    36.00 hour Three wheel Roller 80-100 KN @10cu.m/hour 1704.60 1 hour

    11 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    12/87

    S.

    NoQuantity Unit Description Rate Rs. per

    1 2 3 4 5 6

    24.00 hour Water tanker 6 kl capacity 624.00 1 hour

    Materials

    217.8 cum 60-63mm IRC HBG metal 1021.51 1 cum

    200.38 cum 40-45mm IRC HBG M/C metal 1337.51 1 cum

    17.42 cum 19-22.40 mm IRC HBG M/C metal 1832.51 1 cum

    86.40 cum Type B 11.2 mm for Grading 2 @ 0.18 cum per 10sqm 1577.51 1 cum

    Binding Material

    28.80 cumBinding material @ 0.06 cum / 10sqm (Rate of 2.36mm &

    Below)1015.01 1 cum

    144.00 kl Water 0.00 1 KL

    Seignorage Charges 27540.00

    14% Add over heads& contr.profit Exclu. Sei. Charges 810130.61

    Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)

    Rate per cum = (a+b+c+d+e)/360

    3 c Grading 3 Layer WBM Grading 3 Layer

    RBR-SBBS-9

    (i) Providing, laying, spreading and compacting stone

    aggregates of specific sizes to water bound macadam

    specification including spreading in uniform thickness,

    hand packing, rolling with smooth wheel roller 80-100 kN

    in stages to proper grade and camber, applying and

    brooming, stone screening to fill-up the interstices of

    coarse aggregate, watering and compacting to the required

    density Grading 3 as per Technical Specification Clause

    405 MORD/ 404 MORTH. For compacted thickness of

    75 mm.

    By Manual Means

    Unit = cum

    Taking output = 360 cum

    a) Labour

    12.08 day Mazdoor (Skilled) 280.00 1 day

    250.00 day Mazdoor (Unskilled) 280.00 1 day

    b) Machinery

    36.00 hour Three wheel Roller 80-100 KN @10cu.m/hour 1704.60 1 hour

    24.00 hour Water tanker 6 kl capacity 624.00 1 hour

    c) Material (Refer Tables 400.7, 8, 9 & 10 MORD/

    400.6, 7, 8 & 9 MORTH)

    Aggregate

    cumGrading 3 53 mm to 22.4 mm @ 0.91cum per 10 sqmfor

    compacted thickness of 75 mm

    357.19 cum 40-45mm IRC HBG M/C metal 1337.51 1 cum

    78.41 cum 19-22.40 mm IRC HBG M/C metal 1832.51 1 cum

    Stone Screening

    86.40 cum Type B 11.2 mm for Grading 3 @ 0.18 cum per 10sqm 1422.51 1 cum

    Binding Material

    28.80 cumBinding Material @ 0.06 cum per 10 sqm forGrading 2

    material (Rate of 2.36mm & Below)1015.01 1 cum

    144.00 kl Water 0.00 1 KL

    Seignorage Charges 27540.00

    Note : Type A Screening can be used in Grading 2

    12 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    13/87

    S.

    NoQuantity Unit Description Rate Rs. per

    1 2 3 4 5 6

    14% Add over heads& contr.profit Exclu. Sei. Charges 895753.46

    Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)

    Rate per cum = (a+b+c+d)/360

    3 d II WBM Grading 2

    RBR-SBBS-9

    Providing, laying, spreading and compacting stone

    aggregates of specific sizes to water bound macadam

    specification including spreading in uniform thickness,

    hand packing, rolling with smooth wheel roller 80-100 kN

    in stages to proper grade and camber, applying and

    brooming, stone screening/binding materials to fill-up the

    interstices of coarse aggregate, watering and compacting to

    the required density grading 2 as per Technical

    Specification Clause 405 MORD / 404 MORTH. For

    compacted thickness of 75 mm.

    By Manual Means

    Unit = cum

    Taking output = 360 cum

    a) Labour

    day Mate 280.00 1 day

    12.08 day Mazdoor (Skilled) 280.00 1 day

    250.00 day Mazdoor (Unskilled) 280.00 1 day

    b) Machinery

    36.00 hour Three wheel 80-100 kN static roller @ 10 cum per hour for Rural Area

    works1704.60 1 hour

    24.00 hour Water tanker 6 kl capacity624.00 1 hour

    c) Material (Refer Tables 400.7, 8, 9 and 10 MORD/ 400.6, 7,

    8 & 9 MORTH)

    Aggregate

    435.60 cumGrading 2 63 mm to 45 mm @ 0.91 cum per 10 sqm for

    compacted thickness of 75 mm1058.51 1.00 cum

    Stone Screening

    86.40 cum Type B 11.2 mm for Grading 2 @ 0.18 / 0.20 cum/10sqm 1422.51 1.00 cum

    (OR)

    57.60 cum Type B 13.2 mm for Grading 2 @ 0.12 cum per 10sqm 1577.51 1.00 cum

    Binding Material

    28.80 cumBinding Material @ 0.06 cum per 10 sqm for Grading 2

    material1015.01 1.00 cum

    144.00 kl Water 0.00 1.00 KL

    Using 11.2 mm for Grading 2 :

    Seignorage Charges 26100.00

    14% Add over heads& contr.profit Exclu. Sei. Charges 707615.82

    Cost for 360 cum = a+b+c+d+e

    Note : When BT is taken up, simultaneously, avoid Binding material

    13 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    14/87

    S.

    NoQuantity Unit Description Rate Rs. per

    1 2 3 4 5 6

    Rate per cum = (a+b+c+d+e)/360

    Using 13.2 mm for Grading 2

    Seignorage Charges 26100.00

    14% Add over heads& contr.profit Exclu. Sei. Charges 704807.82

    Cost for 360 cum = a+b+c+d+e

    Rate per cum = (a+b+c+d+e)/360

    4

    Providing and applying track coat with bitumen

    emulsion using emulsion pressure distributor at the

    rate of 0.20 kg per sqm on the prepared

    bituminous/granular surface cleaned with mechanical

    broom as per Tech. specification No 503 MORTH

    Unit = sqm

    Taking output = 3500 sqm

    a) Labour

    2.080 day Mazdoor (Unskilled) 280.00 1 dayb) Machinery

    2.800 hour Mechanical broom @ 1250 sqm per hour 357.00 1 hour

    2.800 hour Air compressor 250 cfm 499.40 1 hour

    2.000 hour Emulsion pressure distributor @ 1750 sqm per hour 860.00 1 hour

    c) Material

    0.700 t Bitumen emulsion @ 0.2 kg per sqm 37179.93 1 Mt

    14% d&e) Overheads & Contractors Profit 30726.27

    Rate per sq.m = (a+b+c+d)/3500 sq.m

    Rate per sq.m = (a+b+c+d)/3500 sq.m

    5

    20mm thick Open-Graded Premix Carpet using

    Bituminous (penetration grade/modified bitumen)

    Binder

    Providing, laying and rolling of open-graded premix carpetof 20 mm thickness composed of 13.2 mm to 5.6 mm

    aggregates either using penetration grade bitumen or

    emulsion to required line, grade and level to serve as

    wearing course on a previously prepared base, including

    mixing a suitable plant, laying and rolling with a three

    wheel 0-100 kN static roller capacity, finished to required

    level and grades to be followed by seal coat of either type

    A or Type B or Type C as per Technical Specification

    Clause 508 MORD.

    Case - II By Mechanical Means

    Bitumen (S-65)

    Unit = sqm

    Taking output = 4000 sqm (80 cum)a) Labour

    10.000 day Mazdoor (Unskilled) 280.00 1 day

    3.520 day Mazdoor (Skilled) 280.00 1 day

    b) Machinery

    6.000 hour HMP 30/40 t per hour 19120.00 1 hour

    6.000 hour Electric generator set 125 KVA 1320.00 1 hour

    6.000 hour Front end loader 1 cum bucket capacity 1646.00 1 hour

    3.640 hour Tipper 5.5 cum - 10 t capacity 877.30 1 hour

    6.000 hour Paver finisher 2249.00 1 hour

    16.000 hour Three wheel 80-100 kN static roller 1283.00 1 hour

    c) Material

    5.840 t Bitumen (S-65) @ 14.60 kg per 10 sqm 37179.93 1 Mt

    14 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    15/87

    S.

    NoQuantity Unit Description Rate Rs. per

    1 2 3 4 5 6

    108.000 cumCrushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum

    per 10 sqm1422.51 1 cum

    Seignorage Charges 5400.00

    14% Add over heads& contr.profit Exclu. Sei. Charges 538878.84

    Cost of 4000 sqm = a+b+c+d+e

    Rate per 1 sq.m = (a+b+c+d)/4000 sq.m

    6 Seal Coat

    Providing and laying seal coat sealing the voids in a

    bituminous surface laid to the specified levels, grade and

    cross fall using Type A, Type B and Type C as per

    Technical Specification Clause 510 MORD. (using Three

    wheel 80-100 kN static roller)

    By Manual Means

    Bitumen (S-65)

    Unit = sqm

    Taking output = 1100 sqm

    a) Labour

    - day Mate1.000 day Bitumen Sprayer 280.00 1 day

    22.000 day Mazdoor (Unskilled) 280.00 1 day

    7.150 day Mazdoor (Semi-Skilled) 280.00 1 day

    b) Machinery

    2.200 hour Bitumen boiler oil fired, capacity 1000 litre fitted with

    spray set209.00 1 hour

    2.200 hour Three wheel 80-100 kN static roller 1283.00 1 hour

    c) Material

    1.078 t Bitumen (S-65) @ 9.80 kg per 10 sqm 37179.93 1 cum

    9.900 cum

    Crushed stone chipping of 6.7 mm size 100 per cent

    passing 11.2 mm sieve and retained on 2.36 mm sieve

    applied @ 0.09 cum per 10 sqm

    1232.51 1 cum

    Seignorage Charges 495.00

    14% Add over heads& contr.profit Exclu. Sei. Charges 63511.21

    Cost of 1100 sqm = a+b+c+d+e

    Rate per 1 sq.m = (a+b+c+d)/1100

    7

    Cost and supply of Gravel for formation of roads

    Including cost and Seignorage charges and conveyance of

    all materials to work site and spreading in uniform layers

    by approved means, on prepared surface and compacating

    with vibrating roller to achieve the desired density.

    A. Gravel Roads

    The rate as applicable for sub-grade construction may be

    adopted.For Grading III Material (CBR Value minimum 20)

    Unit = cum

    Taking output = 300 cum

    D&e) Overheads & Contractors Profit

    2.40 day Mazdoor (Skilled) 280.00 1 day

    8.00 day Mazdoor (Unskilled) 280.00 1 day

    b) Machinery

    36.00 hour Three wheel 80-100 kN Static Roller 1704.60 1 hour

    12.00 hour Tractor with Rotavator 422.00 1 hour

    12.00 hour Tractor with Grader 422.00 1 hour

    3.00 hour Water tanker 6 kl capacity 624.00 1 hour

    15 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    16/87

    S.

    NoQuantity Unit Description Rate Rs. per

    1 2 3 4 5 6

    c) Material

    237.6 cum Gravel(9.5MM-4.75mm)66% 508.46 1 cum

    122.4 cum 2.36 mm below @ 34 per cent (Dust) 1015.01 1 cum

    18.00 kl Water 1 KL

    Seignorage Charges 11347.20

    14% Add over heads& contr.profit Exclu. Sei. Charges 309977.72

    Cost for 300cum = a+b+c+d+e (3 Wheel Roller)

    Rate per cum = (a+b+c+d)/300

    8

    Construction of Gravel shoulders including cost,

    seigniorage charges and conveyance of all materials to

    work site and spreading in uniform layers by approved

    means, on prepared surface and compacting with

    vibratory roller to achieve the desired density at OMC etc.,

    complete for finished item of work as per MoRT&H

    Specification 401& 407 (4th revision) and as directed by

    the Engineer-in-charge.

    ( Payment will be made based on levels for finished

    item of work )

    Unit = cum

    Taking output = 300 cum

    (A) Labour

    0.40 day Mate 280.00 1 day

    2.00 day Mazdoor skilled 280.00 1 day

    8.00 day Mazdoor unskilled 280.00 1 day

    (B) Machinery

    6.00 hr Vibratory roller 8T 2541.40 1.00 hr

    3.00 hr Water tanker 6 KL 624.00 1.00 hr

    (C) Material

    384.00 cum Gravel 508.46 1.00 cum

    Seignorage Charges 8448.00

    14% Add over heads& contr.profit Exclu. Sei. Charges 206833.04

    Cost for 300cum = a+b+c+d

    Rate per cum = (a+b+c+d)/300

    9

    RBR-SBBS-12 Granular sub-base/base/surface course with local materials (Table 400.13)

    by mix in place method normal Construction of granular sub-base by

    providing local material spreading in uniform layers with motor grader on

    prepared surface, mixing by mix in place method with rotavator at once

    and compacting with smooth wheel roller to achieve the desired density

    complete as per Clause 401.4 as per Technical Specification Clause 408

    MORD.

    Using naturally occurring gravel

    Unit = cum

    Taking output = 300 cum

    a) Labour

    day Mate 280.00 1 day

    2.48 day Mazdoor (Skilled) 280.00 1 day

    10.00 day Mazdoor (Unskilled) 280.00 1 day

    b) Machinery

    6.00 hour Motor grader 110 HP 50 cum per hour 3216.00 1 hour

    30.00 hour Three wheel 80-100 kN static roller @10 cum per hour 1704.60 1 hour

    12.00 hour Tractor with rotavator 25 cum per hour 422.00 1 hour

    16 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    17/87

    S.

    NoQuantity Unit Description Rate Rs. per

    1 2 3 4 5 6

    5.00 hour Water tanker 6 kl capacity 624.00 1 hour

    c) Material

    384.00 cum Naturally occurring gravel (Local materials as per Table 400.13) 508.46 1 cum

    30.00 kl Water 0.00 1 kl

    Basic Cost

    Seignorage Charges 19200.0014% Add over heads& contr.profit Exclu. Sei. Charges 258161.04

    Cost for 300cum = a+b+c+d

    Rate per cum = (a+b+c+d)/300

    10

    RBR-CCPV-5

    Unit = cum

    Taking output = 75 cum (172.50 t)

    (100 x 3.75 x 0.200)

    a) Labour

    day Mate 280.00 1.00 day

    5.00 day Mason (1st class) 350.00 1.00 day

    5.00 day Mason (2nd class) 320.00 1.00 day

    150.00 day Mazdoor (Unskilled) 280.00 1.00 day

    6.00 day Mazdoor (Skilled) 280.00 1.00 day

    2.00 day Surveyor 320.00 1.00 day

    6.00 day Mazdoor (Semi-Skilled) 280.00 1.00 day

    1.00 dayBlacksmith for cutting of dowel bars including removal of burrs,

    fabrications & fixing of dowel bars.

    b) Machinery

    36.00 hour Concrete mixer 0.28 / 0.4 cum capacity (6 mixers) with weigh

    batcher and suitable capacity calibrated water tank417.40 1.00 Hour

    9.00 hour Needle vibrator 152.20 1.00 Hour

    9.00 hour Screed vibrator 0.00 1.00 Hour

    9.00 hour Plate vibrator 152.20 1.00 Hour

    4.00 hour Concrete joint cutting machine for initial & final cuts 0.00 1.00 Hour

    5.00 hour Water tanker 6 kl capacity 624.00 1.00 Hour

    2.00 hour Air Compressor (1 hour initial + 1 hour final) 499.40 1.00 Hour

    c) Material

    Crushed stone coarse aggregates, grading will be as per Clause

    1501.2.4.1 (Table 1500.1) of specifications @ 0.90 cum/cum of

    concrete (25 mm & 12.5 mm blending)

    44.55 cum 20 mm HBG Metal 1832.51 1.00 Cum

    22.95 cum 12 mm HBG Metal 1577.51 1.00 Cum

    33.75 cumSand as per IS:383 and conforming to Clause 1500.2.4.2 @ 0.45

    cum/cum of concrete467.77 1.00 Cum

    26.25 t Cement @ 310 kg/cum of concrete 5.70 1.00 Cum

    412.50 sqm Polythene sheet 125 micron 15.00 1.00 Sq mt

    Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain

    cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade

    cement or any other type as per Clause 1501.2.2 M30 (Grade) design mix, coarse and fine

    aggregates conforming to IS : 383, maximum in a concrete mixer of not less than 0.2 cum

    capacity and appropeiate weigh batcher using approved mix design, laid in approved fixed side

    formwork (steel channel, laying and fixing of 125 mictron thick polythene film, wedges, steel

    plates including levelling the formwork as per drawing), spreading the concrete with sholvels,

    rakes, compacted using needle, scareed and plate vibrators and finished in continuous operation

    including provision of contraction and expansion, construction joints, applying debonding

    strips, primer, sealant, dowel bars, near approaches to bridge / culvert and construction joints,admixtures as approved, curing of concrete slabs for 14- days, curing compound (where

    specified) and water finishing to lines and grade as per drawing and Technical Specification

    Clause 1501 MORD.

    17 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    18/87

    S.

    NoQuantity Unit Description Rate Rs. per

    1 2 3 4 5 6

    Mild steel dowel bar 25 mm dia of grade S 240. 500 mm long20

    Nos. at culvert/bridge slab and at construction joint including 5

    per cent wastage.

    0.118 t(4 x 20x 0.500) + 5 per cent wastage = 42 m @ 2.80 kg per m =

    117.6 kg.43000.00 1.00 ton

    5.00 kg Bitumen primer @ 200 ml per joint for 23 joints 37179.93 1.00 ton

    19.00 litre Bituminous sealant 800 ml per joint for 23 joints 37179.93 1.00 ton90.00 m Jute rope 12 mm dia including 5 per cent wastage

    90.00 m

    Debonding strips 3.75 m (length) x 10 mm (width) x 5 mm

    (thick) cut-out of rubber filler board or similar material including

    5 per cent wastage

    483.00 sqmtPolythene sheathing, covering 2/3rd dowel bars (20x23) and tight

    fit including 5 per cent wastage15.00 1.00 Sq mt

    122.00 litre Plasticizer 0.5 per cent by weight of cement 70.00 1.00 Ltr

    131.25 litre Curing compound (if used) @ 0.33 litre per sqm

    18.00 kl Water for curing 0.00 1.00 kl

    3.00 sqmJoint filler board 20 mm thick as per IS:1838

    (4 x 3.75 x 0.200 = 3 sqm)925.00 1.00 Ltr

    3.00%(d) Formwork @ 3% on cost of material, labour and machinery

    (a+b+c)385203.05

    Basic rate per 75 Cum

    Seignorage Charges

    Sand 1350.00

    Agrregate 3375.00

    4725.00

    14% Add over heads& contr.profit Exclu. Sei. Charges 392034.15

    Add sundries

    Rate per 75 Cum

    Rate per Cum

    11 Cost of RCC Pipes NP2

    Unit = 1Rm

    5.00 RM Cost and Conveyance charges of RCC Pipes 370.60 1.00 RM

    1 No Cost of collars 87.00 1.00 No

    Cost for 5Rm =a+b+c+d

    Rate per RM is ( a+b+c+d )/5

    14% Add over heads& contr.profit Exclu. Sei. Charges 388.00

    Add sundries

    Rate Per RM

    12

    Unit = 1Rm

    Taking out put = 7.50 RM (3 pipes of 2.50 Mts length each )

    upto 500 mm dia

    a) Labour

    2.51 day Mazdoor (Unskilled) 280.00 1.00 day

    deduct 20% for 300mm RCC Pipes

    b)Material

    Cost for 5Rm =a+b

    Rate per RM is ( a+b )/7.50

    14% Add over heads& contr.profit Exclu. Sei. Charges 74.97

    Supply and delivery of RCC NP2 pipes of 300mm dia including collars and

    conveyance charges etc, complete

    Laying of RCC pipes NP2

    Laying and fixing of RCC NP2 pipes of300mm diaincluding all labour charges etc, complete

    18 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    19/87

    S.

    NoQuantity Unit Description Rate Rs. per

    1 2 3 4 5 6

    Add sundries

    Rate Per RM

    13 Cost of RCC Pipes NP2

    Unit = 1Rm

    5.00 RM Cost and Conveyance charges of RCC Pipes 666.00 1.00 RM

    1 No Cost of collars 185.00 1.00 No

    Cost for 5Rm =a+b+c+d

    Rate per RM is ( a+b+c+d )/5

    14% Add over heads& contr.profit Exclu. Sei. Charges 703.00

    Add sundries

    Rate Per RM

    14

    Unit = 1Rm

    Taking out put = 7.50 RM (3 pipes of 2.50 Mts length each )

    upto 500 mm dia

    a) Labour

    2.51 day Mazdoor (Unskilled) 280.00 1.00 day

    deduct 20% for 300mm RCC Pipes

    b)Material

    Cost for 5Rm =a+b

    Rate per RM is ( a+b )/7.50

    14% Add over heads& contr.profit Exclu. Sei. Charges 93.71

    Add sundries

    Rate Per RM

    15 Cost of RCC Pipes NP3

    Unit = 1Rm

    5.00 RM Cost and Conveyance charges of RCC Pipes 845.40 1.00 RM

    1 No Cost of collars 124.00 1.00 No

    Cost for 5Rm =a+b+c+d

    Rate per RM is ( a+b+c+d )/5

    14% Add over heads& contr.profit Exclu. Sei. Charges 870.20

    Add sundries

    Rate Per RM

    16

    Unit = 1Rm

    Taking out put = 7.50 RM (3 pipes of 2.50 Mts length each )

    upto 500 mm dia

    a) Labour

    2.51 day Mazdoor (Unskilled) 280.00 1.00 day

    deduct 20% for 300mm RCC Pipes

    b)Material

    Cost for 5Rm =a+b

    Supply and delivery of RCC NP3 pipes of 300mm dia including collars and

    Laying of RCC pipes NP3

    Laying and fixing of RCC NP3 pipes of300mm diaincluding all labour charges etc, complete

    Supply and delivery of RCC NP2 pipes of 450mm dia including collars and

    conveyance charges etc, complete

    Laying of RCC pipes NP2

    Laying and fixing of RCC NP2 pipes of450 mm diaincluding all labour charges etc, complete

    19 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    20/87

    S.

    NoQuantity Unit Description Rate Rs. per

    1 2 3 4 5 6

    Rate per RM is ( a+b )/7.50

    14% Add over heads& contr.profit Exclu. Sei. Charges 74.97

    Add sundries

    Rate Per RM

    17 Cost of RCC Pipes NP3

    Unit = 1Rm

    5.00 RM Cost and Conveyance charges of RCC Pipes 1317.80 1.00 RM

    1 No Cost of collars 233.00 1.00 No

    Cost for 5Rm =a+b+c+d

    Rate per RM is ( a+b+c+d )/5

    14% Add over heads& contr.profit Exclu. Sei. Charges 1364.40

    Add sundries

    Rate Per RM

    18

    Unit = 1Rm

    Taking out put = 7.50 RM (3 pipes of 2.50 Mts length each )

    upto 500 mm dia

    a) Labour

    2.51 day Mazdoor (Unskilled) 280.00 1.00 day

    deduct 20% for 300mm RCC Pipes

    b)Material

    Cost for 5Rm =a+b

    Rate per RM is ( a+b )/7.50

    14% Add over heads& contr.profit Exclu. Sei. Charges 93.71

    Add sundries

    Rate Per RM

    19

    RBR-FNDN-1

    (I) Ordinary soil

    (A) Manual Means

    (i) Upto 3 m depth

    Unit = cum

    Taking output = 10 cum

    a) Labour

    day Mate 280.00 1.00 day

    3.64 day Mazdoor (Unskilled) 280.00 1.00 day

    14% b&c) Overheads & Contractors Profit 1019.20 10.00 Cu.m

    Add sundries

    Cost for 10 cum = a+b+c

    Rate per cum = (a+b+c)/10

    20

    Supply and delivery of RCC NP3 pipes of 450mm dia including collars and

    Note : Classifications of Earth Work Specification are as per 302.2.1(a) of MORD and

    Filling in foundation trenches as per drawing and technical specification Clause 305.3.9 MORD

    & 304 MORTH

    Laying and fixing of RCC NP3 pipes of450 mm diaincluding all labour charges etc, complete

    Laying of RCC pipes NP3

    Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1

    including setting out, construction of shoring and bracing, removal of stumps and other

    deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and

    backfilling in trenches with excavated suitable material as per Technical Specification 305

    MORD / 304 MORTH

    20 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    21/87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    22/87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    23/87

    S.

    NoQuantity Unit Description Rate Rs. per

    1 2 3 4 5 6

    Basic rate per 1 Cum

    Seignorage Charges

    Sand 19.20

    Coarse aggregate 40.00

    Total 59.20

    14% Add over heads& contr.profit Exclu. Sei. Charges 3877.51 1.00 Cu.mAdd sundries

    Rate per cum = a+b+c+d+e+f

    21 d d) RBR-FNDN-5

    Sub-analysis

    Cement mortar 1:5 (1 cement : 5 sand)

    Unit = cum

    (a) Material

    0.288 t Cement 5.70 1.00 Kg

    1.05 cum Sand467.77 1.00 Cum

    (b) Labour

    day Mate 280.00 1.00 day

    0.2 day Mazdoor (Unskilled) 280.00 1.00 day

    Total material and labour = (a+b)

    Cement mortar 1:4 (1 cement : 4 sand)

    Unit = cum

    (a) Material

    0.360 t Cement 5.70 1.00 Kg

    1.05 cum Sand 467.77 1.00 Cum

    (b) Labour

    day Mate 280.00 1.00 day

    0.2 day Mazdoor (Unskilled) 280.00 1.00 day

    Total material and labour = (a+b)

    22Plastering with cement mortar (1:5), 12 mm thick on brickwork in

    substructure as per technical specification

    RBR-SBST-3

    Unit = 10 sqm

    Taking output = 10 sqm

    (a) Material

    0.144 cum Cement mortar 1:5 (Rate as in item 11.5 II ) 2188.76 1.00 Cum

    (b) Labour

    day Mate 280.00 1.00 day

    0.500 day Mason 1st Class 350.00 1.00 day

    0.540 day Mazdoor (Unskilled) 280.00 1.00 day

    Basic rate per 1 Cum

    Seignorage Charges

    Sand 6.05

    14% Add over heads& contr.profit Exclu. Sei. Charges 635.34 1.00 Cu.m

    Add sundries

    Rate per 10 sq mt

    Rate per 1 sq mt

    23Plastering with cement mortar (1:4), on brickwork in substructure as

    per technical specification Section 1300 & 2200 MORTH

    Note : Needle Vibrator is an item of minor T & P which is already included in overhead charges. Hence not added i

    concrete works.

    23 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    24/87

    S.

    NoQuantity Unit Description Rate Rs. per

    1 2 3 4 5 6

    Unit = 10 sqm

    Taking output = 10 sqm

    (a) Material

    0.144 cum Cement mortar 1:4 (Rate as in item 11.5 II ) 2599.16 1.00 Cum

    (b) Labour

    day Mate 280.00 1.00 day

    0.500 day Mason 1st Class 350.00 1.00 day

    0.540 day Mazdoor (Unskilled) 280.00 1.00 day

    Basic rate per 1 Cum

    Seignorage Charges

    Sand 6.05

    14% Add over heads& contr.profit Exclu. Sei. Charges 694.43 1.00 Cu.m

    Add sundries

    Rate per 10 sq mt

    Rate per 1 sq mt

    Assistant Engineer Deputy Executive Engineer Executive

    APSHCL, Duggirala APSHCL, Mangalagiri APSHCL,

    24 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    25/87

    Amount Rs.

    7

    582.40

    9916.20

    13159.50

    3312.13

    26970.23

    74.92

    672.00

    2240.00

    19296.00

    51138.00

    1872.005064.00

    177886.34

    47400.48

    204626.02

    0.00

    510194.84

    ges

    25 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    26/87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    27/87

    Amount Rs.

    7

    14976.00

    222484.88

    268010.25

    31922.32

    136296.86

    29232.29

    0.00

    837670.61

    113418.29

    951088.89

    2642.00

    3382.40

    70000.00

    61365.60

    14976.00

    477745.20

    143687.11

    122904.86

    29232.29

    0.00

    923293.46

    27 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    28/87

    Amount Rs.

    7

    125405.48

    1048698.94

    2913.10

    0.00

    3382.40

    70000.00

    61365.60

    14976.00

    461086.96

    122904.86

    90864.58

    29232.29

    0.00

    733715.82

    99066.21

    832782.03

    28 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    29/87

    Amount Rs.

    7

    2313.28

    730907.82

    98673.09

    829580.91

    2304.39

    582.40

    999.60

    1398.32

    1720.00

    26025.95

    4301.68

    35027.95

    10.10

    2800.00

    985.60

    114720.00

    7920.00

    9876.00

    3193.37

    13494.00

    20528.00

    217130.79

    29 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    30/87

    Amount Rs.

    7

    153631.08

    544278.84

    75443.04

    619721.88

    155.00

    280.00

    6160.00

    2002.00

    459.80

    2822.60

    40079.96

    12201.85

    64006.21

    8891.57

    72897.78

    66.27

    672.00

    2240.00

    61365.60

    5064.00

    5064.00

    1872.00

    30 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    31/87

    Amount Rs.

    7

    120810.10

    124237.22

    0.00

    321324.92

    43396.88

    364721.80

    1215.80

    112.00

    560.00

    2240.00

    15248.40

    1872.00

    195248.64

    215281.04

    28956.63

    244237.67

    814.20

    0.00

    694.40

    2800.00

    19296.00

    51138.00

    5064.00

    31 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    32/87

    Amount Rs.

    7

    3120.00

    195248.64

    0.00

    277361.04

    36142.55

    313503.59

    1045.10

    0.00

    1750.00

    1600.00

    42000.00

    1680.00

    640.00

    1680.00

    15026.40

    1369.80

    0.00

    1369.80

    0.00

    3120.00

    998.80

    81638.33

    36203.86

    15787.24

    149625.00

    6187.50

    32 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    33/87

    Amount Rs.

    7

    5074.00

    185.90

    706.42

    7245.00

    8540.00

    0.00

    2775.00

    11556.10

    396759.15

    54884.79

    0.00

    451644.00

    6021.92

    1853.00

    87.00

    1940.00

    388.00

    54.32

    0.08

    442.40

    702.80

    140.56

    562.24

    74.97

    10.50

    33 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    34/87

    Amount Rs.

    7

    0.03

    85.50

    3330.00

    185.00

    3515.00

    703.00

    98.42

    0.08

    801.50

    702.80

    702.80

    93.71

    13.12

    0.07

    106.90

    4227.00

    124.00

    4351.00

    870.20

    121.83

    0.07

    992.10

    702.80

    140.56

    562.24

    34 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    35/87

    Amount Rs.

    7

    74.97

    10.50

    0.03

    85.50

    6589.00

    233.00

    6822.00

    1364.40

    191.02

    0.08

    1555.50

    702.80

    702.80

    93.71

    13.12

    0.07

    106.90

    0.00

    1019.20

    142.69

    0.01

    1161.90

    116.19

    35 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    36/87

    Amount Rs.

    7

    0.00

    86.80

    367.77

    454.57

    58.04

    0.09

    512.70

    0.00

    145.60

    508.46

    654.06

    88.49

    0.05

    742.60

    1254.00

    210.501203.76

    0.00

    0.00

    35.00

    389.20

    166.96

    81.12

    36 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    37/87

    Amount Rs.

    7

    0.00

    3340.54

    458.86

    0.00

    3799.40

    1881.00

    210.50

    481.51

    659.71

    256.06

    0.00

    35.00

    389.20

    166.96

    163.20

    4243.14

    585.22

    0.04

    4828.40

    1567.50

    224.53

    642.01439.81

    113.81

    0.00

    35.00

    389.20

    166.96

    357.89

    37 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    38/87

    Amount Rs.

    7

    3936.71

    542.860.03

    4479.60

    1641.60

    491.16

    0.00

    56.00

    2188.76

    2052.00

    491.16

    0.00

    56.00

    2599.16

    315.19

    0.00

    175.00

    151.20

    641.39

    88.95

    0.06

    730.40

    73.04

    rate analysis of cement

    38 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    39/87

    Amount Rs.

    7

    374.28

    0.00

    175.00

    151.20

    700.48

    97.23

    0.09

    797.80

    79.78

    ngineer

    untur

    39 /87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    40/87

    SSR "13-14

    MUNICIPAL ALLOWANCE 0%

    Overheads & Contractor's Profit 14%

    Initial 0%Rate Allow.

    1 1st class mason I-11 350.00 0.00 350.00 per day

    2 2nd class mason II-35 320.00 0.00 320.00 per day

    3 1st class Brick Layer I-11 350.00 0.00 350.00 per day

    4 2nd class Brick layer II-35 320.00 0.00 320.00 per day

    5 1st class Painter I-35 400.00 0.00 400.00 per day

    6 2nd class Painter II-37 320.00 0.00 320.00 per day

    7 Head mazdoor II-10 320.00 0.00 320.00 per day

    8 Man mazdoor III-3 280.00 0.00 280.00 per day

    9 Woman mazdoor III-4 280.00 0.00 280.00 per day

    10 skilled electrician I-5 400.00 0.00 400.00 per day

    11 semiskilled electrician II-34 320.00 0.00 320.00 per day

    12 helper II-34 320.00 0.00 320.00 per day

    13 Cost of binding wire pno.231/1292 70.00 0.00 70.00 per Kg

    A 1st - Floorper 1 sqm Rs. 8.99 Rs. 54.34 Rs.

    B 2nd - Floorper 1 sqm Rs. 8.99 Rs. 77.01 Rs.

    C 3rd - Floor per 1 sqm Rs. 8.99 Rs. 99.69 Rs.

    D 4th - Floorper 1 sqm Rs. 8.99 Rs. 122.36 Rs.

    A 1st - Floor per 1 sqm Rs. 0.90 Rs. 5.43 Rs.

    B 2nd - Floorper 1 sqm Rs. 0.90 Rs. 7.70 Rs.

    C 3rd - Floorper 1 sqm Rs. 0.90 Rs. 9.97 Rs.

    D 4th - Floorper 1 sqm Rs. 0.90 Rs. 12.24 Rs.

    A 1st - Floorper 1 sqm Rs. 2.11 Rs. 11.08 Rs.

    B 2nd - Floorper 1 sqm Rs. 2.11 Rs. 15.57 Rs.

    C 3rd - Floorper 1 sqm Rs. 2.11 Rs. 20.05 Rs.

    HIRE CHARGES FOR ACCESS SCAFFOLDING - up to 3.66 M using Casurina Bellies, Bamboos, Woode

    Runners, Wood Posts, Wall Plates etc., for BRICK MASONRY/STONE MASONRY - 1 sqm(Pno.91)

    Labour & Materials

    HIRE CHARGES FOR ACCESS SCAFFOLDING - up to 3.66 M using Casurina Bellies, Bamboos, Woode

    Runners, Wood Posts, Wall Plates etc., for PLASTERING TO WALLS - 1 sqm(Pno-91)

    Final Rate

    HIRE CHARGES FOR STAGE SCAFFOLDING - up to 3.66 M using Casurina Bellies, Bamboos, Wooden

    Runners, Wood Posts, Wall Plates etc., for CEILING PLASTERING - 1 sqm(Pno.92)

    Name of the Work: Construction of Side Drains and CC Roads in Godavarru Villag

    Duggirala Mandal

    LABOUR CHARGES

    UnitSl.No. Description SSR Sl.No.

    Page 40 of 87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    41/87

    D 4th - Floorper 1 sqm Rs. 2.11 Rs. 24.54 Rs.

    Sl.

    No.

    SSR

    Sl. No.Unit Rate

    1 3 4 5

    1 BMS-W.68 Kg 27.00

    2 BMT.J.27 Kg 20.60

    3 BMT.J.24 Kg 47.00

    4 BMT.J.26 Kg 44.24

    5 BMT.J.20 Ltr 40.00

    6 BMT.J.21 Kg 81.00

    7 BMT.J.05 Ltr 135.00

    8 BMT.J.03 Ltr 121.00

    9 BMT.J.01 Kg 134.00

    10 BMT.J.30 Ltr 230.00

    11 BMT.J.22 Ltr 244.00

    12 BMT.H.01 Kg 24.00

    13 CSSR-A.03 Kg 70.00

    14 BMS.W.17 Sqmt. 375.00

    15 BMS.W.16 Sqmt. 274.00

    16 BMT.C.01 Sqmt. 447.00

    17 BMT.C.06 Sqmt. 335.00

    18 BMT.B.16 Sqmt. 1008.00

    19 BMS.W.20 Sqmt. 925.00

    20 BMS.W.21 Sqmt. 530.00

    21 BMT.B.05 10Sqmt. 1544.00

    22 BMT.B.07 10Sqmt. 3603.00

    22 BMT-F.28 Sqmt. 16.00

    23 1 No 0.00

    24 1 No 0.00

    25 1 No 0.00

    Oil Bound Distemper POWDER

    Red Oxide Primer Paint Grade-I

    Mastic Pad 0.60 x 1.20 Mts, 25.4mm thick

    Synthetic enamel paint 1st quality (All Shades)

    White Glazed Tiles of any Size 1st. Quality

    Cement Jally 50mm thick

    Wood Primer

    Cement Primer Grade - I

    Cement Jally 40mm thick

    RCC Door Frame size 0.75 X1.98 mt (NK Materials)

    Rabbit wire mesh

    RCC Window Frame size 0.90 X1.20 mt (NK Materials)

    RCC Door Frame size 0.98 X1.98 mt (NK Materials)

    Polished kadapa slabs

    Mastic Pad 0.60 x 1.20 Mts, 12.7mm thick

    Ceramic tiles 7.3mm thick

    Vitrified floor tiles 600 x 600 mm normal colour 1 st quality

    Cost of binding wire

    White Cement

    Polished kadapa slabs 25mm thick

    Snowcem or Equv. Quality

    Water proof Cement Superior Quality

    Plastic emulsion paint

    Oil Bound Distemper

    MATERIAL RATES OF BUILDING ITEMS

    Description of Item

    Impervious Water proofing compound

    Surya Cem or Equivalent Quality

    2

    Page 41 of 87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    42/87

    63.33

    86.00

    108.68

    131.35

    6.33

    8.60

    10.87

    13.14

    13.19

    17.68

    22.16

    Reapers,

    Reapers,

    Reapers,

    e of

    Page 42 of 87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    43/87

    26.65

    Page 43 of 87

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    44/87

    SSR "13-14

    Muncipal Allowancwe 0%

    Contractor Profit 14%

    DISTANCE

    TOTAL

    RATE

    1 Sand for Mortor M-005 Krishna River Cu.m 425.00 3.00 22.81

    2 Sand for Filling M-004 Krishna River Cu.m 325.00 3.00 22.81

    3 6mm HBG Metal M-050 Lam Cu.m 750.00 50.00 482.51

    4 10 mm HBG metal M-051 Lam Cu.m 940.00 50.00 482.51

    5 12 mm HBG metal M-052 Lam Cu.m 1095.00 50.00 482.51

    6 20 mm HBG metal M-053 Lam Cu.m 1350.00 50.00 482.51

    7 40 mm HBG metal M-055 Lam Cu.m 855.00 50.00 482.51

    8 FAL-G.block (290x200x140) BMT-A11 Local 1 No 16.00 0.00 3.00

    9 FAL-G.block (290x150x140) BMT-A12 Local 1 No 12.00 0.00 3.00

    10 FAL-G.block (290x100x140) BMT-A13 Local 1 No 10.00 0.00 3.00

    11 2nd class Country brick BMT-A01 Kollipara 1000 No 3707.00 12.00 188.48

    12 Cement 0 Local 1kg 5.70 0.00 0.00

    13 Water 0 Local KL 0.00 0.00 0.00

    14 Steel 0 Local MT 43000.00 0.00 0.00

    15 Gravel M-008 Vejandla 1 Cu.m 120.00 37.00 368.50

    16 Stone crusher dust M-021 Lam 1 Cum 390.00 50.00 482.51

    17 Quarry Rubbish M-148 Vejandla Cu.m 267.00 37.00 368.50

    18 Earth(Conveyance only) 0.00

    19300 dia. RCC NP2 class Plain ended

    i esTenali RM 348.00 25.00 22.60

    20 450 dia. RCC NP2 class Plain endedpipes

    Tenali RM 611.00 25.00 55.00

    21600 dia. RCC NP2 class Plain ended

    pipesTenali RM 993.00 25.00 94.20

    1300 dia. RCC NP3 class Plain ended

    pipesTenali RM 791.00 25.00 54.40

    23450 dia. RCC NP3 class Plain ended

    pipesTenali RM 1235.00 25.00 82.80

    24600 dia. RCC NP3 class Plain ended

    i esTenali RM 2019.00 25.00 156.00

    Assistant Engineer

    APSHCL, Duggirala

    LEAD STATEMENT

    SI.

    No.Description Unit Initial CostSSR Sl.No.

    Name of the Work: Construction of Side Drains and CC Roads in Godavarru Village of Duggirala Mandal

    Conveyance Charges

    FOR BUILDINGS-CCRoads-CCDrains

    1. Certified that the above leads are corrcet and best of my knowledge.

    Source of Material

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    45/87

    SSR "13-14

    Muncipal Allowancwe 0%

    Contractor Profit 14%

    DISTANCE

    1 Sand for Mortor M-005 Krishna River Cu.m 425.00 3.00 2

    2 Sand for Filling M-004 Krishna River Cu.m 325.00 3.00 2

    3 60 to 63 mm IRC and MoRTH HBG metal Lam Cu.m 539.00 50.00 4

    4 50 to 55 mm IRC and MoRTH HBG metal Lam Cu.m 576.00 50.00 4

    5 40 to 45 mm IRC and MoRTH HBG metal Lam Cu.m 708.00 50.00 4

    9 SS Revetment work 300mm Lam Cu.m 276.00 50.00 4

    10Quarry spall (Field picked metal) Av. of rate 25mm

    & 40mmLam Cu.m 165.00 50.00 4

    11 150 mm soling stone HBG metal Lam Cu.m 186.00 50.00 4

    12 40 to 45 mm IRC and MoRTH HBG M/C metal Lam Cu.m 855.00 50.00 4

    13 25 to 27 mm IRC and MoRTH HBG M/C metal Lam Cu.m 1300.00 50.00 4

    14 19 to 22 mm IRC and MoRTH HBG M/C metal Lam Cu.m 1350.00 50.00 4

    15 12 to 14 mm IRC and MoRTH HBG M/C metal Lam Cu.m 1095.00 50.00 4

    16 9.5 to 11.20 mm IRC and MoRTH HBG M/C metal Lam Cu.m 940.00 50.00 4

    17 5 to 7 mm IRC and MoRTH HBG M/C metal Lam Cu.m 750.00 50.00 4

    18 2.36 to 5 mm IRC and MoRTH HBG M/C metal Lam Cu.m 505.00 50.00 4

    19 HBG Stone chips 2.36mm and below Lam Cu.m 532.50 50.00 4

    20 75mm size IRC and Morth HBG metal Lam Cu.m 424.00 50.00 4

    21 65mm size IRC and Morth HBG metal Lam Cu.m 499.00 50.00 4

    22 FAL-G.block (290x200x140) BMT-A11 Local 1 No 16.00 0.00

    23 FAL-G.block (290x150x140) BMT-A12 Local 1 No 12.00 0.00

    24 FAL-G.block (290x100x140) BMT-A13 Local 1 No 10.00 0.00

    25 2nd class Country brick BMT-A01 Kollipara 1000 No 3707.00 12.00 1

    26 Cement 0 Local 1kg 5.70 0.00

    27 Water 0 Local KL 0.00 0.00

    28 Gravel M-008 Vejandla 1 Cu. 120.00 37.00 3

    29 Stone crusher dust M-021 Lam 1 Cum 390.00 50.00 4

    30 Mild steel Local ton 4300031 Bitumen Vishakhapatnam 1mt 35829.93 900.00 13

    APSHCL, Duggirala

    Name of the Work: Construction of Side Drains and CC Roads in Godavarru Village of Duggirala Mandal

    FOR ROADS & Levelling Works

    Conveyance Cha

    Source of Material

    Conveyance of Bitumen for Bulk and packed Rs.1.50 KM/MT

    1. Certified that the above leads are corrcet and best of my knowledge.

    Unit Initial CostSI.

    No. Description SSR Sl.No.

    LEAD STATEMENT

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    46/87

    Seigniorage charges 50.00

    Sl.

    NoDescription of Metal

    Initial cost

    Including

    stacking

    Blasting

    charges

    A) FOR ROAD WORKS 70.00

    1 60 to 63 mm IRC and MoRTH HBG metal 419.00 70.00

    2 50 to 55 mm IRC and MoRTH HBG metal 456.00 70.00

    3 40 to 45 mm IRC and MoRTH HBG metal 588.00 70.00

    4 SS Revetment work 300mm 156.00 70.00

    5

    Quarry spall (Field picked metal) Av. of rate 25mm

    & 40mm 45.00 70.00

    6 150 mm soling stone HBG metal 66.00 70.00

    4 40 to 45 mm IRC and MoRTH HBG M/C metal 588.00 70.00

    5 25 to 27 mm IRC and MoRTH HBG M/C metal 944.00 70.00

    6 19 to 22 mm IRC and MoRTH HBG M/C metal 984.00 70.00

    7 12 to 14 mm IRC and MoRTH HBG M/C metal 780.00 70.00

    9 9.5 to 11.20 mm IRC and MoRTH HBG M/C metal 656.00 70.00

    10 5 to 7 mm IRC and MoRTH HBG M/C metal 504.00 70.00

    11 2.36 to 5 mm IRC and MoRTH HBG M/C metal 308.00 70.00

    12 HBG Stone chips 2.36mm and below 330.00 70.00

    13 75mm size IRC and Morth HBG metal 304.00 70.00

    13 65mm size IRC and Morth HBG metal 379.00 70.00

    ROAD METAL RATES

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    47/87

    Machine

    crushing

    charges

    Seigniorage

    charges

    Deduct

    stacking

    charges for

    conveyance

    Toal Cost per

    Cum

    25%

    0.00 50.00 0.00 539.00

    0.00 50.00 0.00 576.00

    0.00 50.00 0.00 708.00

    0.00 50.00 0.00 276.00

    0.00 50.00 0.00 165.00

    0.00 50.00 0.00 186.00

    147.00 50.00 0.00 855.00

    236.00 50.00 0.00 1300.00

    246.00 50.00 0.00 1350.00

    195.00 50.00 0.00 1095.00

    164.00 50.00 0.00 940.00

    126.00 50.00 0.00 750.00

    77.00 50.00 0.00 505.00

    82.50 50.00 0.00 532.50

    0.00 50.00 0.00 424.00

    0.00 50.00 0.00 499.00

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    48/87

    Hire

    Charges

    Fuel

    Charges

    Crew

    Charges

    Total Per

    a) 456.20 280.70 140.40 877.30 Hour

    b) 422.80 280.70 140.40 843.90 Hour

    c) 411.00 280.70 140.40 832.10 Hour

    d) 422.80 280.70 140.40 843.90 Hour

    e) 422.80 280.70 140.40 843.90 Hour

    f) 120.30 114.10 269.50 503.90 Hour

    g) 7.80 19.00 125.40 152.20 Hour

    g) 54.60 74.30 174.20 303.10 Hour

    2754.50 Hour

    877.30 Hour

    3216.00 Hour

    2541.40 Hour

    624.00 Hour

    357.00 Hour

    860.00 Hour

    19120.00 Hour

    1320.00 Hour

    1646.00 Hour2249.00 Hour

    1283.00 Hour

    209.00 Hour

    417.40 Hour

    499.40 Hour

    422.00 Hour

    1704.60 Hour

    1 Minci al area allowance 0.00%

    2 Industrial area allowance 0.00%

    3 Agency area allowance 0.00%

    4 Allowable allowance 0.00%5 Add Overhead Charges & Contractor's Profit 0.00%

    A)

    1 Lead up to 1 Km:

    Out put = 5.00 Cum Rate Per Amount

    0.15 456.20 Hour Rs. 68.43

    0.15 280.70 Hour Rs. 42.11

    0.15 140.40 Hour Rs. 21.06

    0.00 21.06 Rs. 0.00

    Rate fo 5.00 Cum Rs. 131.60

    Rate fo 1.00 Cum Rs. 26.32

    Hire Charges Roads & Irrigation Works Machinery

    Water tanker 6KL capacity

    Emulson Pressure Distributor

    Hot mix plant 40 to 60 TPH Capacity

    Hydraulic Excavator

    Three wheel 80-100 kN Static Roller

    Paver finisher Mechanical 100 TPH

    Batching plant 0.5 cum

    Needle vibrator 40mm

    (petrol)

    Electric Generator 125 KVA

    Concrete mixer 300/200

    (diesel) SSR hire charges

    Pg.no.325, Sl. No.16

    Hrs. fuel charges of Tipper 5.00 Cum @ Rs.

    Vibratory roller 8 tonnes

    Mechanical Broom Hydraulic

    Tractor with ripper attachment

    Front End loader

    Concrete Mixer 0.28 Cum

    Motar Grader

    Air Compressor

    Bitumen boiler oil fired (Bitumen Spraying)

    LEAD, LOADING & UNLOADING STATEMENT

    RATES FOR CONVEYANCE BY MACHINERY

    For Earth/Gravel/Sand/Morrum/Lime/Surki (per Cum):

    Hrs. hire charges of Tipper 5.00 Cum @ Rs.

    Penumatic Road Roller (Static Roller

    Tipper 5.5 Cum

    HIRE CHARGES OF MACHINERY

    Hire charges of Tipper 5.00

    Cum capacity

    Hire charges of Tipper 10

    Tonnes capacity

    Hire charges of Water Tanker

    8000 Ltrs capacity

    Hire charges of Truck 10

    Tonnes capacity

    Hire charges of FE loader

    1.00 Cum bucket capacity @

    45 Cum

    Hrs. crew charges of Tipper 5.00 Cum @ Rs.

    add area allowance at 0% on Rs.

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    49/87

    0.00 26.32 Rs. 0.00

    Total rate for 1.00 Cum Rs. 26.32

    2 Lead up to 2 Km:

    Out ut = 5.00 Cum Rate Per Amount

    0.21 456.20 Hour Rs. 95.80

    0.21 280.70 Hour Rs. 58.95

    0.21 140.40 Hour Rs. 29.48

    0.00 29.48 Rs. 0.00

    Rate fo 5.00 Cum Rs. 184.23Rate fo 1.00 Cum Rs. 36.85

    0.00 36.85 Hour Rs. 0.00

    Total rate for 1.00 Cum Rs. 36.85

    3 Lead up to 3 Km:

    Out put = 5.00 Cum Rate Per Amount

    0.28 456.20 Hour Rs. 127.74

    0.28 280.70 Hour Rs. 78.60

    0.28 140.40 Hour Rs. 39.31

    0.00 39.31 Rs. 0.00

    Rate fo 5.00 Cum Rs. 245.65

    Rate fo 1.00 Cum Rs. 49.13

    0.00 49.13 Hour Rs. 0.00

    Total rate for 1.00 Cum Rs. 49.13

    4 Lead up to 4 Km:

    Out put = 5.00 Cum Rate Per Amount

    0.34 456.20 Hour Rs. 155.11

    0.34 280.70 Hour Rs. 95.44

    0.34 140.40 Hour Rs. 47.74

    0.00 47.74 Rs. 0.00

    Rate fo 5.00 Cum Rs. 298.29Rate fo 1.00 Cum Rs. 59.66

    0.00 59.66 Hour Rs. 0.00

    Total rate for 1.00 Cum Rs. 59.66

    5 Lead up to 5 Km:

    Out ut = 5.00 Cum Rate Per Amount

    0.40 456.20 Hour Rs. 182.48

    0.40 280.70 Hour Rs. 112.28

    0.40 140.40 Hour Rs. 56.16

    0.00 56.16 Rs. 0.00

    Rate fo 5.00 Cum Rs. 350.92

    Rate fo 1.00 Cum Rs. 70.180.00 70.18 Hour Rs. 0.00

    Total rate for 1.00 Cum Rs. 70.18

    6 Lead for every Km from 5 to 30 Km:

    Out put = 5.00 Cum Rate Per Amount

    0.06 456.20 Hour Rs. 27.37

    0.06 280.70 Hour Rs. 16.84

    0.06 140.40 Hour Rs. 8.42

    0.00 8.42 Rs. 0.00

    Rate fo 5.00 Cum Rs. 52.63

    add area allowance at 0% on Rs.

    add overheads and contractors profit at 0%

    on Rs.

    Hrs. hire charges of Tipper 5.00 Cum @ Rs.

    Hrs. fuel charges of Tipper 5.00 Cum @ Rs.

    Hrs. crew charges of Tipper 5.00 Cum @ Rs.

    Hrs. fuel charges of Tipper 5.00 Cum @ Rs.

    Hrs. crew charges of Tipper 5.00 Cum @ Rs.

    add area allowance at 0% on Rs.

    add overheads and contractors profit at 0%

    on Rs.

    Hrs. hire charges of Tipper 5.00 Cum @ Rs.

    Hrs. fuel charges of Tipper 5.00 Cum @ Rs.

    Hrs. fuel charges of Tipper 5.00 Cum @ Rs.

    Hrs. crew charges of Tipper 5.00 Cum @ Rs.

    add area allowance at 0% on Rs.

    add overheads and contractors profit at 0%

    on Rs.

    add area allowance at 0% on Rs.

    Hrs. crew charges of Tipper 5.00 Cum @ Rs.

    add area allowance at 0% on Rs.

    add overheads and contractors profit at 0%

    on Rs.

    Hrs. hire charges of Tipper 5.00 Cum @ Rs.

    add overheads and contractors profit at 0%

    on Rs.

    Hrs. hire charges of Tipper 5.00 Cum @ Rs.

    Hrs. fuel charges of Tipper 5.00 Cum @ Rs.

    Hrs. crew charges of Tipper 5.00 Cum @ Rs.

    Hrs. hire charges of Tipper 5.00 Cum @ Rs.

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    50/87

    Rate fo 1.00 Cum Rs. 10.53

    0.00 10.53 Hour Rs. 0.00

    Total rate for 1.00 Cum Rs. 10.53

    7 Lead for every Km beyond 30 Km:

    Out put = 5.00 Cum Rate Per Amount

    0.05 456.20 Hour Rs. 22.81

    0.05 280.70 Hour Rs. 14.04

    0.05 140.40 Hour Rs. 7.02

    0.00 7.02 Rs. 0.00

    Rate fo 5.00 Cum Rs. 43.87

    Rate fo 1.00 Cum Rs. 8.77

    0.00 8.77 Rs. 0.00

    Total rate for 1.00 Cum Rs. 8.77

    B)

    1 Lead u to 1 Km:

    Out put = 5.00 Cum Rate Per Amount

    0.15 456.20 Hour Rs. 68.43

    0.15 280.70 Hour Rs. 42.11

    0.15 140.40 Hour Rs. 21.060.00 21.06 Rs. 0.00

    Rate fo 5.00 Cum Rs. 131.60

    Rate fo 1.00 Cum Rs. 26.32

    0.00 26.32 Rs. 0.00

    Total rate for 1.00 Cum Rs. 26.32

    2 Lead up to 2 Km:

    Out put = 5.00 Cum Rate Per Amount

    0.21 456.20 Hour Rs. 95.80

    0.21 280.70 Hour Rs. 58.95

    0.21 140.40 Hour Rs. 29.48

    0.00 29.48 Rs. 0.00

    Rate fo 5.00 Cum Rs. 184.23Rate fo 1.00 Cum Rs. 36.85

    0.00 36.85 Hour Rs. 0.00

    Total rate for 1.00 Cum Rs. 36.85

    3 Lead u to 3 Km:

    Out put = 5.00 Cum Rate Per Amount

    0.28 456.20 Hour Rs. 127.74

    0.28 280.70 Hour Rs. 78.60

    0.28 140.40 Hour Rs. 39.31

    0.00 39.31 Rs. 0.00

    Rate fo 5.00 Cum Rs. 245.65

    Rate fo 1.00 Cum Rs. 49.130.00 49.13 Hour Rs. 0.00

    Total rate for 1.00 Cum Rs. 49.13

    4 Lead up to 4 Km:

    Out put = 5.00 Cum Rate Per Amount

    0.34 456.20 Hour Rs. 155.11

    0.34 280.70 Hour Rs. 95.44

    0.34 140.40 Hour Rs. 47.74

    0.00 47.74 Rs. 0.00

    Rate fo 5.00 Cum Rs. 298.29

    add area allowance at 0% on Rs.

    Hrs. crew charges of Tipper 5.00 Cum @ Rs.

    add area allowance at 0% on Rs.

    Hrs. fuel charges of Tipper 5.00 Cum @ Rs.

    add overheads and contractors profit at 0%

    on Rs.

    Hrs. hire charges of Tipper 5.00 Cum @ Rs.

    Hrs. hire charges of Tipper 5.00 Cum @ Rs.

    Hrs. fuel charges of Tipper 5.00 Cum @ Rs.

    Hrs. fuel charges of Tipper 5.00 Cum @ Rs.

    Hrs. crew charges of Tipper 5.00 Cum @ Rs.

    add overheads and contractors profit at 0%

    on Rs.

    Hrs. hire charges of Tipper 5.00 Cum @ Rs.

    add area allowance at 0% on Rs.

    Hrs. fuel charges of Tipper 5.00 Cum @ Rs.

    add overheads and contractors profit at 0%

    on Rs.

    Hrs. crew charges of Tipper 5.00 Cum @ Rs.

    Hrs. crew charges of Tipper 5.00 Cum @ Rs.

    Hrs. hire charges of Tipper 5.00 Cum @ Rs.

    add overheads and contractors profit at 0%

    on Rs.

    Hrs. hire charges of Tipper 5.00 Cum @ Rs.

    Hrs. fuel charges of Tipper 5.00 Cum @ Rs.

    Hrs. crew charges of Tipper 5.00 Cum @ Rs.add area allowance at 0% on Rs.

    add area allowance at 0% on Rs.

    add overheads and contractors profit at 0%

    on Rs.

    For Rubble/Size stones/Cut stones/Coarse aggregates (per Cum):

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    51/87

    Rate fo 1.00 Cum Rs. 59.66

    0.00 59.66 Hour Rs. 0.00

    Total rate for 1.00 Cum Rs. 59.66

    5 Lead up to 5 Km:

    Out put = 5.00 Cum Rate Per Amount

    0.40 456.20 Hour Rs. 182.48

    0.40 280.70 Hour Rs. 112.28

    0.40 140.40 Hour Rs. 56.16

    0.00 56.16 Rs. 0.00

    Rate fo 5.00 Cum Rs. 350.92

    Rate fo 1.00 Cum Rs. 70.18

    0.00 70.18 Hour Rs. 0.00

    Total rate for 1.00 Cum Rs. 70.18

    6 Lead for every Km from 5 to 30 Km:

    Out put = 5.00 Cum Rate Per Amount

    0.06 456.20 Hour Rs. 27.37

    0.06 280.70 Hour Rs. 16.84

    0.06 140.40 Hour Rs. 8.42

    0.00 8.42 Rs. 0.00Rate fo 5.00 Cum Rs. 52.63

    Rate fo 1.00 Cum Rs. 10.53

    0.00 10.53 Hour Rs. 0.00

    Total rate for 1.00 Cum Rs. 10.53

    7 Lead for every Km beyond 30 Km:

    Out ut = 5.00 Cum Rate Per Amount

    0.05 456.20 Hour Rs. 22.81

    0.05 280.70 Hour Rs. 14.04

    0.05 140.40 Hour Rs. 7.02

    0.00 7.02 Rs. 0.00

    Rate fo 5.00 Cum Rs. 43.87Rate fo 1.00 Cum Rs. 8.77

    0.00 8.77 Rs. 0.00

    Total rate for 1.00 Cum Rs. 8.77

    F)

    1 Lead up to 1 Km:

    Out put = 3000 Nos Rate Per Amount

    0.15 422.80 Hour Rs. 63.42

    0.15 280.70 Hour Rs. 42.11

    0.15 140.40 Hour Rs. 21.06

    0.00 21.06 Rs. 0.00

    Rate fo 3000 Nos Rs. 126.59

    Rate fo 1000 Nos Rs. 42.20

    0.00 42.20 Rs. 0.00

    Total rate for 1000 Nos Rs. 42.20

    2 Lead up to 2 Km:

    Out put = 3000 Nos Rate Per Amount

    0.21 422.80 Hour Rs. 88.79

    add overheads and contractors profit at 0%

    on Rs.

    add overheads and contractors profit at 0%

    on Rs.

    Hrs. fuel charges of Tipper 5.00 Cum @ Rs.

    Hrs. hire charges of Tipper 5.00 Cum @ Rs.

    For Bricks (per 1000 Nos):

    Hrs. fuel charges of Tipper 5.00 Cum @ Rs.

    Hrs. crew charges of Tipper 5.00 Cum @ Rs.

    Hrs. hire charges of Truck 10 Tonnes capacity

    @ Rs.

    add area allowance at 0% on Rs.

    add overheads and contractors profit at 0%

    on Rs.

    Hrs. hire charges of Truck 10 Tonnes capacity

    @ Rs.

    Hrs. fuel charges of Truck 10 Tonnes capacity

    @ Rs.

    Hrs. crew charges of Truck 10 Tonnescapacity @ Rs.

    add area allowance at 0% on Rs.

    Hrs. crew charges of Tipper 5.00 Cum @ Rs.

    add area allowance at 0% on Rs.

    Hrs. crew charges of Tipper 5.00 Cum @ Rs.

    add area allowance at 0% on Rs.

    Hrs. hire charges of Tipper 5.00 Cum @ Rs.

    add overheads and contractors profit at 0%

    on Rs.

    add overheads and contractors profit at 0%

    on Rs.

    Hrs. hire charges of Tipper 5.00 Cum @ Rs.

    Hrs. fuel charges of Tipper 5.00 Cum @ Rs.

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    52/87

    0.21 280.70 Hour Rs. 58.95

    0.21 140.40 Hour Rs. 29.48

    0.00 29.48 Rs. 0.00

    Rate fo 3000 Nos Rs. 177.22

    Rate fo 1000 Nos Rs. 59.07

    0.00 59.07 Rs. 0.00

    Total rate for 1000 Nos Rs. 59.07

    3 Lead up to 3 Km:

    Out put = 3000 Nos Rate Per Amount

    0.28 422.80 Hour Rs. 118.38

    0.28 280.70 Hour Rs. 78.60

    0.28 140.40 Hour Rs. 39.31

    0.00 39.31 Rs. 0.00

    Rate fo 3000 Nos Rs. 236.29

    Rate fo 1000 Nos Rs. 78.76

    0.00 78.76 Rs. 0.00

    Total rate for 1000 Nos Rs. 78.76

    Hrs. fuel charges of Truck 10 Tonnes capacity

    @ Rs.

    add overheads and contractors profit at 0%

    on Rs.

    Hrs. fuel charges of Truck 10 Tonnes capacity

    @ Rs.

    Hrs. crew charges of Truck 10 Tonnes

    capacity @ Rs.

    Hrs. crew charges of Truck 10 Tonnes

    capacity @ Rs.

    add area allowance at 0% on Rs.

    add area allowance at 0% on Rs.

    add overheads and contractors profit at 0%

    on Rs.

    Hrs. hire charges of Truck 10 Tonnes capacity

    @ Rs.

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    53/87

    4 Lead up to 4 Km:

    Out put = 3000 Nos Rate Per Amount

    0.34 422.80 Hour Rs. 143.75

    0.34 280.70 Hour Rs. 95.44

    0.34 140.40 Hour Rs. 47.74

    0.00 47.74 Rs. 0.00Rate fo 3000 Nos Rs. 286.93

    Rate fo 1000 Nos Rs. 95.64

    0.00 95.64 Rs. 0.00

    Total rate for 1000 Nos Rs. 95.64

    5 Lead up to 5 Km:

    Out put = 3000 Nos Rate Per Amount

    0.40 422.80 Hour Rs. 169.12

    0.40 280.70 Hour Rs. 112.28

    0.40 140.40 Hour Rs. 56.16

    0.00 56.16 Rs. 0.00

    Rate fo 3000 Nos Rs. 337.56

    Rate fo 1000 Nos Rs. 112.52

    0.00 112.52 Rs. 0.00

    Total rate for 1000 Nos Rs. 112.52

    6 Lead for every Km beyond 5 Kms up to 30 Kms:

    Out ut = 3000 Nos Rate Per Amount

    0.06 422.80 Hour Rs. 25.37

    0.06 280.70 Hour Rs. 16.84

    0.06 140.40 Hour Rs. 8.42

    0.00 8.42 Rs. 0.00

    Rate fo 3000 Nos Rs. 50.63

    Rate fo 1000 Nos Rs. 16.88

    0.00 16.88 Rs. 0.00

    Total rate for 1000 Nos Rs. 16.88

    7 Lead for ever Km be ond 30 Kms:

    Out put = 3000 Nos Rate Per Amount

    0.05 422.80 Hour Rs. 21.14

    0.05 280.70 Hour Rs. 14.04

    0.05 140.40 Hour Rs. 7.02

    0.00 7.02 Rs. 0.00

    Rate fo 3000 Nos Rs. 42.20

    Rate fo 1000 Nos Rs. 14.07

    0.00 14.07 Rs. 0.00

    Total rate for 1000 Nos Rs. 14.07

    add area allowance at 0% on Rs.

    add overheads and contractors profit at 0%

    on Rs.

    Hrs. hire charges of Truck 10 Tonnes capacity

    @ Rs.Hrs. fuel charges of Truck 10 Tonnes capacity

    @ Rs.

    add overheads and contractors profit at 0%

    on Rs.

    add area allowance at 0% on Rs.

    add overheads and contractors profit at 0%

    on Rs.

    Hrs. hire charges of Truck 10 Tonnes capacity

    @ Rs.

    Hrs. crew charges of Truck 10 Tonnes

    capacity @ Rs.

    add area allowance at 0% on Rs.

    Hrs. fuel charges of Truck 10 Tonnes capacity

    @ Rs.

    Hrs. crew charges of Truck 10 Tonnes

    capacity @ Rs.

    Hrs. fuel charges of Truck 10 Tonnes capacity

    @ Rs.

    Hrs. crew charges of Truck 10 Tonnescapacity @ Rs.

    add area allowance at 0% on Rs.

    add overheads and contractors profit at 0%

    on Rs.

    Hrs. hire charges of Truck 10 Tonnes capacity

    @ Rs.

    Hrs. fuel charges of Truck 10 Tonnes capacity

    @ Rs.

    Hrs. crew charges of Truck 10 Tonnes

    capacity @ Rs.

    Hrs. hire charges of Truck 10 Tonnes capacity

    @ Rs.

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    54/87

    A)

    (i) Loading charges:

    Out put = 5.50 Cum Rate Per Amount

    a) Labour:

    0.01 320.00 day Rs. 3.20

    0.25 280.00 da Rs. 70.00

    Rs. 73.200.00 73.20 Rs. 0.00

    Total labour charges Rs. 73.20

    Rate fo 5.50 Cum Rs. 73.20

    Rate fo 1.00 Cum Rs. 13.31

    0.00 13.31 Rs. 0.00

    Total rate for 1.00 Cum Rs. 13.31

    ii Unloadin char es:

    Out ut = 5.50 Cum Rate Per Amount

    a) Labour:

    0.005 320.00 day Rs. 1.60

    0.125 280.00 day Rs. 35.00

    Rs. 36.60

    0.00 36.60 Rs. 0.00

    Total labour charges Rs. 36.60

    Rate fo 5.50 Cum Rs. 36.60

    Rate fo 1.00 Cum Rs. 6.65

    0.00 6.65 Rs. 0.00

    Total rate for 1.00 Cum Rs. 6.65

    B)

    (i) Loading charges:

    Out put = 5.50 Cum Rate Per Amount

    a) Labour:0.02 320.00 day Rs. 6.40

    0.50 280.00 da Rs. 140.00

    Rs. 146.40

    0.00 146.40 Rs. 0.00

    Total labour charges Rs. 146.40

    Rate fo 5.50 Cum Rs. 146.40

    Rate fo 1.00 Cum Rs. 26.62

    0.00 26.62 Rs. 0.00

    Total rate for 1.00 Cum Rs. 26.62

    ii Unloadin char es:

    Out put = 5.50 Cum Rate Per Amounta) Labour:

    0.01 320.00 day Rs. 3.20

    0.25 280.00 day Rs. 70.00

    Rs. 73.20

    0.00 73.20 Rs. 0.00

    Total labour charges Rs. 73.20

    Rate fo 5.50 Cum Rs. 73.20

    Rate fo 1.00 Cum Rs. 13.31

    0.00 13.31 Rs. 0.00

    Total rate for 1.00 Cum Rs. 13.31

    add overheads and contractors profit at 0%

    on Rs.

    day Head mazdoor

    day Mazdoor

    add overheads and contractors profit at 0%

    on Rs.

    add area allowance at 0% on Rs.

    add overheads and contractors profit at 0%

    on Rs.

    day Mazdoor

    day Head mazdoor

    day Head mazdoor

    add area allowance at 0% on Rs.

    day Mazdoor

    add area allowance at 0% on Rs.

    add overheads and contractors profit at 0%

    on Rs.

    For Lime, Agrregate, Stone Boulder, Brick aggregate, Kankar, Building rubbish,

    Crushed slag, Stone for masonry work (per Cum):

    add area allowance at 0% on Rs.

    LOADING & UNLOADING CHARGES BY MANUAL MEANS (EXCLUDING IDLE HIRE

    CHARGES OF TRUCKS)

    For Earth, Sand, Morrum, Manure, Fly Ash (per Cum):

    day Head mazdoor

    day Mazdoor

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    55/87

    C)

    (i) Loading charges:

    Out put = 10.00 MT Rate Per Amount

    a Labour:

    0.06 320.00 day Rs. 19.20

    1.50 280.00 day Rs. 420.00

    Rs. 439.20

    0.00 439.20 Rs. 0.00

    Total labour char es Rs. 439.20

    Rate fo 10.00 MT Rs. 439.20

    Rate fo 1.00 MT Rs. 43.92

    0.00 43.92 Rs. 0.00

    Total rate for 1.00 MT Rs. 43.92

    (ii) Unloading & Stacking charges:

    Out put = 10.00 MT Rate Per Amount

    a Labour:

    0.06 320.00 day Rs. 19.20

    1.50 280.00 day Rs. 420.00

    Rs. 439.20

    0.00 439.20 Rs. 0.00

    Total labour charges Rs. 439.20

    Rate fo 10.00 MT Rs. 439.20

    Rate fo 1.00 MT Rs. 43.92

    0.00 43.92 Rs. 0.00

    Total rate for 1.00 MT Rs. 43.92

    D)

    i Loadin char es:

    Out put = 10.00 MT Rate Per Amount

    a) Labour:

    0.07 320.00 day Rs. 22.40

    1.80 280.00 day Rs. 504.00

    Rs. 526.40

    0.00 526.40 Rs. 0.00

    Total labour charges Rs. 526.40

    Rate fo 10.00 MT Rs. 526.40

    Rate fo 1.00 MT Rs. 52.64

    0.00 52.64 Rs. 0.00

    Total rate for 1.00 MT Rs. 52.64

    (ii) Unloading & Stacking charges:

    Out ut = 10.00 MT Rate Per Amount

    a) Labour:0.07 320.00 day Rs. 22.40

    1.80 280.00 day Rs. 504.00

    Rs. 526.40

    0.00 526.40 Rs. 0.00

    Total labour charges Rs. 526.40

    Rate fo 10.00 MT Rs. 526.40

    Rate fo 1.00 MT Rs. 52.64

    0.00 52.64 Rs. 0.00

    Total rate for 1.00 MT Rs. 52.64

    day Mazdoor

    add area allowance at 0% on Rs.

    add overheads and contractors profit at 0%

    on Rs.

    day Head mazdoor

    day Mazdoor

    add area allowance at 0% on Rs.

    add overheads and contractors profit at 0%

    on Rs.

    add overheads and contractors profit at 0%

    on Rs.

    day Head mazdoor

    day Mazdoor

    add area allowance at 0% on Rs.

    add overheads and contractors profit at 0%

    on Rs.

    For Structural steel, Steel bars (per Tonne):

    day Head mazdoor

    add area allowance at 0% on Rs.

    For Cement (per Tonne):

    day Head mazdoor

    day Mazdoor

  • 8/13/2019 Godavarru Works With SSR 2013-14 Revised Specification 16-12-2013

    56/87

    E)

    (i) Loading charges:

    Out put = 2000.00 Nos Rate Per Amount

    a) Labour:

    0.01 320.00 da Rs. 3.20

    0.25 280.00 day Rs. 70.00

    Rs. 73.20

    0.00 73.20 Rs. 0.00

    Total labour charges Rs. 73.20

    Rate fo 2000 Nos Rs. 73.20

    Rate fo 1000 Nos Rs. 36.60

    0.00 36.60 Rs. 0.00

    Total rate for 1000 Nos Rs. 36.60

    (ii) Unloading & Stacking charges:

    Out put = 2000.00 Nos Rate Per Amount

    a) Labour:

    0.01 320.00 day Rs. 3.20

    0.25 280.00 day Rs. 70.00

    Rs. 73.20

    0.00 73.20 Rs. 0.00

    Total labour charges Rs. 73.20

    Rate fo 2000 Nos Rs. 73.20

    Rate fo 1000 Nos Rs. 36.60

    0.00 36.60 Rs. 0.00

    Total rate for 1000 Nos Rs. 36.60

    A)

    (i) Loading charges:

    Out put = 5.50 Cum Rate Per Amounta Labour:

    0.01 320.00 day Rs. 3.20

    0.25 280.00 day Rs. 70.00

    Rs. 73.20

    0.00 73.20 Rs. 0.00

    Total labour char es Rs. 73.20

    b) Machinery:

    0.50 422.80 Hour Rs. 211.40

    0.50 280.70 Hour Rs. 140.35

    0.50 140.40 Hour Rs. 70.20

    0.00 70.20 Rs. 0.00

    Total machiner char es Rs. 421.95

    Total labour and machinery charges Rs. 495.15

    Rate fo 5.50 Cum Rs. 495.15

    Rate fo 1.00 Cum Rs. 90.03

    0.00 90.03 Rs. 0.00

    Total rate for 1.00 Cum Rs. 90.03

    add area allowance at 0% on Rs.

    Hrs. crew charges of Truck 10 Tonnes

    capacity @ Rs.add area allowance at 0% on Rs.

    day Mazdoor

    add area allowance at 0% on Rs.

    add overheads and contractors profit at 0%