© Scott Ambler + Associates 1 Governance, Phases, and Milestones are not Agile Dirty Words! Mark Lines, Scott Ambler + Associates Co-creator of Disciplined Agile Delivery Enterprise Transformation Coach Helping to create Agile and Lean enterprises around the world @Mark_Lines

Upload: others

Post on 28-May-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

© Scott Ambler + Associates 1

Governance, Phases, and Milestones are not

Agile Dirty Words!

Mark Lines, Scott Ambler + AssociatesCo-creator of Disciplined Agile Delivery

Enterprise Transformation Coach

Helping to create Agile and Lean enterprises around the world

@Mark_Lines

Page 2: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

DAD Has Caught On! - Organizations using

Disciplined Agile Delivery (DAD)

© Scott Ambler + Associates 2

Page 3: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Disciplined Agile Delivery (DAD) is a process decision framework

The key characteristics of DAD:

– People-first

– Goal-driven

– Hybrid agile

– Learning-oriented

– Full delivery lifecycle

– Solution focused

– Risk-value lifecycle

– Enterprise aware

3© Scott Ambler + Associates

Page 4: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Scrum

Extreme

Programming

LeanKanban

DAD is a Hybrid Framework

4

Unified Process Agile Modeling

Agile Data“Traditional”Outside In Dev.

DevOps …and more

DAD leverages proven strategies from several sources,

providing a decision framework to guide your adoption and

tailoring of them in a context-driven manner.

SAFe

© Scott Ambler + Associates

Page 5: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

DAD is Goal-Driven, Not Prescriptive

© Scott Ambler + Associates 5

Page 6: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

6© Scott Ambler + Associates

Page 7: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Functional Requirements: Potential Model Types

7

Usage

Epic/User Story

Persona

Usage Scenario

Story Mapping

UML Use Case Diagram

Domain

Domain/Conceptual Model

Logical Data Model (LDM)

UML Class Diagram

UML Component Diagram

ProcessValue Stream Map

Business Process Model

Data Flow Diagram (DFD)

Flow Chart

UML Activity Diagram

UML State Chart

User Interface (UI)

UI Flow Diagram

UI Prototype (Low Fidelity)

UI Prototype (High Fidelity)

UI Specification

And many more…

General Impact (Mind) Map Business Rule

Context Diagram Feature/Shall Statements

© Scott Ambler + Associates

Page 8: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Some Scope Modeling Options (from the book)

8© Scott Ambler + Associates

Page 9: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

More Scope Modeling Options (from the book)

9© Scott Ambler + Associates

Page 10: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

DAD Initiatives have Milestones and may have Phases

10© Scott Ambler + Associates

Inception Construction Transition

Initiate the endeavor Development of a potentially consumable solution Deploy the solution

Stakeholder vision

Proven architecture

Sufficient functionality

Production readyContinued viability

(several)

Delighted stakeholders

2014 © Disciplined Agile Consortium

Milestone Reviews should be lightweight!

Page 11: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

© Scott Ambler + Associates 11

Page 12: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Basic/Agile Lifecycle

12

A full Scrum-based agile delivery lifecycle.

© Scott Ambler + Associates

Page 13: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

© Scott Ambler + Associates 13

Page 14: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Lean Lifecycle

14

A full lean delivery lifecycle

© Scott Ambler + Associates

Page 15: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

The Phases Disappear Over Time

15

First release: Inception Construction Transition

Second release: I Construction T

Third release: I Construction T

Nth+ releases: C CT C C TT T

.

.

.

© Scott Ambler + Associates

Page 16: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

© Scott Ambler + Associates 16

Page 17: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Lean Continuous Delivery Lifecycle

17

Your evolutionary

end goal?

© Scott Ambler + Associates

Page 18: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

© Scott Ambler + Associates 18

Page 19: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Exploratory “Lean Startup” Lifecycle

19

Sometimes it takes time to identify what your

stakeholders actually need

© Scott Ambler + Associates

Page 20: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

© Scott Ambler + Associates 20

Choice is good!

40%

20%

10%

10%

10%

5%

5%

30%

15%

15%

50%

90%

5years

2years

Current

TypicalEvolutionofLifecycleMix

Agile/Scrum Lean Exploratory/LeanStart-up ContinuousDelivery Traditional

Page 21: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

© Scott Ambler + Associates 21

Governing

Disciplined

Agile Teams

Page 22: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Many Organizations Are Serious About Governance

The farther to the right an organization,

the greater the chance they’re focused on governance

22

Moore’s

Adoption Curve

© Scott Ambler + Associates

Page 23: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Governance Should Address a Range of Issues

• Team roles and responsibilities

• Individual roles and responsibilities

• Decision rights and decision making process

• Governing body

• Exceptions and escalation processes

• Knowledge sharing processes

• Metrics strategy

• Risk mitigation

• Reward structure

• Status reporting

• Audit processes

• Policies, standards, and guidelines

• Artifacts and their lifecycles

© Scott Ambler + Associates 23

Page 24: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Why is Governance Important?

• Sustain and extend your IT strategies and objectives, which in turn should

reflect your corporate strategies and objectives

• Determine how the company will execute its strategy by selecting and

prioritizing the most valuable initiatives to undertake

• Empower teams to carry out their work

• Help to ensure that delivery teams:

– Regularly and consistently create real business value

– Provide appropriate return on investment (ROI)

– Deliver consumable solutions in a timely and relevant manner

– Work effectively with their project stakeholders

– Work effectively with their IT colleagues

– Adopt processes and organizational structures that encourage

successful IT solution delivery

– Present accurate and timely information to project stakeholders

– Mitigate the risks associated with the project

24© Scott Ambler + Associates

Page 25: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Why Traditional Governance Strategies Won’t Work

25

Traditional assumptions that conflict with agile:

– You can judge team progress from generation of artifacts

– Delivery teams should work in a serial manner

– You want teams to follow a common, repeatable process

– Projects should be driven by senior IT management

© Scott Ambler + Associates

Page 26: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Principles of Agile Governance

Collaboration over conformance

Enablement over inspection

Continuous monitoring over quality gates

Transparency over management reporting

© Scott Ambler + Associates 26

Page 27: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

DAD Practices that Support Governance

• “Standard” agile practices:

– Coordination meeting

– Iteration demonstrations

– All-hands demonstrations

– Retrospective

– Information radiators/Visual management

• Disciplined practices:

– Risk-value lifecycle

– Explicit light-weight milestones

– Follow enterprise development guidelines

– Work closely with enterprise professionals

– Development intelligence via automated

dashboards

27© Scott Ambler + Associates

Page 28: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Measuring Agile Teams

• Talk to people; don’t manage to the metrics

• Measure teams, not individuals

• Collect several metrics

• Trends are better than scalar values

• Empirical observation is important but limited

• Prefer automated metrics

• Some metrics must be gathered manually

• Prefer pull versus push reporting

• Beware scientific facades

• The value of many metrics diminishes over time

• If you collect no metrics at all you’re flying blind

• If you collect too many metrics you may be flying blinded

28© Scott Ambler + Associates

Page 29: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Potential Metrics

• Acceleration

• Activity time

• Age of work items

• Blocking work items

• Build health

• Business value delivered

• Code quality

• Cumulative flow

• Cycle time

• Defect density

• Defect trend

• Iteration burndown

• Lead time

• Net present value (NPV)

• Ranged release burndown/up

• Release burndown/up

• Return on investment (ROI)

• Stakeholder satisfaction

• Net promoter score

• Team morale

• Test coverage

• Velocity

• Work in process (WIP)

29© Scott Ambler + Associates

Page 30: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Inception Phase Milestone: Stakeholder Vision

30© Scott Ambler + Associates

Page 31: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

What’s in a Project Vision?• Could be thought of as an agile project charter

• Typically outlines:

– Goals of the project team and who is on it

– High-level scope of the current release

– Technical overview of the solution

– Outline of the plan to do the required work

– Could include feasibility information

• Could also describe:

– Business problem being addressed

– High-level schedule and estimates

– Key milestones

– Stakeholders

– Funding models

– Project risks and constraints

– Process/method used (e.g. DAD), governance strategy

– Key assumptions

31© Scott Ambler + Associates

Page 32: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Milestone: Bringing Stakeholders to Agreement around

your Vision

• Inception is complete and you can enter the Construction phase

when:

– Your stakeholders agree that it makes sense to proceed based upon the

achievable scope, schedule, budget, constraints, and other criteria

related to your business case

– The risks have been identified and seem tolerable

– There is agreement on using a minimalist and agile process for building

the solution

– The team and environment have been set up that supports collaborative

teamwork, or are in the process of being so

– The process and governance strategies have been agreed to by both

your team and your stakeholders

32© Scott Ambler + Associates

Page 33: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Develop Common Vision Goal

© Scott Ambler + Associates 33

Page 34: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

34

Information Radiators

Light-weight

Detailed

© Scott Ambler + Associates

Page 35: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

An Example of a Lightweight Milestone Review…

35

Scenario:• End of 2 week Inception phase

• Invitees to review meeting

• Sponsor

• Product Owner

• Delivery Team

• Other stakeholders

• Architecture

• Data

• Governance

• Support

© Scott Ambler + Associates

Page 36: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Sample Inception Milestone Review Deck

© Scott Ambler + Associates 36

Page 37: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

An Example of a Construction Iteration Review…

© Scott Ambler + Associates 37

Scenario:• End of 2 week Construction iteration

• Invitees to review meeting

• Delivery Team

• Product Owner

• Other stakeholders

• Architecture

• Data

• Governance

• Support

Page 38: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Sample Iteration Review Deck

© Scott Ambler + Associates 38

Page 39: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

© Scott Ambler + Associates 39

Governing

IT

Page 40: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

© Scott Ambler + Associates 40

Governance cuts across all process blades

Page 41: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

© Scott Ambler + Associates 41

IT Governance Governance Views

Guidance Detail

SecurityDataDevelopmentOperationsArchitecturePortfolio

PrinciplesHigh-level rulesChecklistsDetailed definition

Develop Guidance

Collaborative (enterprise level)Collaborative (team level)Top-DownBottom-Up

Monitor

Direct interactionTeam dashboardPortfolio dashboardDirect observationStatus report

2014 © Disciplined Agile Consortium

Define Roles and Responsibilities

Share Knowledge

MeasureAutomated metricsManual metrics

Self-organizingCollaborativeDictatedTop-DownBottom-Up

Communities of practicePractitioner presentationDiscussion forumsExpert systemDevelop communication planKnowledgebaseNewsletterWord of mouth

Develop Metrics

Goal-Question-Metric (GQM)Targeted metricsCommon core metrics“Standard” team metrics

Manage Enterprise Risk

Aggregate organizational riskAggregate IT risk

There are many factors to

consider when adopting

Agile IT Governance

Page 42: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Let’s illustrate a few examples of where we need

to consider governance across IT…

© Scott Ambler + Associates 42

Page 43: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

© Scott Ambler + Associates 43

Page 44: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Governance –

Guidance for Portfolio

Management

© Scott Ambler + Associates 44

Page 45: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

© Scott Ambler + Associates 45

Page 46: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Governance – Guidance

for Enterprise Architecture

© Scott Ambler + Associates 46

Page 47: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

© Scott Ambler + Associates 47

Page 48: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Governance – Guidance

for Reuse Engineering

© Scott Ambler + Associates 48

Page 49: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

© Scott Ambler + Associates 49

Page 50: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Governance – Guidance

for Operations

© Scott Ambler + Associates 50

Page 51: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

In Summary…

• DAD is “pragmatic agile”, not purist or prescriptive

• Flexibility of lifecycle approach with the consistency of a framework

• A collection of good ideas to help you to adjust your approach for

your context

• Not difficult to apply – if you are using Scrum/XP or Lean you are

using a subset of DAD already

• Agile Governance built-in

© Scott Ambler + Associates 51

Disciplined Agile provides a

roadmap for pragmatic Enterprise

Agile

Page 52: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

For More Information…

• Scott Ambler + Associates

– www.scottambler.com

– Mark [at] scottambler.com

@mark_lines

• Disciplined Agile Delivery: A Practitioner’s Guide, by Scott Ambler &

Mark Lines

• DAD Blog: www.DisciplinedAgileDelivery.com

• DAD Certification: www.DisciplinedAgileConsortium.org

• DAD LinkedIn Discussion Group

– http://www.linkedin.com/groups/Disciplined-Agile-Delivery-4685263

• DAD YouTube Channel

– https://www.youtube.com/channel/UCcWJ20C86Mzxcsqb73AReHQ

© Scott Ambler + Associates 52

Page 53: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Scott Ambler + Associates is the thought leader behind the Disciplined

Agile Delivery (DAD) framework and its application. We are a boutique

IT management consulting firm that advises organizations to be more

effective applying disciplined agile and lean processes within the

context of your business.

Our website is ScottAmbler.com

We can help

© Scott Ambler + Associates 53

Page 54: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

PRINCE2 Processes/Stages & DAD Phases

PRINCE2® Process Model

DAD Basic/Agile Lifecycle

DAD’s phases map well to

PRINCE2’s processes & stages

Stage 1 Stage 2 Stage 3

Note: This should be a short-term mapping, not end state!

© Scott Ambler + Associates 54

Page 55: Governance, Phases, and Milestones are not Agile Dirty Words!8wriz40sy4t1ph08pf5vo1dp-wpengine.netdna-ssl.com/wp... · 2018-05-02 · Governance, Phases, and Milestones are not Agile

Recommendation: Apply Low formality In Project

Initiation Document (PID) Where Possible

• DAD’s Vision Statement

– Team Makeup

– Initial Scope

– Initial Technical Strategy

– Initial Release Plan

– Funding

– Identified Risks

• PRINCE2’s PID

– Project Definition

• Background

• Scope and Exclusions

• Constraints & Assumptions

• Users and other parties

• Interfaces

– Project Approach

• Business Case

• Team Structure

• Role Descriptions

• Quality Management Strategy

• Configuration Management Strategy

• Risk Management Strategy

• Communication Management Strategy

• Project Plan

• Project Controls

• Tailoring of PRINCE2

© Scott Ambler + Associates 55