government contracting update series · goal: to clarify the application of the federal information...

42
Government Contracting Update Series Stay Current on Federal Contracting Changes & Developments Paul E. Pompeo, Arnold & Porter LLP Sajeev Malaveetil, EY Government Contract Services October 6, 2016 1

Upload: others

Post on 25-May-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Government Contracting Update SeriesStay Current on Federal Contracting Changes &

Developments

Paul E. Pompeo, Arnold & Porter LLP

Sajeev Malaveetil, EY Government Contract Services

October 6, 2016

1

Page 2: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Agenda

Federal Acquisition Regulation (FAR)

Defense Federal Acquisition Regulation Supplement

(DFARS)

Cost Accounting Standards (CAS)

Defense Contract Audit Agency (DCAA) and the

Defense Contract Management Agency (DCMA)

guidance/policy

Notable Legal Decisions

2

Page 3: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Federal Acquisition Regulation

3

Page 4: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Information on Corporate Contractor Performance and Integrity

(FAR Case 2013-020)

Final Rule – Effective April 16, 2016

Offerors will be required to report and certify information regarding

immediate owners, subsidiaries or predecessors that held a

Federal contact or grant within the last three years

New provision 52.204-20 Predecessor of Offeror and annual

certification requirement

Contracting officers will begin to look at integrity of subsidiaries

and predecessors when assessing performance integrity and past

performance

Source: FAR Case 2013-020 – Federal Register 81 FR 11988, April 6, 20164

Page 5: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Basic Safeguarding of Contractor Information Systems

(FAR Case 2011-020)

Final Rule –Effective June 15, 2016

Adds a contract clause for the basic safeguarding of contractor

information systems that process, store, or transmit Federal

contract information

o DoD, GSA, and NASA will be developing FAR changes to

implement the OMB guidance when it is finalized

o Systems that contain classified information, or CUI such as

personally identifiable information, require more than the basic level

of protection

Goal: To clarify the application of the Federal Information

Security Management Act (FISMA) and the National Institute of

Standards and Technology (NIST) information systems

requirements to contractors and help create a greater

consistency in safeguarding practices across agencies

No exemptions for small entities 5

Source: FAR Case 2011-020 – Federal Register 81 FR 30439 May 16, 2016

Page 6: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

6

Small Business Subcontracting Improvements

(FAR Case 2014-003)

Final Rule –Effective November 1, 2016

The changes being implemented in this final rule include the

following:

Requiring prime contractors to make good faith efforts to utilize their proposed

small business subcontractors during performance of a contract to the same

degree the prime contractor relied on the small business in preparing its bid or

proposal

Authorizing contracting officers to calculate subcontracting goals in terms of

total contract dollars in addition to the required goals in terms of total

subcontracted dollars

Providing contracting officers with the discretion to require a subcontracting

plan in instances where a small business represents its size as other than

small business

Requiring subcontracting plans even for modifications under the

subcontracting plan threshold if said modifications would cause the contract to

exceed the plan threshold

Restricting prime contractors from prohibiting a subcontractor from discussing

payment of utilization matter with the contracting officer

Source: FAR CASE 2014-003 – Federal Register 81 FR 45833 July 14, 2016

Page 7: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Small Business Subcontracting Improvements (cont’d)

Requiring prime contractors to resubmit a corrected subcontracting

report within 30 days of receiving the contracting officer’s notice of

report rejection

Requiring prime contractors to provide the socioeconomic status of the

subcontractor in the notification to unsuccessful offerors for

subcontracts

Requiring prime contracts with subcontracting plans on task and

delivery order contracts to report order level subcontracting information

after November 2017

Funding agencies receiving small business subcontracting credit

On indefinite-delivery, indefinite-quantity contracts, the contracting

officer may establish subcontracting goals at the order level (but not a

new subcontracting plan)7

Page 8: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Audit of Settlement Proposals

(FAR Case 2015–039)

Proposed Rule – September 14, 2016

Proposal to amend the FAR to raise the dollar threshold

requirement for the audit of prime contract settlement proposals

and subcontract settlements from $100,000 to $750,000

Help alleviate contract close-out backlogs and enable

contracting officers to more quickly de-obligate excess funds

from terminated contracts

Small business impact: fewer small businesses will be subject

to audits of their termination settlement proposals

Comments due by November 14, 2016

8Source: FAR Case 2015-039 – Federal Register 81 FR 63158 September 14, 2016

Page 9: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Fair Pay and Safe Workplaces

(FAR Case 2014-025)

Final Rule – Effective October 25, 2016*

Implements 2014 E.O. 3673, Fair Pay and Safe Workplaces

Intended to increase efficiency and cost savings through contractor compliance

with labor laws

Creates Agency Labor Compliance Advisor (ALCA) to advise CO’s as it relates

to consideration of labor matters reported by prospective and existing

contractors

Simultaneously DOL final guidance issued

The rule creates a new FAR Subpart 22.20 - establishes new reporting

requirement, obligations and limitations to contractors as it relates to compliance

with labor and safety statutes and executive orders

1. Requirement to proactive report labor violations

2. Obligations for pay transparency to select covered employees

3. Restricts the use of mandatory arbitration as it relates to claims of violations

related to select labor matters

* Note: requirements are phased in over three years

9

Source: Federal Register 81 FR 58653 (FAR) and 81 FR 58653 (DOL), August 25, 2016

Page 10: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Fair Pay and Safe Workplaces (continued)

Requirements

Requirement to report labor violations

Contractors are require to report “administrative merit determinations, “arbitral award

decisions” and “civil judgments” for violations of 14 E.O. and Statutes related to labor

and safety

Pre-award: Reporting will be considered in making determinations of contractor

responsibility

Post award: Reporting will be evaluated related to labor compliance agreement,

exercising of options, contract termination, potential referral to SDO

COs with advice from ALCA should give consideration to mitigating factors

Obligations for pay transparency to select covered employees

Applies to covered employees and contractors subject to FLSA, DBA and SCA

Contractors will be required to provide employees with information related to pay, hours

worked, overtime hours paid, additions to wages and deductions from wages

Also requires written notification to independent contractors of their status as

independent contractors

Restricts the use of mandatory arbitration for as it relates to claims of violations relates to

select labor matters

Applies to contracts over $1M

Must obtain voluntary consent from the employee to arbitrate claims related to Title VII

of Civil Rights Act of 1964, sexual assault and sexual harassment

10

Page 11: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Fair Pay and Safe Workplaces (continued)

Phase-in of the rule

Phased Implementation Plan:

10/25/2016: Applicable to prime contracts over

$50M (report just one year)

01/01/2017: Pay transparency requirements kick-in

04/25/2017: Applicable to prime contracts over

$500K

10/25/2017: Applicable to subcontracts over $500K

10/25/2018: Reporting requirement expanded to 3

years

11

Page 12: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Non-Retaliation for Disclosure of Compensation Information

(FAR Case 2016-007)

Interim Rule – Effective September 30, 2016

Implements E.O. 13666, “Non-Retaliation for Disclosure of Compensation

Information”, April 8, 2014 and OFCPP DoL final rule from September 11, 2015

Amends Equal opportunity clause to prohibit contractors from discharging, or in

any manner discriminating against, any employee or applicant for employment

because the employee or applicant inquired about, discussed, or disclosed the

compensation of the employee or applicant or another employee or applicant

Defines “compensation” as - any payments made to, or on behalf of, an

employee or offered to an applicant as remuneration for employment, including

but not limited to salary, wages, overtime pay, shift differentials, bonuses,

commissions, vacation and holiday pay, allowances, insurance and other

benefits, stock options and awards, profit sharing, and retirement

Requires dissemination of the non-retaliation provisions to employees and

applicants by

1. Incorporation into existing employee manuals or handbooks; and

2. Electronic posting or by posting a copy of the provision in conspicuous

places available to employees and applicants for employment

Comments to the interim rule are due on November 29, 2016 12

Source: Federal Register 81 FR 67732 September 30, 2016

Page 13: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Limitation on Allowable Government Contractor Employee

Compensation

(FAR Case 2014-012)

Final Rule –Effective September 30, 2016

Adopts as final, with changes, a prior interim rule implementing

compensation cap to all contractor employees pursuant the Bipartisan

Budget Act of 2013

Re-organizes FAR 31.205-6 to:

streamline references to applicability of compensation caps over

time

include references and links to OMB websites related to

compensation

incorporates the following table into the Compensation Cost

Principle

13

Source: Federal Register 81 FR 67778, September 30, 2016

Page 14: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Prohibition on Contracting with Corporations with Delinquent Taxes or a

Felony Conviction

(FAR Case 2015-011)

Final Rule –Effective September 30, 2016

Adopts as final, without any changes, a December 2015 interim

rule prohibiting the Federal Government from entering into a

contract with any corporation having a delinquent Federal tax

liability (in excess of $3,500) or a felony conviction under any

Federal law, unless the agency has considered suspension or

debarment of the corporation and has made a determination

that this further action is not necessary to protect the interests of

the Government

Requires reporting of tax liabilities greater than $3,500 and

felony convictions within 24 months

14Source: Federal Register 81 FR 67728, September 30, 2016

Page 15: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Defense Federal Acquisition

Regulation & Other Supplements

15

Page 16: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Agencies must assess all costs and benefits of available regulatory

alternatives and, if regulation is necessary, select regulatory

approaches that maximize benefits (including potential economic,

environmental, public health and safety effects, distributive

impacts, and equity)

Emphasis on the importance of quantifying both costs and benefits,

or reducing costs, or harmonizing rules, and of promoting flexibility

This rule does not apply to contracts at or below the SAT

Multiyear Contract Requirements

(DFARS Case 2015-D009)

Final Rule – Effective May 10, 2016

Source: DFARS Case 2015-D009 – Federal Register 81 FR 28730, May 10, 201616

Page 17: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Rights in Technical Data and Validation of Proprietary Data Restrictions.

(DFARS Case 2012-D022)

Proposed Rule – June 16, 2016

Public comments ends September 14, 2016

Add special provisions for handling technical data that are necessary

for segregation and reintegration activities

Codify and revise the policies and procedures regarding deferred

ordering of technical data;

Expand the period in which DoD can challenge an asserted restriction

on technical data from three years to six years

Rescind changes to 10 U.S.C. 2320 from the NDAA for FY 2011 and

Codify Government purpose rights as the default rights for technical

data related to technology developed with mixed funding

17Source: DFARS Case 2012-D022 – Federal Register 81 FR 39482 June 16, 2016

Page 18: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Detection and Avoidance of Counterfeit Electronic Parts – Further

Implementation

(DFARS Case 2014-D005)

Final Rule –Effective August 2, 2016

Requires DoD contractors and subcontractors, except in limited

circumstances, to acquire electronic parts from trusted suppliers

in order to further address the avoidance of counterfeit

electronic parts

Contractors and subcontractors that are not the original

component manufacturer are required by this rule to notify the

contracting officer if it is not possible to obtain an electronic part

from a trusted supplier

For those instances where the contractor obtains electronic

parts from sources other than a trusted supplier, the contractor

is responsible for inspection, test, and authentication in

accordance with existing applicable industry standard

18

Source: DFARS Case 2015-004 – Federal Register 81 FR 50635 August 2, 2016

Page 19: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Costs Related to Counterfeit Electronic Parts

(DFARS Case 2016-D010)

Final Rule – Effective Aug. 30, 2016

Revises DFARS cost principles – 231.205-71 Costs

related to counterfeit electronic parts and suspect

counterfeit electronic parts

Counterfeit parts, reworked or corrective action is

unallowable unless

Operational system to detect and avoid counterfeit parts

Parts are GFP or obtained though Sources of Electronic Parts

clause

Contractor discovers counterfeit through inspection, testing &

authentication or by other means AND provides timely (60-day)

notice to COs and Government Industry Exchange Program(GIDEP)

19

Page 20: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Procurement of Commercial Items

(DFARS Case 2016-D006)

Proposed Rule - August 11, 2016

This rule provides guidance to contracting officers to promote

consistency and uniformity in the acquisition process

DoD intends to determine that it is in the best interest of the

Federal Government to apply the rule to contracts for the

acquisition of commercial items, including COTS items

An exception for contracts for the acquisition of commercial

items, including COTS items, would exclude the contracts

intended to be covered by the law, thereby undermining the

overarching public policy purpose of the law

20Source: DFARS CASE 2016-D006 – Federal Register 81 FR 53101 August 11, 2016

Page 21: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Rights in Technical Data

(DFARS Case 2016-D008)

Final Rule - Effective Date September 23, 2016

Implements section 813(a) of NDAA of 2016

Addresses rights in technical data relating to major weapon systems and expands application of the presumption that a commercial item has been developed entirely at private expense

Prior to rule, with the exception of COTS items, a contracting officer’s challenge to asserted restrictions on technical data relating to a major system was sustained unless the contractor or subcontractor submitted information demonstrating that the item was developed exclusively at private expense

Narrowed to apply to only major weapons systems (excludes major non-weapons systems)

Expanded beyond COTS to include (i) COTS items with modifications of a type customarily available in the commercial marketplace or minor modifications made to meet Federal Government requirements; (ii) commercial subsystems or components of a major weapon system, if the major weapon system was acquired as a commercial item in accordance; and (iii) components of a subsystem, if the subsystem was acquired as a commercial item 21

Source: DFARS CASE 2016-D008 – Federal Register 81 FR 65565 September 23, , 2016

Page 22: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Transactional Data Rule

(GSAR Case 2013-G504)

Final Rule – Effective June 23, 2016

Rule will be phased in by GSA Schedule and SIN over the course of a

three-year pilot

Participants are no longer subject to CSP and PRC requirements

Rule aligns with GSA’s long-term objective to adopt a market-driven

pricing model rather than a vendor’s most favored pricing

Monthly reporting of transactional data will be required for all orders

against certain FSS contracts, GWACs and Government-wide IDIQ

contracts

The new reporting clause and corresponding pricing disclosure will be

required for all new offerors and renewals

Existing contractors may voluntarily opt in through acceptance of a

bilateral contract modification

22

Page 23: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

FAR Final Rule

Transactional Data Reporting – Covered schedules

Source: GSAR clause (552.216-75)Note: Graphical data prepared by EY’s Government Contract Services

The initial pilot will cover eight Schedules and related

SINs, as listed below:

Schedule 58 I, Professional Audio/Video,

Telemetry/Tracking, Recording/Reproducing and

Signal Data Solutions

Schedule 72, Furnishing and Floor Coverings

Schedule 03FAC, Facilities Maintenance and

Management

Schedule 51 V, Hardware Superstore

Schedule 75, Office Products

Schedule 73, Food Service, Hospitality, Cleaning

Equipment and Supplies, Chemicals and Services

Schedule 00CORP, The Professional Services (PSS)

Schedule:

SINs 871-1, 2, 3 ,4, 5, 6, and 7 (PES)

Schedule 70, General Purpose Information

Technology Equipment, Software, and Services:

SINs 132-8 (Hardware), 132-32, 33, and 34

(Software), and 132-54 and 55 (Commercial Satellite

Communications, or COMSATCOM)

Contractors with schedules containing only select

SINs — PSS and Sch70 — will be required to report

transactional data for all SINs (i.e., TDR is required

for all SINs even these not subject to the rule).

1 Number reflects all Schedule 70 and OOCORP contracts; some schedule holders

may not have SINs subject to TDR.

Schedule 2015 Sales # of GSA contracts1

70 6,025,923,944 5,060

72 34,560,405 140

73 166,972,222 446

75 518,403,586 392

871 914,909,479 246

03FAC 513,720,277 733

51 V 659,481,363 410

58 I 101,336,613 166

00CORP 862,637,198 3,891

Total 9,797,945,087 11,484

Source: GSA Schedule Sales Query, FY15 reported sales

Covered by TDR

Not covered by TDR70

%

30

%

23

Page 24: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Federal Supply Schedule, Order-Level Materials

(GSAR Case 2016–G506)

Proposed Rule - September 9, 2016

Clarifies the authority to acquire order-level materials when

placing a task order or establishing a Blanket Purchase

Agreement (BPA) against a Federal Supply Schedule (FSS)

contract

Proposed a paragraph (d) be added to FAR 8.401, General,

which would permit the addition of ‘‘open market (noncontract)’’

items to a FSS blanket purchase agreement or task or delivery

order only if

All applicable acquisition regulations have been followed (e.g., publicizing

([FAR] Part 5), competition requirements ([FAR] Part 6), acquisition of

commercial items ([FAR] Part 12), and contracting methods ([FAR] Parts 13,

14, and 15))

The ordering office contracting officer has determined the price for the open

market items is reasonable; and

The items are clearly labeled as open market (noncontract) items on the

order.

24

Page 25: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Revised Voucher Submission & Payment Process

(NFS Case 2016–N025)

Interim Rule – September 14, 2016

To implement revisions to the voucher submittal and payment

process

Revisions necessary due to section 893 of the National

Defense Authorization Act for Fiscal Year 2016 prohibiting the

DCAA from performing audit work for non-Defense Agencies

NASA had delegated to DCAA the task of reviewing contractor requests for

payment under NASA cost-type contracts.

An immediate need to implement procedural changes to

minimize cost voucher submission and payment delays to

NASA suppliers as well the potential accrual of Government

interest payments to contractors

Comments due by November 14, 201625

Page 26: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Establishing Paid Sick Leave for Federal Contractors

DOL Final Rule - Effective January 1, 2017

Implements E.O. 13706, September 7, 2015

Effective Date: contracts awarded on or after January 1, 2017

Covered Contracts: contracts covered by Davis-Bacon Act (DBA) or Service

Contract Act (SCA), concessions contracts (contract to use Federal property),

contract in connection with Federal property to provide services to Federal

employees

Covered Employees: not all employees of a company; if employee is working

on a covered contract and their wages are governed by DBA, SCA, or FLSA

Includes employees exempt from FLSA’s minimum wage and overtime provisions

Includes employees who spend 20% or more of their time in connection with covered

contract

Key Requirements:

Minimum annual accrual of 56 hours of sick leave provided to covered employees; 56

hours can be carried over

Use of sick leave: specific events identified such as caring for parent, time spent

related to domestic violence, sexual assault, or stalking

Various employee notification requirements (e.g. posters, notification of rights)

26

Source: Federal Register 81 FR 67598, September 30, 2016

Page 27: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Cost Accounting Standards (CAS)

27

Page 28: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Implementation of Defense Cost Accounting Standards

Board

The Senate Armed Services Committee has included a provision in

the 2017 NDAA (National Defense Authorization Act) that would

establish a new Cost Accounting Standards Board within the

Department of Defense

The Committee expressed concern that the current cost accounting

standards favor incumbent defense contractors and limit

competition by serving as a barrier to participation by non-

traditional, small business, and commercial contractors

Provision requires cost accounting standards developed - to the

maximum extent practicable - align with Generally Accepted Cost

Accounting Principles, thereby minimizing the requirement for

government-unique cost accounting systems28

Page 29: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Department of Defense

Defense Contract Audit Agency (DCAA) &

The Defense Contract Management Agency (DCMA) policies

29

Page 30: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Defense Procurement Acquisition Policy Memo

Guidance on CIDs and the Determination of Price

Reasonableness for Commercial Items - September 2,

2016

Outlines various DoD policy initiatives related to commercial items

DCMA has stood up six Commercial Item Centers of Excellence

(CoEs) – aligned to various market sectors – to support CO’s CIDs

DCMA is establishing a database of CIDs

COs should recognize prior CIDs and include a copy of the prior CID in

contract files

DPAC and DCMA’s Cost & Pricing Center are working with companies

to develop advance agreements outlining the type of information

needed to support CIDs and fair and reasonable determinations

Advance agreements would be uploaded into Contract Business

Analysis Repository (CBAR)

Reinforces FY 2016 NDAA requirements that IT products and services

in excess of the SAT should be commercial 30

Page 31: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

DCAA – Reorganization

Update

• Implementation timeline - March

through September 2016

Major changes:

oAdding the following contractors

to their Contract Audit

Coordinator (CAC) pilot project:

1) General Dynamics

2) BAE

3) Boeing

4) Honeywell

5) Lockheed Martin

oGoing from five regions to three

– East, Central, and West

Note: Graphical data prepared by EY’s Government Contract Services

31

Page 32: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

DCAA – Audit Guidance on the Impact of the National Defense

Authorization Act on DCAA’s Audit Support to Non-Defense Agencies

MRD 16-PPD-008(R) September 30, 2016

Effective October 1, 2016 – DCAA is again providing full audit

support to non-Defense Agencies

DCAA has met the requirement of less than 18 months of

incurred cost inventory outlined in 2016 NDAA

DoD Comptroller has certified the progress to Congress

Auditors will coordinate with non-Defense agencies on

prioritization of audits

Other agencies continue to ramp-up audit capabilities

32

Page 33: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

DCAA –Audit Alert on Handling Incurred Cost Proposals Using a Blending

Approach of Compensation Caps

MRD 16-PPD-007(R) June 30, 2016

Addresses blending methodologies and requirements for final overhead,

interim billing, and forward pricing rates

DCAA to evaluate forward pricing and incurred cost proposals to ensure

proposed blended rates do not result in costs exceeding allowable

compensation amounts

o Does not require contractors to use blended compensation cap rates

o Address the new compensation caps for 2013 and 2014

DCAA Audit Alert on Handling Incurred Cost Proposals Using a Blending

Approach of Compensation Caps (MRD 16-PPD-007 (R)) – June 30,

2016

o If the contractor proposes to use a blended cap, the contractor and

Administrative Contracting Officers (ACO) are required to execute an

advance agreement

o A list of contractor fiscal years (CFYs) will be furnished to DCMA for all

CFYs

o DCAA will provide a non-audit service on proposed advance

agreement to ensure that it complies with the DDP guidance

33

Page 34: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

DCAA – Audit Guidance on Revised Policy & Procedure for Low-Risk

Incurred Cost Proposal Less Than $250M in ADV

MRD 16-PPD-006(R) May 27, 2016

DCAA will reassess all open audits, of an adequate proposal, that are

classified as high risk with ADV less than $5 million where fieldwork has

not been started

o Must obtain Regional Audit Manager (RAM) approval to continue the

performance of the audit, justifying a warranted need based on

significant risk

Going forward, DCAA will assess risk for all adequate proposals with ADV

less than $250 million using revised policy and procedures and the

appropriate Low-Risk Determination tool

34

Page 35: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

DCAA – Updated Guidance on the Treatment of Overdue Indirect Rate

Proposals

MRD 16-PPD-004(R) February 11, 2016

DCAA Actions

May 2016: Audit teams with send a letter to the designated Contracting Officer

(CO) in May 2016 notifying DCMA of their intent to close the overdue incurred

costs submissions once they reach 12 months overdue.

June 2016: Audit teams must close the assignments on the list on June 30, 2016, if

DMCA Contracting Officers do not notify DCAA of any extensions or ongoing

coordination that would warrant DCAA leaving the assignments open.

DCAA providing support to Unilaterally Establish Contract Costs

Applying unilateral costs decrements is up to the judgment of the CO. When

requested by the CO, DCAA will provide all relevant information related to the

contractor’s delinquent CFY, including billing deficiencies, and incurred cost audit

experience. DCAA may also provide a calculated unilateral contract cost decrement

based on historical questioned costs.

35

Page 36: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Notable Legal Decisions

36

Page 37: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Notable Legal Decisions

False Claims Act

UNIVERSAL HEALTH SERVICES, INC. v. UNITED STATES ET AL. EX REL.

ESCOBAR ET AL.

Argued April 19, 2016 – Settled June 16, 2016

The implied false certification theory can be a basis for FCA liability

when a defendant submitting a claim makes specific representations

about the goods or services provided, but fails to disclose

noncompliance with material statutory, regulatory, or contractual

requirements that make those representations misleading with respect

to those goods or services.

Contrary to Universal Health’s contentions, FCA liability for failing to

disclose violations of legal requirements does not turn upon whether

those requirements were expressly designated as conditions of

payment.

37

Source: Bloomberg BNA Federal Contracts Report – Universal Health Services Inc v. United States et el ex. rel. Escobar et al

Page 38: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Notable Legal Decisions (continued)

False Claims Act

KBR Whistleblower in Iraq False Claims Act (FCA) Case – U.S. ex rel. Conyers v.

KBR Inc. et al.

April 1, 2015: KBR Inc. agreed to settle a first-of-its-kind SEC administrative enforcement

action that one of its confidentiality agreements infringed on federal whistle-blower protections

KBR employees who internally reported potential wrongdoing had to sign a confidentiality

agreement that prohibited them from “discussing any particulars” about the subsequent internal

investigation without permission of the company's legal department

• The SEC said the form violated Rule 21F-17 under the 1934 Securities Exchange Act, which prohibits companies

from impeding employee attempts to report wrongdoing to the agency

Under the LOGCAP III contract, awarded in 2001, KBR served more than 700 million meals,

delivered nearly 400 million pounds of mail, produced almost 14 billion gallons of potable water

and transported more than 1 billion gallons of fuel to support U.S. troops in Iraq. Transportation

reportedly included over 170 million miles.

• The federal government, and a former employee, accused KBR of reaching agreements with the two subcontractors

— La Nouvelle General Trading & Contracting Co. and First Kuwaiti — as part of their LOGCAP III contract in

exchange for kickbacks, then charged the government inflated sums for those agreements in violation of the FCA

38Source: KBR Inc., SEC, Admin. Proc. File No. 3-16466, 4/1/15

Appeals of Kellogg Browns & Root Services, Inc. ASBCA, Nos. 57530, 58161, 7/25/16, decision released 8/9/16

Page 39: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Notable Legal Decisions (continued)

CAS Materiality

Raytheon Co., Space & Airborne Sys., ASBCA No. 58068, 16-1 BCA ¶ ___ (Aug.

9, 2016)

CO abuse of discretion: failure to consider materiality factors in CAS

• Found abuse of discretion even in absence of bad faith

CO found cost impact material simply because there was an impact

CO failed to consider mandatory materiality criteria in CAS regs and was wrong that none

of the criteria were applicable

• Should have compared amount to $3B contract base, or divided amount by the

“hundreds if not thousands of contracts” – Board divided amount by 1,000 and then

again by 4, for each year

• Should have considered administrative expense (lawyers, auditors, etc.) to recover cost

impact – effectively a litigation risk analysis

• Offsets back on the table

• One of the criteria is whether amounts “tend to offset” one another to render them

immaterial

• Board only gave two “examples” – did not limit to the two above39

Page 40: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Notable Legal Decision (continued)

CAS 404

Exelis, Inc., ASBCA No. 60131, 16-1 BCA ¶ __ (Aug. 29, 2016)

Claim that contractor treated building lease as an operating lease

instead of capital lease was a noncompliance with CAS 404 (and

unallowable under FAR 31.205-11(h))

Plain language of CAS 404 applies to “tangible capital assets”: having

physical substance

• Lease is “intangible” asset – it is a legal right to use and occupy a

building and does not have physical substance

• Preamble supports plain language

Dismissed CAS 404 noncompliance on failure to state a claim upon

which relief could be granted

40

Page 41: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Notable Legal Decisions (continued)

Allowability: CERCLA recovery and the interface with indirect rates

Lockheed Martin Corp. v United States, __ F.3d __ (D.C. Cir. Aug. 19

2016)

Lockheed included remediation costs in indirect rates for Lockheed’s

environmental cleanup obligations

United States has proportionate responsibility as PRP remediation

costs

• Asserts Lockheed gets double recovery through its payment and

indirect rate

Government made a choice in a 2000 Billing Agreement that itemized

environmental remediation costs – among many other costs – would

be reimbursed and treated as allowable.

• Focuses on Billing Agreement as a settlement on recovery of the

costs

• Nothing required the government to “funnel the governmental share”

through the indirect pool

41

Page 42: Government Contracting Update Series · Goal: To clarify the application of the Federal Information Security Management Act (FISMA) and the National Institute of Standards and Technology

Contact Information

• Presenters:

• Paul E. Pompeo, Partner, Government Contracts and National

Security, Arnold & Porter LLP – 202.436.1602.

[email protected]

• Sajeev D. Malaveetil, Partner, EY Government Contract Services –

703.862.0543. [email protected]

42