government of india ministry of power central …
TRANSCRIPT
GOVERNMENT OF INDIA
MINISTRY OF POWER CENTRAL ELECTRICITY AUTHORITY
MAY 2020
स�यमेव जयत े
GUIDELINES FOR THE VALIDITY PERIOD OF GUIDELINES FOR THE VALIDITY PERIOD OF GUIDELINES FOR THE VALIDITY PERIOD OF GUIDELINES FOR THE VALIDITY PERIOD OF
TYPE TEST(S) CONDUCTED ON MAJOR TYPE TEST(S) CONDUCTED ON MAJOR TYPE TEST(S) CONDUCTED ON MAJOR TYPE TEST(S) CONDUCTED ON MAJOR
ELECTRICAL EQUIPMENT IN POWER ELECTRICAL EQUIPMENT IN POWER ELECTRICAL EQUIPMENT IN POWER ELECTRICAL EQUIPMENT IN POWER
TRANSMISSIONTRANSMISSIONTRANSMISSIONTRANSMISSION
BYBYBYBY
POWER SYSTEM ENGINEERING & TECHNOLOGY DEVELOPMENT POWER SYSTEM ENGINEERING & TECHNOLOGY DEVELOPMENT POWER SYSTEM ENGINEERING & TECHNOLOGY DEVELOPMENT POWER SYSTEM ENGINEERING & TECHNOLOGY DEVELOPMENT
CENTRAL CENTRAL CENTRAL CENTRAL ELECTRICITY AUTHORITYELECTRICITY AUTHORITYELECTRICITY AUTHORITYELECTRICITY AUTHORITY
भारत सरकार
Government of IndiaGovernment of IndiaGovernment of IndiaGovernment of India केीय िव�ुत �ािधकरण
Central Electricity AuthorityCentral Electricity AuthorityCentral Electricity AuthorityCentral Electricity Authority िव�ुत मं�ालय
Ministry of PowerMinistry of PowerMinistry of PowerMinistry of Power नई िद�ली
New DelhiNew DelhiNew DelhiNew Delhi
MAY 2020MAY 2020MAY 2020MAY 2020
भा�रत सरका�रGovernment of India
वि�द्युत मं�त्रा�लयMinistry of Power
का� न् द्री� य वि� द्यु त प्रा� वि� कारणCentral Electricity Authority
वि�द्युत प्राण�ल� अविभाय��वित्राका� ए�� प्रा�द्यु�वि�का� वि�का�स प्राभा��Power System Engineering & Technology Development Division
Sewa Bhawan, R.K. PuramNew Delhi – 66
To,
As per attached list.
वि�षय /SUB.:- Extension of validity date of Type Test Certificate and amendment toCEA’s “Guidelines for the Validity Period of Type Test(s) conducted on MajorElectrical Equipment in Power Transmission System” - reg.
As you are aware that CEA had prepared “Guidelines for the Validity Period of TypeTest(s) conducted on Major Electrical Equipment in Power Transmission System”, inconsultation with various utilities, manufacturers, testing agencies, IEEMA and otherstakeholders. The guidelines were circulated to all Stakeholders, vide CEA’s letter No. CEA-PS-14-80/1/2019-PSETD Division/195-271 dated 11.05.2020 and the same is also availablein CEA’s website at the link: https://cea.nic.in/wp-content/uploads/pse___td/2020/08/Approved_Type%20test%20validity%20guidelines.pdf
2. Due to COVID pandemic, one year extension on validity period for type test ofequipment listed in abovementioned document was provided in October 2020 which is validupto 30th September 2021. At that time it was anticipated that this pandemic would be overand manufacturing & testing process would become normal again. However, pandemicresurfaced with even more intensity which forced closure of manufacturing units and testinglaboratories. Manufacturers have requested for further extension to validity period as theycould not get opportunity to carry out type test.
3. Complete testing facilities for GIS and Hybrid switchgear are not available in Indiaand manufacturers need to send their equipment abroad for testing which is not only timeconsuming but also costly affair. Since GIS manufacturing is not that old in India and most ofthe manufacturers follow the design and process of their parent company/collaborator,manufacturers have requested for accepting type test report conducted on product
File No.CEA-PS-14-80/1/2019-PSETD Division-Part(2)
manufactured by parent company. Further, many of the utilities already accept these testreports.
4. Keeping in view the difficulties being faced by Indian manufactures, it has beendecided that:
(a) The Type test reports, which could not be re-validated due to COVIDpandemic since 23rd March 2020, shall be treated as valid up to 30thSeptember 2022.
(b) Para 2(g) of CEA’s “Guidelines for the Validity Period of Type Test(s) conductedon Major Electrical Equipment in Power Transmission System” shall be read asfollows: “The equipment shall be supplied from the same manufacturingworks, where from the sample unit was manufactured andsuccessfully type tested as per relevant standard (IS/IEC). However, in caseof GIS and Hybrid switchgear, type test reports of parentcompany/collaborator may be accepted provided same design and process bywhich parent company/collaborator has manufactured the equipment, hasbeen followed by the Indian manufacturer.”
This issues with the approval of Member (PS), CEA.
Yours faithfully,
भंवर सि�हं मीना/ Bhanwar Singh Meena
उप-निनदेशक/ Deputy Director Telephone: 26732358
Email: [email protected]
File No.CEA-PS-14-80/1/2019-PSETD Division-Part(2)
Digitally signed by BHANWARSINGH MEENADate: 2021.09.17 12:21:40 IST
Signature Not Verified
C Central Electricity Authority
Guidelines for the Validity Period of Type Test(s) conducted on Major Electrical Equipment in Power Transmission System Page 1
1. Back ground:
Prior to commercialization, any equipment passes through product
development stage, which requires various testing to achieve
desired functionalities of the equipment. Once, the equipment
design is finalized, it is subjected to type tests before going for
commercial production. Type tests are generally performed on any
equipment conforming to relevant National/ International
standards to validate the design and to demonstrate its functional
requirement meeting the intended application and reliable
performance during its service life. These tests are also called
‘Proof Tests’ or ‘Design Validation Tests’. Such tests are not
required to be performed on each unit of the equipment but are
performed on representative design of the equipment. Moreover,
successfully type tested equipment does not guarantee that there
will be no failure of the equipment as the equipment is likely to
encounter various types of electrical, mechanical, thermal and
environmental stresses during its service life which may not match
exactly with the conditions simulated during testing.
[Note: The word “equipment” used in the document refers to all items listed in
the Table covered under 2(h)]
National/ International standards does not specify any period for
validity of type test results. Ideally, repetition of type tests on the
equipment is not desirable so long as there is no change in basic
design/ technology, mechanical construction including physical
dimensions (e.g. unit spacing, total height, shed diameter, arcing
distance, shed profile, and creepage distance etc. of an insulator),
material, functionality of the equipment, performance
C Central Electricity Authority
Guidelines for the Validity Period of Type Test(s) conducted on Major Electrical Equipment in Power Transmission System Page 2
characteristic and manufacturing process. The change in design
includes change in voltage stress, thermal stress, mechanical
stress, current density, flux density, degree of protection etc. The
change in materials includes enclosure material (magnetic, non-
magnetic etc.), transformer core material (grades of CRGO,
Amorphous, mu metal), insulating material (solid, liquid, gaseous),
electronic parts (processor, memory, principal/ main relays etc.)
etc. If relevant standard (IS/IEC) of the equipment is
revised/amended, fresh type test is warranted even if equipment
has not changed in design/ material etc. provided there is change
in test procedure/ method/ criteria or test levels in the revised
standard. However, many of the equipment involves manual
intervention during manufacturing process and comprises of a
number of bought out items. The quality of workmanship and the
quality of components/ materials used in manufacturing of the
equipment may change/ deteriorate over the years affecting overall
quality, reliability and performance during service life of the
equipment. Therefore, some utilities insists for repetition of type
tests after a reasonable period of time to ensure that equipment
quality, performance and reliability of the equipment is being
maintained. The frequency of repetition of type tests by Indian
utilities, even if the equipment has remained essentially the same
(in terms of basic design, construction, material and
manufacturing process etc.) has become a matter of concern as it
varies from utility to utility. Few utilities even do not accept type
tests conducted on equipment of same rating /specifications and
demand for repetition of type test(s). Sometimes testing time
exceeds the entire production time e.g. over voltage cycling test for
capacitors etc.. Facilities for some of the type tests for some
C Central Electricity Authority
Guidelines for the Validity Period of Type Test(s) conducted on Major Electrical Equipment in Power Transmission System Page 3
equipment are not available in India for which these equipment are
being sent abroad for testing.
In view of the increasing grievances of the manufacturers regarding
type test requirements mandated by the utilities in their
specifications and requests from many utilities , Central Electricity
Authority (CEA) had organized a meeting with all major
stakeholders on 10.09.2018 to deliberate and standardize the
duration of validity of type tests conducted on transmission system
equipment. All manufacturers and utilities had emphasized the
need of uniform guidelines in this regard across the utilities in the
country as this is unnecessarily leading to wastage of national
resources, time & money and increasing burden on manufacturer
and cost to the end consumers. Therefore, there is need to address
such issues and develop uniform practice /guidelines relating to
period of validity of type test reports of major electrical equipment
in Power transmission system for the benefits of end users, utilities
and manufacturers in the country considering the cost/
complexity associated with frequent type testing of the equipment.
2. Broad Guidelines
a) Type tests on indigenous equipment, for which testing facility
is available in India, should have been conducted in any
independent laboratories approved by Government or
accredited by National Accreditation Body of the Country, like
Central Power Research Institute (CPRI), Electrical Research
and Development Association (ERDA) etc.
C Central Electricity Authority
Guidelines for the Validity Period of Type Test(s) conducted on Major Electrical Equipment in Power Transmission System Page 4
b) Type tests on indigenous equipment, for which testing facility
is not available in India, should have been conducted in a
laboratory of foreign Country accredited by National
Accreditation Body of that Country.
c) Type tests on imported equipment should have been
conducted in an Indian laboratory or foreign laboratory
accredited by National Accreditation Body of respective
Country.
d) The type tests conducted in-house by manufacturers shall also
be acceptable provided the lab is accredited by National
Accreditation Body of the Country and the tests have been
witnessed by a representative of NABL accredited laboratory/
Power Utility.
e) The result of all type tests shall be recorded properly in Type
Test Reports (TTRs) containing sufficient information like the
ratings, the relevant drawings, model number, test circuit,
calculations (if any), photos and compliance to the relevant
standards (IS/IEC) etc. The relevant clauses of the standards
(IS/IEC) according to which type tests have been conducted
and acceptance criteria/values need to be brought out clearly
in the report.
f) All the testing equipment used for type testing should have
been duly calibrated and the valid calibration reports should
form part of the Type test reports.
C Central Electricity Authority
Guidelines for the Validity Period of Type Test(s) conducted on Major Electrical Equipment in Power Transmission System Page 5
g) The equipment shall be supplied from the same manufacturing
works, where from the sample unit was manufactured and
successfully type tested as per relevant standard (IS/IEC).
h) Validity period of type tests conducted on the equipment i.e.
the period for which Type Test Reports (TTRs) shall remain
valid and acceptable to user/ utility provided no major change
has been introduced in the basic design/ technology/
material/ mechanical construction/ functionalities of the
equipment/ performance characteristic/ manufacturing
process of the equipment, shall be as follows:
Sl. No. Name of Equipment Periodicity (in
years)
i. Power Transformer 5
ii. Distribution Transformers
(33 kV and below)
5
iii. Shunt Reactor 5
iv. OLTC 10
v. Power transformer Bushing /
Reactor Bushing
7
vi. Transformer/reactor fittings
and Accessories
10
C Central Electricity Authority
Guidelines for the Validity Period of Type Test(s) conducted on Major Electrical Equipment in Power Transmission System Page 6
vii. Circuit Breaker 10
viii. Isolator 10
ix. Lightening Arrester 10
x. Wave Trap 10
xi. Instrument Transformers 7
xii. LV and MV Switchgear 10
xiii. GIS & Hybrid Switchgear 10
xiv. Cables and associated joints 10
xv. Capacitor 10
xvi. Relays 7
xvii. Energy Meter (including smart
meters and ABT meters)
5
xviii. Battery and Battery Charger 7
xix. Conductors and earth wire 10
xx. High Temperature (HT) / High
Temperature Low Sag
Conductor (HTLS) conductor
7
xxi. Insulators (Porcelain/ Glass) 10
xxii. Composite Insulator 5
C Central Electricity Authority
Guidelines for the Validity Period of Type Test(s) conducted on Major Electrical Equipment in Power Transmission System Page 7
xxiii. PLCC/ FO cable / OPGW 5
xxiv. Transmission Line insulator
hardware fittings, and
accessories for conductor &
ground wire
7
Note 1: The type tests reports shall be valid as on the last date
of submission of bid.
Note 2: The period of validity of Short Circuit test (a special
test) conducted on transformer shall be as per CEA (Technical
Standards for Construction of Electrical Plants and Electric
Lines) Regulations.
Note 3: Type test reports of 220kV voltage class equipment
shall be valid for 230kV voltage class equipment as the highest
system voltage is same in both cases provided Basic Insulation
Level is same.
i) The type tests of the equipment shall be repeated during its
validity period, if there is change in technology or basic design
or generic materials employed or manufacturing process or
combination of any of above. However, minor changes, which
have no effect on functionality & reliability of the equipment,
may not require repetition of type tests. Minor changes do not
include change in electrical stress, thermal stress, mechanical
stress, change in construction, change in dielectric material,
impregnating oil, thickness of electrode & internal fuse design
C Central Electricity Authority
Guidelines for the Validity Period of Type Test(s) conducted on Major Electrical Equipment in Power Transmission System Page 8
in a capacitor, enclosure materials (magnetic, non-magnetic
like stainless steel, Aluminum) etc.
j) If relevant standard (IS/IEC) of the equipment is revised or
amended, fresh type test is warranted even if equipment has
not changed in design/ material etc. However fresh type
testing will be limited to only those tests for which test
procedure/ method, any technical requirement or test levels
have been changed in the revised standards. In such cases,
enough time should be given to manufacturer to comply with
revised provision in standards.
k) The utilities should co-relate the need of repeating type test(s)
to changes in design/technology and may emphasize/ insist
for stage inspection to check workmanship, manufacturing
process and to ensure quality of the component/ material used
in the manufacturing of the equipment.
l) The change in the make of component(s) of the equipment shall
not be the criteria for repetition of type tests provided that the
component of new make has been successfully type tested and
its use shall not affect the, functionality, performance &
reliability of the equipment. The type test reports of the
component of new make shall be submitted.
m) Utilities, if so desires, may repeat the type tests, at their own
cost even if valid TTRs have already been provided by the
bidder/manufacturer. However, the utilities should refrain
from making it a regular practice. The utility must clearly
C Central Electricity Authority
Guidelines for the Validity Period of Type Test(s) conducted on Major Electrical Equipment in Power Transmission System Page 9
specify which type tests would be repeated in the event of
award of the contract and quotation for such tests should be
invited separately in the price bid. In such case utility shall
provide extra time for repetition of such type tests.
n) The philosophy of extending type test results of the equipment
is based on two primary factors: similar design and design with
higher stresses (electrical, mechanical, thermal, and
environmental). Validity of type test report of a equipment can
be extended to the same equipment of similar design and/or
lower design stress provided relevant standard (IS/IEC)
permits.
o) It is practically impossible to subject all possible arrangements
of the GIS (for a particular switching scheme corresponding to
a specified voltage level) to type tests as various arrangements
are possible using same combination of equipment depending
on layout arrangement and space availability. The
performance of any particular arrangement shall be
substantiated from type test results obtained on representative
assemblies or sub-assemblies. The user shall check to ensure
that tested sub-assemblies can be a representative form of the
user’s arrangement and meet his desired requirement/
objective.
p) For capacitors, the successful completion of each type test is
also valid for units having the same rated voltage and lower
output (KVAR), provided that they do not differ in any way (i.e.
C Central Electricity Authority
Guidelines for the Validity Period of Type Test(s) conducted on Major Electrical Equipment in Power Transmission System Page 10
design, construction, material, and production process etc.)
that may influence the properties to be checked by the test.
q) Repetition of short circuit test on transformer is not required
due to change in make and type of bushings and/or make of
OLTC provided bushings and OLTC of supplied make have
same or better rating and have been successfully type tested
as per relevant IS/ IEC.
r) The utility shall not reject the transformer for supply against
the contract, if the Short Circuit (SC) tests was conducted on
the subject transformer as per relevant standard (IS/IEC) and
it has successfully passed the SC tests and other type tests as
per relevant standards.
**************************************************
Attached list1. Chairman & Managing Director,
Powergrid Corporation of India Ltd., Saudamini, Plot No. 2, Sector-29,Gurgaon-122001 (Haryana)
2. Chairman & Managing Director, Delhi Transco. Ltd., Shakti Sadan, Kotla Marg, New Delhi-110002
3. Chief Engineer(Electrical)Goa Electricity DepartmentVidyut Bhawan, Panaji, Goa-403001
4. ChairmanHaryana Vidyut Prasaran Nigam Ltd.Shakti Bhawan, Sector No. 6Panchkula - 134 109, Haryana
5. Managing DirectorHimachal Pradesh State Electricity BoardVidyut Bhawan, Shimla- 171 004
6. Managing DirectorJammu & Kashmir Power Development Corporation Ltd. Exhibition Ground, Srinagar (J&K) -190009
7. ChairmanKarnataka Power Corporation Ltd82, Shakti Bhawan, Race Course RoadBangalore- 560 001
8. ChairmanKerala State Electricity BoardBoard SecretariatVidyuthi Bhavanam PattomThiruvananthapuram- 695004
9. Chairman & Managing DirectorMaharashtra State Electricity Transmission Company Ltd., C-19, E-BlockPrakashganga, Bandra-Kurla ComplexBandra(E), Mumbai 400 051
10. Chief Engineer(P)Manipur Electricity DepartmentGovt. of Manipur, Manipur Sectt.
File No.CEA-PS-14-80/1/2019-PSETD Division-Part(2)
South Block, Imphal, Manipur- 795 001
11. Chairman & Managing DirectorMeghalaya Energy Corporation Ltd.Lumjingshai Short Round RoadShillong- 793 001
12. The Engineer-in-ChiefPower and Electricity Deptt., Govt. of Mizoram,Power House, Bara BazarAizwal- 796 001, Mizoram
13. Chief EngineerNagaland Department of PowerKohima 797 001Nagaland
14. Chairman & Managing DirectorPunjab State Power Corporation Ltd.The Mall, Patiala- 147 001, Punjab
15. Chairman & Managing DirectorRajasthan Rajya Vidyut Prasaran Nigam Ltd.Vidyut Bhawan, JanpathJaipur (Rajasthan)-302005
16. Managing DirectorSikkim Power Development Corporation Ltd.31-A, N.H. Way, Gangtok- -737 101
17. Chairman & Managing DirectorTripura State Electricity Corporation Ltd.Govt. of Tripura, Agartala- 799 001
18. Chairman & Managing DirectorUttar Pradesh Power Corporation Ltd.Shakti Bhawan, 14-A, Ashok MargLucknow- 226 001.
19. Chairman & Managing DirectorWest Bengal Power Development Corporation Ltd.Bidyut Unnayan Bhaban, Plot 3/CLA-Block, Sector-III, Salt Lake City,Kolkata- 700 098
20. Secretary(P)Andaman and Nicobar Electricity Department,
File No.CEA-PS-14-80/1/2019-PSETD Division-Part(2)
Secretariat, Andaman and Nicobar Islands,Port Blair- 744 101
21. SecretaryDadra & Nagar Haveli Electricity Department,Dadar Nagar Secretariat,Silvassa- 396230
22. SecretaryDaman & Diu Electricity DepartmentDadar Nagar Secretariat, Moti Daman- 396220
23. SecretaryLakshyadeep Electricity DepartmentU.T. of LakshyadeepKavaratti- 682555
24. SecretaryPuducherry Electricity DepartmentSecretariat, Puducherry- 605001
25. Chairman & Managing DirectorOrissa Power Transmission Corporation Ltd.Janpath, Bhubaneswar- 751 022.
26. Chairman
Jharkhand Urja Sancharan Nigam Ltd.Engineering Building, HECDhurwa, Ranchi- 834 004
27. ChairmanWest Bengal State Electricity Transmission Company Ltd (WBSETCL)Vidyut Bhawan, Block-DJ, Sector-II,Bidhan Nagar, Kolkata- 700 091.
28. Managing DirectorBihar State Power (Holding) Company Ltd.Vidyut Bhawan, Bailey RoadPatna- 800 021
29. Chairman and Managing DirectorGujarat Energy Transmission Corporation Ltd.Sardar Patel Vidyut Bhawan,Race Course , Vadodara- 390 007
30. Managing DirectorMadhya Pradesh Power Transmission CompanyLtd. Block No. 2, Shakti Bhawan
File No.CEA-PS-14-80/1/2019-PSETD Division-Part(2)
Rampur, P.O. Vidyut NagarJabalpur- 482 008(MP)
31. Managing DirectorChhattisgarh State Power Generation Company Ltd., Vidyut Seva BhawanP.O. Sunder Nagar, Danganiya,Raipur- 492 013.(Chhattisgarh)
32. Chairman & Managing DirectorPunjab State Transmission Corporation Ltd.,The Mall, Mall Road,Patiala- 147 001, Punjab
33. Managing DirectorHimachal Pradesh Power Transmission Corporation Ltd.Barowalia House, KhaliniShimla- 171 004.
34. Chairman & Managing DirectorUttar Pradesh Power Transmission Corporation Ltd.Shakti Bhawan, 14-A, Ashok Marg,Lucknow- 226001
35. Chief Engineer (Power) Department of Power Govt. of Arunachal Pradesh Itanagar (Arunachal Pradesh) – 791 111
36. Chief Engineer(Transmission) Transmission Corporation of Andhra Pradesh Ltd. Vidyut Soudha, Gunadala Eluru Road, Vijaywada, Andhra Pradesh – 520 004
37. Managing Director Karnataka Power Transmission Corporation Ltd., Kaveri Bhawan Bangalore-560009
38. Chairman & Managing DirectorTransmission Corporation of Telangana Ltd.Vidyut Soudha, Khairatabad,Hyderabad - 500082
39. Managing DirectorAssam Electricity Grid Corporation Ltd.Bijulee Bhawan,
File No.CEA-PS-14-80/1/2019-PSETD Division-Part(2)
Paltan BazarGuwahati- 781 001
40. Chairman & Managing DirectorTripura State Electricity Corporation Ltd.Govt. of Tripura,Bidyut BhawanAgartala- 799 001.
41. Managing DirectorPower Transmission Corporation of Uttarakhand Ltd.Vidyut Bhawan, Saharnpur Road, Near I.S.B.T. Crossing, Dehra DunUttarakhand -248002
42. Managing DirectorTamil Nadu Transmission Corporation Limited 10th Floor/NPKRR Malikai, No. 144 Anna Salai,Chennai-600002
43. Chairman & Managing DirectorNational Thermal Power Corporation Ltd.NTPC Bhawan, Core 7, Scope Complex7, Institutional AreaLodhi Road, New Delhi-110003
44. Chairman Damodar Valley Corporation,DVC Towers, VIP Road,Kolkata – 700 054
45. Managing Director Assam Power Generation Corporation Ltd.
Bijulee Bhawan, Paltan Bazar, Guwahati- 781 001.
46. Managing DirectorMadhya Pradesh Power Generating Co. Ltd.Shakti Bhawan, VidyutnagarP.O. Jabalpur- 482 008.
47. Managing DirectorHaryana Power Generation Corporation Ltd.Urja bhawan, C-7, Sector-6Panchkula, Haryana-13410
File No.CEA-PS-14-80/1/2019-PSETD Division-Part(2)
48. ChairmanGujarat Urja Vikas Nigam Ltd.Sardar Patel Vidyut Bhawan,Race Course, Vadodara- 390 007
49. Chairman & Managing Director U.P. Rajya Vidyut Utpadan Nigam Ltd.Shakti Bhawan14- Ashok MargLucknow-226001
50. Chairman & Managing DirectorNEEPCO Ltd.Brookland CompoundShillong – 793003
51. Managing Director Maharashtra State Power Generation Co. Ltd. Prakashgad, Plot No. G-9, 4th Floor Bandra(E), Mumbai-400051
52. Chairman Indraprastha Power Generation Co. Ltd. Office of PRO, Himadri Rajghat Office Complex New Delhi.
53. Chairman & Managing Director Block-1 Neyveli-607801NLC India LimitedCuddalore District, Tamilnadu
54. Chairman & Principal Secretary (Energy) A.P. Power Generation Corporation Ltd.
Vidyut Soudha, Gunadala Eluru Road, Vijaywada
Andhra Pradesh – 520 004
55. Chairman & Managing Director Orissa Power Generation Corporation Ltd.Zone- A, 7th floor, Fortune TowersChandrasekharpur,
Bhubaneswar- 751 023.
56. Chairman & Managing Director Rajasthan Rajya Vidyut Utpadan Nigam Ltd. Vidyut Bhawan, Jyoti Nagar Jaipur (Rajasthan)
File No.CEA-PS-14-80/1/2019-PSETD Division-Part(2)
57. Chairman & Managing DirectorChhattisgarh State Power Holding Company Ltd., Vidyut Seva BhawanP.O. Sunder Nagar, Danganiya, Raipur- 492 013 (Chhattisgarh)
58. Chairman & Managing DirectorTANGEDCO10th Floor/NPKR Ramasamy Malikai, No. 144, Anna Salai, Chennai- 600 002
59. Chairman & Managing DirectorTelangana State Power Generation Corporation Ltd.Vidyut Soudha, KharatabadHyderabad – 500082
60. ChairmanJharkhand Urja Utpadan Nigam Ltd.Engineering Building, HECDhurwaRanchi-834004
61. Chairman & Managing DirectorBharat Heavy Electricals Ltd.BHEL House, Siri Fort,New Delhi-110049
62. Chairman & Managing DirectorToshiba Transmission & Distribution System(I) Pvt. Ltd.Rudraram, Patancheru Mandal, Medak District,Telangana-502329
63. ChairmanBhakra Beas Management Road,Sector-19B, Madhya MargChandigarh-160019
64. Chairman & Managing DirectorPragati Power Corporation LimitedHimadri, Rajghat Power House Complex,New Delhi – 110002
65. Managing DirectorUttarakhand Jal Vidyut Nigam Ltd.Maharani Bagh, G M S Road,Dehradun, Uttarakhand- 248 008
66. Chairman & Managing DirectorNational Hydro Power Corporation Ltd.
File No.CEA-PS-14-80/1/2019-PSETD Division-Part(2)
Corporate Office, NHPC Office Complex,Sector 33, Faridabad 121 003, Haryana
67. Chairman & Managing DirectorSJVN LIMITEDHimfed Building,New Shimla 171 009
68. Chairman & Managing DirectorTHDC INDIA LTD.Pragatipuram, Bye Pass Road,Rishikesh 249 201 (Uttarakhand)
69. Head- Transmission BusinessAdani Transmission (India) Ltd.,Sambhav HouseJudges Bungalow Road, BodakdevAhmedabad 380015, Gujarat
70. Shri. T. A. N. ReddyVice president B. D. & Corporate Affairs (Sterlite Power)
F – 1, The Mira Corporate Suits, 1 & 2, Ishwar Nagar,Mathura Road, New Delhi 110065
71. L&T Infrastructure Development Projects Limited (L&T IDPL),L&T campus TCTC Building, First Floor,Mount Poonamallee Road, Manapakkam,Chennai - 600089, Tamil Nadu, India.
72. Essel Infraprojects Limited6th Floor, Plot No. 19 & 20, Film City, Sector 16A,Gautam Buddha Nagar, Noida 201301.
73. ABB Power Products and Systems India Limited(A Hitachi ABB Joint Venture)8th floor, Brigade Opus, 70/401,Kodigehalli Main Road, Bangaluru-560092
74. GE T&D India Limited A225, A Block, Sector 83, Noida, Uttar Pradesh-201305
75. Telawne Power Equipments Private Limited Lodha Supremus – II, A – 129, Rd No. 22. Wagle Estate, MIDC, Thane (W) –400604
76. The Chief EngineerDistribution Planning & Technology Division, Central Electricity Authority
77. Director General
File No.CEA-PS-14-80/1/2019-PSETD Division-Part(2)
CENTRAL POWER RESEARCH INSTITUTE (CPRI)Prof.Sir C.V.Raman Road, Post Box No: 8066,SadaShiva Nagar (p.o),Bangalore, India , Pincode : 560 080
78. DirectorElectrical Research & Development Association (ERDA)ERDA Road, GIDC MakarpuraVadodara – 390 010Gujarat
79. The PresidentIndian Electrical and Electronics Manufacturers Association (IEEMA)Rishyamook Building, First Floor85 A, Panchkuian RoadNew Delhi – 110001
80. Director GeneralIndian Transformer Manufacturers Association (ITMA)2F CS-11, Ansal Plaza, Sector-3 Near Vaishali Metro Station (Opp. Bhushan Steel)Vaishali,Ghaziabad, U.P- 201 010
File No.CEA-PS-14-80/1/2019-PSETD Division-Part(2)