government of maharashtra water resources department...

166
1 Contractor No. of corrections Executive Engineer Government of Maharashtra Water Resources Department Kharland Survey & Investigation Division, Pen, Dist. Raigad Parent Portal: http://maharashtra.etenders.in WRD Portal: http://wrd.maharashtra.etenders.in Tender Notice No. 06 for 2013-2014 On line Tender Forms in B-1 Format, for the following work are invited by the Executive Engineer, Kharland Survey & Investigation Division, Pen, Umbarde Colony, Tal. Pen Dist. Raigad, PIN No. 402107, Phone No.02143-252203 from the contractors registered with the Government of Maharashtra in Appropriate class of Tender Notice. The blank tender documents should be downloaded from Government website http://wrd.maharashtra.etenders.in from 13/12/2013 to 03/02//2014. Blank Tender documents will not be sold by this office. Interested contractors will have to download tender documents from the website. Before submitting the tender documents the blank tender document cost is to be submitted in form of demand draft and to be drawn in favour of Executive Engineer, Khar Land Survey & Investigation Division, Pen, Dist-Raigad and original demand draft should be submitted in the office of the Executive Engineer, Khar Land Survey & Investigation Division, Pen, Umbarde Colony, Tal. Pen, Dist-Raigad on or before 03/02/2014 before 14:00 Hrs. on working days otherwise tender shall be rejected. For any queries in this regard the interested contractors can contact on telephone No. 02143-252203 during office hours. The Contractors participating first time in e-tendering Bids will have to procure Digital Signature Certificate, Username & Password from competent authorities as per guideline mentioned on homepage of the website. All requisite information required for the submission of Bid Capacity documents is available in the above said website. If any assistance is required regarding e-Tendering (upload / download) please contact e-Tendering Help Desk on number: 020 25315555. Note: to view detailed tender schedule, kindly visit e-Tendering portal: http://wrd.maharashtra.etenders.in Sr. No . Name of work Estimated cost Earnest Money Deposit (Rs.) Time limit for completion Class of Contr a- ctor Cost of Blank Tender Form 1 2 3 4 5 6 7 1 Renovation bund work of Annapurna Kharland scheme Tal Roha Dist. Raigad.@ ch. 0 to 3540 m. & Sluice Gate @ Ch. 960 m., 2100 m. & 3540 m. 2,55,34,893/ - 1,50,000/- 24 Calendar Months (Including monsoon) Class III and above Rs. 10,000 /- 1) Interested contractors have to see and download all documents from the above said website from 13/12/2013 to 30/02/2014.

Upload: others

Post on 16-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

1

Contractor No. of corrections Executive Engineer

Government of Maharashtra

Water Resources Department

Kharland Survey & Investigation Division, Pen, Dist. Raigad

Parent Portal: http://maharashtra.etenders.in

WRD Portal: http://wrd.maharashtra.etenders.in

Tender Notice No. 06 for 2013-2014

On line Tender Forms in B-1 Format, for the following work are invited by the

Executive Engineer, Kharland Survey & Investigation Division, Pen, Umbarde Colony, Tal.

Pen Dist. Raigad, PIN No. 402107, Phone No.02143-252203 from the contractors registered

with the Government of Maharashtra in Appropriate class of Tender Notice.

The blank tender documents should be downloaded from Government website

http://wrd.maharashtra.etenders.in from 13/12/2013 to 03/02//2014. Blank Tender

documents will not be sold by this office. Interested contractors will have to download tender

documents from the website. Before submitting the tender documents the blank tender

document cost is to be submitted in form of demand draft and to be drawn in favour of

Executive Engineer, Khar Land Survey & Investigation Division, Pen, Dist-Raigad and

original demand draft should be submitted in the office of the Executive Engineer, Khar Land

Survey & Investigation Division, Pen, Umbarde Colony, Tal. Pen, Dist-Raigad on or before

03/02/2014 before 14:00 Hrs. on working days otherwise tender shall be rejected. For any

queries in this regard the interested contractors can contact on telephone No. 02143-252203

during office hours.

The Contractors participating first time in e-tendering Bids will have to procure

Digital Signature Certificate, Username & Password from competent authorities as

per guideline mentioned on homepage of the website.

All requisite information required for the submission of Bid Capacity documents is

available in the above said website. If any assistance is required regarding e-Tendering

(upload / download) please contact e-Tendering Help Desk on number: 020 – 25315555.

Note: to view detailed tender schedule, kindly visit e-Tendering portal:

http://wrd.maharashtra.etenders.in

Sr.

No

.

Name of work Estimated

cost

Earnest

Money

Deposit

(Rs.)

Time limit

for

completion

Class

of

Contr

a- ctor

Cost of

Blank

Tender

Form

1 2 3 4 5 6 7

1 Renovation bund work of

Annapurna Kharland scheme

Tal Roha Dist. Raigad.@ ch. 0

to 3540 m. & Sluice Gate @

Ch. 960 m., 2100 m. & 3540 m.

2,55,34,893/

- 1,50,000/-

24 Calendar

Months

(Including

monsoon)

Class

III and

above

Rs.

10,000

/-

1) Interested contractors have to see and download all documents from the above said

website from 13/12/2013 to 30/02/2014.

Page 2: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

2

Contractor No. of corrections Executive Engineer

2) It is stipulated that the forms of Bid capacity form are available on the above said

website from 13/12/2013 to 31/12/2013 upto 17.00 hrs. by payment of cash amount of

Rs.2000/-in the office of Executive Engineer, Khar Land Survey & Investigation Division

Pen- Raigad. Bid documents will be available on the above said website after scanning the

copy of receipt. Those contractors whose Bid documents form fees is not received in cash by

the department on or before 31/12/2013 will not be evaluated further & will be disqualified. It

is essential that the details as demanded in the detailed tender notice and duly certified by an

officer not below the rank of the Executive Engineer shall be uploaded online in the format of

the bid capacity form upto 14.00 hrs. on or before -01/01/2014. The bid capacity of the

tenderer will be decided on the basis of these details.

3) The pre-tender conference will be open to only those prospective tenderers whose

photocopy of demand draft towards the cost of blank tender is received in the office of

Executive Engineer, Khar Land Survey & Investigation Division Pen- Raigad, upto before

31/01/2014 and having the proof of identity for authorisation along with the proof showing

that the tenderer is registration appropriate class of Govt. of Maharashtra period of validity.

Pre-tender conference will be held at the office of Chief Engineer, Water Resources

Department, Konkan Region, Hutatma Chowk, Hong Kong Bank Bldg. 4th

floor, Mumbai-23

dated -31/01/2014 at 15.00 hrs.

4) The e-tender will be opened online by the Project Director & Superintending

Engineer, Khar Land Development Circle Thane, Sinchan Bhavan, 4th floor, Kopari Colony,

Thane – East on dt. 07/02/2014 at 15.00 hrs (if possible).

5) No changes are to be made by the contractor in the tender documents published on

the website. If any changes made the tender documents will be rejected & action accordingly

will be taken against the contractor. Information published on the government website will

be final.

6) Right to reject any or all the tenders without assigning any reason thereof is

reserved.

7) If any assistance is required regarding e-Tendering (upload / download) please

contact Sify Nex Tenders Help Desk on No. 020 – 25315555.

(D.G. Mankar)

Executive Engineer,

Khar Land Survey & Investigation Division,

Pen-Raigad.

Page 3: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

3

Contractor No. of corrections Executive Engineer

GOVERNMENT OF

MAHARASHTRA WATER

RESOURCES DEPARTMENT

DETAILED TENDER NOTICE

1. INVITATION:

1.1 Online percentage tenders in B-1 form are invited, from

registered Contractors in class III and above with Government of

Maharashtra, for the work of 4402, capital outlay Renovation

bund work of Annapurna Kharland scheme Tal Roha Dist. Raigad.@ ch. 0 to

3540 m. & Sluice Gate @ Ch. 960 m., 2100 m. & 3540 m.

„Two Envelope System.‟

1.2 Details of work are as under :

1.2.1 Name of work 4402, capital out lay Construction Renovation bund work of Annapurna Kharland

scheme Tal Roha Dist. Raigad.@ ch. 0 to 3540 m. &

Sluice Gate @ Ch. 960 m., 2100 m. & 3540 m.

1.2.2 Estimated Cost Rs. 2,55,34,893/-

1.2.3 Earnest Money

(EMD)

Rs. 1,50,000/-

1.2.4 Security Deposit 4% Rs. 10,22,000/-

a) Initial 2% Rs. 5,11,000/-

b) From R.A.

2% Bills

Rs. 5,11,000/-

1.2.5 Period of Completion of

work

24 months (Including Monsoon Period)

Page 4: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

4

Contractor No. of corrections Executive Engineer

Detailed Tender Schedule

Sr.No. Activities Start Date & Time Expiry Date & Time

1 Online Tender Release 12/12/2013 10:00 Hrs 13/12/2013 16:00 Hrs

2 Online Bid Capacity Document

Purchase 13/12/2013 16.01 Hrs 31/12/2013 17:00 Hrs

3 Online Bid Capacity Document

Download & online Preparation 13/12/2013 16.00 Hrs 01/01/2014 14:00 Hrs

4 Online Hash Generation For Bid

Capacity 01/01/2014 14.01 Hrs 06/01/2014 17:00 Hrs

5 Online Submission of Bid

Capacity 06/01/2014 17:01 Hrs 08/01/2014 13.00 Hrs

6 Online Bid Capacity Opening and

Short listing 08/01/2014 13:01 Hrs 03/02/2014 17:00 Hrs

7 Online Main Tender Preparation 03/02/2014 17.01 Hrs 03/02/2014 21:00 Hrs

8 Online Tender Document

purchase & Download 03/02/2014 21:01 Hrs 07/02/2014 14:00 Hrs

9 Online Technical Bid Preparation 03/02/2014 17:01 Hrs 07/02/2014 14:00 Hrs

10 Online Commercial Bid

preparation 03/02/2014 17:01 Hrs 07/02/2014 14:00 Hrs

11 Online Bid Closing 07/02/2014 14.01 Hrs 07/02/2014 17:00 Hrs

12 Online Submission of Bid 07/02/2014 17.01 Hrs 10/02/2014 17:00 Hrs

13 Online Tender Opening

(Technical) 11/02/2014 11:01 Hrs 12/02/2014 17:00 Hrs

14 Online Tender Opening

(Commercial) 11/02/2014 11:01 Hrs 12/02/2014 17:00 Hrs

1.3 Definitions and Interpretation

In the tender document, the following terms shall have the meanings

hereby assigned to them except where the context otherwise requires. (a) “Government” shall mean the “Government of Maharashtra”

(b) “Department” shall mean water Resources Department of Government of

Maharashtra (c) “Chief Engineer” shall mean Chief Engineer, Water

Resources

Department, Konkan Region, Mumbai. (d) “Engineer/Engineer-in-charge” shall mean the Executive Engineer in

charge of the works and shall also include the superior officers of the

Page 5: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

5

Contractor No. of corrections Executive Engineer

Engineering Departments of the Government i.e. the Superintending

Engineer of the respective Circle or the Chief Engineer. (e) “Engineer‟s Representative” shall mean the Sub-

Divisional Engineer/Assistant Executive Engineer/Sub-Divisional

Officer/Assistant Engineer (Grade-I), who is in direct charge of the works

and shall include any Civil Engineer of the Government. (f) “Contractor” shall mean the person, firm or company who enters into

contact, with the Government and shall include their

executors, administrator‟s successors and submitted assignees. (g) “Contract” shall mean and include agreement having the following

documents

Part I Tender Documents

Part II Specifications

Part III Drawings (h) “Work” shall mean the work to be executed in accordance with the

contract.

(i) “Specifications” shall mean the specifications for material and works as

specified in the contract. (j) “Drawings” shall mean prints of the maps, drawings, plans of the contract

and shall include any modification of such drawings as may be issued by

the Engineer-in-charge from time to time. (k) “Site” shall mean the land and the other places on, under, in or through

which the works are carried out and any other lands or places provided by

the Government. (l) “Defect(s) liability period” shall mean the period mentioned in clause 20 of

B-1 Tender Form from the date of issue of completions certificate by the

Engineer-in-charge. 1.4 Singular and plural:

Words imparting the singular number shall also include the plural and vice

versa where the context requires. 1.5 Heading and marginal headings

The headings and marginal headings in the contract are solely for the

purpose of facilitating references and shall not be be deemed to be a part

thereof or taken into consideration in the interpretation or construction

thereof or of the contract.]

2. ELIGIBILITY- The contractor who qualified in Bid capacity legible to

Page 6: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

6

Contractor No. of corrections Executive Engineer

Download & Upload Blank Tender form

2.1 The contractor shall upload scanned copy of Registration Certificate of

appropriate Class of Government of Maharashtra during bid preparation stage.

2.2 TENDER FORMS: 2.2.1 Information regarding the work for which the Tenders are invited blank tender

forms can be obtained from the office of the Engineer-in- charge of the work

during 11.00 to 17.00 hours on working days from 12/12/2013 to 03/02/2014.

The tender document is uploaded / released on Government of Maharashtra,

(GOM) e-tendering website http://maharashtra.etenders.in and has to be

downloaded as well as filled up and submitted online ONLY as per the

schedule. Tender document and supporting documents may be purchased and

downloaded from following link of http://wrd.maharashtra.etenders.in on e-

Tendering website of Government of Maharashtra,

http://maharashtra.etenders.in by filling Demand Draft details online.

Tenders will be submitted by the bidders online on or before 07/02/2014 upto

14.00 Hrs. and will be opened online in the office of the Project Director and

Superintending Engineer, Kharland Development Circle, Thane, Sinchan

Bhavan, Kopari colony, Thane (E) on dtd. 07/02/2014 at 15.00 hrs. in the

presence of contractors, who intend to remain present, if possible.

2.2.2 The contractor shall upload scanned copy of Registration Certificate of

appropriate Class of Government of Maharashtra during bid preparation stage. 2.2.3 BID CAPACITY

The Bidding capacity will be evaluated as a prequalification in the

following manner.

Bid Capacity = (A x N x 2) – B

A = Maximum value of Civil Engineering works executed in any one year

during the last 5 financial years (value updated to the R.S.R. for the year

2011-2012 which will be taken prevailing into account for the completed

and on goring works.) Financial years concerned are 2008-09, 2009-10,

2010-11, 2011-2012 & 2012-13

B = Value of existing commitments and works (ongoing) as on to be

completed in the period stipulated for completion of the work in the present

tender.

N = Number of years prescribed for completion of the work for which the bids

are invited = (24 Calendar Months) = 2 years.

Page 7: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

7

Contractor No. of corrections Executive Engineer

Information about A and B mentioned above is required to be submitted in

the Proforma given below. Above information is required to be certified by

an officer not below the rank of Executive Engineer, of the concerned

Division. This information will have also to be certified by income tax

clearance certificates which shall be attached with bid capacity documents.

The Bid Capacity calculated as above should not be less than the

estimated cost put to tender. i.e.Rs.255.35 Lakh

Details of “A”: Values of Civil Engineering works executed during the last

5 years.

Financial

Year in

which

work is

executed

Details of

execution 1.Contract-1

2.Contract-2

3.Contract-3

Cost of

work

executed

against

contract

Updated cost of

work executed

against contract

every year (updated

to

current R.S.R.)

Total up

dated

cost of

work for

the year

2008-09

2009-10

2010-11

2011-12

2012-13

NOTE:

i) The cost of work executed in a year updated to the R.S.R. 2012-13 levels to

be justified by detailed computations. ii) The cost may be updated by 10% per year (compounded) and no

supporting detailed computations may be furnished

(Factor of updating cost of each year to bring the cost to 2011-12 level

2008-09 1.464

2009-10 1.331

2010-11 1.21

2011-12 1.1

2012-13 1

iii) Computation for A & B (both) shall be done either by method at note

No. (i) or by No.(ii)

NOTE: R.S.R. which is prevailing on November - 2013 shall be considered as

current R.S.R. for the purpose.

Page 8: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

8

Contractor No. of corrections Executive Engineer

DETAILS OF B:

Value of existing commitments and work (on going) or to be Completed in

the period stipulated for completion of work in the present tender i.e. from

…………. to ………..

Details of existing

commitments separate

for each contract.

Cost of work to be

executed each year

against the contract in

hand at contract rate

updated to

Total cost of existing

commitments.

1.Contract-1

2.Contract-2

3.Contract-3

NOTE:

i) The cost of work executed in a year updated to the RSR 2012-13 levels to

be justified by detailed computation ii) Alternatively the cost may be updated by 10% per year (compounded)

and no supporting detailed computation may be furnished

3. Computation of Value.

3.1 Intending tender should own and also should arrange for the machinery as

shown below :

Sr.N

o.

Type of Machinery Required

Machinery for

the work.

Machinery to be

owned by the

tenderer

1.

2.

3.

4. 5.

6.

Mixer

Vibrator

Poclain

Tippers

Water Pumps

J.C.B.

1

1

1

4

4

1

50% Machinery

to be owned by

the contractor.

In respect of machinery to be owned by the tenderer, satisfactory documentary

proof of ownership shall be produce.

Page 9: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

9

Contractor No. of corrections Executive Engineer

CERTIFICATE

This is to Certify that M/s. Shri.

…………………………… ………………… ………………

Government Contractor has been awarded the work (Name of work)

…………………………….. amounting to Rs………… On B/1/B-2

Agreement No. ………………….. dated ………………. And the

contractor is liable to execute the work amounting to Rs……….. during the

next ……. Years as per conditions stipulated in the Tender.

Executive Engineer

2.3 EXPERIENCE OF SIMILAR TYPE OF WORK :-

The intending tenderer should have experience of construction or renovation of earthen bund and & sluice gates of Kharland Schemes works under Central or State Government one work costing not less than 200 lakhs during the last five years certified by not below the rank of Executive Engineer

2.4 The intending tenderer should have completed quantity of Concrete of 200

Cum and excavation and earthwork of 70,000 Cum. during the last five

years.

2.5 Even though the bidders satisfy the above requirements, they are likely to be

disqualified if they have.

i) Made untrue and/or false representation in the request form statement and

attachments required as proof of qualification requirement.

ii) Records of proof of performance such as abandoning work not properly

completing contract, in ordinate delays in completion or financial failure etc.

The tenderer will be deemed to be eli e to purchase the blank tender form only if

he satisfies all the above criteria (Sr.No. 2.1 to 2.5) by submitting requisite

documentary proof upto the last date for issue of the bid capacity form.

Page 10: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

10

Contractor No. of corrections Executive Engineer

3.0 DETAILS OF WORK

The estimated cost, earnest money deposit, class of contractor period of

completion of and other information is given Annexure 'A' of this Section.

4.0 ISSUE OF BLANK TENDER FORMS

Information regarding the work for which the tender are invited as well as blank

tender forms can be obtained from http://wrd.maharashtra.etenders.in cost of

blank tender form in form of D.D. duly plaged in the name of E.E. Kharland

Survey & Investigation Division, Pen, Dist. Raigad & scan copy of D.D. must

be upload on website.

5.0 PRE TENDER CONFERENCE :

i) A pre tender conference, which is open to all who have purchased the tender

forms, will be held on 31/01/2014 at 15.00 hrs. in the office of the Chief

Engineer, Water Resources Department, Konkan Region, Hutatma Chowk,

Hong Kong Bank Bldg. 4th floor, Mumbai. Where in prospective tenderer will

have an opportunity to obtain clarification regarding the work and the tender

conditions.

ii) The prospective tenderer are free to ask for any additional information or

clarification either in writing or orally and repay to the same will be given by

the Superintending Engineer/Chief Engineer in writing and his clarification

referred to as common set of conditions, shall form part of tender documents

and which will also be common and applicable to all tenderers. The tender

submitted by the tenderer shall be based on the clarification additional facility

issued (if any) by the department and this tender shall be unconditional. The

conditional tenders will be summarily rejected as non from the conditional

tenders will be rejected as non- responsive.

6.0 REVISION OR AMENDMENT OF THE TENDER DOCUMENTS: 6.1 Rights are reserved to revise or amend the tender documents prior to the last

date notified for the online submission of tenders and such revision or

amendments or extensions shall be communicated to all tenderers by printing

notice on the web site and / or by notice in the press as may be considered

suitable.

6.2 Tenderer shall be presumed to have carefully examined all documents, forms,

statements, special conditions, schedules, drawings and pacifications of

contract and to have fully acquainted himself with all details of the site, his

own quarries for rubble, sand, earthwork etc. locations of materials, river

and weather characteristics and labour conditions in general and with all the

necessary information and data etc. prior to tendering of the work.

Page 11: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

11

Contractor No. of corrections Executive Engineer

6.3 The tenderers should see, in particular, the quarry sites and satisfy

themselves about the quality and quantity of materials available as the rates

quoted will be inclusive of all lead and lifts involved even the materials are

required to be brought from areas other than those specified in the quarry,

plants etc. for the above work. 6.4 The tenderers shall arrange to bring his own material from borrow area such

as rubble, boulders, murum, sand, metal and hearting soil etc. from approved

quarries. It is necessary for the contractor to obtain the permissions

from the revenue department and the other concerned authorities through

the Executive Engineer, before removing the materials, pay royalties etc. All

quarry fees, royalties, octroi dues and ground rent for stacking materials, if

any, shall be paid by the contractor. No reimbursement will be allowed thereon

by the department. 7 MANNER OF SUBMISSION OF TENDER AND ITS

ACCOMPANIMENTS a) ENVELOPE NO. 1:

The „Envelope No. 1‟ (Technical Envelope) shall contain the scanned

copy of following documents. These documents need to be digitally signed by

individual contractor‟s digital signature and uploaded during online bid

preparation stage and the required original copies shall be kept ready at the

time of opening of the tender. i. The blank tender document cost Rs 10000/- will have to be paid by demand

draft and is to be drawn in favour of “Executive Engineer, Khar Land Survey &

Investigation Division, Pen-Raigad” and original demand draft should be

submitted in the office of Executive Engineer, Khar Land Survey &

Investigation Division, Umbarde colony, Pen, Raigad on or before 30/02/2014

14:00 Hrs on working days.

ii. Scanned copy of Earnest Money Deposit in the form of Government Treasury

Challan or Term Deposit Receipt for one year of required amount pledged in

the name of the Executive Engineer, Kharland Survey & Investigation

Division, Pen-Raigad shall be enclosed and original Treasury Challan or Term

Deposit Receipt should be submitted in the office of Executive Engineer, Khar

Land Survey & Investigation Division, Umbarde colony, Pen, Raigad on or

before 30/02/2014, 17:00 Hrs on working days. Certificates of exemptions for

payment of earnest money, issued by competent authority, if valid, shall be

accepted instead of the Earnest Money Deposit.

iii. Document certifying the bidder as a registered contractor with Public Works

Department of the Government of Maharashtra valid on date of submission of

tender.

Page 12: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

12

Contractor No. of corrections Executive Engineer

iv. Certificate of Registration under Clause 16(i) of Maharashtra Value Added

Tax Act – 2005 or the Certificate of Registration under Rule-8 of The

Bombay Sales Tax Rules-1959. Contractors not submitting any of the two

documents will be liable for Tax Deduction at Source at the rate of 5% of the

contract Price. v. Deed of partnership or Article of Association and Memorandum of

Association for limited Company, duly registered, if applicable. vi. Power of Attorney, if necessary.

vii. Copy of Certificate of enrolment under The Maharashtra State Tax on

profession, trades, callings and employment act 1975. (See rule 3(2) and

certificate of enrollment under section (2) or sub-section (2A) of section 5 of

Maharashtra State Tax on professions, trades, calling and employment act 1975.

viii. Details of works of similar type and magnitude carried out by the

tenderer (in Appendix A) ix. Details of works of similar type of works tendered for and in hand with the

value of work unfinished on the last date of submission of tender. The

Certificates from the heads of the office, not below the rank of Executive

Engineer, under whom the works are in progress, should be enclosed (in

Appendix B) x. List of plants and machinery immediately available with the tenderer for use

on this work and list of machinery proposed to be utilized on this work but

not immediately available and the manner in which it is proposed to be

procured (in Appendix C) xi. Proof of having tenderer‟s own machinery.

xii. A certified copy of Power of attorney for signing the tender in case of

proprietary firm /partnership firm /Ltd. Co. / Ltd. Corporation

/ sponsoring firm made by a Group of firms. b) ENVELOPE NO. 2:

The Envelope No.2 shall contain only the main tender. A l l f i n a n c i a l

o f f e r s m u s t b e p r e p a r e d a n d s u b m i t t e d o n l i n e a t

h t t p : / / w r d . m a h a r a s h t r a . e t e n d e r s . i n a s p e r t h e

i n s t r u c t i o n s o n t h e p o r t a l a n d s h o u l d b e d i g i t a l l y

s i g n e d . The tenderer should quote his offer in the form of percentage

below or above the estimated cost given in Schedule „B‟. He should not quote

his offer any where directly or indirectly in Envelope No.1, failing which the

Page 13: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

13

Contractor No. of corrections Executive Engineer

Envelope No.2 shall not be opened and his tender shall stand rejected. The

contractor shall quote for the work as per details given in the main tender

This tender shall be unconditional. Documents containing the common set of

conditions, as required in Clause 2.4 of this Detailed Tender Notice, if

applicable, shall also be u p l o a d e d d u r i ng o n l i n e b i d p r e pa r a t i o n in

the Envelope No. 2. 8 INSTRUCTIONS FOR SUBMISSION OF ENVELOPE NO.1:

Documents to be submitted in envelope No.1 should be digitally

signed by individual contractor‟s digital certificate and should confirm

to the instructions given below.

i) EARNEST MONEY:

Each tender shall be accompanied by an Earnest Money for

Rs. 1,50,000/- ( One Lac Fifty thousand Only) in the form of an original

receipt Treasury/Sub-Treasury challan under the Head of Account „Earnest

Money Deposit - Revenue Deposit‟ or one year Term Deposit in any

Nationalized Bank duly pledged in the name of the Executive Engineer,

Kharland Survey & Investigation Division, Pen-Raigad original Treasury

Challan or Term Deposit Receipt should be submitted in the office of

Executive Engineer, Khar Land Survey & Investigation Division, Umbarde

colony, Pen, Raigad on working days. E.M.D in the form of cash or

cheque or bank Guarantee shall not be acceptable.

The amount of E.M.D. will be released back to the unsuccessful tenderers on

deciding upon the acceptance or otherwise of the tender.

The C on t ra c t o r /Contractors w h o i s /are e xempted f r o m payment o f

Earnest Money should upload valid certificate of exemption or attested copy

of such certificate issued by P.W.D without which the tender will not be

considered. The earnest money amount shall not carry any interest whatsoever.

ii) SECURITY DEPOSIT:

The successful tenderer shall have to pay 2% security Deposit in the

form of approved securities in lieu of cash deposit mentioned above such as

Government securities, Bank Guarantee from scheduled banks, National

Savings Certificates, Post Office Cash Certificates for value for which they

can be encashed at the time of presentation as security deposit. Treasury

Savings Deposit Certificates which are issued by the Reserve Bank of India,

and the scrip of rural debentures issued by the Maharashtra State Co-

operative Mortgage bank Ltd., standing in the name of depositor shall be

accepted if those are pledged in the name of the Executive Engineer,

Kharland Survey & Investigation Division, Pen-Raigad towards the payment

of initial security deposit, then the earnest money deposited will be refunded

Page 14: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

14

Contractor No. of corrections Executive Engineer

to him only after payment of Security Deposit. In addition, a 2% Security

Deposit shall be recovered from the bills of Contractors deducting @ 4%

of the value of bills at a time. iii) VALUE ADDED TAX

The tender rates are inclusive of all taxes, rates, cesses and are also inclusive of

the leviable tax in respect of sale by transfer of property in goods involved in the

execution of a works contract under the provision of rule 58 of Maharashtra

Value Added Tax Act 2005, for the purpose of levy of tax.

iv) PROFESSIONAL TAX:

Certificate of registration with the professional tax officer of the district in

Form IA Certificate of registration under Section 5(1) and 5(2) of the

Maharashtra State Tax on Professions, Trades, Callings and Employment Act,

1975 shall be submitted online in the Form as below. V) ADDITIONAL SECURITY DEPOSIT

If the contractor quote this offer more than 10% below the estimated cost. He

shall submit additional security deposit as per following formula

(Contractor‟s offer (-) 10 x 10/100 = percentage of additional security

Deposit)

This additional security deposit should be in the form of bank guarantee for

the period upto prescribed period of tender. This additional security will be

refund at the time of final bill.

PROFESSIONAL TAX CLEARANCE CERTIFICATE

This is to certify that M/s ---------------------------------------------------------

(address)----------------------------------------------------------------------------- is a

registered dealer under the Maharashtra State Tax on Professions. Trades,

calling and Employments Act No. XV of 1975.

holding Registration Certificate No ---------------------w.e.f -----------------------

-------------------- and under section 5 (1) and 5 (2) respectively. This said

dealer has paid all tax due upto 31st

March ------------- (Previous Year) under

this act. The dealer has paid the professional tax dues for the employees

mentioned below.

A Sr.No Name of Employee Designation

Page 15: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

15

Contractor No. of corrections Executive Engineer

B.

Sr.No Name of the owner carrying on

profession status

There is no professional Tax due outstanding against the dealer under the

Act. This Certificate is valid for One year from the date of issue.

Place :

Date :

Designation

Signature

Professional Tax Officer District

Page 16: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

16

Contractor No. of corrections Executive Engineer

It should also be made clear that the employees shall be all those who receive

the wages/salaries from the tenderer and shall include the office and held

staff and those operating the machinery/equipment. This is also to ensure that

the machinery said to be deployable for the said work is really in the ownership

of the tenderer.

9 INSTRUCTIONS FOR SUBMISSION OF ENVELOPE NO. 2

Documents to be submitted online in Envelope No.2 should be

digitally signed by individual contractor‟s digital certificate and

should confirm to the instructions given below. i) CONTRACTOR TO INFORM HIMSELF FULLY:

The tenderer shall be deemed to have fully acquainted himself with the

work and site conditions and carefully examined the special conditions, the

specifications, schedules and drawings and shall be deemed to have fully

informed himself regarding the local conditions. The tenderer shall also be

deemed to have fully acquainted with the various leads and lifts involved in

the works and materials of constructions as well as shall be deemed to

have fully acquainted with his own various quarries for construction

materials, their availability and adequacy etc. ii) CONDITIONAL TENDER:

Conditional tender will be summarily rejected. The tenders which do not

fulfill any of the notified requirements laid down in this detailed tender

notice, the general rule and directions for the guidance of the tenderers as

mentioned in B-1 form or are incomplete in any respect are likely to be

rejected without assigning reasons thereof. iii) TENDERED RATE:

The tenderer should quote his offer online during bid preparation stage as

per online tender schedule, in figures as well as in words in English. In case

there is a difference between the rates quoted as expressed in words and in

figures, the rates as expressed in words will be taken as correct irrespective

of whether it is lower or higher than that expressed in figure.

No alteration in the form of tender and in schedule of quantities will be

permitted. The rates mentioned in the tender for all items of work shall be

taken applying to all conditions, weather and will be inclusive of all taxes, if

any. The rates should be written in words in one line only as far as possible.

iv) If the offer quoted by the tenderer is less than 90 % or more than 110 % of

the updated estimated cost, then the tenderer shall furnish his detailed item-

wise justification for all items costing Rs. 50,000/- (Fifty thousand) and

Page 17: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

17

Contractor No. of corrections Executive Engineer

above put to tender in Envelope No. 2 in order to establish the

workability and reasonableness of the rates. Tenderer shall also submit

additional information in justification of the rates wherever called for by the

department without which the offer will not be considered.

v) QUANTITIES PUT TO TENDER:

The quantities given in the schedule „B‟ as put to tender by the

Department for various items therein are approximate as some of the items

of work put to tender are likely to be executed departmentally, till the

contract agency is fixed. Such quantities which would be executed till the

fixation of contract agency will stand deducted from the quantities entered

in the schedule „B‟ at the time of completing the tender documents by

the contractor. The contractor should take cognizance of this fact and no

claims will be tenable on account of such reduction in quantity.

The quantities of items on which the Department has carried out the work

as measured on the date of work order shall stand deducted from the

quantities stipulated in schedule „B‟ as put to tender by the

Department for the purpose of application the stipulation of clause 38 of

conditions of the contract of the tender.

10

TENDER UNITS

The tender has been invited in the Metric System of measurements.

Tenderer should particularly note the units mentioned in schedule „B‟ on

which rates are to be based.

11

CORRECTIONS

No corrections should ordinarily be made in the tender documents. Any

corrections in the entries made by the tenderer should be signed /

cancelled by crossing the incorrect por t ion and wr i t ing the

corrected portion above and each such correction shall bear the

attestation of the tenderer

12

SIGNING OF TENDER DOCUMENT

The tender shall contain the name, residence and place of business of

person or persons making the tender

The tenderer by partnership firm shall furnish the full names of all the

partners in the forwarding letter. The letter shall be signed by the partner

or by an authorized representative followed by the name and designation

of the person signing.

An attested copy of the partnership deed shall be furnished.

Page 18: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

18

Contractor No. of corrections Executive Engineer

Whenever, whether in the submission of the tender or later, in other

matters, the signatures are made by one person on behalf of the company; the

tenderer shall supply an attested copy of the power of attorney.

Witness shall be persons of status and probity and their names,

occupations and address shall be stated below their signatures. All

signatures shall be dated.

The tender is also liable to be rejected outright, if, while submitting,

i) The tenderer proposes any alternation in work specified in the tender or in

the time allowed for carrying out the work or any other condition, ii) Any erasures are made by the tenderer in the tender,

iii) All corrections and additions or pasted slips are not signed by the

tenderer and

iv) Tenderer, or, in the case of firm, each partner or the person holding the

power of attorney authorizing him to do so thereof does not sign or the

signature is not attested by a witness in B-1 tender form at the space

provided for the purpose. 13 SUBMISSION OF TENDER:

13.1 The interested contractors / bidders will have to make online payment (using

credit card/debit card/net banking) of Rs. 1036/- (including service tax) per bid

per tender to online service provider of e-Tendering system at the time of

entering online Bid Submission stage of the tender schedule

13.2 The two envelopes No. 1 and 2 shall be d i g i t a l l y sealed and s i g n e d

a n d s u b m i t t e d o n l i n e a s p e r t h e o n l i n e t e n d e r s c h e d u l e .

13.3 The date and time for online submission of envelopes shall strictly apply

in all cases. The tenderers should ensure that their tender is prepared

online before the expiry of the scheduled date and time and then

submitted online before the expiry of the scheduled date and time.

Offers not submitted online will not be entertained.

13.4 If for any reason, any interested bidder fails to complete any of online stages

during the complete tender cycle, department shall not be responsible for that

and any grievance regarding that shall not be entertained. 14 OPENING OF TENDERS:

Page 19: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

19

Contractor No. of corrections Executive Engineer

On the date specified in the tender notice, following procedure will be adopted for

opening of tender. 14.1 ENVELOPE No. 1: First of all, Envelope No. 1 of the tenderer will be opened on l in e th r ou gh e -

Ten de r i ng p ro ce d ure to verify its contents as per requirements. For the

purpose of this particular contract, the tenderer shall meet the requirements

as stated at Sr. No. 4 (a) above of this section. If the various documents

contained in this envelope do not meet the requirements, a note will be

recorded accordingly by the tender opening authority and the said tenderer‟s

Envelope No. 2 will not be considered for further action but the same will

be recorded. Decision of the tender opening authority shall be final in this

regard. 14.2 ENVELOPE No. 2: This envelope shall be opened on l ine th r ough e -Tender ing p rocedure

immediately after opening of envelope No. 1 only, if the contents of

envelope No. 1 are found to be acceptable to the Department. The tendered

rate shall then be read out by the Tender Opening authority.

THE TENDER WILL BE LIABLE TO BE REJECTED OUT RIGHT IF,

WHILE SUBMITTING: 14.2.1 The tenderer proposes any alteration in the work specified in the tender or

in time allowed for carrying out work or any other unacceptable

condition, 14.2.2 Any of the pages and pasted slips of the tender are removed and / or

replaced, 14.2.3 All corrections and additions and pasted slips are not initialed by the

tenderer, 14.2.4 The tenderer does not sign, and the signature/signatures (in case of firm

each partner or power of attorney holder) is not witnessed by a

respectable person, in the space provided for in the B-1 tender form. 14.2.5 Schedule „B‟ of contract shows the items of work to be executed, the

estimated quantity, the rate, amount of such item as per estimate and the

total estimated cost put to tender. The tenderer should quote his rate in

terms of percentage above or below the said estimated cost by writing the

percentage both in words and figures In addition, the contractor shall fill

up the additional schedules in the tender (viz. Appendix - A, B, C & D).

Page 20: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

20

Contractor No. of corrections Executive Engineer

14.2.6 No modification in the form of the tender are permitted. 15 ACCEPTANCE OF TENDER:

Acceptance of tender will rest with the Project Director & Superintending

Engineer Kharland Development Circle, Thane who reserves the right to

reject any or all tenders without assigning any reasons thereto. The

acceptance of tender may be intimated to the contractor by letters, such

intimation shall be deemed to be an intimation of acceptance of tenders.

The tenderer whose tender is accepted will have to complete the contract

form within 15 days of being notified to do so and shall abide by all the

rules and regulations and special conditions enumerated therein or

attached herewith. In the event of failure of the tenderer to sign the

agreement within the stipulated time, the earnest money paid by him

shall be liable to be forfeited to the Government and the acceptance of

the tender shall be liable to be considered as withdrawn. In that event, the

work will be awarded to the next lowest or any other contractor to whom

the Government deems to be suitable. 16 VALIDITY FOR 120 DAYS:

The offer shall remain valid for a period of 120 (One hundred twenty)

days from the date of opening of tender and thereafter until it is

withdrawn by notice in writing by the tenderer, and duly addressed to the

competent authority and sent by Registered Post Acknowledgement Due.

If the acceptance of the tender is not communicated within 120 days or

before and if the offer is withdrawn by the contractor as aforesaid,

earnest money shall be refunded in full. 17 LATE BIDS:

Offers not submitted online through e-Tendering procedure will not be

entertained.

18 MODIFICATION AND WITHDRAWAL OF BIDS: 18.1 Withdrawal or modification of a bid between the deadline for submission of

bids and the expiration of the original period and bid validity specified in

the form of bid may result in the forfeiture of the bid security pursuant to

clause 1 of B-1 form. 19 COMPLETION OF TENDER DOCUMENTS: While completing the tender documents, the contractor must invariably complete

the appendices included in the tender documents giving correct information.

However, this information shall have to be submitted online by the

Page 21: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

21

Contractor No. of corrections Executive Engineer

contractor in the prescribed formats separately in Technical Envelope No.

1 as per provisions of paragraph 4 (a) of the detailed tender notice. 20 LANGUAGES: The language of all correspondence regarding this work shall be English only. 21 LICENCES UNDER CONTRACT LABOUR (REGULATION AND

ABOLITION) ACT 1970. The successful tenderer should produce to the satisfaction of the competent

authority accepting the tender a valid and current license issued in his

favour under the provisions of contract labour (Regulation and Abolition)

Act 1970 and the Maharashtra Contract labour (Regulation and Abolition)

Rules 1971, before signing the contract. On failure to do so, the acceptance

of the tender will be withdrawn and also the earnest money and additional

earnest money deposit, if any, will be forfeited to the Government.

22. Certificate from General Provident Fund Authority :-

Intending Tenderer should submit Certificate of Registration as per the

contractual labour Act 1970 from General Provident Fund and No Dues

certificate regarding payment of contribution towards his employer and

should submit this certificated in envelope No.1

23. ADDITIONAL CONDITION RELATING TO INSURANCE

CONTRACT WORK

Contractor shall take out necessary insurance policy / policies ( viz contractor

A 1 insurance policy, Erection All Risks Insurance Policy etc: as' decided by

the Directorate Insurance ) so as to provide adequate insurance cover for

execution of the awarded contract work for total contract value and complete

contract period compulsorily from the,-.Directorate of Insurance, Maharashtra

State Mumbai only. Its postal address for correspondence is 264 MHADA

first floor opp. Kalanagar Bandra (E) Mumbai 400051 (Telephone No.

26590403` / 26590690 ) and Fax nos. 26592461/ 26590403. ). Similarly all

workmen's appointed to complete the contract work are required to insure

Compensation Insurance Policy / Insurance Polices taken out from other

company will not be accepted. If or has effected insurance ' with any

insurance company, the same will not be accepted and the amount of premium

calculated by the Government Insurance Fund will be recovered directly from

the amount payable to contractor for the executed contract work and paid to

the Directorate of insurance fund Maharashtra State Mumbai. The Directorate

of Insurance reserves the distribute the riskk of Insurance among the other

Page 22: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

22

Contractor No. of corrections Executive Engineer

insurers.

24. QUARRIES

24.1 The location of quarries for soil, murum, metal, rubble, sand etc. as shown in

the drawing in case of land shown quarries was not available, the time of the

work in tender shall have to be executed with contractor's own rnarerials.

24.2 For the item of the work in tender all leads & lifts changes own included in

the construct rate hence contractor shall not make any claims what so ever in

this respect.

Page 23: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

23

Contractor No. of corrections Executive Engineer

ANNEXURE “A” (SECTION-I)

WORK AND SITE CONDITIONS 1. DESCRIPTION & SCOPE OF THE TENDERED PROJECT:

This Kharland Development Project is undertaken by Government of

Maharashtra. The work under the project envisages Renovation bund work of

Annapurna Kharland scheme Tal Roha Dist. Raigad.@ ch. 0 m. to 3540 m. &

Sluice Gate @ Ch. 960, 2100 & 3540 m. to protect the agricultural lands of the

above village from saline water entering through the nearby creeks. 2. CLIMATIC CONDITIONS

The climate of this region is humid. The work site is situated in saline &

marshy area. The annual rainfall in the area is heavy and is of the order of

2500 mm to 3500 mm. The rainy season generally commences from early

June and lasts upto beginning of October.

3. INFORMATION REGARDING WORKSITE

3.1 General

Location of work : About 40 km from District place

Alibag 20 km from Taluka place

Roha

Nearest railway Station : Roha on Konkan Railway.

18Kms. away

Road : Approachable by Mumbai-Goa

National Highway No. 17

Nearest petrol & diesel pumps : At Roha which is 18 km away.

Nearest Telephone

Telegram from site

: At Roha which is 18 km away

Land Acquisition : Not required.

3.2 The various leads involved in the work are tentative. The contractor shall

be deemed to have fully acquainted with these leads. He shall also get

acquainted with the availability of construction materials and their

adequacy, etc. No claims whatsoever shall be entertained to the

contractor. 3.3 The contractor has to establish the quarries for the construction

materials required within the leads specified for the respective materials at

his own cost and responsibility. No extra claim whatsoever will be

entertained by the department in this regard.

Page 24: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

24

Contractor No. of corrections Executive Engineer

3.4 Availability of Labour:

Some local unskilled labour may be available during non-agricultural

season but skilled labour may not be available. Contractor must

however make his own inquiries regarding the same. 3.5 Market :

The nearest Market is at ROHA which is 20 Km from the Project site.

The banking and Treasury facility is available at Alibag.

NOTE

It must be specifically understood that the above note is meant only for the

general guidance of contractors. The contractor has to make his own

verifications of the details of the site conditions, accesses to site of quarries,

availability of material, etc. No claim on account of any incorrectness of

the information given above will be entertained.

4 Details of work are as under :

a. Name of work Renovation bund work of Annapurna

Kharland scheme Tal Roha Dist.

Raigad.@ ch. 0 m. to 3540 m. & Sluice

Gate @ Ch. 960 m., 2100 m. & 3540 m.

b. Estimated Cost Rs. 2,55,34,893/-

c. Earnest Money

(EMD)

Rs. 1,50,000/-

d. Security Deposit Rs 10,22,000/-

a) Initial Rs. 5,11,000/-

b) From R.A. Bills Rs. 5,11,000/-

5. Class of contractor Class III and above.

6. Period of completion 24 Calendar months (including monsoon

period

Page 25: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

25

Contractor No. of corrections Executive Engineer

7) Information for obtaining Tender papers and its submittion

7.1 Name and address of the Executive

Engineer in Charge of work issuing

tender papers/bid assessment forms

and in whose name Earnest money and

security deposit is to be pledged.

Executive Engineer, Kharland

Survey & Investigation

Division, Pen-Raigad.

7.2 Period for issue of application forms

for Bid documents. 13/12/2013 to 31/12/2013

7.3 Cost of bank tender forms Rs.10,000/- (Rs. Ten Thousand

only )

7.4 Date, Times and place of pretender

conference 31/01/2014 at 15.00 Hrs. at the

office of the Chief Engineer,

Water Resources, Konkan

Region, Mumbai-23.

7.5 Time and date of submission of Tender

Documents. Upto 17.00 Hrs. on

05/02/2014.to 07/02/2014

7.6 Name and address of the office

receiving and opening of the tender Project Director &

Superintending Engineer,

Kharland Development Circle,

Thane. Kopri colony (E)

7.7 Period for completion of work 24 Calendar months including

monsoon

7.8 The name of authority for accepting Chief Engineer, Water

Resources, Konkan Region,

Mumbai-23.

8. Name of the Executive-in-charge of

the work in whose name Demand Draft

is to be drawn.

Executive Engineer, Kharland

Survey & Investigation

Division, Pen-Raigad.

9. Price Variation Information S.N. Component Percentage

1. Labour (KL) 41.64 %

2. Material (other) 54.69 %

3. POL (Kf) 3.67 %

10. Cost of Cement for Mix Variation N.A.

1) If the cement is procured by the

contractor

Rs. 325/- cost per bag.

11 Star rate of steel Rs. 48800/- MT

12. Star rate of Cement Rs. 6500/- MT.

Page 26: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

26

Contractor No. of corrections Executive Engineer

Page 27: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

27

Contractor No. of corrections Executive Engineer

SPECIAL CONDITIONS OF CONTRACT

1 Contractor to inform himself fully:

The contractor shall be deemed to have carefully examined the work and site

condition the special conditions, the specifications, schedules and drawings

and shall be deemed to have visited the work site, his own quarries for

rubble and sand and to have fully informed himself regarding the availability

of construction materials, local conditions, ancillary works required to be done

etc. before quoting the offer.

If he shall have any doubts as to the meaning of any portion of the special

conditions or the scope of work or the specifications or any other matter

concerning the contract, he shall, in good time, set forth the particulars

thereof and submit them to the Engineer-in-charge. The Engineer-in-

charge generally means the Executive Engineer directly in charge of the

work, but also means the Superintending Engineer of the Department for

exercising powers under this contract. 2. Contract Drawings and Specifications: 2.1 On acceptance of the tender, three sets of contract drawings and working

drawings as well as one certified copy of the accepted tender will be

supplied to the contractor free of charge within one week. On request by the

contractor and at the discretion of the Engineer-in-charge, the

contractor may be supplied additional copies of contract document to be

charged at the rate of Rs. Five/-(Rs. Five thousand only) per set and Rs.

100/- per working drawing. 2.2 The drawings which form a part of this contract show the works to be done

in such details as possible to do for the present. They will be

supplemented or superseded by such additional detail drawings as may be

necessary as the work progresses. The contractor shall carry out the work in

accordance with these additional and/or revised drawings as the case may be

at the applicable rates as per the contract. The contractor shall be supplied a

maximum number of three copies of each of such working drawings free of

charge. Should the contractor require any additional copy for his use, the

same may be supplied at the discretion of the Engineer-in-charge and the

contractor will be charged Rs. 1000/- per set of contract drawings and Rs.

100/- for each of such additional copy of each drawing.

2.3 The contractor shall check all drawings carefully and intimate the

Engineer-in-charge, immediately, the errors or omissions discovered. The

contractor shall not take advantage of any kind of errors or omissions in the

Page 28: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

28

Contractor No. of corrections Executive Engineer

drawing supplied. 3. Data and Drawing to be furnished by the Contractor:

a) Prior to the commencement of the work, the contractor shall submit to the

Engineer-in-charge for approval, drawings or prints as may be suitable in

triplicate showing the location of major plant workshop, if any roadways,

temporary bridges, unloading facilities and storage yards, etc., which he

proposes to put up at the site.

b) Then the contractor shall submit to the Engineer-in-charge for approval

within 7 days from the date of his receiving notice to start the work, a

layout plan of construction plant and equipment for the execution of the

work which the contractor proposes to adopt at site. c) Any changes in the approved layout will be subject to further approval.

d) The approval of the drawings, however, will not relieve the contractor of his

responsibility from any errors or omissions. 4. Errors, Omissions, Discrepancies:

a) In case of errors, omissions and/or disagreement between written and

scaled dimensions on the drawing or between the drawings

and specifications, the following orders of preference shall apply. i) Between actual scaled and written dimensions or description on drawing and

corresponding one in the specification, the latter shall be adopted.

ii) Between the written description of the item in the schedule of quantities and

the detailed specifications of the same item, the latter shall be applying.

iii) Between the quantities shown in the Schedule „B‟ of quantities and those

arrived at from drawings, the latter shall apply. b) The information in connection with works and work site as well as

specifications is contained in this book of contract in general and in

particular in two parts, viz special conditions and specifications for items of

work. In case of any discrepancy or repugnancy in the clauses in these

sections, the specifications will prevail over the special conditions.

c) The special conditions of contract and the specifications shall prevail over

various clauses of B-1 tender form. d) In all cases of omissions and/or doubts of discrepancies in the dimensions or

description of any item, a reference shall be made to the Engineer-in-

charge, whose elucidation, elaborations or decision shall be considered as

authentic and final subject to the clause 30 of B-1 form. The contractor

Page 29: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

29

Contractor No. of corrections Executive Engineer

shall be held responsible for any errors that may occur in the work

through lack of such reference and precaution. 5. Use of Site:

a) All land required shall be arranged by the contractor from private Land

owner/Revenue department at his own cost and no claim on this account

shall be entertained. b) All areas of operation, including those of his staff and labour colonies, in

case handed over to the contractor shall be cleared and handed over back in

good condition to the Engineer-in-charge. The contractor shall make good,

to the satisfaction of the Engineer-in-charge, any damage or alterations

made to areas which he has to hand over back or other property or

land handed over to him for the purposes of this work. c) The land shall, as hereinbefore mentioned, be handed over back to the

Engineer-in-charge within three months after the completion of the work

under this contract or the termination of the contract whichever is earlier.

Also no land shall be held by the contractor longer than that the Engineer- in-

charge shall deem necessary and the contractor shall on due notice by the

Engineer-in-charge vacate and return the land which the Engineer-in- charge

may certify as no longer required by the contractor for the purpose of the

works. In case the lands are not handed over back to the Department

within the time limit specified above, penal rent as may be decided by the

Engineer-in-charge will be recoverable.

d) The mangrove vegetation and forest is noticeable in project area. The

contractor should take utmost care for the preservation of this vegetation

and forest. Any damage in this vegetation and forest will have to be

compensated by the contractor and decision from Engineer-in-charge will be

final and binding on contractor. e) The contractor shall make at his own expenses, all preliminary

arrangements including site clearance, etc., immediately after the contract is

awarded to him. He shall also arrange to get water supply connection from

the local body and lay all distribution pipe lines, cocks, water meters etc. for

water required for Road works / construction and drinking purposes

and shall construct masonry tanks of sufficient capacities and at suitable

places as directed for storage of water. All charges on this account and

all bills for use of water as and when received shall be paid by the

contractor promptly. If the local body refuses to supply water for some

reasons or the other, the contractor shall make his own arrangements to get

water from wells belonging to private owners or from some other sources and

convey the same on site by suitable means and bear all expenses for use

and conveyance of the same after entering into an agreement with the owner.

Page 30: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

30

Contractor No. of corrections Executive Engineer

f) Similarly the contractor will have to make his own arrangements at his cost

for supply of electricity to the camp and work site as may be

necessary and he will not be entitled to any extra payment whatsoever in this

regard. 6. Contractor Not To Dispose Off Soil etc.: The contractor shall not sell or otherwise dispose off or remove except for the

purpose of this contract, sand, stone, clay, ballast, earth, rock or other

substance or materials which may be obtained from the excavation made for

the purpose of this contract or any produce from the site. All such

substance materials and produces shall be the property of the Government and

shall be disposed off in a manner and at a place shown in the

drawings or as and where the Engineer-in-charge may direct. 7. Gold/Silver, Minerals, Oils, Relics etc. found on the site:

All gold, silver; oil or other minerals of any description and all precious

stones, coins, treasures, relics, antiquities and similar things which shall be

found in or upon the site, shall be the property of the Government and the

Contractor shall duly preserve the same to the satisfaction of the

Engineer-in-charge and shall, from time to time, deliver the same to such

person or persons as the Engineer-in-charge may appoint. 8. Access to site and work and co-operation with other contractors:

The Engineer-in-charge may, if he considers fit, from time to time, enter on

any lands which may be in the possession of the contractor under the

contract for the purpose of executing any works not included in the

contract and may execute such works not included in the contract by

agents or by other contractors at his option and the contractor shall, in

accordance with the requirements of Engineer-in-charge, afford all

reasonable facilities for execution of the works, including occupation of

lands by structures or otherwise to any other contractor employed by the

Government and his workmen or to the workman of the Government who may

be employed in the execution on or near the site of work not included

in the contract of any contractor in connection with or specially to the

works and in default, the contractor shall be liable to the Government

to be entitled to claim relief from the obligation to execute the works. The

contractor shall also co-operate with other contractors with all fairness and

mutual understanding and use the common facilities like access road to

quarries, water supply arrangements, etc.

The contractor shall not cause, advertently or inadvertently, any

obstruction or impediments in the progress of the other works being

executed by the Government or through other agencies. In the event of

dispute regarding the claim, the responsibility, liabilities, etc., in respect of

such facilities, the decision of the Engineer-in-charge shall be final.

Page 31: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

31

Contractor No. of corrections Executive Engineer

9. Cleaning Up:

a) The contractor shall, at all times, keep the construction areas and his

colony and storage free from accumulation of waste or rejected materials. b) Prior to the completion of the work, the contractor shall remove all

rubbish from and around the premises and all tools, scaffolding

equipment and materials which are not part of permanent structures,

except otherwise asked for or as provided under any other clause of this

contract, the premises will be left in a manner fully satisfactory to the

Engineer-in-charge. 10. Layout of construction road:

The contractor shall have to submit detailed plan to the Engineer-in-

charge showing the layout of the work site, roads and approach roads

proposed by him, before he starts the actual work. Such a road layout plan will

be scrutinized by the Engineer-in-charge and any modifications suggested by

him will be binding on the contractor. If it is decided by the Engineer-in-

charge to have some of the roads proposed by the contractor as common

roads for common use of Government and other contractors or convenient

and for compact and planned layout of work site, the contractor will be

bound to construct them and allow them to be used simultaneously by other

contractors and departments. In case of disputes, the decision of the

Engineer-in-charge shall be final and binding on the contractor. 11. Period and Hours of work :

Due to daily phenomenon of high tide and low tide, continuous period of

8 hours may not be available for working. The contractor is supposed to

plan his works accordingly. No claim in this regard shall be entertained. 12. Signing field Books, Longitudinal Sections, Cross Sections and

Measurement Books : Before starting the work, and at the end before the work is covered, levels for

plotting the longitudinal section (along the axis as decided by the

Engineer-in-charge or his authorized representative) and cross sections of the

portion of the work shall be taken by the Engineer-in-charge or his duly

authorized representative in the presence of the contractor or his authorized

representative who shall have to sign the field books and plan showing the

L-section and cross sections for the portion of the work in token of

acceptance. If the contractor fails to sign them, the levels recorded by

the Engineer-in-charge or his representative in the authorized books shall be

final and binding on the contractor. For this purpose suitable date or

dates shall be fixed by the Engineer-in-charge and intimated to the

contractor at least three days in advance. If the contractor or his duly

Page 32: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

32

Contractor No. of corrections Executive Engineer

authorized agent fails to attend on the appointed date or dates, the levels shall

be taken in his absence and such levels and longitudinal sections and cross

sections based thereon shall be final and binding on the contractor. The

levels will be taken on such alignment and cross sections as will be useful for

reference permanently and described under specifications for “Excavation”.

The point of location for the level will depend upon the roughness of the

area and will also be at least in conformity with the requirements of

specifications for “Excavation” as far as possible.

Where, for proper measurement of the work, it is necessary to have initial set

of levels or other measurements taken, the same as recorded in the

authorized field book or measurement book of Government by the

Engineer-in-charge or his authorized representative and will be signed by the

contractor or his authorized representative who will be entitled to have a true

copy of the same made at his cost. Any failure on the part of the contractor

to get such levels etc. recorded before starting the work, will render him

liable to accept the decision of the Engineer-in-charge as to the basis of

taking measurements. Likewise, the contractor will not cover any work

which will render its subsequent measurements difficult or impossible

without first getting the same jointly measured by himself and the authorized

representative of the Engineer-in-charge. The record of such measurements

on the Government side will be signed by the contractor and he will be

entitled to have a true copy of the same made at his cost. Whenever there is

change in strata during actual execution in respect of item of Schedule

„B‟, it will be the responsibility of the contractor to intimate this

immediately to the department and get the levels at the change of strata

finalized before doing the further work.

13. Programme of construction:

Work and Progress Schedules :

The construction programme is given in Appendix II based on which the

physical programme is prepared. If the tenderer does not agree with this

programme, he shall submit his own programme without changing total period

of tender along with the Tender documents inclusive of the physical

programme as stated above, subject to the provisions that 50% of the work is

completed within 50% of the contract period.

In case, it is subsequently found necessary to alter this programme agreed to in

the contract document, including the change in the sequence of the items, the

contractor shall submit in good time a revised programme incorporating

necessary modifications proposed and get the same approved from the

Engineer-in-charge.

Additional detailed programme for each working season, beginning from

October showing the progress to be achieved month by month for controlling

items shall also be submitted to the Engineer-in-charge not later than the 31st

Page 33: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

33

Contractor No. of corrections Executive Engineer

August preceding the working season and get approved. The Engineer-in-

charge is further empowered to ask for more detailed programme, say week by

week, for any items of special importance and the Contractor shall supply the

same as and when asked for without delay.

The submission of the works programme and approval to it by the Engineer-in-

charge shall not relieve the contractor of any of his duties or responsibilities

under the contract, like timely completion, the damages due to flood or high

tide or any other natural calamities etc. The contractor shall not be entitled for

any claims for any damages caused due to particular works programme. It is

the entire responsibility of the contractor to frame the programme after

anticipating the rains, flood, tidal behavior etc. Actual work turned out shall be

mainly taken into account and not just total of the various payments made to

the contractor.

14. Materials :-

Cement

The Cement shall conform to I.S.8112 of 10989 and subsequent revisions of

Portland Cement or I.S .455-1989 in respect of Portland Slag cement.

All cement required for the work under this contract shall be procured in

advance by the contractor in polythene bags of twenty to a metric tonne as

received from the cement factories or from authorized dealers. Following

factories have been approved for this purpose.

a) Ordinary Portland Cement-

1) ACC Ltd. 2) ULTRATECH 3) CCI 4) Narmada

b) Port land slag Cement: Indorama Cement Ltd.

The Contractor shall produce proof of purchase of cement from Authorised

dealer.

The Purchase bill supported by delivery challan shall constitute adequate proof

of purchase.

Cement shall be stored in such way as to allow the removal and use of cement

in the chronological order of receipt i.e. first received being first used.

Cement shall be kept in store under double locking arrangement (one lock to be

operated by contractor and second lock to be operated by the authorized person

of the Engineer-in-charge, so that it can be taken out or fresh stock admitted

with the knowledge of supervising staff of the division. The watch and ward of

the cement stores shall be the responsibility of the contractor.

The cement purchased from authorized dealer must be tested from Government

Page 34: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

34

Contractor No. of corrections Executive Engineer

laboratory and test report must be submitted to the Engineer- in-charge before

commencement of work.

If godown facilities are available with the department, the same will have to be

utilized by the contractor as per the terms and conditions as decided by the

Engineer-in-charge.

In the event of cement in branded bags remaining surplus due to authorized

reduction in quantity of work certified by the Engineer-in-charge and as

noticed after the issue of completion certificate, the contractor may choose

either of the following two activities.

1. To transfer the cement in branded bags with prior written permission from

the Engineer-in-charge to any of the contract work with the department

and account for the same therein.

2. To sell the cement in branded bags with prior written permission from the

Engineer-in-charge to any of the contractors carrying out the works on contract

with the department at a price to be negotiated by both the contractors

and account for the same.

Steel:

The contractor shall procure steel from the market. The contractor shall make

necessary arrangement at his own cost for sample from the available stock and

shall conform to the specifications laid down by the Bureau of Indian

Standards vide their specification Nos. I.S.432 (Part I) of 1966, 1139-1166,

1786-1979)

The contractor should store the steel of 60 days requirement at least one month

in advance.

The contractor will have to construct sheds for storing steel, having capacity

not less than the quantity of steel required for 90 days use at work site. The

Engineer-in-charge or his representative shall have access to such stores at all

times.

The contractors shall further, at all times, satisfy the Engineer-in-charge on

demand, by production of records and books or by submission of returns and

other proofs as directed that the steel is being used as tested and approved by

the Engineer-in-charge for the purpose and the contractor shall, at all times,

keep his records up-to-date to enable the Engineer-in-charge to apply checks,

as he may desire.

Contractor shall procure the steel from main producer such as SAIL, TISCO,

and ISCO. Re-rolled steel will not be acceptable. He should bring the test

certificate of steel procured by him from the manufacturer.

Page 35: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

35

Contractor No. of corrections Executive Engineer

Steel samples required for testing shall be supplied by the contractor free of

cost. However the testing charge will be borne by the contractor.

15. Stone

Lead for stone:

The contractor is advised to visit various stone quarries opened out in the

nearby vicinity for the various works and ascertain the levels and areas in

which stone of good and acceptable quality is likely to be available. It is for

contractor to investigate the quarries which will yield stone in sufficient

quantities and of required quality. However, if a quarry location approved by

the Engineer-in-charge does not yield adequate and suitable stone, no claims in

that case will be entertained. Other quarry location will have to be established

by the contractor at his own cost and risk. The stone from quarries should be

got approved from the department for its quality before using it on work. The

contractor shall have to make arrangements at his own cost for construction

and maintenance of all roads leading to and from stone quarries to the work

site, as required by him. The locations of quarries have to be such that they do

not affect permanent structures as well as should not be near existing or

proposed habitation. The locations and sizes of quarries shall be subject to

approval of the Engineer-in-charge. However, if a quarry location, approved by

the Engineer-in-charge, on its opening does not yield adequate and/or suitable

stones, no claim can be raised against the department. In that case other

quarries will have to be established by the contractor at his own cost and risk

and the stone got approved from the department for its quality before using it in

the work.

If the stone quarries arc located in the lands acquired by the department, the

contractor would be allowed to quarry the rubble from these areas. If the

quarries are located in private properties, the contractor has to make his own

arrangement to the legal rights and attend to payment etc to the concerned

parties for operation of these quarries at his cost and risk. Similarly he shall

make arrangement for roads leading to and from the stone quarries to work site

at his own cost, with the permission of the Engineer-in-charge.

In the stone quarries at critical excavation weak rocks like volcanic breccia etc.

are likely to be met with. Such weak rocks will be rejected and not allowed for

use in the masonry or pitching. The quarrying will have to be adjusted to avoid

these and other types of weak rocks.

16. Sand

The contractor shall have to make all arrangements for procurement of sand of

approved quality and the same should be got approved from the Engineer-in-

charge, before it is used on the work. However, if quarry location approved by

the Engineer-in-charge does not yield adequate suitable sand, no claims can be

Page 36: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

36

Contractor No. of corrections Executive Engineer

raised against the Department. In that case other quarry locations will have to

be established by the contractor at his own cost and risk. The sand from such

quarries should be got approved from the department for its quality before

using it on work.

The contractor shall have to make arrangements at his own cost for

construction and maintenance of all roads leadings to and from sand quarries to

the work site as required by him with the permission of Engineer-in-charge.

17. Petrol, Oil and Other Lubricants:

The contractor shall have to make his own arrangement for procurement of

Petrol, Diesel, Oil and Other Lubricants.

18. Supply of materials other than those shown in Schedule „A‟ of the tender:

Government will extend, if possible, necessary assistance in recommending

Contractor‟s genuine demand for materials other than those specified in

Schedule „A‟. The contractor may, if required and approved by the Engineer-

in-charge, obtain from the Government stores such materials as may be

available and would be spared at departmental issue rate of the Division as per

rules in force, by the Engineer-in-charge. The department will however, not

hear responsibility to accept any claim in this respect.

19. Quarries:

19.1 It is for the contractor to investigate quarries which would yield stone and

other material such as sand, surkhi, murrum, soil, etc, and satisfy himself of the

availability in desired quantities and quality.

19.2 The tenderers should, in particular, see and verify the quarry sites and satisfy

themselves about the quality and quantities of the material available as the rates

quoted will be inclusive of all leads and lifts involved in bringing the materials

at site.

1 9.3 While working out the rate of embankment items from borrow area (both for

casing and hearting) the presence of boulders of size more than 0.01 cum in the

borrow area has not been contemplated. However, during the actual operation

of the borrow area, if it is noticed that the borrow areas contain boulders of size

more than 0.1 cum, then the extra efforts required to operate these borrow areas

in strata containing boulders of more than 0.1 cum size, will be considered

at stipulated hereafter.

19.4 In case, it becomes evident from the detailed record which the contractor shall

keep from time to time as directed by the Engineer-in-charge and get it

certified from the Engineer-in-charge, that the borrow areas contain boulders of

size more than 0.1 cum, the contractor may claim for the extra efforts taken for

Page 37: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

37

Contractor No. of corrections Executive Engineer

quarrying in the borrow area in strata containing boulders of size more than 0.1

cum. However the claim will be considered only if all the boulders of size more

than 0.1 cum met with in the borrow area quarry excavation, are neatly stacked

and for which measurements shall be taken and recorded in the measurement

book and quantity arrived at after deduction of 50% of the stacked quantity for

voids, will be considered for the purpose of this claim and dealt with as an

extra item.

The claim for extra efforts will be considered for the stacked quantity less

voids at 50% of contract rate (including escalation as per formula in contract)

of this items of excavation in hard rock applicable for the relevant year of

execution, whichever is lower, subject to the provision that the actual payment

will be made only after the completion of the embankment work under the item

embankment from borrow area in the working season. If shall be the entire

responsibility of the contractor to maintain full data from time to time,

preferably every month, about the boulders (more than 0.1 cum size) stacked

and get it certified from the Engineer-in-charge, without which no claim shall

become tenable and will therefore not be considered.

19.5 He shall supply free of cost necessary quantities of sand, stone and aggregate to

Government for carrying out test as desired by the Engineer- in-charge and

well in advance of the construction operation so as to get approved the quality

of the materials. The cost of opening quarries and operating them shall be

borne by the contractor.

20 Laboratory for Testing Work:

Whenever the testing of materials, concrete mixes, mortar and also foundations

of completed works are required as per the detailed specifications or otherwise

required by the Engineer-in-charge at contractor‟s cost and the results given by

this laboratory shall be considered correct and authentic.

The materials, mixes and any other arrangements, including labourers shall be

supplied by the contractor to the department free of cost. The samples for

testing shall be taken in the presence of the Engineer-in- charge or his

representative present on site.

The contractor or his authorized representative shall have a free access in these

laboratories to get himself satisfied about procedures of testing, etc., even if the

contractor or his representative fails to remain present while collecting samples

or testing, the results will be considered as authentic and binding on the

contractor.

21. Royalties: The royalty charges are as per Govt. G.R. & will be recovered from

the bill as per recovery statement

21.1 On receipt of applications, the competent authorities would work out the

Royalty fees on the entire quantity and the period as certified and issue

necessary permit to the contractor for the quantity and the period as certified by

Page 38: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

38

Contractor No. of corrections Executive Engineer

the Executive Engineer on the contractor paying the security deposit equal to

10 % of the royalty charges or Rs.5000/- whichever is more, if the quarry

process is likely to extend over a period beyond six months. In other cases

security deposit should he 20 % of the royalty charges leviable on the quantity

to be removed. If such security deposit is less than Rs. 5000/- the contractor

shall pay it in cash or furnish to the competent authority a bank guarantee for

the requisite sum of security deposit. Any type of royalty charges will not be

reimbursed by the department. All quarry fees, royalties, octroi, dues and

ground rent for stacking materials, if any, shall be paid by the contractor, which

will not be reimbursed by the department.

21.2 The contractor should furnish by 10‟ of every month the certificate in respect

of the material removed during the preceding month obtained from Executive

Engineer concerned showing quantities of different material used by the

Contractor for particular Government work to the Collector, or other competent

authority and on the Contractor failing to do so the amount of royalty as may

become due from the contractor on use of such material during the preceding

month for the quantity as certified by the Executive Engineer shall be deducted

from the next ensuing payments and in absence of possibility of any such

payment due to the contractor within the month under consideration, it shall be

open for the Collector or the competent authority to stop further quarrying for

which the contractor will be solely responsible for stoppage of work in such

circumstances. In case where quarry process is likely to extend beyond the

period of six months, it will suffice if quantity certificates are sent by the

Contractor.

21.3 In case of quarries in private lands, it will be for the Contractor at his cost to

arrange for quarrying of the materials on the payment of whatever charges

as may be due to the owner.

22. Bills and Payments:

22.1 Two running payments in a month are permitted. First bill shall be

submitted by the contractor by 10‟th day of the month. Payment of this bill

shall be effected as stated in clause 10 of B-1 form. Second bill if

necessary shall be submitted by the contractor by the 25‟th day. Payment

thereof shall be effected as stated above. Non-submission of the bills on the

scheduled dates shall not absolve the department from the liability to make

payment.

22.2 The format of running bill on which the bills are to be submitted by the

contractor will be supplied to the contractor by the department. Printed copies

of the bill forms as per this format shall be arranged by the contractor at his

cost. The bills in five copies shall be submitted to the concerned Sub Divisional

Engineer, in the standard proforma only.

Page 39: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

39

Contractor No. of corrections Executive Engineer

22.3 The final bill shall be submitted within one month of the date of issue of

completion certificate. The final bill shall be paid within six months of initial

submission.

22.4 Secured advance, against the cost of the materials brought on site by the

Contractor, limited to 75% of the cost of such materials, duly certified by the

Engineer‟s representative as received on site shall be paid to the Contractor on

submission of „Indenture for Secured Advances‟ in the format given at

Appendix „G‟. The secured advance thus paid to the Contractor will be

recovered against completion of the respective items for which the materials

were brought on site.

23 Security Deposit:

No interest will be payable on the security deposit by the department.

24 No interest on money due to the contractor:

No commission by the Engineer to pay the amount due upon measurement or

otherwise shall vitiate or make void the contract nor shall the contractor be

entitled to interest on any guarantee bond or payment in arrears nor on any

balance may on the final settlement of his account be found due to him.

25 Other Contractor for the work:

Department has the right to split up the project work detailed in the work and

site conditions into distinct items and this contract shall apply only to those

items which shall have been specified in this contract. Should the department

enter into other contractors for specified items of the Project work, each

contractor shall co-operate with others to the fullest extent and shall allow

others every facility and cooperation for execution of their works

simultaneously and satisfactorily, as intended in the designs, specifications and

drawings. Should there be a dispute or disagreement between the contractors

for any cause whatsoever, the same shall be referred to the Engineer-in-charge

whose decision regarding the coordination, cooperation and facilities to be

provided by any of the contractors to others shall be final and binding on all

parties and such a decision or decisions shall not vitiate any contract nor

absolve the contractor of his responsibilities under the contract nor form the

grounds for any claim of compensation.

26 Contract documents and matters to be treated as confidential:

All documents, correspondence, decisions and other matters concerning the

contract shall be considered as of confidential and restricted nature. The

contractor shall not divulge or allow access thereto for any unauthorized

person.

Page 40: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

40

Contractor No. of corrections Executive Engineer

27 Access to the Contractor‟s Books:

Whenever it is considered necessary by the Engineer-in-charge to ascertain the

actual cost of execution of any particular item of work or supply of plant or

material, he shall direct the contractor to produce the relevant documents, such

as pay-rolls, records of personnel, invoices of materials and all other data and

documents relevant to the item or necessary to determine its cost, etc. and the

contractor shall, when so required furnish information, pertaining to the

aforesaid items in the mode and manner that may be specified.

28 Breach on part of Government not to Annul Contract:

No breach or non-observance on the part of Government of any of the

conditions contained herein shall annul this contract or discharge the contractor

from the observance and performance thereof, but on application to the

Engineer-in-charge, an extension of time may be given to the contractor in

respect of such breach or non-observance by the Government which shall be

governed by clause 6 of B-1 form. The contractor shall not, however, be

entitled to consideration or any extension of time for any item of the work

unless the contractor shall have made an application in writing to the Engineer-

in-charge within one month of the arising of the cause needing such extension,

but the Engineer-in-charge may, at his discretion which shall be conclusive,

waive the condition regarding this period of one month.

29 Local laws:

All local laws in force at the time of entering the contract and those enacted

thereafter shall be binding on the Contractor and he shall abide by the same.

All import and excise duties, sales tax, local panchayat taxes and other taxes

shall be borne by the contractor and they shall be deemed to have been covered

by his quoted tender rates, except that the contractor shall not be liable to any

land tax for the land handed over to him for the operation in connection with

this contract or for his colony or appurtenant works constructed by him for the

purpose of this contract.

The Contractor shall also be liable to all relevant provision of the Indian

Income Tax Act and other Tax laws and labour laws which may be applicable

to him from time to time.

The Contractor shall protect and indemnify Government against all claims or

liabilities arising from or based on the violation of such laws, ordinances,

regulations, and bylaws by him or his employee.

Page 41: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

41

Contractor No. of corrections Executive Engineer

30 Personnel of the contractor:

The Contractor shall, at all times, maintain on the work, as staff of duly

qualified engineers and supervisors of sufficient experience of similar other

jobs, to assure that the quality of work turned out shall be as intended in the

specifications. Contractor shall also maintain at the work a works manager of

sufficient status, experience and office and duly authorize him to deal with all

aspects of the day to day work, all communications to and commitments by this

works manager shall absolutely be binding on the Contractor.

The Contractor shall supply to the Engineer-in-charge the details of names,

qualifications and experience in regards to all the supervisory staff employed

by the contractor and notify changes when made and satisfy the Engineer-in-

charge regarding the quality and sufficiency of the staff thus employed. The

Engineer-in-charge will have the unquestionable right to ask for changes in the

quality and number of Contractor‟s staff. The Contractor shall, on the written

directives of the Engineer-in-charge, remove from the works any person

employed thereon; who may, in the opinion of the Engineer-in-charge, be

incompetent or have misconduct himself, such person shall not be employed

again, on the work without the written permission of the Engineer-in-charge.

The employment of labour on works shall be governed by The Contract

Labour (Regulation and Abolition) Act 1970 and The Maharashtra

Contract labour (Regulation and Abolition) Rules 1971 and amendments

thereof, if any, before start of work.

31 Death, Bankruptcy etc:

If the Contractor shall die or commit any act of bankruptcy or commence

winding up except for reconstruction purpose or carry on his business under

receiver, liquidator or any person whom the contract may become vested, shall

forthwith give notice thereof in writing to the Government and shall for one

month, during which he shall take all reasonable steps to prevent a stoppage of

work, have the option of carrying out this contract subject to his providing such

guarantee as may be required by the Government but not exceeding value of

the work for the time being remaining unexecuted. In the event of stoppage of

works, the period of the option under this clause shall be fourteen days only.

Should the above option be not exercised, the contract may be terminated by

Government by a notice in writing to contractor or his successor. The power

and provisions reserved to Government on this contract, of taking of the work

out of the contractor‟s hand shall immediately become operative. Copy of such

notice shall be posted on worksite and advertised in newspaper.

32 Notices: How to be given:

Where any legal or other notice or any other document or any other direction is

to be given to or served upon the contractor, it shall be deemed to be duly given

or served, if it shall have been either delivered to him personally or to his

Page 42: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

42

Contractor No. of corrections Executive Engineer

recognized agent or Works Manager (including in the case of company, the

secretary of such company) or delivered at or sent through the post, addressed

to the last known place of business, or abode of the Contractor, a notice or

other documents which shall be so given to or served on any one of the partners

in such firms shall be deemed to have been given or served on all of them.

Work Order Book:

The Contractor shall maintain bound work order book at work site as the

Engineer-in-charge may direct. The work order book shall have machine

numbered pages in triplicate. The Contractor shall make them available to the

Engineer-in-charge or his representative whenever called for.

Executive Engineer or his representative may record about works in this book,

leaving the original copy in the book and removing the second and third copy

with him. The contractor or his authorized representative shall also sign this

work order in token of its acceptance.

All orders recorded in this work order book, shall be deemed to have been

served on the contractor. On completion of the work all the work order books

may be handed over to the Executive Engineer.

In the event of refusal of the Contractor‟s representative on the spot to sign the

work order book, Engineer-in-charge shall take necessary further steps in

respect of further communication and control, notification of stoppage of work

as deemed fit at the entire responsibility of the contractor.

33 Passing of Foundation etc.:

After the completion of the work of excavation, the same will be checked and

passed by the Executive Engineer. No masonry or concrete or backfilling shall

be laid unless the foundation is so passed. No concreting shall commence

unless the centering and the reinforcement is checked and passed by the

Engineer-in-charge.

34 Reference to Standard Specifications:

The specifications of the work as enclosed with this contract documents are

drawn with a specific reference to site conditions and do not everywhere

include the detail of the standard tests and procedures which are already laid

down and available in the current Indian Standard Specifications. Wherever

such details are not specified in this contract, the provision under current Indian

Standard Specifications and/or the Standard Specification (1970) of the

Government of Maharashtra shall be deemed to be applicable.

Page 43: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

43

Contractor No. of corrections Executive Engineer

35 Communications and Notices by Contractors:

All communications and/or notices pertaining to works and concerning matters,

such as passing and approving of foundations, reinforcement and form work,

measurements, mark-outs, etc. shall not be addressed by the Contractor to an

officer below the rank of Sub-Divisional Officer. All such notices,

communications, etc. shall be addressed in good time so as not to hold up the

work.

36 Non-compliance of Contract Conditions:

If the contractor shall neglect or fail to proceed with the works, with due

diligence or he violates any of the provisions of the contract, the Engineer-in-

charge may give notice to the contractor, identifying the deficiencies in

performance and demanding corrective action. The Engineer-in-charge, shall

also clearly state in the notice the nature of action that shall be taken if the

contractor fails to fulfill by necessary corrective action.

Depending on nature of default the Engineer-in-charge at his discretion, shall

have two options, regarding the action to be taken in case of‟ default by

contractor. He shall withhold any of the payments due to the contractor or shall

terminate the contract in whole or in part. But the Engineer-in-charge shall

clearly mention in his notice, the action that shall be taken if the contractor fails

to take the corrective action. The period of 14 days shall be given to the

contractor to take such corrective action after the issue of such notice.

No claim for compensation of any sort, from contractor will be entertained for

withholding the bills indefinitely till the specified requirements are complied

with by the contractor.

After the issue of the notice about default by the contractor, the contractor shall

not remove from the site any plant, equipment and materials. The Government

shall have a lien on all such plants, equipments and materials from the date of

such notice till deficiencies have been corrected.

37 Extra Items:

Extra items of work shall not vitiate the contract. The Contractor shall be

bound to execute extra items of work as directed by the Engineer-in- charge.

The rate for extra items will be governed by the provisions of clause 14 and 30

of „Conditions of Contract.‟

38.0 Price Variation Clause:

If during the operative period of the Contract as defined in condition (i)

below, there shall be any variation, in the Consumer Price Index (New

Series) for Industrial Workers for Mumbai Centre as per the Labour

Gazette published by the Commissioner of Labour, Government of

Maharashtra and/or in the whole-sale Price Index for all commodities

Page 44: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

44

Contractor No. of corrections Executive Engineer

prepared by the Office of Economic Adviser, Ministry of Industry,

Government of India, or in the price of petrol/oil and lubricants and major

construction materials like bitumen, cement, steel, various types of metal

pipes etc., then subject to the other conditions mentioned below, price

adjustment on account of

(1) Labour Component

(2) Material Component

(3) Petrol, Oil and Lubricants Component

(4) Bitumen Component

(5) HYSD & Mild Steel Component

(6) Cement Component

(7) C.I. and D.I. Pipes Component

Calculated as per the formula hereinafter appearing, shall be made. Apart

from these, no other adjustments shall be made to the contract price for any

reasons whatsoever. Component percentage as given below are as of the

total cost of work put to tender. Total of labour, Material & POL

components shall be 100 and other components shall be as per

actual.

1 Labour Component – K1 41.64 %

2 Material Component – K2 54.69 %

3 POL Component – K3 3.67 %

4 Bitumen Component 0

5 HYSD & Mid Steel Component Actual

6 Cement Component Actual

7 C.I. and D.I. Pipe Component -

Note: If Cement, Steel, Bitumen, C.I & D.I. Pipes are supplied on

Schedule „A‟, then respective component shall not be considered. Also if

particular component is not relevant same shall be deleted.

1 Formula for Labour Component:

V1 = 0.85 P K1 x L1 – L0

100 L0

Where ,

V1= Amount of price variation in Rupees to be allowed for Labour component

P= Cost of work done during the quarter under consideration minus

The cost of Cement, HYSD and Mild Steel, bitumen, C.I. & D.I. Pipes

calculated at the basic star rates as applicable for the tender, consumed

during the quarter under consideration.

(These star rates shall be specified here)

Page 45: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

45

Contractor No. of corrections Executive Engineer

Here, Star Rates for-

1) Cement = Rs. 6,500 /- MT

2) Steel = Rs. 48,800 /- MT

K1= Percentage of Labour Component as indicated above.

LO= Basic Consumer Price Index for Mumbai Centre shall be average

consumer price index for the quarter preceding the month in which the last date prescribed for receipt of tender, falls.

L1= Average Consumer Price Index for Mumbai Centre for the quarter under

consideration.

2 Formula for Materials Component:

V2 = 0.85 P K2 x M1 – M0

100 M0

Where

V2= Amount of price variation in Rupees to be allowed for Materials

component.

P= Same as worked out for labour component.

K2= Percentage of Material Component as indicated above.

MO= Basic wholesale Price Index shall be average wholesale price index for

the quarter preceding the month in which to the last date prescribed for

receipt tender, falls.

M1= Average Wholesale Price Index during the quarter under consideration.

3 Formula for Petrol, Oil and Lubricant Component

V3 = 0.85 P K3 x P1 – P0

100 P0

Where,

V3= Amount of price variation in Rupees to be allowed for POL component.

P= Same as worked out for labour component K3= Percentage of Petrol, Oil and Lubricant Component. P0= Average Price of HSD at Mumbai Centre during the quarter preceding the

month in which the last date prescribed for receipt of tender, falls. P1= Average Price of HSD at Mumbai Centre during the quarter under

consideration.

Page 46: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

46

Contractor No. of corrections Executive Engineer

4 Formula for Bitumen Component

V4 = QB (B1 – B0)

where

V4= Amount of price variation in Rupees to be allowed for Bitumen

component.

QB= Quantity of Bitumen (Grade..) in metric tones used in the permanent

works and approved enabling works during the quarter

under consideration.

B1= Current, average ex-refinery price per metric tonne of Bitumen (Grade..)

under consideration including taxes (octroi, excise, sales tax) during the quarter under consideration.

B0= Basic rate of Bitumen in rupees per metric tonne as considered for

working out value of P or average ex-refinery price in rupees per metric

ton including taxes (octroi, excise, sales tax) of Bitumen for the grade of bitumen under consideration prevailing quarter preceding the month in

which the last date prescribed for receipt of tender, falls, whichever is higher.

5 Formula for HYSD and Mild Steel Component

V5 = S0 (SI1 - SI0) x

T SI0

Where, Amount of price variation in Rupees to be allowed for HYSD/Mild Steel

component.

Basic rate of HYSD/Mild Steel in rupees per metric tonne as considered for

working out value of P

Average Steel Index as per RBI Bulletin during the quarter under

consideration.

Where

V5= Amount of price variation in Rupees to be allowed for HYSD/Mild Steel

component

S0= Basic rate of HYSD/Mild Steel in rupees per metric tonne as considered

for working out value of P

SI1= Average Steel Index as per RBI Bulletin during the quarter under

consideration

SIO= Average of Steel Index as per RBI Bulletin for the quarter preceding the

month in which to the last date prescribed for receipt of tender, falls.

Page 47: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

47

Contractor No. of corrections Executive Engineer

T= Tonnage of steel used in the permanent works for the quarter under

consideration.

6 Formula for Cement Component V6 = C0 (CI1 - CI0) x T

CI0

Where

V6= Amount of price in Rupees to be allowed for cement component

Co= Basic rate of cement in rupees per metric ton as considered for working

out value of P.

Average cement Index published in the RBI Bulletin for the quarter under

consideration. Average of cement Index published in the RBI Bulletin for the

quarter preceding the month in which to the last date prescribed for receipt of

tender, falls. Tonnage of cement used in the permanent works for the quarter

under consideration.

Formula for C.I./D.I. Pipe Component

V7 = Qd (D1 – D0 )

Where

V7 = Amount of price escalation in Rupees to be allowed for C.I./D.I.

Pipe Component.

D0 = Pig Iron Basic price in rupees per tone as considered for

working out value of P.

D1 = Average Pig Iron price in rupees per tone during the quarter under

consideration.(Published by HSCO)

Qd = Tonnage of C.I./D.I. Pipe used in the works during the quarter

under consideration V5 = [ S0x((SI1 – SI0 )/SI0)xT ]

Where,

V5 = Amount of price variation in Rupees to be allowed for HYSD/Mild

Steel Component.

S0 = Basic rate of HYSD/Mild Steel in rupees per metric tone as

considered for working out value of P.

SI1 = Average steel Index as per RBI Bulletin during the quarter under

consideration.

SI0 = Average of steel Index as per RBI Bulletin for the quarter

preceding the month in which to the last date prescribed for receipt

of tender , falls.

T = Tonnage of steel used in the permanent works for the quarter under

consideration.

Page 48: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

48

Contractor No. of corrections Executive Engineer

Where

Amount of price escalation in Rupees to be allowed for C.I./D.I.Pipe

component Pig Iron basic price in rupees per tonne as considered for

working out value of P Average Pig Iron price in rupees per tonne during

the quarter under consideration (published by HSCO) Tonnage of C.I./D.I.

Pipe used in the works during the quarter under consideration.

39.0 Liability for accidents to persons:

It shall be contractor‟s responsibility to protect against accidents on the work

site. He shall indemnify the government against any claims for damage to the

property, injury to workers or any other persons, deaths etc. On the occurrence

of accident resulting in death or which is so serious as to be likely to result in

death, the contractor shall within 24 hours report in writing to the Engineer-in-

charge, the fact stating clearly about the circumstances in which accident has

occurred and the subsequent action taken. Other minor accidents causing minor

injuries and loss to property should be communicated in writing, promptly to

the Engineer-in-charge. In all cases contractor shall indemnify the Government

against all losses or damage resulting directly or indirectly from the

contractor‟s failure to report in the manner aforesaid or otherwise arising from

such occurrences. This includes penalties or fines, if any, payable by the

Government as a consequence of failure to give notice under the Workmen‟s

Compensation Act or failure to the provisions of the said Act in regard to such

accidents.

In the event of accidents in respect of which compensation may become

payable under Workmen‟s Compensation Act -1923 including all subsequent

modifications thereof, the Engineer-in-charge, may retain the sums of money

as may, in the opinion of the Engineer-in-charge, be sufficient to meet such

liability out of the amounts payable to the contractor. These sums shall be

recovered from the immediate payment due to the contractor in one installment

or in more than one installment the decision of the Engineer-in-charge

regarding this shall be final and binding on the contractor. On receipt of award

from the Labour Commissioner, the balance amount shall be reimbursed to or

recovered from the contractor. It should he noted that though the Government

is the Principal employer, the complete responsibility of compensation shall be

on the contractor.

40.0 The Contractor to supply and be responsible for the sufficiency of the

means employed:

The Contractor shall supply and take upon himself the entire responsibility of

the sufficiency of the scaffolding, machinery, time bearing tools, implements

and generally of all the means irrespective of whether such means may or may

not have been approved or recommended by the Engineer-in-charge and the

Page 49: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

49

Contractor No. of corrections Executive Engineer

contractor must accept and discharge all risks of accidents or damages from

whatever cause they may arise, until the completion this contract.

41. Covering of work:

The Contractor shall give not less than seven days notice in writing to the

Engineer-in-charge of the work which is proposed to be covered up or placed

beyond the reach of measurements so that measurements may be taken before

the work is covered up or placed beyond the reach of measurements. No work

shall be covered up or placed beyond the reach of measurements, before that

the measurements of work to be covered up are recorded.

42. Excavated material:

All the materials available from excavation will be the property of the

Government and shall be disposed off only as directed by the Engineer- in-

charge. The materials of approved quality available from the excavation

including that carried out by the Government may be used by the contractor in

the items of works included in Schedule „B‟ or for ancillary or preparatory

work, free of cost. The Prior approval of the Engineer-in-charge for such use

shall, however, be taken. The Contractor shall make proper arrangements for

sorting out and stacking material of approved quality that he proposes to use as

aforesaid. Government will be free to make use of other materials not required

or not likely to be required for use by the contractor as will be determined by

the Engineer-in-charge.

The excavated material not used by the contractor as above or stacked for his

use, but remaining unused material at site after completion of works shall be

disposed off by the contractor at his own cost in a manner and at places shown

in the drawings or as and where the Engineer-in-charge may direct.

The contractor should utilize the material available from excavated stuff for

backfilling.

43. Safety measures:

The contractor shall arrange for the safety in his operations as required

including the provisions in the safety manual published by the Central Water

Power commission, New Delhi (Jan 1962 Ed.) In case the contractor fails to

make such arrangements, the Engineer-in-charge shall be entitled to cause them

to be provided and recover the cost thereof from the contractor. The following

are some of the measures listed but the same are not exhaustive and the

contractor shall add to and suggest improvement to these precautions on his

own where necessary and should comply with the directions issued by the

Engineer-in-charge in this behalf from time to time and at all times.

Page 50: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

50

Contractor No. of corrections Executive Engineer

Providing protective head guard to workers in the works like deep excavation

to protect them against fall of overburden materials.

Getting the workers in such job periodically examined for chest trouble due to

too much breathing in line dust.

Taking such normal precautions like fencing and lighting to excavations or

trenches, not allowing, nails or metal parts or useless timber spread around,

marking danger area for blasting, whistles etc.

Providing sufficient suitable and safe accesses to all work spots including

ladders, gangways, platforms, etc. avoiding naked wires etc. such would

electrocute the workers.

Taking necessary steps towards training the workers concerned on the use of

machinery before they are allowed to handle them independently and taking all

necessary precautions in and around areas where machines, hoists and similar

units are working.

44. Maintenance:

After the works are completed in all respects in accordance with the contract

conditions, a completion certificate will be issued by the Engineer-in-charge.

From the date of issue of the completion certificate, till the expiry of 12

calendar months the contractor shall be liable for replacement of any part of

plant or work found to be defective from the causes arising from faulty

materials or workmanship or other causes, for which, in the judgment of the

Engineer-in-charge, the contractor is responsible and for making good any

damage arising there from.

45. Sundays and Holidays:

No work shall be done on weekly local holidays or on other government

holidays duly gazettes or on holidays observed by local usage without the prior

sanction of the Engineer-in-charge. Withholding of such sanction shall not

form any grounds for compensation or extension of time limit.

If on the other hand, the Engineer-in-charge directs that the work shall be

proceeded with on days and during hours otherwise not permissible under this

contract; the Contractor shall proceed with works as directed, without in any

way violating this contract or forming any grounds for compensation or claim.

The Contractor shall, in his dealing with labour at all times during the period of

this contract, have due regard to local festival, religious and other customs and

all relevant laws.

Page 51: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

51

Contractor No. of corrections Executive Engineer

46. Bank Guarantee:

Bank Guarantee shall be given on the stamp of Rs.100/- in the form prescribed

by the Government. The bank guarantee shall be valid for the entire period of

contract, including defect liability period. It will be the responsibility of (the

contractor to get validity of bank Guarantee extended at least one month prior

to expiry date from time to time, failing which the Bank Guarantee shall be

encashed well before the expiry date of bank guarantee and cash accrued will

be at the disposal of‟ the Government without interest.

47. Handing over of work:

All the work and materials, before finally taken over by Government will be

the entire liability of the contractor for guarding, maintaining and making good

any damages of any magnitude. Interim payments made for such work will not

alter this position. The handing over by the contractor and taking over by the

Executive Engineer or his authorised representative will be always in writing of

which copies will go to the Executive Engineer or his authorized representative

and the contractor, however, understood that before taking over such work,

Government will not put it into regular use as distinct from casual or incidental

one, except as specifically mentioned elsewhere or as mutually agreed to.

48. Removal of Imperfect Work:

If it shall appear, that the work has been executed with unsound, imperfect or

of an inferior quality or otherwise not in accordance with the contract

documents, the contractor shall at his own cost rectify, reform or reconstruct

the same, wherein whole or in part, as may be directed by the Engineer,

whether or not the value of any such work of material shall have been included

in any payment made to the contractor. The decision of the Engineer-in-charge

shall be final and binding on the contractor. The Executive Engineer may, if he

thinks fit, allow such work to be paid at reduced rates and his decision will be

final and binding, provided further that if the rates fixed by the Engineer, are

not acceptable to the contractor, he shall have the option to replace the

defective work or materials with ones in accordance with the specified

standards.

49 Jurisdiction of court for disputes:

Disputes, if any, arising out of this contract shall be subject to the jurisdiction

of the high court of Mumbai.

50. Inspection of works:

The Engineer or his duly authorized representative shall have at all times full

power to inspect the work, whenever in progress either on the site, in the

contractor‟s premises or the work site. Further, contractor shall not without

written authorization, permit entry on site of work of any person except

Page 52: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

52

Contractor No. of corrections Executive Engineer

authorized representative of the Department or the Engineer or the contractor‟s

staff and labour directly engaged on and in connection with the work.

The contractor shall at his cost, provide all necessary facilities for proper

inspection and supervision of the work gangways, platform, scaffolding and

ladders, etc. of suitable dimension and sufficiently strong at appropriate

location and all accesses to passages etc. shall be well lighted and maintained

in good order. The Engineer‟s decision about the sufficiency and adequacy

thereof shall be final.

The Contractor shall, during working hours, maintain supervisor of sufficient

training and experiences to supervise various items and operation of the work

and the said supervisor shall remain present during inspection of the Engineer-

in-charge. All orders and direction given to such Supervisors or other staff of

the contractor shall be deemed to have been given to the contractor directly.

Further the Engineer, by due notice to the contractor, may direct to be present

on any specified inspection and the contractor shall comply with such

directions.

51. Opening outworks:

Should Engineer consider, if necessary, in order to satisfy himself as to the

quality of work, the contractor shall, at any time during the continuance of the

contract, pull down or cut into any part of the work, and make such opening

into and to such an extent through the same as the Engineer may direct and the

contractor shall make good the same at his cost and to the satisfaction of the

Engineer.

52. No Compensation for washed away quantity:

It shall be the responsibility of the contractor to maintain the work during

construction. Any damages due to heavy flood, High tide, Low tide water shall

be set right by the contractor and no claim or compensation for such a work

would be entertained.

53. Dewatering:

During excavation earth work, concreting and masonry the standing and

percolating water shall be dewatered by the contractor. No claim will be

entertained in respect of any dewatering required for the purpose of inspection

by Engineer-in-charge or for any repeated dewatering involved due to lack of

progress at any location for whatsoever reason.

Page 53: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

53

Contractor No. of corrections Executive Engineer

54. Sub-Surface Conditions:

The contractor may study the actual site conditions and must draw his own

conclusion in this respect. The contractor must also acquaint himself with the

regional geology.

The contractor shall bear full responsibility for deductions and conclusions as

to the nature and conditions of the materials to be excavated and the difficulties

of making and maintaining the required excavation and of doing other works

affected by the geology of the site of the work.

55. Work during rains :

Work during heavy rains will not be allowed. However when masonry or

concreting work is required to be done or continued while it is raining, it shall

be seen that the mortar or concrete is not damaged due to rain while it is being

transported and placed. After placing the green Masonry /Concrete shall be

adequately covered for a period of 24 hours when it shall be capable of being

cured by a splash of water. The surface of fresh masonry/concrete should be

maintained at slope sufficient to result with self drainage of rainwater. The

work shall however, be discontinued when the rain is so severe that water

collects in pools or washes the surface to the fresh masonry/concrete and it

shall not be possible to provide adequate shelter.

56. Ancillary works

These works like construction of the temporary accommodations for residential

and non-residential purpose for contractor‟s staff investigation and opening of

store, sand and/or soil quarries etc, water supply, approach road, etc. shall be

constructed to the satisfaction of the Engineer-in-charge. The cost of

construction and maintenance shall he deemed to have been considered in the

cost of the main works.

57. Land for Work.:

No local housing is available and the contractor should arrange for suitable

housing for his staff and labour, offices, etc. at his own Cost within the area of

works as directed by the Executive Engineer. Land for the same to the extent

available will be made available free of charge for temporary use during the

course of execution.

The land used by contractor for his staff and labour colony will have to be

handed over back to the Government within three months after the physical

completion of the work or termination of‟ contract, whichever is earlier, fully

cleared and fairly brought to the original condition. No structure of

Page 54: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

54

Contractor No. of corrections Executive Engineer

construction shall be left on the land at the time of vacating it without the

specific approval of Engineer-in-charge.

The contractor shall preserve all existing vegetation such as trees on or

adjacent to the site which do not interferes with the construction as determined

by the Engineer-in-charge.

All produce from cutting of trees, grass etc. shall be the property of

Government and shall be stacked at the place specified by the Engineer in

charge. No claim shall be made for such cutting and stacking of trees and grass

etc. by the Contractor.

58. Power to inspect materials transported by the Contractor:

The Engineer-in-charge or his authorized representative will have the power to

inspect any lorry carrying material, of the contractor before allowing it to leave

the works area.

59 Preservation of Forest:

The area near about the work site is largely covered with mangroves and is

under the control of Environment and Forest Department. The contractor must

take all precautions and care to see that no unlawful sorts of activity in

connection with work or colonies arc carried out in these areas. The contractor

and his authorized agent and or his labourers shall not perform any act so as to

violate the provisions of the conservation of Forest (Conservation) Act 1980,

passed by Govt. of India or the notification regarding Coastal Regulatory Zone;

1991. Any infringement of the Conservation of Forest (Conservation) Act 1980

or C.R.Z. notification, 1991 by the contractor and/or his authorized agent and

or labourers, will be at the contractor‟s risk and cost.

Any illicit cutting of trees and any such activities which may cause harm to

forest or mangroves are strictly prohibited and the contractor shall be liable for

payment of heavy compensations if any illicit cutting of trees is done or any

fire hazards take place due to negligence or carelessness of the contractor or his

labour and staff during execution of work.

Contractor‟s labour and staff while working on the project in the forest area

shall not cause destruction of the forest area or mangroves for their fuel wood

needs and or other reasons. Breach thereof will attract penal action as deemed

fit by the Engineer-in-charge of the work.

60. Water Supply and Drainage:

The contractor will have to make his own arrangements for requirements of

Page 55: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

55

Contractor No. of corrections Executive Engineer

drainage and water supply for his work and drinking purpose. No claim

whatsoever due to non-availability of water in the nalla shall be entertained.

61. Medical Aid:

Medical Aid for the Contractor‟s men shall be arranged by the contractor at his

own cost. The medical facilities are available at the nearest Taluka place.

62. Roads:

The contractor shall construct and maintain suitable inspection paths in work‟s

limitation. Any approach road to be constructed for the work shall also be

constructed as directed by Engineer-in-charge; the approach road shall be

maintained by the contractor at his own cost. There will, however, be no charge

for any reasonable use of the approach road constructed by the Department.

63. Government treasury and banking:

The Government Treasury and banking facilities exist at the nearest Taluka

place.

64. The contractor shall make his own enquiries regarding the availability of all

materials required for the work except those provided in the Schedule „A‟.

65. Precautions during the floods:

It shall be the responsibility of the contractor to preserve and maintain in safe

condition all materials, machinery and tools from hood and rain and no

compensation whatsoever will be payable to him on account of loss due to

normal floods, rains and any other causes.

66. Embedded items:

Before placing concrete and/or masonry care shall be taken to see that all

embedded items are firmly and securely fastened in place as indicated on the

drawings or as directed. All embedded item shall be cleaned free from all

foreign matter such as scale, dust, oil paint, etc. The embedded parts which are

not included in the schedule shall be supplied by the Government free of

charges delivered firmly near the work site as whole. The contractor shall

however be responsible for correctly embedding the same as directed without

any charge, the cost of such embedding deemed to have been included in the

item of concrete and or masonry as the case may be. No extra payment wills be

made for the installation of this embedment work for delays or for interruptions

arising there from.

Page 56: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

56

Contractor No. of corrections Executive Engineer

67. Working Drawing :

The plans/drawings attached with the tender papers are only typical

plans/ drawings. The working plans/drawing of earthwork and masonry

structures for bund & C.D. work will be supplied at the time of

execution as per site conditions. The claims for any variations in the

quantity will he governed by the clause 38 of B-1 form.

68. Disputes and arbitration:

No arbitration is allowed.

In case of disputes of difference of opinion arising between the Engineer-in-

charge and the contractor, the contractor shall refer the matter to the

Superintending Engineer through the Engineer-in-charge with an advance copy

to the Superintending Engineer.

In case the Superintending Engineer‟s decision is not acceptable, the contractor

shall refer the matter to the Chief Engineer through the Superintending

Engineer with an advance copy to the Chief Engineer.

In case of the Chief Engineer‟s decision is not acceptable and if the matter

otherwise satisfies the conditions laid down for the purpose, the contractor can

refer the matter to the Secretary‟s Committee appointed by Government of

Maharashtra Vide Government Resolution No. CAT/1274/2906-2 dated

16/12/74 through the Chief Engineer. The decision of the Committee will be

final and binding on the contractor.

Notwithstanding anything contained above in so far as the specifications and

technical provisions of contract are concerned the decision of the Chief

Engineer shall be final & binding on the contractor.

69. Relation with Public Authorities:

The contractor shall comply with all rules, regulation bye-laws, direction given

from time to time by any local or public authority in connection with the work

and shall himself pay fees for charges which are leviable on him without any

extra cost to Department.

70. Rates:

The rates specified by the Contractor shall be inclusive of all taxes (viz. S.T.,

General Tax and other taxes) and Contractor should quote the percentage rate

in B-1 Form.

Page 57: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

57

Contractor No. of corrections Executive Engineer

71. Indemnity:

The Contractor shall indemnify the Government against all actions, suits claims

and demands brought or made against him in respect of anything done or

committed to be done by the Contractor in execution of or in connection with

the work of this contract and against any loss or damage to the Government in

consequence of any action or suit being brought against the Contractor for

anything done or committed to be done in the execution of the works of this

contract.

72. Police Protection:

For the special protection of camp and of the Contractor‟s works, the Engineer-

in-charge will help the Contractor as far as possible to arrange for such

protection with the concerned authorities, if so requested by the Contractor in

writing. The full cost of such protections shall be borne by the Contractor.

73. Contractor‟s Liability and Insurance:

73.1 From commencement to completion of work, the Contractor shall take full

responsibility for the care thereof and for taking precaution to prevent loss or

damage and to the greatest extent possible and shall be liable for any damage

or loss that may happen to the works or any part thereof from any cause

whatsoever (save and except the Excepted Risks) and shall at his own cost

repair and make good the same so that at completion, the work shall be in good

order and condition and in conformity in every respect with requirements of the

contract and instructions of the Engineer in charge.

73.2 Without limiting his obligations and responsibility under Claude 23, the

Contractor shall insure in the joint name of the Government and the Contractor

against all loss or damage from whatever cause (other than the Excepted Risks)

for which he is responsible under the terms of the contract and in such a

manner that the Government and the Contractor are covered during the period

of construction of the works and the defects liability period for loss or damage

arising from a cause occurring prior to the commencement of the damage

cause by the Contractor in the course of any operation carried out by him for

the purpose of complying with his obligations under Clause 20 of B-l Tender

form (regarding Defects Liability)

i) The work and the Temporary works to the full value of such works

executed from time to time.

ii) The materials, constructional plant and other things brought to site by

the Contractor to the full value of such material, constructional plant and

other things.

Page 58: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

58

Contractor No. of corrections Executive Engineer

73.3 The Contractor shall indemnify and keep indemnified the Department against

all losses and claims for injuries or damages to any person or any property

whatsoever which may arise out of or in consequence of the construction and

maintenance of the works and against all claims, demands proceedings,

damages, costs, charges and expenses whatsoever in respect of or in relation

thereto provided always that nothing herein contained shall be deemed to

render the Contractor liable for in respect of or to indemnify the Department

against any compensation or damage caused by "EXCEPTED RISKS".

73.4 Before commencing of the work, the contractor shall, without in any way

limiting his obligations and responsibilities under the conditions, insure against

any damage, loss or injury which may occur to any property (including that of

Department) or to any person (including any employee of Department) by or

arising out of carrying out of the contract.

73.5 Where a Department building or a part thereof is rented to the contractor he

shall insure the entire building if the building or any part thereof is used by him

for the purpose of storing or using materials of combustible nature. In case of

doubt in the matter the decision of Engineer-in-charge shall be final and

binding on the Contractor.

73.6 The contractor shall at all times indemnify the Department against all claims,

damages of compensations under the provisions of payments of wages Act,

1936, Minimum Wages Act 1948, Employment Liability Act, 1938, Industrial

Dispute Act 1947, Maternity Benefit Act, 1961 and Inter Stale Migrant

Workmen(Regulation of Employment and Conditions of Services) Act, 1979 or

any modifications thereof, any other law relating thereto, any rules made there

under from time to time or as a consequence of any accident or injury to any

workmen or other person in or about the works, whether in the employment of

the Contractor or not, save and except where such accident or injury has

resulted from any act of the Department, their agents or servants and also

against all costs charges and expenses or any suit, action or proceedings

arising out of such accident or injury and all sum or sums which may with the

consent of the Contractor be paid to compromise or compound any such claim

without limiting his obligation and liabilities as above provided the Contractor

shall insure against all claims, damages or compensation payable under the

workmen Compensation Act, 1923 or any modifications thereof or any other

law relating thereto.

73.7 All the aforesaid insurance policies shall provide that they shall not be

cancelled till the Engineer-in-charge has agreed to their cancellation.

73.8 The Contractor shall prove to the Engineer-in-charge or his authorized

representative from time to time that he has taken out all the insurance policies

referred to above and has paid the necessary premia for keeping the policies

alive till the expiry of the Defects Liability Period.

Page 59: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

59

Contractor No. of corrections Executive Engineer

73.9 The Contractor shall ensure that similar insurance policies are taken out by his

sub-contractor (if any) and shall be responsible for any claims or losses to

department resisting from their failure to obtain adequate insurance protection

in connection thereof. The Contractor shall produce or cause to be produced

by his sub-contractors (if any), as the case may be, relevant policy or policies

and premium receipts as and when required by the Engineer-in-charge.

73.10 The Contractor/ or his sub-contractor, if any, shall fail to effect and keep in

force the insurance referred to above or any other insurance which he/they may

be required to effect under the terms of the contract, then in any such case,

department shall pay such premium or premia as may be necessary for that

purpose and from time to time deduct the amount so paid by the department

from any moneys due or which may become due to the Contractor or recover

the same as a debt due from the Contractor.

73.11 All insurance to be effected by the Contractor and/or his sub-contractor (if any)

shall be taken out only with the Directorate of insurance, Government of

Maharashtra, New Administrative Building, Mumbai.

74. Construction programme

The construction of new Kharland Scheme or renovation of Kharland Scheme

includes earthen bund and sluice gates at various location‟s. The priority

should be given to the construction of sluice gats. The construction of sluice

gate must be complete before 50% of time limit of contract. No further

payment of earth work is done till the completion of sluice gates.

Page 60: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

60

Contractor No. of corrections Executive Engineer

Page 61: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

61

Contractor No. of corrections Executive Engineer

APPENDIX „A‟

DETAILS OF WORKS SIMILAR TYPE AND MAGNITUDE

CARRIED OUT BY THE TENDERER LIST

Sr. No. Name of the Work Name and

address of the

organization for which

the work was done.

Place

and

country

Tendered

Cost

Time in

which the

work is

complete

d

Date of

completion

Principal

features

in brief

1 2 3 4 5 6 7 8

Page 62: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

62

Contractor No. of corrections Executive Engineer

APPENDIX „B‟

LIST OF OTHER WORKS TENDERED FOR AND IN HAND FOR LAST FIVE

YEARS AS ON THE DATE OF SUBMISSION OF THIS TENDER

Name of the Tenderer : ----------------------------------------------------------------------------

--

Sr.No. Name

of the

Work

Name and

address of

the

organization

for which

the work

was done.

Place

and

country

Work in Hand Work tendered for Remarks

Tendered

Cost

Cost of

remaining

work

Anticipated

date of

completion

Tendered

Cost

Cost of

remaining

work

Anticipated

date of

completion

1 2 3 4 5 6 7 8 9 10 11

Page 63: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

63

Contractor No. of corrections Executive Engineer

APPENDIX „C‟

LIST OF MACHINERY IMMEDIATELY AVAILABLE WITH THE TENDERER WHICH WILL BE

USED ON THIS WORK

Name of the Tenderer : -------------------------------------------------------------------------

Sr.No Name of equipment

No of units

Kind

and

make

Capacity Age of machinery

Present

condition

of

Machinery

Present location

with name and

address of the

organization hire

machinery under

use at present

Whether the

machinery is

hypothecated to

any division,

Bank or Institute

etc.

Whether

owned of

otherwise

1 2 3 4 5 6 7 8 9 10

Page 64: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

64

Contractor No. of corrections Executive Engineer

APPENDIX „D‟

DETAILS OF TECHNICAL PERSONS WITH THE TENDERER FOR PLACEMENT ON THIS WORK

Name of the Tenderer : --------------------------------------------------------------------------------------------

Sr.No. Designation Name Qualification Professional Experience and

details of work carried out

Remarks

1 2 3 4 5 6

Page 65: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

65

Contractor No. of corrections Executive Engineer

APPENDIX „E‟

DECLARATION OF THE

CONTRACTOR

1. I/We -----------------------------------------------------------------------------

Contractor (s) hereby undertake that I/We shall pay to the labourers,

engaged on the work of Construction of “4402 capital out lay

Renovation bund work of Annapurna Kharland scheme Tal Roha

Dist. Raigad.@ ch. 0 m. to 3540 m. & Sluice Gate @ Ch. 960 m.,

2100 m. & 3540 m. wages as per minimum wages act 1948 and

amendments thereto applicable to the zone in which the work lies and

acts accordingly. I/We also undertake to abide by the various laws in

force and extend necessary facilities and amenities to the staff and

workers employed by me/us. 2. I/We hereby declare that I/We have made myself/ourselves thoroughly

conversant with the local condition regarding all materials and labour on

which I/We have bidded my/our rates for this work. The specifications

and drawings of this work have been carefully studied and understood

by me/us before submitting this tender.

3. I/We hereby undertake to indemnify and hereby to indemnify the

Government against all liabilities arising out of application of all labour

laws viz. the minimum wages act, the workmen‟s compensation act, the

payment of wages act, ESIS and PF act, etc with reference to labour

engaged on subject work.

4. I/We hereby declare that I/We are aware of the inclusion of all lead and

lift charges of the required materials in the rates of items in the schedule

„B‟ of this tender for the work of Renovation bund work of

Annapurna Kharland scheme Tal Roha Dist. Raigad.@ ch. 0 m. to

3540 m. & Sluice Gate @ Ch. 960 m., 2100 m. & 3540 m. The rates

are agreeable to me/us. I will not claim any charges for extra lead and

lift of the materials.

5. I/We hereby declare that I/We have made myself/ourselves thoroughly

conversant with the site conditions particularly daily tidal variations,

approach to the work site, behavior of embankment in tidal variations

during construction till completion on which my rates are based for this

work. I undertake to use only the best materials approved by the

Executive Engineer, Kharland Survey & Investigation Division, Pen by

his duly authorized assistant and to abide by his decision.

Page 66: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

66

Contractor No. of corrections Executive Engineer

APPENDIX F‟

FORM OF BANK GURANTEE BOND

(ON STAMP PAPER WORTH Rs. 100/-)

In consideration of the Governor of Maharashtra (hereinafter called “The

Government”) having agreed to exempt ----------------------------------------------

----------- (hereinafter called the said contractors) from depositing with

Government in cash of being the amount of security deposit payable by

the contractor to the Executive Engineer, Kharland Survey & Investigation

Division, Pen of the one part and the contractor of the other part (herein

referred „The said agreement‟) for ------------------------- as security for the

due observance and performance by the contractor of the terms and

conditions contained in the said agreement, on the contract furnishing to the

Government guarantee in the prescribed form of a Scheduled Bank in India

being in fact these present in the like sum of our Local Head Office at ---------

---------------------- hereby. 1. Guarantee to the Government

a) Due performance and observance by the contractor of the terms,

covenants and conditions on the part of the contractor contained in the said

agreement. Due and punctual payment by the contractor to the Government

of all sums of money, losses, damages, cost charges, penalties and expenses

payable to the Government by the contractor under or in respect to the said

agreement.

2. Undertake to pay to the Government on demand by the Executive

Engineer, Kharland Survey & Investigation Division, Pen and without demur

and not withstanding any dispute or disputes raised by the contractor in any

suit or proceeding filed in any court of Tribunal relating thereto the said sum

of Rs. ----------- (Rupees -----------------------) or such lesser sum as may

be demanded by the Executive Engineer, Kharland Survey &

Investigation Division, Pen from us our liability hereunder being absolute

and unequivocal and agree that.

3. a) The guarantee herein contained shall remain in all full force & effect

during the subsistence of the said agreement and the same will continue to be

enforceable till all the dues of the Government under or by virtue of the said

agreement have been duly paid and its claims satisfied or discharged and

till the Executive Engineer, Kharland Survey & Investigation Division, Pen

certifies that the terms and conditions of the said agreement have been duly

and properly carried out by the contractor. b) We shall not be discharged or released from the liability under this

Guarantee by reasons of i) any change in the constitution of the bank of the contractor, or

Page 67: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

67

Contractor No. of corrections Executive Engineer

ii) any arrangement entered in between the Government and the

contractor with or without our consent: iii) any forbearance of indulgence shown to the contractor:

iv) any variation in terms of covenants or conditions contained in the said

agreement v) any time given to the contractor

vi) any other conditions or circumstances under which, in law, a surety

would be discharged.

c) Our liabilities hereunder shall be joint and several with that of the

contractor as if we were the principal debtors in respect of the said sum of

Rs. ----------- (Rupees -------------------------------------- only) AND

d) We shall not revoke this guarantee during its currency except with the

previous consent in writing of the Executive Engineer, Kharland Survey

& Investigation Division, Pen. IN WITNESS WHEREOF THE common seal of

Has been hereinto affixed this ----------- day of ----------200

The common seal of ---------------------------------------------------------- was

pursuant to the resolution of the Board of Directors of the company

dated the ------- --- day of ------------,20 herein affixed in the presence

of -------------------------------------------,who, in token thereof, have set their

respective hands in the presence of- 1) ------------------------------------------------------------------------------

2) ------------------------------------------------------------------------------

Page 68: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

68

Contractor No. of corrections Executive Engineer

APPENDIX „H‟

Programme of work to be carried out until completion Renovation bund work of Annapurna Kharland scheme Tal Roha Dist. Raigad.@ ch. 0 to 3540 m. & Sluice Gate @ Ch. 960 m., 2100 m. &

3540 m.

Item

No.

Item of Work Total Tender

Quantity

Unit Programme of execution

Year-I Year-II

Quarter Quarter Quarter Quarter Quarter Quarter Quarter Quarter

I II III IV I II III IV

As per schedule B

1 Item No.1:- Cleaning and

removing grass bushes and

shrubs etc. stacking the stuffs

up for all leads and lifts, etc.

complete.

57984.36 Sqm

. 20000 20000 -- -- 17984 --- --- ---

2 Item No.2:- Excavation in soil

/ soft murum / lime shadu

exceeding 1.50 m. in width

including depositing the

material as directed for all

leads and lifts including

dressing etc. complete.

Cum --- --- --- --- --- --- --- ---

For “C” Work 7357.69

Cum

5000 2357.69 --- -- -- -- -- --

For F.R.H.T. Works 1398.72 Cum --- --- --- -- -- 1398.72 -- --

3 Item No.3 :- Constructing

embankment for Hearting

Zone with selected material

from barrow area including

transporting the material with

Page 69: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

69

Contractor No. of corrections Executive Engineer

leads of 15 m. and lifts upto

1.50 m. laying in layers,

leveling, spreading, breaking

clods including watering etc.

complete. For “C” Work (Wet

condition) 45281.16 Cum 20000 20000 -- -- 5281.16 --- --- ---

4 Item No. 4 :- Constructing

embankment for Casing Zone

with selected material from

borrow area including

transporting the material with

all leads & lifts laying in

layers, leveling and dressing

the bank work including

watering etc complete.

For a"C" Work ( Dry

condition)

19406.21 Cum -- 15000 -- -- 4406.21 -- --- --

For F.R.H.T. Works 7690.90 Cum -- -- -- -- -- 7690.90 -- --

5 Item No. 5 :- Constructing

embankment for Casing Zone

with selected material from

borrow area including

transporting the material with

all leads & lifts laying in

layers, leveling and dressing

the bank work including

watering etc complete.

6539.09 Cum 2000 2000 -- -- 2000 539.09 -- --

6 Item No. 6 :- Providing and

laying dry stone pitching 20

CM thick to side slopes

embankment including

dressing the bank work with all

leads and lifts, etc. complete.

Page 70: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

70

Contractor No. of corrections Executive Engineer

A) from borrow area 24543.85 Sqm 10000 7543.85 --- -- 7000 --- --- ---

B) From Available material 10518.80 Sqm 3506 3506 -- -- 3506.80 --- --- ---

7 Item No.7 :- Providing &

constructing down stream rock

toe with 15 to 23 cm. rubble

stone of approved quality from

borrow area with hand packing

including all leads and lifts.

67.50 Cum 67.50 --- --- -- --- --- --- ---

8 Item No.8:- Providing and

laying in situ of grade M - 200

(1:1.5:3) controlled reinforced

cement Concrete of trap metal

for raft slab etc. including "V"

haunches form work,

scaffolding, compaction by

vibrating,finishing curing etc.&

Centering (excluding

dewatering by means of

pumps) including complete(

Upto 5 m height)-excluding

reinforcement.

113.83 Cum --- --- --- --- --- 113.83 --- --

9 Item No.9- Dismantling

carefully the existing structure

of stone masonry in cement or

Lime Morter, including sorting

out serviceable materials and

stacking the dismantled

material with all lead and lifts

neatly as directed etc.

complete.

186.70 Cum --- --- --- --- --- 186.70 -- --

10 Item No.10:- Dewatering for

Abutment, Returns, Piers, Raft,

Cut of walls, Toe wall, Apron

in perennial river or stream

28400 Cum --- --- --- --- 14000 14400 --- --

Page 71: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

71

Contractor No. of corrections Executive Engineer

including diversion of stream

providing coffer dams, bunds

etc. as may be necessary for

foundation and other parts of

work and bailing out and / or

pumping out water below the

actual initial natural water level

during execution of all item of

construction as required (from

start of that particular

component till completion of

bridge) including all leads and

lifts etc. complete. 11 Item No.11:- Providing rubble

of trap/ granite/ quartzite/

gneiss stone of approved

quality in foundation

including hand packing filling

gravel of sand in the voids etc.

complete.

1334.50 Cum --- --- --- --- 500 834.50 --- --

12 Item No.12:- Providing and

laying in situ PCCM-15

cement concrete of trap/

granite/ quartzite/ gneiss metal

in foundation, including

necessary bailing out water,

compacting and curing,

(excluding dewatering by

pump).

71.60 Cum --- --- --- --- --- 71.60 --- --

13 Item No.13 - Providing and

laying in situ R.C.C.M-20

controlled reinforced cement

concrete of trap metal for raft

slab including ''v'' haunches,

formwork, scaffolding,

compaction by vibrating,

190.94 Cum --- --- --- --- 90.00 100.94 -- --

Page 72: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

72

Contractor No. of corrections Executive Engineer

finishing curing, etc. complete.

(Excluding reinforcement )

14 Item No.14:- Providing &

laying in situ R.C.C. M-20

cement concrete of trap/

granite/ quartzite/ gneiss metal

for cast in citu R.C.C. solid

piers, column etc. including

provision of "V" shaped false

joints to form suitable panels

on the faces to approve design

with compacting by vibrating

and curing complete, including

formwork centering (excluding

dewatering by means of pump)

and including bailing out water

and curing, (upto 5.00 m.

height ) ( Excluding

reinforcement)

163.57 Cum --- --- --- --- 63.00 100.57 --- --

15 Iten No. 15:- Providing and

cutting bending, hooking,

laying in position and laying

HYSD bars for reinforcement

as per detailed drawings for

R.C.C. work

8.10 Cum --- --- --- --- --- 8.10 --- --

16 Item No.16 :- Providing and

cutting bending, hooking,

laying in position and tying

HYSD bars for reinforcement

as per detailed drawings for

R.C.C. work.

31.73 M.T. --- --- --- --- --- --- --- 31.73

17 Item No.17 :- providing &

applying anticorrosive

treatment for MS & TOR steel

reinforcement as per cement

polymer composite coating

31.73 Cum --- --- --- --- --- 31.73 --- --

Page 73: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

73

Contractor No. of corrections Executive Engineer

(CPCC) method developed by

CECRI including cleanihg the

bar by means of any

established mechanical or

manual method for removing

the rust and deletious

matter,applying rapid setting

primer and cement polymer

sealing coat of approved and

licensed by CECRI including

redoing the process if damaged

occur during handling stacking

etc.complete as directed by the

Engineer in charge (With prior

approval of S.E. is essential) 18 Item No.18 :- Providing &

fixing polipropelyne glass lined

F.R.P.Rectangular gate

Including fixing with a - lead

of 15 m. and lift 1.5 m. etc

25.50 Sqm --- --- --- --- --- 25.50 --- --

19 Item No.19:- Providing and

laying dry stone masonry

(Groyness) excluding pointing

etc. complete.

1920 Cum --- --- --- --- --- 900 1020 --

Page 74: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

74

Contractor No. of corrections Executive Engineer

FORM B – 1

ITEM RATE TENDER AND CONTRACT FOR WORKS

DEPARTMENT : WATER RESOURCES DEPARTMENT

REGION : KONKAN REGION, MUMBAI

CIRCLE : KHARLAND DEVELOPMENTCIRCLE, THANE

DIVISION : KHARLAND SURVEY & INVESTIGATION DIVISION, PEN-RAIGAD.

THANE NAME OF WORK : Renovation bund work of Annapurna Kharland

scheme Tal Roha Dist. Raigad.@ ch. 0 m. to 3540 m. &

Sluice Gate @ Ch. 960 m., 2100 m. & 3540 m.

General Rules and Directions for the Guidance of

Contractors

1. All works proposed to be executed by contractor shall be notified in a

form of invitation to tender pasted on a board displayed in the office of the

Executive Engineer and signed by the Executive Engineer.

This form will state the work to be carried out as well as the date for

submitting and opening tenders, and the time allowed for carrying out the

work, also the amount of earnest money to be deposited with the tender

and the amount of security deposit to be deposited by the successful

tenderer and the percentage, if any, to be deducted from bills. It will also

state whether a refund of a quarry fees, royalties, dues and ground rents

will be granted. Copies of the specifications, designs and drawings and any

other documents required in connection with the work shall be signed by

the Executive Engineer for the purpose of identification and shall also be

open for inspection by contractors at the office of the Executive Engineer

during office hours.

Where the works are proposed to be executed according to the

specifications recommended by a contractor and approved by a

competent authority on behalf of the Government of Maharashtra such

specifications with designs and drawings shall form part of the accepted

tender.

2. In the event of the tender being submitted by a firm, it must be signed by each

partner thereof, and in the4 event of absence of any partner it shall be signed on

his behalf by a person holding a power of attorney authorizing him to do so.

2 (A)

(i) The contractor shall pay the sum of Rs. 1,50,000 (Rupees One Lakh Fifty

Thousand Only) as and by way of earnest money. The contractor may

pay the said amount by forwarding “Treasury challan / Call deposit receipt or

short term deposit receipt for a period of one year of any nationalized bank

Page 75: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

75

Contractor No. of corrections Executive Engineer

for the like amount in favour of the Executive Engineer and to be submitted

in the office of Executive Engineer, Khar Land Survey & Investigation

Division Pen-Raigad, Umbarde Colony, Tal. Pen, Dist. Raigad on or before

15/01/2014 17.00 Hrs on working days. The said amount of earnest money

shall not carry any interest whatsoever.

(Amended vide G.P.W. & H. Department‟s Corrigendum)

(ii) In the event of this tender being accepted, subject to the provision of sub

clause (iii) below, the said amount or earnest money shall

be appropriated towards the amount of security deposit payable by him

under conditions of General conditions of contract.

(iii) If, after submitting the tender, the contractor withdraw his offer, or

modifies the same or if after the acceptance of his tender the contractor fails

or neglects to furnish the balance of security deposit without prejudice

to any other rights and powers of the Government hereunder or in law,

Government shall forfeit the full amount of the earnest money deposited by

him.

(iv) In the event of his tender not being accepted, the amount of earnest money

deposited by the contractor shall, unless it is prior thereto forfeited

under the provisions of sub-clause (iii) above, be refunded to him on his

passing receipt thereof.

3. Receipts for payments made on account of any work, when executed by a

firm, should also be signed by all the partners except where the

contractors are described in their tender as a firm, in which case the receipt

shall be signed in the name of the firm by one of the partners, or by some

other person having authority to give effectual receipt for the firm.

4. Any person who submits a tender shall fill up the printed schedule “B” form

stating at what rate (memorandum showing items of work to be carried out) he

is willing to undertake the item of works. Tenders which propose any

alteration in the works specified in the said form of invitation to tender,

or in the time of allowed for carrying out the work, or which contain any

other conditions of any sort will be liable to rejection. No printed form

of tender shall include a tender for more than one works but if contractor

who wish to tender two or more works, they shall submit separate tender

for each. Tenders shall have the name and number of the work to which

they refer written outside the envelope.

5. Superintending Engineer, Kharland Development Circle, Thane or his duly

authorized Assistant shall open the tenders online as per e-

Tendering procedure in the presence of contractors who have submitted

tenders or their representatives who may be present at the time and he will

enter the amounts of the several tenders in a comparative statement in a

suitable form. In the event of a tender being accepted, the contractor shall

Page 76: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

76

Contractor No. of corrections Executive Engineer

for the purpose of identification, sign copies of the specifications and

other documents mentioned in Rule 1. In the event of tender being

rejected, the Divisional officer shall refund the amount of earnest money

deposited by the contractor on his giving a receipt for the return of the money

6. The officer competent to dispose off the tenders shall have the right of

rejecting all or any of the tenders.

7. No receipt for any payment alleged to have been made by a contractor in

regard to any matter relating to this tender or the contract shall be valid and

binding on Government, unless it is signed by the Executive Engineer.

8. The memorandum of work to be tendered for and the schedule of

materials to be supplied by the department and their rates be filled in and

completed by the office of the Executive Engineer before the tender form is

issued. If a form issued to an intending tenderer has not been so filled in and

completed he shall request the said office to have this done before he

completes and delivers his tender.

9. All works shall be measured net by standard measure and according to the

rules and customs of the Department and their rates shall be without reference

to any local custom.

10. Under no circumstances shall any contractor be entitled to claim

enhanced rates for items in this contract.

11. Every registered contractor should produce along with his tender

certificate of registration as approved contractor in the appropriate class and

renewal of such registration with date of expiry. 12 All corrections and additions or pasted slips should be initialed.

13. The measurements of work will be taken according to the usual method in

use in the department and no proposals to adopt alternative methods will be

accepted. The Executive Engineers decision as to what is the usual method

in use in the Department will be final.

14. The tendering contractor shall furnish a declaration along with the

tender showing all works for which he has already entered into contract, and

the value of work that remains to be executed in each case on the date of

submitting tender.

15. Every tenderer shall furnish along with the tender, information regar5ding the

Income Tax circle or ward of the district in which he is assessed to income tax

the reference to the number of assessment and the assessment year, and a valid

Income tax clearance Certificate or copy of the balance sheet for the previous

year.

16. In view of the difficult position regarding the availability of foreign

exchange no foreign exchange would be released by the Department for the

Page 77: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

77

Contractor No. of corrections Executive Engineer

purchase of plant and machinery required for the execution of the work

contracted for. (GCB/PWD/CFM/1058-62517 dated 26.09.59)

17. The contractor will have to construct shed for storing controlled and

valuable materials issued to him under schedule „A‟ of the agreement, at the

work site, having double locking arrangement. The materials will be taken for

use in the presence of the Departmental person. No materials will be allowed

to be removed from the site of works.

18. The contractor shall also give a list of machinery in their possession and

which they propose to use on the work.

19. Every registered contractor should furnish along with the tender a

statement showing previous experience and technical staff employed by him.

20. Successful tenderer will have to produce to the satisfaction of the

accepting authority a valid and current license issued in his favour under the

provision of contract Labour (Regulation and Abolition Act, 1970) before

starting work, failing which acceptance of the tender will be liable for

withdrawal and earnest money will be forfeited to Government. 21. The contractor shall comply with the provision of the apprentices Act

1961 and the rules and orders issued there under from time to time. If he fails

to do so, his failure will be a breach of the contract and the

Superintending Engineer, may in his discretion cancel the contract. The

contractor shall also be liable, for any pecuniary liability arising on account

of any violation by him of the provision of the act.

22. Where the words Irrigation Department appear in this contract the Water

Resources Department of the Government of Maharashtra shall be

implied.

23. As a prima contractor he should have executed at list one work with Earthen

bund and sluice gate of Kharland Scheme work in one working season not less

than 100 lakhs during last five years

Page 78: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

78

Contractor No. of corrections Executive Engineer

TENDER FOR THE WORKS

Note: The Commercial Offer must be filled online using individual‟s digital

certificate. (An online form will be provided for this during online bid

preparation stage).

I/We hereby tender for the execution for the Government of

Maharashtra (hereinbefore and hereinafter referred to as “Government” of

the work specified in the under written memorandum within the time

specified in such memorandum at * ------------% (in figures)---------------

----------------------percent (in words) percent below / above the estimated

rates entered in schedule - B (memorandum showing items of the work to be

carried out) and in accordance in all respects with the specifications, designs,

drawings and instructions in writing referred to in Rule -1 hereof and in clause

-13 of the annexed conditions of contract and agree that when materials

for the work are provided by the Government such materials and the

rates to be paid for them shall be as provided in schedule „A‟ hereto.

Memorandum

a) General Description Renovation bund work of Annapurna

Kharland scheme Tal Roha Dist.

Raigad.@ ch. 0 to 3540 m. & Sluice Gate

@ Ch. 960 m., 2100 m. & 3540 m.

b) Estimated Cost Rs. 2,55,34,893/-

c) Earnest Money Rs.1,50,000/-

d) Security Deposit Rs. 10,22,000/-

i) Cash (Not less than the amount

of E.M.D

ii) To be deducted from the

current bills

iii) Additional Security Deposit (if

required)

Rs. 5,11,000/- Rs. 5,11,000/-

Nil

e) Percentage, if any to be deducted

from bills so as to make up the

total amount required as security

deposit by the time, half the work, as

measured by the cost of work done.

(4) percent

f) Time allowed for the work from

date of order to commence

24 calendar months including

monsoon.

Page 79: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

79

Contractor No. of corrections Executive Engineer

I/We agree that the offer shall remain open for a minimum period of 120 days

from the date fixed for opening the same and thereafter until it is withdrawn

by me/us by notice in writing duly addressed to the authority opening the

tenders and sent by Registered Post Acknowledgement Due or otherwise

delivered at the office of such authority. Treasury/Bank challan No. and date

in respect of the sum Rs. ……. (Rupees ………………….. only)

representing the earnest money is herewith forwarded. The amount of earnest

money shall not bear interest and shall be liable to be forfeited to the

Government should I/We fail to (1) abide by the stipulations to keep the

offer open for the period mentioned above or (2) sign and complete the

contract documents as required by the Engineer and furnish the security

deposit as specified in item (d) of the memorandum contained in

paragraph (i) above within the time limit laid down in clause (1) of the

annexed General Condition of Contract. The amount of earnest money may

be adjusted towards the security deposit or refunded to me/us if so desired by

me/us in writing, unless the same or any part thereof has been forfeited as

aforesaid.

I/We have secured exemption from payment of earnest money after

executing the necessary bond in favour of the Government, a true copy of

which is enclosed herewith. Should any occasion for forfeiture of earnest

money for this work arise due to failure on my/our part to (1) abide by the

stipulations to keep the offer open for the period mentioned above or (2) sign

and complete the contract documents and furnish the security deposit as

specified in item (d) of the memorandum contained in paragraph - I above

within the time limit laid down in clause (1) of the annexed conditions of

contract, the amount payable by me/us may, at the option of the Engineer be

recovered out of the amount deposited in lump sum for securing exemption in

so far as the same may extend in terms of the said bond and in the event of the

deficiency out of any other moneys which are due or payable to me/us by the

Government under any other contract or for transaction of any nature

whatsoever or otherwise. Should this tender be accepted I/We hereby agree to abide by and fulfill all the

terms and provision of the conditions annexed hereto so far as applicable and

in default thereof to forfeit and pay to Government the sum of money

mentioned in the said conditions.

Contractor

Signature of contractor before

submission of tender

Address Dated

Page 80: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

80

Contractor No. of corrections Executive Engineer

Witness Address

(Occupation)

Signature of Witness

to contractor‟s signature

The above tender is hereby accepted by me for and on behalf of

the Government of Maharashtra. . . . . . . . . . . . . Dated.

Executive Engineer,

Kharland Survey & Investigation Division,

Pen – Raigad.

Page 81: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

81

Contractor No. of corrections Executive Engineer

CONDITIONS OF CONTRACT

Clause 1

The person/persons whose tender may be accepted

(hereinafter called "The Contractor "which

expression unless excluded by or repugnant to the

context include his heirs, executor, administrators,

and assigns) shall (A) within 10 days (which may

be extended by the Superintending Engineer

concerned up to 15 days if the Superintending

Engineer thinks fit to do so) of the receipt by him of

the notification of the acceptance of his Tender

deposit with the Executive Engineer in cash or

Govt. securities endorse to the Executive Engineer

(if deposited for more than 12 months) of sum

sufficient which will make up the full security

deposit specified in the tender or (B) Permit

Government at the time of making any payment to

him for work done under the contact to deduct such

sum as will amount to 4% (Four percent)* of all

moneys so payable such deductions to be held by

Government by way of security deposit Provided

always that in the event of the contractor depositing

a lump sum by way of security deposits as

contemplated as (A) above then and in such case, if

the sum so deposited shall not amount to 4% (Four

percent)* of the total estimated cost of the work, it

shall be lawful for Government at the time of

making any payment to the contractor for work

done under the contract to make up the full amount

of 4% (Four percent) by deducting a sufficient sum

from every such payment as last aforesaid until the

full amount of the security deposit is made up. All

compensation or other sums of money payable by

the contractor to Government under the terms of his

contract may be deducted from, or paid by the sale

of a sufficient part of his security deposit or from

the interest arising there from or from any sums

which may be due or may become due by

Government to the contractor under any other

contract or transaction for any nature on any

account whatsoever and in the event of his security

deposit being reduced by reason of any such

deduction or sale as aforesaid the contractor shall

within 10 (Ten) days thereafter make good in cash

Security deposit

PWD, Resolution No.

CAT 1087/CR-

94/Bldg.2 dl.

14.06.89.E/C.manual

Page 82: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

82

Contractor No. of corrections Executive Engineer

or Government securities endorsed as aforesaid any

sum or sums which may have been deducted from

or raised by sale of his security deposit or any part

thereof. The security deposit referred to when paid

in cash may, at the cost of the depositor be

converted into interest bearing securities provided

that the depositor has expressly desired this in

writing.

The security deposit will not be accepted in the

form of Insurance company bonds as per

Government order contained in No.

CCM / PWD/ CAT / 4350 dated 27.2.1956.

If the amount of the security deposit to be paid in

lump sum within the period specified at (A) above

is not paid the tender/contract-already accepted

shall be considered as cancelled and legal steps

shall be taken against the contractor for recovery of

the amounts. The amount of the security deposit

lodged by a contractor shall be refunded, along with

the payment of the final bill. if the date up to which

the contractor has agreed to maintain the work in

good order is over. If such date is not over only

50% amount of security Deposit shall be refunded

along with the payment of thee final bill. The

amount of security deposit' retained by the

Government shall be released after expiry of

period up to which the contractor has agreed to

maintain the work in good order is over. In the

event of the contractor failing or neglecting to

complete rectification of work within the period up

to which the contractor has agreed to maintain the

work in good order, then, subject to provisions of

clauses 17 and 20 hereof the amount of security

deposit retained by the Government shall be

adjusted towards the excess cost incurred by the

department on rectification work.

Clause 2:-

The time allowed for carrying out the work as

entered in the tender shall be strictly observed by

Contractor and shall be reckoned from the date on

which the order to commence work is given to the

contractor. The work shall throughout the

stipulated period of the contract be proceeded with,

all due diligence (Time being deemed to be the

essence of the contract on the part of the contractor)

Compensation for delay.

Page 83: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

83

Contractor No. of corrections Executive Engineer

and the contractor shall pay as compensation an

amount equal to one percent or such smaller amount

as the Superintending Engineer (whose decision in

writing shall be final) may decide, of the estimated

cost of the whole work as shown by the tenderer for

every day that the work remains uncommenced, or

unfinished, after the proper dates. And further to

ensure good progress during the execution of the

work, the contractor shall be bound, in all cases in

which the time allowed for any work exceeds one

month to complete.

1/6 of the work in 1/4 of the time.

½ of the work in 1/2 of the time.

¾ of the work in 3/4 of the time.

Note: -The quantity of the work to be done within a

particular time to be specified above shall be fixed

and inserted in the blank space kept for the purpose

by the officer competent to accept the contract after

taking into consideration the circumstances of each

case and the contractor shall abide by the program

of detailed progress laid down by the Executive

Engineer.

The following proportion will usually be found

suitable: In ¼, ½, and ¾ of the time.

Reasonable progress of earthwork: 1/6, 1/2, and 3/4

of the total value of the work to be done.

Reasonable progress of masonry work: 1/10, 4/10,

and 8/10 of the total value of the work to be done.

Performance of the contactor in respect of physical

progress of prominent items shall be adjusted with

reference to the bar chart attached with the B-1

contract or the programme submitted by the

contractor and approved by the Engineer-in-charge.

In the event of the contractor failing to comply with

these conditions he shall be liable to pay as

compensation an amount equal to one percent, or

such smaller amount as the Superintending

Engineer (whose decision in writing shall be final)

may decide of the said estimated cost of the whole

work for every day that the due quantity of work

remains incomplete, provided always that the total

Page 84: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

84

Contractor No. of corrections Executive Engineer

amount of compensation to be paid under the

provision of this clause shall not exceed 10

percent of the estimated cost of the work as shown

in the tender. The Superintending Engineer should

be the final authority in this respect.

Clause 3: -

In any case in which under any clause or clauses of

this contract the contractor shall have rendered

himself liable to pay compensation amounting to

the whole of his security deposit (whether paid in

one sum or deducted by installment) or in the case

of abandonment of the work owing to serious

illness or death of the contractor or any other cause,

the Executive Engineer, on behalf of the Governor

of Maharashtra, shall have power to adopt any of

the following courses, as he may deem best suited

to the interest of the Government.

(a) To rescind the contract (of which rescission

notice in writing to the contractor under the hand of

Executive Engineer) shall be conclusive evidence

and in that case the security deposit of the

contractor shall stand forfeited and be absolutely at

the disposal of the Government.

(b) To carry out the work or any part of the work

departmentally debiting the contractor with the cost

of the work expenditure incurred on tools and plant

and charges on additional supervisory staff

including the cost of work-charged establishment

employed for getting the unexecuted part of the

work completed and crediting him with the value of

the work done departmentally in all respects in the

same manner and at the same rates as if it had been

carried out by the contractor under the term of his

contract. The certificate of the Executive Engineer

as to the costs and other allied expenses so incurred

and as to the value of the work so done

departmentally shall be final and conclusive against

the contractor.

(c) To order that the work of the contractor be

measured up and to take such part thereof as shall

be unexecuted, out of his hands and to give it to

another contractor to complete, in which case all

expenses incurred on advertisement for fixing a new

contracting agency, additional supervisory staff

Action when whole of

security deposited is

forfeited.

Page 85: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

85

Contractor No. of corrections Executive Engineer

including the cost of the work-charged

establishment and the cost of the work executed by

the new contract at the value of the work done or

executed through the new contractor shall be

credited to the contractor in all respects and in the

same manner and at the same rates as if it had been

carried out by the contractor under the terms of his

contract. The certificate of the Executive Engineer

as to all the cost of the work and other expenses

incurred as aforesaid for or in getting the

unexecuted work done by the new a contractor and

as to the value of the work done by the new

contractor and as to the value of the work so done

shall be final and conclusive against the contractor.

In case the contract shall be rescinded under the

clause (a) above the contractor shall not be entitled

to recover or be paid, any sum for any work thereof

actually performed by him under this contract

unless and until the Executive Engineer shall have

certified in writing the performance of such work

and the amount payable to him in respect thereof

and he shall only be entitled to be paid the amount

so certified. In the event of either of the course

referred to in clause (b) or (c) being adopted and the

cost of the work executed departmentally or through

a new contractor and other allied expenses

exceeding the value of such work credited to the

contractor, the amount of excess value shall be

deducted from any money due to the contractor, by

the Government under the contract or otherwise

howsoever or from his security deposits or the sale

proceeds thereof provided, however, that contractor

shall have no claim against Government even if the

certified value of the work done departmentally or

through a new contractor exceeds the certified cost

of such work and allied expenses, provided always

that whichever of the three courses mentioned in

clause(a) (b) or (c) is adopted by the Executive

Engineer, the contractor shall have no claim to

compensation for any loss sustained by him by

reason of his having purchased or procured any

material or entered into any engagements or made

any advance on account of or with a view to the

execution of the work or the performance of the

contract.

Page 86: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

86

Contractor No. of corrections Executive Engineer

Clause 4:

If the progress of any particular portion of the work

is unsatisfactory, the Executive Engineer shall

notwithstanding that the general progress of the

work is in accordance with the conditions

mentioned in clause 2 be entitled to take action

under clause 3 (b) after giving the contractor 10

days notice in writing. The contractor will have no

claim for compensation for any loss sustained by

him owing lo such action.

Clause 5: -

In any case in which any of the powers conferred

upon the Executive Engineer by clauses 3 and 4

hereof shall have become exercisable and the same

shall not have exercised, the non-exercised thereof

shall not constitute a waiving of any of the

conditions hereof and such powers shall

notwithstanding be exercisable in the event of any

future case of default by the contractor for which

under any clause hereof he is declared liable to pay

compensation amounting to the whole of his

security deposit and the liability of the contractor

for past and future compensation shall remain

unaffected.

In the event of the Executive Engineer taking action

under sub-clause (a) or (c) of clause 3, he may, if he

so desires, take possession of all or any tools, plant,

material and stores in or upon the works of the site

thereof or belonging to the contractor, or procured

by him and intended to be used for the execution of

the work or any part thereof paying or allowing for

the same in account at the contract rates or in the

case of contract rates not being applicable at current

market rates, to be certified by the by the Executive

Engineer whose certificate thereof shall be final. In

the alternative the Executive Engineer may, after

giving notice in writing to the contractor or his clerk

of the 'work, foreman or other authorized agent

require him to remove such tools, plant, materials or

stores from the premises within a time to be

specified in such notice, and in the event of the

contractor failing to comply with any such

Action when the progress

of any particular portion

of the work is

unsatisfactory

Contractor remains liable

to pay compensation if

action not taken under

clause 3 and 4.

Power to take possession

of or require removal of

or sell contractor’s plant.

Page 87: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

87

Contractor No. of corrections Executive Engineer

requisition, the Executive Engineer may remove

them at the contractor's expenses or sale them by

auction or private sale on account of the contractor

and at his risk in all respects and the certificate of

the Executive Engineer as to the expenses of any

such removal and the amount of proceeds and

expenses of any such sale shall be final and

conclusive against the contractor. Clause 6: -

If the contractor shall desire an extension of the

time for completion of work on the ground of his

having been unavoidably hindered in its execution

or on any other ground shall apply in writing to the

Executive engineer before the expiration. of the

period, stipulated in the tender or before the

expiration of 30 days from the date on which he

was hindered as aforesaid or on which the cause for

asking for extension occurred, whichever is earlier

and the Executive Engineer, or in the opinion of the

Superintending engineer, or Chief Engineer as the

case may be if in his opinion, there were reasonable

grounds for granting an extension, grant such

extension as he thinks necessary or proper. The

decision of the Executive Engineer Superintending

Engineer or Chief Engineer in this matter shall be

final.

Extension of time

Clause 7: -

On the completion of the work the contractor shall

be furnished with a certificate by the Executive

Engineer (hereinafter called the Engineer-in-

charge) of such completion, but no such certificate

shall be given shall the work be considered to be

complete, until the contractor shall have removed

from the premises on which the work shall have

been executed, all scaffolding, surplus materials and

rubbish, and shall have cleaned off, the dirt from all

wood work, doors, windows, walls, floor or other

parts of any building in or upon which the work has

been executed or of which he may have had

possession for the purpose of executing the work, or

until the work shall have been measured by the

Engineer-in-charge or where the measurement have

been taken by his subordinates until they have

Final certificate.

Page 88: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

88

Contractor No. of corrections Executive Engineer

received approval of the Engineer-in-charge, the

said measurements being binding and conclusive

against the contractor. If the contractor fail to

comply with the requirements of this clause as to the

removal of scaffolding, surplus materials and

rubbish and cleaning of dirt on or before the date

fixed for the completion of the work the Engineer-

in-charge, may at the expense of the contractor,

remove such scaffolding, surplus materials and

rubbish and dispose of the same as he thinks fit and

clean off such dirt as aforesaid and the contractor

shall forthwith pay the amount of all expense so

incurred, but shall have no claim in respect of any

such scaffolding or surplus materials as aforesaid

except for any sum actually realized by the sale

thereof.

Clause 8:-

No payment shall be made for any work estimated to

cost less than rupees one thousand till after the

whole of work shall have been completed and a

certificate of completion given. But in the case of

works estimated to cost more than rupees one

thousand, the contractor shall, on submitting a

monthly bill therefore be entitled to receive payment

proportionate to the part of the work then approved

and passed by the Engineer-m-charge, whose

certificate of such approval and passing of the sum

so payable shall be final and conclusive against the

contractor. All such intermediate payments shall be

regarded as payment by way of advance against the

final payments only and not as payments for work

actually done and completed and shall not preclude

the Engineer-in-charge, from requiring any bad,

unsound imperfect or unskillful work to be removed

and taken away and reconstructed or re-erected or

shall any such payment be considered as an

admission of the due performance of the contract or

any part thereof in any respect or the occurring of

any claim nor shall it conclude, determine or affect

in any other way the powers of the Engineer-in-

charge as to the final settlement and adjustment

of the accounts or otherwise, or in any other way

vary or affect the contract. The final bill shall be

submitted by the contractor within one month of the

Payment on intermediate

certificate to be regarded

as advances.

Page 89: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

89

Contractor No. of corrections Executive Engineer

date fixed for the completion of the work, otherwise

the Engineer-in-charge's certificate of the

measurements and of the total amount payable for

the work shall be final and binding on all parties.

Clause 9: -

The rates for several items of work estimated to cost

more than Rs.1000 agreed to with in, shall be, valid

only when the item concerned is accepted as having

been completed fully in accordance with the

sanctioned specifications. In Cases where the items

of work are not accepted as so completed the

Engineer-in-charge may make payment on account

of such items at such reduced rates as he may

consider reasonable in the preparation of final or on

account bills.

Payment or reduced rates

on account of items of

work not accepted as

complete, to be at the

discretion of the

Engineer- in-charge

Clause 10: -

A bill shall be submitted by the contractor in each

month or before the date fixed by the Engineer-in-

charge for all work executed in the previous month,

and the Engineer-in-charge shall take or cause to be

taken the requisite measurement for the purpose of

having the same verified, and the claim, so far as it

is admissible, shall be adjusted, if possible, within

ten days from the presentation of the bill. If the

contractor does not submit the bill within the time

fixed as aforesaid the Engineer-in-charge may

depute subordinate to measure up the said work in

the presence of the contractor or his duly authorized

agent whose countersignature to the measurement

list shall be sufficient warrant, and Engineer-in-

charge may prepare a bill from such list which shall

be binding on the contractor in all respects.

Clause 11: -

The contractor shall submit all bills on the printed

forms to be had on application at the office of the

Engineer-in-charge. The charges to be made in the

bills shall always be entered at the rates specified in

the tender or in the case of any extra work ordered in

pursuance of these conditions, and not mentioned or

provided for in the tender at the rates hereinafter

provided for such work.

Page 90: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

90

Contractor No. of corrections Executive Engineer

Clause 12:-

If the specification or estimate of the work supplied

provides for the use of any special description of

materials to be supplied from the stores of the Dept

store or if it is required that the contractor shall use

certain stores to be provided by the Engineer-in-

charge. (Such material and stores and the prices to

be charged therefore as hereinafter mentioned being

so far as practicable for the convenience of the

contractor but not so as in any way to control the

meaning or effect of this contract specified in the

schedule of memorandum hereto annexed) the

contractor shall be supplied with such materials and

stores as may be required from time to time to be

used by him for the purpose of the contract only, and

value of the full quantity of the materials and stores

so supplied shall be set off or deducted from any

sums then due, or thereafter to become due to the

contractor under the contract, or otherwise or from

the security deposit or the proceeds of sale threof.

If the security is held in Government securities, the

same or a sufficient portion thereof shall, in that

case, be sold for the purpose. All materials supplied

to the contractor shall remain the absolute property

of Govt. and shall on no account be removed from

the site of the work, and shall at all times be open

for inspection by the Engineer-in-charge. Any such

materials unused and in perfectly good condition at

the time of completion or determination of the

contract shall be returned to the Department store if

the Engineer-in-charge so requires by a notice in

writing given under his hand but the contractor shall

not be entitled to return any such materials except

with the consent of the Engineer-in-charge and he

shall have no claim for compensation on account of

any such material supplied to him as aforesaid but

remaining unused by him or for any wastage in or

damage to any such materials.

Bills to be on printed

forms

Clause 12 (A) :-

All stores such as cement, steel etc. supplied to the

contractor by Government should be kept by the

contractor under lock and key and will be accessible

for inspection by the Executive Engineer or his

Page 91: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

91

Contractor No. of corrections Executive Engineer

authorized agent at all the times.

Clause 13 :-

The contractor shall execute the whole and every

part of the work in the most substantial and

workman like manner and both as regards material

and every other respect in strict accordance with

specifications. The contractor shall also conform

exactly, fully and faithfully to the designs, drawings

and instruction in writing relating to the work

Signed by the Engineer-in-charge and lodged in his

office and to which the contractor shall be entitled to

have access for the purpose of inspection and such

officer or on the site of the work during office hour.

The contractor will be entitled to receive three sets

of contract drawings and working drawings as well

as one certified copy of the accepted tender along

with the work order free of cost. Further copies of

the contract drawings and working drawings

documents if required by him, shall be supplied at

the rate specified in the Special Conditions of

Contract except where otherwise specified.

Works to be executed in

accordance with

specifications, drawings,

orders etc.

Clause 14: -

The Engineer-in-charge shall have power to make

any alteration in or additions to the original

specifications, drawings, designs and

instrumentations that may appear to him to be

necessary or advisable during the progress of the

work and the contractor shall be bound to carry out

the work in accordance with any instruction in this

connection which may be given to him in writing

signed by the Engineer-in-charge and such

alteration shall not invalidate the contract and any

additional work which the contractor may be

directed to do in the manner above specified as part

of the work shall be carried out by the contractor on

the same conditions in all respects on which he

agreed to do the main work, and at the same rates as

specified in the tender the lender for the main work.

And if the additional and altered work includes any

class of work for which no rate is specified in this

contract, then such class of work shall be carried out

at the rates entered in the Schedule of Rates of the

Division or at the rates mutually agreed upon

between the Engineer-in-charge and the contractor,

Alternation in

specifications and

designs not to invalidate

contract.

Rates for works not

entered in estimate or

Page 92: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

92

Contractor No. of corrections Executive Engineer

whichever are lower.

If the additional or altered work for which no

rates are entered in the schedule of Rates of the

Division is ordered to be carried out before the rates

are agreed upon then the contractor shall within

seven days of the date of receipt by him of the order

carry out the work, inform the Engineer-in-charge of

the rate which it is his intention to charge for such

class of work and if the Engineer-in-charge does not

agree to this rate he shall by notice in writing be at

liberty to cancel his order to carry out such class of

work and arrange to carry out in such manner as he

may consider advisable provided always that the if

the contractor shall commence work or incur any

expenditure in regard thereto before the rates shall

have been determined as lastly hereinbefore

mentioned, then in such case he shall only be

entitled to be paid in respect of the work carried out

or expenditure incurred by him prior to the date of

the determination of the rate as aforesaid according

to such rate or rates as shall be fixed by the

Engineer-in-charge. In the event of a dispute the

decision of Superintending Engineer of the Circle

will be final.

schedule of rate of the

district.

Where, however, the work is to be executed

according to the designs, drawings and

specifications recommended by the contractor and

accepted by the competent authority the alterations

above referred to shall be within the scope of such

designs, drawings, and specifications appended to

the tender.

The time limit for the completion of the work shall

be extended in the proportion that the increase in its

cost occasioned by, alterations or additions bears to

the cost of the original contract work, and the

certificate of the Engineer-in-charge as to such

proportion shall be conclusive. (B&C depts. No.

C/R- Memo-No. CAT-1268/59382-Q Dt. 14.3.1974.

Clause 15: -

1. If at any time after the execution of the contract

documents the Engineer-in-charge shall, for any

reason whatsoever (other than default on the part

of the contractor for which the Government is

Extension of time in

consequence of additions

or alternations

Page 93: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

93

Contractor No. of corrections Executive Engineer

entitled to rescind the contract), desire that the

whole or any pan of the work specified in the

tender should be suspended for any period or

that the whole or part of the work should not be

carried out at all, he shall give to the

contractor a notice in writing of such desire and

upon the receipt of such notice the contractor

shall forthwith suspend or stop the work wholly

or in part as required, after having due

regard to the appropriate stage at which the

work should be stopped or suspended so as not

to cause any damage or injury to the work

already done or endanger the safely thereof

provided that the decision of the Engineer as to

the stage at which the work or any part of it

could be or could have been safely stopped or

suspended shall be final and conclusive against

the contractor. The contractor shall have no

claim to any payment or compensation

whatsoever, by reason of or in pursuance of any

notice as aforesaid, on account of any

suspension, stoppage or curtailment except to

the extent specified hereinafter

No claim to any payment

or compensation for

alteration in or

restriction of work.

2. Where the total suspension of work ordered

as aforesaid continued for a continuous period

exceeding 90 days the contractor shall be at

liberty to withdraw from the contractual

obligations under the contract so far as it

pertains to the unexecuted part of the work by

giving a 10 days' prior notice in writing to the

Engineer, within 30 days of the expiry of the

said period of 90 days, of such intention and

requiring the Engineer to record the final

measurement of the work already done and to

pay final bill. Upon giving such notice the

contractor shall be deemed to have been

discharged from his obligations to complete the

remaining unexecuted work under his contract.

On receipt of such notice the Engineer shall

proceed to complete the measurements and

make such payment as may be finally due to

the contractor within a period of 90 days from

the receipt of such notice in respect of the work

already done by the contractor. Such payment

shall not in any manner prejudice the right of

the contractor to any further compensation

Page 94: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

94

Contractor No. of corrections Executive Engineer

under the remaining provisions of this clause.

3. Where the Engineer-in-charge requires the

contractor to suspend the work for period in

excess of 30 days at any time or 60 days in the

aggregate, the contractor shall be entitled to

apply to the Engineer within 30 days of the

resumption of work after such suspension of

payment of compensation to the extent of

pecuniary loss suffered by him in respect of

working machinery remained idle on the site or

on the account of his having had to pay the

salary or wages of labour engaged by him

during the said period of suspension provided

always that the contractor shall not be entitled

to any claim in respect of any such working

machinery, salary or wages for the first 30 days

whether consecutive or in the aggregate of such

suspension or in respect of any suspension

whatsoever occasioned by unsatisfactory work

or any other default on his part. The decision of

the Engineer-in-charge in this regard shall he

final and conclusive against the contractor.

4. In the event of-

i) Any total stoppage of work on notice from

Engineer under Sub Clause (1) in that behalf.

ii) Withdrawal by the contractor from the

Contractual obligation to complete the

remaining unexecuted work under sub-clause (2)

on account of continued suspension of work for

a period exceeding 90 days. OR

iii) Curtailment in the quantity of item or items

originally tendered on account of any alteration,

omission or substitution in the specifications,

drawings, designs or instructions under clause

(14) (1) where such curtailment exceeds 25% in

quantity and the value of the quantity curtailed

beyond 25 percent at the rates for the item

specified in the tender is more than Rs.5000/-

It shall be open to the contractor, within 90 days

from the service of (i) the notice of stoppage of

work or (ii) the notice of withdrawal from the

Page 95: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

95

Contractor No. of corrections Executive Engineer

contractual obligations under the contract on

account of the continued suspension of work or

(iii) notice under clause 14(1) resulting in

such curtailment to produce to the Engineer

satisfactory documentary evidence that he had

purchased or agreed to purchase material for use

in the contracted work, before receipt by him

of the notice of stoppage, suspension or

curtailment and require the Government to

take over on payment such material at the rates

determined by the Engineer, provided, however,

such rates shall in no case exceed the rates at

which the same was acquired by contractor.

(Amended vide govt. in P.W.&H. Dept‟s.

circular memorandum No.CAT1208 / 59382-96

K-II dt. 22.02.1978). The Government shall

thereafter take over the material so offered,

provided the quantities offered are not in excess

of the requirement of the unexecuted work as

specified in the accepted tender and are of

quality and specifications approved by the

Engineer.

Clause 15 A: -

The contractor shall not be entitled to claim any

compensation from Government for the loss

suffered by him on account of delay by

Government in supply of materials entered in

schedule A where such delay is caused by.

i) Difficulties relating to the supply of railway

wagons.

ii) Force major

iii) Act of God

iv) Act of enemies of the State or any other

reasonable cause beyond the control of

Government.

In the case of such delay in the supply of

materials, Government shall grant such

extension of time for the completion of the

works as shall appear to the Executive Engineer

to be reasonable in accordance with

circumstances of the case. The decision of

Executive Engineer as to the extension of the

No claim to

compensation on account

of loss due to delay in

supply of material by

Government.

Page 96: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

96

Contractor No. of corrections Executive Engineer

time shall be accepted as final by the contractor.

Clause l6 : -Under no circumstance, whatever may

be, the contractor shall be entitled to any

compensation from Government on any account

unless the contractor shall have submitted a claim in

writing to the Engineer-in-charge within one month

of the cause of such claim occurring

Time limit for

unforeseen claims.

Clause l7: -

If any time before the security deposit or any part

thereof is refunded to the contractor it shall appear

to the Engineer-in-charge or his subordinate in

charge of the work, that any work has been

executed with unsound, imperfect or unskillful

workmanship or with materials of inferior quality,

or that any materials or articles provided by him

for the execution of the work are unsound, or of a

quality inferior to that contracted for or are

otherwise not in accordance with the contract, it

shall be lawful for the Engineer-in-charge to

intimate this fact in writing to the contractor and

then notwithstanding the fact that the work,

materials or articles complained of may have been

inadvertently passed, certified and paid for, the

contractor shall be bound forthwith to rectify, or

remove and reconstruct the work so specified in

whole or in part, as the case may require or if so

required, shall remove the materials or articles so

specified and provided other proper and suitable

materials or articles at his own charge and cost and

in the event of his failing to do so within a period to

be specified by the Engineer-in-charge in the

written intimation aforesaid, the contractor shall be

liable to pay compensation at the rate of one per

cent on the amount of the estimate for every day not

exceeding 10 days, during which, if the failure so

continues and in the case of any such failure the

Engineer-in-charge may rectify or remove and re-

execute the work or remove, and replace the

materials or articles complained of as the case may

be at the risk and expense in all respects of the

contractor. Should the Engineer-in-charge consider

that any such inferior work or materials as

described above may be accepted or made use of it

Action and compensation

payable in case of bad

work P.W.D. Resolution

No. CAT/1087/CR-

94/Bldg-2 dt. 14.06.1989

Page 97: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

97

Contractor No. of corrections Executive Engineer

shall be within his discretion to accept the same at

such reduced rates as he may fix therefore.

Clause 18 :-

A work under or in course of execution or executed

in pursuance of the contract shall at all times be

open to the inspection and supervision of the

Engineer-in-charge and his subordinates, and the

contractor shall, at all times during the usual

working hours, and at all other times at which

reasonable notice of the intention of the Engineer-

in-charge and his subordinate to visit the work shall

have been given to the contractor, either himself be

present to receive order and instructions or have

responsible agent duly accredited in writing present

for that purpose. Orders given to the contractor's

duly authorised agent shall be considered to have

the same force and effect as if they had been given

to the contractor himself.

Work to be open to

inspection

Clause 19:-

The contractor shall give not less than five days

notice in writing to the Engineer-in-charge or his

subordinate in charge of the work before covering

up or otherwise placing beyond the reach of

measurements any work in order that the same may

be measured and correct dimension thereof taken

before the same is covered up or placed beyond the

reach of measurements and shall not cover up or

place beyond the reach of measurement any work

without the consent in writing of the Engineer-in-

charge or his subordinate in charge of the work, and

if any work shall be covered up or placed beyond

the reach of measurement, without such notice

having been given or consent obtained the same

shall be uncovered at the contractor's expenses and

in default thereof no payment or allowance shall be

made for such work or for the materials with which

the same was executed.

Contractor or responsible

agent to be present.

Notice to be given before

work is covered up.

Clause 20:-

lf during the period of 12 Months from the date of

completion as certificated by the Engineer-in-

charge pursuant to Clause- of the contract or 12

.Contractor liable for

damage done and for

imperfections.

Page 98: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

98

Contractor No. of corrections Executive Engineer

Months after commissioning the work, whichever is

earlier, in the opinion of the Executive Engineer,

the said work is found defective in any manner

whatsoever, the contractor shall forthwith, on

receipt of notice in that behalf from the Executive

Engineer, duly commence execution and

completely carry out at his cost in every respect all

the work that may be necessary for rectifying &

setting right the defects specified therein including

dismantling and reconstruction of unsafe

portions strictly in accordance with and in the

manner prescribed and under the supervision of the

Executive Engineer. In the event of the contractor

failing or neglecting to commence execution of the

said rectification work within the period prescribed

therefore in the said notice and / or to complete the

same as aforesaid as required by the said notice, the

Executive Engineer shall get the same executed

and carry out departmentally or by any other

agency at the risk on account and at the cost of the

contractor. The contractor shall forthwith, on

demand, pay to the Government the amount of such

costs, charges and expenses sustained or incurred

by the Government of which the certificate of

Executive Engineer shall be final and binding on

the contractor. Such cost, charges and expenses

shall be deemed to be arrears of land revenue and

on the event of the contractor failing or neglecting

to pay the same on demand as aforesaid without

prejudice to any other rights and remedies of the

Government; the same may be recovered from the

contractor as arrears of land revenue. The

Government shall also be entitled to deduct the

same from any amount which may then be payable

or which may thereafter become payable by the

Government to the contractor either in respect of

the said work or any other work whatsoever or

from the amount of security deposit retained by the

Government.

P.W.D. Resolution

No.CAT/1087/CR-

94/Bldg.2 Dt.14.06.1989

Clause 21:-

The contractor shall supply at his own cost all

material (except such special materials, if any, as

may, in accordance with the contract, be supplied

from the Department Stores) plant, tools,

appliances, implements, ladders, cordage, tackle,

scaffolding and any temporary works requisite or

Contractor to supply

plant, ladder, scaffolding

etc. and is liable for

damages arising from

non provision of lights

fencing etc.

Page 99: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

99

Contractor No. of corrections Executive Engineer

proper for the proper execution of the work,

whether in the original, altered or substitute form

and whether included in the specification or other

documents forming part of the contract or referred

to in these conditions or not and which may be

necessary for the purpose of satisfying or

complying with the requirements of the Engineer-

in-charge as to any matter as to which under these

conditions he is entitled to be satisfied or which he

is entitled to require together with the carriage

therefore and from the work. The contractor shall

also supply without charge the requisite number of

persons with the means and materials necessary for

the purpose of setting out works and counting,

weighting and assisting in the measurement or

examination at any time and from time to time of

the work or the materials, failing which the same

may be provided by the Engineer-in-charge at the

expense of the contractor and the expense may be

deducted from any money due to the contractor

under the contract or from his security deposit or

the proceeds of sale thereof, or of a sufficient

portion thereof. The contractor shall provide all

necessary fencing and lights required to protect the

public from accident and shall also be bound to,

bear the expense of defense of every suit, action or

other legal proceeding, that may be brought by any

person for injury sustained owing to neglect of the

above precautions, and to pay any damages and

costs which may be awarded in any such suit action

or proceeding to any such person or which may

with consent of the contractor be paid for

compromising any claim by any such person.

Clause 21 A:- The contractor shall provide suitable scaffolds and

working platforms, gangways and stairways and

shall comply with the following regulations in

connections herewith -

(a) Suitable scaffoldings shall be provided for

Workmen for all works that cannot be safely

done from a ladder or by other means.

(b) A scaffold shall not be constructed, taken

down or substantially altered except.

(i) Under the supervision of a competent and

Page 100: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

100

Contractor No. of corrections Executive Engineer

responsible person and

(ii) As far as possible by competent workers

possessing adequate experience in this kind

of work.

(c) All scaffolds and appliances connected

therewith and ladders shall -

(i) Be of sound material.

(ii) Be of adequate strength having regard to the

loads and strains to which they will be

subjected, and

(iii) Be maintained in proper condition.

(d) Scaffolds shall be so constructed that no part

thereof can be displaced in consequence of

normal use.

(c) Scaffolds shall not be over-loaded and so far

as practicable the load shall be evenly

distributed.

(f) Before installing lifting gear on scaffolds

special precautions shall be taken to ensure

the strength and stability of the scaffold.

Competent person shall periodically inspect

scaffold.

(h) Before allowing a scaffold to be used by his

workmen the contractor shall, whether the

scaffold has been erected, by his workmen or

not, take steps to ensure that it complies fully

with the regulations herein specified.

(i) Working platform, gangways stairways shall

(i) Be so constructed that no part thereof

can sag unduly or unequally.

(ii) be so constructed and maintained having

regard to the prevailing conditions as to

reduce as far as practicable risks of

persons tripping or slipping and

(iii) Be kept free from any unnecessary

obstruction.

(j) In the case of working platform, gangways,

working places and stairways at the height

exceeding 3 meters (to be specified)

(i) Every working platform and every

Page 101: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

101

Contractor No. of corrections Executive Engineer

gangways shall be closely boarded unless

other adequate measures are taken to ensure

safety.

(ii) Every working platform and gangway shall

have adequate width and

(iii) Every working platform, gangway, working

place and stairway shall be suitably fenced.

(k) Every opening in the floor of a building or in

a working platform shall except for the time

and to the extent required to allow the excess

of persons or the transport or shifting of

materials be provided with suitable means to

prevent the fall of persons or materials.

(l) When persons are employed on roof where

there is a danger of talling from a height

exceeding 3 meters (To be prescribed)

suitable precautions shall be taken to prevent

the fall of persons or materials.

(m) Suitable precautions shall be taken to prevent

persons being struck by articles, which might

fall from scaffold or other working places.

(n) Safe means of access shall be provided to all

working platforms and other working places.

(o) The contractor (s) will have to make

payments to the laborers as per minimum

Wages Act.

Clause 21 B: -

The contractor shall comply with the following

regulations as regards the Hoisting Appliances to be

used by him:

(a) Hoisting machine and tackle, including their

attachments, anchorages and support shall

(i) be of good mechanical construction,

sound material and adequate strength and

free from patent defect, and

(ii) be kept in good repair and in good

working order.

(b) Every rope used in hoisting or lowering

materials or as a means of suspension shall

be of suitable quality and adequate strength

Page 102: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

102

Contractor No. of corrections Executive Engineer

and free from patent defect.

(c) Hoisting machine and tackle shall be

examined and adequately tested after erection

on the site and before re-examined in position

at intervals to be prescribed by the

Government.

(d) Every chain, ring, hook, shackle, swivel and

pulley block used in hoisting or lowering

materials or as means of suspension shall be

periodically examined.

(e) Every crane driver or foisting appliance

operator shall be properly qualified.

(f) No person who is below the age of 18 years

shall be in control of any hoisting machine,

including any scaffold which, or give signals

to the operator

(g) In the case of every hoisting machine and of

every chain, ring, hook, shackle, swivel,

pulley block used in hoisting or lowering or

as means of suspension, the safe working

load shall be ascertained by adequate means.

(h) Every hoisting machine and all gear referred

to in preceding regulation shall be plainly

marked with the safe working load.

(i) In the case of hoisting machine having a

variable safe working load, each safe

working load and the conditions under which

it is applicable shall be clearly indicated.

(j) No part of any hoisting machine or of any

gear referred to in regulation above shall be

loaded beyond the safe working load except

for the purpose of testing.

(k) Motors gearing transmissions, electric wiring

and other dangerous parts or hoisting

appliances shall be provided with efficient

safeguards.

(1) Hoisting appliances shall be provided with such

Page 103: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

103

Contractor No. of corrections Executive Engineer

means as will reduce to minimum and the risk

or the accidental decent of the load.

(m) Adequate precaution shall be taken to reduce

to a minimum the risk of any part of a

suspended load becoming accidentally

displaced.

Clause 22:-

The contractor shall not set fire to any standing

jungle, trees, brushwood or grass without a written

permission from the Executive Engineer. When

such permit is given, and also in all cases when

destroying out or dug up trees, bush wood, grass

etc. by fire the contractor shall, take the necessary

measures to prevent such fire spreading to or

otherwise damaging surrounding property. The

contractor shall make his own arrangement for

drinking water for the labour employed by him

Measure for prevention of

fire.

Clause 23:-

Compensation for all damages done intentionally or

unintentionally by contractor's labour whether in or

beyond the limits of Government property including

any damage caused by the spreading of fire

mentioned in clause 22 shall be estimated by the

Engineer-in-charge or such other officer as he may

be appointed and the estimate of the engineer-in-

charge subject to the decision of the

Superintending Engineer on appeal shall be final

and the contractor shall be bound to pay the amount

of the assessed compensation on demand, failing

which, the same will be recovered from the

contractor as damages in the manner prescribed in

clause I or deducted by the Engineer-in-charge from

any sums that may be due or become due from

the Government to the contractor under this

contract or otherwise. The contractor shall bear the

expenses of defending any action or other legal

proceeding that may be brought by any persons for

injury sustained by him owing to neglect of

precautions to prevent the spread of fire and he shall

pay any damages and cost that may be awarded by

the court in consequence.

Liability of contractor for

any damage done in or

outside work area.

Page 104: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

104

Contractor No. of corrections Executive Engineer

Clause 24: -

The employment of female labours on works in

neighborhood of soldier‟s barracks should be

avoided as far as possible. The contractor shall

employ the labor with the nearest employment

exchange.

Employment of female

labour

Clause 25: -

No work shall be done on a Sunday without the

sanction in writing of the Engineer-in-charge.

Work on Sunday

Clause 26: -

The contract shall not be assigned or sublet without

the written approval of the Engineer-in-charge. And

if the contractor shall assign or sublet his

contract, or attempt so to do, or become insolvent

or commence any proceeding to get himself

adjudicated and insolvent or make any composition

with his creditors, or attempt so to do or if bribe,

gratuity, gift, load, perquisite reward or advantage,

pecuniary or otherwise shall either directly or

indirectly be given, promised or offered by the

contractor, or any of his servants or agents to any

public officer person in the employ of Government,

in any way relating to his office or employment or

in any way relating to his officer or employment or

if any such officer or person shall become in any

way directly or indirectly interested in the contract,

the Engineer-in-charge may thereupon by notice in

writing rescind the contract, and the security deposit

of the contractor shall thereupon stand forfeited and

be absolutely at the disposal of government, and the

same consequences shall ensure if the contract had

been rescinded under clause 3 hereof and in

addition the contractor shall not be entitled to

recover or be paid for any work therefore actually

performed under the contract.

Work not to be sublet

Contract may be

rescinded and security

deposit forfeited for

subletting it without

approval or for bribing a

public office or if

contractor becomes

insolvent.

Clause 27: -

All sums payable by a contractor by way of

compensation under any of these conditions shall be

considered as a reasonable compensation to be

Sum payable by way of

compensation to be

considered as reasonable

Page 105: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

105

Contractor No. of corrections Executive Engineer

applied to the use of government without reference

to the actual loss or damage sustained, and whether

any damage has or has not been sustained.

compensation without

reference to actual loss.

Clause 28: -

In the case of tender by partners, any changes in the

constitution of a firm shall be forthwith notified by

the contractor to the Engineer-in-charge for his

information.

Changes in the

constitution of firm to be

notified.

Clause 29:-

All works to be executed under the contract shall be

executed under the direction and subject to the

approval in all respects of the Superintending

Engineer of the Circle, for the time being, who shall

be entitled to direct at what point or points and in

what manner they are to be commenced, and from

time to time carried on.

Direction and control of

the Superintending

Engineer..

Clause 30: -

Except where otherwise specified in the contract

and subject to the powers delegated to him by

Government under the Code, rules then in force, the

decision of the Superintending engineer of the

Circle for the time being shall be final conclusive,

and binding on all parties to the contract upon all

question relating to the meaning of the

specification, design, drawings, and instructions,

hereinbefore mentioned and as to the quality or

workmanship or materials used on the work, or as

to any other question, claim, right, matter, or thing

whatsoever, if any way arising out of, or relating to

the contract, designs, drawings, specifications,

estimates, quantities, instructions, orders, or these

condition, or otherwise concerning the works, or the

execution, or failure to execute the same, whether

arising, during the progress of the work, or after the

completion or abandonment thereof.

(2) The contractor may within thirty days of

receipt by him of any order passed by the

Superintending Engineer of the Circle as aforesaid

appeal against it to the Chief Engineer concerned

Decision of the

Superintending Engineer

to be final

Page 106: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

106

Contractor No. of corrections Executive Engineer

with the contract work project, provided that

(a) The accepted value of the Contract exceeds

Rs.10 Lakhs (Rs.Ten Lakhs).

(b) Amount of claim is not less than Rs.1

Lakh (Rupees One Lakh.).

(3) If the contractor is not satisfied with the order

passed by the Chief Engineer as aforesaid, the

contractor may, within thirty days of receipt by him

of any such order, appeal against it to the concerned

secretary, Water Resources Department whom, if

convinced that prima - facie the contractor's claim

rejected by Superintending Engineer Chief Engineer

is not frivolous and that there is some substance in

the claim of the contractor as would merit a detailed

examination and decision by the Standing

Committee, shall put up to the Standing Committee

at Government level for suitable decision.

Clause 31:-

The contractor shall obtain from the Water

Resources Department stores, all stores and articles

of European or American manufacture which may

be required for the work, or any part thereof or in

making up any articles required therefore in

connection therewith unless he has obtained

permission in writing from the Engineer-in-charge

to obtain such stores and articles elsewhere. The

Value of such stores and articles as may be supplied

to the contractor in his account at the rates shown in

the schedule in Form-A attached to the contract and

if they are not entered in the said schedule, they

shall be debited to him at cost price which for the

purpose of this contract shall include the cost of

carriage and all other expenses whatsoever, which

shall have been incurred in obtaining delivery of the

same at the stores aforesaid

Stores of European of

American manufacture

to be obtained from

Govt.

Clause 32:-

When the estimate on which a tender is made

includes lump sum in respect of parts of the wok,

the contractor shall be entitled to payment in respect

of the items of wok involved or the part of the work

Lump sums in estimates.

Page 107: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

107

Contractor No. of corrections Executive Engineer

in question at the same rates as are payable under

this contract for each items, or if the part of work in

question is not in the opinion of the Engineer-in-

charge capable of measurement, the Engineer-in-

charge may at his discretion pay the lump sum

amount entered in the estimate and the certificate in

writing of Engineer-in-charge shall be final and

conclusive against the contractor with regards to

any sum or sums payable to him under the provision

of this clause

Clause 33:- In the case of any class of work for which there is

no such specification as is mentioned in rule I, such

work shall be carried out in accordance with the

Divisional specifications, and in the event of there

being no Divisional specification, then in such case

the work shall be carried out in all respect in

accordance with all instructions and requirement of

the Engineer-in-charge.

Actions where no

specification

Clause 34:-

The expression 'work' or 'works' where used in

these conditions, shall unless there be something in

the subject or context repugnant to such

construction, be constructed, to mean the work or

works contracted to be executed under or in virtue

of the contract, whether temporary or permanent

and whether original altered substituted or

additional

Definition of work.

Clause 35:-

The percentage referred to in the tender shall be

deducted from/added to the gross amount of the bill

before deducting value of any stock issued.

Contractor‟s percentage

whether applied for net or

gross amount of bill.

Clause 36: -

All quarry fees, royalties, octroi dues and ground

rent for stacking materials, if any should be paid by

the contractor, which will not be reimbursed by the

Department.

Quarry fees and royalties.

Clause 37:-

Page 108: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

108

Contractor No. of corrections Executive Engineer

The contractor shall be responsible for and shall pay

any compensation to his workmen payable under

the Workmen's Compensation Act, 1923 (VII of

1923), for injuries caused to the workmen. If such

compensation is payable/paid by Government as per

the principle under Sub-section (1) of section 12 of

the said Act on behalf of the contractor, it shall be

recoverable by Government from the contractor

under sub-section 20 of the said section. Such

Compensation shall be recovered in the manner laid

down in clause 1 above.

Compensation under

workmen‟s Compensation

Act

Clause 37 A: -

The contractor shall be responsible for and shall pay

the expenses of providing medical aid to any

workmen who may suffer a bodily injury as a result

of an accident. If such expenses are incurred by

Government, the same shall be recoverable from the

contractor other remedy of forthwith and be

deducted without prejudice to any other remedy of

Government from any amount due or that may

become due to the contractor.

Clause 37 B: -

The contractor shall provide all necessary personal

safety equipment and first aid apparatus available

for the use of the persons employed on the site, and

shall maintain the same in condition suitable for

immediate use at any time and shall comply with

the following regulations in connection therewith.

(a) The workers shall be required to use the

equipment so provided by the contractor and the

contractor shall take adequate steps to ensure proper

use of the equipment by those concerned.

(b) When work is carried on in proximity to any

place Where there is a risk of drawing all

necessary equipment shall be provided and kept

ready for use and all necessary steps shall be

taken for the prompt rescue of any person in

danger.

(c) Adequate provision shall be made for prompt

first-aid treatment of all injuries likely to be

sustained during the course of the work

.

Clause 37 C :-

Page 109: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

109

Contractor No. of corrections Executive Engineer

The contractor shall duly comply with .the

provisions of the Apprentices Act, 1961 (III of

1961) the rules made there under and the orders that

may be issued from time to lime under the Act the

said rules and on his failure or neglect to do so, he

shall all be subject to all the liabilities and penalties

provided by the said Act and said Rules. (Govt.

circular No. PWD H.O. CAT-6076-3336/ (440)

Bldg.-2 dated 16/08/1985.)

Clause 38: -

(1) Quantities shown in The Tender are

approximate and no claim shall be entertained for

quantities of work executed being either more or

less than those entered in the tender or estimate.

(2) Quantities in respect of the several items shown

in the tender are approximate and no revision in the

tendered rate shall be permitted in respect of any

of the items so long as, subject to any special

provision contained in the specifications prescribing

a different percentage of permissible variation, the

quantity of the item does not exceed the tender

quantity by more than 25% and so long as the value

of the excess quantity beyond this limit at the

rate of the item specified in the tender is not

more than Rs.5000.

3) The contractor shall, if ordered in writing by the

Engineer-in-charge to do so, also carry out any

quantities in excess of the limit mentioned in sub-

clause thereof on the same conditions as and in

accordance with the specifications in the tender and

at the rates (i) derived from the rates entered in the

current schedule of rates and in the absence of

such rate, (ii) at the rate prevailing in the market,

the said rates being increased or decreased, as the

case may be by the percentage which the total

tendered amount bears to the estimated cost of the

work as put to tender based upon the schedule of

rates applicable to the year in which the tenders

were invited. For the purpose of operation of this

clause, this cost shall be taken to be Rs.

2,55,34,893/- Two Crore Fifty Five lakh Thirty

four Thousand Eight hundred Ninety Three

only

Claim for quantities

entered in the tender on

estimates.

Page 110: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

110

Contractor No. of corrections Executive Engineer

(4) Claims arising out of reduction in the tendered

quantity of any item beyond 25% will be governed

by the provision of clause 15 only when the amount

of such reduction beyond 25 percent at the rate of

the item specified in the tender is more than

Rs.5000/-.

(5) There shall be no change in the rate if the

excess in quantity is less than or equal lo 25% of

the tender quantity. Also there should be no change

in the rate if the quantity of work done is more than

125% of the tendered quantity, but the value

of the excess work at the tendered rates does not

exceeds Rs.5000/-.

(6) The quantities to be paid at tendered rate

shall include:

(a) Tendered quantity, plus

(b) 25% excess of the tendered quantity or the

excess quantity of the value of Rs.5000/- at the

tendered rates whichever is more.

(c) The clause is not applicable to extra items.

Clause 39:-

The contractor shall employ any famine, convict or

other labor of a particular kind or class if ordered in

writing to do so by the Engineer-in-charge.

Employment of famine

labor etc.

Clause 40: -

No compensation shall be allowed for any delay

caused in the starting of the work on account of

acquisition of land or in the case of clearance

works, on account of any delay in according

sanction to estimates.

Claim for compensation

for delay in starting the

work.

Clause 41:-

No compensation shall be allowed for any delay in

the execution of the work on account of water,

standing in borrow pits or compartments. The rates

are inclusive for hard or cracked soil excavation in

mud, subsoil, water standing in borrow pits and no

claim for an extra rate shall be entertained, unless

otherwise expressly specified.

Claim for compensation

for delay in execution of

the work

Clause 42:-

The contractor shall not enter upon or commence

Page 111: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

111

Contractor No. of corrections Executive Engineer

any portion of work except with the written

authority and instructions of the Engineer-in-charge

or of his subordinate in charge of the work. Failing

such authority the contractor shall have no claim to

ask for measurements for or payment for work.

Entering upon or

commencing any portion

of work

Clause 43: -

(i) No contractor shall employ any person

who is under the age of 18 years.

(ii) No contractor shall employ donkeys or other

animals with breaching of string or thin rope.

The breaching must be at least three inches

wide and should be of tape (Nawer).

(iii) No animal suffering from sores, lameness or

emaciation or which is immature shall be

employed on the work.

(iv) The Engineer-in-charge or his agent is

authorized to remove from the work any

person or animal found working which does

not satisfy these conditions and no

responsibility shall be accepted by

Government for any delay caused in the

completion of the work by such removal.

(v) The contractor will have to make

payments to the labourers as per wages

permitted by the minimum wages Act.

(vi) Contractor shall provide drinking water

facilities to the workers. Similar amenities

shall be provided to the workers engaged on

large work in urban areas.

(vii) The contractor should take precautions

against accidents, which take place on

account of labour using loose garments labor

while working near machinery.

Minimum age of person,

employment of donkeys

and/or other animals and

the payment of fair wages.

Clause 44: -

Payment to contractors shall be made by cheque

drawn on any treasury within the division

convenient to them, provided the amount exceeds

Method of payment.

Page 112: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

112

Contractor No. of corrections Executive Engineer

Rs.10/-. Amounts not exceeding Rs.10/- will be

paid in cash.

Clause 45: -

Any contractor who does not accept these

conditions shall not be allowed to tender for works.

Acceptance of conditions

compulsory before

tendering for work. Clause 46: -

If Government declares a state of scarcity or famine

to exist in any village situated within 10 miles of

the work, the contractor shall employ upon such

parts of the work, as are suitable for unskilled

labour, any person certified to him by the Executive

Engineer, or by any person to whom the Executive

Engineer may have delegated this duty in writing to

be in need of relief and shall be bound to pay to

such person wages not below the minimum which

Government may have fixed in this behalf. Any

disputes which may arise in connection with the

implementation of this clause shall be decided by

the Executive Engineer whose decision shall be

final and binding on the contractor.

Clause 47: -

The price quoted by the contractor shall not in any

case exceed the control price, if any, fixed by Govt.

or reasonable price which it is permissible for him

to charge a private purchaser for the same class and

description, the controlled prices or price

permissible under the provisions of Hoarding and

Profiteering Prevention Ordinances, 1948 as

amended from time to time if the price quoted

exceeds the controlled price or the price permissible

under Hoarding and Profiteering Prevention

Ordinance, the contractor will specifically

mention this fact in his tender along with the

reasons for quoting such higher prices. The

purchaser at his discretion will in such case exercise

the right of revising the price at any stage so as to

conform with the controlled prices as permissible

under the Hoarding and profiteering Prevention

Ordinance. This discretion will be exercised without

prejudice to any other action that may be taken

against the contractor.

Employment of scarcity

labour.

Page 113: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

113

Contractor No. of corrections Executive Engineer

Clause 48: -

The rates to be quoted by the contractor must be

inclusive of sales tax. No extra payment on this

account will be made to the contractor.

Clause 49:-

In case of materials that may remain surplus with

the contractor from those issued for the work

contracted for, the date of ascertainment of the

materials being surplus will be taken as the date of

sale for the purpose of sales tax and the sales tax

will be recovered on such sale.

Clause 50:-

The contractor shall employ at least 80% of the

total number of the unskilled labour to be employed

by him on the said work only from locally available

labor and shall give preference to those persons

enrolled under Maharashtra Government

Employment and Self Employment department's

Scheme.

Provided, however, that if the required number of

unskilled labour are not available locally, the

contractor shall in the first instant employ such

number of person as is available and thereafter may

with previous permission in writing of the

Engineer-in-charge of the said work, obtain the rest

of requirement of unskilled labour from outside the

above scheme. (Government of Maharashtra B &

C Dept. Resolution No. (CAT-1097/478/

Bldg-2 dt.23/03/1998.

Clause 51:-

Wages to be paid to the skilled and unskilled

labours engaged by the contractor

(1) A Contractor shall comply with the

provision of the Apprentice Act, 1961 and the rules

and order issued there under from time to

time, if he fails to do so, his failure will be a

breach of the contract and the Superintending

Engineer may, in his discretion, cancel the

contract. The contractor shall also be liable for any

pecuniary liability arising on account of any

violation by him of the provision of the act. The

contractor shall pay the laborers skilled and

Wearing of loose

clothes prohibition

Page 114: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

114

Contractor No. of corrections Executive Engineer

unskilled according to the prescribed wages by the

Minimum Wages Act applicable to the area in

which the work lies.

(2) The contractor to take precautions against

accidents which take place on account of using

loose garments by labours while working

near machinery.

Clause 52:-

All amounts whatsoever which the contractor is

liable to pay to the Government in connection with

the execution of the work including the amount

payable in respect of (i) materials and or stores

supplied/issued hereunder by the Government to the

contractor (ii) hire charges in respect of heavy plant,

machinery and equipment given on hire by the

Government to the contractor for execution by him

of the work and/or on which advances have been

given by the Government to the contractor shall be

deemed to be arrears of the land revenue and the

Government may without prejudice to any other

rights and remedies of the Government recover the

same from the contractor as arrears of Land

Revenue.

Clause 53: -

The contractor shall duly comply with all the

provisions of the Contract Labor (Regulation and

Abolition) Act, 1970 (Act No. 37 of 1970) and

the Maharashtra Contract Labor (Regulation and

Abolition) Rules, 1971 as amended from time to

time

and all other relevant statutes and statutory

provisions concerning payment of wages

particularly to the workmen employed by the

Contractor and working on the site of the work. In

particular the Contractor shall pay wages to each

worker employed by him on the site of the work at

the rates prescribed under the Maharashtra Contract

Labor (regulation and Abolition) Rules, 1971. If the

Contractor fails or Neglects to pay wages at the said

rates or makes short payment and Government

makes such payment of wages in full or part thereof

less paid by the Contractor as the case may be, the

amount so paid by the Government to such workers

P.W.D. No. CAT

/284(120)/Building 2

dated 14.08.83

Page 115: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

115

Contractor No. of corrections Executive Engineer

shall be deemed to be arrears of Land revenue and

the Government shall be entitled to recover the

same as such amount from the Contractor or deduct

the same from the amount payable by the

Government to the Contractor hereunder or from

any other amount payable to him by the

Government.

Clause 54: -

Th The tendered rates are inclusive of all taxes, rates

and cesses and are also inclusive of the tax

leviable tax in respect of sell by transfer of

property in goods involved in the execution of

works contract under the provision of rule 58 of

Maharashtra Value added tax Act 2005 for the

purpose of levy of tax.

M VAT TAX

Clause 55:-

(a) The anti-malaria and other health measures

shall be as directed by the Joint Director

(Malaria and Filaria) of Health Services,

Pune.

(b) The Contractor shall see that

mosquitogenic conditions are not created so

as to keep vector population to minimum

level.

(c) The Contractor shall carry out anti-malaria

measures in the area as per guidelines

prescribed under National Malaria Eradication

Programme and as directed by the Joint

Director (Malaria and Filaria) of Health

Services, Pune.

(d) In case of default in carrying out

prescribed anti-malaria measures resulting in

increase in malaria incidence, contractor shall

be liable to pay to Government the amount

spent by the Government on anti-malaria

measures to control the situation in addition to

fine.

(e) The contractor shall, make sufficient

arrangements for draining away the sewerage

water as well is water coming from the

Page 116: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

116

Contractor No. of corrections Executive Engineer

bathing and washing places and shall dispose

off this water in such a way as not to cause

any nuisance. He shall also keep the premises

clean by employing sufficient number of

sweepers. The Contractor shall comply with

rules, regulation, byelaws and directions

given from time lo time by any local or

public authority in connection with this

work "hall pay fees or charges, which are

livable on him without any extra cost to

Government. (Govt. circular No. CAT-1 086/

CR-243 /Desk/ Building 2 dt l.9.1987)

(f) In view of the difficult position regarding

availability of the foreign exchange it will not

be realized by the Department to the

purchaser of the plant and machinery require

for the execution of work contracted for.

Clause 56:-

The contractor shall make arrangements to supply

fuel for domestic use to all the labours engaged on

the site and prevent labours from cutting trees for

the purpose of fuel. Is the contractor‟s labours town

to cut the trees, the contractor shall be held

responsible for the same and should be punished as

per the provision in the Forest (Conservation) Act

1980

Supply of fuel

Clause 57:-

The contractor shall dully comply with all the

provisions of the Maharashtra State Tax on

professions and trades Callings and employment

Act 1975 [see Rule 3(2)]. The contractor shall

obtain certificate of registration under this act and

should produce the corporation/ Department the

clearance certificate as and when demanded.

Clause 58:-

Wages to be paid to the skilled and unskilled

labours engaged by the contractor. The contractor

shall pay the labours skill and unskilled according

to the wages prescribe by the minimum wages Act

1948 applicable to the area in which the work of the

contractor is located.

Clause 59:-

Page 117: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

117

Contractor No. of corrections Executive Engineer

Deduction of income tax at 2% or as applicable

from time to time of the value of the work will be

made from the contractor‟s R.A. bills and

surcharge as applicable on Income Tax will be

deducted.

Wages as per minimum

wage Act 1948

Clause 60:-

The contractor shall take out necessary Insurance

Policy/ policies so as to provide adequate insurance

cover for execution of the awarded contract from

the Director of Insurance, Maharashtra , Mumbai

400051 only.

Its postal address for correspondence is „264,

MHADA, Opp. Kalanagar, Bandra, Mumbai-

400051. ( Tel. No. 26438403, Fax No.

26438461/26438690). Insurance policy/policies

taken out t\from any other company will not be

accepted. However, the contractor desire to effect

insurance with the local office of any insurance

company, the same should be under the Co-

Insurance the policy taken out by the contractor is

on Co-Insurance basis ( G.I.F. 60% and Insurance

Company 40% ) the same will be accepted and the

amount of premium calculated by the Director of

Insurance will be recovered directly from the

amount payable to the contractors for the executed

contract work which may be noted.

Condition relating to

Insurance

Clause 61:-

The successful tendered shall produce to the

construction of Competent authority accepting the

tender in a valid and current license issued in his

favour under the provision of contract labour

(Resolution and Abolition) Act 1970 and

Maharashtra Contract (Resolution & Abolition) Act

1971 before signing the contract. On failure to do

so the acceptance of additional earnest money

deposited if any will be forfeited to Irrigation

Department / Corporation.

Labour Contract

Page 118: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

118

Contractor No. of corrections Executive Engineer

Clause 62:-

The workers welfare cess 1% will be recovered

from the bill as per Govt. Marathi GR No.

BCA/2009/pra.No.108/Kamgar-7 (A) dated

17/06/2010.

Page 119: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

119

Contractor No. of corrections Executive Engineer

SCHEDULE “A” SCHEDULE OF MATERIALS

Name of Work :- Renovation bund work of Annapurna Kharland scheme Tal Roha Dist.

Raigad.@ ch. 0 m.to 3540 m. & Sluice Gate @ Ch. 960 m., 2100 m. & 3540 m.

Schedule showing (approximately) the materials from the stores for the work

contracted to be executed and the rates at which they are to be charged for:

Sr.No

Particulars

Quantity

(Approximately)

Required

Unit Rate

in Rs.

Remarks

NIL

Page 120: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

120

Contractor No. of corrections Executive Engineer

Page 121: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

121

Contractor No. of corrections Executive Engineer

SCHEDULE “B”

Renovation bund work of Annapurna Kharland scheme Tal Roha Dist. Raigad.@ ch. 0 m. to 3540 m. & Sluice Gate @ Ch. 960 m., 2100 m. & 3540 m.

Sr.

No.

Quantity

Estimated (may be

more or less)

Item of Work Estimated Rates Unit Total Amount

according to

Estimated

Quantities In Figure In Word

1 57984.36 Item No.1:- Cleaning and removing grass

bushes and shrubs etc. stacking the stuffs

up for all leads and lifts, etc. complete.

4.70 Rs. Four and paisa seventy

only.

Square Meter. 272526.49

2 Item No.2:- Excavation in soil / soft

murum / lime shadu exceeding 1.50 m. in

width including depositing the material as

directed for all leads and lifts including

dressing etc. complete.

7357.69

For “C” Work 49.15 Rs. Forty nine and paisa

fifteen only.

Cubic Meter. 361630.46

1398.72 For F.R.H.T. Works 129.40 Rs. One hundred twenty nine

and paisa forty only.

Cubic Meter. 180994.37

3 Item No.3 :- Constructing embankment for

Hearting Zone with selected material from

barrow area including transporting the

material with leads of 15 m. and lifts upto

1.50 m. laying in layers, leveling,

spreading, breaking clods including

watering etc. complete.

45281.16 For “C” Work (Wet condition) 155.10 Rs. One hundred Fifty five

and paisa ten only.

Cubic Meter. 7023107.92

Page 122: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

122

Contractor No. of corrections Executive Engineer

4.

Item No.4 :- Constructing embankment for

Hearting Zone with selected material from

barrow area including transporting the

material with leads of 15 m. and lifts upto

1.50 m. laying in layers, leveling,

spreading, breaking clods including

watering etc. complete.

19406.21 For “C” Work (\dry condition) 169.25 Rs. One hundred sixty nine

and paisa twenty five only.

Cubic Meter 3284501.04

7690.90 For F.R.H.T. Works 159.20 Rs. One hundred fifty nine

and paisa twenty only.

Cubic Meter 1224391.28

5 6563.09 Item No. 5 :- Constructing embankment

for Casing Zone with selected material

from borrow area including transporting the

material with all leads & lifts laying in

layers, leveling and dressing the bank work

including watering etc complete.

198.80 Rs. One hundred ninety eight

and paisa eighty only.

Cubic Meter. 1304742.29

6 Item No. 6 :- Providing and laying dry

stone pitching 20 CM thick to side slopes

embankment including dressing the bank

work with all leads and lifts, etc. complete.

24543.85 A) from borrow area 133.10 Rs. One hundred thirty three

and paisa ten only.

Square Meter. 3266786.44

10518.80 B) From Available material 50.85 Rs. Fifty and paisa eighty five

only.

Square Meter. 534880.98

7 67.50 Item No.7 :- Providing & constructing

down stream rock toe with 15 to 23 cm.

rubble stone of approved quality from

borrow area with hand packing including

all leads and lifts.

469.95 Rs. Four hundred sixty nine

and paisa ninety five only.

Cubic Meter. 31721.63

Page 123: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

123

Contractor No. of corrections Executive Engineer

8 113.83 Item No.8:- Providing and laying in situ of

grade M - 200 (1:1.5:3) controlled

reinforced cement Concrete of trap metal

for raft slab etc. including "V" haunches

form work, scaffolding, compaction by

vibrating,finishing curing etc.& Centering

(excluding dewatering by means of pumps)

including complete( Upto 5 m height)-

excluding reinforcement.

418.90 Rs. Four hundred eighteen

and paisa ninety only.

Cubic Meter. 47683.39

9 186.70 Item No.9- Dismantling carefully the

existing structure of stone masonry in

cement or Lime Morter, including sorting

out serviceable materials and stacking the

dismantled material with all lead and lifts

neatly as directed etc. complete.

339.35 Rs. Three hundred thirty nine

and paisa thirty five only.

Cubic Meter 63356.65

10 28400.00 Item No.10:- Dewatering for Abutment,

Returns, Piers, Raft, Cut of walls, Toe wall,

Apron in perennial river or stream

including diversion of stream providing

coffer dams, bunds etc. as may be

necessary for foundation and other parts of

work and bailing out and / or pumping out

water below the actual initial natural water

level during execution of all item of

construction as required (from start of that

particular component till completion of

bridge) including all leads and lifts etc.

complete.

18.90 Rs. Eighteen and paisa ninety

only.

Cubic Meter 536760.00

11 1334.50 Item No.11:- Providing rubble of trap/

granite/ quartzite/ gneiss stone of approved

quality in foundation including hand

packing filling gravel of sand in the voids

etc. complete.

616.55 Rs. Six hundred sixteen and

paisa fifty five only.

Cubic Meter. 822785.98

12 71.60 Item No.12:- Providing and laying in situ

PCCM-15 cement concrete of trap/ granite/ 4114.30 Rs. Four thousand one

hundred fourteen and paisa

Cubic Meter. 294583.88

Page 124: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

124

Contractor No. of corrections Executive Engineer

quartzite/ gneiss metal in foundation,

including necessary bailing out water,

compacting and curing, (excluding

dewatering by pump).

thirty only.

13 190.94 Item No.13 - Providing and laying in situ

R.C.C.M-20 controlled reinforced cement

concrete of trap metal for raft slab

including ''v'' haunches, formwork,

scaffolding, compaction by vibrating,

finishing curing, etc. complete. (Excluding

reinforcement )

5252.90 Rs. Five thousand two

hundred fifty two only and

paisa ninety only.

Cubic Meter. 1002988.73

14 163.57 Item No.14:- Providing & laying in situ

R.C.C. M-20 cement concrete of trap/

granite/ quartzite/ gneiss metal for cast in

citu R.C.C. solid piers, column etc.

including provision of "V" shaped false

joints to form suitable panels on the faces

to approve design with compacting by

vibrating and curing complete, including

formwork centering (excluding dewatering

by means of pump) and including bailing

out water and curing, (upto 5.00 m. height

) ( Excluding reinforcement)

5144.20 Rs. Five thousand one

hundred forty four and paisa

twenty only.

Cubic Meter. 841436.79

15 8.10 Iten No. 15:- Providing and cutting

bending, hooking, laying in position and

laying HYSD bars for reinforcement as per

detailed drawings for R.C.C. work

6584.90 Rs. Six thousand five hundred

eighty four and paisa ninety

only.

Cubic meter 53337.69

16 31.73 Item No.16 :- Providing and cutting

bending, hooking, laying in position and

tying HYSD bars for reinforcement as per

detailed drawings for R.C.C. work.

64261.40 Rs. Sixty four thousand two

hundred sixty one and paisa

forty only.

M.T. 2039014.22

17 31.73 Item No.17 :- providing & applying

anticorrosive treatment for MS & TOR

steel reinforcement as per cement polymer

composite coating (CPCC) method

8555.40 Rs. Eight thousand five

hundred fifty five and paisa

forty only.

Cubic Meter 271462.84

Page 125: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

125

Contractor No. of corrections Executive Engineer

developed by CECRI including cleanihg

the bar by means of any established

mechanical or manual method for removing

the rust and deletious matter,applying rapid

setting primer and cement polymer sealing

coat of approved and licensed by CECRI

including redoing the process if damaged

occur during handling stacking

etc.complete as directed by the Engineer in

charge (With prior approval of S.E. is

essential)

18 25.50 Item No.18 :- Providing & fixing

polipropelyne glass lined

F.R.P.Rectangular gate Including fixing

with a - lead of 15 m. and lift 1.5 m. etc

28476.55 Rs. Twenty eight thousand

four hundred seventy six and

paisa fifty five only.

Square Meter. 726152.03

19 1920.00 Item No.19 :- Providing and laying dry

stone masonry (Groyness) excluding

pointing etc. complete.

703.15 Rs. Seven hundred three and

paisa fifteen only.

Cubic Meter 1350048.00

Total Rs……… 2,55,34,893.10

Say Rs…………………………… 2,55,34,893/-

Page 126: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

126

Contractor No. of corrections Executive Engineer

GENERAL SPECIFICATIONS

1. DEFINITION:

1.1 Soft - Strata This shall include all kinds of rock or shale, indurate clay, soil, silt, sand and

gravel, soft and hard murrum and any other material which can best be

removed with a shovel after loosening with a pick and/or bar. It shall also

include isolated boulders upto 0.1 cubic meter each which do not need

blasting and could be removed with a pick, bar and shovel.

At the change of the strata the contractor shall inform the Department in

writing before proceeding work of excavation in hard strata. The

Engineer-in-charge may their upon cause to take levels of finished

excavation in the soft strata. Safety of excavation: Before any work of excavation for foundation is taken upon all loose rock

sand, semidetached rock, it or close to the area to be excavated that is liable to

fall or otherwise endanger the workmen on the project shall be stripped. The

methods employed shall be such that it will not shatter any rock that was

originally sound or any soft material not requiring removal, as contemplated

therein, but which may later become loosened or unstable shall be promptly

and satisfactorily removed. The cost of such clearing shall be deemed to

have been included in the unit rates accepted under the different item of

excavation and upto pay lines. Shoring and strutting slopes:-

Maintenance of excavation slopes:-

Any shoring and strutting required during construction shall be deemed to be

covered by the rates quoted for the items. The contractor shall be responsible for the accuracy of the excavated slopes.

If in any particular locations, the contractor considers it necessary in

the interest of safety to provide berms he shall forthwith bring the same to

the notice of the Engineer-in-charge by prior written order, which will be

paid for at the rates accepted for the particular class of material. Slips Every precaution shall be taken to prevent slips. But should slips occur, the

slipped material shall be removed to slopes as directed. No

compensation shall be paid to the contractor because of mishaps arising out

of slips.

Page 127: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

127

Contractor No. of corrections Executive Engineer

1.2 Hard Strata: This includes all rock occurring in masses which could best be removed by

blasting where such blasting is permissible. It shall also include rock which

owing to the proximity of buildings and for any other reasons has to be cut by

means of chisel or wedges. It shall also include boulders in mass or isolated

boulders over 0.1 cubic meter each which require blasting or wedging and

breaking for easy removal.

2.0 Slopes admissible for various strata 2.1 Soft Strata:

The slopes allowable in this strata will be ½ : 1 (horizontal

: Vertical) side of cut will be governed by requirements of stability.

2.2 Hard Strata: The slopes allowable in this strata for the sides are 1/8 : 1 (Horizontal

: Vertical) for payment of this strata.

3.0 General specifications for excavation: 3.1 Clearing Site:

Unless otherwise explicitly provided for the item of clearing site as given

below will be considered as included in the item of the excavation. 3.2 Removal of Rubbish: The area to be occupied by the bund and its appurtenant work etc. shall be

cleared of all trees, roots stumps, decayed timber bush rubbish and all other

objectionable materials. Trees and dismantled material shall be the property

of the Government.

All trees fallen and all materials from dismantled structure shall be the

property of the Government and shall be stacked in a suitable place as

directed by the Engineer-in-charge or his representative. 3.3 Disposal of waste materials:

Waste material from bunds site decided as such by the Engineer-in- charge

obtained from clearing operation or excavation shall be burnt or removed

immediately and deposited in the upstream at such places and in the manner

directed by the Engineer-in-charge in order to avoid unsightly appearance.

Page 128: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

128

Contractor No. of corrections Executive Engineer

4.0 Stone 4.1 Quality:

All stones used on the work under these specifications shall be obtained from

quarries approved by the Engineer-in-charge. The stone shall be sound,

tough and of durable quality and shall be free from decays and holes, vein,

flaws, cracks or other defects. 4.2 Size:

The dimensions of the stones to be used shall not be less than 20 to 25 cms.

On any face. Only stones weighing between 25 to 50 kgs. Shall be allowed to

be used. 4.3 Test for good stones: While approving any quarry for stone besides satisfyingthe

specification mentioned in paras above it shall be seen that the stone

obtained shall be such as will not absorb water more than 1 % of its own dry

weight after keeping it under water for 24 hours.

Laterite stone should be compact in texture streaked colours prevailing it

should not be very unevenly distributed. Those types in which white clay

occurs should not be used. Laterite stones exposed to weather to harden for a

considerable time should be preferred. It should not be used where subject to

great pressure and liable to be soaked with water. 5.0 Sand 5.1 Source and Size:

Sand used for mortar shall be either natural river sand, creek sand or crushed

trapped stone or mixtures of both in specified proportion. The maximum

size be limited to 5 mm. 5.2 Quality:

The sand shall consist of hard, dense, durable, uncoated siliceous gritty

materials obtained from rock fragments. It shall be free from injurious

amounts of dust, lumps, soft and flaky particles, shale‟s, alkali, organic

matter, loam, mica and other deleterious substances. The maximum

percentage of deleterious substances in the sand as delivered for use in

mortar shall not exceed the following values.

Percentage of Weight: Materials passing No. 200 sieve B.S. or I.S.No.8 4 %

Page 129: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

129

Contractor No. of corrections Executive Engineer

average opening 0.0029

Shale 1 %

Clay Lumps 1 %

Coal 1 %

Total of other deleterious substances such as 2 %

alkali, mica coated grains, soft and flaky

particles.

The sum of the percentage of all deleterious substances shall not exceed

5 % by weight. The sand shall free from injurious amounts of organic

impurities. Sand producing of colour darker than the standard in

colorimetric test for organic impurities shall be rejected.

5.3 Mechanical Analysis: The sand shall be well graded and the sieve analysis shall conform to the

following limits of gradation.

Sieve No.

A.S.T.M

Equivalent

I.S.S

Cumulative

percentage by

weight retained on

sieve 3

/

8

3/8 Nil

4 480 0 to 8

8 240 10 to 25

1

6

120 25 to 45

3

0

60 50 to 70

5

0

30 75 to 90

1

0

0

13 90 to 97

5.4 Fineness Modulus

The sand shall have fineness modulus ranging between 2.60 and 3.00. The modulus shall be computed by adding cumulative percentage of sand retained on the 6th

standard screens from No. 4 to No. 100 both inclusive

(A.S.T.M. standard) or (480, 240, 120, 60, 30 and 15 sieves of the I.S. Designation) and dividing the sum by 100. Any deviation from the specification in respect of the gradation and the fineness modulus shall not be permitted without the permission of the Engineer-in-charge.

6.0 Mix Variation:

In case the ratio of cement to total aggregate is modified by changing the

cement under specific orders of the Executive Engineer-in-charge. The

Page 130: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

130

Contractor No. of corrections Executive Engineer

contractor shall be paid increased or reduced rate according to the

variation in the cost of cement resulting from change in mix proportion,

calculated as per table given below. The variation in cost of cement will be calculated according to the rate of

cement as specified in the schedule „A‟ and the change in the

requirements of cement by weight per cubic meter volume of concrete as

determined by the following table.

VARIOUS GRADES OF CEMENT CONCRETE

Class

Nominal

Mix

Grade

Of equival

ent

L.S.S. mix

Cement

contents in

kg/cum.

(bags)

Maximum

size of

aggregate

in mm.

lump in

mm.

Stipulated Strength in 15

cm. cube

Indicative

probable

location foe

use.

Preliminary

test of

28 days

kg/sq.c m

Work

test of

7 days

kg/sq.

cm

Work

test of

28 days

kg/sq.c m

1 2 3 4 5 6 7 8 9

1:2:4 M-150 380 (7.6) 20 200 100 150

1:2:4 M-150 -- 40 200 100 150

1:3:6 M-100 235.5

(4.71)

40 100 100 100

7.0 Slump Test for concrete:

In order to test the consistency of the mixed concrete, slump test shall have

to be taken by contractor when required by the Engineer-in-charge and as per

the Indian Standard Specifications. The allowable slump shall be decided by

the Engineer-in-charge, depending upon the location of the concrete. 8.0 Cement:

Cement obtained by the contractor shall confirm to specification by the

I.S.Institute (Vide their Sp.No.I.S. 8112 of 1989 for Portland cement) 9.0 Water: 9.1 Quality:

Water used for making mortar or curing shall be of potable grade and

reasonably clean and free from objectionable quantities of silt, organic

matter, alkali, salts and other injurious materials.

Page 131: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

131

Contractor No. of corrections Executive Engineer

9.2 Turbidity permissible:

The turbidity of water for mixing mortar shall not be more than 50 part per

million and shall preferably be as low as possible. 10.0 Mortar General: 10.1 Mode of mixing:

Mortar shall be obtained by thoroughly mixing in mechanically worked mixer

or mills, the constituents being in the specified proportions. If the mortar

mixing by manual labour is permitted by the Engineer-in-charge. T shall be

mixed only on large size M.S. Sheets and after taking precautions

against contamination with foreign materials. 10.2 Specification for ingredients:

It shall be seen that the ingredients going from finished product of mortar

comply individually with the specification separately laid out for each of

them. 10.3 Time for use:

Mortar shall be used in masonry within the time specified for the initial set or

as directed in the detailed specifications. 10.4 Proportions of ingredients:

The Proportions of ingredients mentioned in the schedule „B‟ for each type

of mortar are proportions for only the nominal mixes. The criteria governing

the mix will be the strengths specified and the actual proportions of

the ingredients to give the requisite strength shall be determined by

experiments. 10.5 Strength:

The minimum compressive strength of mortar used in any part of

masonry shall not less than 53.5 kg/sq.cm and that in tension not less than

10.7 kg/sq.cm at the end of 28 days in the case of cement mortar. 11.0 Coarse Aggregate:

11.1 Coarse Aggregate for concrete shall consist of hard, dense, durable

uncoated, crushed rock and shall be free from injurious amounts of soft

feeble, thin elongated or laminated pieces, alkali, organic matter or other

deleterious substances. Flakey and weathered stones shall not be used.

Aggregate shall be tested in accordance with teat prescribed in I.S.516-

59 and 1299-59 or subsequent revision. Use of gravel fraction left

behind after sieving river sand shall be permitted in the blending of coarse

aggregate if asked for after suitable experiments and without any variation in

rates.

Page 132: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

132

Contractor No. of corrections Executive Engineer

11.2 Impurities: The broken stone or metal shall be free from dust and dirt shall be washed

if necessary to ensure all faces of the stones are perfectly clean. The

maximum percentage of deleterious substances in any size of coarse aggregate

shall not exceed the following value. Materials passing through: No. 100 screen (ASTM) One percent by weight

Shale One percent by weight

Coal One percent by weight

Soft fragments One percent by weight

Clay lumps One fourth percent by weight

Other deleterious substances One percent by weight

The sum of the percentages by weight of all deleterious substances of any

size shall not exceed five. 11.3 GRADING

(a) The approximate range in grading of coarse aggregate is as under.

Maximum

size of

aggregate

nominal

range mm

Percentage of Coarse Aggregate fraction

20 to 40 5 to 20 10 to 20 5 to 10

20 mm 10 to 20 100 55 to 67 33 to 45

40 mm 20 to 40 40 to 50 50 to 60 23 to 40 18 to 30

(b) The coarse aggregate shall be of such a size as shall be retained on a mesh

5 mm square.

(c) The grading between the limit specified above shall be such that it shall

produce a dense concrete of the specified proportions and consistency that

will work readily into position without segregation and without the use of

excessive water content.

11.4 Stacking: The aggregate of different size shall be such that it shall be stacked

separately and bundled in such a manner as to prevent inter mixing of

different size of aggregates, required separately for grading purposes. No

foreign matter will be allowed to be mixed up in the aggregate. If covered

with dust etc. they shall be washed cleaned before use.

Page 133: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

133

Contractor No. of corrections Executive Engineer

12.0 Forms:

12.1 Forms to confine the concrete and shape in the required lines be used

wherever necessary. The forms shall have sufficient strength and

rigidity to hold concrete and withstand the pressure of ramming and

vibration within permissible deflections from the prescribed lines, when the

concrete is vibrated.

The surface of all forms in concrete shall be clean, rigid, water tight and

smooth. Suitable devices shall be used to hold corners adjustment end and

edges of panels of other forms together in accurate alignment.

Forms to be used more than once shall be maintained in serviceable

condition and shall be thoroughly cleaned and smooth before being

reused. Where metal sheets are used for lining forms, the sheets shall be

placed and maintained on the forms with the minimum amount or

wrinkles. Humps or other imperfections. The use of sheet metal to

correct surface that will be permanently exposed to view shall not be

permitted. All forms shall be checked for shape and strength before reuse

by Engineer-in-charge or his representative.

12.2 Erection and removal of forms: Before placing concrete the surface of all forms be oiled with suitable non

staining oil such as raw linseed oil so as to prevent sticking of concrete and

facilitate the removal of forms for use on wood form. The oil should be

capable of penetrating the wood forms and of remaining sufficiently oily to

eliminate sticking of and preventing absorption of water and consequent

warping. The oil shall cover the form fully and evenly without excess or drip. Care

shall be taken to prevent oil from getting to the surface of

construction joints and on reinforcement bars. Special care shall be taken

into account thoroughly of the form stripes for narrow grooves so as to

prevent swelling of the forms. Immediately before concrete is placed,

precautions shall be taken to see that all forms are in proper alignment and

that, angles and tees are thoroughly secure and tight. Where forms for

continuous surface are placed in successive units the form shall fit tightly

over the completed surface so as to prevent leakages of mortar from the

concrete and to maintain accurate alignment of surface.

12.3 Removal of Form: Removal of form shall never be started until the concrete thoroughly sets

and harden adequately to carry its own weight, besides their live load which

is likely to come on the work during construction. The length of time for

which the forms remain in place shall be decided by the Engineer-in-charge

with reference to weather conditions, shape and position of the structure or

Page 134: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

134

Contractor No. of corrections Executive Engineer

structural member and the nature and amount of dead and live loads. In

normal circumstances, form shall be struck after the expiry of the following

periods.

A) Beam sides wall columns (Un loaded) 72 Hrs.

B) Slabs and arches (Props left under) 4 days

C) Props to slabs and arches 10 days

D) Beam soffit (Props left under) 1 day

E) Props to Beams 21 days

F) Lean concrete (Side) 2 days

In no case shall forms be removed until there is assurance that removal can be

accomplished without damaging the concrete surface. No load will be

allowed to damage concrete surface. Heavy load shall not be permitted until

after the concrete reaches its designed strength. The form shall be removed

with great caution and without injuring the structure or throwing heavy

forms upon the floor.

13.0 Classification of form work:

Straight and Plane :

This category shall include which can be formed by use of plain panels. Curved in one direction :

This category shall include which can be formed by use of straight

planks or battens for works such as roof of gallery or pier cut water. Curve in more than one direction :

This category shall include such curved surfaces as cannot be included

in category above.

14.0 Steel for reinforcement:

Tor steel reinforcement bars for R.C.C work shall confirm to I.S. 432 :

960 and shall be of tested quality. All the reinforcement shall be clean and free

from dirt, oil paint, grease, mill scale or loose or thick rust at the time of

placing. 14.1 Scope of work: This item covers providing, handing, storing, cleaning, cutting, bending,

placing and / or erecting in position, securing and maintaining in position all

Page 135: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

135

Contractor No. of corrections Executive Engineer

reinforcement and anchoring bars and reinforcement fabric till concrete is

placed around it. It also includes placing of the bars as shown on the

drawings or as required by the Engineer-in-charge and providing the hooks at

the ends. It includes the cost of furnishing and attaching wire, ties and

chairs, metal supports etc. The rate is inclusive of the splitting and welding

required at the end of anchor bar, if required. It also includes welding of

reinforcing bars where directed or permitted by the Engineer-in-charge.

14.2 Supply:

The reinforcing steel shall be supplied by the contractor. 14.3 Bar Bending Schedule: The department will indicate the design requirements of reinforcement steel

for the different components. The contractor shall prepare the bar bending

schedule from those design statements showing the details of bends, cracks

and splices provided by him for all the bars to be placed and get them

approved from the Engineer-in-charge. The

schedule shall be presented for approval well in advance of the laying of

the reinforcement. 14.4 Cleaning :-

Before steel reinforcement is placed in position the surface of these

reinforcement bars shall be cleaned of rust scale, dirt, grease or other

objectionable deleterious foreign substances, heavy flaky rust and mill scale

that can be removed by firm rubbing with burlap or equivalent treatment.

The fact that early stage rust has no detrimental effect on

bond hence could be disregarded shall not be accepted an excuse for careless

handling and storages of steel.

14.5 Distance between Reinforcement bars :-

14.5.1 The distance between two parallel reinforcement bars shall be extended as

provided below in 5.2 not less than the greatest of the following distances. a) The dia of the either bar if their diameters be equal.

b) The dia of the larger bar if the diameters be unequal and

c) 6 mm more than larger bar if the diameters be unequal

aggregate comprised in such concrete.

A greater distance should however be provided when convenient.

14.5.2 The vertical distance between two horizontal main steel reinforcement of the

corresponding distance at right angles to two inclined main steel

reinforcements shall be not less than 12 mm except at a splice or lap and

except where one of each reinforcement and transverse to the other.

14.5.3 The pitch of the main bars in a reinforced concrete solid slab shall be not

Page 136: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

136

Contractor No. of corrections Executive Engineer

more than three times the effective depth of such slab. The pitch of the

distribution bars in a reinforced concrete solid slab shall be not more than

four times the effective depth of such slab.

14.5.4 Concrete Cover:- Sufficient concrete cover shall be provided to protect reinforcement from

corrosion or as indicated in the drawings.

All protruding bars from concrete to which other bars are to be spliced and

which will be exposed to action of weather for an indefinite period shall be

protected from rusting by a thin coat of neat cement grout. The thickness of concrete cover (Exclusive of plaster or other

decorative finish) shall be 50 mm at faces and 75 mm at ends.

15.0 ADDITIONAL IMPORTANT POINTS FOR ATTENTION:

15.1 Before the reinforcement bars are fixed in position it shall be verified as to

whether they are of specified sizes and are cut and bent in accordance

with the relevant drawing and specification. For

mistake the contractor is liable for all rectification of mistakes at his risks

and costs. 15.2 Reinforcement bars shall be accurately placed and secured in position by

means of build in concrete blocks, metallic chairs, hangers, spacers or other

suitably approved devices at sufficiently closed intervals so that they will

not sag between supports and shall not be displaced during the placing of

concrete or any operation of the work. 15.3 Before starting concreting the contractor shall make certain that the

measurement of reinforcement placed have been recorded by the

authorized representative of the department and that the Engineer-in- charge

certifies to the correctness of reinforcement use. Engineer-in-charge at

discretion may order dismantling and reconstruction of the work where

necessary. Engineer-in-charge or his authorized representative shall record the

fact of his having checked and approved the reinforcement in work order

book kept on work before allowing concreting to commerce. STEEL:- Reinforcing bars and rods (of mild Steel or round steel) 6 mm or higher in

diameter shall be obtained by the contractor. The bars and rods shall be obtained according to the standard size. The contractor shall make suitable arrangements for storage of steel and

the Executive Engineer or his representative shall have the authority at

all times to inspect the storage arrangements and to suggest modifications and

improvements if any, and the contractor shall comply with the same.

Page 137: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

137

Contractor No. of corrections Executive Engineer

The storing arrangements shall be such as to afford convenience of the

inspection and check of material bars of the size, length, shape and grade

shall be assembled in stacks and marked distinctly.

The contractor shall at all times maintain proper records showing the basis

of indents the receipts and utilization of the steel and these shall at all times be

open for inspection by the Engineer and his authorized representative.

Tables of Weight

Table No.1 (Torsteel weight as per ISI-9 Bars)

Section Rolled in Metric System Diameter of Bar in mm

Weight in Kg. Per Meter

6

0.2

22

8

0.3

95

1

0

0.6

17

1

2

0.8

88

1

4

1.2

10

1

6

1.5

80

1

8

2.0

00

2

0

2.4

70

2

2

2.9

80

2

5

3.8

50

2

8

4.8

3

3

2

6.3

10

Page 138: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

138

Contractor No. of corrections Executive Engineer

DETAILED ITEMWISE SPECIFICATIONS

Item No. 1:

Clearing and removing grass, bushes and shrubs etc. stacking the stuff with all leads

and lifts etc. complete. General This item provides for clearing the area required for construction of earthen bund as

shown in the drawing. This item includes all tools, materials and labour required for

satisfactory completion of item as directed by the Engineer-in-charge or his

representative. Materials : The rate of this item shall include the cost of all necessary materials required for carrying

out the item. Method of execution : The seat of bund or the area to be cleared shall be properly marked at site with

reference to centre line of bund. All objectionable vegetation including bushes, trees

stumps etc. shall be removed and to be dumped on the sea side of the bund at least 15

meter away from the working area. However the contractor shall not remove or

damage existing mangrove trees in the working area. The contractor shall not sell

the vegetation which is cleared by the contractor. All necessary precautions shall

be taken to protect the persons working on such work and should not damage any

private or government properties nearby. The contractor shall be held responsible for

its compensation, if any, arises thereon.

Mode of measurement and payment : The contract rate shall be for one square meter of area cleared restricted to the design

dimension shown in the drawing. The payment for this item will be made in the

final bill, only after completion of all other items of embankment included in the

tender. If all the items in the tender are not executed fully, the payment for this

item will not be released.

Item No. 2:- Excavation in soil/soft murum/lime shadu exceeding 1.5 m. in width including

depositing the material as directed with all leads and lifts including dressing etc.

complete.

General :- The excavation of Kharlands works consists of excavation for foundation to required

grade, line, levels etc, as per the section shown on the drawing, finishing the

surface and removal of excavated material to the place as directed by the

Engineer-in- charge or his representative. He has to provide all labours,

Page 139: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

139

Contractor No. of corrections Executive Engineer

materials, equipments and tools required for completion of the work including

clearing the site of work. The item also consist the cost for back filling unless

otherwise specified separately. Materials :- The contractor has to provide all materials such as lime string, pegs, nails, bamboo,

stones, mortar and concrete required for marking Bench marks or other reference

marks. Method of Execution :- The ground levels shall be taken at suitable intervals considering site condition and

nature of work, in the presence of contractor or his authorized representative. Before

start of the excavation field books/drawing etc. showing details are required to be

signed by the contractor/authorized representative. The excavation and disposal is to

be planned so that it will not obstruct stacking of construction material and pumping

devices. The excavated material shall be dumped sufficiently clear of edges of

excavation, so as not to endanger stability of slopes of the excavation. Any shoring

and strutting required during construction shall be deemed to be covered by the

rates quoted for the items and no extra claims will be entertained. If the excavation is

done below the specified level or outside the section, it will not be paid to contractor. The contractor in such cases of over cuts will be required to fill up the same at his own

cost with approved materials as directed by Engineer-in-charge or his

representative. The classification of the stratas will be done as indicated in para 1.1 of the general

specification. The back filling shall be done after concrete or masonry is fully set and as per

directions of Engineer-in-charge or his representative.

Mode of Measurements and Payment :- The quantity of items shall be computed from the cross sectional areas by the

trapezoidal formula and contract rate shall be for the unit of one cubic meter for the

strata classified by the competent authorities. No payment will be made till the

construction of structure raises above ground level.

Item No. 3 & 4:- Constructing embankment for Hearting Zone with selected material with

contractor‟s own material from borrow area including transporting the

material with all leads and lifts laying in even layers breaking clods, spreading,

levelling, and dressing to the required section including watering etc. complete.

(wet Condition)

General :-

After clearing the site, the toes of bund will be demarcated on ground on the

basis of cross-sections. For this, levels will be taken at regular interval of 30 meter

or at closer interval depending upon the topography of the site. If the contractor or

Page 140: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

140

Contractor No. of corrections Executive Engineer

his representative fails to remain present during taking levels, the levels taken by the

field staff of the Department will be treated as final and binding on the contractor. The

item includes quarrying, transporting and spreading the suitable material from the

borrow pits in uniform layer as directed. This item includes all tools and

equipments, materials and labour required for satisfactory completion of item as

directed by the Engineer-in-charge or his representative. Clearing borrows pit areas : All area required for borrow pits for selected material (marine clay) shall be selected

that felling of existing mangroves is not necessitated. However it should be cleared of

all stumps, routs and other objectionable materials, etc. particular care shall be taken

that all organic matter shall be excluded from the material which is to be placed in the

bund embankment. The cleared area shall be maintained free of vegetation growth

during the progress of work without any extra payment. The borrow pit shall be stripped to depth, necessary to obtain material of the desired

quality where borrow pits are opened adjacent to the bunds, the edge of the excavation

shall not approach the toe of the bund closer than 5 m. as directed by Engineer-in-

charge. Borrow pits shall be so selected that required materials will be furnished as

close as practicable to the point of utilization and so that they will not interfere with

location of permanent structure not the usefulness of appearance of any of the

work. The formation of pools shall be avoided and all borrow pits shall be drained

as necessary by ditches to the nearest nallas. All pits shall be arranged with certain amount of regularity having regard to the

convenience of the work during the excavation and to its safety and appearance of finished

after its completion. Temporary quarry roads leading to and from the respective

borrow areas to the site of the embankment where the material are required to be

deposited shall be constructed and maintained by the contractor at his own expenses

with permission of and as directed by Engineer-in-charge. The borrow pit material shall be got classified by the Engineer-in-charge with regard

to its suitability for bund. During construction, contractor may after careful testing with specific permission

of the Executive Engineer bring suitable material from the areas other than those

indicated in borrow area plan. No extra payment would however be admissible on

this account. For the guidance of the contractor, quarries will be shown at site if desired. The data

presented therein are to be taken only as a guidance and no claims shall be

entertained in future due to lack of conformity between the nature of materials

actually met with during construction and that indicated in the borrow area plan. The

contractor is expected to have his own prospects carried out before tendering for the

work. During construction the contractor, may after careful prospecting and with

specific written approval of the Executive Engineer, bring suitable material from areas

other than those in the borrow area shown. No extra payment would however be

admissible on this account.

Page 141: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

141

Contractor No. of corrections Executive Engineer

Method of Execution : The materials obtained from borrow area at distance at least 5 m. from toe line and

shall be laid as per line out approved by the Engineer-in-charge or his

representative. Considering the local factor site conditions and tide level etc., the

laying of hearting material should be done in layers. Clods should be broken and

manual kneading tampering by earth master rammer or timber mallet should be

done to have homogeneous mass without voids. The work of hearing should be

done in such a manner that it will be covered immediately with casing material if

included in the tender and will not remain half-way by the end of season so as not to

get damaged during monsoon. The ring bund for ughadi in constructed upto high

tide level with locally available impervious clay, measurements shall be taken after

completion of bund but paid after construction of ughadi is completed. The

maintenance of bund during the construction to the designed section is sole

responsibility of the contractor. Mode of Measurement and Payment :- The running bills will be paid on the basis of actual cross sections taken at 30m or closer

interval as may be necessary as per the site conditions restricted to designed section.

All running bills will be paid at 90 % as part rate and the same 10 % will be released

at the time of final bill provided all other items such as casing pitching and other

related items of the bank work, if any are completed satisfactorily. In case of failure

to do so the quantity arrived at after due deduction for shrinkage will be considered for

final payment and paid at 90 % reduced rate. The final measurements will be based on the basis of actual cross sections taken,

restricted to designed sections, the contract rate shall be for one cum of finished

bank work. The deduction for shrinkage would be made from the computed quantity at

15 % if the measurements are taken during the same working season and at 10 % if

the measurements are taken after passing of one monsoon. The ring bund for sluice gate shall be constructed up to high tide level (Plus) 0.30

meter. Measurement of the bund will be taken after Completion of the bund however

payment thereof will be made after construction of sluice gate is completed. The

contractor till the completion of sluice gate shall maintain the top of ring bund. As

such deduction of shrinkage from the earthwork of the ring bund is not necessary.

After completion of sluice gate the contractor shall remove at his own cost and risk and

directed by Engineer-in-charge. In the case work spills over one monsoon it shall be incumbent to take

measurements of the work already executed but not finalized before restarting the

work in second season.

Item No. 5 :- Constructing embankment for casing zone, with selected material with

contractors own material from borrow area including transporting the material with

all leads & lifts, laying in even layers, breaking clods, Spreading, Leveling,

Dressing to the required section including watering etc. complete.

Page 142: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

142

Contractor No. of corrections Executive Engineer

General :- This item provides for laying topping and bedding below pitching of casing material over

the Kharland bund already laid with hearting material. The item to include all tools

equipment, material and labour required to complete the item as directed by the

Engineer-in-charge or his representative (For Thane & Raigad Dist.) After clearing the site, the toes of bund will be demarcated on ground on the basis of

cross-section. For this levels will be taken at the regular interval of 30 meter or at

closer interval depending upon the topography of the site. If the contractor or his

representative fails to present during taking levels, the levels taken by field staff

will be treated as final and binding on contractor. The item included quarrying,

transporting and spreading the suitable material from the borrow pits in uniform layers as

directed. (For Ratnagiri and Sindhudurg Dist.). Clearing borrows pit areas : All areas required for borrow pits for selected material shall be so selected that felling of

existing mangroves is not necessitated. However it should cleared of all trees,

stumps, roots and other objectionable materials etc. Particular care shall be taken

that all organic matter shall be excluded from the material which is to be placed in

the bund embankment. The cleared area shall maintain free of vegetation growth

during the progress of the work without any extra payment. The borrow pits shall be stripped to depth necessary to obtain material of the desired

quality where borrow pits are opened adjacent to the bund the edge of the excavation

shall not approach the toe of the bund closer than 5m. Borrow pits shall be so selected

that required materials will be furnished as close as practicable to the point of

utilization and so that they will not interfere with location of permanent structure

not the usefulness of appearance of any of the work. The formation of pools shall

be avoided and all borrow pits shall be drained as necessary by ditches to the nearest

nallas. All pits shall be arranged with certain amount of regularity having regard to the

convenience of the work during the excavation and to its safety and appearance of finish

after its completion. Temporary quarry roads leading to and fro from the respective borrow areas to the

site of the embankment where the material are required to be deposited shall be

constructed and maintained by the contractor at his own expenses with permission

of and as directed by Engineer-in-charge. The borrow pit material shall be got classified by the Engineer-in-charge with regard

to its suitability for bund. During construction contractor may after careful testing

with specific permission of the Executive Engineer, bring suitable material, from the

areas other than those indicated in borrow area plan. No extra payment would

however be admissible on this account. For the guidance of the contractor, quarries will be shown at site if desired. The date

presented therein are to be taken only as a guidance and no claims shall be

Page 143: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

143

Contractor No. of corrections Executive Engineer

entertained in future due to lack of conformity between the nature of materials

actually met with during construction and that indicated in the borrow area plan. The

contractor is expected to have his own prospects carried out before tendering for the

work. During construction the contractor, may after careful prospecting and with

specific written approval of the Executive Engineer, bring suitable material from areas

other than those in the borrow area shown. No extra payment would however be

admissible on this account.

Method of Execution : The casing material shall be laid in layers as per the section shown in the drawing and

as directed by the Engineer-in-charge or his representative. The material should

contain proper moisture. (Water should be sprinkled whenever required). Every

layer should be completed by manual kneading tamping by earth master rammer or by

timber mallet. The contractor has to make his own conveyance arrangements; casing or

the murum topping shall be done and got finalized before start of monsoon. Mode of Measurement and Payment :- The running bills will be paid on the basis of cross section taken restricted to the design

section. The final measurements will be based on the basis of actual cross sections taken

restricted to designed sections. The contract rate shall be for one cum of finished

bank work. The deduction for shrinkage would be made from the computed quantity at

15% if the measurements are taken during the same working season and at 10% if

the measurements are taken after passing of one monsoon.

The ring bund for sluice gate shall be constructed upto H.T.L. + 0.3 m. Measurement of

the bund will be taken after completion of bund however payment thereof will be made

after construction of sluice gat is completed. The contractor till the completion of sluice

gate maintains the top of ring bund. As such deduction of shrinkage from the earthwork

of the ring bund is not necessary. After the completion of sluice gate the contractor

shall remove at his own cost and risk and as directed by Engineer-in-charge.

Item No. 6 :

Providing and laying dry stone pitching with contractors own material of 20 cms.

thickness to side slopes of embankment including dressing the bank work with all

leads & lift etc. complete. as directed

A) Field side without header

B) Creek side with header

General

The bank work, before laying the pitching, should be brought to required slope and

section. The item includes all tools and equipments, materials, transportation and

labour required for satisfactory completion of item with necessary dressing the

Page 144: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

144

Contractor No. of corrections Executive Engineer

embankment.

Materials :- The quarries and the materials should be got approved from the Engineer- in-charge or

his representative at the quarry itself. The materials are to be brought from quarries

with his own cost and risk. Method of Execution :- The slopes of bank work where the pitching is to be laid shall first be trimmed to

the required slope. Stores should be large and placed vertically so as to interlock with each other and the

chips used for filling the interstices and wedging may be in pieces. The pitching

should be made in one layer but stones in the layer should be as large as possible and

of a weight as will not get disturbed by wave action or during heavy rain. Layer

will be with flat large face resting on the prepared sloping surface. Remaining interstices

being filled in with chips, spauls properly hammered in so that the entire mass

become firm and cannot be disturbed by hand. The stones used for the pitching shall be perfectly sound and as regular in shape as

possible. Sixty percent of the stones shall be such as not to weight less then 25 Kg.

each. The stones shall as far as practicable be selected as to size and shape to secure

fairly large flat surfaced stones with will be laid up with an even surface and

minimum number of voids.

The stones shall be placed on end with broadcast base down and length normal to

the slope. Beginning at the bottom of the slope, the stones shall be laid compactly and

so matched and interlocked that they shall be keyed together with a minimum of joint

space. Rock fragments and spauls shall be tightly driven into the interstices to

wedge and stones in place and close direct opening to the underlying slope. Such

filling shall be carried out simultaneously with the placing in position of the large

stones and shall in no case be permitted to fall behind. The wedging shall be done with

the largest size chips practicable, each chip being well driven home with a hammer so

that no chip is possible of being picked or removed by hand. The smaller size stones

required for filling in interstices and wedging shall only be supplied to the actual

requirements for such work and shall not be used in two or more layers as a substitute

for the full thickness stones. High irregular points shall be knocked off and the

finished pitching shall present a neat and reasonably smooth and uniform surface, free

of loose stones. Work of laying murum bedding and stone pitching shall be done

simultaneously. Mode of Measurement and Payment :- The contract rate shall be for one square meter of finished pitching worked out on actual

measurements restricted to designed section. The rate includes stone pitching.

Item No. 7 :- Providing & constructing down stream Rock toe with 15 to 23

cms. rubble stone of approved quality from borrow area with hand packing

including all leads & lifts etc. complete.

Page 145: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

145

Contractor No. of corrections Executive Engineer

General

The bank work, before laying the pitching, should be brought lo required slope and'

section. The item includes all tools and equipments, materials, transportation and

labour required for satisfactory completion of item with necessary dressing the

embankment.

Materials:-

The quarries and lie materials should be got approved from the Engineer-in-charge or

his representative at the quarry itself. The materials are to be brought from quarries

with his own cost and risk.

Method of Execution:-

1. The slopes of bank work where the pitching is to be laid shall first be trimmed to the

required slope.

2. Stores should be large and placed vertically so as to interlock with each other and the

chips used for filling the interstices and wedging may be in pieces. The pitching

should be made in one layer but stones in the layer should be as large as possible and

of a weight as will not get disturbed by wave action or during heavy rain. Layer will

be with flat large face resting on the prepared sloping surface. Remaining

interstices being filled in with chips, spauls properly hammered in so that the entire

mass become firm and cannot be disturbed by hand.

3. The stones used for the pitching shall be perfectly sound and as regular in shape as

possible. Sixty percent of the stones shall be such as not to weight less then 25 Kg.

each. The stones shall as far as practicable be selected as to size and shape to secure

fairly large flat surfaced stones with will be laid up with an even surface and

minimum number of voids.

The stones shall be placed on end with broadcast base down and length normal to the

slope. Beginning at the bottom of the slope, the stones shall be laid compactly and so

matched and interlocked that they shall be keyed together with a minimum of joint

space. Rock fragments and spalls shall be tightly driven into the interstices to wedge

and stones in place and close direct opening to' the underlying slope. Such filling shall

be carried out simultaneously with the placing in position of the large stones and shall

in no case be permitted lo fall behind. The wedging shall be done with the largest

size chips practicable, each chip being well driven home with a hammer so that no

chip is possible of being picked or removed by hand. The smaller size stones required

for filling in interstices and wedging shall only be supplied to the actual requirements

for such work and shall not be used in two or more layers as a substitute for the full

thickness stones. High irregular points shall be knocked off and the finished pitching

shall present a neat and reasonably smooth and uniform surface, free of loose stones.

Work of laying murum bedding and stone pitching shall be done simultaneously.

Page 146: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

146

Contractor No. of corrections Executive Engineer

4. Mode of Measurement and Payment :

The contract rate shall be for one cubic meter of finished pitching worked out on

actual measurements restricted to designed section. The rate includes stone pitching.

Item No. :- 8, 12 ,13 & 14:- Providing and casting in situ cement concrete of grade PCC M-15 of

trap/granite/quartizite/gneisis metal for cast in situ piers , abutment ,

returns, wings etc. including provision of “V” shaped false joints to form

suitable panels on the faces to approve design with compacting , vibrating

and curing complete including formwork ,centering,(Excluding

dewatering by means of pump ) and bailing out water and curing etc.

complete.

1.Scope:-

The work covered by this item shall consist of furnishing all material

Equipments and labour for the manufacture transport, placing and curing of

concrete and performing all the functions necessary and ancillary thereto

including finishing of the surface to the required specificationProviding fixing

and removing formwork is also included unless otherwise specified.

2.Mixing :-

The ingredients of concrete shall be properly mixed designed so as to

positively ensure uniform distribution of all the component materials

throughout the mass at the end of the mixing period. The mixing of each batch

shall continue for about one and half to two minutes or as found best in

practice after all materials except mixing period specified above assumes

proper control of the speed of the rotation of the mixer and of the introduction

of the materials including water. The mixing time shall be increased when the

charging operation fails to produce the required uniformity to composition art

consistency within the batch and form batch. Excessive mixing requiring the

addition of the water to preserve the required concrete consistency shall be

avoided. If the mixing arise charging operations arc such that the required

uniformity of the concrete is obtained in the short mixing time may be

shortened ads directed by the Engineer – in charge. Mixing shall be done by

Chemical means only.

3.The following Generals Principles shall be followed in operation of mixing.

The ingredients shall be fed into the mixer simultaneously.

A portion of water ( between 5 and 10 percent ) shall precede and in equal

quantity shall follow introduction of the other materials.

The reminder the water shall be added uniformity and simultaneously with

other materials. Care shall be taken that mixing of concrete in the mixer shall

be uniform.

Page 147: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

147

Contractor No. of corrections Executive Engineer

4. Placing of Concrete :-

Concrete shall be placed only –in location where authorized and no concrete of

mortar shall be placed until formwork, installation of embedded parts,

preparation of surfaces or masonry clean –up has been done and approved.

Rock surface/rigid masonry or concrete surface upon or against which concrete

is to be placed shall be prepared in the same manner as in rock foundations or

old masonry for concrete surface with reference to relevant specifications for

preparation of foundations and starting masonry over old masonry.

Before starting the placing of concrete it should be made certain that the

transporting and placing equipment is clean and in good condition and that the

equipments along with the operation staff is arranged to deliver to concrete in

the final position without undue delay and objectionable segregation .If

concrete is to be placed at right adequate lighting arrangements as directed by

the Engineer – in Charge shall be made. The concrete shall be such as will

permit the delivery of the concrete of the required consistency into the work

without objectionable segregation porosity of excessive or less workability.

All concrete shall be placed in the final position within 30 minutes after being

mixed. Excessive segregation from what ever cause shall be inanities in

handling and placing operation by avoiding or controlling lateral movement of

the concrete as on dumping at an angle or depositing continuously at one point

and allowing the concrete to flow. Concrete shall not be dropped from

excessive heights and the free fall shall be kept minimum. All surfaces of form

and metal work including reinforcement bar that have become encrusted with

dried mortar or grout from concrete previously placed shall be cleaned of all

such mortar or grout before surrounding or adjacent concrete is placed.

Concrete shall be deposited in continuous horizontal layers of 15 cm .to 20

cms. The layers being decided by the time lapse between successive layers.

The time of laying one layer shall not exceed 30 minutes .When work is to be

resumed on a surface which has hardened such a surface shall be roughened

and scrubbed with brushes to remove laitance, care being taken to avoid

dislodgement of coarse aggregate ,swept lean ,thoroughly wetted and covered

with 6mm (about 14” thick mortar layer composed of cement and sand in the

same proportion as the cement & sand in the concrete immediately before

commencement of concrete, for securing good bond.

5. Embedded parts and installation in concrete :-

All embedded metal work in concrete shall be installed without any extra

payment except when otherwise specified.

6. Concreting during rains :-

Page 148: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

148

Contractor No. of corrections Executive Engineer

When concreting is required to be done or continued when it is raining , it

shall be seen that the concrete is not damaged due to rain while it is being

transported and placed. The green concrete shall be adequately covered with

suitable covering ,suitable after placing for a period of 24 hours when it will be

capable of being cured by splash of water. The surface of fresh concrete should

be maintained on a slope sufficient to result in the self –drainage of the rain

water. The work shall however be discontinued when the rain is too severe that

water collects in pools or mashes the surface of the fresh concrete and is ot

feasible to provide adequate shelter.

7. Tests. for cement concrete.

Crushing Strength :- The compression test of concrete shall be made 15 cms.

cubes. Concrete cube shall be taken immediately after it has been placed on

the work. Whenever this is not possible , sample shall be taken s the concrete

is being placed to obtain a representative sample. A sufficient number of

samples each large enough to make one test cube shall be taken at different

points so that the test cube made from them will be representative of the

concrete placed in that portion of structure for test. The one set of test cubes

not be less than 3 numbers per set for 20 cum each of concrete placed after

proper curing for 7 days and 28 days respectively. These shall be tested and

should give compressive strengths of 100 kgs./Sq.Cm. respectively for nominal

mix of (1:3:6).However 5% variation in the strength is permissible.

If the test results show that the concrete blocks give results below the specified

strength, such bad quality of concrete shall be removed and redone by the

contractor at his own cost.

8. Slump Test :-

In order to test the consistency of the mixed concrete, slump test shall have to

be made by the contractor when and where required by the Engineer – In

Charge . The slump test shall be carried out as per I.S.Specifications ,BR27.4 .

9. Rate of Placing :-

Concreting should continue without avoidable interruption or until the section

of structure is completed or until satisfactory construction joints can be made.

Concrete shall not be placed faster than the placing crew can compact it

property. In placing thin members and columns precaution shall be taken

against too rapid placement which may result in movement or failure of the

form due to excessive lateral pressure. An interval of at least 12 hours and

preferably 21 hours should elapse between the completion of columns and

walls and the placing of slabs, beams, or grinders supported by thick in order to

avoid cracking due top settlement. All concrete shall be laced in approximately

horizontal lifts exceeding 1.2m in height in one day.

Page 149: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

149

Contractor No. of corrections Executive Engineer

10. Compaction :-

All concrete shall be vibrated by mechanical vibrators of an approved type so

as to ensure dense concrete hand tamping ,rodding shall not be used for

compaction of concrete except in special circumstances when permitted by the

Engineer in Charge .When impression type vibrators are used they shall be

used vertically at about 45 cms. apart. The vibrator shall be inserted into the

full depth of the newly laid concrete layer. The vibrator shall not be however

revibrate in concrete which has commenced his final set. Special care shall be

taken to see that the vibrator touching the reinforcement or embedded pats do

not disturb the concrete below which has comme4nced his final set . The

concrete shall not be vibrated excessively so as to cause segregation.

Each layer of concrete and specially where smooth surface are required

and for all surface which are permanently exposed to the weather and for all

surfaces next to embedded metal work shall be worked and vibrated by

vibrators of approved type to obtain concrete of maximum density and

imperviousness and to assure close contact of the concrete with forms

reinforcement bars and other embedded parts. If the method of transporting and

placement have been conducive to air entrainment segregation or stiffening ,

the work of compacting should receive special attention .

For concrete surfaces to be exposed to high velocities of water special

precautions shall be taken to minimize and to prevent surface splitting and

protrusions without sorting to over manipulation of the concrete mix to the

forms. No plastering for getting a smooth finish shall be permitted on these

locations. Any protrusions shall be ground smooth.

11. Finishing :-

Finishing of uniformed surfaces shall be performed only by skilled

workman. All exposed concrete surface shall be cleaned of all

incrustations of cement mortar or grout and unsightly stains shall be

removed.

12. Formed Surface :-

Surface of concrete finished against forms shall be smooth free from

projections and filled thoroughly with mortar. Immediately upon removal of

forms all unsightly ridges or fins shall be removed and any local bulging on

exposed surface shall be rectified by tooling and rubbing. All holes left by

removal of plaster ,shall after being reamed with toothed reamer, be neatly

filled with dry patching mortar. All porous & fractured concrete & surface

concrete to which additions are required to bring it to the prescribed lines shall

be removed by chiseling opening into concrete. The chipped opening shall be

sharp aged and keyed and shall be filled to required lines with fresh concrete

or dry patching mortar. Where concrete is used for filling the chipped opening,

Page 150: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

150

Contractor No. of corrections Executive Engineer

these shall not be less than 75 cms. in depths and the concrete filling shall be

reinforced and be leveled so surface of the openings

13. Dry Batching :-

Dry batching concrete shall consist of one part of the cement and two parts of

sand by volumes and just enough water so that the mortar used will stick

together on being molded into a ball by slight pressure of the hand and will

not exude, water when so pressured but will leave hands damp. The mortar

shall be placed in layers of not more than 2.5 cms. thickness. After being

compacted , each layer shall be roughened by scratching , to provide an

effective bond with the successive layers. The last or finishing layer shall be

smooth to form a surface continuance with surroundings concrete .All patches

shall be blended thoroughly to the surface to that the chipped openings and

shall be

sound and free from shrinkage or cracks.

14. Finishing permanently exposed surfaces :-

Except or otherwise specified or directed all permanently exposed concrete

surface and other waterway surfaces requiring durability under water shall be

finished i the following manner.

Immediately upon the removal of the forms the surface shall be wetted and

all surfaces pits and air bubbles filled by rubbing mortar composed of cement

and fine sand in proportion (1:2) into the pits with burlap so as to, secure a

uniform density and smooth face. The rubbing of mortar with burlap shall be

performed in such a manner so as to leave the surface free from mortar not

needed for filling the pits. When the filling operation s be unduly delayed and

surface of pits become coated with dirt or other contaminating materials, they

shall be thoroughly cleaned and washed and shall be maintained in as moist

condition until mortar filling is placed. Such cleaning satisfactorily means of

without damaging the surrounding concrete. All operations i connection with

the filling of surface pits shall be handled as quickly as practicable to

minimize the period during which concrete and mortar filling are exposed to

drying. When the treatment of a surface has been completed the surface shall

be cured. All patches and mortar filing pits on exposed surface shall be neat

and of the same colour and texture as the adjoining concrete.

15. Finishing :-

For exterior concealed surface below ground o5 back till level or below

maximum draw down or minimum tail water or like surfacing not

otherwise specified no finish is necessary except that sand streaks gravel

pockets , honey combing or other imperfections which are of consequences

Page 151: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

151

Contractor No. of corrections Executive Engineer

affecting strength . water tightness or protection of enforcing steel from

corrosion shall be corrected and repaired as prescribed for formed surface.

16. Finishing :-

Uniformed surface shall be finished by one or more of the operations of

screening floating, toweling and work of the surface should be done at proper

time in employing experienced men and should be sufficient to produce the

desired finish. Screening which gives the surface its approximate shape by

striking off surplus concrete immediately after completions shall be

accompanied by moving a straight edge or template with a sawing motion

across wood or metal strips that have been established as guides. Where the

surface is curved a special screen should be

Shortly after the concrete is screened the surface should be brought true to

form and grade by working in sparingly with a wooden float. If a coursed

textured finish is desired or if the surface is to be steel trawled a second or final

floating should be performed after some stiffening has occurred and the

surface insure film or shine has disappeared. Where a smooth dense finish is

desired floating shall be followed by steel trowelling sometime after moisture

films or shine has disappeared from the floated surface and when the concrete

has hardened sufficiently to prevent fine material and water from being

worked out to the surface. Excessive trowelling particularly that too at an early

stage shall be avoided.

17 Chipping and Roughening concrete surface :-

Surface upon or against which additional concrete is to be placed shall be

chipped and roughened to a depth grater than 2.5 cms. Roughening shall be

performed by clipping or other satisfactorily methods and in such a manner as

not to loosen, cracks or shatter any part of the concrete beyond the roughened

surfaces. After being roughened the surface of the concrete shall be cleaned

thoroughly of all loose fragments ,dirt and other objectionable substances and

shall be sound and hard in such conditions as to assure good mechanical bond

between old and new concrete. All concrete which is not hard dense and

durable shall be removed to the depth required to secure a satisfactorily

surface .

18. Curing and Projection :-

All concrete shall be protected against injury until final acceptance. Exposed

finished surfaces of concrete shall be protected from the direct rays of the sun

for at least 72 hours after placement . Concrete shall be kept continuously

Page 152: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

152

Contractor No. of corrections Executive Engineer

moist for not less than 21 days. Constructions joints shall be cured in the way

as other concrete and shall also be kept for at least 72 hours prior to the

placing of additional concrete upon the forms. Approximately horizontal

surfaces shall be cured by covering of damp‟s and or may be cured by the

use of wet quality nets. If drain sand or quilt is used for curing it shall be

removed completely later water curing shall be used on all concrete work in the

C.D.Work and shall be applied by means of sprays or sprinkles which will

cover entire area of concrete Forms shall be kept sprinkled until removal.

19. Measurement and mode of Payments :-

The concrete shall be for a unit of one cubic meter of concrete. The concrete

shall be measured for its length, breadth & depth, limiting dimensions to those

specified on the plan, or as directed by the Engineer – in Charge. no deduction

shall be made for reinforcement in concrete in RCC Work. Individual

dimension shall be worked out to two decimal places. The rate of concrete is

inclusive of all ,i.e. finishing, chipping etc. complete.

Item No. 9 :-

Dismantling carefully the existing structure of stone masonry /RCC

Structure in cement mortor or lime mortor including sorting out

serviceable material and stacking the dismantled material within 50

m lead neatly as directed etc. complete.

I. General : The item provides for complete removal of the existing structure except such

portions as may be required or permitted to be left in place shown on the

drawing or as directed by the Engineer –in Charge, clearing to site, sorting out

useful material and stacking them neatly within a lead of 100m ( about 328 feet

) the bank indicated by the Engineer whichever is more than and wasting the

non-materials.

2. Preliminaries :

If necessary and directed by the Engineer the contractor shall have to exact

screens of canvas or other suitable materials and or near the structure and area

to avoid the nuisance of dust before and during dismantling. Care shall be

taken to see that dismantling is done in such sequence or manner as to prevent

all avoidable damage to usable material. In case of structures which are to be

removed for re-erection, all members are properly match – marked with paint.

The pins, nuts, plates, structural steel, piers, timber etc. shall be similarly

marked for identification of their position of entire assembly. All machined

surfaces pin, holes, pins, etc. shall be coated by grease. The inventory of all

serviceable materials shall be kept on the record and pursuance of the

Page 153: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

153

Contractor No. of corrections Executive Engineer

contractor obtained in token of his acceptance. Any doubt or agreement with

the same shall be reported by the contractor before starting the removal.

Portions required to kept intact shall be marked before starting dismantling.

If no separate provision exists in the tender for necessary diversion, the

contractor shall nevertheless invariably be responsible for the construction and

maintenance of adequate barriers, watchman and or lights at ends portions the

road closed by construction, to the satisfaction of the Engineer at his

(Contractor‟s) cost, diversion itself being treated as extra work.

A register shall be opened by contractor on the work site to show day – to day

account of the turn out, salvages materials, and whether properly worked or

wasted .It shall by the representative of the contractor and responsible member

of the departmental supervising staff every day.

3. Dismantling and Removal :

The structure shall be dismantled carefully and the materials removed

Without causing damage to the serviceable materials ,salvaged ,the party

or the structure to be retained and any properties or structure, near by

property or structure shall be made good by the contractor without extra

claims ,the contractor shall be responsible for any injury to the workers

or the public.Unless otherwise specified the structure shall be removed up to

45cms.(about 18” ) below the ground level and the portion which

interferes in any way with the new construction shall be removed entirely

Removal of over laying or adjacent materials if required for the

dismantling of the structure shall be included in the item.

Where existing bridge is to be extended or otherwise incorporated in the

new work , only such a part or parts of the existing structure shall be

removed as necessary to provide a proper connection to the new work. The

connecting edges shall be cut , chipped and trimmed to the required lines and

grades without weakening or damaging the part of the structure to be retained.

Blasting if required , may be resorted with the written permission of the

Engineer. In such a case blasting shall be finished before the new

construction is commenced.

4. Item to include :-

1.All labour , materials, use of equipment tools and plants required for

completing the job satisfactorily.

2.Erecting and removing screens and watering when necessary and

directed.

3.Making the structure suitably.

4.Opening register of salvaged materials.

5.Providing adequate barricades , signs, lights etc.

Page 154: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

154

Contractor No. of corrections Executive Engineer

6.Removal of the structures.

7.Diverting the existing drains, road, etc. temporarily and redoing the

same ,if not separately provided.

8.Stacking the serviceable material.

9.Wasting unserviceable materials.

10.Clearing site on completion.

11.Conpesation for damaged properties or injuries to persons.

5. Mode of Measurement and Payment :

The contract rate shall be for one cubic meter for completion job.

Proportionate payments may made through running accounts bills.Fully

payment shall be made on completion of the job in all respects

Item No.10 :-

Dewatering for Abutment, Returns, Piers, Raft, Cut of walls, Toe wall,

Apron in perennial river or stream including diversion of stream

providing of ferbams, bunds etc. as may be necessary for foundation and

other parts of work and bailing out and / or pumping out water below the

actual initial natural water level during execution of all item of

construction as required (from start of that particular component till

completion of bridge) including all leads and lifts etc. complete.

1.General :-

The foundation trenches shall be kept dry by resort to pumping alone or

pumping in combination inaction with Diversion channels, bunds, diversion

weirs, the contractor should supply details of his proposal for approval of

Engineer-in-charge but such an approval will in no way release the contractor

from his responsibility for, adequacy of dewatering arrangements for the

quality and safety of the work.

This item shall include all labour, material pumps, plants, equipments staging,

shoring, strutting zing and other arrangements necessary for dewatering during

excavation and construction of other items requiring dewatering.

2. Materials :-

All materials such as pumpset, pipes, fuel etc. required to carry out this

shall be brought by the contractor.

3. Method of execution :-

Page 155: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

155

Contractor No. of corrections Executive Engineer

Method to be adopted shall be entirely left to the choice of contractor, provided

adequate dewatering is carried out during construction. The coffer crams shall

be of sufficient heights to prevent ingress of water in the foundation pits, to

protest green concrete or masonry, damage from tides or sudden rise of stream

and to prevent damage off the foundation by erosion.

Pumping

Adequate pumping arrangements shall be made for dewatering foundation

trenches and areas of construction. Where dewatering, is essential and keeping

them dry while masonry or concrete or other construction is in progress, till the

concrete or mortar or masonry has sufficiently set and construction can be

proceed without pumping.

Desilting :-

If any foundation pits are filled due to accumulation of surface flow during the

progress of the work or during rainy season or due to any other cause, all

pumping required for dewatering the pits and removing silt shall be done

without extra cost.

Shoring etc. :-

Staging shoring, strutting, sumps and other protective works required for

facility of dewatering shall be designed and put up by the contractor to ensure

full safety to the work, workmen, machinery and property and shall be

removed after they have served their purpose in a manner and to the extend

directed by the Engineer. The contractor shall be responsible for all damage

and injury caused by the execution of this item.

Disposal of Water :-

The water from the excavated trenches shall be disposed off in the manner

detailed below or in any other manner in conformity with the rules in force and

approved by the Engineer-in-charge.

a) In case the area is developed such as cities which are severed or have open

gutter along the roadside, the water may be led to the nearest such gutters or

sewers.

b) In undeveloped areas such as countryside where sewing system has not been

introduced the water may be led to the nearest natural drain or pond through

properly laid and dug channels or through pipes as directed by Engineer-in-

charge.

Page 156: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

156

Contractor No. of corrections Executive Engineer

Disposal of water shall I no case cause inconvenience or nuisailce to the

Inhabitants of the area or cause damage to the property and Nearby Municipal

or Government regulations shall be complied with the rights or private land

owner shall be respected regarding disposal of water.

Contractor shall be responsible for the incidental, formalities like obtaining

permission of local bodies (Municipalities etc) and persons, concerned, to lead

the water to the open or under ground, sewers or digging up channels making

use of lands and properties owned by private persons or public bodies etc. and

for the damage caused in the operation of this item.

4. Mode of measurement and payment :-

The unit rate for the payment shall be one B.H.P. hour. The actual working

hours or pump set on site will be counted and recorded in log book and B.H.P

hours worked out. Payment for this item shall not be released till the structure

has been completed upto safe stage.

Item No.11:- Providing rubble filling of trap/granite/quartzite/gneiss stones of approved quality in foundation including hand packing filling gravel of sand in voids etc. complete.

1. General :-

The item provides for preparing the foundation, filling rubble, hand packing

rubble in the foundation and filling the voids with either gravel or sand as per

the item and as directed by Engineer in charge. The item includes all the

labour, materials and tools required for completion of the same.

2. Materials

The required material such as rubble, gravel, or sand etc. shall comply with

details of 4 & 5 of general specification. Gravel shall be natural obtained from

streams in the region and shall not contain particles bigger than 20 mm in

diameter. It shall be clean and free from weathered and soft crumbling

portions. The materials are to be brought form private or Government quarries

with contractor‟s own cost and risk.

The sand shall not contain more than 5% of clay or silt.

3. Method of Execution :-

The on which rubble filling is to be laid shall be cleared off all looser materials

leveled and compacted and got approved form the Engineer-in-Charge before

Page 157: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

157

Contractor No. of corrections Executive Engineer

filling. The rubble filling shall be carried out to the dimension and levels

indicated on the drawing or as instructed by the Engineer in charge. The rubble

shall be laid with the broadest face downwards and in close contact with each

other, in layers not exceeding 30 cm. thick. Each layer of rubble shall be

packed, wedged with quarry spauls and chips of rubble, by hammer. The

further voids shall be filled up with gravels or sand.

4. Mode of Measurements and Payment :-

The contract rate shall be for the unit of one cubic meter of filling completed as

specified, with dimensions restricted to those shown in the drawing or those as

instructed to do by the Engineer-in-Charge or his representative.

Item No. 15, 16 & 17:-

Providing and cutting bending, hooking, laying in position mild steel/

HYSD/ TMT bars for reinforcement including cost of reinforcement

binding wire as per detailed drawings for R.C.C. work etc. complete with

all leads and lifts.

1. Scope of work

2. This item shall include cutting, bending, binding and erecting in position

steel reinforcement.

3. Reinforcement

Steel reinforcement bars and fabric shall be placed in the concrete as 0shown in

the drawing or as directed, before steel reinforcement is placed in position the

surface of the reinforcement shall be cleaned of rust, scale, dirt and grease, any

other objectionable foreign substance (heavy flaky rust and mill scale that

cannot be removed by firm rubbing with burlap, or equivalent treatment is

considered objectionable). The fact that light early stage rust has no detrimental

effect on bond and hence could be disregarded. This shall not be used to excuse

careless handling and storage of steel. In sorting bars of the same sizes lengths,

shapes and grades shall be assembled in-racks and marked distinctly.

The steel shall be treated with approved Anti-Corrosive treatment. Before the

reinforcement bars are fixed in position it shall be verified that they are of the

specified sizes and are cut and bent in accordance with the plans and

specification: they shall be accurately placed and secured in position by means

of built in sufficiently concrete blocks, metallic chairs, hangers, spaces or other

suitable device at close intervals so that they will not sag between supports nor

be displaced during the placing of the concrete or by any operation of the work

Special care shall be exercised to prevent any disturbance of the reinforcement

in the concrete that has already been placed. The reinforcement after being

placed in position shall be maintained in clean condition until its Completely

Page 158: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

158

Contractor No. of corrections Executive Engineer

embedded in concrete, to prevent further damage to the concrete or unsightly

rust stains on exposed concrete surface.

Reinforcement shall not be straightened or bent in a manner that will injure or

weaken materials. Bars with kinks or bends not shown on the plans shall not be

used. Bars shall be bent to the shape and dimension as shown on the drawing or

as directed using a bar bender operated .by hand power to obtain the proper

bending of rod. The radius of bend shall not be less than 4 times diameter of

the bar. Heating of the reinforcement bars to facilitate bending will not

normally be-permitted. When, however such to facilitate bending will not

normally be permitted. When, however such heating is permitted in the case of

large diameter bars, the temperature of the, steel shall not exceed that

corresponding to a cherry red color i.e.&1.50C)

4. Binding

Wire for tying reinforcement shall be of soft and annealed steel. The wire may

be of 16 to 18 B.W.G. and shall have an ultimate strength of not less than 5,600

kgs per sq.cm. yield point of not less' than 3,900 kgs per sq.cm. metal.

Dissimilar metal shall not be placed in concrete in intimate proximity with each

other or be joined by a conductor especially in the continued presence of

moisture unless it is known that galvanic action will not result.

5. Distance between Reinforcement Bars

The distance between two parallel reinforcement bars shall be as shown in the

drawing. Where ever such distance is not shown on the drawing the reference

shall be made. to the Executive Engineer to get the necessary details The

vertical distance between two horizontal main steel a reinforcement of the

corresponding distance at right angles to two inclined main steel

reinforcements shall be as shown on the drawing. When the distances are not

shown on the drawing the reference shall be made to the Executive Engineer

and the necessary details sought The pitch of main and distribution bars shall

be as shown in the drawing. Bar splices as indicated in the drawing or as

specified by the Engineer-in-charge shall only be allowed. The lapped ends-

shall be placed to ensure full bond on each bar splicing shall not be done in the

region of maximum bending moment and splicing of adjustment bars shall be

avoided as far as possible

Weight shall be computed from the table in general specifications. The unit rate

accepted for the reinforcement shall include the cost of Anti corrosive

treatment & laying, cutting, bending, cleaning, straightening, fixing and

maintaining the reinforcement. Supplying and attaching binding wire supports

separators, metallic chairs, hangers, etc. shall be deemed to be included in the

unit rate for reinforcement and shall not be measured or paid

6. Cover

The thickness of concrete cover (exclusive of plastic or other decorative finish)

shall be as per drawings. Incase it is not shown on the drawing a reference shall

be made to the Executive Engineer to get, the necessary clarification. Where,

Page 159: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

159

Contractor No. of corrections Executive Engineer

because of splicing, the thickness of concrete in between reduces to less than

the maximum size of aggregate concrete with a reduced maximum size of

aggregate shall be used so as lo allow development of bond in the slice. The

extra cost of such special concrete shall be deemed to have been included in the

unit rate for the main concrete and shall not be paid separately.

7. Inspection before Concreting

No concreting shall be started unless the reinforcement as laid is finally

checked and certified by the Engineer-in-charge or his authorized

representative before starting concreting the contractor shall make certain that

the measurement of the reinforcement placed have been record and that the

Engineer-in-charge has certified to the correctness of reinforcement used.

Failure to do so may mean no payment or payment at the discretion of the

Engineer-in-charge for the reinforcement concreted.

8. Mode of Measurement

Accurate records through record entries in measurement book shall be kept at

all times, of numbers, sizes, lengths and weight of bars placed in position for

different parts of the work.

The Reinforcement shall be paid as per the weight of the actual quantity of

steel reinforcement placed in the structure arrived at by measuring the actual

length of the bars used and placed as shown in the bar bending schedules

including hooks, bend and laps. The length of the bar shall be measured to the

nearest 7.5 cm a fraction less than 4 cm neglected and a fraction of 4 cm more

being taken as 7.5 cm. Weight shall be computed from the table in general

specifications. The unit rate accepted for the reinforcement shall include the

cost of Anti corrosive treatment & laying, cutting, bending, cleaning,

straightening, fixing and maintaining the reinforcement. Supplying and

attaching binding wire supports separators, metallic chairs, hangers, etc. shall

be deemed to be included in the unit rate for reinforcement and shall not be

measured or paid.

Item No. 18

Providing and fixing polypropelene glass lined F.R.P. Rectangular gate

including fixing in position with all lead & lift etc. complete.

Providing and fixing polypropelene glass lined fibre glass reinforced

rectangular automatic gate.

Gate shutter shall be made out of heavy duty PPGL and FRP

material, shutter shall be smooth finished from the both sides shutter water

tightness, shutter shall be reinforced with suitable section of size 50 x 40 mm.

The frames supporting the shutter shall be made out of 50x50x5 mm thick

metal angle section intercepted by vertical and horizontal sections. This

skeleton of steel in duly coated with FRP material structural steel sections

Page 160: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

160

Contractor No. of corrections Executive Engineer

shall be used as per IS handbook Sp:6 (a) 1964.

Steel “J” section duly coated with FRP material shall be used for horizontal

support as per ISI handbook Sp .6(a) 1964

Suitable hinges shall be provided to initiate the operation of the gate, hinges

shall be made of P aid composit material.

The proof of the gate design shall be checked to with stand 4.5 mtr. height

hydrostatic pressure with adequate facto of safety, including transportation

work site etc. complete.

General :-

The work consist of providing PPGL FRP rectangular automatic gate of

in position at site etc. complete.

The weight of gate should be 120kg.including FRP coated M.S. Angle and I

section or channel FRP supporting the structure and material to be used

fixing gate on site.

The dimension should be such that it will fit properly and there will be no

leakages through gates during high tide of sea water.

The colour of the shutter should be “ Gray “ PP sheet.

Materials :-

Specification Resin :- Unsaturateed Polyester resin based on Isopathalic Acid

of High reactivity.

Specification of the Material :- Specification of PPGL sheet (GERP 1000)

having high mechanical strength and acid all call proof and properties as

follows.

Properties of PPGL Sheet :-

1 Carcol Hardness : 57 ASTMD -2583

2 Flexural Strength : 160M/m‟ – ISO 08 –1975 (E)

3 Cross Break Strength : 120-140 N/mm

4 Tensile Strength : 95.7 N/mm -ISO/R/527-1966(E)

5 Compressive Strength : 180 N/mm – ISO –178-1975 (E)

6 Flexural Modulus : 4800 N/mm ISO – 178-1975 (E)

7 Percentage Elengation Break

(Percentage at break ) : 4.5%

Properties of steel

Rectangular Pipe

:

1 Size of Pipe : 50mm x 410 mm

Page 161: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

161

Contractor No. of corrections Executive Engineer

2 Thickness : 1.98 mm

3 Area : 340.71 mm2

4 Weight considering density of

Steel : 2.6Kg/Mtr.Density:7.80gm/Cm

3

5 Flexural Strength : 250 N/mm2

- IS 800

6 Permissible Flexural Strength : 165 N/mm2

( 0.66 x fy ) :

Specification for Chopped STR and MAT :-

Fibre glass chopped strand MAT consisting Glass fibre strand approximately

cm. in length laid down in random pattern and uniform thickness and held

together by liquid adhesive binder . The glass composition should be that of

low alkali class “E” .The mat binder should have fast wetting out and good

mouldability with all common used types of polyester resigns. The glass

filaments should have a coat of silence coupling agent. The density of mat

should be 450 Gms/Sqm. The width of mat should be 1.5 packing in rolls of

average 40 kg. The roll should be supplied in a sealed polythene bag packed in

a cardboard box.

Details Specification as follows :-

Width 1.5 cm. the glass fiber used in the manufacture of chopped strand mat of

low alkali type confirming of “K” type glass.

Width 1.5m + 3m.

Strand Box – 29 (Average )

Dry breaking strength :- J-7/Kg-per 100mm width (minimum) gross breaking

strength of laminate (Map ) – Dry –205 (min) Wet –155

Emulsion bonded Mat Binder percent –3.90

Tolerance –2 %

Laminate Proportion

UTS –200 (min) N/Nh width per Kg/M2 giass

Lap shear strength N/NM –7(N-M)

Mass per unit area -450 Gm /M2

% Variation + 8%

Page 162: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

162

Contractor No. of corrections Executive Engineer

Speciation shall be as per IS –3496 IS –4994 of 1973 and 2782 Part 3

COBALT ACCELARATOR

1 Appearance : Intence Blue Liquid

2 Metal : +0.01

3 Viscosity : Less than 0.5 paise

4 Non Volatile Content : Not more than 38%

5 Solvent : Mineral sprits

6 Specific Gravity : 0.90 + 0.015

The above accelerator in combination of ketone peroxide of 50% strength

should be able to get polyester resin in 25 urinates. Test per ISI –6746

Addition 3% Accelerator

2% Peroxide

Hardner :-

This has to be a M.E. ketone peroxide of suitable concentrate which will get

resin in 25 minutes with addition by 2% and 3% of Accelerators. Get test as

per ISI .6746 .

Construction Operation :-

PPGL FRP Rectangular shutters shall be made finished from both side and

fixed in M.S. frame duly coated with reinforcement of two layers of 450 CSM

impression with isothelic grade polyester resin both frame and shutter

fabricated /coated at factory lead proof seat and setting of hinges also made at

factory.

To provide lead 45 degree angle provided to both shutters and frame.

Fixing :-

“C” channel “I” beam duly coated with two layers of 450 CSM impressive with

ISO resin shall be supported from back side of the frame grouted in the side

walls.

Item to Include :-

This item includes manufacture of gate , fixing it in position with skilled

workmanship on site etc.( Excluding Transportation )

Mode of Measurement and Payment :-

Page 163: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

163

Contractor No. of corrections Executive Engineer

The contract rate shall be for Sq. Meter .It includes all manufacturing and

fixing in position .90% rate will be paid after delivery of the gate on site and

balance 10% after fixing off the gate on site .Any damages or defects to gate

within one year should be got repaired by contractor at his own cost. Agency

should give in writing

Item No.19 :-

Providing and laying dry stone masonry (Groynes) excluding pointing for

all leads and lifts etc. complete.

General :-

The item provides for preparing the foundation, filling rubble, hand packing

rubble in the foundation and filling the voids with either gravel or sand as per

the item and as directed by Engineer-in-charge. The item includes all the

labour, material and tools required for completion of the same.

Materials :-

The required materials such as rubble, gravels or sand etc. shall comply with

details of 4 and 5 of general specifications, Gravel shall be natural obtained

from streams in the region and shall not contain particles bigger than 20mm in

diameter. It shall be clean and free from weathered and soft crumbling

portions. The materials are to be brought from private or Government quarries

with contractor‟s own cost and risk.

The sand shall not contain more than 5% of clay or silt.

Method of Execution :-

The bed on which rubble filling is to be laid shall be cleared off all loose

materials leveled and compacted and got approved form the Engineer-in-

charge, before filling. The rubble filling shall be carried out to the dimensions

and level indicated on the drawing or as instructed by the Engineer-in-charge.

The rubble shall be laid with the broadest face down words, and in close

contact with each other, in layers not exceeding 30 cm. thick. Each layer of

rubble shall be packed, wedged with quarry spauls and chips of rubble by

hammer. The further voids shall be filled up with gravels or sand.

Mode of Measurement and Payment :

The contract rate shall be for the unit of one cum. Of filling completed as

specified, with dimension restricted to those shown in the drawing or those as

instructed to do by the Engineer-in-charge or his representative.

Page 164: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

164

Contractor No. of corrections Executive Engineer

Undertaking of the contractor

I/We...............................................................................................

do hereby undertake and identify the Govt. of Maharashtra water resources

department from the following.

We have quoted for the work of..................................................... and hereby declare

to indemnify to Govt. in case of delay in payment of our bills as per tender

agreement and shall not demand interest on bills dues and we further undertake not

to make any claim for losses which will be incurred for the delay in payment as

per procurement of Government.

The progress of the work shall be maintain in order to complete the said

work within stipulated time as per schedule of work provided by the tenderer in

respect of delay of bill by the Dept.

Seal & Signature of the Contractor

Page 165: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

165

Contractor No. of corrections Executive Engineer

List of documents to be scanned and uploaded online

The following documents should be scanned and uploaded on the e-Tendering website

by the tenderers during online bid preparation stage. If any documents / information

are not submitted then the tender will be summarily rejected.

1) Earnest Money Deposit in the form of Government Treasury Challan or Term

Deposit Receipt for one year of required amount pledged in the name of the

Executive Engineer, Kharland Survey & Investigation Division – Pen shall be

enclosed. Certificates of exemptions for payment of earnest money, issued by

competent authority, if valid, shall be accepted instead of the Earnest Money

Deposit.

2) Document certifying the bidder as a registered contractor with Public Works

Department of the Government of Maharashtra valid on date of submission of

tender.

3) Certificate of Registration under Clause 16(i) of Maharashtra Value Added Tax

Act – 2005 or the Certificate of Registration under Rule-8 of The Bombay

Sales Tax Rules-1959. Contractors not submitting any of the two documents

will be liable for Tax Deduction at Source at the rate of 4% of the contract Price.

4) Scanned copy of Demand Draft for Tender Document Fees

5) Copy of Certificate of enrolment under The Maharashtra State Tax on profession,

trades, callings and employment act 1975. (See rule 3(2)) and certificate of

enrollment under section (2) or sub-section (2A) of section 5 of Maharashtra State

Tax on professions, trades, calling and employment act 1975.

6) Details of works of similar type and magnitude carried out by the tenderer

(in Appendix A)

7) Deed of partnership or Article of Association and Memorandum of Association

for limited Company, duly registered, if applicable.

8) Details of works of similar type of works tendered for and in hand with the value

of work unfinished on the last date of submission of tender. The Certificates from

the heads of the office, not below the rank of Executive Engineer, under whom

the works are in progress, should be enclosed (in Appendix B)

9) List of plants and machinery immediately available with the tenderer for use on

this work and list of machinery proposed to be utilized on this work but not

immediately available and the manner in which it is proposed to be procured

(in Appendix C)

10) Proof of having tenderer‟s own machinery.

11) Details of Technical Personnel on the roll of the tenderer (in Appendix D)

Page 166: Government of Maharashtra Water Resources Department ...wrd.maharashtra.etenders.in/tpoimages/wrd/tender/Tender643.pdf6 Contractor No. of corrections Executive Engineer Download &

166

Contractor No. of corrections Executive Engineer

12) A certified copy of Power of attorney for signing the tender in case of proprietary

firm / partnership firm / Ltd. Co. Ltd. Corporation / sponsoring firm made by a

Group of firms.

13) Scanned copy of memorandum

14) Declaration of the contractor

15) Undertaking of the contractor

Note: If, during online bid preparation, any need arises to upload additional

documents, apart from the above mentioned documents, an option to upload

additional documents has been provided in the e-Tendering software which will

be available to bidders during online bid preparation stage.

List of supporting forms / documents / proforma to be downloaded by

contractors

Documents mentioned below, have been made available online as supporting

documents. Bidders will be able to download these documents, along with main

tender document, by following online tender document purchase procedure explained

in main tender document.

1) Drawings

2) Copies of Technical Sanctions and Administration Approvals