gp e getting started din
DESCRIPTION
Bridge design softwareTRANSCRIPT
-
RM Bridge Professional Engineering Software for Bridges of all Types
RM Bridge V8i
September 2010
TRAINING GETTING STARTED MODELER DIN
-
RM Bridge General
Training Getting Started Modeler DIN I
Bentley Systems Austria
Contents
1 General ......................................................................................................................... 1-1
1.1 The Example (Tutorial) ....................................................................................... 1-2
1.2 The Structural System.......................................................................................... 1-2
1.2.1 Support Constraints ......................................................................................... 1-3
1.2.2 Cross-Section ................................................................................................... 1-3
2 Program Start ............................................................................................................... 2-1
3 Creating a New Project Directory................................................................................ 3-1
4 Construction of Axis .................................................................................................... 4-3
4.1 Create an Axis...................................................................................................... 4-4
4.2 Constructing an Axis in Plan ............................................................................... 4-4
4.3 Constructing an Axis in Elevation ....................................................................... 4-7
4.4 Modify ................................................................................................................. 4-9
5 Construction of Cross-Section ..................................................................................... 5-1
5.1 Definitions ........................................................................................................... 5-4
5.1.1 Construction Lines ........................................................................................... 5-4
5.1.2 Cross-section and axis ..................................................................................... 5-4
5.1.3 Cross-section.................................................................................................... 5-4
5.1.4 Cross-section element ...................................................................................... 5-4
5.1.5 Part ................................................................................................................... 5-4
5.1.6 Reference Points .............................................................................................. 5-5
5.1.7 Reference Sets ................................................................................................. 5-5
5.1.8 Layer Management .......................................................................................... 5-5
5.2 Definition of Construction Lines ......................................................................... 5-6
5.3 Cross-Section Elements ....................................................................................... 5-9
5.4 Definition of Reference-Sets ............................................................................. 5-11
5.4.1 Connection Points .......................................................................................... 5-11
5.4.2 Stress Points ................................................................................................... 5-13
5.4.3 Reinforcement Groups ................................................................................... 5-15
6 Segment Definition ...................................................................................................... 6-1
6.1 Definition of the Structural System ..................................................................... 6-2
6.2 Definition of Segment Points .............................................................................. 6-2
6.3 Cross-Section Assignment ................................................................................... 6-3
-
RM Bridge General
Training Getting Started Modeler DIN II
Bentley Systems Austria
6.4 Assignment of Element Numbers ........................................................................ 6-4
7 Definition of Supports ................................................................................................. 7-1
7.1 Geometrical position of bearing: ......................................................................... 7-1
7.2 Definition of Support ........................................................................................... 7-2
8 3D - View .................................................................................................................... 8-1
9 Export to Analyzer .................................................................................................... 9-1
9.1 Export to Analyzer ............................................................................................ 9-1
10 Data management and backup ................................................................................... 10-2
-
RM Bridge General
Training Getting Started Modeler DIN 1-1
Bentley Systems Austria
1 General
In this example, the necessary definitions for modeling the bridge structure will be shown
step by step. The subprogram Modeler is a geometry-preprocessor. The following geome-
tric data should be defined:
Axes The street-axes geometric location. The definition is done in ground, elevation plan. It provides straight line,
circle, spiral and cubic curve elements which are usual-
ly used for the street design.
Cross-section Cross-section definition, typical for cross-section in main girder (hollow box) and pier (rectangle).
Segment The different structure parts are assigned to a seg-ment.(i.e. segment for main girder, pier, link segment).
The segments will be closed to each other according to
the static connection after the assignment.
Static system Preparation for the static system (the static analyze is executed in RMBridge)
The start point of one axis should be located in the global-coordination system in ground-
plan(X and Z-coordination) or in elevation plan (the desired position and the height) at first.
The segment is created by assigning cross-section to one section of an axis. Use the axis
station to define the start point and the end point of a section.
The segment is subdivided into segment points. The cross-sections are assigned to these
points. In the segment point list (in Modeler), each segment point has its own station and is
defined with certain distance to the next one. After the export to RMBridge, the stations will
be converted into structure nodes. The distance between the segment points will be the
length of element. They are used for static analyze in RMBridge.
-
RM Bridge General
Training Getting Started Modeler DIN 1-2
Bentley Systems Austria
1.1 The Example (Tutorial)
A two span T-beam structure (see Fig. 1) will be created, it consists of one axis, one seg-
ment (60 m).
Fig. 1: T-Beam with 2*30m span wise
1.2 The Structural System
A1 A3 30m
10x3m
A2
10x3m
30m
Fig. 2: Structural System
Axis in plan: Part 1: straight line: Station: 0-60 m
Axis in elevation: Part 1.: straight line: Station: 0-60 m
The numbering: Node numbers (span wise): 101-111-121
Element numbers (span wise): 101-110,111-120
Support (spring) elements: 1100, 1200, 1300
-
RM Bridge General
Training Getting Started Modeler DIN 1-3
Bentley Systems Austria
1.2.1 Support Constraints
A 1 A 2
X
Z
101-110
A 3
111-120
1100 1200 1300
Fig. 3: Defined Support Constraints
1.2.2 Cross-Section
8.00 m
3.50 m 3.40 m
0.10 m
1.00 m
2.0
0 m
1.6
5 m
0.2
5 m
0.1
0 m
Fig. 4: T-Beam Cross-section
-
RM Bridge Program Start
Training Getting Started Modeler DIN 2-1
Bentley Systems Austria
2 Program Start
After the program installation, you can find the RM-Icon on the desktop.
The program can be started by double-clicking this symbol or selection in the window-
startmenu.
-
RM Bridge Creating a New Project Directory
Training Getting Started Modeler DIN 3-1
Bentley Systems Austria
3 Creating a New Project Directory
The program starts and the main window of RmBridge appears.
Double-click the RM-Icon to start the program.
If the program starts for the first time, RM-Default database(material, tables and variables
which are depend on different standards) and cross-section catalog will be loaded, the project
starts in the installation directory. The program starts always in the last work directory. The
complete pad is shown on the top of main window.
First le
vel
-
RM Bridge Creating a New Project Directory
Training Getting Started Modeler DIN 3-2
Bentley Systems Austria
Cre
ate
a n
ew
pro
ject dir
ecto
ry
Use File change work directory in main
menu to change the
project into the desired
directory.
The project should be
initialized. In the set-
ting window, you can
set some general op-
tions (i.e. Standard,
material group).
After the initialization,
the modelling-process
can begin.
-
RM Bridge Construction of Axis
Training Getting Started Modeler DIN 4-3
Bentley Systems Austria
4 Construction of Axis
Axis elements are used to define the axis in plan. For this example the axis is straight.
Click Modeler in the navigation to start Modeler. Use Modeler to prepare the geometry of
the bridge. The project is shown in the ground plan (empty yet).
The input window changes according to the selected geometric definition (navigation
menu). Modeler can be closed by pressing Esc-button or click the close icon x. It is also possible to exit Modeler that if you switch to another function, which could be found in
the navigation menu and not a sub-function of Modeler.
In helpbrief help for Icons you can find the description for different functions.
Note: Recalc-function in Modeler(GP) and Analyzer(RM) are not the same. In Modeler, the Re-calcfunction is used to export the Modeler data to Analyzer. But in Analyzer, the Recalc function is used to start the calculation. The calculation options can also be set in the Re-calc-function.
The import and export function for Tcl-file works in the same manner. The import and export
process is executed in the Modeler database (if Modeler is active) or in the Analyzer database
(if Analyzer is active).
Close Modelers
View and zoom function
Functions, which are pro-
vided in ground plan
Recalc(Export the data from Modeler to Analyzer (RM))
Navigation menu
Use tcl files to import
and export the Modeler
data.
Input window Axes in ground plan
-
RM Bridge Construction of Axis
Training Getting Started Modeler DIN 4-4
Bentley Systems Austria
There is a detailed description about data management and backup in RmBridge, see
chapter 1010.
4.1 Create an Axis
The geometric definition of one axis consisting of axis-elements. The definition should
be done in ground, elevation plan. The axis-element can be a straight line, circle, spiral
and cubic curve elements.
Define a
n A
xis
New Axis:
A new axis should be
defined at first. Select
the axis-menu in the navigation. Click the
right mouse-button and
choose new axis
Confirm
If there are more axes existing, double-click the desired axis to select it.
Active
The currently active
axis is shown in the
information-bar at the
left lower corner (
Axis1 in this exam-ple).
4.2 Constructing an Axis in Plan Axis in plan: straight line: Station: 0-60 m
Select ground plan list in the navigation-menu.
-
RM Bridge Construction of Axis
Training Getting Started Modeler DIN 4-5
Bentley Systems Austria
Select P0 in order to
define the starting point
of the axis in the
ground plan. The coordinates for the
starting points (X =
east, Y = north).
Confirm
Keep the default set for this example (P0 (0.0/0.0).). The new axis goes along the X-
direction, no angle needs to be defined. After input confirmation the point with the speci-
fied direction are visible on the screen. Please use the Zoom functions at the left vertical tool bar (or use Free hand symbols, see next page) to view.
Select Append straight
line to axis from the
tool-bar.
The length of the
straight line is 60.0 m.
Confirm
The axis is now defined in the ground plan and is displayed on the screen.
-
RM Bridge Construction of Axis
Training Getting Started Modeler DIN 4-6
Bentley Systems Austria
Top level of M
OD
ELE
R w
ith a
xis
in p
lan
Alternatively to the zooming facilities, the so called free hand symbols can be used. Such a free hand symbol is executed with the left mouse button and simultaneously pressing
[Ctrl]-key on the keyboard. The free hand symbolV creates a full view of the cur-rently available items.
The other free hand symbols can be viewed by clicking the explanation button on top of the screen.
-
RM Bridge Construction of Axis
Training Getting Started Modeler DIN 4-7
Bentley Systems Austria
4.3 Constructing an Axis in Elevation Axis in Elevation: planar line: Station: 0-60 m
Select elevation graphic or elevation list to specify the elevation.
Select P0 to define the starting point of the
axis.
The default setting can
be kept.
Confirm
Select the button ap-
pend straight line by
station and set Station
Difference to 60 m..
Confirm
Now the axis definition is finish. You can use the zoom-function as explained above to
check the axis.
-
RM Bridge Construction of Axis
Training Getting Started Modeler DIN 4-8
Bentley Systems Austria
Ele
vation o
f A
xis
-
RM Bridge Construction of Axis
Training Getting Started Modeler DIN 4-9
Bentley Systems Austria
4.4 Modify
The Delet last axis element button allows to delete the last input.
Modific
atio
ns
Modifications to the axis
definition in plan and
elevation can be done in
the ground plan list or
elevation list.
In the list, the existing
element can be modi-
fied. By modification,
you should pay atten-
tion, that some elements
are related to each other,
they can only be
changed in the right se-
quence.
The upcoming listing
allows to change data in
any line (radius, slope,
lengths, ..).
Confirm with .
and the win-
dow.
Use Modify button to modify.
Use Delete button to eliminate the input data.
-
RM Bridge Construction of Cross-Section
Training Getting Started Modeler DIN 5-1
Bentley Systems Austria
5 Construction of Cross-Section
8.00 m
3.50 m 3.40 m
0.10 m
1.00 m
2.0
0 m
1.6
5 m
0.2
5 m
0.1
0 m
Fig. 5: Cross Section
Click cross-section in the navigation-menu with the right mouse-button. Select New Cross Section in the context.
Define C
ross-S
ection
The basic definitions
for the cross-section
name can be used, con-
firm with .
Confirm
-
RM Bridge Construction of Cross-Section
Training Getting Started Modeler DIN 5-2
Bentley Systems Austria
The new cross-section is listed
in the navigation-tree on your
left. Several cross-sections can
be defined in one project, only
one is needed for this example.
Changing between the cross-
sections is done by double-
clicking on the desired cross
section.
Aktive C
S
The active CS is always dis-
played at the lower window on
the information-bar. All further
CS definitions will refer to this
Cross-Section (cross1).
-
RM Bridge Construction of Cross-Section
Training Getting Started Modeler DIN 5-3
Bentley Systems Austria
Select the cross-section to open the graphic input screen.
CS
Win
dow
Draw functions for con-
struction line
Draw functions for FE-Element in
Cross-section network
Draw functions for Refe-
rence point
Draw functions for Dimen-
sion line
Different view- and
zoom functions
Reference-Sets (Click the arrow to
open it) and shows the active Ref-
Set.
Cross-section Part (Click the arrow to
open it) and shows the active parts.
Variables in the cross-section (Click
the arrow to open it) and shows the
active variables or constants, which are
used in this cross-section to define the
construction line.
Basic construction line CL1 and CL2 ()
(The default directions are along Z- and
Y-coordination axes in the cross-section)
Default position for part 1 (in the inter-
section point of CL1 and CL2). It is
marked by a small flag and the part
number.
Direction
-
RM Bridge Construction of Cross-Section
Training Getting Started Modeler DIN 5-4
Bentley Systems Austria
5.1 Definitions
5.1.1 Construction Lines
The construction line (CL) is needed for locating the intersection points, which are used to
draw a FE-element. The FE-elements construct the cross-section network. Use the draw-
functions to create the construction lines. The construction lines are referenced on each
other (i.e. parallel to). All the construction lines are depends on CL1 (horizontal) or CL2 (vertical).
Note: Different dependencies of construction lines on each other are important for defining construction lines
with variables. The assigned variables are given in Tables and formulas. The influence of variables on the other construction lines should be considered.
5.1.2 Cross-section and axis
The default position of CL1 and CL2 are the Z- and Y- coordinate-axis of cross-section.
The intersection point of CL1 and CL is the connection point of cross-sections.
Note: Use Offset-option can move cross-section position (CL1, CL2) relate to the Axes.
5.1.3 Cross-section
In order to create a cross-section, the elements are required, which defined by intersection
point of construction lines. Every element is a build-part of the cross-section.
Note: The construction of cross-section is done in the direction against X-axis.
5.1.4 Cross-section element
The shape of the cross-section is defined by individual elements. These elements are based
on the intersection points of the construction lines. These 2 dimensional elements are cre-
ated with either 3 or with 4 corner nodes. A polygonal line around the element defines the
border, the first and the last polygon part close the element. The order of input does not
matter (cycle), the polygonal line must not cross itself.
5.1.5 Part
The cross-section elements with different properties can be summarized into different
groups (part). I.e. For the composite cross-section, the concrete elements and the steel ele-
ments should be assigned into different groups.
Note: Parts can also be used to assign the different static length system of one cross-section into
different part. (i.e. Doppel-T cross-section prepared as Grillage, that means instead of two
single cross-section (each -T)to two different segments, you just need one cross-section and one segment, the cross-section consists of two parts for two separate longitudinal ele-
ment series ),
-
RM Bridge Construction of Cross-Section
Training Getting Started Modeler DIN 5-5
Bentley Systems Austria
5.1.6 Reference Points
The intersection of CL1 and CL2 represents the axis of the bridge and acts as a reference
point for the position of the cross-section in the overall 3D geometry.
5.1.7 Reference Sets
In addition to the cross-section geometry information for the structural analysis such as
temperature points, reinforcement layers, stress points and others are defined in so called
reference sets. Properties (e.g. material) of a Reference Set can be defined and grouped in so called Attribute Sets.
5.1.8 Layer Management
Each object of the cross-section can exist in all, one or several graphical layers.
-
RM Bridge Construction of Cross-Section
Training Getting Started Modeler DIN 5-6
Bentley Systems Austria
5.2 Definition of Construction Lines
Six vertical and four horizontal lines are needed for the following cross-section. First paral-
lel and vertical lines with a distance of 4.0m to the centre are defined.
Consta
nts
Set the constant to 4.0
in the vari-ables/constants-input field.
Press the icon Parallel Line to activate this function. The graphic cursor is then displayed
as continuous line indicating a function being active.
During the execution of this action the following information is displayed in the status
line:
Select the vertical line as basic line (CL_2).
During the execution of this action the following information is displayed in the status
line:
Click to the right side of the selected line to create a new construction line. This new CL
has a distance of 4.0m to the centre.
Create the second line on the other side in the same way:
Select the vertical basic line.
Click to the left side of the selected basic line (CL_2) to create a new CL. This new CL
has a distance of 4.0m to the centre.
-
RM Bridge Construction of Cross-Section
Training Getting Started Modeler DIN 5-7
Bentley Systems Austria
CS
win
dow
The next figure shows the rest of the needed CLs with the corresponding distances . The
procedure is the same as explained above. Click at the vertical or horizontal basic line and
set the constant to the appropriate value.
-
RM Bridge Construction of Cross-Section
Training Getting Started Modeler DIN 5-8
Bentley Systems Austria
The following overview shows all necessary construction lines for this example:
CS
Win
dow
4.00 4.00
0.2
5
2.0
0
0.6
0.5 0
.35
Basic lines CL1 and CL2
-
RM Bridge Construction of Cross-Section
Training Getting Started Modeler DIN 5-9
Bentley Systems Austria
5.3 Cross-Section Elements
After all CLs are available the cross-section elements can be defined:
Activate the "Cross-section element by selecting the appropriate icon.
During the execution of this action the following information is displayed in the status
line:
Click at the intersection points of the construction lines to create the corner nodes 1, 2, 3
and 4 of the new element (see picture below). The new element is automatically assign
to part 1, thus the number 1 appears in the middle of the element. (Different parts are
needed in composite constructions, see next training)
CS
Win
dow
-
RM Bridge Construction of Cross-Section
Training Getting Started Modeler DIN 5-10
Bentley Systems Austria
All other elements are generated in the same way. Please make use of the zoom functions
to properly select the intersection points. A wrong definition can be interrupted by hitting
the key (or right mouse button). A wrongly defined element can be selected (ele-
ment line changes colour) and deleted with the delete icon.
Elements can be copied and mirrored to speed up the input. These icons can be found with
right click above the icon Linear 4-Point-Element.
The cross-section of this example consist of 4 elements only, see picture below:
CS
Win
dow
-
RM Bridge Construction of Cross-Section
Training Getting Started Modeler DIN 5-11
Bentley Systems Austria
5.4 Definition of Reference-Sets
Four sets are used in this example: 2 for reinforcement layer (top and bottom), one for the
stress points (to calculate stress at top and bottom fibre at a certain point). The forth set is
needed to define the geometrical position of the support springs (connection points).
5.4.1 Connection Points
Select the arrow key next to the reference point.
Refe
rence
-Sets
Create a new reference
set with the name sup-port and select the type connection point .
Confirm
Connection p
oin
ts
This new reference set
is inserted in the table
of existing reference
sets. Several sets can be
defined in one project.
Select the wanted set
and hit to change
the active set
Insert
Active
The activated reference
set will be displayed in
the input field. All
definitions on the
cross-section level will
now refer to this refer-
ence set.
-
RM Bridge Construction of Cross-Section
Training Getting Started Modeler DIN 5-12
Bentley Systems Austria
Select the icon for the
connection point defini-
tion.
Connection p
oin
t
Select the intersection
of CLs with cross-
section element border
to define the position of
the reference point.
Sin
gle
Po
int
The upcoming window
asks for the name of
this new point (CP0 in
this case).
Confirm
-
RM Bridge Construction of Cross-Section
Training Getting Started Modeler DIN 5-13
Bentley Systems Austria
5.4.2 Stress Points
Open the reference set input window by clicking the arrow key next to it.
Refe
rence
-Sets
Select Insert after button to add another
reference set to the list-
ing.
Insert
Str
ess P
oin
ts
Create a new set with
the name STRESS and select the type
Stress check points . The Attribute-Set is
named similar to the set
name: STRESS
Confirm
The newly defined reference set is inserted in the table of available reference sets.
Select the new set and hit to activate the reference set.
Active
The active reference set
is displayed in the
lower side of the win-
dow. All definitions
from now on will refer
to the active reference
set (STRESS in this case).
-
RM Bridge Construction of Cross-Section
Training Getting Started Modeler DIN 5-14
Bentley Systems Austria
Select the icon for the
stress point definition.
The intersection point
is selected by clicking
it with the cursor in
order to define the
wanted position of the
reference point.
The upcoming window
asks for the definition
of the point name for
the selected point
(SP_TOP in this case).
Confirm
Select the icon for the
stress point definition.
The intersection point
is selected by clicking
it with the cursor in
order to define the
wanted position of the
reference point.
The upcoming window
asks for the definition
of the point name for
the selected point
(SP_BOT in this case).
Confirm
-
RM Bridge Construction of Cross-Section
Training Getting Started Modeler DIN 5-15
Bentley Systems Austria
5.4.3 Reinforcement Groups
Reinforcement is defined either as one or more single points or polygons. Reinforcement
areas that are assigned or automatically calculated later are distributed over these points and
polygons. Positions are defined relative to construction intersection points or cross-section
element nodes. The sole geometry is stored in form of Reference-Sets, which may be
grouped and addressed by Attribute-Sets. Attribute-Sets hold additional information such as
material definitions. In most cases the Attribute-Set names are identical to the Reference-
Set names.
First a Reference-Set is created as already shown above.
Open the reference set input window by clicking the arrow key next to it.
Refe
rence
-Sets
Use the Insert after button to define a new
Reference-Set.
Insert
Rein
forc
em
ent
Top
Create a new Refer-
ence-Set with name
REBAR_TOP and select type Bending Reinforcement. Use the same name again
(REBAR_TOP) for the Attribute-Set and
assign the wanted ma-
terial.
Confirm
The newly defined reference set is inserted in the table of available reference sets.
Select the new set and hit to activate the reference set.
-
RM Bridge Construction of Cross-Section
Training Getting Started Modeler DIN 5-16
Bentley Systems Austria
Select the appropriate
icon for the reinforce-
ment definition.
Select the element cor-
ner to which the refer-
ence point is relative to
using the mouse cursor.
The upcoming window
requires data for point
type, point name and
offset to the selected
element corner. The
new point will be the
start of the reinforce-
ment polygon.
Confirm
Select the appropriate
icon for the reinforce-
ment definition.
Select the element cor-
ner to which the refer-
ence point is relative to
using the mouse cursor.
The upcoming window
requires data for point
type, point name and
offset to the selected
element corner. The
new point will be the
end of the reinforce-
ment polygon.
Confirm
After the reinforcement definition at the top layer is defined the bottom reinforcement will
following as next:
-
RM Bridge Construction of Cross-Section
Training Getting Started Modeler DIN 5-17
Bentley Systems Austria
Open the reference set input window by clicking the arrow key next to it.
Refe
rence
-Sets
Use the Insert after button to define a new
Reference-Set.
Insert
Rein
forc
em
ent B
ottom
Create a new Refer-
ence-Set with name
RBAR_BOT an se-lect type Bending Re-inforcement. Use the same name again
(REBAR_BOT) for the Attribute-Set and
assign the wanted ma-
terial.
Confirm
The newly defined reference set is inserted in the table of available reference sets.
Select the new set and hit to activate the reference set.
-
RM Bridge Construction of Cross-Section
Training Getting Started Modeler DIN 5-18
Bentley Systems Austria
Select the appropriate
icon for the reinforce-
ment definition.
Select the element cor-
ner to which the refer-
ence point is relative to
using the mouse cursor.
The upcoming window
requires data for point
type, point name and
offset to the selected
element corner. The
new point will be the
start of the reinforce-
ment polygon. Define
the polygon end point
in the same way.
-
RM Bridge Segment Definition
Training Getting Started Modeler DIN 6-1
Bentley Systems Austria
6 Segment Definition
The structural system consists of 2 span girders with a constant T-shaped cross-section.
Only one Segment is needed for this project.
Click Segment in the navigation-menu with the right mouse-button. Select New seg-ment in the contex.
De
fine S
egm
en
t
Name, type, reference
axis and eccentricity
type can be defined for
the new segment in the
upcoming window.
For this example the
default set is ok and the
name is seg1. After confirmation the new
segment will be avail-
able in the segment
listing.
Confirm
The newly created segment is displayed in the table of existing segments. Several seg-
ments may exist for one project. Changing the currently active segment is done by click-
ing the wanted segment and confirming with .
-
RM Bridge Segment Definition
Training Getting Started Modeler DIN 6-2
Bentley Systems Austria
6.1 Definition of the Structural System
The next step in MODELER is the assembly of the structural system. A structural system consists of Elements, Nodes, Cross-sections and Material properties.
Each segment consists of several segment points. Each segment point is defined in 3D with
its position along the axis. The structural nodes are created using these segment points, the
structural elements are generated using the spacing between the segment points. Material
properties are assigned to the elements, the cross-sections are assigned to the segment
points.
6.2 Definition of Segment Points
Open the segment point listing by clicking the symbol on the right side.
Segm
ent P
oin
t Lis
ting
The table will be empty
since no data has bee n
defined yet.
Define new segment points by clicking the "Insert after" - button (at the left of the gen-
eral screen).
The structural system shall start at 0 and shall end at Station 60.0 m.
All elements will have a length of 3.0m, 20 elements will finally compose the girder. 10
elements for the left span and 10 elements for the right span.
-
RM Bridge Segment Definition
Training Getting Started Modeler DIN 6-3
Bentley Systems Austria
Insert
Segm
ent
Poin
ts
The input for the Seg-
ment Points can be seen
in the Figure on the left
side.
A step of 3 m is used to define segment
points that will reflect
the element lengths of
the structural system.
Confirm
Segm
ent P
oin
ts
The structural system is
herewith defined. (60m
long with elements of 3
m length).
6.3 Cross-Section Assignment
The assigned cross-sections are shown in the segment list. The column OK describes if the cross-section at this stage is correctly defined for the further procedure. The + shows that at this station the appropriate cross-section is assigned. If this sign switches to - the cross-section was recently modified after it had been assigned to the segment.. In the lower
list all specified variables, parts and connections of the cross-section are displayed. Later on
tables and formulas will be assigned to those variables.
-
RM Bridge Segment Definition
Training Getting Started Modeler DIN 6-4
Bentley Systems Austria
6.4 Assignment of Element Numbers
Ele
ment
num
be
ring
The element and node
numbering for the
whole system can be
done at once. First se-
lect parts to view the undefined parts. Only
one line is displayed
since the cross-section
exists only of one part.
The element numbering should start at segment point 1, the first element and node-number
should be 101. At the end of the first element (101) the nodenumber is 102. The in-crement is definition by 1.
The properties of the material is:C_35/45 (DIN 1045-1) will be applied.
All elements are grouped with the name MG (main girder).
Activate the 'Modify' - Function at the left of the table to open the input pad.
-
RM Bridge Segment Definition
Training Getting Started Modeler DIN 6-5
Bentley Systems Austria
Ele
ment
num
be
ring
Definition for all seg-
ment points (1 to 21):
See Fig. on the left
siede.
Confirm
Segm
ent P
oin
t L
isting
The numbering can be
controlled by stepping
through the segment
point listing in the up-
per table.
The data to the cur-
rently marked line is
shown in the lower
table.
Any modification after this initial definition can be done, but must be exe-
cuted in MODELER before export the project to ANALYZER .
-
RM Bridge Segment Definition
Training Getting Started Modeler DIN 6-6
Bentley Systems Austria
The cross-section 'cross1' is locked after this initial assignment. Any modification to the
cross-section requires to unlock the cross-section (program asks for it). Again must be executed in MODELER before the export to ANALYZER starts.
-
RM Bridge Definition of Supports
Training Getting Started Modeler DIN 7-1
Bentley Systems Austria
7 Definition of Supports
The following definitions are required:
A connection point is required for the support. It should be defined in the cross-section (see Definition of Reference-Sets).
Create the connection between sub- and superstructure with spring elements- see be-low:
7.1 Geometrical position of bearing:
CS
W
indow
/ A
dd. P
oin
ts
The green, triangular
symbol attached at the
bottom of the girder is
the geometrical posi-
tion of the bearing. The
definition is already
done in chapter 5.4.1.
-
RM Bridge Definition of Supports
Training Getting Started Modeler DIN 7-2
Bentley Systems Austria
7.2 Definition of Support
Open the segment point table.
Select the first line in the upper listing (Station 0).
Select the button for connection to open the corresponding input window.
Select insert before to see the possible
choices.
Select New spring-0 to open the correspond-
ing spring definition
window.
-
RM Bridge Definition of Supports
Training Getting Started Modeler DIN 7-3
Bentley Systems Austria
Supp
ort
De
finitio
n
The support spring
1100 represents the
connection between
girder and soil. The
position of this spring
element is done with
the assignment to the
nodes (Node1 = 0 =
earth, Node2 = 101 top
of girder)
Switch over to the input
of spring constants.
Press
Spri
ng C
onsta
nts
The spring constants
are defined here. The
element 1100 repre-
sents the support condi-
tion in vertical (X) and
transverse (Z) direc-
tion. A constant of 1e8
represents the stiffness
of the support condi-
tion.
Confirm
The newly defined spring element will be displayed in the table for support definitions.
-
RM Bridge Definition of Supports
Training Getting Started Modeler DIN 7-4
Bentley Systems Austria
Supp
ort
De
finitio
n
Press the i-button to see a graphical picture
of the support.
Several conditions can
be defined at any seg-
ment point. Select the
wanted line in the table
to see the correspond-
ing support condition.
The same procedure is repeated for the other two connections (segment point 11 und 21).
The element numbers shall be 1200 and 1300.
The table below shows the sprig constants for the spring elements.
Element 1100 1200 1300
Spring constants KN/M KN/M KN/M
CX 1e8 1e8 1e8
CY 0 1e8 0
CZ 1e8 1e8 1e8
CMX 0 0 0
CMY 0 1e8 0
CMZ 0 0 0
-
RM Bridge 3D - View
Training Getting Started Modeler DIN 8-1
Bentley Systems Austria
8 3D - View
The completed girder can be viewed in 3D now.
Select the corresponding button to open the 3D view.
3D
- V
iew
-
RM Bridge Export to Analyzer
Training Getting Started Modeler DIN 9-1
Bentley Systems Austria
9 Export to Analyzer
9.1 Export to Analyzer
The completed structural system can be transformed into a structural model for further use
in Analyzer.
Recalc: Some sub-functions are provided in the Recalc window for Modeler. They are separate
calculation parts. For complex project, sometimes the evaluate formulas check box
will not be selected to reduce the calculation time.
The Evaluate formulas has to be selected for further calculation options. Hamblyis a special algorithm to find the common gravity line of several different cross-section
areas. Precast segmentation is used in RMCast.
Check numbering of
elements and nodes:
To check if any element or node-number is used for more times. This option will be
set automatically, if the Create model is set.
Create model: Export the Modeler data to Analyzer. There are three sub-options can be set.
(1)Keep the original model data in Analyzer, only the new data will be added into the
database. (2) initialize the model structure in analyzer or (3) initialize the whole ana-
lyzer data (include the input data in Analyzer).
Select 'Recalc'-Icon to start the calculation and export the Modeler data to Analyzer .
Export
to A
na
lyzer
Export
Set the project calcula-
tion options. Click
to start the cal-
culation. After the cal-
culation, the Modeler
data can be exported to
Analyzer, if the Create
model option is set.
Close the input-window
to exit Modeler. The Analyzer part can begin.
-
RM Bridge Data management and backup
Training Getting Started Modeler DIN 10-2
Bentley Systems Austria
10 Data management and backup
Since the version RmBridge V8i, Modeler (previously GP) is the geometric preprocessor,
Analyzer (previously RM) is mainly used to prepare the static calculation. And they are
executed in the same user interface.
Nevertheless, Modeler and Analyzer have separate database. Executes the initialization,
both database are initialized.
The input-data writes according to the input window into different databases. Restart the
program, the database is in the last work state.
It is suggested to create backup-files, when a certain state is reached and the next modeling
state will begin. It cannot return to an unsaved state (Undo function). The backup-files are separate in Modeler and Analyzer database.
The database is exported in ASCII-text file (Tcl-format). That means the project-data can
be read and edited, they are stored in a readable text-file (use Text-Editor). In the text-
editor, it is possible to use script-languages for defining variables (loops and if..then) and so on. It simplifies and speeds up the input-process. When the project-data is imported,
the programmed routines are also executed.
By export and import Modeler-data, the entire project is always saved or loaded.
By export the Analyzer-database, there are additional options, which are able to assign cer-
tain project-part to export (Default: the entire project). So the single project-part can be
saved in a separate Tcl-file for further use. By import Tcl-file project data in Analyzer is
possible to make a part import Add to project, which just adds this Tcl-file to the current project. The option New project executes an initialization of the database and then loads the Tcl-file.
GeneralThe Example (Tutorial)The Structural SystemSupport ConstraintsCross-Section
Program StartCreating a New Project DirectoryConstruction of AxisCreate an AxisConstructing an Axis in PlanConstructing an Axis in ElevationModify
Construction of Cross-SectionDefinitionsConstruction LinesCross-section and axisCross-sectionCross-section elementPartReference PointsReference SetsLayer Management
Definition of Construction LinesCross-Section ElementsDefinition of Reference-SetsConnection PointsStress PointsReinforcement Groups
Segment DefinitionDefinition of the Structural SystemDefinition of Segment PointsCross-Section AssignmentAssignment of Element Numbers
Definition of SupportsGeometrical position of bearing:Definition of Support
3D - ViewExport to AnalyzerExport to Analyzer
Data management and backup