gp e getting started din

47
RM Bridge Professional Engineering Software for Bridges of all Types RM Bridge V8i September 2010 TRAINING GETTING STARTED MODELER DIN

Upload: orlando-lopes

Post on 30-Sep-2015

13 views

Category:

Documents


0 download

DESCRIPTION

Bridge design software

TRANSCRIPT

  • RM Bridge Professional Engineering Software for Bridges of all Types

    RM Bridge V8i

    September 2010

    TRAINING GETTING STARTED MODELER DIN

  • RM Bridge General

    Training Getting Started Modeler DIN I

    Bentley Systems Austria

    Contents

    1 General ......................................................................................................................... 1-1

    1.1 The Example (Tutorial) ....................................................................................... 1-2

    1.2 The Structural System.......................................................................................... 1-2

    1.2.1 Support Constraints ......................................................................................... 1-3

    1.2.2 Cross-Section ................................................................................................... 1-3

    2 Program Start ............................................................................................................... 2-1

    3 Creating a New Project Directory................................................................................ 3-1

    4 Construction of Axis .................................................................................................... 4-3

    4.1 Create an Axis...................................................................................................... 4-4

    4.2 Constructing an Axis in Plan ............................................................................... 4-4

    4.3 Constructing an Axis in Elevation ....................................................................... 4-7

    4.4 Modify ................................................................................................................. 4-9

    5 Construction of Cross-Section ..................................................................................... 5-1

    5.1 Definitions ........................................................................................................... 5-4

    5.1.1 Construction Lines ........................................................................................... 5-4

    5.1.2 Cross-section and axis ..................................................................................... 5-4

    5.1.3 Cross-section.................................................................................................... 5-4

    5.1.4 Cross-section element ...................................................................................... 5-4

    5.1.5 Part ................................................................................................................... 5-4

    5.1.6 Reference Points .............................................................................................. 5-5

    5.1.7 Reference Sets ................................................................................................. 5-5

    5.1.8 Layer Management .......................................................................................... 5-5

    5.2 Definition of Construction Lines ......................................................................... 5-6

    5.3 Cross-Section Elements ....................................................................................... 5-9

    5.4 Definition of Reference-Sets ............................................................................. 5-11

    5.4.1 Connection Points .......................................................................................... 5-11

    5.4.2 Stress Points ................................................................................................... 5-13

    5.4.3 Reinforcement Groups ................................................................................... 5-15

    6 Segment Definition ...................................................................................................... 6-1

    6.1 Definition of the Structural System ..................................................................... 6-2

    6.2 Definition of Segment Points .............................................................................. 6-2

    6.3 Cross-Section Assignment ................................................................................... 6-3

  • RM Bridge General

    Training Getting Started Modeler DIN II

    Bentley Systems Austria

    6.4 Assignment of Element Numbers ........................................................................ 6-4

    7 Definition of Supports ................................................................................................. 7-1

    7.1 Geometrical position of bearing: ......................................................................... 7-1

    7.2 Definition of Support ........................................................................................... 7-2

    8 3D - View .................................................................................................................... 8-1

    9 Export to Analyzer .................................................................................................... 9-1

    9.1 Export to Analyzer ............................................................................................ 9-1

    10 Data management and backup ................................................................................... 10-2

  • RM Bridge General

    Training Getting Started Modeler DIN 1-1

    Bentley Systems Austria

    1 General

    In this example, the necessary definitions for modeling the bridge structure will be shown

    step by step. The subprogram Modeler is a geometry-preprocessor. The following geome-

    tric data should be defined:

    Axes The street-axes geometric location. The definition is done in ground, elevation plan. It provides straight line,

    circle, spiral and cubic curve elements which are usual-

    ly used for the street design.

    Cross-section Cross-section definition, typical for cross-section in main girder (hollow box) and pier (rectangle).

    Segment The different structure parts are assigned to a seg-ment.(i.e. segment for main girder, pier, link segment).

    The segments will be closed to each other according to

    the static connection after the assignment.

    Static system Preparation for the static system (the static analyze is executed in RMBridge)

    The start point of one axis should be located in the global-coordination system in ground-

    plan(X and Z-coordination) or in elevation plan (the desired position and the height) at first.

    The segment is created by assigning cross-section to one section of an axis. Use the axis

    station to define the start point and the end point of a section.

    The segment is subdivided into segment points. The cross-sections are assigned to these

    points. In the segment point list (in Modeler), each segment point has its own station and is

    defined with certain distance to the next one. After the export to RMBridge, the stations will

    be converted into structure nodes. The distance between the segment points will be the

    length of element. They are used for static analyze in RMBridge.

  • RM Bridge General

    Training Getting Started Modeler DIN 1-2

    Bentley Systems Austria

    1.1 The Example (Tutorial)

    A two span T-beam structure (see Fig. 1) will be created, it consists of one axis, one seg-

    ment (60 m).

    Fig. 1: T-Beam with 2*30m span wise

    1.2 The Structural System

    A1 A3 30m

    10x3m

    A2

    10x3m

    30m

    Fig. 2: Structural System

    Axis in plan: Part 1: straight line: Station: 0-60 m

    Axis in elevation: Part 1.: straight line: Station: 0-60 m

    The numbering: Node numbers (span wise): 101-111-121

    Element numbers (span wise): 101-110,111-120

    Support (spring) elements: 1100, 1200, 1300

  • RM Bridge General

    Training Getting Started Modeler DIN 1-3

    Bentley Systems Austria

    1.2.1 Support Constraints

    A 1 A 2

    X

    Z

    101-110

    A 3

    111-120

    1100 1200 1300

    Fig. 3: Defined Support Constraints

    1.2.2 Cross-Section

    8.00 m

    3.50 m 3.40 m

    0.10 m

    1.00 m

    2.0

    0 m

    1.6

    5 m

    0.2

    5 m

    0.1

    0 m

    Fig. 4: T-Beam Cross-section

  • RM Bridge Program Start

    Training Getting Started Modeler DIN 2-1

    Bentley Systems Austria

    2 Program Start

    After the program installation, you can find the RM-Icon on the desktop.

    The program can be started by double-clicking this symbol or selection in the window-

    startmenu.

  • RM Bridge Creating a New Project Directory

    Training Getting Started Modeler DIN 3-1

    Bentley Systems Austria

    3 Creating a New Project Directory

    The program starts and the main window of RmBridge appears.

    Double-click the RM-Icon to start the program.

    If the program starts for the first time, RM-Default database(material, tables and variables

    which are depend on different standards) and cross-section catalog will be loaded, the project

    starts in the installation directory. The program starts always in the last work directory. The

    complete pad is shown on the top of main window.

    First le

    vel

  • RM Bridge Creating a New Project Directory

    Training Getting Started Modeler DIN 3-2

    Bentley Systems Austria

    Cre

    ate

    a n

    ew

    pro

    ject dir

    ecto

    ry

    Use File change work directory in main

    menu to change the

    project into the desired

    directory.

    The project should be

    initialized. In the set-

    ting window, you can

    set some general op-

    tions (i.e. Standard,

    material group).

    After the initialization,

    the modelling-process

    can begin.

  • RM Bridge Construction of Axis

    Training Getting Started Modeler DIN 4-3

    Bentley Systems Austria

    4 Construction of Axis

    Axis elements are used to define the axis in plan. For this example the axis is straight.

    Click Modeler in the navigation to start Modeler. Use Modeler to prepare the geometry of

    the bridge. The project is shown in the ground plan (empty yet).

    The input window changes according to the selected geometric definition (navigation

    menu). Modeler can be closed by pressing Esc-button or click the close icon x. It is also possible to exit Modeler that if you switch to another function, which could be found in

    the navigation menu and not a sub-function of Modeler.

    In helpbrief help for Icons you can find the description for different functions.

    Note: Recalc-function in Modeler(GP) and Analyzer(RM) are not the same. In Modeler, the Re-calcfunction is used to export the Modeler data to Analyzer. But in Analyzer, the Recalc function is used to start the calculation. The calculation options can also be set in the Re-calc-function.

    The import and export function for Tcl-file works in the same manner. The import and export

    process is executed in the Modeler database (if Modeler is active) or in the Analyzer database

    (if Analyzer is active).

    Close Modelers

    View and zoom function

    Functions, which are pro-

    vided in ground plan

    Recalc(Export the data from Modeler to Analyzer (RM))

    Navigation menu

    Use tcl files to import

    and export the Modeler

    data.

    Input window Axes in ground plan

  • RM Bridge Construction of Axis

    Training Getting Started Modeler DIN 4-4

    Bentley Systems Austria

    There is a detailed description about data management and backup in RmBridge, see

    chapter 1010.

    4.1 Create an Axis

    The geometric definition of one axis consisting of axis-elements. The definition should

    be done in ground, elevation plan. The axis-element can be a straight line, circle, spiral

    and cubic curve elements.

    Define a

    n A

    xis

    New Axis:

    A new axis should be

    defined at first. Select

    the axis-menu in the navigation. Click the

    right mouse-button and

    choose new axis

    Confirm

    If there are more axes existing, double-click the desired axis to select it.

    Active

    The currently active

    axis is shown in the

    information-bar at the

    left lower corner (

    Axis1 in this exam-ple).

    4.2 Constructing an Axis in Plan Axis in plan: straight line: Station: 0-60 m

    Select ground plan list in the navigation-menu.

  • RM Bridge Construction of Axis

    Training Getting Started Modeler DIN 4-5

    Bentley Systems Austria

    Select P0 in order to

    define the starting point

    of the axis in the

    ground plan. The coordinates for the

    starting points (X =

    east, Y = north).

    Confirm

    Keep the default set for this example (P0 (0.0/0.0).). The new axis goes along the X-

    direction, no angle needs to be defined. After input confirmation the point with the speci-

    fied direction are visible on the screen. Please use the Zoom functions at the left vertical tool bar (or use Free hand symbols, see next page) to view.

    Select Append straight

    line to axis from the

    tool-bar.

    The length of the

    straight line is 60.0 m.

    Confirm

    The axis is now defined in the ground plan and is displayed on the screen.

  • RM Bridge Construction of Axis

    Training Getting Started Modeler DIN 4-6

    Bentley Systems Austria

    Top level of M

    OD

    ELE

    R w

    ith a

    xis

    in p

    lan

    Alternatively to the zooming facilities, the so called free hand symbols can be used. Such a free hand symbol is executed with the left mouse button and simultaneously pressing

    [Ctrl]-key on the keyboard. The free hand symbolV creates a full view of the cur-rently available items.

    The other free hand symbols can be viewed by clicking the explanation button on top of the screen.

  • RM Bridge Construction of Axis

    Training Getting Started Modeler DIN 4-7

    Bentley Systems Austria

    4.3 Constructing an Axis in Elevation Axis in Elevation: planar line: Station: 0-60 m

    Select elevation graphic or elevation list to specify the elevation.

    Select P0 to define the starting point of the

    axis.

    The default setting can

    be kept.

    Confirm

    Select the button ap-

    pend straight line by

    station and set Station

    Difference to 60 m..

    Confirm

    Now the axis definition is finish. You can use the zoom-function as explained above to

    check the axis.

  • RM Bridge Construction of Axis

    Training Getting Started Modeler DIN 4-8

    Bentley Systems Austria

    Ele

    vation o

    f A

    xis

  • RM Bridge Construction of Axis

    Training Getting Started Modeler DIN 4-9

    Bentley Systems Austria

    4.4 Modify

    The Delet last axis element button allows to delete the last input.

    Modific

    atio

    ns

    Modifications to the axis

    definition in plan and

    elevation can be done in

    the ground plan list or

    elevation list.

    In the list, the existing

    element can be modi-

    fied. By modification,

    you should pay atten-

    tion, that some elements

    are related to each other,

    they can only be

    changed in the right se-

    quence.

    The upcoming listing

    allows to change data in

    any line (radius, slope,

    lengths, ..).

    Confirm with .

    and the win-

    dow.

    Use Modify button to modify.

    Use Delete button to eliminate the input data.

  • RM Bridge Construction of Cross-Section

    Training Getting Started Modeler DIN 5-1

    Bentley Systems Austria

    5 Construction of Cross-Section

    8.00 m

    3.50 m 3.40 m

    0.10 m

    1.00 m

    2.0

    0 m

    1.6

    5 m

    0.2

    5 m

    0.1

    0 m

    Fig. 5: Cross Section

    Click cross-section in the navigation-menu with the right mouse-button. Select New Cross Section in the context.

    Define C

    ross-S

    ection

    The basic definitions

    for the cross-section

    name can be used, con-

    firm with .

    Confirm

  • RM Bridge Construction of Cross-Section

    Training Getting Started Modeler DIN 5-2

    Bentley Systems Austria

    The new cross-section is listed

    in the navigation-tree on your

    left. Several cross-sections can

    be defined in one project, only

    one is needed for this example.

    Changing between the cross-

    sections is done by double-

    clicking on the desired cross

    section.

    Aktive C

    S

    The active CS is always dis-

    played at the lower window on

    the information-bar. All further

    CS definitions will refer to this

    Cross-Section (cross1).

  • RM Bridge Construction of Cross-Section

    Training Getting Started Modeler DIN 5-3

    Bentley Systems Austria

    Select the cross-section to open the graphic input screen.

    CS

    Win

    dow

    Draw functions for con-

    struction line

    Draw functions for FE-Element in

    Cross-section network

    Draw functions for Refe-

    rence point

    Draw functions for Dimen-

    sion line

    Different view- and

    zoom functions

    Reference-Sets (Click the arrow to

    open it) and shows the active Ref-

    Set.

    Cross-section Part (Click the arrow to

    open it) and shows the active parts.

    Variables in the cross-section (Click

    the arrow to open it) and shows the

    active variables or constants, which are

    used in this cross-section to define the

    construction line.

    Basic construction line CL1 and CL2 ()

    (The default directions are along Z- and

    Y-coordination axes in the cross-section)

    Default position for part 1 (in the inter-

    section point of CL1 and CL2). It is

    marked by a small flag and the part

    number.

    Direction

  • RM Bridge Construction of Cross-Section

    Training Getting Started Modeler DIN 5-4

    Bentley Systems Austria

    5.1 Definitions

    5.1.1 Construction Lines

    The construction line (CL) is needed for locating the intersection points, which are used to

    draw a FE-element. The FE-elements construct the cross-section network. Use the draw-

    functions to create the construction lines. The construction lines are referenced on each

    other (i.e. parallel to). All the construction lines are depends on CL1 (horizontal) or CL2 (vertical).

    Note: Different dependencies of construction lines on each other are important for defining construction lines

    with variables. The assigned variables are given in Tables and formulas. The influence of variables on the other construction lines should be considered.

    5.1.2 Cross-section and axis

    The default position of CL1 and CL2 are the Z- and Y- coordinate-axis of cross-section.

    The intersection point of CL1 and CL is the connection point of cross-sections.

    Note: Use Offset-option can move cross-section position (CL1, CL2) relate to the Axes.

    5.1.3 Cross-section

    In order to create a cross-section, the elements are required, which defined by intersection

    point of construction lines. Every element is a build-part of the cross-section.

    Note: The construction of cross-section is done in the direction against X-axis.

    5.1.4 Cross-section element

    The shape of the cross-section is defined by individual elements. These elements are based

    on the intersection points of the construction lines. These 2 dimensional elements are cre-

    ated with either 3 or with 4 corner nodes. A polygonal line around the element defines the

    border, the first and the last polygon part close the element. The order of input does not

    matter (cycle), the polygonal line must not cross itself.

    5.1.5 Part

    The cross-section elements with different properties can be summarized into different

    groups (part). I.e. For the composite cross-section, the concrete elements and the steel ele-

    ments should be assigned into different groups.

    Note: Parts can also be used to assign the different static length system of one cross-section into

    different part. (i.e. Doppel-T cross-section prepared as Grillage, that means instead of two

    single cross-section (each -T)to two different segments, you just need one cross-section and one segment, the cross-section consists of two parts for two separate longitudinal ele-

    ment series ),

  • RM Bridge Construction of Cross-Section

    Training Getting Started Modeler DIN 5-5

    Bentley Systems Austria

    5.1.6 Reference Points

    The intersection of CL1 and CL2 represents the axis of the bridge and acts as a reference

    point for the position of the cross-section in the overall 3D geometry.

    5.1.7 Reference Sets

    In addition to the cross-section geometry information for the structural analysis such as

    temperature points, reinforcement layers, stress points and others are defined in so called

    reference sets. Properties (e.g. material) of a Reference Set can be defined and grouped in so called Attribute Sets.

    5.1.8 Layer Management

    Each object of the cross-section can exist in all, one or several graphical layers.

  • RM Bridge Construction of Cross-Section

    Training Getting Started Modeler DIN 5-6

    Bentley Systems Austria

    5.2 Definition of Construction Lines

    Six vertical and four horizontal lines are needed for the following cross-section. First paral-

    lel and vertical lines with a distance of 4.0m to the centre are defined.

    Consta

    nts

    Set the constant to 4.0

    in the vari-ables/constants-input field.

    Press the icon Parallel Line to activate this function. The graphic cursor is then displayed

    as continuous line indicating a function being active.

    During the execution of this action the following information is displayed in the status

    line:

    Select the vertical line as basic line (CL_2).

    During the execution of this action the following information is displayed in the status

    line:

    Click to the right side of the selected line to create a new construction line. This new CL

    has a distance of 4.0m to the centre.

    Create the second line on the other side in the same way:

    Select the vertical basic line.

    Click to the left side of the selected basic line (CL_2) to create a new CL. This new CL

    has a distance of 4.0m to the centre.

  • RM Bridge Construction of Cross-Section

    Training Getting Started Modeler DIN 5-7

    Bentley Systems Austria

    CS

    win

    dow

    The next figure shows the rest of the needed CLs with the corresponding distances . The

    procedure is the same as explained above. Click at the vertical or horizontal basic line and

    set the constant to the appropriate value.

  • RM Bridge Construction of Cross-Section

    Training Getting Started Modeler DIN 5-8

    Bentley Systems Austria

    The following overview shows all necessary construction lines for this example:

    CS

    Win

    dow

    4.00 4.00

    0.2

    5

    2.0

    0

    0.6

    0.5 0

    .35

    Basic lines CL1 and CL2

  • RM Bridge Construction of Cross-Section

    Training Getting Started Modeler DIN 5-9

    Bentley Systems Austria

    5.3 Cross-Section Elements

    After all CLs are available the cross-section elements can be defined:

    Activate the "Cross-section element by selecting the appropriate icon.

    During the execution of this action the following information is displayed in the status

    line:

    Click at the intersection points of the construction lines to create the corner nodes 1, 2, 3

    and 4 of the new element (see picture below). The new element is automatically assign

    to part 1, thus the number 1 appears in the middle of the element. (Different parts are

    needed in composite constructions, see next training)

    CS

    Win

    dow

  • RM Bridge Construction of Cross-Section

    Training Getting Started Modeler DIN 5-10

    Bentley Systems Austria

    All other elements are generated in the same way. Please make use of the zoom functions

    to properly select the intersection points. A wrong definition can be interrupted by hitting

    the key (or right mouse button). A wrongly defined element can be selected (ele-

    ment line changes colour) and deleted with the delete icon.

    Elements can be copied and mirrored to speed up the input. These icons can be found with

    right click above the icon Linear 4-Point-Element.

    The cross-section of this example consist of 4 elements only, see picture below:

    CS

    Win

    dow

  • RM Bridge Construction of Cross-Section

    Training Getting Started Modeler DIN 5-11

    Bentley Systems Austria

    5.4 Definition of Reference-Sets

    Four sets are used in this example: 2 for reinforcement layer (top and bottom), one for the

    stress points (to calculate stress at top and bottom fibre at a certain point). The forth set is

    needed to define the geometrical position of the support springs (connection points).

    5.4.1 Connection Points

    Select the arrow key next to the reference point.

    Refe

    rence

    -Sets

    Create a new reference

    set with the name sup-port and select the type connection point .

    Confirm

    Connection p

    oin

    ts

    This new reference set

    is inserted in the table

    of existing reference

    sets. Several sets can be

    defined in one project.

    Select the wanted set

    and hit to change

    the active set

    Insert

    Active

    The activated reference

    set will be displayed in

    the input field. All

    definitions on the

    cross-section level will

    now refer to this refer-

    ence set.

  • RM Bridge Construction of Cross-Section

    Training Getting Started Modeler DIN 5-12

    Bentley Systems Austria

    Select the icon for the

    connection point defini-

    tion.

    Connection p

    oin

    t

    Select the intersection

    of CLs with cross-

    section element border

    to define the position of

    the reference point.

    Sin

    gle

    Po

    int

    The upcoming window

    asks for the name of

    this new point (CP0 in

    this case).

    Confirm

  • RM Bridge Construction of Cross-Section

    Training Getting Started Modeler DIN 5-13

    Bentley Systems Austria

    5.4.2 Stress Points

    Open the reference set input window by clicking the arrow key next to it.

    Refe

    rence

    -Sets

    Select Insert after button to add another

    reference set to the list-

    ing.

    Insert

    Str

    ess P

    oin

    ts

    Create a new set with

    the name STRESS and select the type

    Stress check points . The Attribute-Set is

    named similar to the set

    name: STRESS

    Confirm

    The newly defined reference set is inserted in the table of available reference sets.

    Select the new set and hit to activate the reference set.

    Active

    The active reference set

    is displayed in the

    lower side of the win-

    dow. All definitions

    from now on will refer

    to the active reference

    set (STRESS in this case).

  • RM Bridge Construction of Cross-Section

    Training Getting Started Modeler DIN 5-14

    Bentley Systems Austria

    Select the icon for the

    stress point definition.

    The intersection point

    is selected by clicking

    it with the cursor in

    order to define the

    wanted position of the

    reference point.

    The upcoming window

    asks for the definition

    of the point name for

    the selected point

    (SP_TOP in this case).

    Confirm

    Select the icon for the

    stress point definition.

    The intersection point

    is selected by clicking

    it with the cursor in

    order to define the

    wanted position of the

    reference point.

    The upcoming window

    asks for the definition

    of the point name for

    the selected point

    (SP_BOT in this case).

    Confirm

  • RM Bridge Construction of Cross-Section

    Training Getting Started Modeler DIN 5-15

    Bentley Systems Austria

    5.4.3 Reinforcement Groups

    Reinforcement is defined either as one or more single points or polygons. Reinforcement

    areas that are assigned or automatically calculated later are distributed over these points and

    polygons. Positions are defined relative to construction intersection points or cross-section

    element nodes. The sole geometry is stored in form of Reference-Sets, which may be

    grouped and addressed by Attribute-Sets. Attribute-Sets hold additional information such as

    material definitions. In most cases the Attribute-Set names are identical to the Reference-

    Set names.

    First a Reference-Set is created as already shown above.

    Open the reference set input window by clicking the arrow key next to it.

    Refe

    rence

    -Sets

    Use the Insert after button to define a new

    Reference-Set.

    Insert

    Rein

    forc

    em

    ent

    Top

    Create a new Refer-

    ence-Set with name

    REBAR_TOP and select type Bending Reinforcement. Use the same name again

    (REBAR_TOP) for the Attribute-Set and

    assign the wanted ma-

    terial.

    Confirm

    The newly defined reference set is inserted in the table of available reference sets.

    Select the new set and hit to activate the reference set.

  • RM Bridge Construction of Cross-Section

    Training Getting Started Modeler DIN 5-16

    Bentley Systems Austria

    Select the appropriate

    icon for the reinforce-

    ment definition.

    Select the element cor-

    ner to which the refer-

    ence point is relative to

    using the mouse cursor.

    The upcoming window

    requires data for point

    type, point name and

    offset to the selected

    element corner. The

    new point will be the

    start of the reinforce-

    ment polygon.

    Confirm

    Select the appropriate

    icon for the reinforce-

    ment definition.

    Select the element cor-

    ner to which the refer-

    ence point is relative to

    using the mouse cursor.

    The upcoming window

    requires data for point

    type, point name and

    offset to the selected

    element corner. The

    new point will be the

    end of the reinforce-

    ment polygon.

    Confirm

    After the reinforcement definition at the top layer is defined the bottom reinforcement will

    following as next:

  • RM Bridge Construction of Cross-Section

    Training Getting Started Modeler DIN 5-17

    Bentley Systems Austria

    Open the reference set input window by clicking the arrow key next to it.

    Refe

    rence

    -Sets

    Use the Insert after button to define a new

    Reference-Set.

    Insert

    Rein

    forc

    em

    ent B

    ottom

    Create a new Refer-

    ence-Set with name

    RBAR_BOT an se-lect type Bending Re-inforcement. Use the same name again

    (REBAR_BOT) for the Attribute-Set and

    assign the wanted ma-

    terial.

    Confirm

    The newly defined reference set is inserted in the table of available reference sets.

    Select the new set and hit to activate the reference set.

  • RM Bridge Construction of Cross-Section

    Training Getting Started Modeler DIN 5-18

    Bentley Systems Austria

    Select the appropriate

    icon for the reinforce-

    ment definition.

    Select the element cor-

    ner to which the refer-

    ence point is relative to

    using the mouse cursor.

    The upcoming window

    requires data for point

    type, point name and

    offset to the selected

    element corner. The

    new point will be the

    start of the reinforce-

    ment polygon. Define

    the polygon end point

    in the same way.

  • RM Bridge Segment Definition

    Training Getting Started Modeler DIN 6-1

    Bentley Systems Austria

    6 Segment Definition

    The structural system consists of 2 span girders with a constant T-shaped cross-section.

    Only one Segment is needed for this project.

    Click Segment in the navigation-menu with the right mouse-button. Select New seg-ment in the contex.

    De

    fine S

    egm

    en

    t

    Name, type, reference

    axis and eccentricity

    type can be defined for

    the new segment in the

    upcoming window.

    For this example the

    default set is ok and the

    name is seg1. After confirmation the new

    segment will be avail-

    able in the segment

    listing.

    Confirm

    The newly created segment is displayed in the table of existing segments. Several seg-

    ments may exist for one project. Changing the currently active segment is done by click-

    ing the wanted segment and confirming with .

  • RM Bridge Segment Definition

    Training Getting Started Modeler DIN 6-2

    Bentley Systems Austria

    6.1 Definition of the Structural System

    The next step in MODELER is the assembly of the structural system. A structural system consists of Elements, Nodes, Cross-sections and Material properties.

    Each segment consists of several segment points. Each segment point is defined in 3D with

    its position along the axis. The structural nodes are created using these segment points, the

    structural elements are generated using the spacing between the segment points. Material

    properties are assigned to the elements, the cross-sections are assigned to the segment

    points.

    6.2 Definition of Segment Points

    Open the segment point listing by clicking the symbol on the right side.

    Segm

    ent P

    oin

    t Lis

    ting

    The table will be empty

    since no data has bee n

    defined yet.

    Define new segment points by clicking the "Insert after" - button (at the left of the gen-

    eral screen).

    The structural system shall start at 0 and shall end at Station 60.0 m.

    All elements will have a length of 3.0m, 20 elements will finally compose the girder. 10

    elements for the left span and 10 elements for the right span.

  • RM Bridge Segment Definition

    Training Getting Started Modeler DIN 6-3

    Bentley Systems Austria

    Insert

    Segm

    ent

    Poin

    ts

    The input for the Seg-

    ment Points can be seen

    in the Figure on the left

    side.

    A step of 3 m is used to define segment

    points that will reflect

    the element lengths of

    the structural system.

    Confirm

    Segm

    ent P

    oin

    ts

    The structural system is

    herewith defined. (60m

    long with elements of 3

    m length).

    6.3 Cross-Section Assignment

    The assigned cross-sections are shown in the segment list. The column OK describes if the cross-section at this stage is correctly defined for the further procedure. The + shows that at this station the appropriate cross-section is assigned. If this sign switches to - the cross-section was recently modified after it had been assigned to the segment.. In the lower

    list all specified variables, parts and connections of the cross-section are displayed. Later on

    tables and formulas will be assigned to those variables.

  • RM Bridge Segment Definition

    Training Getting Started Modeler DIN 6-4

    Bentley Systems Austria

    6.4 Assignment of Element Numbers

    Ele

    ment

    num

    be

    ring

    The element and node

    numbering for the

    whole system can be

    done at once. First se-

    lect parts to view the undefined parts. Only

    one line is displayed

    since the cross-section

    exists only of one part.

    The element numbering should start at segment point 1, the first element and node-number

    should be 101. At the end of the first element (101) the nodenumber is 102. The in-crement is definition by 1.

    The properties of the material is:C_35/45 (DIN 1045-1) will be applied.

    All elements are grouped with the name MG (main girder).

    Activate the 'Modify' - Function at the left of the table to open the input pad.

  • RM Bridge Segment Definition

    Training Getting Started Modeler DIN 6-5

    Bentley Systems Austria

    Ele

    ment

    num

    be

    ring

    Definition for all seg-

    ment points (1 to 21):

    See Fig. on the left

    siede.

    Confirm

    Segm

    ent P

    oin

    t L

    isting

    The numbering can be

    controlled by stepping

    through the segment

    point listing in the up-

    per table.

    The data to the cur-

    rently marked line is

    shown in the lower

    table.

    Any modification after this initial definition can be done, but must be exe-

    cuted in MODELER before export the project to ANALYZER .

  • RM Bridge Segment Definition

    Training Getting Started Modeler DIN 6-6

    Bentley Systems Austria

    The cross-section 'cross1' is locked after this initial assignment. Any modification to the

    cross-section requires to unlock the cross-section (program asks for it). Again must be executed in MODELER before the export to ANALYZER starts.

  • RM Bridge Definition of Supports

    Training Getting Started Modeler DIN 7-1

    Bentley Systems Austria

    7 Definition of Supports

    The following definitions are required:

    A connection point is required for the support. It should be defined in the cross-section (see Definition of Reference-Sets).

    Create the connection between sub- and superstructure with spring elements- see be-low:

    7.1 Geometrical position of bearing:

    CS

    W

    indow

    / A

    dd. P

    oin

    ts

    The green, triangular

    symbol attached at the

    bottom of the girder is

    the geometrical posi-

    tion of the bearing. The

    definition is already

    done in chapter 5.4.1.

  • RM Bridge Definition of Supports

    Training Getting Started Modeler DIN 7-2

    Bentley Systems Austria

    7.2 Definition of Support

    Open the segment point table.

    Select the first line in the upper listing (Station 0).

    Select the button for connection to open the corresponding input window.

    Select insert before to see the possible

    choices.

    Select New spring-0 to open the correspond-

    ing spring definition

    window.

  • RM Bridge Definition of Supports

    Training Getting Started Modeler DIN 7-3

    Bentley Systems Austria

    Supp

    ort

    De

    finitio

    n

    The support spring

    1100 represents the

    connection between

    girder and soil. The

    position of this spring

    element is done with

    the assignment to the

    nodes (Node1 = 0 =

    earth, Node2 = 101 top

    of girder)

    Switch over to the input

    of spring constants.

    Press

    Spri

    ng C

    onsta

    nts

    The spring constants

    are defined here. The

    element 1100 repre-

    sents the support condi-

    tion in vertical (X) and

    transverse (Z) direc-

    tion. A constant of 1e8

    represents the stiffness

    of the support condi-

    tion.

    Confirm

    The newly defined spring element will be displayed in the table for support definitions.

  • RM Bridge Definition of Supports

    Training Getting Started Modeler DIN 7-4

    Bentley Systems Austria

    Supp

    ort

    De

    finitio

    n

    Press the i-button to see a graphical picture

    of the support.

    Several conditions can

    be defined at any seg-

    ment point. Select the

    wanted line in the table

    to see the correspond-

    ing support condition.

    The same procedure is repeated for the other two connections (segment point 11 und 21).

    The element numbers shall be 1200 and 1300.

    The table below shows the sprig constants for the spring elements.

    Element 1100 1200 1300

    Spring constants KN/M KN/M KN/M

    CX 1e8 1e8 1e8

    CY 0 1e8 0

    CZ 1e8 1e8 1e8

    CMX 0 0 0

    CMY 0 1e8 0

    CMZ 0 0 0

  • RM Bridge 3D - View

    Training Getting Started Modeler DIN 8-1

    Bentley Systems Austria

    8 3D - View

    The completed girder can be viewed in 3D now.

    Select the corresponding button to open the 3D view.

    3D

    - V

    iew

  • RM Bridge Export to Analyzer

    Training Getting Started Modeler DIN 9-1

    Bentley Systems Austria

    9 Export to Analyzer

    9.1 Export to Analyzer

    The completed structural system can be transformed into a structural model for further use

    in Analyzer.

    Recalc: Some sub-functions are provided in the Recalc window for Modeler. They are separate

    calculation parts. For complex project, sometimes the evaluate formulas check box

    will not be selected to reduce the calculation time.

    The Evaluate formulas has to be selected for further calculation options. Hamblyis a special algorithm to find the common gravity line of several different cross-section

    areas. Precast segmentation is used in RMCast.

    Check numbering of

    elements and nodes:

    To check if any element or node-number is used for more times. This option will be

    set automatically, if the Create model is set.

    Create model: Export the Modeler data to Analyzer. There are three sub-options can be set.

    (1)Keep the original model data in Analyzer, only the new data will be added into the

    database. (2) initialize the model structure in analyzer or (3) initialize the whole ana-

    lyzer data (include the input data in Analyzer).

    Select 'Recalc'-Icon to start the calculation and export the Modeler data to Analyzer .

    Export

    to A

    na

    lyzer

    Export

    Set the project calcula-

    tion options. Click

    to start the cal-

    culation. After the cal-

    culation, the Modeler

    data can be exported to

    Analyzer, if the Create

    model option is set.

    Close the input-window

    to exit Modeler. The Analyzer part can begin.

  • RM Bridge Data management and backup

    Training Getting Started Modeler DIN 10-2

    Bentley Systems Austria

    10 Data management and backup

    Since the version RmBridge V8i, Modeler (previously GP) is the geometric preprocessor,

    Analyzer (previously RM) is mainly used to prepare the static calculation. And they are

    executed in the same user interface.

    Nevertheless, Modeler and Analyzer have separate database. Executes the initialization,

    both database are initialized.

    The input-data writes according to the input window into different databases. Restart the

    program, the database is in the last work state.

    It is suggested to create backup-files, when a certain state is reached and the next modeling

    state will begin. It cannot return to an unsaved state (Undo function). The backup-files are separate in Modeler and Analyzer database.

    The database is exported in ASCII-text file (Tcl-format). That means the project-data can

    be read and edited, they are stored in a readable text-file (use Text-Editor). In the text-

    editor, it is possible to use script-languages for defining variables (loops and if..then) and so on. It simplifies and speeds up the input-process. When the project-data is imported,

    the programmed routines are also executed.

    By export and import Modeler-data, the entire project is always saved or loaded.

    By export the Analyzer-database, there are additional options, which are able to assign cer-

    tain project-part to export (Default: the entire project). So the single project-part can be

    saved in a separate Tcl-file for further use. By import Tcl-file project data in Analyzer is

    possible to make a part import Add to project, which just adds this Tcl-file to the current project. The option New project executes an initialization of the database and then loads the Tcl-file.

    GeneralThe Example (Tutorial)The Structural SystemSupport ConstraintsCross-Section

    Program StartCreating a New Project DirectoryConstruction of AxisCreate an AxisConstructing an Axis in PlanConstructing an Axis in ElevationModify

    Construction of Cross-SectionDefinitionsConstruction LinesCross-section and axisCross-sectionCross-section elementPartReference PointsReference SetsLayer Management

    Definition of Construction LinesCross-Section ElementsDefinition of Reference-SetsConnection PointsStress PointsReinforcement Groups

    Segment DefinitionDefinition of the Structural SystemDefinition of Segment PointsCross-Section AssignmentAssignment of Element Numbers

    Definition of SupportsGeometrical position of bearing:Definition of Support

    3D - ViewExport to AnalyzerExport to Analyzer

    Data management and backup