Green Power Initiative May 23, 2013 Department of Energy – Office of the Biomass Program P. Barry Butler, Ph.D. Executive Vice President and Provost Albert Ratner, Ph.D. Associate Professor, College of Engineering Presented by Ferman Milster Principal Engineer – Renewables, Office of Sustainability This presentation does not contain any proprietary, confidential, or otherwise restricted information

Upload: alan-muncy

Post on 31-Mar-2015

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Green Power Initiative May 23, 2013 Department of Energy – Office of the Biomass Program P. Barry Butler, Ph.D. Executive Vice President and Provost Albert

Green Power Initiative

May 23, 2013Department of Energy – Office of the Biomass Program

P. Barry Butler, Ph.D.Executive Vice President and Provost

Albert Ratner, Ph.D.Associate Professor, College of Engineering

Presented by

Ferman MilsterPrincipal Engineer – Renewables, Office of Sustainability

This presentation does not contain any proprietary, confidential, or otherwise restricted information

Page 2: Green Power Initiative May 23, 2013 Department of Energy – Office of the Biomass Program P. Barry Butler, Ph.D. Executive Vice President and Provost Albert

Goal Statement & Project Overview

GoalDemonstrate the viability and performance of an atmospheric downdraft gasifier for producing syngas from locally available agricultural materials and organic industrial byproducts.

Focus on solid biomass fuels available in the local area.

2

Page 3: Green Power Initiative May 23, 2013 Department of Energy – Office of the Biomass Program P. Barry Butler, Ph.D. Executive Vice President and Provost Albert

Goal Statement & Project Overview

Overview • Install a locally designed and built gasifier to a new staged-

combustion biomass boiler.• Characterize syngas produced using biomass (e.g. seed,

stover, grass, etc.) and organic industrial byproducts (e.g. lignin) not commonly employed as fuel.

• Provide opportunities for research, education, and application of agricultural and alternate fuel gasification technology.

3

Page 4: Green Power Initiative May 23, 2013 Department of Energy – Office of the Biomass Program P. Barry Butler, Ph.D. Executive Vice President and Provost Albert

4

Green Power Initiative

• Air permitting by Iowa DNR – issued 6.22.2010

• Boiler/Gasifier Project Bid Opening: JAN 13, 2011

• Significant project growth in scope due to complexity and code requirements

• Equipment $2,870,165– DOE share : 32.1%– University of Iowa share: 67.9%

• Research $265,000– DOE share : 35.8%– University of Iowa share: 64.2%

Timeline

Budget

Project Development

• UI College of Engineering• UI Facilities Management• Ag Bio-Power

Project Participants

• Project start date – Q3FY10• Project end date – Q1FY13• Percent complete – 100%

Page 5: Green Power Initiative May 23, 2013 Department of Energy – Office of the Biomass Program P. Barry Butler, Ph.D. Executive Vice President and Provost Albert

Click to edit the title text format• Install a research gasifier coupled to a new biomass

boiler to produce steam for a district energy system.– Unique coupling of facility utility asset (boiler) and

research (gasifier)– Design, bid, build capital project for boiler and gasifier– Successful air permitting was a project prerequisite

• Successfully completed short course on gasification (Nov 2012)

5

1 - Approach

Page 6: Green Power Initiative May 23, 2013 Department of Energy – Office of the Biomass Program P. Barry Butler, Ph.D. Executive Vice President and Provost Albert

Click to edit the title text format• Actively being used for undergraduate and graduate

level research• Disseminated research and testing results

– Hosted numerous tours and information sessions for interested parties (e.g. other universities, companies, and utilities)

– Presented research findings at several national meetings (e.g. ASME, Combustion Institute, Iowa Academy of Science)

6

1 – Approach (cont.)

Page 7: Green Power Initiative May 23, 2013 Department of Energy – Office of the Biomass Program P. Barry Butler, Ph.D. Executive Vice President and Provost Albert

Click to edit the title text format

7

Biomass Boiler

7

Gasification / Combustion Process• Gasify biomass fuel in lower portion of furnace (gasification region)• Ignition of generated fuel gas in upper region (combustion region)• Steam produced in boiler delivered to district energy system for

building heating and ventilation, as well as process loads.

Gasification Region

Combustion Region

Page 8: Green Power Initiative May 23, 2013 Department of Energy – Office of the Biomass Program P. Barry Butler, Ph.D. Executive Vice President and Provost Albert

Click to edit the title text format

8

Research Gasifier Biomass Boiler

Gasifier and Boiler System

Page 9: Green Power Initiative May 23, 2013 Department of Energy – Office of the Biomass Program P. Barry Butler, Ph.D. Executive Vice President and Provost Albert

Project Management

9

• Challenging integration of research project with installation of replacement boiler design, bid, build project

• Many players – some key players did not have complex solid fuel boiler experience

• Complex capital project procedures not well understood by all parties – led to confusion of responsibilities

• In the future, would look to separate major capital project from research equipment installation.

Page 10: Green Power Initiative May 23, 2013 Department of Energy – Office of the Biomass Program P. Barry Butler, Ph.D. Executive Vice President and Provost Albert

Accomplishments and Results

10

• Project construction, installation, testing, commissioning complete. All project tasks are complete.

• Gasifier began operations on June 2012.

• Current gasifier fuel is corn.–Demonstrating production scale, versus bench-top platform

for biomass fuel testing, and steady state production of syngas for testing and study.

–Syngas produced from corn in the research gasifier is burned in the biomass boiler.

Page 11: Green Power Initiative May 23, 2013 Department of Energy – Office of the Biomass Program P. Barry Butler, Ph.D. Executive Vice President and Provost Albert

Accomplishments and Results

11

• State of the art small production size (3 MMBtu/hr.) atmospheric downdraft gasifier. One patent issued, one pending. Unique stratified, rotating bed design.

• Efficiency ____(later)

• Fuel – originally designed for seed corn. Large quantities available of off-spec and excess product. Intend to test and characterize wide variety of locally available industrial and agricultural biomass materials.

• Post-graduate student qualified and proficient in system start up, operation, and shutdown.

Page 12: Green Power Initiative May 23, 2013 Department of Energy – Office of the Biomass Program P. Barry Butler, Ph.D. Executive Vice President and Provost Albert

3. Relevance

12

• Thermochemical conversion of solid biomass to useful biopower syngas provides more uses for the renewable energy source, compared to direct combustion.

• An abundance of agriculture biomass and organic industrial byproducts is available in the Midwest. There are more sources than can be effectively used by the growing cellulosic ethanol industry.

• This project provides the capability to demonstrate, study, and characterize steady-state production of syngas from locally available biomass sources.

• The gasifier is designed and developed by a local Iowa inventor (http://www.agbiopower.com/).

Page 13: Green Power Initiative May 23, 2013 Department of Energy – Office of the Biomass Program P. Barry Butler, Ph.D. Executive Vice President and Provost Albert

4 - Critical Success Factors

13

• Technical– Successful integration of research gasifier with

production biomass boiler control and operating systems, using university capital project procurement procedures

– Compliance with appropriate codes for operational district energy plant, versus bench top research

Page 14: Green Power Initiative May 23, 2013 Department of Energy – Office of the Biomass Program P. Barry Butler, Ph.D. Executive Vice President and Provost Albert

14

4 - Critical Success Factors (cont.)

• Market– The technology is usable with readily available agricultural

and organic industrial byproduct feedstocks, not used as traditional sources of renewable fuel.

– More and more material will be available with growth of cellulosic plants coming on-line.

Page 15: Green Power Initiative May 23, 2013 Department of Energy – Office of the Biomass Program P. Barry Butler, Ph.D. Executive Vice President and Provost Albert

15

4 - Critical Success Factors (cont.)

• Financial / Business– The project provides an operational demonstration

facility showcasing reliable and lower-cost gasification technology.

– The gasifier provides a technology that allows use of locally available materials for energy production, replacing out-of-state procurement of fossil fuels.

Page 16: Green Power Initiative May 23, 2013 Department of Energy – Office of the Biomass Program P. Barry Butler, Ph.D. Executive Vice President and Provost Albert

16

4 - Critical Success Factors (cont.)

• Challenges– Biomass boiler has low operating hours, restricting use

of gasifier. Facilities staff working to increase boiler operating hours.

– Air permitting – each new fuel requires a permit modification.

– Industrial byproducts must be classified by EPA as non-hazardous secondary material to consider as fuel

– Tar in syngas requires sample pretreatment before analysis.

Page 17: Green Power Initiative May 23, 2013 Department of Energy – Office of the Biomass Program P. Barry Butler, Ph.D. Executive Vice President and Provost Albert

17

4 - Critical Success Factors (cont.)

• Technology advancement and commercial viability– Production scale facility is available to characterize

existing and new feedstock.– Production scale facility demonstrates viability of

gasification for appropriate size industrial and commercial needs for renewable energy.

Page 18: Green Power Initiative May 23, 2013 Department of Energy – Office of the Biomass Program P. Barry Butler, Ph.D. Executive Vice President and Provost Albert

18

4 - Critical Success Factors (cont.)

• The project is replicable where sufficient feedstocks are available to support steady-state operation. A use for the syngas produced also needs to be available.

• It would be ideally suited for industrial energy production and small-scale combined heat and power.

Page 19: Green Power Initiative May 23, 2013 Department of Energy – Office of the Biomass Program P. Barry Butler, Ph.D. Executive Vice President and Provost Albert

5. Future Work

19

Different fuels and fuel blends

A different fuel sources will be tested, both individually and in blends, to characterize syngas generation.

Need to study ‘engineered’ fuels (e.g. blended, densified, etc.)

Continue to disseminate knowledge

Tours, academic journals, short courses and workshops, trade journals, and conference presentations.

Page 20: Green Power Initiative May 23, 2013 Department of Energy – Office of the Biomass Program P. Barry Butler, Ph.D. Executive Vice President and Provost Albert

Summary

20

Approach

This project presented unique opportunity to couple research project with operating district energy system.

It successfully demonstrated the challenges and successes of coupling the facilities management organization with teaching and research functions.

Page 21: Green Power Initiative May 23, 2013 Department of Energy – Office of the Biomass Program P. Barry Butler, Ph.D. Executive Vice President and Provost Albert

Summary (cont.)

21

Technical accomplishments

The project is operational and initial testing and research successful.

Relevance

The project provides opportunity to showcase gasification technology capable of expanding biomass energy production using locally available feedstocks, including organic industrial byproducts.

Page 22: Green Power Initiative May 23, 2013 Department of Energy – Office of the Biomass Program P. Barry Butler, Ph.D. Executive Vice President and Provost Albert

Summary (cont.)

22

Critical Success factors and challenges

Air permitting, capital project procedures, installation in an existing facility, code requirements, syngas tar

Future Work

New fuels, continue demonstrations and education efforts

Technology transfer

Solicit proposals from interested parties to characterize fuels

Overall Impressions

Outstanding opportunity to form unique facilities / academic partnership to advance renewable energy deployment

Page 23: Green Power Initiative May 23, 2013 Department of Energy – Office of the Biomass Program P. Barry Butler, Ph.D. Executive Vice President and Provost Albert

Publications, Presentations, and Commercialization

23

Presentation at the 123rd and the 124th Annual Meetings of the Iowa Academy of Science and at the 2012 meeting of the Central States Section of the Combustion Institute. Continuing presentation of the results as expected at the Joint US Sections Meeting of the Combustion Institute in May 2013.

 Muilenburg, M., Shi, Y., and Ratner, A., “Computational Modeling of the Combustion and Gasification Zones in a Downdraft Gasifier,” ASME Proceedings, Vol. 4, paper#IMECE2011-64009, pp. 151-158, 2011.

Shi, Y., Gong, Z., Ratner, A., and Emadi, M., “Gas Evolution of Biomass in Gasification and Pyrolysis,” Central States Section Meeting of the Combustion Institute, paper 12S-54, Dayton, OH, April 22-24, 2012.

Gong, Z., Shi, Y., Ratner, A., and Emadi, M., “Gas Evolution of Corn from Biomass Gasification,” Central States Section Meeting of the Combustion Institute, paper 12S-53, Dayton, OH, April 22-24, 2012.