greenmeadows draft

Upload: vholts-villa-vitug

Post on 03-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Greenmeadows Draft

    1/38

    Quantity Unit U/Cost Amount U/Cost Amount

    Pre-Construction

    PRC-01 Permits, licenses & clearances from the Office of the Building 1.00 lotOfficial of Quezon City to include all the necessary documents,

    financial requirements, covering the following :

    PRC-01-A Architectural / Structural / Civil & Finishing Works

    PRC-01-B Sanitary / Plumbing Works

    PRC-01-C Electrical Works

    PRC-01-D Air-conditioning & Ventilation

    PRC-01-E Zoning and Locational Clearance

    Sub-total for PRC-01

    PRC-02 Permits, fees & clearances from The First Greenmeadows

    Homewoners Association Inc., to include settlement of allfinancial and surety requirements as follows:

    PRC-02-A Bonds & fees for medical, security & garbage 1.00 lot

    PRC-02-B Workers ID 1.00 lot

    PRC-02-C Utility connection fees 1.00 lot

    PRC-02-D Others - please provide specifics

    Sub-total for PRC-02

    PRC-03 Bonds & Insurance covering Work Contract Package No. 1 & 2

    (WCP-01 and WCP-02 respectively)

    PRC-03-A Downpayment Bond 1.00 lot

    PRC-03-B Performance Bond 1.00 lot

    PRC-03-C Comprehensive All-Risk Insurance coverage 1.00 lot

    Sub-total for PRC-03

    PRC-04 Mobilization & Site Preparation

    PRC-04-A Mobilization and site preparation (clearing & cleaning) 1.00 lot

    PRC-04-B Field office of the House Contractor with a 1.00 lot

    conference room or area for 10-12 persons, drawing

    file-rack, whiteboard, auto-cadd station and air-

    conditioning

    PRC-04-C Secured storeroom / warehouse 1.00 lot

    PRC-04-D Two (2) separate sanitation facilities for 1.00 lot

    office staff / visitors and workers complete withwater supply, sink and ventilation windows

    Material Labor

    PRICE PROPOSAL DETAIL - 08 May 2012

    Page 1 of 38

  • 7/28/2019 Greenmeadows Draft

    2/38

    Quantity Unit U/Cost Amount U/Cost Amount

    Material Labor

    PRC-04-E Site board-up / fence and gates 1.00 lot

    PRC-04-F Temporary utility connections for telephone, power 1.00 lot

    and light, water to include control meters

    Sub-total for PRC-04

    Total for Pre-Construction

    Page 2 of 38

  • 7/28/2019 Greenmeadows Draft

    3/38

    Quantity U nit U/Cost Amount U/Cost Amount

    Material Labor

    Site Works

    SW-01 Civil and Structual Works

    SW-01-A Earthworks

    (a) Excavation 155.00 cu.m 500.00 77500.00(b) Gravel fill 1.00 cu.m 900.00 900.00 250.00 250.00

    (c) Backfill 110.00 cu.m 350.00 38500.00 250.00 27500.00

    (d) Compaction sm

    SW-01-B Reinforced concrete works

    (a) Flat slab-on-fill / grade

    (a-1) concrete 1.00 cu.m 3750.00 3750.00 550.00 550.00

    (a-2) rebar 120.00 kgs 42.00 5040.00 6.50 780.00

    (b) Stepped slab-on-fill / grade

    (b-1) concrete 1.00 cu.m 3750.00 3750.00 550.00 550.00

    (b-2) rebar 100.00 kgs 42.00 3750.00 6.50 650.00(c) Suspended slab (S-1, S-3)

    (c-1) concrete cu.m 3750.00 550.00

    (c-2) rebar kgs 42.00 6.50

    (d) Below grade reinforced concrete fish pond

    containment

    (e) Gate column GC-1 and gate column footing

    (e-1) concrete 3.50 cu.m 3750.00 13125.00 550.00 1925.00

    (e-2) rebars 475 kgs 42.00 19950.00 6.50 3087.50

    (f) Fence and garbage wall stiffener columns (SC) and

    SC footings:

    (f-1) concrete 1.00 cu.m 3750.00 3750.00 550.00 550.00

    (f-2) rebars 130.00 kgs 42.00 5460.00 6.50 845.00

    (g) Retaining wall RW-1 and RW footing RWF-1:

    (g-1) concrete cu.m 3750.00 550.00

    (g-2) rebars kgs 42.00 6.50

    (h) Beams (B-1A, B-2, B-1, CRB-1)

    (h-1) concrete cu.m 3750.00 550.00

    (h-2) rebars kgs 42.00 6.50

    (i) Stair-4

    (i-1) concrete 1.00 cu.m 3750.00 3750.00 550.00 550.00

    (i-2) rebars 400.00 kgs 42.00 16800.00 6.50 2600.00SW-01-C Associated Works

    Page 3 of 38

  • 7/28/2019 Greenmeadows Draft

    4/38

    Quantity Unit U/Cost Amount U/Cost Amount

    Material Labor

    (a) Dowels for slab-on-fill attachments to building 100 kgs 42.00 4200.00 6.50 650.00

    (b) Hauling of excess soil 20.00 cu.m 500.00 10000.00

    (c) Formworks 120.00 sm

    (d) Testing works 1.00 lot

    (e) Misc works (specify) : Sub-Total for SW-01

    Page 4 of 38

  • 7/28/2019 Greenmeadows Draft

    5/38

    Quantity Unit U/Cost Amount U/Cost Amount

    Material Labor

    SW-02 Architectural and Finishing Works

    SW-02-A WE-02 CHB planters, internal fences within the East

    & West easements, garden retaining wall and 1000mm

    low wall within the service yard, to include mortar

    and reinforcements

    SW-02-B WE-1 CHB garbage staging area enclosure, south-

    boundary fence and elevated patio, to include mortar

    and reinforcements

    SW-02-C Pre-cast concrete curb

    SW-02-D Plaster works PW-01, for all WE-01 and WE-02 walls

    within the perimeter easements, including the existing

    fence structures along the West, South & East boundaries

    SW-02-E Pavement Topping

    (a) FP-01

    (b) FP-02

    (c) FP-03SW-02-F Surface Finishes & Treatment

    (a) SFT-01 (fences, planter)

    (b) SFT-03

    (c) SFT-04

    (d) SFT-05 [parking over the low wall at the service

    yard & handrail of stair (1)]

    SW--2-G Associated Works

    (a) AWM-01

    (b) AWM-02

    (c) AWM-03(d) AWM-06

    Sub-Total for SW-02

    Total for Site Works

    Building Works

    BW-01 Civil and Structural

    BW-01-A Earthworks

    (a) excavation 150.00 cu.m 500.00 75000.00

    (b) gravel fill 7.00 cu.m 900.00 6300.00 250.00 1750.00

    (c) backfill 131.00 cu.m 350.00 45850.00 250.00 32750.00

    Page 5 of 38

  • 7/28/2019 Greenmeadows Draft

    6/38

    Quantity Unit U/Cost Amount U/Cost Amount

    Material Labor

    (d) compaction sm

    BW-01-B Reinforced /Concrete Works

    (a) column footing (F-1A, F-2 & F-1)

    (a-1) concrete 8.00 cu.m 3750.00 30000.00 550.00 4400.00

    (a-2) rebars 391.00 kgs 42.00 16422.00 6.50 2541.50

    (b) wall footing (WF-1 & WF-2))

    (b-1) concrete 4.00 cu.m 3750.00 15000.00 550.00 2200.00

    (b-2) rebars 104 kgs 42.00 4368.00 6.50 676.00

    (c) Retaining wall footing RWF-1

    (c-1) concrete 9.00 cu.m 3750.00 33750.00 550.00 4950.00

    (c-2) rebars 417.00 kgs 42.00 17514.00 6.50 2710.50

    (d) Slab-On Fill

    (d-1) concrete 58.00 cu.m 3750.00 217500.00 550.00 31900.00

    (d-2) rebars 1743.00 kgs 42.00 73206.00 6.50 11329.50

    (e) Suspended slabs (S-1 thru S-6, CS-1 and CS-2)

    (e-1) concrete 19.00 cu.m 3750.00 71250.00 550.00 10450.00(e-2) rebars 2218.00 kgs 42.00 93156.00 6.50 14417.00

    (f) Columns (C-1, C-2, C-2B, C-2A & PC-1)

    (f-1) concrete 17.00 cu.m 3750.00 63750.00 550.00 9350.00

    (f-2) rebars 3902.00 kgs 42.00 163884.00 6.50 25363.00

    (g) Retaining wall (RW-1)

    (g-1) concrete 19.00 cu.m 3750.00 71250.00 550.00 10450.00

    (g-2) rebars 1664.00 kgs 42.00 69888.00 6.50 10816.00

    (h) Beams (RB-1 thru RB-5, B-1, B-1A, B-2 thru B-8,

    LB-1, CB-1, CRB-1 thru CRB-4)

    (h-1) concrete 22.00 cu.m 3750.00 82500.00 550.00 12100.00(h-2) rebars 3532.00 kgs 42.00 148344.00 6.50 22958.00

    BW-01-C Structural Steel Works

    (a) Planted steel columns (PSC-1, PSC-2) to include 1725.00 kgs 55.00 94875.00 22.00 37950.00

    (b) Steel girders (SB-1, SG-1A, SG-2 thru SG-6) 17385.00 kgs 55.00 956175.00 22.00 382470.00

    (c) Stair-7 framework to include all related steel/metal 697.00 kgs 55.00 38335.00 22.00 15334.00

    components and hardwares

    (d) Roof C-joists 50mmX150mm gauge-12 to include 8704.00 kgs 55.00 478720.00 22.00 191488.00

    shelf angles, bridgings, etc.

    (e) Skylite opening frame, 50mmX150mm gauge-14 0.00 kgs 55.00 0.00 22.00 0.00

    C-joists

    Page 6 of 38

  • 7/28/2019 Greenmeadows Draft

    7/38

    Quantity Unit U/Cost Amount U/Cost Amount

    Material Labor

    BW-01-D Associated Works

    (a) dowels for slab-on-fill attachments 100 kgs 55.00 5500.00 22.00 2200.00

    (b) formworks 242.00 sm 55.00 13310.00 22.00 5324.00

    (c) hauling of excess soil cu.m 55.00 0.00 22.00 0.00

    (d) structural epoxy grouts 1.00 lot 0.00 0.00

    (e) consummables 1.00 lot 0.00 0.00

    (f) testing works & laboratory reports/certifications 1.00 lot 0.00 0.00

    (g) other works (specify & itemize)

    Sub-Total for BW-01

    BW-02 Sanitary & Plumbing Works

    BW-02-A Hot & cold water supply

    (a) pipes

    (a-1) 50-mm 6.00 lght 1707.20 10243.20 682.88 4097.28

    (a-2) 32-mm 27.00 lght 1048.596 28312.09 419.44 11324.84

    (a-3) 25-mm 6.00 lght 533.86 3203.16 213.54 1281.26

    (a-4) 20-mm 25.00 lght 327.49 8187.25 131.00 3274.90(b) fittings 1.00 lot 28500.00 28500.00 12825.00 12825.00

    (c) gate valves

    (c-1) 50-mm pc/s

    (c-2) 32-mm pc/s

    (c-3) 25-mm pc/s

    (c-4) 20-mm pc/s

    (d) water meter

    (d-1) 50mm pc/s

    (d-2) 32mm pc/s

    (e) check valves(e-1) 50mm pc/s

    (e-2) 32mm

    (f) flexible connector 50-mm pc/s

    (g) suction float valve 50-mm pc/s

    (h) 2000-gallon domestic storage tank, 1.00 set/s 265000.00 265000.00 92750.00 92750.00

    complete with all pipes & fittings punp system,

    bladder tank, ladder and manhole cover with

    handle, electrical controls & panels, valves,

    connectors, including the reinforced cement

    tank structure as shown on sheet SP-7

    (i) associated works

    Page 7 of 38

  • 7/28/2019 Greenmeadows Draft

    8/38

    Quantity U nit U/Cost Amount U/Cost Amount

    Material Labor

    (h-1) excavation 9.00 cu.m 500.00 4500.00

    (h-2) backfill 9.00 cu.m 350.00 3150.00 250.00 2250.00

    (h-3) sand bedding 1.00 cu.m 250.00 250.00 150.00 150.00

    (h-4) formworks sm

    (h-5) other works (specify & itemize)

    BW-02-B Sewer / Waste / Vent

    (a) pipes

    (a-1) 100-mm 53.00 lght 787.50 41737.50 354.38 18781.88

    (a-2) 50-mm 9.00 lght 275.00 2475.00 123.75 1113.75

    (a-3) 75mm 3.00 lght 593.75 1781.25 267.19 801.56

    (b) fittings 1.00 lot 23850.00 23850.00 10732.50 10732.50

    (c) floor drains 50-mm 21 pc/s 550.00 11550.00 247.50 5197.50

    (d) clean-outs 11 pc/s 400.00 4400.00 180.00 1980.00

    (e) 7.00-gpm grease trap units, complete with 3.00 pc/s 12500.00 37500.00 5625.00 16875.00

    fittings and attachments

    (f) Sewage pit / tank reinforced concrete structure 1.00 unit 189000.00 189000.00 85050.00 85050.00to include (1) sewage ejector pump, duplex type

    submersible non-clog, 20 GPM vs. 40 ft.TDH

    approximately 0.5 HP as shown on sheet SP-2.

    (g) Septic tank in reinforced concrete construction, 1.00 unit 225000.00 225000.00 101250.00 101250.00

    to include manhole with covers as shown on

    sheet SP-3 piping works

    (h) associated works 1.00 lot 25000.00 25000.00 11250.00 11250.00

    (h-1) excavation

    (h-2) backfil

    (h-3) sand bedding(h-4) testing works

    (h-5) other works (specify & itemize)

    BW-02-C Storm Drainage

    (a) pipes\

    (a-1) 500-mm 3.00 lght

    (a-2) 250-mm 11.00 lght

    (a-3) 200-mm 9.00 lght

    (a-4) 150-mm 9.00 lght

    (a-5) 100-mm 14.00 lght 787.50 11025.00 354.38 4961.25

    (a-6) 75-mm 33.00 lght 275.00 9075.00 123.75 4083.75

    (a-7) 50-mm 20.00 lght 593.75 11875.00 267.19 5343.75

    Page 8 of 38

  • 7/28/2019 Greenmeadows Draft

    9/38

    Quantity Unit U/Cost Amount U/Cost Amount

    Material Labor

    (b) fittings 1.00 lot 18950.00 18950.00 8527.50 8527.50

    (c) deck drain 75-mm 22.00 pc/s 850.00 18700.00 382.50 8415.00

    (d) canopy drain 75-mm 18.00 pc/s 850.00 15300.00 382.50 6885.00

    (e) trench drain 8.00 pc/s 1350.00 10800.00 607.50 4860.00

    (f) area drain / catch basin structure 19.00 pc/s 2250.00 42750.00 1012.50 19237.50

    (g) associated works 1.00 lot

    (g-1) excavation

    (g-2) backfil

    (g-3) sand bedding

    (g-4) testing works

    (g-5) other works (specify & itemize)

    BW-02-D LPG Line

    (a) B.I. pipes

    (a-1) 20-mm 4.00 lghts 1850.00 7400.00 832.50 3330.00

    (a-2) 15-mm 2.00 lghts 1275.00 2550.00 573.75 1147.50

    (b) ball valve 2.00 set 475.00 950.00 213.75 427.50(c) safety regulator 2.00 set 985.00 1970.00 443.25 886.50

    (d) fittings 1.00 lot

    (e) associated works 1.00 lot

    (e-1) hinges / brackets

    (e-2) testing works

    (e-3) other works (specify & itemize)

    BW-02-E Installation of Owner-Supplied, toilet and bathroom

    fixtures & fittings :

    (a) Master Bedroom TB

    (a-1) Water closet : 2-units 2.00 unit 1250.00 2500.00

    (a-2) Lavatory/basin : 2-units 2.00 unit 1000.00 2000.00

    (a-2) Shower fittings : 1-set 1.00 sets 1000.00 1000.00

    (a-3) Lavatory fittings: 2-sets 1.00 sets 500.00 500.00

    (a-4) Paper Holder : 2-pcs 2.00 sets 500.00 1000.00

    (a-5) Towel bars : 4-pcs 4.00 pc/s 350.00 1400.00

    (b) TB (1), (2), (5), (6) & Powder Room

    (b-1) Water closet : 5-units 5.00 unit 1250.00 6250.00

    (b-2) Lavatory basin : 5-units 5.00 unit 1250.00 6250.00

    (b-3) Shower fittings : 4-sets 4.00 unit 200.00 800.00

    (b-4) Lavatory fittings : 5-sets 5.00 unit 200.00 1000.00

    (b-5) Paper holder : 5-pcs 5.00 unit 200.00 1000.00

    Page 9 of 38

  • 7/28/2019 Greenmeadows Draft

    10/38

    Quantity Unit U/Cost Amount U/Cost Amount

    Material Labor

    (b-6) Towel bars : 8-pcs 8.00 unit 200.00 1600.00

    (c) TB (3), (4) & (8)

    (c-1) Water closet : 3-units 3.00 unit 1250.00 3750.00

    (c-2) Lavatory basin : 3-units 3.00 unit 1250.00 3750.00

    (c-3) Shower fittings : 3-sets 3.00 unit 200.00 600.00

    (c-4) Laundry fittings : 3-sets 3.00 unit 200.00 600.00

    (c-5) Paper holder : 3-pcs 3.00 unit 200.00 600.00

    (c-6) Towel bars : 8-pcs 8.00 unit 200.00 1600.00

    Sub-Total for BW-02

    BW-03 Electrical and Auxiliary Works

    BW-03-A Service entrance and sub-feeders

    (a) 100mm THW 140.00 mts 698.00 97720.00 279.20 39088.00

    (b) 80mm THW 30.00 mts 568.00 17040.00 227.20 6816.00

    (c) 22mm THW 30.00 mts 156.75 4702.50 62.70 1881.00

    (d) 14mm THW 100.00 mts 102.00 10200.00 40.80 4080.00

    (e) C410(f) 1 - 1/4" PVC pipe 5.00 lghts 850.00 4250.00 340.00 1700.00

    (g) 2" RSC pipe 2.00 lghts 1475.00 2950.00 590.00 1180.00

    (h) Ground rod 20mm X 3M 1.00 lghts 1125.00 1125.00 450.00 450.00

    (i) Fittings, hangers, accessories 1.00 lot

    (j) Miscellaneous items 1.00 lot

    (k) Excavation works 1.00 lot

    (l) Others : pls specify

    BW-03-B Panelboards and disconnects

    (a) LPA 1.00 set 38080.00 38080.00 15232.00 15232.00

    (b) LPB 1.00 set 28840.00 28840.00 11536.00 11536.00

    (c) PPA 1.00 set 41440.00 41440.00 16576.00 16576.00

    (d) MDP 1.00 set 43652.00 43652.00 17460.80 17460.80

    (e) 225, 3P 65KAJC in stainless steel weatherproof 1.00 set 16750.00 16750.00 6700.00 6700.00

    enclosure

    (f) Miscellaneous items 1.00 lot

    (g) others: pls specify

    BW-03-C Power System Distribution

    (a) Conductors, THW insulation, rated 600V, 90oC

    2.0 mm 2250.00 mts 20.00 45000.00 7.00 15750.00

    3.5 mm 4950.00 mts 28.00 138600.00 9.80 48510.00

    5.5 mm 2400.00 mts 42.00 100800.00 14.70 35280.00

    Page 10 of 38

  • 7/28/2019 Greenmeadows Draft

    11/38

    Quantity U nit U/Cost Amount U/Cost Amount

    Material Labor

    (b) Conduits, nominal diameters indicated : 1380.00 pcs 60.00 82800.00 21.00 28980.00

    '' pipe

    (c) ''National'' wide series convenience outlet, 16A, 140.00 sets 315.00 44100.00 126.00 17640.00

    250V : Single, grounding type WEG1001 w/

    WEG6801W-1 Duplex, grounding type WEG1512

    w/ WEG6803W-1

    (d) Special purpose outlet with matching plug : 19.00 sets 375.00 7125.00 150.00 2850.00

    3-prong 30A

    (e) Fittings, hangers, accessories 1.00 lot

    (f) Misc items

    (g) Chipping works

    (h) Others : pls specify

    BW-03-D Auxiliary System Distribution

    (a) Sched. 40 PVC conduits, nominal indicated :

    ''

    '' 21''

    (b) Conductors

    4PR Cat 5E UTP cable

    (c) Telephone outlets with number of RJ-type

    4-position/4-conductor (Cat. 5) sockets as required

    Single

    (d) Cable TV outlet, modular type

    (e) Telephone terminal cabinet (TTC) :

    300mm(W) x 450mm(H) x 150mm(D)

    GA#16 sheet metal with key lock handle,

    12-pair bolt-screw type terminal block and

    20mm thick wooden backboard

    (f) Cable TV terminal cabinet (TTC) :

    300mm(W) x 450mm(H) x 150mm(D)

    GA#16 sheet metal with key lock handle, and

    20mm thick wooden backboard

    (g) Fittings, hangers, accessories

    (h) Misc items

    (i) Chipping works

    (j) Others : pls specify

    BW-03-E Lighting System Distribution

    Page 11 of 38

  • 7/28/2019 Greenmeadows Draft

    12/38

    Quantity U nit U/Cost Amount U/Cost Amount

    Material Labor

    (a) Conductors, THW insulation, rated 600V, 90oC

    3.5 mm 33.00 rolls 28.00 924.00 9.80 323.40

    5.5 mm 16.00 rolls 42.00 672.00 14.70 235.20

    8.0 mm 150.00 mts 63.00 9450.00 22.05 3307.50

    (b) Conduits, nominal diameters indicated : 0.00 0.00

    '' pipe 1380.00 pcs 60.00 82800.00 21.00 28980.00

    '' pipe

    (c) ''National'' wide series wall switches, 16A, 250V :

    1-Gang (WEG5001K w/ WEG6801W-1) 22.00 sets 110.00 2420.00 38.50 847.00

    1-Gang (WEG5002K w/ WEG6801W-1)

    2-Gang (WEG5001K w/ WEG6802W-1) 18.00 sets 170.00 3060.00 59.50 1071.00

    3-Gang (WEG5001K w/ WEG6803W-1) 12.00 sets 230.00 2760.00 80.50 966.00

    (d) Fittings, hangers, accessories

    (e) Misc items

    (f) Chipping works

    (g) Others : pls specifyBW-03-F Standby Power System

    (a) 100mm THW

    (b) 14mm THW

    (c) 2" PVC pipe

    (d) Fittings, hangers, accessories

    (e) Fire alarm bell 8" "Mircom"

    (f) Fire alarm pull station "Mircom"

    (g) Fittings, hangers, accessories

    (h) Misc items

    (i) Chipping works

    (j) Others : pls specify

    BW-03-G Installation of Owner-Supplied lighting fixtures:

    (a) Indoor bracket lamp -Type (A)

    Qty: 2-pcs (LG) 2.00 pcs 450.00 900.00

    3-pcs (2F) 3.00 pcs 450.00 1350.00

    (b) Surface mounted fluorescent

    Qty: 12-pcs (LG) SM 12.00 pcs 450.00 5400.00

    5-pcs (LG) WM 5.00 pcs 450.00 2250.00

    (c) In-wall lamp - Type (A)'' PVC pipe

    Qty: 2-pcs (LG) 2.00 pcs 450.00 900.00

    9-pcs (RD) 9.00 pcs 450.00 4050.00

    Page 12 of 38

  • 7/28/2019 Greenmeadows Draft

    13/38

    Quantity U nit U/Cost Amount U/Cost Amount

    Material Labor

    (d) On-ground uplights

    Qty: 24-pcs 24.00 pcs 450.00 10800.00

    (e) Outdoor bracket lamp

    Qty: 4-pcs (Site) 4.00 pcs 450.00 1800.00

    9-pcs (Ground) 1.00 pcs 450.00 450.00

    1-pc (SF)

    (f) Bracket lamp - Type (C)

    Qty: 1-pc (LG) 1.00 pcs 450.00 450.00

    3-pcs (GF) 3.00 pcs 450.00 1350.00

    (g) In-wall lamp - Type (B)

    Qty: 4-pcs 4.00 pcs 450.00 1800.00

    (h) Outdoor recessed downlights

    Qty: 18-pcs (GF) 18.00 pcs 450.00 8100.00

    (I) Indoor recessed downlights - Type (A) High Beam

    200mm

    Qty: 4-pcs (RD) 4.00 pcs 450.00 1800.00(j) Indoor recessed downlights - Type (B) 150mm

    Qty: 32-pcs (2F) 32.00 pcs 450.00 14400.00

    38-pcs (GF) 38.00 pcs 450.00 17100.00

    (k) Indoor recessed downlights - Type (C) 100mm

    Qty: 17-pcs (2F) 17.00 pcs 450.00 7650.00

    6-pcs (GF) 6.00 pcs 450.00 2700.00

    (l) Pendant light

    Qty: 5-pcs (RD) 5.00 pcs 450.00 2250.00

    5-pcs (GF) 5.00 pcs 450.00 2250.00

    (m) Surface mounted lights

    Qty: 1-pc (RD) 1.00 pcs 450.00 450.00

    4-pcs (2F) 4.00 pcs 450.00 1800.00

    10-pcs (GF) 10.00 pcs 450.00 4500.00

    (n) Outdoor under water lights

    Qty: 3-pcs (Site) 3.00 pcs 450.00 1350.00

    BW-03-H Coordination of the installation and commissioning

    of the Stand-by Power Generator by the contractor

    Sub-Total for BW-03

    BW-04 Architectural Works

    BW-04-A Roof

    (a) R-01 44.00 m2 475.00 20900.00 166.25 7315.00

    Page 13 of 38

  • 7/28/2019 Greenmeadows Draft

    14/38

    Quantity Unit U/Cost Amount U/Cost Amount

    Material Labor

    (b) R-02 513.00 m2 1926.00 988038.00 674.10 345813.30

    (c) R-03

    BW-04-B Walls and Enclosures

    (a) WE-01 366.00 m2 1125.00 411750.00 393.75 144112.50

    (b) WE-02 79.00 m2 875.00 69125.00 306.25 24193.75

    (c) WE-03

    (d) WE-04

    (e) WE-05 790.00 m2 975.00 770250.00 341.25 269587.50

    (f) WE-06 (glass blocks) 8.00 m2 4500.00 36000.00 1575.00 12600.00

    BW-04-C Plaster Works

    (a) PW-01 772.00 m2 135.00 104220.00 120.00 92640.00

    (b) PW-02

    BW-04-D Ceiling Works

    (a) C-01 578.00 m2 750.00 433500.00 262.50 151725.00

    (b) C-02 405.00 m2 650.00 263250.00 227.50 92137.50

    (c) C-03 179.00 m2 110.00 19690.00 120.00 21480.00BW-04-E Floors and Pavements

    (a) FP-02 119.00 m2 110.00 13090.00 120.00 14280.00

    (b) FP-03 245.00 m2 110.00 26950.00 38.50 9432.50

    (c) FP-04 264.00 m2 110.00 29040.00 38.50 10164.00

    (d) FP-05 3.00 m2 875.00 2625.00 306.25 918.75

    (e) FP-01 56.00 m2 110 6160.00 120.00 6720.00

    BW-04-F Surfacing / Finishes / Treatments

    (a) SFT-01 56.00 m2 275.00 15400.00 120.00 6720.00

    (b) SFT-02 793.00 m2 180.00 142740.00 120.00 95160.00

    (c) SFT-03 730.00 m2 450.00 328500.00 120.00 87600.00

    (d) SFT-04 105.00 m2

    (e) SFT-05 250.00 m2

    (f) SFT-06 24.00 m2

    BW-04-G Associated Works 280.00 m2

    (a) AWM-01 Integral waterproofing

    (b) AWM-02 Fiber reinforcenment 517.00 m2

    (c) AWM-03 Moisture barrier 1326.00 m2

    (d) AWM-04 Wire mesh 693.00 m2

    (e) AWM-05 Thermal insulation/bubble fiber 513.00 m2

    (f) AWM-06 PU-sealant 513.00 m2

    (g) AWM-07 Thermal insulation fibre

    Page 14 of 38

  • 7/28/2019 Greenmeadows Draft

    15/38

    Quantity Unit U/Cost Amount U/Cost Amount

    Material Labor

    (h) AWM-08 Protective paint

    (i) AWM-09 Termiticide

    BW-04-H Installation of Owner-Supplied /building products,

    materials and contracted goods

    (a) WB-01 floor boards 12.00 sm

    (b) WB-02 stair boards (stair-7) 3.00 sm(c) Wood Doors Assemblies 2.00

    c-1) Sliding door - 2-sets WSD-1 1.00 set/s 1500.00 3000.00

    c-2) Sliding door - 1-set WSD-2 1.00 set/s 1500.00 1500.00

    c-3) Sliding door - 1-set WSD-3 1.00 set/s 1500.00 1500.00

    c-4) Sliding door - 1-set WSD-4 1.00 set/s 1500.00 1500.00

    c-5) Slliding door - 1-set WSD-5 1.00 set/s 1500.00 1500.00

    c-6) Hinged door - 1-set WD-6 1.00 set/s 1500.00 1500.00

    c-7) Hinged door - 2-sets WD-7 2.00 set/s 1500.00 3000.00

    c-8) Hinged door - 8-sets WD-8 8.00 set/s 1500.00 12000.00

    c-9) Hinged door - 1-set WD-9 1.00 set/s 1500.00 1500.00c-10) Hinged door - 18-sets WD-10 18.00 set/s 1500.00 27000.00

    c-11) Hinged door - 2-sets WD-11 2.00 set/s 1500.00 3000.00

    c-12) Hinged door - 4-sets WD-12 4.00 set/s 1500.00 6000.00

    (d) Wood Door Hardwares

    (d-1) 5-sets WDH-1 sliding mechanism 5.00 set/s 100.00 500.00

    (d-2) 5-pairs WDH-2 sliding door guide 5.00 set/s 100.00 500.00

    (d-3) 5-sets WDH-3 flushed handle lock 5.00 set/s 100.00 500.00

    (d-4) 3-sets WDH-4 custom handle 3.00 set/s 100.00 300.00

    (d-5) 3-sets WDH-5 floor hinge 3.00 set/s 100.00 300.00

    (d-6) 2-sets WDH-6 deadbolt 2.00 set/s 100.00 200.00

    (d-7) 9-sets WDH-7 deadbolt 9.00 set/s 100.00 900.00

    (d-8) 9-sets WDH-8 deadbolt 9.00 set/s 100.00 900.00

    (d-9) 2-sets WDH-9 knobset 2.00 set/s 100.00 200.00

    (d-10) 1-set WDH-10 knobset 1.00 set/s 100.00 100.00

    (d-11) 3-sets WDH-11 knobset 3.00 set/s 100.00 300.00

    (d-12) 22-sets WDH-12 lever lockset 22.00 set/s 100.00 2200.00

    (d-13) 8-sets WDH-13 lever lockset 8.00 set/s 100.00 800.00

    (d-14) 130-pairs WDH-14 butt hinges 130.00 set/s 100.00 13000.00

    (d-15) 37-pairs WDH-15 door stopper 37.00 set/s 100.00 3700.00

    (e) Wood Handrail

    (e-1) Main stair balustrade top rail 3.00 set/s 1500.00 4500.00

    Page 15 of 38

  • 7/28/2019 Greenmeadows Draft

    16/38

    Quantity U nit U/Cost Amount U/Cost Amount

    Material Labor

    (e-2) 2/f corridor balustrade top rail 3.00 set/s 1500.00 4500.00

    (f) Custom Steel Works 0.00

    (f-1) CSW-01 balustrade of main stair/2F corridor 3.00 set/s 1500.00 4500.00

    (f-2) CSW-02 MBR balcony balustrade 3.00 set/s 1500.00 4500.00

    (f-3) CSW-03 Stair (2) & (3) 2.00 set/s 1500.00 3000.00

    (f-4) CSW-04 ladder 1.00 set/s 1500.00 1500.00(f-5) CSW-05 balustrade 16.00 set/s 1500.00 24000.00

    (g) Floor and Wall Tiles BY OTHERS

    (g-1) FWT-01 Floor tiles

    (g-2) FWT-02 Floor tile

    (g-3) FWT-03 Floor tiles

    (g-4) FWT-04 Floor tiles

    (g-5) FWT-05 Floor & wall tiles

    (g-6) FWT-06 Floor & wall tiles

    BW-04-I Coordination of the execution and installation of BY OTHERS

    Owner's contracted works/systems with othercontractors

    (a) Roof skylight

    (b) AC and ventilation systems

    (c) Waterproofing & water barrier systems

    (d) Kitchen cabinets & counter systems

    (e) Wardrobe cabinet systems

    (f) Shower screens/ enclosures

    (g) Fitted / Built-in casegoods

    (h) Landscape works

    (i) Aluminum & glass doors & windows systems

    Sub-Total for BW-04

    Total for Building Works

    Site and General Overhead

    SGO-01 Site utilities operating and consumption cost

    SGO-01-A Electricity

    SGO-01-B Water

    SGO-02-C Telephone / communication

    SGO-01-D Transportation fares / gasoline

    SGO-01-E Delivery tolls

    Page 16 of 38

  • 7/28/2019 Greenmeadows Draft

    17/38

    Quantity Unit U/Cost Amount U/Cost Amount

    Material Labor

    Sub-Total for SGO-01

    SGO-02 Technical and administrative staffing

    (pls itemize manpower with corresponding designations / titles

    and costs, i.e., wages / salaries + benefits)

    Sub-Total for SGO-02

    SGO-03 Other expenses (specify and itemize)

    Sub-Total for SGO-03

    Sub-Total for Site and General Overhead

    Page 17 of 38

  • 7/28/2019 Greenmeadows Draft

    18/38

    Quantity Unit U/Cost Amount U/Cost Amount

    Material Labor

    Post-Construction

    POC-01 Occupancy permits and Certificate of Inspection from

    the Office of the Building Official - Quezon City to include

    settlement of the fees and other financial requirementsSub-total for POC-01

    POC-02 Certification of Completion and Compliance / clearance

    from First Greenmeadows Homeowners Asso. Inc.(FGHAI) Office

    Sub-total for POC-02

    POC-03 Warranty Bond covering the WCP-01 & WCP-02

    Sub-total for POC-03

    POC-04 Preparation, submission and turn-over of the followng

    technical and legal documents :

    POC-04-A As-Built and Record drawings for

    Architectural, Structural, Electrical andSanitary/Plumbing

    POC-04-B Original copies of all permits, certification,

    certificate of compliance issued by FGHAI

    and Office of the Building Official - Quezon City

    POC-04-C Test-reports and duly certified results

    POC-04-D Literature, warranties and maintenance

    manuals of all building products, equipment,

    and special materials other than those

    procured directly by the Owner

    Sub-total for POC-04

    POC-05 Affidavit & other legal instruments necessary to safeguard

    the Owners from liabilities and disputes, arising from the

    performance of the works by the Main Contractor

    Sub-total for POC-05

    POC-06 Demobilization & site of work clearing, cleaning and

    disinfection, to include removal of all temporary facilities

    and utilities.

    Sub-total for POC-06

    Total for Post-Construction

    Total Price Proposal Before Value Added Tax

    Page 18 of 38

  • 7/28/2019 Greenmeadows Draft

    19/38

    Quantity Unit U/Cost Amount U/Cost Amount

    Material Labor

    Value Added Tax

    Grand Total Price Proposal

    Page 19 of 38

  • 7/28/2019 Greenmeadows Draft

    20/38

    Total

    230000.00

    230000.00

    100000.00

    3500.00

    5000.00

    108500.00

    65000.00

    65000.00

    90000.00

    220000.00

    60000.00

    30000.00

    25000.00

    20000.00

    Page 20 of 38

  • 7/28/2019 Greenmeadows Draft

    21/38

    Total

    20000.00

    22000.00

    177000.00

    735500.00

    Page 21 of 38

  • 7/28/2019 Greenmeadows Draft

    22/38

    Total

    77500.001150.00

    66000.00

    4300.00

    5820.00

    4300.00

    4400.00

    15050.00

    23037.50

    4300.00

    6305.00

    4300.0019400.00

    Page 22 of 38

  • 7/28/2019 Greenmeadows Draft

    23/38

    Total

    4850.00

    10000.00

    2500.00

    253212.5

    Page 23 of 38

  • 7/28/2019 Greenmeadows Draft

    24/38

    Total

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.000.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.000.00

    0.00

    0.00

    75000.00

    1750.0078600.00

    Page 24 of 38

  • 7/28/2019 Greenmeadows Draft

    25/38

    Total

    34400.00

    18963.50

    17200.00

    5044.00

    38700.00

    20224.50

    249400.00

    84535.50

    81700.00107573.00

    73100.00

    189247.00

    81700.00

    80704.00

    94600.00171302.00

    132825.00

    1338645.00

    53669.00

    670208.00

    0.00

    Page 25 of 38

  • 7/28/2019 Greenmeadows Draft

    26/38

    Total

    7700.00

    18634.00

    0.00

    10000.00

    18000.00

    2500.00

    3755924.50

    4097.28

    39636.93

    4484.42

    11462.15

    41325.00

    357750.00

    Page 26 of 38

  • 7/28/2019 Greenmeadows Draft

    27/38

    Total

    4500.00

    5400.00

    400.00

    60519.38

    3588.75

    2582.81

    34582.50

    16747.50

    6380.00

    54375.00

    274050.00

    326250.00

    36250.00

    15986.25

    13158.7517218.75

    Page 27 of 38

  • 7/28/2019 Greenmeadows Draft

    28/38

    Total

    27477.50

    27115.00

    22185.00

    15660.00

    61987.50

    17500.00

    10730.00

    3697.50

    1377.502856.50

    4500.00

    9000.00

    2500.002000.00

    1000.00

    500.00

    1000.00

    1400.00

    6250.00

    6250.00

    800.00

    1000.00

    1000.00

    Page 28 of 38

  • 7/28/2019 Greenmeadows Draft

    29/38

    Total

    1600.00

    3750.00

    3750.00

    600.00

    600.00600.00

    1600.00

    1571031.97

    136808.00

    23856.00

    6583.50

    14280.00

    5950.00

    4130.00

    1575.00

    12500.00

    18000.00

    4000.00

    53312.00

    40376.00

    58016.00

    61112.80

    23450.00

    22350.00

    60750.00

    187110.00

    136080.00

    Page 29 of 38

  • 7/28/2019 Greenmeadows Draft

    30/38

    Total

    111780.00

    61740.00

    9975.00

    3500.00

    Page 30 of 38

  • 7/28/2019 Greenmeadows Draft

    31/38

    Total

    1247.40

    907.20

    12757.50

    0.00

    111780.00

    3267.00

    4131.00

    3726.00

    900.00

    1350.00

    5400.00

    2250.00

    900.004050.00

    Page 31 of 38

  • 7/28/2019 Greenmeadows Draft

    32/38

    Total

    10800.00

    1800.00

    450.00

    450.00

    1350.00

    1800.00

    8100.00

    1800.00

    14400.00

    17100.00

    7650.00

    2700.00

    2250.00

    2250.00

    450.00

    1800.00

    4500.00

    1350.00

    5000

    4433867.06

    28215.00

    Page 32 of 38

    T t l

  • 7/28/2019 Greenmeadows Draft

    33/38

    Total

    1333851.30

    0.00

    555862.50

    93318.75

    0.000.00

    1039837.50

    48600.00

    196860.00

    585225.00

    355387.50

    41170.00

    27370.00

    36382.50

    39204.00

    3543.75

    12880.00

    22120.00

    237900.00

    416100.00

    Page 33 of 38

    Total

  • 7/28/2019 Greenmeadows Draft

    34/38

    Total

    3000.00

    1500.00

    1500.00

    1500.00

    1500.00

    1500.00

    3000.00

    12000.00

    1500.0027000.00

    3000.00

    6000.00

    500.00

    500.00

    500.00

    300.00

    300.00

    200.00

    900.00

    900.00

    200.00

    100.00

    300.00

    2200.00

    800.00

    13000.00

    3700.00

    4500.00

    Page 34 of 38

    Total

  • 7/28/2019 Greenmeadows Draft

    35/38

    Total

    4500.00

    4500.00

    4500.00

    3000.00

    1500.0024000.00

    5207727.8

    14968551.33

    100000.00

    70000.00

    15000.00

    50000.00

    Page 35 of 38

    Total

  • 7/28/2019 Greenmeadows Draft

    36/38

    Total

    235000.00

    300000.00

    300000.00

    535000.00

    Page 36 of 38

    Total

  • 7/28/2019 Greenmeadows Draft

    37/38

    100000.00

    100000.00

    25000.00

    65000.00

    25000.00

    5000.00

    20000.00

    5000.00

    55000.00

    60000.00

    60000.00

    215,000.00

    16,454,051.33

    Page 37 of 38

  • 7/28/2019 Greenmeadows Draft

    38/38

    Total

    Page 38 of 38