grid code supervisory committee...engr. khalid huzaifa al-nafey engr. rasheed mohammad al-shubaili...
TRANSCRIPT
ANNUAL REPORT 2011
Activities and
Accomplishments
Grid Code Supervisory Committee
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
Table of Contents
1. Message from the Chairman ..................................................................... 1
2. Establishment ............................................................................................ 3
3. A Pictorial Introduction to the GCSC Team ............................................... 4
4. GCSC Function ......................................................................................... 5
5. Highlights of Activities, Performance and Achievements ........................... 6
6. Business Meetings Over the Years ......................................................... 11
7. Salient Features of 2012 Action Plan ...................................................... 13
8. Captured Moments During this Year's Meetings ..................................... 14
9. Annexure ................................................................................................. 17
Schedule A: Record of Amendments
Schedule B: Record of Derogation
Schedule C: Recommendation sent to ECRA
Schedule D: ECRA’s Decision on the Recommendations
Schedule E: Minutes of GCSC’s Meetings
ANNUAL REPORT 2011
1
GCSC
A Message from the Chairman
Congratulations GCSC for another year well done.
It has been another fruitful year for the GCSC and it is noteworthy to mention the
excellent efforts made by our distinguished Committee Members and the Secretariat
as well. Through the detailed discussions on the proposals submitted before us, we
were able to process and recommend to ECRA the numerous derogations requested
by the existing generators as well as some amendments in the SAGC. I, therefore,
thank all the members of the GCSC for their untiring efforts in sharing their knowledge
and expertise for the betterment of the Kingdom's Electricity Industry.
Moving forward to our 5th year of efficient operation, we need to be strongly
determined to continuously face the enormous challenges ahead, welcoming new
policies, directives, and strategies coming from our competent government and
regulatory authorities. Such may include new policies and programs to encourage the
private sector to facilitate the development of new technologies and renewable
energy sources within the Kingdom. I believe that we cannot ignore the fact that these
new technologies e.g. nuclear; and the renewable energies such as solar and wind are
now being lined up to contribute to our generation mix in the near future.
I, therefore, ask all of you to constantly deliver and give your best to enhance the
operation of our humble Committee. All of us must continue to study and seek
appropriate changes to our SAGC to further improve and enhance its implementation.
SAGC is not cast in stone. As what other prominent countries have been doing with
respect to their Grid Codes, amendments must also be done to our SAGC, whenever
ANNUAL REPORT 2011
2
GCSC
necessary. Provide as much technical proof as needed to support any request for
amendment or derogation. For the last 5 years that the SAGC has been in existence,
we already have a handful of amendments that have gained approval of ECRA. With
this, I believe that it is now timely that we should work on the issuance of the first
revision of the SAGC.
Year 2012 will be a more exciting and challenging year for us. As all of you may be
aware, the preparation towards the unbundling of the Generation, Transmission, and
Distribution sectors of SEC are ongoing. The setting-up of the Kingdom's National
Control Center is also ongoing to ensure smooth flow and transfer of electricity among
the different operating areas (e.g. Central, East, South, and West). On another note,
we are also hoping that the initial set of guidelines for the monitoring of the effective
implementation of the SAGC will be completed and approved for implementation,
Insha Allah.
With the ongoing restructuring of our electricity industry, there will be more
challenges to be expected especially when the time comes that the Market Code has
been finalized, approved, and ready for implementation.
With this, I am looking forward for more active participation and support from the
members as we face more challenges this 2012. Again, thank you and more power.
Hamed A. Al-Saggaf
Chairman, GCSC
ANNUAL REPORT 2011
Establishment 3
GCSC
1. Establishment
The Grid Code Supervisory Committee (GCSC) was established as per the ECRA
Governor's decision number 12\429 dated 4\3\2008. The GCSC was established to
assist the TSP in ensuring effective implementation of the SAGC. In addition, the
GCSC will help to ensure fair, economical, and transparent connection to, and
operation of the grid, as well as to contribute in the development of a competitive
power market in the Kingdom. It is worth to note here that National Grid has already
been created within SEC to perform the transmission function of the Saudi Electricity
Company.
Table 1: Components of the Grid Code Supervisory Committee
Representation
Category
Component Stakeholder Entity
Chairman Member
Transmission
1 2
1
Regulator 1
Generation
(More than 500 MW)
1
1
Generation
(Less than 500 MW) 1
Distribution
2
1
1
Directly Connected Customers
1
ANNUAL REPORT 2011
A Pictorial Introduction to the GCSC Team 4
GCSC
2. A Pictorial Introduction to the GCSC Team
Engr. Hamed A Al-Saggaf
Engr. Fayez Gaith
Al-Jabri
Dr. Abdullah Muhammad Al-
Abbas
Chairman, SEC Regulator, ECRA Generation, SEC
Engr. Ahmed Yaqoub Al-Furaih
Dr. Mahmoud Bahi El-Din Zayan Engr. Nezar M Saeed Al-Khanaizi
Generation, SWCC Generation, ARAMCO Transmission, SEC
Engr. Mohammad Y Al-ZahraniEngr. Salman Atiya Al-Zahrani
Engr. Mohammad Y. Al-Taher
Transmission, SEC Transmission, MARAFIQ Distribution, SEC
Engr. Fouad M. Al-
AbdulqaderEngr. Saleh Al-Amri
Engr. Khalid Huzaifa
Al-Nafey
Engr. Rasheed
Mohammad Al-Shubaili
Distribution, SEC Distribution, ARAMCO Distribution, MARAFIQ DCC, SABIC
ANNUAL REPORT 2011
GCSC Function 5
GCSC
3. GCSC Function
Keep the SAGC and its working under review
Review and recommend amendments to SAGC
Guide on Code's implementation & interpretation
Consider changes to deal with unforeseen issues
Review and recommend on derogation requests
ANNUAL REPORT 2011
Highlights of Activities, Performance and Achievements 6
GCSC
4. Highlights of Activities, Performance and Achievements
1. Updating of Web Portals
The information provided in both the SAGC and the Committee Web Portals
were updated as follows: (i) recent status of Members' information; (ii) Minutes
of the Meetings; (iii) Annual Reports; (iv) GCSC's recommendations on
amendment and derogation requests; and (v) ECRA's decisions.
2. Sub-committee formed to review SEC's derogation requests
The GCSC formed a sub-committee to study the technical justifications found in
derogation requests package 09D05-09D074 submitted by SEC-Generation of
Western region. This sub-committee consisted of members from the Generation
and SEC’s Transmission Operation.
The sub-committee coordinated with the different manufacturers of generating
units to inquire about the capabilities of these units requesting for derogations
as well as to receive some technical inputs regarding the actual performance
relating to the compliance with the requirements of the Code on voltage and
frequency limits. The sub-committee also conducted a couple of meetings to
discuss the responses of manufacturers and to share the views of other
members as well.
The sub-committee informed the GCSC of the correspondences to
manufacturers and their responses regarding under frequency and overvoltage
cases. In addition, the sub-committee determined that sections 2.5.5.2 and
2.5.5.8 of the SAGC clearly stipulate that a proportionate decrease in active
power of the generating unit is allowed as a consequence of deviation of the
frequency to operate within the required frequency range. As a result, the GCSC
voted on the set of derogation requests.
ANNUAL REPORT 2011
Highlights of Activities, Performance and Achievements 7
GCSC
3. Forming of a Sub-Committee tasked to monitor Users Compliance with the
Code
The Chairman directed to form a Technical Sub-Committee composing of two
members from the Transmission Operation and one from ECRA that would be
responsible for the monitoring of the Compliance of Users with the SAGC. The
member from ECRA was designated by the Chairman to head this
subcommittee. The GCSC has then agreed to add a fix agenda item to discuss
relevant examples pertaining to users' compliance with the Code.
The Committee stated that the GCSC is required to guide the Users with respect
to the implementation of the Code. However, the TSP should monitor the
compliance with the Code as stated in the Implementing Regulations of the
Electricity Law, Condition 11.1.11.
4. Amendment Requests recommended by the Committee for approval of ECRA
On the processing of Amendment Requests, the Committee has recommended
two (2) requests for amendments pertaining to "Schedule Day" and "Alerts"
having Amendment Nos. 11A030 and 11A031, respectively, in order for the
SAGC to become consistent with the Interconnection Transmission Code of the
Gulf Cooperation Council Interconnection Authority. Please see the attached
Schedule C of the Annexure for complete details.
5. Granting a set of derogations submitted by SEC Generation - Western
Operating Area- regarding frequency variation of generating unit
The Committee has granted approval on a set of Derogation for Alstom (ABB)
units as follow: Units are to be derogated for the lower limit 57.5 Hz for 30
minutes and the lower limit 57.0 Hz for 30 seconds, pertaining to clause 2.4.2. of
the SAGC. The details of the approval were as follows:
ANNUAL REPORT 2011
Highlights of Activities, Performance and Achievements 8
GCSC
No. Particular SAGC Requirement Derogation granted
1 Frequency Variations
57.5 to 58.7 Hz. for a period of 30 minutes
57.6 to 58.7 Hz. for a period of 30 minutes
2 57 to 57.4 Hz. for a
period of 30 seconds 57 to 57.5 Hz. for a period
of 5 seconds
The detailed proposal with the corresponding approval is provided in Schedule C
of the Annexure for complete details.
6. Derogation Requests approved by the Committee pertaining to Voltage
Variations
On the processing of derogation requests regarding Voltage Variations, three (3)
requests have been approved for ABB GT Units and two (2) for GE Gas Turbine
units. Said units are to be derogated for 15 years for operating on the upper
limit +10% on 30 minutes as follows: (i) 09D041 for Makkah Power Plant - Type
11D5 GT Nos. 8 to 12; (ii) 09D053 for Madinah PP1, Type 9C GT No. 3; (iii)
09D056 for Madinah PP2, Type 9D GT Nos. 1, 2 & 5; (iv) 09D045 Makkah Power
Plant - GE Gas Turbines, Frame 7B GT Nos. 4 to 7; and (v) 09D049 for Makkah
Power Plant - GE Gas Turbines, Frame 7E GT Nos. 13 to 18. Please see the
attached Schedule C of the Annexure for complete details.
7. ECRA's Approval on the Proposed Amendments to the SAGC
The GCSC has received the approval of the Board of ECRA pertaining to the
various amendments to be included in the new publication of the Code. The
GCSC has discussed in its 12’th meeting, the mechanism of the inclusions of the
approved amendments, since 5 years has already passed after the issuance of
the Grid Code. The committee then decided to issue the subsequent revisions of
the code every 5 years. Hence, the next version is expected to be issued on July
2012. Details of said approvals are attached under Schedule D of the Annexure.
ANNUAL REPORT 2011
Highlights of Activities, Performance and Achievements 9
GCSC
8. Updating the Registry of Amendment and Derogation requests
The committee discussed and processed twenty-four requests for amendment
to the SAGC, and sixty derogation requests from the SAGC during its regular
meetings since 2008. The committee clarified among its members the difference
between the amendment requests and derogation requests, and the conditions
when to ask for such request. Shown in the figure below are the steps for
processing amendments and derogation requests.
Figure 1: Steps for processing amendments and derogation requests
As shown in the above diagram, the GCSC will consider the amendment or
derogation request, and submit its recommendations to ECRA for a final
decision. ECRA will take decision after considering the proposal and
recommendation from the GCSC and will inform the GCSC about its decision.
The GCSC will then inform the initiator whether his request has been accepted
or not. For amendment proposals, the GCSC will keep a record of all approved
amendments to be incorporated in the next revision of the SAGC. While for
Proposal Prepared
Submitted to GCSC
GCSC consults experts
GCSC finalizes its review
GCSC recommends to
ECRA
ECRA condisers and decides
ECRA informs GCSC
GCSC informs the initiator
GCSC takes action
ANNUAL REPORT 2011
Highlights of Activities, Performance and Achievements 10
GCSC
derogation proposals, if a user’s proposal is rejected, he shall comply with the
existing provisions of the Code. If his proposal is accepted or modified then this
user will not be required to comply with the relevant provision(s) of the SAGC
but will instead comply with any alternate provision(s) mentioned in the
derogation.
Chart 1: Statistics of the status of Amendment and Derogation Requests
So far, the GCSC has received 44 Amendments Requests classified as follows:
Requests discussed: 24
Withdrawn and re-submitted as derogation requests: 4
Clarification sought for: 1
Suspended as per proposer's request: 20
Agreed and recommended to ECRA: 8
Refuted with appropriate justifications: 11
Approved by ECRA: 5
In addition, the GCSC has received 74 requests for derogation, from provisions of
the SAGC, classified as follows:
44
74
24
68
8
18
58
0
10
20
30
40
50
60
70
80
Amendments Derogations
Received
Discussed
Recommended
Approved
ANNUAL REPORT 2011
Business Meetings Over the Years 11
GCSC
Requests discussed: 68
Withdrawn by the proposer: 45
Agreed and recommended to ECRA: 18
Granted by ECRA: 8
5. Business Meetings Over the Years
Statistics of GCSC Meetings
Event Date Attendees Venue Sponsor
1st Meeting 23/03/2008
Members:12
Guests:1
Absent:1
Riyadh -
ECRA office
2nd Meeting 05/05\2008
Members:10
Alternates:2
Guest:1
Absents:3
Riyadh -
Sheraton
Hotel
3rd Meeting 21/10/2008
Members:12
Guests:5
Absent:1
Riyadh -
Sabic HQ.
4th Meeting 19/01/2009
Members:11
Alternates:2
Guests:3
Absents:2
Dhahran -
Aramco R&D
Center
5th Meeting 25/03/2009
Members:11
Alternates:2
Guests:2
Absents:2
Yanbu -
Holiday Inn
Hotel
6th Meeting 10/06/2009
Members:13
Alternate1:1
Guests:4
Absent:1
Al-Khobar -
Golden Tulip
7th Meeting 03/11/2009
Members:12
Alternates:2
Guests:2
Absents:2
Riyadh -
Marriot Hotel
8th Meeting 03/03/2010
Members:10
Alternates:3
Guests:2
Absents:4
Jeddah -
Hilton Hotel
9th Meeting 15/06/2010
Members:12
Alternate:1
Guests:4
Absents:2
Al- Khobar -
Holiday Inn
Hotel
ANNUAL REPORT 2011
Business Meetings Over the Years 12
GCSC
Event Date Attendees Venue Sponsor
10th
Meeting 30/10/2010
Members:11
Alternates:2
Guest:1
Absents2:
Al- Khobar -
Holiday Inn
Hotel
11th
Meeting 16/2/2011
Members:13
Alternates:
Guest:5
Absents:
Madinah –
Movenpick Hotel
12th
Meeting 24/5/2011
Members:10
Alternates:3
Guest:2
Absents:
Al- Khobar -
Coral
International
Hotel
13th
Meeting 21/9/2011
Members:6
Alternates:6
Guest:1
Absents:7
Riyadh –
Madareem
Crown Hotel
ANNUAL REPORT 2011
Salient Features of 2012 Action Plan 13
GCSC
6. Salient Features of 2012 Action Plan
SALIENT FEATURES OF 2012 ACTION PLAN
ecommend proposals to amend SAGC for the handlingand treatment of New Technologies and RenewableEnergy Sources in the Grid.
xplore the possible amendments that must be included in the SAGC with regard to the functions and obligations of the Single Buyer.
acilitate improvement, by providing necessary recommendations, on the performance of the Grid Users pertaining to their compliance with the pertinent provisions of the SAGC.
rganize workshops for the industry stakeholders with regard to the important technical aspects of the Code as well as on the amendments recently approved by the Board of ECRA.
equire the entities that have been granted derogations by ECRA to prepare and submit reports, as may be necessary, with respect to its continued need and the details of actions being done to restore compliance with the SAGC.
onitor and quickly respond to any important and relevant issues pertaining to the restructuring of the Kingdom's Electricity Industry including matters such as on the developments with respect to the crafting of the Market Code.
ANNUAL REPORT 2011
Captured Moments During this Year's Meetings 14
GCSC
7. Captured Moments During this Year's Meetings
11th GCSC Meeting at Movenpick Hotel, Madinah on February 16, 2011
ANNUAL REPORT 2011
Captured Moments During this Year's Meetings 15
GCSC
12th GCSC Meeting at Coral International Hotel, Al-Khobar on May 24, 2011
ANNUAL REPORT 2011
Captured Moments During this Year's Meetings 16
GCSC
13th GCSC Meeting held at Madareem Crown Hotel, Riyadh on September 21, 2011
ANNUAL REPORT 2011
Annexure 17
GCSC
8. Annexure
Schedule A: Record of Amendments
Schedule B: Record of Derogations
Schedule C: Recommendations sent to ECRA
Schedule D: ECRA’s Decisions on the Recommendations
Schedule E: Minutes of GCSC's Meetings
ANNUAL REPORT 2011
GCSC
Schedule A: Record of Amendments
ANNUAL REPORT 2011
Schedule A: Record of Amendments
GCSCSr. No.
Amendment Registration
No.
Date of Submission
Submitted by SAGC Clause(s)
No. Summary of the
Request GCSC
Recommendation(s)
Date Submitted
to ECRA
ECRA's Decision
Action Taken /
Required Status
1 08A001 25-Aug-08 Aramco-
Distribution
1 Include definition of captive cogeneration as defined by ECRA
Not recommended __ __ None Completed at the 3
rd GCSC
Meeting
1.16.1
Revise to state that in the event of conflict
between the Grid Code and agreements
between a User and the TSP or ECRA, the
agreement shall govern.
Not recommended __ __ None
Discussed and withdrawn by proposer at the 3
rd GCSC
Meeting
3.3.1.2
Revise to give the users the right to review the requirements for users
to modify or install new plants or
apparatus
Not recommended __ __ None
Discussed and withdrawn by proposer at the 3
rd GCSC
Meeting
2 08A002 15-Sep-08 SEC - Generation 2.4.2 Frequency
Variations
The frequency shall be revised and minimum
frequency for all generators shall not go
below 58.2 Hz
To be discussed later __ __ __ Postponed
3 08A003 15-Sep-08 SEC - Generation 2.4.3 Voltage
Variations
The voltage settings shall be revised to +8%
for all the GT generators in power
plants.
To be discussed later __ __ __ Postponed
4 08A004 15-Sep-08 SEC - Generation 2.5.1.1 and
2.5.2.9
Remove contradiction for specifying
connection points Not recommended __ __ None
Completed at the 3
rd GCSC
Meeting
5 08A005 15-Sep-08 SEC - Generation 2.5.2.14 (i)
The TSP should not be the final deciding
authority in case of disputes
Not recommended __ __ None Completed at the 4
th GCSC
Meeting
ANNUAL REPORT 2011
Schedule A: Record of Amendments
GCSCSr. No.
Amendment Registration
No.
Date of Submission
Submitted by SAGC Clause(s)
No. Summary of the
Request GCSC
Recommendation(s)
Date Submitted
to ECRA
ECRA's Decision
Action Taken /
Required Status
6 08A006 15-Sep-08 SEC - Generation 2.7.7.1 The TSP shall follow
the user safety rules in all cases.
Not recommended __ __ None Completed at the 4
th GCSC
Meeting
7 08A007 15-Sep-08 Aramco-
Generation
2.3.1.10 (proposed new
section)
Establishing a queue system for
interconnection requests
Not recommended __ __ None Completed at the 4
th GCSC
Meeting
8 08A008 15-Sep-08 Aramco-
Generation 2.3.2
TSP should have separate and standardized
documents to deal with interconnection
requests
Not recommended __ __ None Completed at the 4
th GCSC
Meeting
9 08A009 15-Sep-08 Aramco-
Generation 2.3.2.6
Delete whole paragraph and replace with the suggested text
Not recommended __ __ None Completed at the 4
th GCSC
Meeting
10 08A010 15-Sep-08 Aramco-
Generation 2.3.4.2 Delete item (i) Not recommended __ __ None
Completed at the 4
th GCSC
Meeting
11 08A011 15-Sep-08 Aramco-
Generation 2.3.4.3 Delete item (ii) Not recommended __ __ None
Completed at the 4
th GCSC
Meeting
12 08A012 15-Sep-08 SEC- Generation 4.9.7.10
Modify the period required to
synchronize fast start capability of the units
Not recommended __ __ None Completed at the 4
th GCSC
Meeting
13 08A013 15-Sep-08 SEC- Generation 7.7
Flexibility shall be made in the codes for metering data storage
requirements
For withdrawal since it should be
submitted as derogation request
__ __ None
To be withdrawn as agreed during
5th
GCSC Meeting
14 08A014 15-Sep-08 SEC- Generation 7.9 Flexibility shall be
made in the codes for testing of metering
For withdrawal since it should be
submitted as derogation request
__ __ None
To be withdrawn as agreed during
5th
GCSC
ANNUAL REPORT 2011
Schedule A: Record of Amendments
GCSCSr. No.
Amendment Registration
No.
Date of Submission
Submitted by SAGC Clause(s)
No. Summary of the
Request GCSC
Recommendation(s)
Date Submitted
to ECRA
ECRA's Decision
Action Taken /
Required Status
Meeting
15 08A015 15-Sep-08 SEC- Generation 7.10
Flexibility shall be made in the codes for
main and check metering
For withdrawal since it should be
submitted as derogation request
__ __ None
To be withdrawn as agreed during
5th
GCSC Meeting
16 08A016 15-Sep-08 SEC- Generation 7.11
Flexibility shall be made in the codes for
time keeping requirements till the installation of new
digital meters
For withdrawal since it should be
submitted as derogation request
__ __ None
To be withdrawn as agreed during
5th
GCSC Meeting
17 08A017 15-Sep-08 Aramco-
Generation 2.3
This section should detail the steps and
procedures for requesting
interconnections
For postponement by the proposer
__ __ __
Postponed as agreed during
5th
GCSC Meeting
18 08A018 15-Sep-08 Aramco-
Generation 2.3.1.2
Suggested rephrasing is proposed :“The User
has to specify in the appropriate application
form the date of intended
Interconnection to the grid. The TSP may
specify in the Connection Agreement a minimum timeframe from the date of User’s application before the User can be connected
to the grid.”
For postponement by the proposer
__ __ __
Postponed as agreed during
5th
GCSC Meeting
ANNUAL REPORT 2011
Schedule A: Record of Amendments
GCSCSr. No.
Amendment Registration
No.
Date of Submission
Submitted by SAGC Clause(s)
No. Summary of the
Request GCSC
Recommendation(s)
Date Submitted
to ECRA
ECRA's Decision
Action Taken /
Required Status
19 08A019 15-Sep-08 Aramco-
Generation 2.3.1.3
Add following phrase at the end of the
second sentence: “, and other subsequent studies, if warranted.”
For postponement by the proposer
__ __ __
Postponed as agreed during
5th
GCSC Meeting
20 08A020 15-Sep-08 Aramco-
Generation 2.3.1.7 Delete entire section
For postponement by the proposer
__ __ __
Postponed as agreed during
5th
GCSC Meeting
21 08A021 15-Sep-08 Aramco-
Generation 2.3.2.3
Should specify those conditions that require more detailed studies.
For postponement by the proposer
__ __ __
Postponed as agreed during
5th
GCSC Meeting
22 09A022 29-Apr-09 GCSC Members 1.10.5
The Regulator shall provide administrative and logistic support to
the GCSC
For recommendation to ECRA as agreed
during 6th
GCSC Meeting
12-Jul-09 Not
approved None
Settled at the 7
th GCSC
Meeting
23 09A023 16-May-09 Aramco-
Distribution 5.3.6
Adding a new clause after the clause 5.3.6.2 to state that the TSP
will give priority in dispatch for
cogeneration plants
For recommendation to ECRA as agreed
during 6th
GCSC Meeting
12-Jul-09 Approved
To be added in the next
revision of the Code
Ongoing inclusion in
the first revision of the
SAGC
24 09A024 16-May-09 Aramco-
Distribution 7.7.5
Specify the confidential data and the data to be disclosed to the public
For recommendation to ECRA as agreed
during 6th
GCSC Meeting
__ __ __ Discussed at the 6
th GCSC
Meeting
25 09A025 4-Nov-09 SEC- Transmission 3.3.5 Update status of
developing Planning Criteria
For recommendation to ECRA as agreed
during 7th
GCSC Meeting
13-Dec-09 Approved
To be added in the next
revision of the Code
Ongoing inclusion in
the first revision of the
SAGC
ANNUAL REPORT 2011
Schedule A: Record of Amendments
GCSCSr. No.
Amendment Registration
No.
Date of Submission
Submitted by SAGC Clause(s)
No. Summary of the
Request GCSC
Recommendation(s)
Date Submitted
to ECRA
ECRA's Decision
Action Taken /
Required Status
26 09A026 26-Oct-09 SEC- Transmission 7.12 Four suggested
modifications to be added to the section
For recommendation to ECRA as agreed
during 7th
GCSC Meeting
__ __ __
Modified as shown in request 09A027-
09A029 as discussed at the 7
th GCSC
Meeting
27 09A027 4-Nov-09 SEC- Transmission 7.12
Modify sub-clause 7.12.2 to refer to the
TSP standard 01-TMSS-01
For recommendation to ECRA as agreed
during 7th
GCSC Meeting
13-Dec-09 Approved
To be added in the next
revision of the Code
Ongoing inclusion in
the first revision of the
SAGC
28 09A028 4-Nov-09 SEC- Transmission 7.12
Add new clauses under 7.12 to provide general description of metering
equipment seals
For recommendation to ECRA as agreed
during 7th
GCSC Meeting
13-Dec-09 Approved
To be added in the next
revision of the Code
Ongoing inclusion in
the first revision of the
SAGC
29 09A029 4-Nov-09 SEC- Transmission 7.12
Inserting a new section to specify how to deal
with damaging or tampering with
metering equipment
For recommendation to ECRA as agreed
during 7th
GCSC Meeting
13-Dec-09 Approved
To be added in the next
revision of the Code
Ongoing inclusion in
the first revision of the
SAGC
30 11A030 10-Sep-11 SEC- Transmission 5.3.1.2 changing the start of
the Schedule Day from 06:00 hrs to 00:00 hrs
For recommendation to ECRA as agreed during 13
th GCSC
Meeting
28 Dec-11 - Awaiting for ECRA approval
Submitted to ECRA
31 11A031 10-Sep-11 SEC- Transmission 4.5.5; 4.5.5.1-
4.5.5.3;and 4.7.4.1
Changing colors of alerts/ warning system to match the one for
the GCC Code
For recommendation to ECRA as agreed during 13
th GCSC
Meeting
28 Dec-11 - Awaiting for ECRA approval
Submitted to ECRA
ANNUAL REPORT 2011
GCSC
Schedule B: Record of Derogation
ANNUAL REPORT 2011
GCSC
Sr. No.
Derogation Registration
No.
Date of Submission
Submitted by
SAGC Clause(s) No.
Summary of the Request
GCSC Recommendation(s) Date
Submitted to ECRA
ECRA's Decision
Action Taken /
Required Status
1 08D001 25-Aug-08 Saudi
Aramco - Distribution
4.9.7 and 4.3.4.12
Various subsections out of Chapter 4 ( Operating
Code) hinder Saudi Aramco from operating
and maintaining its cogeneration units
including the 3rd party in the most optimal way
ECRA granted these derogations and others as annexed with the Captive
Co-generation Licence granted for Saudi Aramco.
So that, no need to recommend it to ECRA.
__ __ __ Settled at the
3rd
GCSC Meeting
2 08D002 15-Sep-08 SEC - West Generation
2.4.2 Frequency Variations
Frequency variations requirements is not
applicable to the most of generating units
The request needs to be modified by specifying the units to be derogated. The request should specify the
frequencies those could not be complied, and include the support documents
from manufacturer.
__ __ __
Proposer prepared the
detailed requests for the required units
as shown in received
derogation package
09D005-09D074
3 08D003 15-Sep-08 SEC - West Generation
2.4.3 Voltage Variations
10% Over-Voltage limits not possible for most of
the GE Units
The request is to be modified by specifying the units to be derogated, and
include the support documents from
manufacturer.
__ __ __
Proposer prepared the
detailed requests for the required units
as shown in received
derogation package
09D005-09D074
ANNUAL REPORT 2011
GCSC
Sr. No.
Derogation Registration
No.
Date of Submission
Submitted by
SAGC Clause(s) No.
Summary of the Request
GCSC Recommendation(s) Date
Submitted to ECRA
ECRA's Decision
Action Taken /
Required Status
4 08D004 15-Sep-08 SEC - West Generation
2.5.2 Protection
Equipment/ Schemes (2.5.2.7, 2.5.2.11)
Backup protection and Pole Slip protection are
not available for most of the generators
The proposer should specify units to be derogated, and prepare a plan to comply with backup protection requirement. Pole Slip
protection is not required from all units as mentioned in the Code. TSP will decide whenever it is required in the relevant Connection
Agreement
__ __ __
Proposer prepared the
detailed requests for the required units
as shown in received
derogation package
09D005-09D074
5 09D005 21-Apr-09 SEC - West Generation
2.4.3 Voltage Variations
Rabigh Power Plant- MHI Steam turbine, Stage1
Steam# 1-4 can achieve 10% over-voltage limits
for2 minutes only. Derogation is asked for
15 years
Discussed at the 8th
GCSC Meeting. GCSC to consider
applying derogation granted in the letter 020/11
__ __ __ To be discussed
in the next meeting
6 09D006 21-Apr-09 SEC - West Generation
2.5.2 Protection
Equipment/ Schemes (2.5.2.7)
Backup protection is not available at Rabigh
Power Plant- MHI Steam turbine, Stage1Steam#
1-4, and need to be installed in all the power
plants. Derogations sought for 5years.
No need for derogation, since the user's system
fulfill the SAGC requirement as discussed at the 8
th GCSC
Meeting. The request is withdrawn by the proposer.
__ __ __ Withdrawn
ANNUAL REPORT 2011
GCSC
Sr. No.
Derogation Registration
No.
Date of Submission
Submitted by
SAGC Clause(s) No.
Summary of the Request
GCSC Recommendation(s) Date
Submitted to ECRA
ECRA's Decision
Action Taken /
Required Status
7 09D007 21-Apr-09 SEC - West Generation
2.4.3 Voltage Variations
Rabigh Power Plant- MHI Steam turbine, Stage III Steam# 5-6 can achieve 10% over-voltage limits
for2 minutes only. Derogation is asked for
15 years
Discussed at the 8th
GCSC Meeting. GCSC to consider
applying derogation granted in the letter 020/11
__ __ __ To be discussed
in the next meeting
8 09D008 21-Apr-09 SEC - West Generation
2.5.2 Protection
Equipment/ Schemes (2.5.2.7)
Backup protection is not available at Rabigh
Power Plant- MHI Steam turbine, Stage III Steam#
5-6, and need to be installed in all the power
plants. Derogations sought for 5years.
No need for derogation, since the user's system
fulfill the SAGC requirement as discussed in the 8th MoM. The request is
withdrawn by the proposer.
__ __ __ Withdrawn
9 09D009 21-Apr-09 SEC - West Generation
2.4.3 Voltage Variations
Rabigh Power Plant- ABB Gas-turbine, Type-11D5
GT#1-8 can not withstand the dielectric
and thermal stresses due to 10% over-voltage for
long period. The generation can con
guarantee the operation of the units on 10% over-voltage for 30 minutes.
Derogation
Discussed at the 8th
GCSC Meeting. GCSC to consider
applying derogation granted in the letter 020/11
__ __ __ To be discussed
in the next meeting
ANNUAL REPORT 2011
GCSC
Sr. No.
Derogation Registration
No.
Date of Submission
Submitted by
SAGC Clause(s) No.
Summary of the Request
GCSC Recommendation(s) Date
Submitted to ECRA
ECRA's Decision
Action Taken /
Required Status
10 09D010 21-Apr-09 SEC - West Generation
2.5.2 Protection
Equipment/ Schemes (2.5.2.7)
Backup protection is not available at Rabigh
Power Plant- ABB Gas-turbine, Type-11D5
GT#1-8, and need to be installed in all the power
plants. Derogation is sought for 5years.
No need for derogation, since the user's system
fulfill the SAGC requirement as discussed at the 8
th GCSC
Meeting. The request is withdrawn by the proposer.
__ __ __ Withdrawn
11 09D011 21-Apr-09 SEC - West Generation
2.5.5.12 On Load Tap changer
Rabigh Power Plant- ABB Gas-turbine, Type-11D5
GT#1-8, step up transformers as installed
have off load tap changer. Derogation is required for 15 years
Committee accepted the derogation after modifying
the period required for derogation from 15 years to
the date of transformer's replacement.
The Acceptance is concurred by a majority of votes (12 out of 13 votes).
Against (G2).
Letter # 016\10 dated
23/8/2010
Approved
Proposer informed by letter #017\10
Derogation Granted
12 09D012 21-Apr-09 SEC - West Generation
2.4.3 Voltage Variations
Rabigh Power Plant- ABB Combined Cycle units, Stage II CC1-2 can not
withstand the dielectric and thermal stresses due to 10% over-voltage for long period. Derogation
is asked for 15 years from the operation of the units on 10% over-
voltage.
Discussed at the 8th
GCSC Meeting. GCSC is to consider applying
derogation granted in the letter 020/11
__ __ __ To be discussed
in the next meeting
ANNUAL REPORT 2011
GCSC
Sr. No.
Derogation Registration
No.
Date of Submission
Submitted by
SAGC Clause(s) No.
Summary of the Request
GCSC Recommendation(s) Date
Submitted to ECRA
ECRA's Decision
Action Taken /
Required Status
13 09D013 21-Apr-09 SEC - West Generation
2.5.2 Protection
Equipment/ Schemes (2.5.2.7)
Backup protection is not available at Rabigh Power Plant- ABB
Combined Cycle units, Stage II CC1-2, and need to be installed in all the
power plants. Derogation is sought for
5years.
No need for derogation, since the user's system
fulfill the SAGC requirement as discussed at the 8
th GCSC
Meeting. The request is withdrawn by the proposer.
__ __ __ Withdrawn
14 09D014 21-Apr-09 SEC - West Generation
2.5.5.12 On Load Tap changer
Rabigh Power Plant- ABB Combined Cycle units, Stage II CC1-2, step up
transformers as installed have off load tap
changer. Derogation is required for 15 years
Committee accepted the derogation after modifying
the period required for derogation from 15 years to
the date of transformer's replacement.
The Acceptance is concurred by a majority of votes (12 out of 13 votes).
Against (G2).
Letter # 016\10 dated
23/8/2010
Approved
Proposer informed by letter #017\10
Derogation Granted
15 09D015 21-Apr-09 SEC - West Generation
2.4.2 Frequency Variations
Rabigh Power Plant- GE Gas Turbines, Frame 7EA GT#9-12, is designed to operate under 57-60.6
Hz. Derogation is required for 15 years from operating under
60.6-62.5 Hz.
No need for derogation from over frequency.
Request is withdrawn by the Committee as discussed
at the 8th and 9th
GCSC Meeting since there is no protection in the unit for
over frequency
__ __ __ Withdrawn
ANNUAL REPORT 2011
GCSC
Sr. No.
Derogation Registration
No.
Date of Submission
Submitted by
SAGC Clause(s) No.
Summary of the Request
GCSC Recommendation(s) Date
Submitted to ECRA
ECRA's Decision
Action Taken /
Required Status
16 09D016 21-Apr-09 SEC - West Generation
2.4.3 Voltage Variations
Rabigh Power Plant- GE Gas Turbines, Frame 7EA
GT#9-12 can not withstand the operation under 10% over-voltage
for 30 minute. Derogation is asked for
15 years.
Discussed at the 8th
GCSC Meeting. GCSC to consider
applying derogation granted in the letter 020/11
__ __ __ To be discussed
in the next meeting
17 09D017 21-Apr-09 SEC - West Generation
2.5.2 Protection
Equipment/ Schemes (2.5.2.7)
Backup protection is not available at Rabigh
Power Plant- GE Combined Cycle-unit,
Stage-IV CC3, and need to be installed in all the
power plants. Derogation is sought for
5years.
No need for derogation, since the user's system
fulfill the SAGC requirement as discussed at the 8
th GCSC
Meeting. The request is withdrawn by the proposer.
__ __ __ Withdrawn
18 09D018 21-Apr-09 SEC - West Generation
2.4.3 Voltage Variations
Rabigh Power Plant- GE Combined Cycle-unit, Stage-IV CC3 can not
withstand the operation under 10% over-voltage
for 30 minute. Derogation is asked for
15 years.
Discussed in the 8th
GCSC Meeting. GCSC to consider
applying derogation granted in the letter 020/11
__ __ __ To be discussed
in the next meeting
19 09D019 21-Apr-09 SEC - West Generation
2.5.2 Protection
Equipment/ Schemes (2.5.2.7)
Backup protection is not available at Rabigh
Power Plant- GE Gas Turbines, Frame 7EA
GT#9-12, and need to be installed in all the power
plants. Derogation is sought for 5years.
No need for derogation, since the user's system
fulfill the SAGC requirement as discussed at the 8
th GCSC
Meeting. The request is withdrawn by the proposer.
__ __ __ Withdrawn
ANNUAL REPORT 2011
GCSC
Sr. No.
Derogation Registration
No.
Date of Submission
Submitted by
SAGC Clause(s) No.
Summary of the Request
GCSC Recommendation(s) Date
Submitted to ECRA
ECRA's Decision
Action Taken /
Required Status
20 09D020 11-Apr-09 SEC - West Generation
2.4.2 Frequency Variations
Jeddah PP3 - GE Gas Turbines, Model 7B
GT#1-11, is designed to operate under 57-60.6
Hz. Derogation is required for 15 years from operating under
60.6-62.5 Hz.
No need for derogation from over frequency.
Request is withdrawn by the Committee as discussed
at the 9th
GCSC Meeting since there is no protection
in the unit for over frequency
__ __ __ Withdrawn
21 09D021 11-Apr-09 SEC - West Generation
2.4.3 Voltage Variations
Jeddah PP3 - GE Gas Turbines, Model 7B
GT#1-11, can not withstand 10% over
voltage. Derogation is required for 15 years.
The request is to be withdrawn as
recommended at the 13th
GCSC Meeting, since all units under the request
have On-Load Tap Changer
__ __ __ Withdrawn
22 09D022 11-Apr-09 SEC - West Generation
2.5.2 Protection
Equipment/ Schemes (2.5.2.7)
Jeddah PP3 - GE Gas Turbines, Model 7B
GT#1-11, do not have backup protection which is needed to be installled in all the power plants. Derogation is required
for 5 years.
No need for derogation, since the user's system
fulfill the SAGC requirement as discussed at the 9
th GCSC
Meeting. The request is withdrawn by the proposer.
__ __ __ Withdrawn
ANNUAL REPORT 2011
GCSC
Sr. No.
Derogation Registration
No.
Date of Submission
Submitted by
SAGC Clause(s) No.
Summary of the Request
GCSC Recommendation(s) Date
Submitted to ECRA
ECRA's Decision
Action Taken /
Required Status
23 09D023 11-Apr-09 SEC - West Generation
2.4.2 Frequency Variations
Jeddah PP3 - ABB Gas Turbines, Type 11D5-
GT#12-27, is designed to operate over 57.6 Hz. Derogation is required
for 15 years from operating under 57.6 Hz.
Recommended at the 12th
GCSC Meeting to grant
derogation for Alstom (ABB) units as follow: Units are to be derogated from under
frequency limits of the range 30 minutes to be
57.6Hz instead of 57.5 Hz; the frequencies above
57.1Hz to 57.6Hz will be required for 30 seconds as
stated in the SAGC; the lower limit 57.0 Hz will be
required for 5 seconds period instead of 30
seconds.
__ __ to be
submitted to ECRA
Ongoing preparation of the documents for submission
to ECRA
24 09D024 11-Apr-09 SEC - West Generation
2.4.3 Voltage Variations
Jeddah PP3 - ABB Gas Turbines, Type 11D5 GT#12 to 27, can not withstand 10% over
voltage. Derogation is required for 15 years.
The request is to be withdrawn as
recommended at the 13th
GCSC Meeting, since all units under the request
have On-Load Tap Changer
__ __ __ Withdrawn
25 09D025 11-Apr-09 SEC - West Generation
2.5.2 Protection
Equipment/ Schemes (2.5.2.7)
Jeddah PP3 - ABB Gas Turbines, Type 11D5
GT#12 to27, do not have backup protection which is needed to be installed in all the power plants. Derogation is required
for 5 years.
No need for derogation, since the user's system
fulfill the SAGC requirement as discussed at the 9
th GCSC
Meeting. The request is withdrawn by the proposer.
__ __ __ Withdrawn
ANNUAL REPORT 2011
GCSC
Sr. No.
Derogation Registration
No.
Date of Submission
Submitted by
SAGC Clause(s) No.
Summary of the Request
GCSC Recommendation(s) Date
Submitted to ECRA
ECRA's Decision
Action Taken /
Required Status
26 09D026 11-Apr-09 SEC - West Generation
2.4.2 Frequency Variations
Jeddah PP3 - GE Gas Turbines, Frame 7EA
GT#28-35, require derogation is for 15
years from operating on 57 Hz for 30sec.
Awaiting proposer clarification since there is no need for derogation from over frequency.
__ __ __
Discussed at the 13
th GCSC
Meeting. Awaiting proposer
clarification
27 09D027 11-Apr-09 SEC - West Generation
2.4.3 Voltage Variations
Jeddah PP3 - GE Gas Turbines, Frame 7EA
GT#28-35, can not withstand 10% over
voltage. Derogation is required for 15 years.
The request is to be withdrawn as
recommended in the 13th
GCSC Meeting, since all units under the request
have On-Load Tap Changer
__ __ __ Withdrawn
28 09D028 11-Apr-09 SEC - West Generation
2.4.2 Frequency Variations
Jeddah PP2 - GE Gas Turbines, Frame 5 GT#4, is designed to operate
under 57-60.6 Hz. Derogation is required
for 15 years from operating under 60.6-
62.5 Hz.
No need for derogation from over frequency.
Request is withdrawn by the Committee as discussed
at the 9th
GCSC Meeting since there is no protection
in the unit for over frequency
__ __ __ Withdrawn
29 09D029 11-Apr-09 SEC - West Generation
2.4.3 Voltage Variations
Jeddah PP2 - GE Gas Turbines, Frame 5 GT#4, can not withstand 10%
over voltage. Derogation is required for 15 years.
The request is to be withdrawn as
recommended in the 13th meeting, since all units
under the request have On-Load Tap Changer
__ __ __ Withdrawn
ANNUAL REPORT 2011
GCSC
Sr. No.
Derogation Registration
No.
Date of Submission
Submitted by
SAGC Clause(s) No.
Summary of the Request
GCSC Recommendation(s) Date
Submitted to ECRA
ECRA's Decision
Action Taken /
Required Status
30 09D030 11-Apr-09 SEC - West Generation
2.5.2 Protection
Equipment/ Schemes (2.5.2.7)
Jeddah PP2 - GE Gas Turbines, Model 5 GT#4,
do not have backup protection which is
needed to be installed in all the power plants.
Derogation is required for 5 years.
No need for derogation, since the user's system
fulfill the SAGC requirement as discussed in the 9th MoM. The request is
withdrawn by the proposer.
__ __ __ Withdrawn
31 09D031 11-Apr-09 SEC - West Generation
2.4.2 Frequency Variations
Jeddah PP2 - ABB Gas Turbines, Type 11B
GT#7,8 &10, require derogation from
operating under 57.6 Hz. Derogation is required
for 15 years
Recommended at the 12th
GCSC Meeting to grant
derogation for Alstom (ABB) units as follows: Units are to be derogated for the lower limit 57.5 Hz for 30 minutes
to be 57.6Hz for 30 minutes; Units are to be derogated for only the
lower limit 57.0 Hz to be for 5 seconds period instead of 30 seconds, the frequencies above 57.1Hz to 57.6Hz will be for 30 seconds as stated
in the SAGC.
__ __ to be
submitted to ECRA
Ongoing preparation of the documents for submission
to ECRA
32 09D032 11-Apr-09 SEC - West Generation
2.4.3 Voltage Variations
Jeddah PP2 - ABB Gas Turbines, Type 11B
GT#7,8 &10, can not withstand 10% over
voltage. Derogation is required for 15 years.
The request is to be withdrawn as
recommended at the 13th
GCSC Meeting, since all units under the request
have On-Load Tap Changer
__ __ __ Withdrawn
ANNUAL REPORT 2011
GCSC
Sr. No.
Derogation Registration
No.
Date of Submission
Submitted by
SAGC Clause(s) No.
Summary of the Request
GCSC Recommendation(s) Date
Submitted to ECRA
ECRA's Decision
Action Taken /
Required Status
33 09D033 11-Apr-09 SEC - West Generation
2.5.2 Protection
Equipment/ Schemes (2.5.2.7)
Jeddah PP2 - ABB Gas Turbines, Type 11B
GT#7,8 &10, do not have backup protection which is needed to be installed in all the power plants. Derogation is required
for 5 years.
No need for derogation, since the user's system
fulfill the SAGC requirement as discussed at the 9
th GCSC
Meeting. The request is withdrawn by the proposer.
__ __ __ Withdrawn
34 09D034 14-Apr-09 SEC - West Generation
2.4.2 Frequency Variations
Makkah Power Plant - ABB Gas Turbines, Type 9C GT#7.8 &10, require
derogation from operating under 57.6 Hz.
Derogation is required for 15 years
Recommended at the 12th
GCSC Meeting to grant
derogation for Alstom (ABB) units as follows: Units are to be derogated for the lower limit 57.5 Hz for 30 minutes
to be 57.6Hz for 30 minutes; Units are to be derogated for only the
lower limit 57.0 Hz to be for 5 seconds period instead of 30 seconds, the frequencies above 57.1Hz to 57.6Hz will be for 30 seconds as stated
in the SAGC.
__ __ to be
submitted to ECRA
Ongoing preparation of the documents for submission
to ECRA
35 09D035 14-Apr-09 SEC - West Generation
2.4.3 Voltage Variations
Makkah Power Plant - ABB Gas Turbines, Type
9C GT#1, can not withstand 10% over
voltage. Derogation is required for 15 years.
The request is to be withdrawn as
recommended at the 13th
GCSC Meeting, since all units under the request
have On-Load Tap Changer
__ __ __ Withdrawn
ANNUAL REPORT 2011
GCSC
Sr. No.
Derogation Registration
No.
Date of Submission
Submitted by
SAGC Clause(s) No.
Summary of the Request
GCSC Recommendation(s) Date
Submitted to ECRA
ECRA's Decision
Action Taken /
Required Status
36 09D036 14-Apr-09 SEC - West Generation
2.5.2 Protection
Equipment/ Schemes (2.5.2.7)
Makkah PP - ABB Gas Turbines, Type 9C GT#1,
do not have backup protection which is
needed to be installed in all the power plants.
Derogation is required for 5 years.
No need for derogation, since the user's system
fulfill the SAGC requirement as discussed at the 9
th GCSC
Meeting. The request is withdrawn by the proposer.
__ __ __ Withdrawn
37 09D037 14-Apr-09 SEC - West Generation
2.4.2 Frequency Variations
Makkah Power Plant - ABB Gas Turbines, Type
9D GT#2 & 3, require derogation from
operating under 57.6 Hz. Derogation is required
for 15 years
Recommended at the 12th
GCSC Meeting to grant
derogation for Alstom (ABB) units as follows: Units are to be derogated for the lower limit 57.5 Hz for 30 minutes
to be 57.6Hz for 30 minutes; Units are to be derogated for only the
lower limit 57.0 Hz to be for 5 seconds period instead of 30 seconds, the frequencies above 57.1Hz to 57.6Hz will be for 30 seconds as stated
in the SAGC.
__ __ to be
submitted to ECRA
Ongoing preparation of the documents for submission
to ECRA
38 09D038 14-Apr-09 SEC - West Generation
2.4.3 Voltage Variations
Makkah Power Plant - ABB Gas Turbines, Type
9D GT#2 &3, can not withstand 10% over
voltage. Derogation is required for 15 years.
The request is to be withdrawn as
recommended at the 13th
GCSC Meeting, since all units under the request
have On-Load Tap Changer
__ __ __ Withdrawn
ANNUAL REPORT 2011
GCSC
Sr. No.
Derogation Registration
No.
Date of Submission
Submitted by
SAGC Clause(s) No.
Summary of the Request
GCSC Recommendation(s) Date
Submitted to ECRA
ECRA's Decision
Action Taken /
Required Status
39 09D039 14-Apr-09 SEC - West Generation
2.5.2 Protection
Equipment/ Schemes (2.5.2.7)
Makkah PP - ABB Gas Turbines, Type 9D GT#2-
3, do not have backup protection which is
needed to be installed in all the power plants.
Derogation is required for 5 years.
No need for derogation, since the user's system
fulfill the SAGC requirement as discussed at the 9
th GCSC
Meeting. The request is withdrawn by the proposer.
__ __ __ Withdrawn
40 09D040 14-Apr-09 SEC - West Generation
2.4.2 Frequency Variations
Makkah Power Plant - ABB Gas Turbines, Type
11D5 GT#8 to 12, require derogation from operating under 57.6 Hz.
Derogation is required for 15 years
Recommended at the 12th
GCSC Meeting to grant
derogation for Alstom (ABB) units as follows: Units are to be derogated for the lower limit 57.5 Hz for 30 minutes
to be 57.6Hz for 30 minutes; Units are to be derogated for only the
lower limit 57.0 Hz to be for 5 seconds period instead of 30 seconds, the frequencies above 57.1Hz to 57.6Hz will be for 30 seconds as stated
in the SAGC.
__ __ to be
submitted to ECRA
Ongoing preparation of the documents for submission
to ECRA
41 09D041 14-Apr-09 SEC - West Generation
2.4.3 Voltage Variations
Makkah Power Plant - ABB Gas Turbines, Type
11D5 GT#8 to 12, cannot withstand 10% over
voltage. Derogation is required for 15 years.
As per manufacturer feedback, Committee
recommended at the 13th
GCSC Meeting to grant the requested derogation since the units have off load tap
changer
__ __ to be
submitted to ECRA
Ongoing preparation of the documents for submission
to ECRA
ANNUAL REPORT 2011
GCSC
Sr. No.
Derogation Registration
No.
Date of Submission
Submitted by
SAGC Clause(s) No.
Summary of the Request
GCSC Recommendation(s) Date
Submitted to ECRA
ECRA's Decision
Action Taken /
Required Status
42 09D042 14-Apr-09 SEC - West Generation
2.5.2 Protection
Equipment/ Schemes (2.5.2.7)
Makkah PP - ABB Gas Turbines, Type 11D5
GT#8,9 &12, do not have backup protection which is needed to be installed in all the power plants. Derogation is required
for 5 years.
No need for derogation, since the user's system
fulfill the SAGC requirement as discussed at the 9
th GCSC
Meeting. The request is withdrawn by the proposer.
__ __ __ Withdrawn
43 09D043 14-Apr-09 SEC - West Generation
2.5.5.12 On Load Tap changer
Makkah PP - ABB Gas turbine, 11D5, GT#8 to
12 step up transformers as installed have off load tap changer. Derogation is required for 15 years
Committee accepted the derogation after modifying
the period required for derogation from 15 years to
the date of transformer's replacement.
The Acceptance is concurred by a majority of votes (12 out of 13 votes).
Against (G2).
Letter # 016\10 dated
23/8/2010
Approved
Proposer informed by letter #017\10
Derogation Granted
44 09D044 14-Apr-09 SEC - West Generation
2.4.2 Frequency Variations
Makkah PP - GE Gas Turbines, Frame 7B GT#4
to7, is designed to operate under 57-60.6
Hz. Derogation is required for 15 years from operating under
60.6-62.5 Hz.
No need for derogation from over frequency.
Request is withdrawn by the Committee as discussed
at the 9th
GCSC Meeting since there is no protection
in the unit for over frequency
__ __ __ Withdrawn
ANNUAL REPORT 2011
GCSC
Sr. No.
Derogation Registration
No.
Date of Submission
Submitted by
SAGC Clause(s) No.
Summary of the Request
GCSC Recommendation(s) Date
Submitted to ECRA
ECRA's Decision
Action Taken /
Required Status
45 09D045 14-Apr-09 SEC - West Generation
2.4.3 Voltage Variations
Makkah Power Plant - GE Gas Turbines, Frame
7B GT#4 to 7, can not withstand 10% over
voltage. Derogation is required for 15 years.
Committee recommended at the 13
th GCSC Meeting to
grant the requested derogation since the units have off load tap changer
__ __ to be
submitted to ECRA
Ongoing preparation of the documents for submission
to ECRA
46 09D046 14-Apr-09 SEC - West Generation
2.5.2 Protection
Equipment/ Schemes (2.5.2.7)
Makkah PP - GE Gas Turbines, Frame 7B
GT#4 to7, do not have backup protection which is needed to be installed in all the power plants. Derogation is required
for 15 years.
No need for derogation, since the user's system
fulfill the SAGC requirement as discussed at the 9
th GCSC
Meeting. The request is withdrawn by the proposer.
__ __ __ Withdrawn
47 09D047 14-Apr-09 SEC - West Generation
2.5.5.12 On Load Tap changer
Makkah PP - GE Gas turbine, Frame 7B, GT#4
to7 step up transformers as installed
have off load tap changer. Derogation is required for 15 years
Committee accepted the derogation after modifying
the period required for derogation from 15 years to
the date of transformer's replacement.
The Acceptance is concurred by a majority of votes (12 out of 13 votes).
Against (G2).
Letter # 016\10 dated
23/8/2010
Approved
Proposer informed by letter #017\10
Derogation Granted
ANNUAL REPORT 2011
GCSC
Sr. No.
Derogation Registration
No.
Date of Submission
Submitted by
SAGC Clause(s) No.
Summary of the Request
GCSC Recommendation(s) Date
Submitted to ECRA
ECRA's Decision
Action Taken /
Required Status
48 09D048 14-Apr-09 SEC - West Generation
2.4.2 Frequency Variations
Makkah PP - GE Gas Turbines, Frame 7E
GT#13 to18, is designed to operate under 57-
60.6 Hz. Derogation is required for 15 years from operating under
60.6-62.5 Hz.
No need for derogation from over frequency.
Request is withdrawn by the Committee as discussed
at the 9th
GCSC Meeting since there is no protection
in the unit for over frequency
__ __ __ Withdrawn
49 09D049 14-Apr-09 SEC - West Generation
2.4.3 Voltage Variations
Makkah Power Plant - GE Gas Turbines, Frame 7E GT#13 to 18, can not
withstand 10% over voltage. Derogation is required for 15 years.
Committee recommended in the 13th meeting to grant
the requested derogation since the units have off load
tap changer
__ __ to be
submitted to ECRA
Ongoing preparation of the documents for submission
to ECRA
50 09D050 14-Apr-09 SEC - West Generation
2.5.2 Protection
Equipment/ Schemes (2.5.2.7)
Makkah PP - GE Gas Turbines, Frame 7E
GT#13 to18, do not have backup protection which is needed to be installed in all the power plants. Derogation is required
for 5 years.
No need for derogation, since the user's system
fulfill the SAGC requirement as discussed at the 9
th GCSC
Meeting. The request is withdrawn by the proposer.
__ __ __ Withdrawn
ANNUAL REPORT 2011
GCSC
Sr. No.
Derogation Registration
No.
Date of Submission
Submitted by
SAGC Clause(s) No.
Summary of the Request
GCSC Recommendation(s) Date
Submitted to ECRA
ECRA's Decision
Action Taken /
Required Status
51 09D051 14-Apr-09 SEC - West Generation
2.5.5.12 On Load Tap changer
Makkah PP - GE Gas turbine, Frame 7E,
GT#13 to16 step up transformers as installed
have off load tap changer. Derogation is required for 15 years
Committee accepted the derogation after modifying
the period required for derogation from 15 years to
the date of transformer's replacement.
The Acceptance is concurred by a majority of votes (12 out of 13 votes).
Against (G2).
Letter # 016\10 dated
23/8/2010
Approved
Proposer informed by letter #017\10
Derogation Granted
52 09D052 14-Apr-09 SEC - West Generation
2.5.5.12 On Load Tap changer
Makkah PP - GE Gas turbine, Frame 7E,
GT#17 &18 step up transformers as installed
have off load tap changer. Derogation is required for 15 years
Committee accepted the derogation after modifying
the period required for derogation from 15 years to
the date of transformer's replacement.
The Acceptance is concurred by a majority of votes (12 out of 13 votes).
Against (G2).
Letter # 016\10 dated
23/8/2010
Approved
Proposer informed by letter #017\10
Derogation Granted
53 09D053 19-Apr-09 SEC - West Generation
2.4.3 Voltage Variations
Madinah PP1 - ABB Gas Turbines, Type 9C GT#3, can not withstand 10%
over voltage. Derogation is required for 15 years.
As per manufacturer feedback, Committee
recommended at the 13th
GCSC Meeting to grant the requested derogation since the units have off load tap
changer
__ __ to be
submitted to ECRA
Ongoing preparation of the documents for submission
to ECRA
ANNUAL REPORT 2011
GCSC
Sr. No.
Derogation Registration
No.
Date of Submission
Submitted by
SAGC Clause(s) No.
Summary of the Request
GCSC Recommendation(s) Date
Submitted to ECRA
ECRA's Decision
Action Taken /
Required Status
54 09D054 19-Apr-09 SEC - West Generation
2.5.2 Protection
Equipment/ Schemes (2.5.2.7)
Madinah PP1 - ABB Gas Turbines, Type 9C GT#3,
do not have backup protection which is
needed to be installed in all the power plants.
Derogation is required for 5 years.
No need for derogation, since the user's system
fulfill the SAGC requirement as discussed at the 9
th GCSC
Meeting. The request is withdrawn by the proposer.
__ __ __ Withdrawn
55 09D055 19-Apr-09 SEC - West Generation
2.5.5.12 On Load Tap changer
Madinah PP1 - ABB Gas turbine, Type 9C, GT#3 step up transformers as installed have off load
tap changer. Derogation is required for 15 years
Committee accepted the derogation after modifying
the period required for derogation from 15 years to
the date of transformer's replacement.
The Acceptance is concurred by a majority of votes (12 out of 13 votes).
Against (G2).
Letter # 016\10 dated
23/8/2010
Approved
Proposer informed by letter #017\10
Derogation Granted
56 09D056 19-Apr-09 SEC - West Generation
2.4.3 Voltage Variations
Madinah PP2 - ABB Gas Turbines, Type 9D
GT#1,2 &5, can not withstand 10% over
voltage. Derogation is required for 15 years.
As per manufacturer feedback, Committee
recommended at the 13th
GCSC Meeting to grant the requested derogation since the units have off load tap
changer
__ __ to be
submitted to ECRA
Ongoing preparation of the documents for submission
to ECRA
ANNUAL REPORT 2011
GCSC
Sr. No.
Derogation Registration
No.
Date of Submission
Submitted by
SAGC Clause(s) No.
Summary of the Request
GCSC Recommendation(s) Date
Submitted to ECRA
ECRA's Decision
Action Taken /
Required Status
57 09D057 19-Apr-09 SEC - West Generation
2.5.2 Protection
Equipment/ Schemes (2.5.2.7)
Madinah PP2 - ABB Gas Turbines, Type 9D
GT#1,2 &5, do not have backup protection which is needed to be installed in all the power plants. Derogation is required
for 5 years.
No need for derogation, since the user's system
fulfill the SAGC requirement as discussed at the 9
th GCSC
Meeting. The request is withdrawn by the proposer.
__ __ __ Withdrawn
58 09D058 19-Apr-09 SEC - West Generation
2.5.5.12 On Load Tap changer
Madinah PP2 - ABB Gas turbine, Type 9D, GT#1,2
&5 step up transformers as installed
have off load tap changer. Derogation is required for 15 years
Committee accepted the derogation after modifying
the period required for derogation from 15 years to
the date of transformer's replacement.
The Acceptance is concurred by a majority of votes (12 out of 13 votes).
Against (G2).
Letter # 016\10 dated
23/8/2010
Approved
Proposer informed by letter #017\10
Derogation Granted
59 09D059 19-Apr-09 SEC - West Generation
2.4.3 Voltage Variations
Madinah PP2 - ABB Gas Turbines, Type 11D5
GT#6-7, can not withstand 10% over
voltage. Derogation is required for 15 years.
The request is to be withdrawn as
recommended at the 13th
GCSC Meeting, since all units under the request
have On-Load Tap Changer
__ __ __ Withdrawn
ANNUAL REPORT 2011
GCSC
Sr. No.
Derogation Registration
No.
Date of Submission
Submitted by
SAGC Clause(s) No.
Summary of the Request
GCSC Recommendation(s) Date
Submitted to ECRA
ECRA's Decision
Action Taken /
Required Status
60 09D060 19-Apr-09 SEC - West Generation
2.5.2 Protection
Equipment/ Schemes (2.5.2.7)
Madinah PP2 - ABB Gas Turbines, Type 11D5 GT#6-7, do not have
backup protection which is needed to be installed in all the power plants. Derogation is required
for 5 years.
No need for derogation, since the user's system
fulfill the SAGC requirement as discussed at the 9
th GCSC
Meeting. The request is withdrawn by the proposer.
__ __ __ Withdrawn
61 09D061 19-Apr-09 SEC - West Generation
2.4.2 Frequency Variations
Madinah PP2 - GE Gas Turbines, Frame 7EA
GT#8-9, is designed to operate under 57-60.6
Hz. Derogation is required for 15 years from operating under
60.6-62.5 Hz.
No need for derogation from over frequency.
Request is withdrawn by the Committee as discussed
at the 9th
GCSC Meeting since there is no protection
in the unit for over frequency
__ __ __ Withdrawn
62 09D062 19-Apr-09 SEC - West Generation
2.4.3 Voltage Variations
Madinah PP2 - GE Gas Turbines, Frame 7EA
GT#8-9, can not withstand 10% over
voltage. Derogation is required for 15 years.
The request is to be withdrawn as
recommended at the 13th
GCSC Meeting, since all units under the request
have On-Load Tap Changer
__ __ __ Withdrawn
63 09D063 19-Apr-09 SEC - West Generation
2.5.2 Protection
Equipment/ Schemes (2.5.2.7)
Madinah PP2 - GE Gas Turbines, Frame 7EA GT#8-9, do not have
backup protection which is needed to be installed in all the power plants. Derogation is required
for 5 years.
No need for derogation, since the user's system
fulfill the SAGC requirement as discussed at the 13
th
GCSC Meeting. The request is withdrawn by the
proposer.
__ __ __ Withdrawn
ANNUAL REPORT 2011
GCSC
Sr. No.
Derogation Registration
No.
Date of Submission
Submitted by
SAGC Clause(s) No.
Summary of the Request
GCSC Recommendation(s) Date
Submitted to ECRA
ECRA's Decision
Action Taken /
Required Status
64 09D064 19-Apr-09 SEC - West Generation
2.4.2 Frequency Variations
Yanbu PP - GE Gas Turbines, Frame 5 GT#1
to3, is designed to operate under 57-60.6
Hz. Derogation is required for 15 years from operating under
60.6-62.5 Hz.
No need for derogation from over frequency.
Request is withdrawn by the Committee as discussed
at the 9th
GCSC Meeting since there is since there is
no protection in the unit for over frequency
__ __ __ Withdrawn
65 09D065 19-Apr-09 SEC - West Generation
2.4.3 Voltage Variations
Yanbu PP - GE Gas Turbines, Frame 5 GT#1 to 3, can not withstand
10% over voltage. Derogation is required
for 15 years.
The request is to be withdrawn as
recommended at the 13th
GCSC Meeting, since all units under the request
have On-Load Tap Changer
__ __ __ Withdrawn
66 09D066 19-Apr-09 SEC - West Generation
2.5.2 Protection
Equipment/ Schemes (2.5.2.7)
Yanbu PP - GE Gas Turbines, Frame 5 GT#1 to 3, do not have backup
protection which is needed to be installed in
all the power plants. Derogation is required
for 5 years.
No need for derogation, since the user's system
fulfill the SAGC requirement as discussed at the 9
th GCSC
Meeting. The request is withdrawn by the proposer.
__ __ __ Withdrawn
67 09D067 14-Apr-09 SEC - West Generation
2.4.2 Frequency Variations
Taif PP - ABB Gas Turbines, Type 9D1 GT#4
to6, is not recommended to
operate continuously above 60.6 Hz.
Derogation is required for 15 years from
operating under 60.6-62.5 Hz.
No need for derogation from over frequency.
Request is withdrawn by the Committee as discussed
at the 9th
GCSC Meeting since there is no protection
in the unit for over frequency
__ __ __ Withdrawn
ANNUAL REPORT 2011
GCSC
Sr. No.
Derogation Registration
No.
Date of Submission
Submitted by
SAGC Clause(s) No.
Summary of the Request
GCSC Recommendation(s) Date
Submitted to ECRA
ECRA's Decision
Action Taken /
Required Status
68 09D068 14-Apr-09 SEC - West Generation
2.4.3 Voltage Variations
Makkah PP - ABB Gas Turbines, Type 9D1
GT#4-6, can not withstand 10% over
voltage. Derogation is required for 15 years.
The request is to be withdrawn as
recommended in the 13th meeting, since all units
under the request have On-Load Tap Changer
__ __ __ Withdrawn
69 09D069 14-Apr-09 SEC - West Generation
2.5.2 Protection
Equipment/ Schemes (2.5.2.7)
Taif PP - ABB Gas Turbines, Type 9D1 GT#4 to6, do not have backup
protection which is needed to be installed in
all the power plants. Derogation is required
for 5 years.
No need for derogation, since the user's system
fulfill the SAGC requirement as discussed at the 9
th GCSC
Meeting. The request is withdrawn by the proposer.
__ __ __ Withdrawn
70 09D070 14-Apr-09 SEC - West Generation
2.4.2 Frequency Variations
Taif PP - ABB Gas Turbines, Type 9D2
GT#1-2, is not recommended to
operate continuously above 60.6 Hz.
Derogation is required for 15 years from
operating under 60.6-62.5 Hz.
No need for derogation from over frequency.
Request is withdrawn by the Committee as discussed in the 9th MoM since there
is since there is no protection in the unit for
over frequency
__ __ __ Withdrawn
71 09D071 14-Apr-09 SEC - West Generation
2.4.3 Voltage Variations
Taif PP - ABB Gas Turbines, Type 9D2
GT#1-2, can not withstand 10% over
voltage. Derogation is required for 15 years.
The request is to be withdrawn as
recommended at the 13th
GCSC Meeting, since all units under the request
have On-Load Tap Changer
__ __ __ Withdrawn
ANNUAL REPORT 2011
GCSC
Sr. No.
Derogation Registration
No.
Date of Submission
Submitted by
SAGC Clause(s) No.
Summary of the Request
GCSC Recommendation(s) Date
Submitted to ECRA
ECRA's Decision
Action Taken /
Required Status
72 09D072 14-Apr-09 SEC - West Generation
2.5.2 Protection
Equipment/ Schemes (2.5.2.7)
Taif PP - ABB Gas Turbines, Type 9D2
GT#1-2, do not have backup protection which is needed to be installed in all the power plants. Derogation is required
for 5 years.
No need for derogation, since the user's system
fulfill the SAGC requirement as discussed at the 9
th GCSC
Meeting. The request is withdrawn by the proposer.
__ __ __ Withdrawn
73 09D073 14-Apr-09 SEC - West Generation
2.4.2 Frequency Variations
Taif PP - AEG Gas Turbine designed by GE,
Frame 5 GT#3, is not recommended to
operate continuously above 60.6 Hz.
Derogation is required for 15 years from
operating under 60.6-62.5 Hz.
No need for derogation from over frequency.
Request is withdrawn by the Committee as discussed
at the 9th
GCSC Meeting since there is no protection
in the unit for over frequency
__ __ __ Withdrawn
74 09D074 14-Apr-09 SEC - West Generation
2.5.2 Protection
Equipment/ Schemes (2.5.2.7)
Taif PP - AEG Gas Turbine designed by GE,
Frame5 GT#3, do not have backup protection which is needed to be
installed in all the power plants. Derogation is required for 5 years.
No need for derogation, since the user's system
fulfill the SAGC requirement as discussed at the 9
th GCSC
Meeting. The request is withdrawn by the proposer.
__ __ __ Withdrawn
ANNUAL REPORT 2011
GCSC
Schedule C: Recommendations sent to ECRA
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
Schedule D: ECRA’s Decision on the Recommendations
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
ANNUAL REPORT 2011
GCSC
Schedule E: Minutes of GCSC’s Meetings
ANNUAL REPORT 2011
GCSC
Minutes of 11th Meeting 16\2\2011
Meeting Period
From 10:00 a.m. to 2:00 p.m.
Venue Sponsor
Madinah- Movenpick Hotel Marafiq
Members Attendance
1- Engr. Hamed Al-Saggaf Saudi Electricity Company Chairman
2- Engr. Fayez Al-Jabri Electricity & Co-generation
Regulatory Authority Regulator
3- Dr. Abdullah Al-Abbas Saudi Electricity Company Generation
4- Engr. Ahmed Al-Furaih Saline Water Conversion
Corporation
Generation
5- Dr. Mahmoud Zayan ARAMCO Generation
6- Engr. Nezar M. Al-Khanaizi Saudi Electricity Company Transmission
7- Engr. Mohammad Al-Zahrani Saudi Electricity Company Transmission
8- Engr. Salman A. Al-Zahrani MARAFIQ Transmission
9- Engr. Mohammad Al-Taher Saudi Electricity Company Distribution
10- Engr. Fouad Al-Abdulqader Saudi Electricity Company Distribution
11- Engr. Shafi Zeitoun ARAMCO Distribution
12- Engr. Khalid Al-Nafey MARAFIQ Distribution
13- Engr. Rasheed Al-Shubaili SABIC Directly-connected
Customers
Guests Attendance
1- Engr. Ramzi Kamfar Saudi Electricity Company Generation
2- Engr. Sheikh Nazemuddin Saudi Electricity Company Generation
3- Engr. Jamal Buqshan ARAMCO Generation
4- Engr. Faisal Al-Yemni ARAMCO Distribution
5- Engr. Khalid Al-Omrani SABIC Directly-connected
Customers
Secretariat
1- Engr. Yousef Al-Zahrani Saudi Electricity Company Secretariat
2- Mr. Sultan Al-Amri Electricity & Co-generation
Regulatory Authority Secretariat
ANNUAL REPORT 2011
GCSC
SN Clause Responsibilities
1- Review of previous MoM, and action plan
Committee concurred the last action plan Committee noted that the Secretariat is to update GCSC page as
per the SAGC page. Dr. Zayan noted to add links in GCSC webpage to Amendment and
Derogation Record for the original request and the decision taken.
Secretariat
Secretariat
2- Presentation of the 3rd Annual Report, and get it agreed.
Al-Saggaf introduced the annual report to the committee.
Dr. Al-Abbas requested the committee to publish printed copy of
the report to different stakeholder.
Al-Saggaf informed that the Company usually published the report
electronically through the web, and send a printed copy to ECRA.
Committee requested ECRA to published at least 50 copies of the
report.
Committee agreed to modify Chart 5 of the report by including the
attendance of Alternates.
Fayez suggested adding a sentence at the end of clause b and c at
page 12, to brief the results of the studies.
Khalid pointed that Aramco Derogations attached in its license was
not included in the record
Al-Saggaf stated that the record include only the requests
submitted to the committee.
Shafi mentioned that Captive cogeneration can be added to the
code so, all companies having similar technical conditions will be
dealt with as captive-Cogen. Moreover, Saudi Aramco generation is
used for industrial purposes and not as the case of Utility
companies.
Fayez clarified that any company having similar technical
conditions will be granted similar derogations.
Al-Saggaf requested the Members to send and finalize their
comment on the report within two weeks.
3- Discuss the progress for the sub-committee of reviewing SEC
derogation requests
Dr. Al-Abbas presented a summary of the existing units as per
different manufacturers. He informed the committee of the
correspondences to manufacturers and their responses regarding
underfrequency and overvoltage cases as mentioned in the sub-
committee minute of meeting at 12\1\2011.
Ahmad pointed that according to clauses 4.4.4.4 (iv), and 4.4.3.2
(v) the generator are allowed to not comply with specified limits
for voltage and frequency in certain conditions to protect its
ANNUAL REPORT 2011
GCSC
SN Clause Responsibilities
plants. Thus, no need to request derogation in those conditions.
Al-Saggaf clarified that clause 4.4.4.4 (iv), and 4.4.3.2 (v) is made
for unexpected operational conditions and not applicable to these
cases which known in advance that can be complied with the
SAGC.
Ahmad and Dr. Al-Abbas added that the manufacturer response is
based on maximum continuous rating (MCR).
Al-Saggaf clarified that MCR is required for 5% as specified in
clause 2.5.5.6 of SAGC, and +10% voltage limits are for the system
not on generation terminals.
Dr. Zayan pointed out that clause 2.5.5.14 page26 of SAGC stated
that generator to comply with voltage limit referred in clause 2.4.3
Ahmad added that the limit specified in clause 2.5.5.14 is required
for transient condition not for normal condition.
The sub-committee was directed to clarify from manufacturers
about +10% voltage capabilities with compensation of output
power.
Dr. Al-Abbas added that the manufacturers have shown their
responses very clearly as well as the corresponding references so
there is no need to contact the manufacturers again and such issue
should be resolved by either the sub-committee or the committee.
Committee insisted that the sub-committee should finalize voltage
limit study.
Sub-committee
Sub-committee
4- Voting on a set of derogations submitted by SEC Generation-
Western Operating Area- regarding voltage variation of generating
unit:
09D021,09D024,09D027,09D029,09D032,09D035,09D038,
09D041,09D045,09D049,09D053,09D056,09D059,09D062,
09D065, 09D068, 09D071.
The committee decided to defer voting until the sub-committee
complete voltage limit study.
5- Voting on a set of derogations submitted by SEC Generation -
Western Operating Area- regarding frequency variation of
generating unit:
09D023,09D026,09D031,09D034, 09D037,09D040.
It is postponed to the next meeting, due to shortage of time.
6- Discussion of a suitable mechanism to sort all approved
recommendations to be included in the new publication of the
Code.
It is postponed to the next meeting, due to shortage of time.
ANNUAL REPORT 2011
GCSC
SN Clause Responsibilities
7- Proposing a mechanism to insure a proper implementation of the
Code.
It is postponed to the next meeting, due to shortage of time.
8- Communication Channel over the internet.
It is postponed to the next meeting, due to shortage of time.
9- Determining the date and venue of the next meeting
The next meeting will be conducted on Tuesday 24 May 2011, the
venue will be in Khobar and it will be hosted by SWCC.
Ahmad, and
Secretariat
10- Any other business
Nil.
11- Acknowledgement of Engr. Shafi Zeitoun, the previous GCSC
member
The committee appreciated and acknowledged Engr. Shafi Zeitoun
for his participation and efforts during his membership in the
GCSC.
Acknowledgement of Marafiq
The committee thanked and appreciated Marafiq for the generous
hosting for the meeting, and the warm welcome and hospitality.
Hamed Abdallah Al- Saggaf
Grid Code Supervisory
Committee, Chairman
cc: Electricity & Co-generation Regulatory Authority; and
All Members and participants
ANNUAL REPORT 2011
GCSC
Minutes of 12th Meeting 24\5\2011
Meeting Period
From 10:00 a.m. to 2:00 p.m.
Venue Sponsor
Al-Khobar, Coral International Hotel
Saline Water Conversion
Corporation (SWCC)
Members Attendance
1- Engr. Hamed Al-Saggaf Saudi Electricity Company Chairman
2- Engr. Fayez Al-Jabri Electricity & Co-generation Regulatory Authority
Regulator
3- Dr. Abdullah Al-Abbas Saudi Electricity Company Generation
4- Engr. Ahmed Al-Furaih Saline Water Conversion Corporation
Generation
5- Dr. Mahmoud Zayan ARAMCO Generation
6- Engr. Nezar M. Al-Khonaizi Saudi Electricity Company Transmission
7- Engr. Mohammad Al-Zahrani Saudi Electricity Company Transmission
8- Engr. Salman A. Al-Zahrani MARAFIQ Transmission
9- Engr. Fouad Al-Abdulqader Saudi Electricity Company Distribution
10- Engr. Khalid Al-Nafey MARAFIQ Distribution
Absentee(s) with Alternate(s)
1- Engr. Mohammad Al-Taher Saudi Electricity Company Distribution
2- Engr. Saleh Al-Amri ARAMCO Distribution
3- Engr. Rasheed Al-Shubaili SABIC Directly-connected
Customers
Alternates Attendance
1- Engr. Fouad Al-Abdulqader Saudi Electricity Company Distribution
2- Engr. Khaled Al-Ghadban ARAMCO Distribution
3- Engr. Khalid Al-Omrani SABIC Directly-connected Customers
Guests Attendance
1- Engr. Ramzi Kamfar Saudi Electricity Company Generation
2- Engr. Sheikh Nazemuddin Saudi Electricity Company Generation
Secretariat
1- Engr. Yousef Al-Zahrani Saudi Electricity Company Secretariat
2- Mr. Sultan Al-Amri Electricity & Co-generation
Regulatory Authority Secretariat
ANNUAL REPORT 2011
GCSC
SN Clause Responsibilities
1- Review of previous MoM, and action plan
Committee reviewed the previous MoM. Committee approved the agenda items to be discussed. The action plan was discussed and updated. Dr. Al-Abbas asked about the necessity of appointing Alternates. Chairman clarified that, as stated in the GCSC Constitution, it is a
privilege for each member to appoint his Alternate as he decides. Al-Jabri commented that any member replacement shall be
officially notified to ECRA. Dr. Zayan noted to add FAQ (frequently asked questions) in the
GCSC site to include all inquiries raised by other parties with their answers.
Secretariat
2- Discuss the progress for the sub-committee of reviewing SEC
derogation requests
Dr. Al-Abbas explained the summary of the recommendations on
the study.
Dr. Zayan presented the outcome and the results of the sub-
committee's recommendations.
Sub-committee proposed to accept the small difference (0.1 Hz) in
frequency limits of the ALSTOM unts, given that the ALSTOM units
fulfill the requirements of section 2.4.2.2 of the SAGC with a slight
variation (57.6Hz instead of 57.5Hz) in the lower limit of the “30
minute” frequency operating range. The subcommittee
determined that this 0.1Hz difference is acceptable and hence,
ALSTOM units should be considered as in compliance with the
SAGC's frequency variation requirements.
Chairman clarified that any deviation from the limits specified in
the SAGC is considered as violation and noncompliance with its
requirements.
Sub-committee determined that sections 2.5.5.2 and 2.5.5.8 of the
SAGC clearly stipulate that a proportionate decrease in active
power of the generating units is allowed as a consequence of
deviation of the frequency to operate within the underfrequency
range of 57.0 to 59.5Hz. Since this frequency range is covered
under the exceptional circumstances tabulated in section 2.4.2.2 of
the SAGC, and the equipment manufacturers (including ALSTOM)
are in compliance, then the subcommittee does not see a need for
SEC Western region to seek derogation from section 2.4.2 of the
SAGC.
Al-Furaih added that the SAGC is more flexible than manufacturers'
conditions since it allow compensation from 59.5Hz while the
manufacturers permitted that from 58Hz.
ANNUAL REPORT 2011
GCSC
SN Clause Responsibilities
Ramzi noted that all units can withstand 57Hz for about 5 seconds
and not for 30 seconds. Hence, units need to be derogated.
Dr. Zayan noted that the 30 seconds limit is for a span of
frequencies starting at 57.4Hz continuing down to 57Hz. That is,
the 30-second timer starts once the frequency reaches 57.4Hz (as it
continues dropping toward 57Hz), and it does not start at 57Hz.
Meaning, the 30-second period is for 57.4Hz, 57.3Hz, 57.2Hz,
57.1Hz, 57.0Hz, and all fractions in between. For a spiraling system
if it stays 5 seconds (out of these 30 seconds) at 57Hz then you
might as well trip. Of course, if frequency drops below 57.0Hz for
any duration, then the unit is allowed to trip. If SEC’s 5-second
timer only starts counting once the frequency drops to 57Hz, it
means that these units had plenty of time prior to reaching 57Hz.
Furthermore, if the SEC units do not have any other frequency
timer/relay settings, then they have infinite time prior to reaching
57Hz, but that has to do with individual User’s implementation,
while the Code speaks to design and manufacturer’s specifications.
3- Voting on a set of derogations submitted by SEC Generation -
Western Operating Area- regarding frequency variation of
generating unit: 09D023,09D026,09D031,09D034, 09D037,09D040.
The committee recommended to grant derogation for Alstom
(ABB) units as follow: Units are to be derogated for the lower limit
57.5 Hz for 30 minutes to be 57.6Hz for 30 minutes (11 votes out of
13)
Al-Furaih and Al-Zahrani disagreed, they noted that the units have
no setting on 57.5Hz or 57.6Hz.
The committee also recommended to grant derogation for Alstom
(ABB) units as follow: Units are to be derogated for only the lower
limit 57.0 Hz to be for 5 seconds period instead of 30 seconds, the
frequencies above 57.1Hz to 57.6Hz will be for 30 seconds as
stated in the SAGC. (12 votes out of 13)
Al-Furaih disagreed. He stated that "The sub-committee in its
report have reached the conclusion that SEC Western Region Unit
are complying “based on ALSTOM (ABB) Document # HTCZ656910
Rev. A” to SAGC requirements of Section 2.4.2.2 upto almost a
frequency of 57.5Hz.with slight and insignificant difference This is
also corresponding to IEC 60034-3. Now neither SAGC nor any
other relevant reference requires that generators should remain
connected and synchronized to TSP for 30 second duration at any
specific frequency level. What section 2.4.2.2 calls for is that the
ANNUAL REPORT 2011
GCSC
SN Clause Responsibilities
TSP frequency could reach 57 Hz under exceptional circumstances,
which according to SEC Western Unit could be tolerated for 5
second based on existing setting. This even without manipulating
with active power output of the generators which SAGC permits
(Section 2.5.5.2.) under such conditions." For all above reasons; he
saw no justifications whatsoever to entertain the request of SEC
Western Unit for seeking derogation from Section 2.4.2.2.
4- Voting on a set of derogations submitted by SEC Generation-
Western Operating Area- regarding voltage variation of generating
unit:
09D021,09D024,09D027,09D029,09D032,09D035,09D038,
09D041,09D045,09D049,09D053,09D056,09D059,09D062,
09D065, 09D068, 09D071.
All units are compliant with 5%, however, they are not compliant
with +10% for 30 minutes.
Al-Furaih noted that clause 2.5.5.14 is required for faults and
transient condition and not for steady state condition.
Chairman clarified that clause 2.5.5.14 of SAGC is for continuous
uninterrupted operation for the voltage variation specified in
(2.4.3), while the second part of the clause elaborated the fault
conditions.
Dr. Zayan noted that clause 2.5.5.14 is to be modified to remove
misunderstanding.
Committee asked Al-Furaih and Dr. Zayan to prepare the required
amendments to the clause 2.5.5.14.
Ramzi noted that the units are able to withstand up to almost 10
seconds on +10% before these units were disconnected.
Subcommittee pointed that the impact on units from changing
Voltage and frequency is a dynamic effect not relating to the time
only.
Committee noted that units with On-Load Tap Changer (OLTC ) can
comply with voltage limits, while those with off-load tap changer
may not.
Al-Zahrani noted that OLTC has no effect on unit's capability to
withstand +10%, since it depends on thermal effect.
Committee proposed to grant derogation for +10% for 10 minutes
instead of 30 minutes, and for units with off-load tap changer only.
Voting was postponed to the next meeting since the issue need
further discussion.
Committee asked Ramzi to list all the requests with off-load tap
Al-Furaih and
Dr. Zayan
Ramzi
ANNUAL REPORT 2011
GCSC
SN Clause Responsibilities
changer to be studied further.
5- Discussion of a suitable mechanism to sort all approved
recommendations to be included in the new publication of the
Code.
Al-Jabri clarified that after 3 years of GCSC functioning, it is
necessary to make a mechanism to include all approved
recommendations for amendments in the Code, and to establish a
subcommittee to review the Code. The period of issuing the new
version of the Code should be decided to be each 3 years.
Al-Nafey recommended that 3-5 years is suitable for issuing the
new version. It is recommended also to make new workshops for
the SAGC.
Chairman noted that it may be preferred to form a subcommittee
for reviewing the SAGC based on the specialized groups:
generation, transmission, and distribution.
Chairman noted also that the proposal of making new SAGC
workshops will be planned to enforce the proper implementation
of the Code.
Committee decided to re-issue new revisions of the Code every 5
years, hence the next version is expected to be issued in July 2012.
Dr. Zayan highlighted that SAGC contained several typographical
errors and technical discrepancies in the few sections he visited
while working on the frequency and voltage derogations, and
noted if we found multiple errors in a small part of the code, then
there are probably large number of errors in the rest of the Code.
He pointed out the following:
Section 2.5.5.14: Committee already agreed that this section
needs rework to separate between generators running in
continuous operation and under fault conditions.
Section 2.5.5.14: Fix the voltage levels and durations under
transient fault conditions, and clarify the insertion of 90%
voltage.
Section 2.4.3: Fix the language addressing the +10% over
voltage limit which states: “maximum over voltage limits
stated below should not be exceeded for more than thirty (30)
minutes”. The way it is written could imply that voltage can go
above 110% (no telling by how much) as long as it is not more
than 30-minutes!
Section 2.5.5.5: The section language needs revising, as the
phrase starting with “also….” is not clear:
ANNUAL REPORT 2011
GCSC
SN Clause Responsibilities
“2.5.5.5 The Generating Unit shall be capable of absorbing
Power (under Excitation operation) defined by the capability
Generating Unit also at maximum voltages (380, 230, of the
Grid) assuming that Stability is maintained.”
Hence, he recommended hiring a consultant to review the Code,
and form a subcommittee to work with the consultant to make the
required changes. He offered to be part of this team.
Chairman clarified that the Code was reviewed by two consultants
from ECRA, and also it was reviewed by many grid's stakeholders
including ARAMCO, WEC, and IPPs. All appreciated the work done
and the development team responded to all comments officially.
The next step is to open the floor for any person to raise his
amendment requests to the committee.
6- Proposing a mechanism to insure a proper implementation of the
Code.
Al-Jabri asked to build a mechanism to insure a full implementation
of the Code. He asked all Members to bring case studies from their
representative companies regarding voltage drops, frequency
variations, and other cases related to the Code requirements to be
discussed in the GCSC meetings. The GCSC should discuss these
issues to recommend the proper procedures to enforce the Code's
implementation.
Al-Jabri noted that many entities did not submit any derogation.
Does it mean that they are fully compliant with the Code?
Al-Furaih stated that SWCC prepared many derogation requests
regarding requirements from generating units, but it is dependent
on the interpretation of the Code's clauses. He emphasized that
each Member is responsible to follow-up compliance with the Code
of its representative company.
Chairman noted that SEC is preparing monitoring guidelines of the
SAGC, and it will be shared with the committee when it is
completed.
Al-Nafey said that Marafiq had prepared a list of all provisions of
the Code, including whether they are in compliant or not, and also
includes the necessary or required actions.
Al-Jabri requested that the representatives from the Transmission
operation bring to the next meeting examples of incidents of
voltage or frequency variations and the status of the connected
generators whether in compliance or not. He also requested that
this becomes a fixed agenda item in the next regular meetings of
M. Al-Zahrani,
and Salman
ANNUAL REPORT 2011
GCSC
SN Clause Responsibilities
the GCSC committee.
Chairman noted that the national control center will have
responsibilities in this regard and there will be a technical audit in
the new setup of the Company to report the technical
performance.
7- Communication Channel over the internet.
Salman introduced a presentation on how to build interactive
communication channel for the GCSC to facilitate sharing of
information through internet and to seek the insight of GCSC
members during the implementation of the Code.
The committee welcomed the idea, and recommended to build a
site in Facebook or Twitter channel.
Chairman proposed to add also a photo gallery for the meetings.
Salman, and
Secretariat
8- Determining the date and venue of the next meeting
The next meeting will be conducted on Wednesday 21 September
2011, in Riyadh and it will be hosted by SEC.
Al-Saggaf, and
Secretariat
Acknowledgement of SWCC
The committee thanked and appreciated SWCC for the generous hosting
of the meeting, and the warm welcome and hospitality.
Hamed Abdallah Al- Saggaf
Grid Code Supervisory
Committee, Chairman
cc: Electricity & Co-generation Regulatory Authority; and
All Members and participants
ANNUAL REPORT 2011
GCSC
Minutes of 13th Meeting 21\9\2011
Meeting Period
From 10:00 a.m. to 2:00 p.m.
Venue Sponsor
Riyadh, Madareem Crown Hotel Saudi Electricity Company (SEC)
Members Attendance
1- Engr. Hamed Al-Saggaf Saudi Electricity Company Chairman
2- Dr. Abdullah Al-Abbas Saudi Electricity Company Generation
3- Dr. Mahmoud Zayan Saudi Aramco Generation
4- Engr. Nezar M. Al-Khonaizi Saudi Electricity Company Transmission
5- Engr. Salman A. Al-Zahrani MARAFIQ Transmission
6- Engr. Khalid Al-Nafey MARAFIQ Distribution
Absentee(s) with Alternate(s)
1- Engr. Fayez Al-Jabri Electricity & Co-generation Regulatory Authority
Regulator
2- Engr. Mohammad Al-Zahrani Saudi Electricity Company Transmission
3- Engr. Mohammad Al-Taher Saudi Electricity Company Distribution
4- Engr. Fouad Al-Abdulqader Saudi Electricity Company Distribution
5- Engr. Saleh Al-Amri Saudi Aramco Distribution
6- Engr. Rasheed Al-Shubaili SABIC Directly-connected Customers
Absentee(s) without Alternate(s)
1- Engr. Ahmed Al-Furaih Saline Water Conversion
Corporation
Generation
Alternates Attendance
1- Engr. Fahad A. Al-Ajlan Electricity & Co-generation
Regulatory Authority Regulator
2- Engr. Nezar M. Al-Khonaizi Saudi Electricity Company Transmission
3- Engr. Mohammad Mazhar Saudi Electricity Company Distribution
4- Engr. Saleh A. Al-Obysi Saudi Electricity Company Distribution
5- Engr. Khaled Al-Ghadhban Saudi Aramco Distribution
6- Engr. Khalid Al-Omrani SABIC Directly-connected
Customers
Guests Attendance
1- Engr. Ramzi Kamfar Saudi Electricity Company Generation
ANNUAL REPORT 2011
GCSC
SN Clause Responsibilities
1- Review of previous MoM
Committee reviewed the previous MoM. Committee approved the agenda items to be discussed.
2- Follow up on action plan items
The action plan was discussed and the opened items are updated.
GCSC recommended that all new generation projects should
comply with the Code.
For Item 29 of the action plan, Secretariat clarified that any
derogation request should include the requirements under clause
1.11.4 (i) up to (vi) of the Code. Ramzi notified that it is not possible
to have a plan to mitigate the expected risks and restoring
compliance in this case.
For Item 28, Dr. Zayan proposed an amendment request for clause
2.5.5.14 of the Code, and it will be discussed when Al-Furaih
comes.
For item 26, it is discussed under clause 6 below.
For item 25, Salman mentioned that he is collecting the
information which is applicable to be posted in the proposed site.
3- Voting on a set of derogations submitted by SEC Generation-
Western Operating Area- regarding voltage variation of generating
unit:
09D021,09D024,09D027,09D029,09D032,09D035,09D038,
09D041,09D045,09D049,09D053,09D056,09D059,09D062,
09D065, 09D068, 09D071.
Ramzi pointed that requests 09D021,09D024,09D027,09D029,
09D032,09D035,09D038,09D059,09D062,09D065,09D068,09D071
are withdrawn as recommended in the last meeting, since all units
under these request have On-Load Tap Changer (OLTC).
Committee Voted on the remaining 5 requests 09D041,09D045,
09D049,09D053,09D056 which have off load tap changer.
Committee recommended to grant derogation for Alstom (ABB)
units (09D041, 09D053,09D056)as follow: Units are to be
derogated for 15 years for operating on +10% for 10 minutes only
instead of 30 minutes (12 votes out of 12), G2 absent.
2- Engr. Sheikh Nazemuddin Saudi Electricity Company Generation
3- Engr. Mohammad Sajid Saudi Electricity Company Transmission
Secretariat
1- Engr. Yousef Al-Zahrani Saudi Electricity Company Secretariat
ANNUAL REPORT 2011
GCSC
SN Clause Responsibilities
Committee recommended to grant derogation for other units
(09D045, 09D049) as follow: Units are to be derogated for 15 years
from operating on +10% limit. (8 votes out of 12) against R1, T1,
T2,T3. G2 absent.
4- Voting on a set of derogations submitted by SEC Generation-
Western Operating Area- regarding frequency variation of
generating unit: 09D026.
Committee asked Ramzi to provide technical reason for seeking
derogation on over frequency.
Chairman asked about recommendation of subcommittee.
Ramzi
Subcommittee
5- Discussion of 2 new Amendment Requests regarding harmonizing
between GCC Interconnection Transmission Code and the Saudi
Arabian Grid Code.
Sajid gave a presentation on the requests 11A031, 11A031 to
remove inconsistency between the SAGC and ITC.
Committee recommended to accept the amendment request
11A030 (12 votes out of 12), G2 absent.
Committee recommended to accept the amendment request
11A031 (12 votes out of 12), G2 absent.
Some Members suggested notifying such approved changes to
Users and giving them grace time for compliance.
Ghadhban suggested to define how much time should be given for
the users to comply with the new amendments.
Chairman highlighted that any amendment or derogation will
follow same process as in clause 1.11.14 of the SAGC.
6- Presentation on compliance of users with the Grid Code
requirements.
Upon request from Al-Jabri, GCSC decided to add a fix agenda item
to discuss examples for user compliance with the Code.
Salman argued that the scope of user’s compliance is not clear.
Chairman clarifies that compliance is not related to the KPI of the
grid, but is mainly related to voltage and frequency limits and other
standards specified in Chapter 2 and other Chapters of the Code.
Dr. Zayan suggested that compliance is to be monitored for the
users and the TSP as well.
Committee stated that the GCSC is required to guide
implementation of the Code, but not asked to conduct monitoring
ANNUAL REPORT 2011
GCSC
SN Clause Responsibilities
compliance itself since it is beyond its function and ability; however
the TSP should monitor the compliance with the Code as stated in
the Implementing Regulations of the Electricity Law- Condition
11.1.11.
Chairman suggested to form a sub-committee from M. Al-Zahrani,
Salman, and headed by Al-Jabri to follow up the issue and report its
results to GCSC.
Al-Jabri,
M. Al-Zahrani,
and Salman
7- Discuss the merits of having the OLTC on the GSU Transformer.
Ghadhban informed that he is conducting a study that evaluate the
feasibility of establishing the new generation units’ transformers
with off load tap changer to avoid OLTC malfunction problem. Also
during the meeting, Ghadhban highlighted that the main purpose
of raising this topic is to discuss and share experience with other
companies operating their GSU Transformers with and without
OLTC. Ghadhban highlighted that more research is required on this
topic before we can go forward and decide to amend the grid code
or leave it for each user to ask for derogation for their future
plants.
Nezar informed to committee that the problem happened in
Qurayyah PP was not resulted from OLTC. OLTC may cause up to
only 9% of generating unit (step up transformers) problem. OLTC is
considered a good tool to regulate the voltage in addition to other
components such as SVCs, capacitors, etc.
Dr. Zayan informed that sometimes AVR and OLTC seem
overlapping operation of each other.
Dr. Abbas informed that a group from Generation Technical Service
Department in Dammam wanted to share their experience
regarding OLTC in the next meeting.
The topic will be further discussed in the next meeting.
Al-Abbas
Ghadhban
8- Determining the date and venue of the next meeting
The next meeting will be conducted on Monday 9 January 2012, in
Riyadh and it will be hosted by ECRA.
Fayez, and
Secretariat
9- Any other business
Dr. Zayan argued that the Standards and procedures mentioned in
SAGC Chapter 2 are not available.
Chairman notified the argument and informed that SEC -
Transmission has been working on collecting and unifying those
documents mentioned in the Code from SEC’s departments.
Committee suggested to upgrade the GCSC website by mentioning
the new changes and decision of the GCSC.
Secretariat
ANNUAL REPORT 2011
GCSC
SN Clause Responsibilities
Acknowledgement of SWCC
The committee thanked and appreciated SEC for the generous hosting of
the meeting, and the warm welcome and hospitality.
Hamed Abdallah Al- Saggaf
Grid Code Supervisory
Committee, Chairman
cc: Electricity & Co-generation Regulatory Authority; and
All Members and participants
ANNUAL REPORT 2011
GCSC
Please contact for your comments and suggestions at:
Grid Code Supervisory Committee
Al-Riyadh, Kingdom of Saudi Arabia
http://www.se.com.sa/SEC/English/Menu/PowerTransmissionNetwok/