    Group Members:Kamran AzharRozina IqbalMirabel DSouzaSamrah-tul-MehdiZakia Siddiqui

  • 8/2/2019 Group I - Day Care

    2/48

    PROJECT SCOPE MANAGEMENT Collect requirement

    Define Scope

    Create WBS

    Verify Scope

    Control Scope

  • 8/2/2019 Group I - Day Care

    3/48

    1. COLLECET REQUIREMENT

    The process of defining the stake holders needstomeet project requirements.

    1. The increase in the number of working mothers

    2. Nuclear family type

    3. Security threats related to child minder

  • 8/2/2019 Group I - Day Care

    4/48

    COLLECET

    REQUIREMENT..(continue)Purpose of a CHILD CARAE

    Providing social needs of the working women

    Providing the educational needs

  • 8/2/2019 Group I - Day Care

    5/48

    2.DEFINE SCOPEDefining the detailed description of the project and product

    Our Program

    We offer stimulating, high quality care and education tochildren 0 months to 7 years. Qualified staff membersencourage children to develop problem-solving skills, creativity,a sense of responsibility, independence and a positive sense ofself worth. Our centre offer stimulating play activities that are

    organized into interest areas such as blocks, art activities, sand-and-water area, and outdoor play. Consistent daily routines helpchildren feel safe and secure and include opportunities for themto plan their own activities.

  • 8/2/2019 Group I - Day Care

    6/48

    DEFINE SCOPE.. Continue .(CORE VALUES)

    we understand that each child is unique andimportant

    we encourage children to become independent,responsible, and confident

    we support children to become active learners, withstaff as their guides

    we provide activities that promote and enhancephysical, social, emotional, language and intellectualdevelopment.

  • 8/2/2019 Group I - Day Care

    7/48

    3.WORK BREAK DOWN

    STRUCTUREWBS mainly consist of 4 M

    MANPOWER MACHINARY

    MATERIAL

    METHODS

  • 8/2/2019 Group I - Day Care

    8/48

    WBS..continue

    1 MANPOWER

    The staff would be familiar with the emotional,

    physical, intellectual and language development ofchildren between 0 to 7 years of age.

    2. MACHINARY

    There will be close circuit cameras in the rooms as well asin the out door to keep an eye on the children

  • 8/2/2019 Group I - Day Care

    9/48

    WBS..continue

    3 .MATERIAL

    Adequate space is provided for children to storetheir personal belongings.

    Toilets, soap and water (for drinking and washing)are accessible to the children.

    All rooms are well-lighted and well-ventilated.4. METHODS

    Health and Safety

    Nutrition and Food Service

    Staff Family Interaction

  • 8/2/2019 Group I - Day Care

    10/48

    VERIFY AND CONTROL SCOPEVERIFICATION CONTROL

    After 3 months the admissionrate will be analyzed.

    There will be periodicevaluations of every childslearning skills, creativity andconfidence level

    Promotion activities will beincreased accordingly.

    If there is a lack, extraattention will be given torespective children.

  • 8/2/2019 Group I - Day Care

    11/48

    PROJECT TIME AND COST

    MANAGEMENT

  • 8/2/2019 Group I - Day Care

    12/48

    Location Decision

  • 8/2/2019 Group I - Day Care

    13/48

    Data Results

    Profit Low Demand High Demand EMV Minimum MaximumProbability 0.8 0.2

    Small Facility 13790500 1500000 11332400 1500000 13790500

    Large Facility 12008500 1600000 9926800 1600000 12008500

    Maximum 11332400 1600000 13790500

    Expected Value of Perfect Information

    Column best 13790500 1600000 11352400

  • 8/2/2019 Group I - Day Care

    14/48

    Pert Chart (Project Management)

    Startnode End node

    Optimistictime

    Most Likelytime

    Pessimistictime

    Activitytime

    StandardDeviation Variance

    Taking Building on the rent 1 2 10 15 25 15.83 2.5 6.25

    Licensing 2 3 8 11 15 11.17 1.17 1.36

    Hiring Project team 3 4 10 15 20 15 1.67 2.78

    Ads for staff and personnel 4 5 7 10 14 10.17 1.17 1.36

    Recruiting 5 6 10 14 22 14.67 2 4

    Ordering Furniture and

    Supplies 6 7 6 10 14 10 1.33 1.78

    Selection 7 8 7 9 15 9.67 1.33 1.78

    Orientation and Training 8 9 7 9 11 9 0.67 0.44

    Painting and decorating the

    Rooms 9 10 15 20 30 20.83 2.5 6.25

    Ads For Admission 10 11 14 20 25 19.83 1.83 3.36

    Admission open 11 12 45 55 65 55 3.33 11.11

    Session start 12 13 7 10 15 10.33 1.33 1.78

    Project results

    Total of critical Activities 42.25

    Square root of total 6.5

  • 8/2/2019 Group I - Day Care

    15/48

    Pert Chart (Project Management)Start

    node End node

    Activity

    time

    Early

    Start

    Early

    Finish Late Start

    Late

    Finish Slack

    Standard

    DeviationProject 201.5 6.5

    Taking Building on

    the rent 1 2 15.83 0 15.83 0 15.83 0 2.5

    Licensing 2 3 11.17 15.83 27 15.83 27 0 1.17

    Hiring Project team 3 4 15 27 42 27 42 0 1.67

    Ads for staff andpersonnel 4 5 10.17 42 52.17 42 52.17 0 1.17

    Recruiting 5 6 14.67 52.17 66.83 52.17 66.83 0 2

    Ordering Furniture

    and Supplies 6 7 10 66.83 76.83 66.83 76.83 0 1.33

    Selection 7 8 9.67 76.83 86.5 76.83 86.5 0 1.33

    Orientation and

    Training 8 9 9 86.5 95.5 86.5 95.5 0 0.67

    Painting and

    decorating the

    Rooms 9 10 20.83 95.5 116.33 95.5 116.33 0 2.5

    Ads For Admission 10 11 19.83 116.33 136.17 116.33 136.17 0 1.83

    Admission open 11 12 55 136.17 191.17 136.17 191.17 0 3.33

    Session start 12 13 10.33 191.17 201.5 191.17 201.5 0 1.33

    Pert Chart (Project Management)

  • 8/2/2019 Group I - Day Care

    16/48

    Pert Chart (Project Management)

  • 8/2/2019 Group I - Day Care

    17/48

    Pert Chart (Project Management)

    Center Fee Worksheet

  • 8/2/2019 Group I - Day Care

    18/48

    Center Fee Worksheet(entire data in yellow cells)

    Classrooms Ages # children Tuition/week Annual Income Total

    Infant Room 1 0-24 months 10 PKR 2,700.00 PKR 1,350,000.00

    Infant Room 2 0-24 months 10 PKR 2,700.00 PKR 1,350,000.00

    otal Infant Fees PKR 2,700,000.00

    Toddler Room 1 24-36 months 10 PKR 2,500.00 PKR 1,250,000.00

    Toddler Room 2 24-36 months 10 PKR 2,500.00 PKR 1,250,000.00

    otal Toddler Fees PKR 2,500,000.00

    Preschool Room 1 Three year olds 12 PKR 2,500.00 PKR 1,500,000.00

    Preschool Room 2 Four year olds 12 PKR 2,500.00 PKR 1,500,000.00

    Preschool Room 3 Five year olds 12 PKR 2,500.00 PKR 1,500,000.00

    otal Preschool Fees PKR 4,500,000.00

    Kindergarten 15 PKR 2,700.00 PKR 2,025,000.00

    School-age (school-term) 15 PKR 2,700.00 PKR 1,579,500.00

    School-age (summer) 15 PKR 2,700.00 PKR 486,000.00

    otal School-age Fees PKR 4,090,500.00

    otal Center Income 121 PKR 26,000.00 PKR 13,790,500.00

    Start up Budget Worksheet

  • 8/2/2019 Group I - Day Care

    19/48

    Start-up Budget WorksheetIncome Items Description Expense

    Bank Loan Loans From Personal bank for the commercial use PKR 300,000.00

    Personal

    investmentpersonal saving PKR 1,000,000.00

    TOTAL

    INCOMEPKR 1,300,000.00

    Expense Items Description Expense

    Personnel Expenses

    Program DirectorStaff who plans and implements start-up period which could be as long as 6-

    12 monthsPKR 360,000.00

    Staff Staff employed up to a month before children are enrolled PKR 50,000.00

    Staff trainingAn intensive multi-day all-staff orientation should be conducted before

    opening.PKR 15,000.00

    Professional Services Architect, attorney, contractors, etc. PKR 300,000.00

    Staff recruitment Signs, classified ads, etc PKR 30,000.00

    Building/renovation All costs such as rent, construction, and/or renovation. PKR 720,000.00

    Furniture/

    Equipment

    For kids Toys etc PKR 1,500,000.00

    Office PKR 200,000.00

    Kitchen and cleaning Commercial kitchen equipment will be required PKR 300,000.00

    Other

    Advertising/marketingMoney spent on making the program visible such as signage and attractive

    landscaping will be worth the investment.PKR 200,000.00

    Licensing fees PKR 30,000.00

    TOTAL EXPENSES PKR 3,705,000.00

    Salary Expense Worksheet

  • 8/2/2019 Group I - Day Care

    20/48

    y p(entire data in yellow cells)

    Hours Salary Annual Mandated

    per Week per Hour Wage Benefits Total Total

    (enter # hrs) (enter wage) w/o Benefits at .6% Benefits Expense

    Room One (8 infants)

    Lead Teacher 54 PKR 100.00 PKR 280,800.00 PKR 33,696.00 PKR 33,696.00 PKR 314,496.00

    Assistant staff 54 PKR 45.00 PKR 126,360.00 PKR 15,163.20 PKR 15,163.20 PKR 141,523.20

    Assistant staff 54 PKR 45.00 PKR 126,360.00 PKR 15,163.20 PKR 15,163.20 PKR 141,523.20

    Room Two (8 infants)

    Lead Teacher 54 PKR 100.00 PKR 280,800.00 PKR 33,696.00 PKR 33,696.00 PKR 314,496.00

    Assistant staff 54 PKR 45.00 PKR 126,360.00 PKR 15,163.20 PKR 15,163.20 PKR 141,523.20Assistant staff 54 PKR 45.00 PKR 126,360.00 PKR 15,163.20 PKR 15,163.20 PKR 141,523.20

    Total Infant Staff Salaries PKR 1,195,084.80

    Room Three (10 toddlers)

    Lead Teacher 54 PKR 92.00 PKR 258,336.00 PKR 31,000.32 PKR 31,000.32 PKR 289,336.32

    Assistant staff 54 PKR 40.00 PKR 112,320.00 PKR 13,478.40 PKR 13,478.40 PKR 125,798.40

    Assistant staff 54 PKR 40.00 PKR 112,320.00 PKR 13,478.40 PKR 13,478.40 PKR 125,798.40

    Room Four (10 toddlers)

    Lead Teacher 54 PKR 92.00 PKR 258,336.00 PKR 31,000.32 PKR 31,000.32 PKR 289,336.32

    Assistant staff 54 PKR 40.00 PKR 112,320.00 PKR 13,478.40 PKR 13,478.40 PKR 125,798.40

    Assistant staff 54 PKR 40.00 PKR 112,320.00 PKR 13,478.40 PKR 13,478.40 PKR 125,798.40

    Total Toddler StaffSalaries PKR 1,081,866.24

    Room Five (14 3-4 year olds)

    Lead Teacher 54 PKR 92.00 PKR 258,336.00 PKR 31,000.32 PKR 31,000.32 PKR 289,336.32

    Assistant staff 54 PKR 40.00 PKR 112,320.00 PKR 13,478.40 PKR 13,478.40 PKR 125,798.40

    Assistant staff 54 PKR 40.00 PKR 112,320.00 PKR 13,478.40 PKR 13,478.40 PKR 125,798.40

    Room Six (20 5-year olds)

    Lead Teacher 54 PKR 92.00 PKR 258,336.00 PKR 31,000.32 PKR 31,000.32 PKR 289,336.32

    Assistant staff 54 PKR 40.00 PKR 112,320.00 PKR 13,478.40 PKR 13,478.40 PKR 125,798.40

    Assistant staff 54 PKR 40.00 PKR 112,320.00 PKR 13,478.40 PKR 13,478.40 PKR 125,798.40Total Preschool StaffSalaries

    PKR 1,081,866.24

    Room Seven (School-age)Lead Staff 15 PKR 100.00 PKR 78,000.00 PKR 9,360.00 PKR 9,360.00 PKR 87,360.00

    Assistant staff 15 PKR 40.00 PKR 31,200.00 PKR 3,744.00 PKR 3,744.00 PKR 34,944.00

    Assistant staff 15 PKR 40.00 PKR 31,200.00 PKR 3,744.00 PKR 3,744.00 PKR 34,944.00

    Total School-age Salaries PKR 157,248.00

    Adminstration and Support

    Director 6 PKR 1,600.00 PKR 499,200.00 PKR 59,904.00 PKR 59,904.00 PKR 559,104.00

    Receptionist 54 PKR 23.00 PKR 64,584.00 PKR 7,750.08 PKR 7,750.08 PKR 72,334.08

    Cook 54 PKR 23.00 PKR 64,584.00 PKR 7,750.08 PKR 7,750.08 PKR 72,334.08

    Accountant (2) 36 PKR 22.00 PKR 41,184.00 PKR 4,942.08 PKR 4,942.08 PKR 46,126.08

    peon (5) 270 PKR 14.00 PKR 196,560.00 PKR 23,587.20 PKR 23,587.20 PKR 220,147.20

    TotalAdmininstration/Support PKR 970,045.44

    TOTAL SALARYEXPENSES

    4,486,111

    Annual Operating Budget

  • 8/2/2019 Group I - Day Care

    21/48

    Annual Operating Budget(Complete yellow cells. Blue cells link with fee and salary worksheets.)

    Income Items Description Expense

    uition Consider a reduced utilization rate (85-95%)

    Infant we are expecting 10 infants per month PKR 2,700,000.00

    Toddler we are expecting 10 toddlers per month PKR 2,500,000.00

    Preschool we are expecting 21 preschool children per month PKR 4,500,000.00

    School-age we are expecting 29 school age children per month PKR 4,090,500.00

    Fundraising expecting it in future

    Grants expecting it in future

    OTAL INCOME PKR 13,790,500.00

    Expense Items Description Expense

    Salaries

    Infant Staff one lead teacher and two assistants PKR 1,195,084.80Toddler Staff one lead teacher and two assistants PKR 1,081,866.24

    Preschool Staff one lead teacher and two assistants PKR 1,081,866.24

    School-age Staff one lead teacher and two assistants PKR 157,248.00

    Admin/Support Staff one director,one receptionalist,one cook,two accountants and 5 peons PKR 970,045.44

    Staff Training Include workshop fees, substitutes and staff library PKR 15,000.00

    OccupancyAll costs arising from use of a building and land such as rent, mortgage,real estate taxes, lawn services, mechanical maintenance, etc.

    PKR 960,000.00

    Utilities Contact utility provider to inquire about projected fee increases. PKR 300,000.00

    Phone/internet access PKR 60,000.00

    Loan payment PKR 36,000.00

    Supplies PKR 2,500,000.00

    Equipment PKR 100,000.00

    Repair/maintainance PKR 50,000.00

    Advertising PKR 200,000.00

    OTAL EXPENSES PKR 8,707,110.72

  • 8/2/2019 Group I - Day Care

    22/48

    Break Even Quantity (#of Students)

    Doddlers Day Care Solution Column1 Column2 Column3

    Cost Type Costs Revenues

    Fixed Costs Fixed 5249711 xxxxxx

    Variable costs Variable 104743 xxxxxx

    Revenue per unit Variable xxxxxx 113971

    BREAKEVEN POINTS Units Dollars

    Costs vs Revenues 568.89 64836890

    Volume analysis @ 121

    Total Fixed Costs 5249711 0

    Total Variable Costs/Revenues 12673900 13790490

    Total Costs 17923610 13790490

    Net Cost 4133119

  • 8/2/2019 Group I - Day Care

    23/48

    Break Even Quantity (# of

    Students)

  • 8/2/2019 Group I - Day Care

    24/48

    Advertising budget breakup

    Advertising Start Date End Date Budget

    Yellow Pages 1/1/2011 12/1/2011 Rs40000

    Newapapers 1/1/2011 6/1/2011 Rs75000

    MotherCare News

    Letter campaign #11/1/2011 6/1/2011 Rs25000

    Strategic Alliance

    development1/1/2011 12/1/2011 Rs60000

    Total Advertising

    BudgetRs200,000

  • 8/2/2019 Group I - Day Care

    25/48

  • 8/2/2019 Group I - Day Care

    26/48

    QUALITY MANAGEMENT PROCESSES

    Process Project Phase Key Deliverables

    Plan Quality Planning Quality Management Plan,

    Perform Quality Assurance Execution Change Requests

    Perform Quality Control Monitoring and Controlling Quality control measurements

    The quality of child care varies widely and childrens outcomes differ depending upon the quality of their child

    care experiences.

  • 8/2/2019 Group I - Day Care

    27/48

    ADVANTAGES OF DOODLE DAY CARE CENTRE

    o More affordable than nanny care

    o Ample supervision

    o Toddlers can socialize with other children of same or other age groups

    o Staff members are trained in early childhood education

    o Licensed and regulated

  • 8/2/2019 Group I - Day Care

    28/48

    QUALITY EVALUATION & ASSURANCE OF DOODLE DAY CARE

    ENVIRONMENT

    Safe, clean and uncluttered.

    Colorful and inviting atmosphere. Child size furniture and accessible displays.

    STAFF

    One-on-one interaction with children in a warm, responsive way.

    Low rate of staff turnover.

    LICENSING

    Doodle day care is in compliance with all licensing regulations.

    SAFETY & HEALTH Clean and well ventilated environment.

    Safe and proper functioning toys.

    Staff trained in CPR and first aid.

    Policies regarding injuries and emergencies.

  • 8/2/2019 Group I - Day Care

    29/48

    THE PROGRAN/CURRICULUM

    Play activities that enhance development.

    Both small and large group activities. Balance between rest and activity.

    FAMILY INVOLVEMENT

    Encouragement to parents for joining B.O.D.

    Parents suggestions for Doodle day cares policies.

    Openness to parents visits.

    FACILITY

    Safe indoor and outdoor areas and equipments. Classrooms based on age.

    Airy, well-lit and attractive rooms with bright colors.

    Sanitary bathrooms and diaper-changing areas.

  • 8/2/2019 Group I - Day Care

    30/48

    DOODLE DAY CARES QUALITY CHECKLIST

    AVAILABILITY

    Questions to ask:

    What ages are accepted? What time can I drop my child off?

    What is the latest time that I can pick up my child?

    Do you have space available for my child?

    Can I visit the facility without an appointment?

    Do you have a list of references that I can call?

    STAFF TRAINING & FACILITY LICENCING

    Questions to ask:

    Are you licensed and accredited?

    How long has your facility been providing daycare?

    Does your staff have training in early childhood development?

    Are teachers trained in first aid and CPR?

    What is your staff turnover?

    Are background checks completed on staff members?

  • 8/2/2019 Group I - Day Care

    31/48

    DAILY ACTIVITIES & SCHEDULES

    Questions to ask:

    Are nap times provided? What time and where?

    What activities will be available for my child? Is there an education curriculum?

    MEALS

    Questions to ask:

    Are meals provided by the daycare? Are snacks provided by the daycare?

    Are they nutritious meals and snacks?

    ENVIRONMENT

    Questions to ask:

    Do you have an outdoor playground?

    Are there personal cribs for each infant?

    Are there separate rooms for each age group?

    Is the staff allowed to smoke on facility premises?

  • 8/2/2019 Group I - Day Care

    32/48

    SAFETYQuestions to ask:

    Is there a safety plan in place in case of an emergency?

    Does the playground equipment meet safety standards?

    Are hazardous materials kept out of reach of children?

    Is there a first aid kit?

    SANITATION

    Questions to ask:

    How often are toys washed? What do you use to clean them?

    Are children taught to wash their hands before eating and after using the toilet?

  • 8/2/2019 Group I - Day Care

    33/48

    QUALITY ASSURANCE AND CONTROL

    The provider reviews their service against agreed quality standards. Investigation of complaints or concerns regarding a health and safety

    issues.

    Technical assistance provided by quality assurance teams.

    Parental access to online child care licensing inspections. Parental access to online licensing complaints.

    Monthly inspection of Doodles day cares programs and facilities.

    Fulfillment of staff requirements.

    Educational requirements of teachers and volunteers.

  • 8/2/2019 Group I - Day Care

    34/48

    Developing HumanResource in Child

    Care Centre

  • 8/2/2019 Group I - Day Care

    35/48

    Project Human Resource

    Management Develop Human Resource Plan

    The process of identifying and documenting projectroles, responsibilities, and required skills, reportingrelationships, and creating a staffing managementplan

  • 8/2/2019 Group I - Day Care

    36/48

    Project Human Resource

    Management Acquire Project Team

    It ensures the availability of the team to complete theproject achieve the project objective on time

    There must be a minimum of one qualified staff in eachdefined group of childrenShe/he must have completed at least a two year early

    childhood education program from a community collegeThere are no specified educational qualifications for

    assistants under the Day Nurseries ActStaff training has been identified as a key indicator ofquality child care.

    Resource Teachers are available in some centers

    Project Human Resource

  • 8/2/2019 Group I - Day Care

    37/48

    Project Human Resource

    Management

    Develop Project Team

    it require the development of capabilities in suchareas as formulating business and HR strategies

    Child care centres may also employ support staffIn a high quality program, all staff strive to meet

    the physical, social, emotional and needs of theyoung children in their care

    Project Human Resource

  • 8/2/2019 Group I - Day Care

    38/48

    Project Human Resource

    Management Manage Project Team

    It involves tracking the team member performance and providefeedback to ensure that the team is :

    Implementing with speed, flexibility and teamwork

    Obtaining lasting results that continue to grow improved staff-to-child ratios to ensure each child gets attention

    Influence Project Team

    It includes factors which impact the project like: Team environment Geographical location Cultural issues or the factors which can alter project performance new staff qualification requirements to ensure staff skills

  • 8/2/2019 Group I - Day Care

    39/48

    Age Group Staff to child ratio

    Long Day Care

    and Preschool

    Birth to 24months

    1 staff to4 children

    25 to 35 months 1 staff to5 children1

    36 months toschool age

    1 staff to11 children

    Family DayCare

    Mixed agegroups

    A proportional formulawill be applied

    Mixed age

    groups ofchildren

    1 staff member to

    7 children with amaximum of fourchildren

  • 8/2/2019 Group I - Day Care

    40/48

    Project Human Resource

    Management Professional & Ethical Behavior

    The project management team should be aware of

    and ensure that all team members follow ethicalbehavior

  • 8/2/2019 Group I - Day Care

    41/48

  • 8/2/2019 Group I - Day Care

    42/48

    Day Care Communication Plan

    Identify Stakeholders

    Plan Communication

    DistributeInformation

    Manage Stakeholderexpectations

    Report performance

  • 8/2/2019 Group I - Day Care

    43/48

    Identifying Stakeholders

    Owner

    Parents

    Teachers

    Qualified staff

    Children

  • 8/2/2019 Group I - Day Care

    44/48

    Plan Communication Communication Objective To reach nuclear

    families with children and educated working parentsbelonging to SEC A & B. This group has the money forchild care, and are willing to spend a little extra to get ahigher level of care.

    Media We will be following a pull approach.Advertisements will be printed in newspaper, journals formothers and magazines.

  • 8/2/2019 Group I - Day Care

    45/48

    Distribute Information

    The Doodles Day Care willrun advertisements innewspaper, journals formothers and magazines.

    Two different campaigns willbe used. The first will be amultifaceted advertisingcampaign, the second will be

    the formation of strategicalliances.

  • 8/2/2019 Group I - Day Care

    46/48

    Managing Stakeholder expectations

    Selection: A complete service

    offering of child care and learningdevelopment for children aged 0 to6 years.

    Accessibility: The facility iscentrally located and is open from 9

    a.m.- 6 p.m. Customer service: Treating the

    customer like they are the mostimportant customer thatThe Doodles Day Care has is

    reinforced in all employee trainingprograms.

    Competitive pricing: The pricingis reasonable relative to the servicesoffered@ less than 3000/week

  • 8/2/2019 Group I - Day Care

    47/48

    Report Performance

    Standards Grow the number of customers

    by 10% annually.

    Build customer loyalty throughsuperior service andeducational/development systems.

    Build The Doodles Day Care

    brand to the point where itbecomes a household brandsynonymous with superiorchild care/development in theDoodles area.

  • 8/2/2019 Group I - Day Care