gulf schedule

5

Click here to load reader

Upload: karen-ortiz

Post on 23-Oct-2015

8 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: GULF Schedule

Activity ID Activity Name OriginalDuration

Activity %Complete

Start Finish BL1 Start BL1 Finish Variance -BL1

Duration

Energia Mayakan Pipeline Expansion Project - Detailed E&D - RevisedEnergia Mayakan Pipeline Expansion Project - Detailed E&D - Revised246 22-May-13 A

30-Apr-14 22-May-13 15-Oct-13 -141

MilestonesMilestones 213 22-May-13 A 14-Mar-14 22-May-13 15-Oct-13 -108

A1000 Limited Notice to Proceed (LNTP) 0 100% 22-May-13 A 22-May-13 0

A1010 Full Notice to Proceed (FNTP) 0 100% 17-Jun-13 A 17-Jun-13 0

A1020 Project Kick-off Meeting 0 100% 22-May-13 A 22-May-13 0

A1030 LNTP Deliverables Issued 0 100% 14-Jun-13 A 14-Jun-13 0

A1040 Detail Engineering & Design Schedule 0 100% 11-Jul-13 A 11-Jul-13 0

A1050 Receive 100% Survey Data for Pipeline Cooridor 0 0% 03-Dec-13* 19-Jul-13 0

A1060 Issue Drawings for Client Review - EM#2 0 100% 12-Nov-13 A 24-Sep-13 0

A1070 Issue for Construction Drawings - All Drawings 0 0% 14-Mar-14* 15-Oct-13 0

A1080 Issue SCADA Specification 0 100% 23-Jul-13 A 31-Jul-13 0

A1090 Issue Preliminary Plot Plans 0 100% 18-Jul-13 A 17-Jul-13 0

A1170 Issue Drawings for Client Review - Pipeline, MLV#1, MLV#2 0 0% 06-Mar-14 24-Sep-13 0

A1180 Issue Drawings for Client Review - EM#3 0 100% 24-Oct-13 A 10-Sep-13 0

A1190 Issue Drawings for Client Review - Interconnect 0 100% 12-Nov-13 A 17-Sep-13 0

Engineering, Design and ProcurementEngineering, Design and Procurement 213 22-May-13 A 14-Mar-14 22-May-13 15-Oct-13 -108

Limited Notice to Proceed (LNTP)Limited Notice to Proceed (LNTP) 18 22-May-13 A 14-Jun-13 A 22-May-13 14-Jun-13 0

Project Management / Project EngineeringProject Management / Project Engineering 18 22-May-13 A 14-Jun-13 A 22-May-13 14-Jun-13 0

A1100 Mobilization of Project Team Personnel and famil iari zati on of FEED documents3 100% 22-May-13 A 24-May-13 A 22-May-13 24-May-13 0

A1120 Design Basis Manual 17 100% 22-May-13 A 14-Jun-13 A 22-May-13 14-Jun-13 -1

PipelinePipeline 15 22-May-13 A 11-Jun-13 A 22-May-13 11-Jun-13 0

A1110 Survey Specification 7 100% 22-May-13 A 31-May-13 A 22-May-13 31-May-13 -1

A1130 Preliminary Hydraulic Analysis 11 100% 22-May-13 A 06-Jun-13 A 22-May-13 06-Jun-13 -1

A1150 Preliminary Pipe/Costing Requisition 7 100% 03-Jun-13 A 11-Jun-13 A 03-Jun-13 11-Jun-13 0

Mechanical / PipingMechanical / Piping 18 22-May-13 A 14-Jun-13 A 22-May-13 14-Jun-13 0

A1140 Preliminary P&IDs 17 100% 22-May-13 A 14-Jun-13 A 22-May-13 14-Jun-13 -1

Full Notice to Proceed (FNTP)Full Notice to Proceed (FNTP) 201 07-Jun-13 A 14-Mar-14 07-Jun-13 15-Oct-13 -108

GeneralGeneral 201 07-Jun-13 A 14-Mar-14 07-Jun-13 14-Oct-13 -109

Project Management (General)Project Management (General) 201 07-Jun-13 A 14-Mar-14 07-Jun-13 09-Aug-13 -155

A1220 Pipeline Cooridor Survey - By Arendal 11 90.91% 07-Jun-13 A 03-Dec-13 07-Jun-13 21-Jun-13 -117

A1230 Detail Engineering and Design Schedule 19 100% 07-Jun-13 A 11-Jul-13 A 07-Jun-13 03-Jul-13 -6

A1380 Facilities Survey 15 100% 07-Jun-13 A 19-Jul-13 A 07-Jun-13 27-Jun-13 -16

A1440 Site Visit 5 100% 24-Jun-13 A 28-Jun-13 A 24-Jun-13 28-Jun-13 0

A1790 Formal Client HAZOP 2 100% 05-Aug-13 A 06-Aug-13 A 30-Jul-13 31-Jul-13 0

A1800 Review IFC Package 21 0% 14-Feb-14 14-Mar-14 29-Jul-13 09-Aug-13 -11

A1860 Internal HAZOP 1 100% 16-Jul-13 A 16-Jul-13 A 16-Jul-13 16-Jul-13 0

Engineering (General)Engineering (General) 146 07-Jun-13 A 30-Dec-13 07-Jun-13 14-Oct-13 -55

Mechanical/Piping (General)Mechanical/Piping (General) 135 24-Jun-13 A 30-Dec-13 24-Jun-13 14-Oct-13 -55

A1980 Stress Analysis 16 0% 03-Dec-13* 27-Dec-13 01-Aug-13 30-Aug-13 3

A1990 Filters/Separator Skids Requisition 15 100% 24-Jun-13 A 16-Jul-13 A 24-Jun-13 15-Jul-13 -1

A2010 Meter Skid Requisition 16 100% 15-Jul-13 A 05-Aug-13 A 11-Jul-13 01-Aug-13 0

A2030 Condensate Tank Requi sit ion 15 100% 16-Aug-13 A 27-Aug-13 A 05-Aug-13 23-Aug-13 8

A3010 Instrument Gas Posts Requisition 5 100% 02-Aug-13 A 21-Aug-13 A 22-Jul-13 09-Aug-13 2

A3040 Ball Valves Requisition 15 100% 08-Jul-13 A 30-Jul-13 A 29-Jul-13 16-Aug-13 -1

A3060 Plug Valves Requisition 6 100% 26-Jul-13 A 31-Jul-13 A 15-Jul-13 02-Aug-13 12

A3080 Large Pipe and Fittings Requisition 15 100% 19-Aug-13 A 18-Oct-13 A 19-Aug-13 09-Sep-13 -30

A3400 Pressure Safety Valves Requisition 15 100% 20-Aug-13 A 23-Oct-13 A 26-Aug-13 16-Sep-13 -31

A3420 Restriction Orifices Requisition 15 100% 20-Aug-13 A 19-Nov-13 A 26-Aug-13 16-Sep-13 -50

A3440 Valves (6" and Smaller) Requisition 15 100% 15-Aug-13 A 07-Oct-13 A 08-Aug-13 28-Aug-13 -22

A3470 Filters/Separator Skid TBE 5 100% 20-Aug-13 A 27-Aug-13 A 08-Oct-13 14-Oct-13 0

A3480 Check Valves Requisition 15 100% 05-Aug-13 A 20-Aug-13 A 29-Jul-13 16-Aug-13 4

A3490 Ball Valves TBE 5 100% 20-Aug-13 A 13-Sep-13 A 03-Sep-13 09-Sep-13 -14

A3500 Globe Valves Requisition 15 100% 05-Aug-13 A 20-Aug-13 A 29-Jul-13 16-Aug-13 4

A3510 Meter Skid TBE 3 100% 26-Aug-13 A 30-Aug-13 A 03-Sep-13 09-Sep-13 0

A3520 Plug Valves TBE 5 100% 30-Aug-13 A 06-Sep-13 A -6

A3530 Instrument Gas Post TBE 5 100% 01-Oct-13 A 28-Oct-13 A -19

A3540 Condensate Tank TBE 6 16.67% 26-Sep-13 A 09-Dec-13 -53

A3550 Check Valves TBE 5 100% 26-Sep-13 A 02-Oct-13 A -5

A3560 Globe Valves TBE 5 100% 26-Sep-13 A 02-Oct-13 A -5

A3570 Valves (2"-6") TBE 9 0% 28-Oct-13 A 16-Dec-13 -36

19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04June July August September October November December January February March April May

2013 2014

30-Apr-14, Energia Mayakan Pipeline Expansion Project - Detailed E&D - Revised

14-Mar-14, Milestones

Limited Notice to Proceed (LNTP)

Full Notice to Proceed (FNTP)

Project Kick-off Meeting

LNTP Deliverables Issued

Detail Engineering & Design Schedule

Receive 100% Survey Data for Pipeline Cooridor

Issue Drawings for Client Review - EM#2

Issue for Construction Drawings - All Drawings

Issue SCADA Specification

Issue Preliminary Plot Plans

Issue Drawings for Client Review - Pipeline, MLV#1, MLV#2

Issue Drawings for Client Review - EM#3

Issue Drawings for Client Review - Interconnect

14-Mar-14, Engineering, Design and Procurement

14-Jun-13 A, Limited Notice to Proceed (LNTP)

14-Jun-13 A, Project Management / Project Engineering

Mobilization of Project Team Personnel and famil iari zati on of FEED documents

Design Basis Manual11-Jun-13 A, Pipel ine

Survey Specification

Preliminary Hydraulic Analysis

Preliminary Pipe/Costing Requisition14-Jun-13 A, Mechanical / Piping

Preliminary P&IDs14-Mar-14, Full Notice to Proceed (FNTP)

14-Mar-14, General

14-Mar-14, Project Management (General)

Pipeline Cooridor Survey - By Arendal

Detail Engineering and Design Schedule

Facilities Survey

Site Visit

Formal Client HAZOP

Review IFC Package

Internal HAZOP30-Dec-13, Engineering (General)

30-Dec-13, Mechanical/Piping (General)

Stress Analysis

Filters/Separator Skids Requisition

Meter Skid Requisition

Condensate Tank Requi sit ion

Instrument Gas Posts Requisition

Ball Valves Requisition

Plug Valves Requisition

Large Pipe and Fittings Requisition

Pressure Safety Valves Requisition

Restriction Orifices Requisition

Valves (6" and Smaller) Requisition

Filters/Separator Skid TBE

Check Valves Requisition

Ball Valves TBE

Globe Valves Requisition

Meter Skid TBEPlug Valves TBE

Instrument Gas Post TBE

Condensate Tank TBE

Check Valves TBE

Globe Valves TBE

Valves (2"-6") TBE

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary

Page 2: GULF Schedule

Activity ID Activity Name OriginalDuration

Activity %Complete

Start Finish BL1 Start BL1 Finish Variance -BL1

DurationA3580 Large Pipe and Fittings TBE 11 27.27% 25-Nov-13 A 12-Dec-13 19-Aug-13 30-Aug-13 -4

A3590 Gate Valve 19 100% 09-Aug-13 A 06-Sep-13 A 09-Sep-13 09-Sep-13 -20

A4960 Wall Thickness Calculations 33 100% 01-Jul-13 A 26-Jul-13 A 01-Jul-13 15-Aug-13 13

A4970 Facility Piping Specification 29 100% 08-Jul-13 A 30-Jul-13 A 08-Jul-13 15-Aug-13 13

A4980 Tie-in List 12 100% 12-Sep-13 A 07-Oct-13 A 15-Jul-13 01-Oct-13 39

A4990 Pressure Safety Valves TBE 8 0% 03-Dec-13 12-Dec-13 01-Aug-13 14-Aug-13 2

A5110 Restriction Orifices TBE 5 0% 25-Nov-13 A 30-Dec-13 03-Sep-13 09-Sep-13 -21

Electrical (General)Electrical (General) 50 26-Jul-13 A 23-Oct-13 A 26-Jul-13 27-Sep-13 -17

A1520 Thermoelectric Generators Requisition 15 100% 26-Jul-13 A 28-Aug-13 A 26-Jul-13 15-Aug-13 -8

A2450 Thermoelectric Generators TBE 6 100% 26-Sep-13 A 23-Oct-13 A 23-Sep-13 27-Sep-13 -14

Instrumentation (General)Instrumentation (General) 117 07-Jun-13 A 16-Dec-13 07-Jun-13 07-Oct-13 -50

A1710 SCADA Specification 38 100% 07-Jun-13 A 23-Jul-13 A 07-Jun-13 31-Jul-13 6

A1960 Telecommunications Specification 38 100% 07-Jun-13 A 30-Jul-13 A 08-Jul-13 28-Aug-13 1

A2200 Leak Detection Specification 38 100% 07-Jun-13 A 01-Aug-13 A 08-Jul-13 28-Aug-13 -1

A2410 Instrument Skid Specification 2 100% 08-Jul-13 A 16-Jul-13 A 09-Jul-13 10-Jul-13 -4

A2960 Analyzer Control Building TBE 12 75% 24-Oct-13 A 05-Dec-13 -31

A3140 RTU Requisition 20 100% 01-Aug-13 A 05-Sep-13 A 22-Aug-13 22-Aug-13 -25

A3150 RTU TBE 5 100% 16-Oct-13 A 22-Oct-13 A 26-Aug-13 09-Sep-13 5

A4010 Analyzer Control Building Requisition 39 100% 10-Jul-13 A 11-Sep-13 A 15-Jul-13 06-Sep-13 -6

A4380 Instruments Requisitions 24 100% 08-Jul-13 A 26-Sep-13 A 08-Jul-13 08-Aug-13 -35

A4390 SCADA TBE 5 100% 03-Sep-13 A 10-Sep-13 A 12-Aug-13 07-Oct-13 35

A4400 Leak Detection TBE 5 100% 03-Sep-13 A 10-Sep-13 A 29-Jul-13 09-Sep-13 25

A4410 Telecommunications TBE 5 100% 03-Sep-13 A 10-Sep-13 A 07-Oct-13 07-Oct-13 -5

A4420 Instruments TBE 20 50% 26-Sep-13 A 16-Dec-13 23-Sep-13 27-Sep-13 -53

A5400 SCADA Requisition 1 100% 07-Jun-13 A 19-Aug-13 A -51

A5410 Leak Detection Requisition 1 100% 07-Jun-13 A 19-Aug-13 A -51

A5420 Telecommunications Requisition 1 100% 07-Jun-13 A 19-Aug-13 A -51

Design (General)Design (General) 18 10-Jul-13 A 23-Jul-13 A 08-Jul-13 31-Jul-13 9

Instrumentation (General)Instrumentation (General) 18 10-Jul-13 A 23-Jul-13 A 08-Jul-13 31-Jul-13 9

A3020 SCADA Network Architectural Diagram 18 100% 10-Jul-13 A 23-Jul-13 A 08-Jul-13 31-Jul-13 9

Pipeline, MLV#1, MLV#2Pipeline, MLV#1, MLV#2 195 17-Jun-13 A 14-Mar-14 17-Jun-13 15-Oct-13 -108

Engineering (PL, MLV1, MLV2)Engineering (PL, MLV1, MLV2) 195 17-Jun-13 A 14-Mar-14 17-Jun-13 24-Sep-13 -123

Pipeline (PL, MLV1, MLV2)Pipeline (PL, MLV1, MLV2) 195 17-Jun-13 A 14-Mar-14 17-Jun-13 24-Sep-13 -123

A1390 Mainline Pipe / Coating Requisition 30 100% 17-Jun-13 A 31-Jul-13 A 17-Jun-13 29-Jul-13 -2

A1430 Monolithic Isolation Joint Requisition 24 100% 17-Jun-13 A 18-Jul-13 A 17-Jun-13 19-Jul-13 1

A1460 Cathodic Protection Calculations 46 0% 22-Jul-13 A 14-Mar-14 08-Jul-13 24-Sep-13 -114

A1620 Monolithic Isolation Joint TBE 5 100% 19-Aug-13 A 20-Aug-13 A 13-Aug-13 19-Aug-13 4

A1640 Hinged Closures TBE 12 100% 29-Aug-13 A 20-Sep-13 A 29-Jul-13 09-Aug-13 -6

A1650 Review IFC Package 6 0% 07-Mar-14 14-Mar-14 16-Aug-13 16-Aug-13 -6

A1660 Pig Sig Passage Indicator Requisition 1 100% 30-Sep-13 A 01-Oct-13 A 30-Jul-13 12-Aug-13 9

A1670 Pig Sig Passage Indicator TBE 4 100% 16-Oct-13 A 26-Nov-13 A 19-Aug-13 19-Aug-13 -29

A5300 Hinged Closures Requisition 13 100% 08-Jul-13 A 11-Jul-13 A 25-Jun-13 12-Jul-13 10

Mechanical/Piping (PL, MLV1, MLV2)Mechanical/Piping (PL, MLV1, MLV2) 82 19-Aug-13 A 14-Mar-14 19-Aug-13 30-Aug-13 -140

A3600 Small Pipe and Fittings Requisition 5 100% 18-Nov-13 A 26-Nov-13 A 19-Aug-13 30-Aug-13 4

A3620 Large Pipe and Fittings TBE 1 0% 25-Nov-13 A 12-Dec-13 -14

A5480 Review IFC Package 71 0% 03-Dec-13 14-Mar-14 -74

A5560 Small Pipe & Fitting TBE 8 0% 03-Dec-13 12-Dec-13 -8

A5590 Large Pipe and Fittings Requisition 1 100% 19-Aug-13 A 19-Nov-13 A -66

Civil/Structural (PL, MLV1, MLV2)Civil/Structural (PL, MLV1, MLV2) 73 20-Aug-13 A 14-Mar-14 01-Jul-13 30-Aug-13 -104

A1550 MLV Foundation Calculations 5 0% 20-Aug-13 A 20-Dec-13 26-Aug-13 30-Aug-13 -84

A1610 Review IFC Package 34 0% 07-Oct-13 A 14-Mar-14 01-Jul-13 23-Aug-13 -76

Electrical (PL, MLV1, MLV2)Electrical (PL, MLV1, MLV2) 36 07-Oct-13 A 14-Mar-14 -115

A5490 Review IFC Package 34 0% 07-Oct-13 A 14-Mar-14 -115

Instrumentation (PL, MLV1, MLV2)Instrumentation (PL, MLV1, MLV2) 108 03-Jul-13 A 14-Mar-14 08-Jul-13 20-Sep-13 -128

A5360 Instrument Index 8 100% 03-Jul-13 A 18-Jul-13 A 08-Jul-13 17-Jul-13 -3

A5370 I/O List 13 100% 16-Jul-13 A 18-Jul-13 A 16-Jul-13 01-Aug-13 11

A5380 Review IFC Package 34 0% 07-Oct-13 A 14-Mar-14 09-Sep-13 20-Sep-13 -105

Design (PL, MLV1, MLV2)Design (PL, MLV1, MLV2) 195 17-Jun-13 A 14-Mar-14 17-Jun-13 15-Oct-13 -108

Pipeline (PL, MLV1, MLV2)Pipeline (PL, MLV1, MLV2) 190 24-Jun-13 A 14-Mar-14 24-Jun-13 15-Oct-13 -108

A1360 Construction Alignment Sheets 65 0% 24-Jun-13 A 06-Mar-14 24-Jun-13 24-Sep-13 -119

A1400 HDD Drawings 46 0% 08-Jul-13 A 06-Mar-14 08-Jul-13 24-Sep-13 -118

A1410 Typical Pipeline Drawings/Details 28 35.71% 12-Aug-13 A 31-Dec-13 01-Aug-13 24-Sep-13 -64

A1420 Site Location Maps 28 0% 22-Jul-13 A 06-Mar-14 01-Aug-13 24-Sep-13 -126

A1480 Geotech Testing Locati on Drawi ngs 8 100% 02-Jul-13 A 10-Jul-13 A 02-Jul-13 12-Jul-13 2

A1490 Crossing Drawings 36 0% 01-Aug-13 A 06-Mar-14 15-Jul-13 24-Sep-13 -105

A1510 Class Location Study 64 0% 25-Jun-13 A 06-Mar-14 25-Jun-13 24-Sep-13 -119

A1600 Finalize IFC Drawings 6 0% 07-Mar-14 14-Mar-14 25-Sep-13 15-Oct-13 9

Mechanical/Piping (PL, MLV1, MLV2)Mechanical/Piping (PL, MLV1, MLV2) 195 17-Jun-13 A 14-Mar-14 17-Jun-13 15-Oct-13 -108

A1450 PFD/P&ID (IFCA) 17 100% 17-Jun-13 A 23-Jul-13 A 17-Jun-13 10-Jul-13 -9

A1570 Piping Sections and Details 41 100% 02-Jul-13 A 12-Nov-13 A 15-Jul-13 24-Sep-13 -45

A1580 MLV Assembly Drawing 51 100% 15-Jul-13 A 12-Nov-13 A 15-Jul-13 24-Sep-13 -35

A1760 Finalize IFC Drawings 71 0% 03-Dec-13 14-Mar-14 25-Sep-13 15-Oct-13 -59

A1820 Piping Plot Plan 22 100% 17-Jun-13 A 18-Jul-13 A 08-Jul-13 06-Aug-13 -1

Civil/Structural (PL, MLV1, MLV2)Civil/Structural (PL, MLV1, MLV2) 176 24-Jun-13 A 14-Mar-14 12-Jul-13 15-Oct-13 -122

19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04June July August September October November December January February March April May

2013 2014

Large Pipe and Fittings TBE

Gate Valve

Wall Thickness Calculations

Facility Piping Specification

Tie-in List

Pressure Safety Valves TBE

Restriction Orifices TBE23-Oct-13 A, Electrical (General)

Thermoelectric Generators Requisition

Thermoelectric Generators TBE16-Dec-13, Instrumentation (General)

SCADA Specification

Telecommunications Specification

Leak Detection Specification

Instrument Skid SpecificationAnalyzer Control Building TBE

RTU Requisition

RTU TBE

Analyzer Control Building Requisition

Instruments Requisitions

SCADA TBE

Leak Detection TBE

Telecommunications TBE

Instruments TBESCADA Requisition

Leak Detection Requisition

Telecommunications Requisition

23-Jul-13 A, Design (General)

23-Jul-13 A, Instrumentation (General)

SCADA Network Architectural Diagram14-Mar-14, Pipeline, MLV#1, MLV#2

14-Mar-14, Engineering (PL, MLV1, MLV2)

14-Mar-14, Pipeline (PL, MLV1, MLV2)

Mainline Pipe / Coating Requisition

Monolithic Isolation Joint Requisition

Cathodic Protection Calculations

Monolithic Isolation Joint TBE

Hinged Closures TBE

Review IFC Package

Pig Sig Passage Indicator Requisition

Pig Sig Passage Indicator TBE

Hinged Closures Requisition14-Mar-14, Mechanical/Piping (PL, MLV1, MLV2)

Small Pipe and Fittings RequisitionLarge Pipe and Fittings TBE

Review IFC Package

Small Pipe & Fitting TBE

Large Pipe and Fittings Requisition

14-Mar-14, Civil/Structural (PL, MLV1, MLV2)

MLV Foundation Calculations

Review IFC Package14-Mar-14, Electrical (PL, MLV1, MLV2)

Review IFC Package

14-Mar-14, Instrumentation (PL, MLV1, MLV2)

Instrument Index

I/O List

Review IFC Package14-Mar-14, Design (PL, MLV1, MLV2)

14-Mar-14, Pipeline (PL, MLV1, MLV2)

Construction Alignment Sheets

HDD Drawings

Typical Pipeline Drawings/Details

Site Location Maps

Geotech Testing Locati on Drawi ngs

Crossing Drawings

Class Location Study

Finalize IFC Drawings14-Mar-14, Mechanical/Piping (PL, MLV1, MLV2)

PFD/P&ID (IFCA)

Piping Sections and Details

MLV Assembly Drawing

Finalize IFC Drawings

Piping Plot Plan14-Mar-14, Civil/Structural (PL, MLV1, MLV2)

Page 3: GULF Schedule

Activity ID Activity Name OriginalDuration

Activity %Complete

Start Finish BL1 Start BL1 Finish Variance -BL1

DurationA1470 Soil Erosion & Sediments and Control Details 51 100% 15-Jul-13 A 07-Oct-13 A 15-Jul-13 24-Sep-13 -9

A1530 Foundation Plans & Details 16 100% 24-Jun-13 A 07-Oct-13 A 26-Aug-13 17-Sep-13 -59

A1560 Fencing/Grading Details 52 100% 08-Jul-13 A 07-Oct-13 A 12-Jul-13 24-Sep-13 -13

A1750 Finalize IFC Drawings 71 0% 03-Dec-13 14-Mar-14 25-Sep-13 15-Oct-13 -59

Electrical (PL, MLV1, MLV2)Electrical (PL, MLV1, MLV2) 185 03-Jul-13 A 14-Mar-14 01-Jul-13 15-Oct-13 -106

A1590 Electrical Plans & Details 60 100% 03-Jul-13 A 07-Oct-13 A 01-Jul-13 24-Sep-13 -8

A1770 Finalize IFC Drawings 71 0% 03-Dec-13 14-Mar-14 25-Sep-13 15-Oct-13 -59

Instrumentation (PL, MLV1, MLV2)Instrumentation (PL, MLV1, MLV2) 160 24-Jul-13 A 14-Mar-14 08-Jul-13 27-Sep-13 -108

A1780 Finalize IFC Drawings 71 0% 03-Dec-13 14-Mar-14 09-Sep-13 27-Sep-13 -59

A2480 Wiring Diagrams 24 100% 24-Jul-13 A 07-Oct-13 A 08-Jul-13 06-Sep-13 -9

CPG Nuevo Pemex InterconnectCPG Nuevo Pemex Interconnect 195 17-Jun-13 A 14-Mar-14 17-Jun-13 15-Oct-13 -108

Engineering (Interconnect)Engineering (Interconnect) 185 01-Jul-13 A 14-Mar-14 01-Jul-13 16-Sep-13 -129

Mechanical/Piping (Interconnect)Mechanical/Piping (Interconnect) 185 01-Jul-13 A 14-Mar-14 01-Jul-13 16-Sep-13 -129

A2210 Flow Control Valves Skid Requisition 15 100% 01-Jul-13 A 26-Jul-13 A 01-Jul-13 22-Jul-13 -4

A2330 Flow Control Valves Skid TBE 3 100% 28-Aug-13 A 30-Aug-13 A 10-Sep-13 16-Sep-13 2

A2380 Review IFC Package 71 0% 03-Dec-13 14-Mar-14 15-Jul-13 06-Sep-13 -35

Civil/Structural (Interconnect)Civil/Structural (Interconnect) 108 21-Oct-13 A 14-Mar-14 -105

A5500 Review IFC Package 71 0% 03-Dec-13 14-Mar-14 -74

A5510 Flow Control Valve Skid Foundation Calculation 7 0% 21-Oct-13 A 20-Dec-13 -45

A5520 Engineered Pipe Supports Requisition 9 0% 18-Nov-13 A 17-Dec-13 -22

A5530 Engineered Pipe Supports TBE 5 0% 06-Jan-14 10-Jan-14 -5

A5540 Vault Foundation Calculation 10 0% 21-Oct-13 A 20-Dec-13 -45

Design (Interconnect)Design (Interconnect) 195 17-Jun-13 A 14-Mar-14 17-Jun-13 15-Oct-13 -108

Mechanical/Piping (Interconnect)Mechanical/Piping (Interconnect) 195 17-Jun-13 A 14-Mar-14 17-Jun-13 15-Oct-13 -108

A1830 PFD / P&IDs (IFCA) 30 100% 17-Jun-13 A 23-Jul-13 A 17-Jun-13 29-Jul-13 4

A1840 Piping Plot Plan (IFCA) 22 100% 17-Jun-13 A 18-Jul-13 A 17-Jun-13 17-Jul-13 -1

A1850 Piping Plans, Sections, Details 27 100% 19-Aug-13 A 12-Nov-13 A 08-Aug-13 17-Sep-13 -33

A1870 Piping Isometric Drawings 71 0% 03-Dec-13 14-Mar-14 18-Sep-13 01-Oct-13 -64

A1920 Finalize IFC Drawings 71 0% 03-Dec-13 14-Mar-14 18-Sep-13 15-Oct-13 -54

A5090 Finalize Piping Plot Plan 15 100% 18-Jul-13 A 15-Aug-13 A 18-Jul-13 07-Aug-13 -5

Civil/Structural (Interconnect)Civil/Structural (Interconnect) 122 19-Aug-13 A 14-Mar-14 -150

A5430 Site Fence & Grading Plan 1 100% 19-Aug-13 A 12-Nov-13 A -62

A5440 Pipe Support Details 1 100% 19-Aug-13 A 12-Nov-13 A -62

A5450 Hot Tap Vault Details 1 100% 19-Aug-13 A 11-Nov-13 A -61

A5460 Typical Details 1 100% 19-Aug-13 A 12-Nov-13 A -62

A5470 Finalize IFC Drawings 71 0% 03-Dec-13 14-Mar-14 -74

Nuevo Pemex Meter Station - EM#2Nuevo Pemex Meter Station - EM#2 195 17-Jun-13 A 14-Mar-14 17-Jun-13 15-Oct-13 -108

Engineering (EM#2)Engineering (EM#2) 185 27-Jun-13 A 14-Mar-14 01-Jul-13 15-Oct-13 -110

Mechanical/Piping (EM#2)Mechanical/Piping (EM#2) 185 01-Jul-13 A 14-Mar-14 01-Jul-13 07-Oct-13 -114

A1880 Line Sizing Calculations 27 100% 10-Jul-13 A 23-Aug-13 A 08-Jul-13 13-Aug-13 -5

A1890 Cathodic Protection Design 69 0% 01-Jul-13 A 14-Mar-14 01-Jul-13 07-Oct-13 -116

A1950 Valve List 56 91.07% 15-Jul-13 A 09-Dec-13 15-Jul-13 01-Oct-13 -50

A3610 Small Pipe & Fittings Requisition 1 100% 31-Oct-13 A 26-Nov-13 A 09-Sep-13 09-Sep-13 -18

A3630 Large Pipe and Fittings Requisition 1 100% 19-Aug-13 A 18-Nov-13 A -65

A3640 Large Pipe and Fittings TBE 1 0% 25-Nov-13 A 12-Dec-13 -14

A5000 Restriction Orifice Sizing Calculation 13 100% 16-Aug-13 A 19-Nov-13 A 01-Aug-13 21-Aug-13 -52

A5010 Equipment List 41 87.8% 29-Jul-13 A 09-Dec-13 15-Jul-13 01-Oct-13 -40

A5020 Line List 41 87.8% 16-Aug-13 A 09-Dec-13 15-Jul-13 01-Oct-13 -26

A5160 Review IFC Package 71 0% 03-Dec-13 14-Mar-14 24-Sep-13 30-Sep-13 -69

A5570 Small Pipe & Fittings TBE 5 60% 18-Nov-13 A 06-Dec-13 -15

Civil/Structural (EM#2)Civil/Structural (EM#2) 154 20-Aug-13 A 14-Mar-14 10-Jul-13 11-Oct-13 -81

A5100 Analyzer Building Foundation Calculation 5 0% 20-Aug-13 A 20-Dec-13 07-Oct-13 11-Oct-13 -84

A5120 Filter/Scrubber Skid Foundation Calculation 5 0% 20-Aug-13 A 20-Dec-13 13-Aug-13 19-Aug-13 -84

A5130 Meter Skid Foundation Calculation 5 0% 20-Aug-13 A 20-Dec-13 30-Aug-13 06-Sep-13 -84

A5140 Misc. Equipment Foundation Calculations 10 0% 20-Aug-13 A 20-Dec-13 18-Sep-13 01-Oct-13 -79

A5150 Emergeny Generator Foundation Calculation 5 0% 20-Aug-13 A 20-Dec-13 30-Sep-13 04-Oct-13 -84

A5240 Engineered Pipe Supports TBE 2 0% 20-Dec-13 23-Dec-13 10-Jul-13 30-Jul-13 13

A5270 Review IFC Package 71 0% 03-Dec-13 14-Mar-14 20-Aug-13 20-Aug-13 -74

A5310 Engineered Pipe Supports Requisition 41 80.49% 20-Aug-13 A 12-Dec-13 12-Aug-13 16-Aug-13 -78

Electrical (EM#2)Electrical (EM#2) 175 27-Jun-13 A 14-Mar-14 15-Jul-13 15-Oct-13 -120

A2220 Emergency Generator Requisition 15 100% 01-Aug-13 A 29-Aug-13 A 09-Aug-13 29-Aug-13 -5

A2230 Distribution Panel / MCC Requisition 15 100% 13-Aug-13 A 11-Sep-13 A 16-Aug-13 06-Sep-13 -6

A2250 Transformer Requisition 15 100% 01-Aug-13 A 22-Aug-13 A 04-Sep-13 24-Sep-13 0

A2260 UPS Requisition 15 100% 20-Aug-13 A 11-Sep-13 A 16-Aug-13 06-Sep-13 -2

A2270 ATS Requisition 15 100% 08-Aug-13 A 29-Aug-13 A 16-Aug-13 06-Sep-13 0

A2280 200 A Breakers Requisition 15 100% 20-Aug-13 A 11-Sep-13 A 16-Aug-13 06-Sep-13 -2

A2300 SKM Calculations 11 100% 11-Jul-13 A 11-Oct-13 A 25-Jul-13 08-Aug-13 -56

A2310 Load Study 7 100% 27-Jun-13 A 22-Jul-13 A 15-Jul-13 23-Jul-13 -10

A2320 Cable Sizing 21 100% 20-Aug-13 A 17-Oct-13 A 26-Aug-13 24-Sep-13 -21

A2340 Emergency Generator TBE 5 100% 26-Sep-13 A 26-Nov-13 A 15-Aug-13 21-Aug-13 -38

A2440 Review IFC Package 71 0% 03-Dec-13 14-Mar-14 16-Aug-13 06-Sep-13 -59

A2470 Distribution Panel / MCC TBE 5 0% 02-Oct-13 A 09-Dec-13 27-Sep-13 27-Sep-13 -49

A2680 UPS TBE 4 0% 02-Oct-13 A 09-Dec-13 15-Jul-13 02-Aug-13 -34

A2690 ATS TBE 6 100% 26-Sep-13 A 23-Oct-13 A 19-Aug-13 23-Aug-13 -14

19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04June July August September October November December January February March April May

2013 2014

Soil Erosion & Sediments and Control Details

Foundation Plans & Details

Fencing/Grading Details

Finalize IFC Drawings14-Mar-14, Electrical (PL, MLV1, MLV2)

Electrical Plans & Details

Finalize IFC Drawings14-Mar-14, Instrumentation (PL, MLV1, MLV2)

Finalize IFC Drawings

Wiring Diagrams14-Mar-14, CPG Nuevo Pemex Interconnect

14-Mar-14, Engineering (Interconnect)

14-Mar-14, Mechanical/Piping (Interconnect)

Flow Control Valves Skid Requisition

Flow Control Valves Skid TBE

Review IFC Package14-Mar-14, Civil/Structural (Interconnect)

Review IFC Package

Flow Control Valve Skid Foundation Calculation

Engineered Pipe Supports Requisition

Engineered Pipe Supports TBE

Vault Foundation Calculation

14-Mar-14, Design (Interconnect)

14-Mar-14, Mechanical/Piping (Interconnect)

PFD / P&IDs (IFCA)

Piping Plot Plan (IFCA)

Piping Plans, Sections, Details

Piping Isometric Drawings

Finalize IFC Drawings

Finalize Piping Plot Plan14-Mar-14, Civil/Structural (Interconnect)

Site Fence & Grading Plan

Pipe Support Details

Hot Tap Vault Details

Typical Details

Finalize IFC Drawings

14-Mar-14, Nuevo Pemex Meter Station - EM#2

14-Mar-14, Engineering (EM#2)

14-Mar-14, Mechanical/Piping (EM#2)

Line Sizing Calculations

Cathodic Protection Design

Valve List

Small Pipe & Fittings RequisitionLarge Pipe and Fittings Requisition

Large Pipe and Fittings TBE

Restriction Orifice Sizing Calculation

Equipment List

Line List

Review IFC PackageSmall Pipe & Fittings TBE

14-Mar-14, Civil/Structural (EM#2)

Analyzer Building Foundation Calculation

Filter/Scrubber Skid Foundation Calculation

Meter Skid Foundation Calculation

Misc. Equipment Foundation Calculations

Emergeny Generator Foundation Calculation

Engineered Pipe Supports TBE

Review IFC Package

Engineered Pipe Supports Requisition14-Mar-14, Electrical (EM#2)

Emergency Generator Requisition

Distribution Panel / MCC Requisition

Transformer Requisition

UPS Requisition

ATS Requisition

200 A Breakers Requisition

SKM Calculations

Load Study

Cable Sizing

Emergency Generator TBE

Review IFC Package

Distribution Panel / MCC TBE

UPS TBE

ATS TBE

Page 4: GULF Schedule

Activity ID Activity Name OriginalDuration

Activity %Complete

Start Finish BL1 Start BL1 Finish Variance -BL1

DurationA2710 200 A Breakers TBE 4 0% 02-Oct-13 A 09-Dec-13 09-Oct-13 15-Oct-13 -44

A2720 Lighting Requisition 5 0% 26-Sep-13 A 12-Dec-13 03-Sep-13 09-Sep-13 -51

A2950 Transformer TBE 6 100% 26-Sep-13 A 18-Oct-13 A -16

Instrumentation (EM#2)Instrumentation (EM#2) 183 03-Jul-13 A 14-Mar-14 03-Jul-13 20-Sep-13 -125

A2350 Instrument Index 8 100% 03-Jul-13 A 18-Jul-13 A 03-Jul-13 15-Jul-13 -3

A2360 I/O List 13 100% 16-Jul-13 A 18-Jul-13 A 16-Jul-13 01-Aug-13 11

A2460 Review IFC Package 71 0% 03-Dec-13 14-Mar-14 09-Sep-13 20-Sep-13 -64

Design (EM#2)Design (EM#2) 195 17-Jun-13 A 14-Mar-14 17-Jun-13 15-Oct-13 -108

Mechanical/Piping (EM#2)Mechanical/Piping (EM#2) 195 17-Jun-13 A 14-Mar-14 17-Jun-13 15-Oct-13 -108

A1900 PFD / P&IDs (IFCA) 17 100% 17-Jun-13 A 23-Jul-13 A 17-Jun-13 10-Jul-13 -9

A1910 Piping Plot Plan (IFCA) 22 100% 17-Jun-13 A 18-Jul-13 A 17-Jun-13 17-Jul-13 -1

A1930 Piping Plans, Sections, Details 28 100% 19-Aug-13 A 12-Nov-13 A 15-Aug-13 24-Sep-13 -34

A1940 Piping Isometric Drawings 10 0% 22-Oct-13 A 14-Mar-14 25-Sep-13 08-Oct-13 -94

A2570 Finalize IFC Drawings 71 0% 03-Dec-13 14-Mar-14 25-Sep-13 15-Oct-13 -59

A5070 Finalize Piping Plot Plan 20 100% 18-Jul-13 A 15-Aug-13 A 18-Jul-13 14-Aug-13 0

Civil/Structural (EM#2)Civil/Structural (EM#2) 180 24-Jun-13 A 14-Mar-14 08-Jul-13 15-Oct-13 -118

A2040 Foundation Plans & Details 30 100% 24-Jun-13 A 12-Nov-13 A 08-Jul-13 16-Aug-13 -72

A2050 Steel Plans & Details 18 100% 19-Aug-13 A 12-Nov-13 A 29-Aug-13 24-Sep-13 -44

A2060 Sedimentation and Erosion Control Details 36 100% 29-Jul-13 A 12-Nov-13 A 29-Jul-13 24-Sep-13 -36

A2070 Site Plan 51 100% 02-Jul-13 A 12-Nov-13 A 15-Jul-13 24-Sep-13 -45

A2080 Grading & Drainage Plan 35 100% 15-Jul-13 A 12-Nov-13 A 15-Jul-13 30-Aug-13 -52

A2090 Typical Details 49 100% 24-Jun-13 A 12-Nov-13 A 09-Jul-13 16-Sep-13 -53

A2100 Foundation Location Plan 36 100% 19-Aug-13 A 12-Nov-13 A 01-Aug-13 24-Sep-13 -24

A2110 Finalize IFC Drawings 71 0% 03-Dec-13 14-Mar-14 25-Sep-13 15-Oct-13 -59

Electrical (EM#2)Electrical (EM#2) 178 25-Jun-13 A 14-Mar-14 10-Jul-13 15-Oct-13 -119

A2370 Conduit & Cable Schedule 46 100% 05-Aug-13 A 12-Nov-13 A 10-Jul-13 24-Sep-13 -18

A2390 Area Classification Plan & Details 24 100% 03-Jul-13 A 12-Nov-13 A 21-Aug-13 24-Sep-13 -71

A2400 One Line Diagrams 54 100% 25-Jun-13 A 29-Jul-13 A 10-Jul-13 24-Sep-13 30

A2420 Electrical Details 46 100% 03-Jul-13 A 12-Nov-13 A 22-Jul-13 24-Sep-13 -49

A2430 Electrical Plans 31 100% 19-Aug-13 A 12-Nov-13 A 22-Jul-13 24-Sep-13 -16

A2490 Finalize IFC Drawings 71 0% 03-Dec-13 14-Mar-14 25-Sep-13 15-Oct-13 -59

Instrumentation (EM#2)Instrumentation (EM#2) 167 25-Jul-13 A 14-Mar-14 30-Jul-13 15-Oct-13 -111

A2500 Wiring Diagrams 31 100% 25-Jul-13 A 12-Nov-13 A 30-Jul-13 24-Sep-13 -39

A2930 Finalize IFC Drawings 71 0% 03-Dec-13 14-Mar-14 25-Sep-13 15-Oct-13 -59

Macuspana Meter Station - EM#3Macuspana Meter Station - EM#3 195 17-Jun-13 A 14-Mar-14 17-Jun-13 15-Oct-13 -108

Engineering (EM#3)Engineering (EM#3) 138 27-Jun-13 A 14-Mar-14 01-Jul-13 11-Oct-13 -112

Mechanical/Piping (EM#3)Mechanical/Piping (EM#3) 120 01-Jul-13 A 14-Mar-14 01-Jul-13 07-Oct-13 -114

A2520 Line Sizing Calculations 69 100% 01-Jul-13 A 23-Aug-13 A 01-Jul-13 07-Oct-13 30

A2530 Cathodic Protection Design 69 88.41% 01-Jul-13 A 12-Dec-13 01-Jul-13 07-Oct-13 -50

A2540 Valve List 56 89.29% 15-Jul-13 A 10-Dec-13 15-Jul-13 01-Oct-13 -51

A3370 Pressure Regulating Skid Requisition 16 100% 22-Jul-13 A 30-Jul-13 A 15-Jul-13 05-Aug-13 10

A5030 Restriction Orifice Sizing Calculation 13 100% 16-Aug-13 A 19-Nov-13 A 01-Aug-13 21-Aug-13 -52

A5040 Line List 41 82.93% 16-Aug-13 A 11-Dec-13 15-Jul-13 01-Oct-13 -28

A5050 Equipment List 41 82.93% 29-Jul-13 A 11-Dec-13 15-Jul-13 01-Oct-13 -42

A5250 Pressure Regulating Skid TBE 3 100% 28-Aug-13 A 30-Aug-13 A 14-Aug-13 20-Aug-13 2

A5260 Fuel Gas Supply Package Requisition 1 100% 12-Aug-13 A 21-Aug-13 A 31-Jul-13 13-Aug-13 3

A5320 Fuel Gas Supply Package TBE 5 0% 01-Oct-13 A 11-Dec-13 01-Aug-13 14-Aug-13 -42

A5330 Review IFC Package 34 0% 07-Oct-13 A 14-Mar-14 21-Aug-13 21-Aug-13 -115

A5340 Large Pipe and Fittings TBE 1 0% 25-Nov-13 A 12-Dec-13 15-Jul-13 06-Sep-13 25

A5550 Small Pipe & Fittings Requisition 1 100% 20-Aug-13 A 21-Nov-13 A -68

A5580 Small Pipe & Fittings TBE 6 0% 06-Dec-13 13-Dec-13 -6

A5600 Large Pipe and Fittings Requisition 1 100% 19-Aug-13 A 10-Dec-13 A -81

Civil/Structural (EM#3)Civil/Structural (EM#3) 107 20-Aug-13 A 14-Mar-14 06-Aug-13 11-Oct-13 -100

A2700 Engineered Pipe Supports Requisition 15 26.67% 20-Aug-13 A 17-Dec-13 04-Sep-13 24-Sep-13 -71

A2970 Engineered Pipe Supports TBE 3 0% 06-Jan-14 08-Jan-14 -3

A3000 Review IFC Package 22 0% 07-Oct-13 A 14-Mar-14 19-Aug-13 10-Sep-13 -99

A5170 Filters/Scrubber Skid Foundation Calculation 5 0% 20-Aug-13 A 20-Dec-13 06-Aug-13 12-Aug-13 -84

A5190 Pressure Regulating Skid Foundation Calculation 5 0% 20-Aug-13 A 10-Dec-13 04-Sep-13 10-Sep-13 -76

A5200 Misc. Equipment Foundation Calculations 10 0% 20-Aug-13 A 20-Dec-13 18-Sep-13 01-Oct-13 -79

A5210 Emergency Generator Foundation Calculation 24 41.67% 20-Aug-13 A 20-Dec-13 16-Sep-13 20-Sep-13 -84

A5220 Analyzer Building Foundation Calculation 5 0% 20-Aug-13 A 20-Dec-13 07-Oct-13 11-Oct-13 -84

A5230 Meter Skid Foundation Calculation 5 0% 20-Aug-13 A 20-Dec-13 17-Sep-13 23-Sep-13 -84

Electrical (EM#3)Electrical (EM#3) 108 27-Jun-13 A 14-Mar-14 08-Jul-13 30-Sep-13 -126

A2740 Emergency Generator Requisition 15 100% 26-Jul-13 A 22-Aug-13 A 26-Jul-13 15-Aug-13 -4

A2750 Distribution Panel / MCC Requisition 15 100% 30-Jul-13 A 11-Sep-13 A 16-Aug-13 06-Sep-13 -17

A2770 Transformer Requisition 15 100% 01-Aug-13 A 22-Aug-13 A 20-Aug-13 10-Sep-13 0

A2780 UPS Requisition 15 100% 07-Aug-13 A 11-Sep-13 A 16-Aug-13 06-Sep-13 -10

A2790 ATS Requisition 15 100% 07-Aug-13 A 27-Aug-13 A 16-Aug-13 06-Sep-13 1

A2800 100 A Breakers Requisition 15 100% 07-Aug-13 A 11-Sep-13 A 16-Aug-13 06-Sep-13 -10

A2820 SKM Calculations 11 100% 11-Jul-13 A 11-Oct-13 A 11-Jul-13 25-Jul-13 -56

A2830 Load Study 7 100% 27-Jun-13 A 22-Jul-13 A 08-Jul-13 16-Jul-13 -10

A2840 Cable Sizing 20 100% 12-Aug-13 A 08-Oct-13 A 12-Aug-13 09-Sep-13 -21

A2880 Review IFC Package 34 0% 07-Oct-13 A 14-Mar-14 15-Jul-13 06-Sep-13 -76

19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04June July August September October November December January February March April May

2013 2014

200 A Breakers TBE

Lighting RequisitionTransformer TBE

14-Mar-14, Instrumentation (EM#2)

Instrument Index

I/O List

Review IFC Package14-Mar-14, Design (EM#2)

14-Mar-14, Mechanical/Piping (EM#2)

PFD / P&IDs (IFCA)

Piping Plot Plan (IFCA)

Piping Plans, Sections, Details

Piping Isometric Drawings

Finalize IFC Drawings

Finalize Piping Plot Plan14-Mar-14, Civil/Structural (EM#2)

Foundation Plans & Details

Steel Plans & Details

Sedimentation and Erosion Control Details

Site Plan

Grading & Drainage Plan

Typical Details

Foundation Location Plan

Finalize IFC Drawings14-Mar-14, Electrical (EM#2)

Conduit & Cable Schedule

Area Classification Plan & Details

One Line Diagrams

Electrical Details

Electrical Plans

Finalize IFC Drawings14-Mar-14, Instrumentation (EM#2)

Wiring Diagrams

Finalize IFC Drawings14-Mar-14, Macuspana Meter Station - EM#3

14-Mar-14, Engineering (EM#3)

14-Mar-14, Mechanical/Piping (EM#3)

Line Sizing Calculations

Cathodic Protection Design

Valve List

Pressure Regulating Skid Requisition

Restriction Orifice Sizing Calculation

Line List

Equipment List

Pressure Regulating Skid TBE

Fuel Gas Supply Package Requisition

Fuel Gas Supply Package TBE

Review IFC Package

Large Pipe and Fittings TBESmall Pipe & Fittings Requisition

Small Pipe & Fittings TBE

Large Pipe and Fittings Requisition

14-Mar-14, Civil/Structural (EM#3)

Engineered Pipe Supports RequisitionEngineered Pipe Supports TBE

Review IFC Package

Filters/Scrubber Skid Foundation Calculation

Pressure Regulating Skid Foundation Calculation

Misc. Equipment Foundation Calculations

Emergency Generator Foundation Calculation

Analyzer Building Foundation Calculation

Meter Skid Foundation Calculation14-Mar-14, Electrical (EM#3)

Emergency Generator Requisition

Distribution Panel / MCC Requisition

Transformer Requisition

UPS Requisition

ATS Requisition

100 A Breakers Requisition

SKM Calculations

Load Study

Cable Sizing

Review IFC Package

Page 5: GULF Schedule

Activity ID Activity Name OriginalDuration

Activity %Complete

Start Finish BL1 Start BL1 Finish Variance -BL1

DurationA2980 Emergency Generator TBE 6 100% 26-Sep-13 A 26-Nov-13 A -43

A3030 Distribution Panel / MCC TBE 5 0% 02-Oct-13 A 09-Dec-13 26-Aug-13 30-Aug-13 -44

A3050 UPS TBE 5 0% 02-Oct-13 A 09-Dec-13 12-Aug-13 16-Aug-13 -44

A3070 ATS TBE 6 100% 26-Sep-13 A 31-Oct-13 A 19-Aug-13 23-Aug-13 -21

A3090 100 A Breakers TBE 5 0% 02-Oct-13 A 09-Dec-13 24-Sep-13 30-Sep-13 -44

A3100 Transformer TBE 6 100% 26-Sep-13 A 18-Oct-13 A -17

A3110 Lighting Requisition 5 100% 26-Sep-13 A 12-Nov-13 A 16-Jul-13 29-Jul-13 -24

Instrumentation (EM#3)Instrumentation (EM#3) 111 03-Jul-13 A 14-Mar-14 03-Jul-13 01-Aug-13 -161

A2850 Instrument Index 8 100% 03-Jul-13 A 18-Jul-13 A 03-Jul-13 15-Jul-13 -3

A2860 I/O List 13 100% 16-Jul-13 A 18-Jul-13 A 16-Jul-13 01-Aug-13 11

A2940 Review IFC Package 34 0% 07-Oct-13 A 14-Mar-14 -115

Design (EM#3)Design (EM#3) 195 17-Jun-13 A 14-Mar-14 17-Jun-13 15-Oct-13 -108

Mechanical/Piping (EM#3)Mechanical/Piping (EM#3) 195 17-Jun-13 A 14-Mar-14 17-Jun-13 15-Oct-13 -108

A2550 PFD / P&IDs (IFCA) 17 100% 17-Jun-13 A 23-Jul-13 A 17-Jun-13 10-Jul-13 -9

A2560 Piping Plot Plan (IFCA) 22 100% 17-Jun-13 A 18-Jul-13 A 17-Jun-13 17-Jul-13 -1

A2580 Piping Plans, Sections, Details 21 100% 19-Aug-13 A 07-Oct-13 A 01-Aug-13 10-Sep-13 -7

A2590 Piping Isometric Drawings 56 0% 27-Dec-13 14-Mar-14 11-Sep-13 24-Sep-13 -46

A5060 Finalize IFC Drawings 31 0% 07-Oct-13 A 14-Mar-14 11-Sep-13 15-Oct-13 -90

A5080 Finalize Piping Plot Plan 10 100% 18-Jul-13 A 15-Aug-13 A 18-Jul-13 31-Jul-13 -10

Civil/Structural (EM#3)Civil/Structural (EM#3) 109 24-Jun-13 A 14-Mar-14 28-Jun-13 15-Oct-13 -112

A2600 Foundation Plans & Details 30 100% 24-Jun-13 A 24-Oct-13 A 30-Jul-13 10-Sep-13 -58

A2610 Steel Plans & Details 18 100% 19-Aug-13 A 24-Oct-13 A 15-Aug-13 10-Sep-13 -31

A2620 Sedimentation and Erosion Control Details 41 100% 15-Jul-13 A 07-Oct-13 A 15-Jul-13 10-Sep-13 -19

A2630 Site Plan 51 100% 28-Jun-13 A 07-Oct-13 A 28-Jun-13 10-Sep-13 -20

A2640 Grading & Drainage Plan 41 100% 10-Jul-13 A 07-Oct-13 A 15-Jul-13 10-Sep-13 -22

A2650 Typical Details 49 100% 24-Jun-13 A 24-Oct-13 A 02-Jul-13 10-Sep-13 -39

A2660 Foundation Location Plan 26 100% 19-Aug-13 A 07-Oct-13 A 18-Jul-13 10-Sep-13 3

A2670 Finalize IFC Drawings 22 0% 07-Oct-13 A 14-Mar-14 11-Sep-13 15-Oct-13 -90

Electrical (EM#3)Electrical (EM#3) 112 25-Jun-13 A 14-Mar-14 25-Jun-13 15-Oct-13 -108

A2870 Conduit & Cable Schedule 26 100% 19-Aug-13 A 07-Oct-13 A 10-Jul-13 10-Sep-13 9

A2890 Area Classification Plan & Details 24 100% 03-Jul-13 A 07-Oct-13 A 07-Aug-13 10-Sep-13 -44

A2900 One Line Diagrams 54 100% 25-Jun-13 A 29-Jul-13 A 25-Jun-13 10-Sep-13 30

A2910 Electrical Details 46 100% 03-Jul-13 A 07-Oct-13 A 08-Jul-13 10-Sep-13 -22

A2920 Electrical Plans 26 100% 19-Aug-13 A 07-Oct-13 A 22-Jul-13 10-Sep-13 1

A5280 Finalize IFC Drawings 31 0% 07-Oct-13 A 14-Mar-14 11-Sep-13 15-Oct-13 -90

Instrumentation (EM#3)Instrumentation (EM#3) 80 18-Jul-13 A 14-Mar-14 12-Aug-13 15-Oct-13 -125

A2990 Wiring Diagrams 21 100% 18-Jul-13 A 07-Oct-13 A 12-Aug-13 10-Sep-13 -36

A5290 Finalize IFC Drawings 31 0% 07-Oct-13 A 14-Mar-14 11-Sep-13 15-Oct-13 -90

Construction / CommissioningConstruction / Commissioning 12 15-Apr-14 30-Apr-14 -12

CommissioningCommissioning 12 15-Apr-14 30-Apr-14 -12

A5610 Pre-Commissioning / Commissioning Plan 12 0% 15-Apr-14* 30-Apr-14 -12

19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04June July August September October November December January February March April May

2013 2014

Emergency Generator TBE

Distribution Panel / MCC TBE

UPS TBE

ATS TBE

100 A Breakers TBETransformer TBE

Lighting Requisition14-Mar-14, Instrumentation (EM#3)

Instrument Index

I/O ListReview IFC Package

14-Mar-14, Design (EM#3)

14-Mar-14, Mechanical/Piping (EM#3)

PFD / P&IDs (IFCA)

Piping Plot Plan (IFCA)

Piping Plans, Sections, Details

Piping Isometric Drawings

Finalize IFC Drawings

Finalize Piping Plot Plan14-Mar-14, Civil/Structural (EM#3)

Foundation Plans & Details

Steel Plans & Details

Sedimentation and Erosion Control Details

Site Plan

Grading & Drainage Plan

Typical Details

Foundation Location Plan

Finalize IFC Drawings14-Mar-14, Electrical (EM#3)

Conduit & Cable Schedule

Area Classification Plan & Details

One Line Diagrams

Electrical Details

Electrical Plans

Finalize IFC Drawings14-Mar-14, Instrumentation (EM#3)

Wiring Diagrams

Finalize IFC Drawings30-Apr-14, Construction / Commissioning

30-Apr-14, Commissioning

Pre-Commissioning / Commissioning Plan