Activity ID Activity Name OriginalDuration
Activity %Complete
Start Finish BL1 Start BL1 Finish Variance -BL1
Duration
Energia Mayakan Pipeline Expansion Project - Detailed E&D - RevisedEnergia Mayakan Pipeline Expansion Project - Detailed E&D - Revised246 22-May-13 A
30-Apr-14 22-May-13 15-Oct-13 -141
MilestonesMilestones 213 22-May-13 A 14-Mar-14 22-May-13 15-Oct-13 -108
A1000 Limited Notice to Proceed (LNTP) 0 100% 22-May-13 A 22-May-13 0
A1010 Full Notice to Proceed (FNTP) 0 100% 17-Jun-13 A 17-Jun-13 0
A1020 Project Kick-off Meeting 0 100% 22-May-13 A 22-May-13 0
A1030 LNTP Deliverables Issued 0 100% 14-Jun-13 A 14-Jun-13 0
A1040 Detail Engineering & Design Schedule 0 100% 11-Jul-13 A 11-Jul-13 0
A1050 Receive 100% Survey Data for Pipeline Cooridor 0 0% 03-Dec-13* 19-Jul-13 0
A1060 Issue Drawings for Client Review - EM#2 0 100% 12-Nov-13 A 24-Sep-13 0
A1070 Issue for Construction Drawings - All Drawings 0 0% 14-Mar-14* 15-Oct-13 0
A1080 Issue SCADA Specification 0 100% 23-Jul-13 A 31-Jul-13 0
A1090 Issue Preliminary Plot Plans 0 100% 18-Jul-13 A 17-Jul-13 0
A1170 Issue Drawings for Client Review - Pipeline, MLV#1, MLV#2 0 0% 06-Mar-14 24-Sep-13 0
A1180 Issue Drawings for Client Review - EM#3 0 100% 24-Oct-13 A 10-Sep-13 0
A1190 Issue Drawings for Client Review - Interconnect 0 100% 12-Nov-13 A 17-Sep-13 0
Engineering, Design and ProcurementEngineering, Design and Procurement 213 22-May-13 A 14-Mar-14 22-May-13 15-Oct-13 -108
Limited Notice to Proceed (LNTP)Limited Notice to Proceed (LNTP) 18 22-May-13 A 14-Jun-13 A 22-May-13 14-Jun-13 0
Project Management / Project EngineeringProject Management / Project Engineering 18 22-May-13 A 14-Jun-13 A 22-May-13 14-Jun-13 0
A1100 Mobilization of Project Team Personnel and famil iari zati on of FEED documents3 100% 22-May-13 A 24-May-13 A 22-May-13 24-May-13 0
A1120 Design Basis Manual 17 100% 22-May-13 A 14-Jun-13 A 22-May-13 14-Jun-13 -1
PipelinePipeline 15 22-May-13 A 11-Jun-13 A 22-May-13 11-Jun-13 0
A1110 Survey Specification 7 100% 22-May-13 A 31-May-13 A 22-May-13 31-May-13 -1
A1130 Preliminary Hydraulic Analysis 11 100% 22-May-13 A 06-Jun-13 A 22-May-13 06-Jun-13 -1
A1150 Preliminary Pipe/Costing Requisition 7 100% 03-Jun-13 A 11-Jun-13 A 03-Jun-13 11-Jun-13 0
Mechanical / PipingMechanical / Piping 18 22-May-13 A 14-Jun-13 A 22-May-13 14-Jun-13 0
A1140 Preliminary P&IDs 17 100% 22-May-13 A 14-Jun-13 A 22-May-13 14-Jun-13 -1
Full Notice to Proceed (FNTP)Full Notice to Proceed (FNTP) 201 07-Jun-13 A 14-Mar-14 07-Jun-13 15-Oct-13 -108
GeneralGeneral 201 07-Jun-13 A 14-Mar-14 07-Jun-13 14-Oct-13 -109
Project Management (General)Project Management (General) 201 07-Jun-13 A 14-Mar-14 07-Jun-13 09-Aug-13 -155
A1220 Pipeline Cooridor Survey - By Arendal 11 90.91% 07-Jun-13 A 03-Dec-13 07-Jun-13 21-Jun-13 -117
A1230 Detail Engineering and Design Schedule 19 100% 07-Jun-13 A 11-Jul-13 A 07-Jun-13 03-Jul-13 -6
A1380 Facilities Survey 15 100% 07-Jun-13 A 19-Jul-13 A 07-Jun-13 27-Jun-13 -16
A1440 Site Visit 5 100% 24-Jun-13 A 28-Jun-13 A 24-Jun-13 28-Jun-13 0
A1790 Formal Client HAZOP 2 100% 05-Aug-13 A 06-Aug-13 A 30-Jul-13 31-Jul-13 0
A1800 Review IFC Package 21 0% 14-Feb-14 14-Mar-14 29-Jul-13 09-Aug-13 -11
A1860 Internal HAZOP 1 100% 16-Jul-13 A 16-Jul-13 A 16-Jul-13 16-Jul-13 0
Engineering (General)Engineering (General) 146 07-Jun-13 A 30-Dec-13 07-Jun-13 14-Oct-13 -55
Mechanical/Piping (General)Mechanical/Piping (General) 135 24-Jun-13 A 30-Dec-13 24-Jun-13 14-Oct-13 -55
A1980 Stress Analysis 16 0% 03-Dec-13* 27-Dec-13 01-Aug-13 30-Aug-13 3
A1990 Filters/Separator Skids Requisition 15 100% 24-Jun-13 A 16-Jul-13 A 24-Jun-13 15-Jul-13 -1
A2010 Meter Skid Requisition 16 100% 15-Jul-13 A 05-Aug-13 A 11-Jul-13 01-Aug-13 0
A2030 Condensate Tank Requi sit ion 15 100% 16-Aug-13 A 27-Aug-13 A 05-Aug-13 23-Aug-13 8
A3010 Instrument Gas Posts Requisition 5 100% 02-Aug-13 A 21-Aug-13 A 22-Jul-13 09-Aug-13 2
A3040 Ball Valves Requisition 15 100% 08-Jul-13 A 30-Jul-13 A 29-Jul-13 16-Aug-13 -1
A3060 Plug Valves Requisition 6 100% 26-Jul-13 A 31-Jul-13 A 15-Jul-13 02-Aug-13 12
A3080 Large Pipe and Fittings Requisition 15 100% 19-Aug-13 A 18-Oct-13 A 19-Aug-13 09-Sep-13 -30
A3400 Pressure Safety Valves Requisition 15 100% 20-Aug-13 A 23-Oct-13 A 26-Aug-13 16-Sep-13 -31
A3420 Restriction Orifices Requisition 15 100% 20-Aug-13 A 19-Nov-13 A 26-Aug-13 16-Sep-13 -50
A3440 Valves (6" and Smaller) Requisition 15 100% 15-Aug-13 A 07-Oct-13 A 08-Aug-13 28-Aug-13 -22
A3470 Filters/Separator Skid TBE 5 100% 20-Aug-13 A 27-Aug-13 A 08-Oct-13 14-Oct-13 0
A3480 Check Valves Requisition 15 100% 05-Aug-13 A 20-Aug-13 A 29-Jul-13 16-Aug-13 4
A3490 Ball Valves TBE 5 100% 20-Aug-13 A 13-Sep-13 A 03-Sep-13 09-Sep-13 -14
A3500 Globe Valves Requisition 15 100% 05-Aug-13 A 20-Aug-13 A 29-Jul-13 16-Aug-13 4
A3510 Meter Skid TBE 3 100% 26-Aug-13 A 30-Aug-13 A 03-Sep-13 09-Sep-13 0
A3520 Plug Valves TBE 5 100% 30-Aug-13 A 06-Sep-13 A -6
A3530 Instrument Gas Post TBE 5 100% 01-Oct-13 A 28-Oct-13 A -19
A3540 Condensate Tank TBE 6 16.67% 26-Sep-13 A 09-Dec-13 -53
A3550 Check Valves TBE 5 100% 26-Sep-13 A 02-Oct-13 A -5
A3560 Globe Valves TBE 5 100% 26-Sep-13 A 02-Oct-13 A -5
A3570 Valves (2"-6") TBE 9 0% 28-Oct-13 A 16-Dec-13 -36
19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04June July August September October November December January February March April May
2013 2014
30-Apr-14, Energia Mayakan Pipeline Expansion Project - Detailed E&D - Revised
14-Mar-14, Milestones
Limited Notice to Proceed (LNTP)
Full Notice to Proceed (FNTP)
Project Kick-off Meeting
LNTP Deliverables Issued
Detail Engineering & Design Schedule
Receive 100% Survey Data for Pipeline Cooridor
Issue Drawings for Client Review - EM#2
Issue for Construction Drawings - All Drawings
Issue SCADA Specification
Issue Preliminary Plot Plans
Issue Drawings for Client Review - Pipeline, MLV#1, MLV#2
Issue Drawings for Client Review - EM#3
Issue Drawings for Client Review - Interconnect
14-Mar-14, Engineering, Design and Procurement
14-Jun-13 A, Limited Notice to Proceed (LNTP)
14-Jun-13 A, Project Management / Project Engineering
Mobilization of Project Team Personnel and famil iari zati on of FEED documents
Design Basis Manual11-Jun-13 A, Pipel ine
Survey Specification
Preliminary Hydraulic Analysis
Preliminary Pipe/Costing Requisition14-Jun-13 A, Mechanical / Piping
Preliminary P&IDs14-Mar-14, Full Notice to Proceed (FNTP)
14-Mar-14, General
14-Mar-14, Project Management (General)
Pipeline Cooridor Survey - By Arendal
Detail Engineering and Design Schedule
Facilities Survey
Site Visit
Formal Client HAZOP
Review IFC Package
Internal HAZOP30-Dec-13, Engineering (General)
30-Dec-13, Mechanical/Piping (General)
Stress Analysis
Filters/Separator Skids Requisition
Meter Skid Requisition
Condensate Tank Requi sit ion
Instrument Gas Posts Requisition
Ball Valves Requisition
Plug Valves Requisition
Large Pipe and Fittings Requisition
Pressure Safety Valves Requisition
Restriction Orifices Requisition
Valves (6" and Smaller) Requisition
Filters/Separator Skid TBE
Check Valves Requisition
Ball Valves TBE
Globe Valves Requisition
Meter Skid TBEPlug Valves TBE
Instrument Gas Post TBE
Condensate Tank TBE
Check Valves TBE
Globe Valves TBE
Valves (2"-6") TBE
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
![Page 2: GULF Schedule](https://reader038.vdocument.in/reader038/viewer/2022100501/55cf99f9550346d0339ff58f/html5/thumbnails/2.jpg)
Activity ID Activity Name OriginalDuration
Activity %Complete
Start Finish BL1 Start BL1 Finish Variance -BL1
DurationA3580 Large Pipe and Fittings TBE 11 27.27% 25-Nov-13 A 12-Dec-13 19-Aug-13 30-Aug-13 -4
A3590 Gate Valve 19 100% 09-Aug-13 A 06-Sep-13 A 09-Sep-13 09-Sep-13 -20
A4960 Wall Thickness Calculations 33 100% 01-Jul-13 A 26-Jul-13 A 01-Jul-13 15-Aug-13 13
A4970 Facility Piping Specification 29 100% 08-Jul-13 A 30-Jul-13 A 08-Jul-13 15-Aug-13 13
A4980 Tie-in List 12 100% 12-Sep-13 A 07-Oct-13 A 15-Jul-13 01-Oct-13 39
A4990 Pressure Safety Valves TBE 8 0% 03-Dec-13 12-Dec-13 01-Aug-13 14-Aug-13 2
A5110 Restriction Orifices TBE 5 0% 25-Nov-13 A 30-Dec-13 03-Sep-13 09-Sep-13 -21
Electrical (General)Electrical (General) 50 26-Jul-13 A 23-Oct-13 A 26-Jul-13 27-Sep-13 -17
A1520 Thermoelectric Generators Requisition 15 100% 26-Jul-13 A 28-Aug-13 A 26-Jul-13 15-Aug-13 -8
A2450 Thermoelectric Generators TBE 6 100% 26-Sep-13 A 23-Oct-13 A 23-Sep-13 27-Sep-13 -14
Instrumentation (General)Instrumentation (General) 117 07-Jun-13 A 16-Dec-13 07-Jun-13 07-Oct-13 -50
A1710 SCADA Specification 38 100% 07-Jun-13 A 23-Jul-13 A 07-Jun-13 31-Jul-13 6
A1960 Telecommunications Specification 38 100% 07-Jun-13 A 30-Jul-13 A 08-Jul-13 28-Aug-13 1
A2200 Leak Detection Specification 38 100% 07-Jun-13 A 01-Aug-13 A 08-Jul-13 28-Aug-13 -1
A2410 Instrument Skid Specification 2 100% 08-Jul-13 A 16-Jul-13 A 09-Jul-13 10-Jul-13 -4
A2960 Analyzer Control Building TBE 12 75% 24-Oct-13 A 05-Dec-13 -31
A3140 RTU Requisition 20 100% 01-Aug-13 A 05-Sep-13 A 22-Aug-13 22-Aug-13 -25
A3150 RTU TBE 5 100% 16-Oct-13 A 22-Oct-13 A 26-Aug-13 09-Sep-13 5
A4010 Analyzer Control Building Requisition 39 100% 10-Jul-13 A 11-Sep-13 A 15-Jul-13 06-Sep-13 -6
A4380 Instruments Requisitions 24 100% 08-Jul-13 A 26-Sep-13 A 08-Jul-13 08-Aug-13 -35
A4390 SCADA TBE 5 100% 03-Sep-13 A 10-Sep-13 A 12-Aug-13 07-Oct-13 35
A4400 Leak Detection TBE 5 100% 03-Sep-13 A 10-Sep-13 A 29-Jul-13 09-Sep-13 25
A4410 Telecommunications TBE 5 100% 03-Sep-13 A 10-Sep-13 A 07-Oct-13 07-Oct-13 -5
A4420 Instruments TBE 20 50% 26-Sep-13 A 16-Dec-13 23-Sep-13 27-Sep-13 -53
A5400 SCADA Requisition 1 100% 07-Jun-13 A 19-Aug-13 A -51
A5410 Leak Detection Requisition 1 100% 07-Jun-13 A 19-Aug-13 A -51
A5420 Telecommunications Requisition 1 100% 07-Jun-13 A 19-Aug-13 A -51
Design (General)Design (General) 18 10-Jul-13 A 23-Jul-13 A 08-Jul-13 31-Jul-13 9
Instrumentation (General)Instrumentation (General) 18 10-Jul-13 A 23-Jul-13 A 08-Jul-13 31-Jul-13 9
A3020 SCADA Network Architectural Diagram 18 100% 10-Jul-13 A 23-Jul-13 A 08-Jul-13 31-Jul-13 9
Pipeline, MLV#1, MLV#2Pipeline, MLV#1, MLV#2 195 17-Jun-13 A 14-Mar-14 17-Jun-13 15-Oct-13 -108
Engineering (PL, MLV1, MLV2)Engineering (PL, MLV1, MLV2) 195 17-Jun-13 A 14-Mar-14 17-Jun-13 24-Sep-13 -123
Pipeline (PL, MLV1, MLV2)Pipeline (PL, MLV1, MLV2) 195 17-Jun-13 A 14-Mar-14 17-Jun-13 24-Sep-13 -123
A1390 Mainline Pipe / Coating Requisition 30 100% 17-Jun-13 A 31-Jul-13 A 17-Jun-13 29-Jul-13 -2
A1430 Monolithic Isolation Joint Requisition 24 100% 17-Jun-13 A 18-Jul-13 A 17-Jun-13 19-Jul-13 1
A1460 Cathodic Protection Calculations 46 0% 22-Jul-13 A 14-Mar-14 08-Jul-13 24-Sep-13 -114
A1620 Monolithic Isolation Joint TBE 5 100% 19-Aug-13 A 20-Aug-13 A 13-Aug-13 19-Aug-13 4
A1640 Hinged Closures TBE 12 100% 29-Aug-13 A 20-Sep-13 A 29-Jul-13 09-Aug-13 -6
A1650 Review IFC Package 6 0% 07-Mar-14 14-Mar-14 16-Aug-13 16-Aug-13 -6
A1660 Pig Sig Passage Indicator Requisition 1 100% 30-Sep-13 A 01-Oct-13 A 30-Jul-13 12-Aug-13 9
A1670 Pig Sig Passage Indicator TBE 4 100% 16-Oct-13 A 26-Nov-13 A 19-Aug-13 19-Aug-13 -29
A5300 Hinged Closures Requisition 13 100% 08-Jul-13 A 11-Jul-13 A 25-Jun-13 12-Jul-13 10
Mechanical/Piping (PL, MLV1, MLV2)Mechanical/Piping (PL, MLV1, MLV2) 82 19-Aug-13 A 14-Mar-14 19-Aug-13 30-Aug-13 -140
A3600 Small Pipe and Fittings Requisition 5 100% 18-Nov-13 A 26-Nov-13 A 19-Aug-13 30-Aug-13 4
A3620 Large Pipe and Fittings TBE 1 0% 25-Nov-13 A 12-Dec-13 -14
A5480 Review IFC Package 71 0% 03-Dec-13 14-Mar-14 -74
A5560 Small Pipe & Fitting TBE 8 0% 03-Dec-13 12-Dec-13 -8
A5590 Large Pipe and Fittings Requisition 1 100% 19-Aug-13 A 19-Nov-13 A -66
Civil/Structural (PL, MLV1, MLV2)Civil/Structural (PL, MLV1, MLV2) 73 20-Aug-13 A 14-Mar-14 01-Jul-13 30-Aug-13 -104
A1550 MLV Foundation Calculations 5 0% 20-Aug-13 A 20-Dec-13 26-Aug-13 30-Aug-13 -84
A1610 Review IFC Package 34 0% 07-Oct-13 A 14-Mar-14 01-Jul-13 23-Aug-13 -76
Electrical (PL, MLV1, MLV2)Electrical (PL, MLV1, MLV2) 36 07-Oct-13 A 14-Mar-14 -115
A5490 Review IFC Package 34 0% 07-Oct-13 A 14-Mar-14 -115
Instrumentation (PL, MLV1, MLV2)Instrumentation (PL, MLV1, MLV2) 108 03-Jul-13 A 14-Mar-14 08-Jul-13 20-Sep-13 -128
A5360 Instrument Index 8 100% 03-Jul-13 A 18-Jul-13 A 08-Jul-13 17-Jul-13 -3
A5370 I/O List 13 100% 16-Jul-13 A 18-Jul-13 A 16-Jul-13 01-Aug-13 11
A5380 Review IFC Package 34 0% 07-Oct-13 A 14-Mar-14 09-Sep-13 20-Sep-13 -105
Design (PL, MLV1, MLV2)Design (PL, MLV1, MLV2) 195 17-Jun-13 A 14-Mar-14 17-Jun-13 15-Oct-13 -108
Pipeline (PL, MLV1, MLV2)Pipeline (PL, MLV1, MLV2) 190 24-Jun-13 A 14-Mar-14 24-Jun-13 15-Oct-13 -108
A1360 Construction Alignment Sheets 65 0% 24-Jun-13 A 06-Mar-14 24-Jun-13 24-Sep-13 -119
A1400 HDD Drawings 46 0% 08-Jul-13 A 06-Mar-14 08-Jul-13 24-Sep-13 -118
A1410 Typical Pipeline Drawings/Details 28 35.71% 12-Aug-13 A 31-Dec-13 01-Aug-13 24-Sep-13 -64
A1420 Site Location Maps 28 0% 22-Jul-13 A 06-Mar-14 01-Aug-13 24-Sep-13 -126
A1480 Geotech Testing Locati on Drawi ngs 8 100% 02-Jul-13 A 10-Jul-13 A 02-Jul-13 12-Jul-13 2
A1490 Crossing Drawings 36 0% 01-Aug-13 A 06-Mar-14 15-Jul-13 24-Sep-13 -105
A1510 Class Location Study 64 0% 25-Jun-13 A 06-Mar-14 25-Jun-13 24-Sep-13 -119
A1600 Finalize IFC Drawings 6 0% 07-Mar-14 14-Mar-14 25-Sep-13 15-Oct-13 9
Mechanical/Piping (PL, MLV1, MLV2)Mechanical/Piping (PL, MLV1, MLV2) 195 17-Jun-13 A 14-Mar-14 17-Jun-13 15-Oct-13 -108
A1450 PFD/P&ID (IFCA) 17 100% 17-Jun-13 A 23-Jul-13 A 17-Jun-13 10-Jul-13 -9
A1570 Piping Sections and Details 41 100% 02-Jul-13 A 12-Nov-13 A 15-Jul-13 24-Sep-13 -45
A1580 MLV Assembly Drawing 51 100% 15-Jul-13 A 12-Nov-13 A 15-Jul-13 24-Sep-13 -35
A1760 Finalize IFC Drawings 71 0% 03-Dec-13 14-Mar-14 25-Sep-13 15-Oct-13 -59
A1820 Piping Plot Plan 22 100% 17-Jun-13 A 18-Jul-13 A 08-Jul-13 06-Aug-13 -1
Civil/Structural (PL, MLV1, MLV2)Civil/Structural (PL, MLV1, MLV2) 176 24-Jun-13 A 14-Mar-14 12-Jul-13 15-Oct-13 -122
19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04June July August September October November December January February March April May
2013 2014
Large Pipe and Fittings TBE
Gate Valve
Wall Thickness Calculations
Facility Piping Specification
Tie-in List
Pressure Safety Valves TBE
Restriction Orifices TBE23-Oct-13 A, Electrical (General)
Thermoelectric Generators Requisition
Thermoelectric Generators TBE16-Dec-13, Instrumentation (General)
SCADA Specification
Telecommunications Specification
Leak Detection Specification
Instrument Skid SpecificationAnalyzer Control Building TBE
RTU Requisition
RTU TBE
Analyzer Control Building Requisition
Instruments Requisitions
SCADA TBE
Leak Detection TBE
Telecommunications TBE
Instruments TBESCADA Requisition
Leak Detection Requisition
Telecommunications Requisition
23-Jul-13 A, Design (General)
23-Jul-13 A, Instrumentation (General)
SCADA Network Architectural Diagram14-Mar-14, Pipeline, MLV#1, MLV#2
14-Mar-14, Engineering (PL, MLV1, MLV2)
14-Mar-14, Pipeline (PL, MLV1, MLV2)
Mainline Pipe / Coating Requisition
Monolithic Isolation Joint Requisition
Cathodic Protection Calculations
Monolithic Isolation Joint TBE
Hinged Closures TBE
Review IFC Package
Pig Sig Passage Indicator Requisition
Pig Sig Passage Indicator TBE
Hinged Closures Requisition14-Mar-14, Mechanical/Piping (PL, MLV1, MLV2)
Small Pipe and Fittings RequisitionLarge Pipe and Fittings TBE
Review IFC Package
Small Pipe & Fitting TBE
Large Pipe and Fittings Requisition
14-Mar-14, Civil/Structural (PL, MLV1, MLV2)
MLV Foundation Calculations
Review IFC Package14-Mar-14, Electrical (PL, MLV1, MLV2)
Review IFC Package
14-Mar-14, Instrumentation (PL, MLV1, MLV2)
Instrument Index
I/O List
Review IFC Package14-Mar-14, Design (PL, MLV1, MLV2)
14-Mar-14, Pipeline (PL, MLV1, MLV2)
Construction Alignment Sheets
HDD Drawings
Typical Pipeline Drawings/Details
Site Location Maps
Geotech Testing Locati on Drawi ngs
Crossing Drawings
Class Location Study
Finalize IFC Drawings14-Mar-14, Mechanical/Piping (PL, MLV1, MLV2)
PFD/P&ID (IFCA)
Piping Sections and Details
MLV Assembly Drawing
Finalize IFC Drawings
Piping Plot Plan14-Mar-14, Civil/Structural (PL, MLV1, MLV2)
![Page 3: GULF Schedule](https://reader038.vdocument.in/reader038/viewer/2022100501/55cf99f9550346d0339ff58f/html5/thumbnails/3.jpg)
Activity ID Activity Name OriginalDuration
Activity %Complete
Start Finish BL1 Start BL1 Finish Variance -BL1
DurationA1470 Soil Erosion & Sediments and Control Details 51 100% 15-Jul-13 A 07-Oct-13 A 15-Jul-13 24-Sep-13 -9
A1530 Foundation Plans & Details 16 100% 24-Jun-13 A 07-Oct-13 A 26-Aug-13 17-Sep-13 -59
A1560 Fencing/Grading Details 52 100% 08-Jul-13 A 07-Oct-13 A 12-Jul-13 24-Sep-13 -13
A1750 Finalize IFC Drawings 71 0% 03-Dec-13 14-Mar-14 25-Sep-13 15-Oct-13 -59
Electrical (PL, MLV1, MLV2)Electrical (PL, MLV1, MLV2) 185 03-Jul-13 A 14-Mar-14 01-Jul-13 15-Oct-13 -106
A1590 Electrical Plans & Details 60 100% 03-Jul-13 A 07-Oct-13 A 01-Jul-13 24-Sep-13 -8
A1770 Finalize IFC Drawings 71 0% 03-Dec-13 14-Mar-14 25-Sep-13 15-Oct-13 -59
Instrumentation (PL, MLV1, MLV2)Instrumentation (PL, MLV1, MLV2) 160 24-Jul-13 A 14-Mar-14 08-Jul-13 27-Sep-13 -108
A1780 Finalize IFC Drawings 71 0% 03-Dec-13 14-Mar-14 09-Sep-13 27-Sep-13 -59
A2480 Wiring Diagrams 24 100% 24-Jul-13 A 07-Oct-13 A 08-Jul-13 06-Sep-13 -9
CPG Nuevo Pemex InterconnectCPG Nuevo Pemex Interconnect 195 17-Jun-13 A 14-Mar-14 17-Jun-13 15-Oct-13 -108
Engineering (Interconnect)Engineering (Interconnect) 185 01-Jul-13 A 14-Mar-14 01-Jul-13 16-Sep-13 -129
Mechanical/Piping (Interconnect)Mechanical/Piping (Interconnect) 185 01-Jul-13 A 14-Mar-14 01-Jul-13 16-Sep-13 -129
A2210 Flow Control Valves Skid Requisition 15 100% 01-Jul-13 A 26-Jul-13 A 01-Jul-13 22-Jul-13 -4
A2330 Flow Control Valves Skid TBE 3 100% 28-Aug-13 A 30-Aug-13 A 10-Sep-13 16-Sep-13 2
A2380 Review IFC Package 71 0% 03-Dec-13 14-Mar-14 15-Jul-13 06-Sep-13 -35
Civil/Structural (Interconnect)Civil/Structural (Interconnect) 108 21-Oct-13 A 14-Mar-14 -105
A5500 Review IFC Package 71 0% 03-Dec-13 14-Mar-14 -74
A5510 Flow Control Valve Skid Foundation Calculation 7 0% 21-Oct-13 A 20-Dec-13 -45
A5520 Engineered Pipe Supports Requisition 9 0% 18-Nov-13 A 17-Dec-13 -22
A5530 Engineered Pipe Supports TBE 5 0% 06-Jan-14 10-Jan-14 -5
A5540 Vault Foundation Calculation 10 0% 21-Oct-13 A 20-Dec-13 -45
Design (Interconnect)Design (Interconnect) 195 17-Jun-13 A 14-Mar-14 17-Jun-13 15-Oct-13 -108
Mechanical/Piping (Interconnect)Mechanical/Piping (Interconnect) 195 17-Jun-13 A 14-Mar-14 17-Jun-13 15-Oct-13 -108
A1830 PFD / P&IDs (IFCA) 30 100% 17-Jun-13 A 23-Jul-13 A 17-Jun-13 29-Jul-13 4
A1840 Piping Plot Plan (IFCA) 22 100% 17-Jun-13 A 18-Jul-13 A 17-Jun-13 17-Jul-13 -1
A1850 Piping Plans, Sections, Details 27 100% 19-Aug-13 A 12-Nov-13 A 08-Aug-13 17-Sep-13 -33
A1870 Piping Isometric Drawings 71 0% 03-Dec-13 14-Mar-14 18-Sep-13 01-Oct-13 -64
A1920 Finalize IFC Drawings 71 0% 03-Dec-13 14-Mar-14 18-Sep-13 15-Oct-13 -54
A5090 Finalize Piping Plot Plan 15 100% 18-Jul-13 A 15-Aug-13 A 18-Jul-13 07-Aug-13 -5
Civil/Structural (Interconnect)Civil/Structural (Interconnect) 122 19-Aug-13 A 14-Mar-14 -150
A5430 Site Fence & Grading Plan 1 100% 19-Aug-13 A 12-Nov-13 A -62
A5440 Pipe Support Details 1 100% 19-Aug-13 A 12-Nov-13 A -62
A5450 Hot Tap Vault Details 1 100% 19-Aug-13 A 11-Nov-13 A -61
A5460 Typical Details 1 100% 19-Aug-13 A 12-Nov-13 A -62
A5470 Finalize IFC Drawings 71 0% 03-Dec-13 14-Mar-14 -74
Nuevo Pemex Meter Station - EM#2Nuevo Pemex Meter Station - EM#2 195 17-Jun-13 A 14-Mar-14 17-Jun-13 15-Oct-13 -108
Engineering (EM#2)Engineering (EM#2) 185 27-Jun-13 A 14-Mar-14 01-Jul-13 15-Oct-13 -110
Mechanical/Piping (EM#2)Mechanical/Piping (EM#2) 185 01-Jul-13 A 14-Mar-14 01-Jul-13 07-Oct-13 -114
A1880 Line Sizing Calculations 27 100% 10-Jul-13 A 23-Aug-13 A 08-Jul-13 13-Aug-13 -5
A1890 Cathodic Protection Design 69 0% 01-Jul-13 A 14-Mar-14 01-Jul-13 07-Oct-13 -116
A1950 Valve List 56 91.07% 15-Jul-13 A 09-Dec-13 15-Jul-13 01-Oct-13 -50
A3610 Small Pipe & Fittings Requisition 1 100% 31-Oct-13 A 26-Nov-13 A 09-Sep-13 09-Sep-13 -18
A3630 Large Pipe and Fittings Requisition 1 100% 19-Aug-13 A 18-Nov-13 A -65
A3640 Large Pipe and Fittings TBE 1 0% 25-Nov-13 A 12-Dec-13 -14
A5000 Restriction Orifice Sizing Calculation 13 100% 16-Aug-13 A 19-Nov-13 A 01-Aug-13 21-Aug-13 -52
A5010 Equipment List 41 87.8% 29-Jul-13 A 09-Dec-13 15-Jul-13 01-Oct-13 -40
A5020 Line List 41 87.8% 16-Aug-13 A 09-Dec-13 15-Jul-13 01-Oct-13 -26
A5160 Review IFC Package 71 0% 03-Dec-13 14-Mar-14 24-Sep-13 30-Sep-13 -69
A5570 Small Pipe & Fittings TBE 5 60% 18-Nov-13 A 06-Dec-13 -15
Civil/Structural (EM#2)Civil/Structural (EM#2) 154 20-Aug-13 A 14-Mar-14 10-Jul-13 11-Oct-13 -81
A5100 Analyzer Building Foundation Calculation 5 0% 20-Aug-13 A 20-Dec-13 07-Oct-13 11-Oct-13 -84
A5120 Filter/Scrubber Skid Foundation Calculation 5 0% 20-Aug-13 A 20-Dec-13 13-Aug-13 19-Aug-13 -84
A5130 Meter Skid Foundation Calculation 5 0% 20-Aug-13 A 20-Dec-13 30-Aug-13 06-Sep-13 -84
A5140 Misc. Equipment Foundation Calculations 10 0% 20-Aug-13 A 20-Dec-13 18-Sep-13 01-Oct-13 -79
A5150 Emergeny Generator Foundation Calculation 5 0% 20-Aug-13 A 20-Dec-13 30-Sep-13 04-Oct-13 -84
A5240 Engineered Pipe Supports TBE 2 0% 20-Dec-13 23-Dec-13 10-Jul-13 30-Jul-13 13
A5270 Review IFC Package 71 0% 03-Dec-13 14-Mar-14 20-Aug-13 20-Aug-13 -74
A5310 Engineered Pipe Supports Requisition 41 80.49% 20-Aug-13 A 12-Dec-13 12-Aug-13 16-Aug-13 -78
Electrical (EM#2)Electrical (EM#2) 175 27-Jun-13 A 14-Mar-14 15-Jul-13 15-Oct-13 -120
A2220 Emergency Generator Requisition 15 100% 01-Aug-13 A 29-Aug-13 A 09-Aug-13 29-Aug-13 -5
A2230 Distribution Panel / MCC Requisition 15 100% 13-Aug-13 A 11-Sep-13 A 16-Aug-13 06-Sep-13 -6
A2250 Transformer Requisition 15 100% 01-Aug-13 A 22-Aug-13 A 04-Sep-13 24-Sep-13 0
A2260 UPS Requisition 15 100% 20-Aug-13 A 11-Sep-13 A 16-Aug-13 06-Sep-13 -2
A2270 ATS Requisition 15 100% 08-Aug-13 A 29-Aug-13 A 16-Aug-13 06-Sep-13 0
A2280 200 A Breakers Requisition 15 100% 20-Aug-13 A 11-Sep-13 A 16-Aug-13 06-Sep-13 -2
A2300 SKM Calculations 11 100% 11-Jul-13 A 11-Oct-13 A 25-Jul-13 08-Aug-13 -56
A2310 Load Study 7 100% 27-Jun-13 A 22-Jul-13 A 15-Jul-13 23-Jul-13 -10
A2320 Cable Sizing 21 100% 20-Aug-13 A 17-Oct-13 A 26-Aug-13 24-Sep-13 -21
A2340 Emergency Generator TBE 5 100% 26-Sep-13 A 26-Nov-13 A 15-Aug-13 21-Aug-13 -38
A2440 Review IFC Package 71 0% 03-Dec-13 14-Mar-14 16-Aug-13 06-Sep-13 -59
A2470 Distribution Panel / MCC TBE 5 0% 02-Oct-13 A 09-Dec-13 27-Sep-13 27-Sep-13 -49
A2680 UPS TBE 4 0% 02-Oct-13 A 09-Dec-13 15-Jul-13 02-Aug-13 -34
A2690 ATS TBE 6 100% 26-Sep-13 A 23-Oct-13 A 19-Aug-13 23-Aug-13 -14
19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04June July August September October November December January February March April May
2013 2014
Soil Erosion & Sediments and Control Details
Foundation Plans & Details
Fencing/Grading Details
Finalize IFC Drawings14-Mar-14, Electrical (PL, MLV1, MLV2)
Electrical Plans & Details
Finalize IFC Drawings14-Mar-14, Instrumentation (PL, MLV1, MLV2)
Finalize IFC Drawings
Wiring Diagrams14-Mar-14, CPG Nuevo Pemex Interconnect
14-Mar-14, Engineering (Interconnect)
14-Mar-14, Mechanical/Piping (Interconnect)
Flow Control Valves Skid Requisition
Flow Control Valves Skid TBE
Review IFC Package14-Mar-14, Civil/Structural (Interconnect)
Review IFC Package
Flow Control Valve Skid Foundation Calculation
Engineered Pipe Supports Requisition
Engineered Pipe Supports TBE
Vault Foundation Calculation
14-Mar-14, Design (Interconnect)
14-Mar-14, Mechanical/Piping (Interconnect)
PFD / P&IDs (IFCA)
Piping Plot Plan (IFCA)
Piping Plans, Sections, Details
Piping Isometric Drawings
Finalize IFC Drawings
Finalize Piping Plot Plan14-Mar-14, Civil/Structural (Interconnect)
Site Fence & Grading Plan
Pipe Support Details
Hot Tap Vault Details
Typical Details
Finalize IFC Drawings
14-Mar-14, Nuevo Pemex Meter Station - EM#2
14-Mar-14, Engineering (EM#2)
14-Mar-14, Mechanical/Piping (EM#2)
Line Sizing Calculations
Cathodic Protection Design
Valve List
Small Pipe & Fittings RequisitionLarge Pipe and Fittings Requisition
Large Pipe and Fittings TBE
Restriction Orifice Sizing Calculation
Equipment List
Line List
Review IFC PackageSmall Pipe & Fittings TBE
14-Mar-14, Civil/Structural (EM#2)
Analyzer Building Foundation Calculation
Filter/Scrubber Skid Foundation Calculation
Meter Skid Foundation Calculation
Misc. Equipment Foundation Calculations
Emergeny Generator Foundation Calculation
Engineered Pipe Supports TBE
Review IFC Package
Engineered Pipe Supports Requisition14-Mar-14, Electrical (EM#2)
Emergency Generator Requisition
Distribution Panel / MCC Requisition
Transformer Requisition
UPS Requisition
ATS Requisition
200 A Breakers Requisition
SKM Calculations
Load Study
Cable Sizing
Emergency Generator TBE
Review IFC Package
Distribution Panel / MCC TBE
UPS TBE
ATS TBE
![Page 4: GULF Schedule](https://reader038.vdocument.in/reader038/viewer/2022100501/55cf99f9550346d0339ff58f/html5/thumbnails/4.jpg)
Activity ID Activity Name OriginalDuration
Activity %Complete
Start Finish BL1 Start BL1 Finish Variance -BL1
DurationA2710 200 A Breakers TBE 4 0% 02-Oct-13 A 09-Dec-13 09-Oct-13 15-Oct-13 -44
A2720 Lighting Requisition 5 0% 26-Sep-13 A 12-Dec-13 03-Sep-13 09-Sep-13 -51
A2950 Transformer TBE 6 100% 26-Sep-13 A 18-Oct-13 A -16
Instrumentation (EM#2)Instrumentation (EM#2) 183 03-Jul-13 A 14-Mar-14 03-Jul-13 20-Sep-13 -125
A2350 Instrument Index 8 100% 03-Jul-13 A 18-Jul-13 A 03-Jul-13 15-Jul-13 -3
A2360 I/O List 13 100% 16-Jul-13 A 18-Jul-13 A 16-Jul-13 01-Aug-13 11
A2460 Review IFC Package 71 0% 03-Dec-13 14-Mar-14 09-Sep-13 20-Sep-13 -64
Design (EM#2)Design (EM#2) 195 17-Jun-13 A 14-Mar-14 17-Jun-13 15-Oct-13 -108
Mechanical/Piping (EM#2)Mechanical/Piping (EM#2) 195 17-Jun-13 A 14-Mar-14 17-Jun-13 15-Oct-13 -108
A1900 PFD / P&IDs (IFCA) 17 100% 17-Jun-13 A 23-Jul-13 A 17-Jun-13 10-Jul-13 -9
A1910 Piping Plot Plan (IFCA) 22 100% 17-Jun-13 A 18-Jul-13 A 17-Jun-13 17-Jul-13 -1
A1930 Piping Plans, Sections, Details 28 100% 19-Aug-13 A 12-Nov-13 A 15-Aug-13 24-Sep-13 -34
A1940 Piping Isometric Drawings 10 0% 22-Oct-13 A 14-Mar-14 25-Sep-13 08-Oct-13 -94
A2570 Finalize IFC Drawings 71 0% 03-Dec-13 14-Mar-14 25-Sep-13 15-Oct-13 -59
A5070 Finalize Piping Plot Plan 20 100% 18-Jul-13 A 15-Aug-13 A 18-Jul-13 14-Aug-13 0
Civil/Structural (EM#2)Civil/Structural (EM#2) 180 24-Jun-13 A 14-Mar-14 08-Jul-13 15-Oct-13 -118
A2040 Foundation Plans & Details 30 100% 24-Jun-13 A 12-Nov-13 A 08-Jul-13 16-Aug-13 -72
A2050 Steel Plans & Details 18 100% 19-Aug-13 A 12-Nov-13 A 29-Aug-13 24-Sep-13 -44
A2060 Sedimentation and Erosion Control Details 36 100% 29-Jul-13 A 12-Nov-13 A 29-Jul-13 24-Sep-13 -36
A2070 Site Plan 51 100% 02-Jul-13 A 12-Nov-13 A 15-Jul-13 24-Sep-13 -45
A2080 Grading & Drainage Plan 35 100% 15-Jul-13 A 12-Nov-13 A 15-Jul-13 30-Aug-13 -52
A2090 Typical Details 49 100% 24-Jun-13 A 12-Nov-13 A 09-Jul-13 16-Sep-13 -53
A2100 Foundation Location Plan 36 100% 19-Aug-13 A 12-Nov-13 A 01-Aug-13 24-Sep-13 -24
A2110 Finalize IFC Drawings 71 0% 03-Dec-13 14-Mar-14 25-Sep-13 15-Oct-13 -59
Electrical (EM#2)Electrical (EM#2) 178 25-Jun-13 A 14-Mar-14 10-Jul-13 15-Oct-13 -119
A2370 Conduit & Cable Schedule 46 100% 05-Aug-13 A 12-Nov-13 A 10-Jul-13 24-Sep-13 -18
A2390 Area Classification Plan & Details 24 100% 03-Jul-13 A 12-Nov-13 A 21-Aug-13 24-Sep-13 -71
A2400 One Line Diagrams 54 100% 25-Jun-13 A 29-Jul-13 A 10-Jul-13 24-Sep-13 30
A2420 Electrical Details 46 100% 03-Jul-13 A 12-Nov-13 A 22-Jul-13 24-Sep-13 -49
A2430 Electrical Plans 31 100% 19-Aug-13 A 12-Nov-13 A 22-Jul-13 24-Sep-13 -16
A2490 Finalize IFC Drawings 71 0% 03-Dec-13 14-Mar-14 25-Sep-13 15-Oct-13 -59
Instrumentation (EM#2)Instrumentation (EM#2) 167 25-Jul-13 A 14-Mar-14 30-Jul-13 15-Oct-13 -111
A2500 Wiring Diagrams 31 100% 25-Jul-13 A 12-Nov-13 A 30-Jul-13 24-Sep-13 -39
A2930 Finalize IFC Drawings 71 0% 03-Dec-13 14-Mar-14 25-Sep-13 15-Oct-13 -59
Macuspana Meter Station - EM#3Macuspana Meter Station - EM#3 195 17-Jun-13 A 14-Mar-14 17-Jun-13 15-Oct-13 -108
Engineering (EM#3)Engineering (EM#3) 138 27-Jun-13 A 14-Mar-14 01-Jul-13 11-Oct-13 -112
Mechanical/Piping (EM#3)Mechanical/Piping (EM#3) 120 01-Jul-13 A 14-Mar-14 01-Jul-13 07-Oct-13 -114
A2520 Line Sizing Calculations 69 100% 01-Jul-13 A 23-Aug-13 A 01-Jul-13 07-Oct-13 30
A2530 Cathodic Protection Design 69 88.41% 01-Jul-13 A 12-Dec-13 01-Jul-13 07-Oct-13 -50
A2540 Valve List 56 89.29% 15-Jul-13 A 10-Dec-13 15-Jul-13 01-Oct-13 -51
A3370 Pressure Regulating Skid Requisition 16 100% 22-Jul-13 A 30-Jul-13 A 15-Jul-13 05-Aug-13 10
A5030 Restriction Orifice Sizing Calculation 13 100% 16-Aug-13 A 19-Nov-13 A 01-Aug-13 21-Aug-13 -52
A5040 Line List 41 82.93% 16-Aug-13 A 11-Dec-13 15-Jul-13 01-Oct-13 -28
A5050 Equipment List 41 82.93% 29-Jul-13 A 11-Dec-13 15-Jul-13 01-Oct-13 -42
A5250 Pressure Regulating Skid TBE 3 100% 28-Aug-13 A 30-Aug-13 A 14-Aug-13 20-Aug-13 2
A5260 Fuel Gas Supply Package Requisition 1 100% 12-Aug-13 A 21-Aug-13 A 31-Jul-13 13-Aug-13 3
A5320 Fuel Gas Supply Package TBE 5 0% 01-Oct-13 A 11-Dec-13 01-Aug-13 14-Aug-13 -42
A5330 Review IFC Package 34 0% 07-Oct-13 A 14-Mar-14 21-Aug-13 21-Aug-13 -115
A5340 Large Pipe and Fittings TBE 1 0% 25-Nov-13 A 12-Dec-13 15-Jul-13 06-Sep-13 25
A5550 Small Pipe & Fittings Requisition 1 100% 20-Aug-13 A 21-Nov-13 A -68
A5580 Small Pipe & Fittings TBE 6 0% 06-Dec-13 13-Dec-13 -6
A5600 Large Pipe and Fittings Requisition 1 100% 19-Aug-13 A 10-Dec-13 A -81
Civil/Structural (EM#3)Civil/Structural (EM#3) 107 20-Aug-13 A 14-Mar-14 06-Aug-13 11-Oct-13 -100
A2700 Engineered Pipe Supports Requisition 15 26.67% 20-Aug-13 A 17-Dec-13 04-Sep-13 24-Sep-13 -71
A2970 Engineered Pipe Supports TBE 3 0% 06-Jan-14 08-Jan-14 -3
A3000 Review IFC Package 22 0% 07-Oct-13 A 14-Mar-14 19-Aug-13 10-Sep-13 -99
A5170 Filters/Scrubber Skid Foundation Calculation 5 0% 20-Aug-13 A 20-Dec-13 06-Aug-13 12-Aug-13 -84
A5190 Pressure Regulating Skid Foundation Calculation 5 0% 20-Aug-13 A 10-Dec-13 04-Sep-13 10-Sep-13 -76
A5200 Misc. Equipment Foundation Calculations 10 0% 20-Aug-13 A 20-Dec-13 18-Sep-13 01-Oct-13 -79
A5210 Emergency Generator Foundation Calculation 24 41.67% 20-Aug-13 A 20-Dec-13 16-Sep-13 20-Sep-13 -84
A5220 Analyzer Building Foundation Calculation 5 0% 20-Aug-13 A 20-Dec-13 07-Oct-13 11-Oct-13 -84
A5230 Meter Skid Foundation Calculation 5 0% 20-Aug-13 A 20-Dec-13 17-Sep-13 23-Sep-13 -84
Electrical (EM#3)Electrical (EM#3) 108 27-Jun-13 A 14-Mar-14 08-Jul-13 30-Sep-13 -126
A2740 Emergency Generator Requisition 15 100% 26-Jul-13 A 22-Aug-13 A 26-Jul-13 15-Aug-13 -4
A2750 Distribution Panel / MCC Requisition 15 100% 30-Jul-13 A 11-Sep-13 A 16-Aug-13 06-Sep-13 -17
A2770 Transformer Requisition 15 100% 01-Aug-13 A 22-Aug-13 A 20-Aug-13 10-Sep-13 0
A2780 UPS Requisition 15 100% 07-Aug-13 A 11-Sep-13 A 16-Aug-13 06-Sep-13 -10
A2790 ATS Requisition 15 100% 07-Aug-13 A 27-Aug-13 A 16-Aug-13 06-Sep-13 1
A2800 100 A Breakers Requisition 15 100% 07-Aug-13 A 11-Sep-13 A 16-Aug-13 06-Sep-13 -10
A2820 SKM Calculations 11 100% 11-Jul-13 A 11-Oct-13 A 11-Jul-13 25-Jul-13 -56
A2830 Load Study 7 100% 27-Jun-13 A 22-Jul-13 A 08-Jul-13 16-Jul-13 -10
A2840 Cable Sizing 20 100% 12-Aug-13 A 08-Oct-13 A 12-Aug-13 09-Sep-13 -21
A2880 Review IFC Package 34 0% 07-Oct-13 A 14-Mar-14 15-Jul-13 06-Sep-13 -76
19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04June July August September October November December January February March April May
2013 2014
200 A Breakers TBE
Lighting RequisitionTransformer TBE
14-Mar-14, Instrumentation (EM#2)
Instrument Index
I/O List
Review IFC Package14-Mar-14, Design (EM#2)
14-Mar-14, Mechanical/Piping (EM#2)
PFD / P&IDs (IFCA)
Piping Plot Plan (IFCA)
Piping Plans, Sections, Details
Piping Isometric Drawings
Finalize IFC Drawings
Finalize Piping Plot Plan14-Mar-14, Civil/Structural (EM#2)
Foundation Plans & Details
Steel Plans & Details
Sedimentation and Erosion Control Details
Site Plan
Grading & Drainage Plan
Typical Details
Foundation Location Plan
Finalize IFC Drawings14-Mar-14, Electrical (EM#2)
Conduit & Cable Schedule
Area Classification Plan & Details
One Line Diagrams
Electrical Details
Electrical Plans
Finalize IFC Drawings14-Mar-14, Instrumentation (EM#2)
Wiring Diagrams
Finalize IFC Drawings14-Mar-14, Macuspana Meter Station - EM#3
14-Mar-14, Engineering (EM#3)
14-Mar-14, Mechanical/Piping (EM#3)
Line Sizing Calculations
Cathodic Protection Design
Valve List
Pressure Regulating Skid Requisition
Restriction Orifice Sizing Calculation
Line List
Equipment List
Pressure Regulating Skid TBE
Fuel Gas Supply Package Requisition
Fuel Gas Supply Package TBE
Review IFC Package
Large Pipe and Fittings TBESmall Pipe & Fittings Requisition
Small Pipe & Fittings TBE
Large Pipe and Fittings Requisition
14-Mar-14, Civil/Structural (EM#3)
Engineered Pipe Supports RequisitionEngineered Pipe Supports TBE
Review IFC Package
Filters/Scrubber Skid Foundation Calculation
Pressure Regulating Skid Foundation Calculation
Misc. Equipment Foundation Calculations
Emergency Generator Foundation Calculation
Analyzer Building Foundation Calculation
Meter Skid Foundation Calculation14-Mar-14, Electrical (EM#3)
Emergency Generator Requisition
Distribution Panel / MCC Requisition
Transformer Requisition
UPS Requisition
ATS Requisition
100 A Breakers Requisition
SKM Calculations
Load Study
Cable Sizing
Review IFC Package
![Page 5: GULF Schedule](https://reader038.vdocument.in/reader038/viewer/2022100501/55cf99f9550346d0339ff58f/html5/thumbnails/5.jpg)
Activity ID Activity Name OriginalDuration
Activity %Complete
Start Finish BL1 Start BL1 Finish Variance -BL1
DurationA2980 Emergency Generator TBE 6 100% 26-Sep-13 A 26-Nov-13 A -43
A3030 Distribution Panel / MCC TBE 5 0% 02-Oct-13 A 09-Dec-13 26-Aug-13 30-Aug-13 -44
A3050 UPS TBE 5 0% 02-Oct-13 A 09-Dec-13 12-Aug-13 16-Aug-13 -44
A3070 ATS TBE 6 100% 26-Sep-13 A 31-Oct-13 A 19-Aug-13 23-Aug-13 -21
A3090 100 A Breakers TBE 5 0% 02-Oct-13 A 09-Dec-13 24-Sep-13 30-Sep-13 -44
A3100 Transformer TBE 6 100% 26-Sep-13 A 18-Oct-13 A -17
A3110 Lighting Requisition 5 100% 26-Sep-13 A 12-Nov-13 A 16-Jul-13 29-Jul-13 -24
Instrumentation (EM#3)Instrumentation (EM#3) 111 03-Jul-13 A 14-Mar-14 03-Jul-13 01-Aug-13 -161
A2850 Instrument Index 8 100% 03-Jul-13 A 18-Jul-13 A 03-Jul-13 15-Jul-13 -3
A2860 I/O List 13 100% 16-Jul-13 A 18-Jul-13 A 16-Jul-13 01-Aug-13 11
A2940 Review IFC Package 34 0% 07-Oct-13 A 14-Mar-14 -115
Design (EM#3)Design (EM#3) 195 17-Jun-13 A 14-Mar-14 17-Jun-13 15-Oct-13 -108
Mechanical/Piping (EM#3)Mechanical/Piping (EM#3) 195 17-Jun-13 A 14-Mar-14 17-Jun-13 15-Oct-13 -108
A2550 PFD / P&IDs (IFCA) 17 100% 17-Jun-13 A 23-Jul-13 A 17-Jun-13 10-Jul-13 -9
A2560 Piping Plot Plan (IFCA) 22 100% 17-Jun-13 A 18-Jul-13 A 17-Jun-13 17-Jul-13 -1
A2580 Piping Plans, Sections, Details 21 100% 19-Aug-13 A 07-Oct-13 A 01-Aug-13 10-Sep-13 -7
A2590 Piping Isometric Drawings 56 0% 27-Dec-13 14-Mar-14 11-Sep-13 24-Sep-13 -46
A5060 Finalize IFC Drawings 31 0% 07-Oct-13 A 14-Mar-14 11-Sep-13 15-Oct-13 -90
A5080 Finalize Piping Plot Plan 10 100% 18-Jul-13 A 15-Aug-13 A 18-Jul-13 31-Jul-13 -10
Civil/Structural (EM#3)Civil/Structural (EM#3) 109 24-Jun-13 A 14-Mar-14 28-Jun-13 15-Oct-13 -112
A2600 Foundation Plans & Details 30 100% 24-Jun-13 A 24-Oct-13 A 30-Jul-13 10-Sep-13 -58
A2610 Steel Plans & Details 18 100% 19-Aug-13 A 24-Oct-13 A 15-Aug-13 10-Sep-13 -31
A2620 Sedimentation and Erosion Control Details 41 100% 15-Jul-13 A 07-Oct-13 A 15-Jul-13 10-Sep-13 -19
A2630 Site Plan 51 100% 28-Jun-13 A 07-Oct-13 A 28-Jun-13 10-Sep-13 -20
A2640 Grading & Drainage Plan 41 100% 10-Jul-13 A 07-Oct-13 A 15-Jul-13 10-Sep-13 -22
A2650 Typical Details 49 100% 24-Jun-13 A 24-Oct-13 A 02-Jul-13 10-Sep-13 -39
A2660 Foundation Location Plan 26 100% 19-Aug-13 A 07-Oct-13 A 18-Jul-13 10-Sep-13 3
A2670 Finalize IFC Drawings 22 0% 07-Oct-13 A 14-Mar-14 11-Sep-13 15-Oct-13 -90
Electrical (EM#3)Electrical (EM#3) 112 25-Jun-13 A 14-Mar-14 25-Jun-13 15-Oct-13 -108
A2870 Conduit & Cable Schedule 26 100% 19-Aug-13 A 07-Oct-13 A 10-Jul-13 10-Sep-13 9
A2890 Area Classification Plan & Details 24 100% 03-Jul-13 A 07-Oct-13 A 07-Aug-13 10-Sep-13 -44
A2900 One Line Diagrams 54 100% 25-Jun-13 A 29-Jul-13 A 25-Jun-13 10-Sep-13 30
A2910 Electrical Details 46 100% 03-Jul-13 A 07-Oct-13 A 08-Jul-13 10-Sep-13 -22
A2920 Electrical Plans 26 100% 19-Aug-13 A 07-Oct-13 A 22-Jul-13 10-Sep-13 1
A5280 Finalize IFC Drawings 31 0% 07-Oct-13 A 14-Mar-14 11-Sep-13 15-Oct-13 -90
Instrumentation (EM#3)Instrumentation (EM#3) 80 18-Jul-13 A 14-Mar-14 12-Aug-13 15-Oct-13 -125
A2990 Wiring Diagrams 21 100% 18-Jul-13 A 07-Oct-13 A 12-Aug-13 10-Sep-13 -36
A5290 Finalize IFC Drawings 31 0% 07-Oct-13 A 14-Mar-14 11-Sep-13 15-Oct-13 -90
Construction / CommissioningConstruction / Commissioning 12 15-Apr-14 30-Apr-14 -12
CommissioningCommissioning 12 15-Apr-14 30-Apr-14 -12
A5610 Pre-Commissioning / Commissioning Plan 12 0% 15-Apr-14* 30-Apr-14 -12
19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04June July August September October November December January February March April May
2013 2014
Emergency Generator TBE
Distribution Panel / MCC TBE
UPS TBE
ATS TBE
100 A Breakers TBETransformer TBE
Lighting Requisition14-Mar-14, Instrumentation (EM#3)
Instrument Index
I/O ListReview IFC Package
14-Mar-14, Design (EM#3)
14-Mar-14, Mechanical/Piping (EM#3)
PFD / P&IDs (IFCA)
Piping Plot Plan (IFCA)
Piping Plans, Sections, Details
Piping Isometric Drawings
Finalize IFC Drawings
Finalize Piping Plot Plan14-Mar-14, Civil/Structural (EM#3)
Foundation Plans & Details
Steel Plans & Details
Sedimentation and Erosion Control Details
Site Plan
Grading & Drainage Plan
Typical Details
Foundation Location Plan
Finalize IFC Drawings14-Mar-14, Electrical (EM#3)
Conduit & Cable Schedule
Area Classification Plan & Details
One Line Diagrams
Electrical Details
Electrical Plans
Finalize IFC Drawings14-Mar-14, Instrumentation (EM#3)
Wiring Diagrams
Finalize IFC Drawings30-Apr-14, Construction / Commissioning
30-Apr-14, Commissioning
Pre-Commissioning / Commissioning Plan