    Programme and Planning

    David Hannay

    BAA Project Leader

  • 7/28/2019 H ADB 10 May 07runway Overlay Stanstead

    2/17

    ScopeTime PeriodAccessWorking window

  • 7/28/2019 H ADB 10 May 07runway Overlay Stanstead

    3/17

    New surface 3048m x 60m

    New Pit and Duct system

    New RET New RAT

  • 7/28/2019 H ADB 10 May 07runway Overlay Stanstead

    4/17

    New runway AGL system for October 2006

    Displaced Runway 05 Threshold for Summer 2007

    300m

    New Inset

    Approach lightsAdditional TDZNew Elevated Approach

    plus taxiway lead on/offs and RETILs

    New

    Threshold

  • 7/28/2019 H ADB 10 May 07runway Overlay Stanstead

    5/17

    Summer working

    loss of Cat 3 (April to October) only

    less weather delays (rain/low temperature/fog)better quality

    2 seasons if necessary

    Early start available for off-runway works (February & March)

    Runway possessions to end November

  • 7/28/2019 H ADB 10 May 07runway Overlay Stanstead

    6/17

    Progress

    PreparationSurfacingFinishes

    bufferbuffer

  • 7/28/2019 H ADB 10 May 07runway Overlay Stanstead

    7/17

    Priority to this area

    Phase 1 Monday to WednesdayInitial period

    Phase 2 Saturday and SundayThroughout project

    Phase 3 Monday to WednesdayFinal period

    845m

    845m

    1352m

    Safety area 1900m Active runway

    Active runway Safety area

  • 7/28/2019 H ADB 10 May 07runway Overlay Stanstead

    8/17

    Phase 1 and 2 1st May to 28th June

    Phase 3 and 2 1st July to 13th September

    ch1000 ch1848 ch2530

    ch2530 ch3200 ch4048

    Surfacing 27 shifts(includes taxiways and risk)

    Surfacing 27 shifts(includes taxiways and risk)

    Surfacing continuesfor another 16 shifts

    Surfacing16 shifts

    NB 6 mid-week shifts July 1st to 15th spent elsewhereto allow prepwork to advance in Phase 3

  • 7/28/2019 H ADB 10 May 07runway Overlay Stanstead

    9/17

    Start of shift: 2330 Assemble at Holding Point

    2359 Runway closed; gain access to works 0015 Shortened runway re-opened

    Restraints on activities:

    0230 Complete wet concrete activities 0400 Complete resin type activities 0430 Complete surfacing activity

    End of shift:

    0500 Start runway inspection 0545 Runway closed; lighting changes

    0600 Full length runway opens

  • 7/28/2019 H ADB 10 May 07runway Overlay Stanstead

    10/17

    Prior to April (loss of Cat 3): New pit and duct system from sub-station to runway New pits and ducts along both sides of runway Primary cabling New approach lights for Displaced Threshold off runway

    Following runway downgrade: Core out existing lights (centre line, TDZ and taxiway) Install secondary cabling and support plug for new AGL Install duct in concrete trench to feed and support light bars

    (TDZ, Inset Approach and Displaced Threshold lights)

  • 7/28/2019 H ADB 10 May 07runway Overlay Stanstead

    11/17

  • 7/28/2019 H ADB 10 May 07runway Overlay Stanstead

    12/17

    AGL Light Bars(TDZ,Threshold, Approach, SALs)

  • 7/28/2019 H ADB 10 May 07runway Overlay Stanstead

    13/17

    50mm of existing surface removedand replaced by 50mm new material60m x 45m runway each shift400m x 7.5m shoulder every 2nd week

    existing edge lights left insurface grooved following week

  • 7/28/2019 H ADB 10 May 07runway Overlay Stanstead

    14/17

    Once surfacing activities complete, new AGL potsinstalled on top of concrete plugs.

    Pots aligned and levelled using jig sighted to targetFittings connected to secondary cable stored in plug

    Work in phase 1 continued after phase change,but atweekends only

    Emphasis on returning Cat3for existing runway:

    New centreline lightsNew TDZsExisting Threshold lights(with new fittings)

    Existing Approach lights1 set of lead on/off lightsfor each runway direction

  • 7/28/2019 H ADB 10 May 07runway Overlay Stanstead

    15/17

    transformers installed in pits

    mounted on retractable cageswork ongoing in sub-stationsinstalling regulatorsswitch from old to new edge lightscircuits completed and testedMALMS testing of lightsFlight checks

    CAT 3 returned on 30th Octoberwork continued to 30th Novemberon taxiway lead ons, RETILs etc

  • 7/28/2019 H ADB 10 May 07runway Overlay Stanstead

    16/17

    Works completedby 30th November

    Remaining worksubstantiallycompleteby Dec 21st