h5 wet weather pump station

15
Presentation to Maxwell Place Homeowners Association 1

Upload: vuongdang

Post on 04-Feb-2017

215 views

Category:

Documents


0 download

TRANSCRIPT

Presentation to Maxwell Place Homeowners Association

1

AgendaProject Needs/Benefits

Site PlanConstruction Process

Access at the SiteNoise ReductionEffect on BusinessesCommunications with Residents

Restoration of the SiteOn-going Maintenance ScheduleQuestions

2

Project Needs/Benefits Reduce and Protect Against Flooding

Pump Station Minimizes /Eliminates Street Flooding in Northern Hoboken

Integral Part of Overall Plan (“Rebuild by Design”) to Guard Against Rising Sea Levels/Superstorm Sandy Event

3

Project Needs/BenefitsProvides Maxwell Place Infrastructure with Greater Resiliency

Pump Station Reduces Potential for Backups in Long-Term for Maxwell Place Private System

New Emergency Generator for Backup Power at 11th Street Pump Station

Protects the PSE&G Substation that provides power to Maxwell Place

4

Project Site Plan

5

Construction Process: Noise Reduction Noise Reduction

Hours of Construction Limited to Reduce Community Disruption:

Monday through Friday Only Between Hours of 8 am to 5 pm No Weekend or Off-Hour Construction Activity

No Pile Driving East of Hudson Street Substantially Less Noise without Need for Piles

Limited Truck Traffic Concentrated During Excavation and Concrete

Placement No Need for Constant Trucks In and Out of Site

6

Construction Process: AccessAccess at the Site

Sidewalks South Sidewalk: Open at All Times South Sidewalk: Maintain Drop-Offs for School North Sidewalk: Brief Intervals of Closure Between

Sinatra Drive North and Hudson StreetTraffic

Uninterrupted Access to Parking Garage East-Bound Traffic Lanes (Between Sinatra Drive

North and Hudson Street): Open at All Times West-Bound Traffic Lanes: Temporary Closures

Parking No Street Parking During Construction Hours Parking During Non-Construction Hours & on

Weekends7

Construction Process: BusinessesEffect on Local Businesses

Sidewalk Access Permits Unimpeded Foot Traffic to Local Businesses

Traffic Controls at Site Should Not Impact Businesses Drop-off Point Will Be Maintained During

Construction Parking Access May Have Limited Effect

Parking Garage Access Remains In Place Restrictions on Street Parking May Have Limited

Impact

8

Construction Process: CommunicationsKeeping Residents Informed

Monthly Progress Report Posted on North Hudson Sewerage Authority Website http://www.nhudsonsa.com/

Onsite Construction Field Office Executive Director and Authority Engineer

Available for Update Meetings24/7 Community Outreach Hotline

9

Restoration of SiteStreet

Complete repaving of 11th Street Both Sides Between Sinatra Drive North & Hudson Street

Restoration of Island Landscaping

Blend Covers into Landscape Plan

10

H5 Wet Weather Pump Station Control Vault View

H5 Wet Weather Pump Station View 11th Street from Sinatra Drive North

On-Going MaintenancePump Station

2 Hours Monthly Maintenance VisitsSafety ChecksEquipment Inspection & Preventative

MaintenanceControl Vault

2 Hours Weekly Maintenance VisitsControls CheckPreventative Maintenance

13

ScheduleNovember/December 2014 – Public

AdvertisementJanuary/February 2015 – Contract Award April 2015 – Commence ConstructionFebruary 2016 – Construction CompletedMarch 2016- Ribbon Cutting

14

Questions?

North Hudson Sewerage Authority1600 Adams StreetHoboken, NJ 07030

Phone: (201)-963-4685http://www.nhudsonsa.com/

15