haberfield-presentation on geotechnical investigation& design for piling works

Upload: shakirhamid6687

Post on 04-Nov-2015

8 views

Category:

Documents


0 download

DESCRIPTION

presentation on piling foundation required subsurface investigation

TRANSCRIPT

  • Piling & Deep Foundations 2010

    Geotechnical I ti ti dInvestigation and Design for Piling WorksChris HaberfieldChris Haberfield

    1

  • Outline

    Client Moments Client Moments You get what you pay for Benefits of Doing More Case Studies Closing Remarks

    2

  • Client Moments

    Just do a basic investigation the piling contractors can take the risk

    A primary risk to my project involves the in-ground constructionA primary risk to my project involves the in ground construction

    Can you guys help us out as we have a problem with our foundations ... we have a geotechnical report .. but.....?we have a geotechnical report .. but.....?

    The piling contractor cant install the piles to the design depth in the way I want them to install them

    Geotechnical advice during construction is an expense I dont need the investigation, analysis and design have all been done I dont need construction advice

    The piling contractor is claiming latent conditions can you help

    I must have bored piles on this project, and you cant use bentonite or polymer to install them

    3

  • Client Moments

    You pay for geotechnical advice/investigation one way or another

    I t ki ti h I hI am taking a conservative approach....so I can go cheap on my geotechnical advice/investigation

    It worked down the road so it will work hereIt worked down the road so it will work here

    I want to spend as little money as I can on the foundations as we never see them what we cant see wont hurt us and if it does I can alwayssee them what we can t see won t hurt us .... and if it does I can always go and get decent geotechnical advice/investigation later on

    Your proposal for the geotechnical investigation is too expensive I canYour proposal for the geotechnical investigation is too expensive I can get one from Joe for half the price

    We have to take the cheapest price I know we will pay for it in the endWe have to take the cheapest price I know we will pay for it in the end but that is the policy

    With geotechnical advice/investigation you get what you pay forg g y g y p y4

  • Levels of Geotechnical Input

    Ground investigation, analysis, design, construction services...You get what you pay for...g y p y

    PlatinumPlatinumGoldSilver

    Bronze

    5

  • You get what you pay for !Bronze Silver Gold Platinum

    boreholes > toe depth ofSilver+moreboreholes, Gold+comprehensive

    insitu and laboratoryGroundInvestigation

    shallowboreholesnotestingand/orsampling

    boreholes toedepthofpiles

    SPTtestingIndextesting

    someinsitutestingformodulus,laboratory

    testingforpermeability,modulusandstrength

    insituandlaboratorytestingformodulus,

    strengthandpermeability,staticpileloadtesting

    GeotechnicalEngineer

    LimitedexperienceNonexpert

    ExperiencedLimitedinexpertise

    ExperiencedExpert

    ExperiencedExpert

    DesignG d G i Si ifi E h d i ifi

    gParameters

    Guessed Generic Sitespecific Enhancedsitespecific

    Analysis None EmpiricalSilver+simple

    theoreticalorbasicnumerical modelling

    Gold+advancednumericalmodelling

    numericalmodelling

    Design Rulesofthumb(overlyconservative)

    Empirical,Loadbased,standardindustry

    ImprovedServiceabilitybased

    OptimisedServiceabiltybased

    FoundationsUsuallyoverdesignedMay be impractical

    UsuallyoverdesignedPartiallyoptimiseddesign

    Practical to buildOptimiseddesignPractical to buildFoundations Maybeimpractical

    MaybeunsafeSafe

    PracticaltobuildSafe

    PracticaltobuildSafe

    Risk High Low VeryLow VeryLowCost $50k $80k $120k $250k

    6

  • Implications of Enhanced Geotechnical Input

    How does enhanced geotechnical input help you? g p p y Relatively small increase in initial cost (as % of total foundation cost) Potential significant savings in overall foundation costs due to:

    i. Improved strength reduction factors (AS2159 2009)ii. Improved design parametersiii Improved estimate of foundation performance (design foriii. Improved estimate of foundation performance (design for

    serviceability)iv. Improved confidence (due to ii and iii and reduced risk) allowing

    optimisationv. Reduced duration for foundation works

    Reduction in risk due to improved knowledge Reduction in risk due to improved knowledge

    7

  • Improved Strength Reduction FactorsPiling Code AS2159 2009Piling Code AS2159 2009

    8

  • Hypothetical Example 1

    Simple Geology 30 m compressible soils over weathered rock, high d t t blgroundwater table

    50 No. 1.2 m diameter bored piles, no basement 40 m x 40 m in plan 40 m x 40 m in plan Pile working load of 15 MN

    9

  • Improved Strength Reduction factorsSame Design ParametersSame Design Parameters

    10

  • Improved Parameters, Analysis and Design

    11

  • Pile Construction TimeImproved Parameters, Analysis and DesignImproved Parameters, Analysis and Design

    12

  • Hypothetical Example 2

    Complex Geology e.g. Two separate flows of basalt of variable thi k lit d t t t d b tiff il l ithickness, quality and extent separated by stiff soil over sloping weathered bedrock surface. Bedrock varies in weathering with depth and location and is intersected by dykes. High groundwater table.

    50 No. 1.2 m diameter bored piles, 3 level basement, diaphragm wall 40 m x 40 m in plan

    Pil ki l d f 10 MN t 50 MN Pile working loads from 10 MN to 50 MN

    13

  • Example 2 - Risks and Opportunities

    Risks Opportunities

    ExcavationG d /d i

    Optimised retention system Groundwater/dewatering

    Pile founding levels

    system Optimised pile lengths

    e g piles founding atSi ifi t t iti f Socket lengths - dykes Differential settlement/tilt

    e.g. piles founding at different levels in basalt/bedrock

    Significant opportunities for reducing foundation costs,

    Longer piles Construction difficulties

    Alternative footing systems

    construction time and risk

    Delays Latent conditions

    Shorter construction time

    14

  • Case StudiesCase Studies

    15

  • Case Study 1 Royal Domain Towers, Melbourne

    EW-MW siltstone from f d

    0

    5GARSP - as

    t t d

    0

    5GARSP - as

    t t dsurface - deep weathering

    dykes

    5

    10EW - MW Siltstone/Sandstone

    constructed5

    10EW - MW Siltstone/Sandstone

    constructed

    ~ 85 piles0.75 m to 1.5 m dia

    i bilit l d

    15

    D

    e

    p

    t

    h

    (

    m

    ) Traditional approach15

    D

    e

    p

    t

    h

    (

    m

    ) Traditional approachGold level investigation provided significant

    cost and time savings to projectserviceability loads5 MN to 15 MN

    design pile head ttl t 1 % di

    20

    Saving of 9.5 m

    20

    Saving of 9.5 m

    Benefits - savings 950 m socket length

    950 3 t

    cost and time savings to project

    settlement : 1 % dia2525

    1.2 m dia. pile, SL= 15.3 MN

    950 m3 concrete 1400 m3 spoil $$ + 42 days Additional Cost for

    P t t ti UCS30301.2 m dia. pile, SL 15.3 MN Pressuremeter testing, UCS

    testing, analysis on-site presence

  • Case Study 2 Freshwater Place, Melbourne

    30 m overburden over HW MW ilt t

    1.2 m diameter pile, serviceability load = 27 MN30

    HW-MW siltstone (variable)

    70 x 1.2 m dia. Piles ( l th )

    35 GARSP - as constructed

    (plus others)

    serviceability loads17 MN to 30 MN

    Benefits - savings

    40HW - SW Siltstone /

    Gold level investigation provided significant cost and time savings to project

    design top of socket settlement : 1 % dia

    FE l i

    Benefits savings 900 m socket length 1000 m3 concrete 1500 m3 spoil

    45

    D

    e

    p

    t

    h

    (

    m

    )

    Sandstone

    Traditional approach Saving of up to 17 m

    cost and time savings to project

    FE analysis $$ + 40 days Additional Cost for Pressuremeter testing, UCS

    testing analysis +$20k

    50

    testing, analysis, +$20k on-site presence55

    60

  • Case Study 3 SU Building, Melbourne

    Multi storey building Subsurface stratigraphy weathered siltstoneg p y Recommended Gold level geotechnical investigation. Client wanted

    only to pay for silver (for about $20 k less)Sil i d t f ti d i d di l Silver carried out, footings designed accordingly

    Piling contractor engaged on lump sum price design and construct Golder novated to piling contractor Golder novated to piling contractor Piling contractor requested additional geotech Gold Footings redesigned significant savings to piling contractor (>>$20k) Original client unhappy !!!!!

    The piling contractor saw the benefits of a GoldThe piling contractor saw the benefits of a Gold level investigation and reaped the benefits

  • Case Study 4 - Eureka Tower, Melbourne

    19

  • Case Study 5 - Eureka Tower, Melbourne

  • Inferred Stratigraphy Section AA

    Upper basalt

    Lower basaltLower basalt

    Siltstone

  • Inferred Stratigraphy Section BB

    Upper basaltUpper basalt

    25m

    35 m

    Lower basalt

    Siltstone

  • Limits of basalt

    Upper Basalt

    L B ltLower Basalt

  • CFA and Bored Pile solution

    Gold level investigation provided significant cost and time savings to project and managed g p j g

    the risks of complex ground conditions

  • Case Study 6 Residential Building, Melbourne

    40 level building, small site Subsurface stratigraphy weathered siltstone shallow footings/raftg p y g Recommended Gold level geotechnical investigation. Silver (by others) carried out (for $30 k less), piled footings

    d d t ti l f thi itrecommended not practical for this site. Original Gold investigation carried out to estimate deformation

    propertiesp p Raft footing proposed and built

    Silver investigation provided impractical solution. Gold provided practical footing p p g

    solution at reduced cost and construction time.

  • Case Study 5 Esplanade, Darwin

    Case StudyDarwin

    Deeply weathered phyllite

    Bored piles

    Difficult to sample

    UCS not possibleThe original Silver level investigation did not

    identify the risks Gold level investigationIs(50) < 0.05 MPaPressuremetertesting unsuccessful

    identify the risks. Gold level investigation identified the risks and resulted in significant

    foundation cost and construction time savingsSlakesPDA testing allowed modulus estimate

    foundation cost and construction time savings

    modulus estimate

    Analysis

    Founded on shallow f ifootings

  • Case Study 6 Oracle Towers, Gold Coast

    Two x 40 level towers Stratigraphy 25 m sand, 8 m

    clay, 4 m gravel, hard rock Original design bored pilesTh i i l Sil l l i ti ti t Original design bored piles socketed into rock. Piled raft

    considered but discounted.

    The original Silver level investigation was not sufficient for alternative design options. Gold

    No bored piling rigs available Delay to project start Further borehole test clay

    level investigation allowed alternative footing options to be considered and resulted in Further borehole test clay

    Piled raft using CFA piles Reduction in piling costs and

    options to be considered and resulted in significant foundation cost and construction

    time savingsconstruction time time savings

    27

  • Case Study 6 Nakheel Tower, Dubai

    > 1km high tower Mass > 2,000,000 tonnes, , 90 m diameter 20 m deep basement, 120 m diameter High saline groundwater Soft calcareous rock to 200 m

  • Worlds Tallest Towers

  • Platinum Level Investigation

    Initial investigation Boreholes to 60 m, one borehole to 120 m, lower standard of drilling, laboratory testing only (disturbed samples) Preliminary recommendations piles possibly in excess of 120 m

    d th (t li it ttl t )depth (to limit settlements) Settlement estimate of about 500 mm risk of tilt

    Subsequent InvestigationTh Pl ti l l i ti tiq g Boreholes to 300 m, triple tube coring Extensive laboratory testing for strength, stiffness and constitutive

    behaviour

    The Platinum level investigation gave everyone the confidence that

    Extensive insitu testing including pressuremeter, crosshole seismic, full scale pile load tests and construction trials

    Extensive 3D finite element analysis plus others

    this could be done y p

    Settlement estimate of about 80 mm Basement retention no anchors

    30

  • Footing Layout

    Barrette toe levels

    -55 m DMD

    -60 m DMD

    -79 m DMD

    Barrette sizes

    1 5 m x 2 8 m 1.5 m x 2.8 m

    1.2m x 2.8 m

    Raft thicknesses

    2.5 m

    4.0 m

    6.0 m to 8.0 m

  • Case Study 7 Basement

    2 level basement in alluvium on beach

    Tertiary clay at about 12 m depth Potential buried channels

    S t il t t d i i Secant piles to extend minimum 3 m into tertiary clay

    Additional investigation The original Silver level investigation identified risks but insufficient for design Constructiongrecommended to confirm depth to tertiary clay not done

    Penetration to be confirmed

    risks but insufficient for design. Construction difficulties with increased cost and time followed. Penetration to be confirmed

    during CFA piling Not done - not all piles

    penetrated to tertiary clay Construction issues

    32

  • Concluding Comments

    Numerous examples of the value of better geotechnical investigations But ... Our clients continue to accept lower cost investigationsp g The market is competitive you are not being ripped off. Dont take bids for geotechnical advice based on price look what they

    ff If i i hi h th b bl t h i l i k thoffer. If a price is higher there are probably geotechnical risks the others have not forseen or there is opportunity for significant savings on foundations.

    Be open minded - foundation solution, pile type or installation technique. Some piling methods can be impractical for some ground conditions.

    You get what you pay forYou pay for the ground investigation sooner or laterp y g g

    Thank you33