haberfield-presentation on geotechnical investigation& design for piling works
DESCRIPTION
presentation on piling foundation required subsurface investigationTRANSCRIPT
-
Piling & Deep Foundations 2010
Geotechnical I ti ti dInvestigation and Design for Piling WorksChris HaberfieldChris Haberfield
1
-
Outline
Client Moments Client Moments You get what you pay for Benefits of Doing More Case Studies Closing Remarks
2
-
Client Moments
Just do a basic investigation the piling contractors can take the risk
A primary risk to my project involves the in-ground constructionA primary risk to my project involves the in ground construction
Can you guys help us out as we have a problem with our foundations ... we have a geotechnical report .. but.....?we have a geotechnical report .. but.....?
The piling contractor cant install the piles to the design depth in the way I want them to install them
Geotechnical advice during construction is an expense I dont need the investigation, analysis and design have all been done I dont need construction advice
The piling contractor is claiming latent conditions can you help
I must have bored piles on this project, and you cant use bentonite or polymer to install them
3
-
Client Moments
You pay for geotechnical advice/investigation one way or another
I t ki ti h I hI am taking a conservative approach....so I can go cheap on my geotechnical advice/investigation
It worked down the road so it will work hereIt worked down the road so it will work here
I want to spend as little money as I can on the foundations as we never see them what we cant see wont hurt us and if it does I can alwayssee them what we can t see won t hurt us .... and if it does I can always go and get decent geotechnical advice/investigation later on
Your proposal for the geotechnical investigation is too expensive I canYour proposal for the geotechnical investigation is too expensive I can get one from Joe for half the price
We have to take the cheapest price I know we will pay for it in the endWe have to take the cheapest price I know we will pay for it in the end but that is the policy
With geotechnical advice/investigation you get what you pay forg g y g y p y4
-
Levels of Geotechnical Input
Ground investigation, analysis, design, construction services...You get what you pay for...g y p y
PlatinumPlatinumGoldSilver
Bronze
5
-
You get what you pay for !Bronze Silver Gold Platinum
boreholes > toe depth ofSilver+moreboreholes, Gold+comprehensive
insitu and laboratoryGroundInvestigation
shallowboreholesnotestingand/orsampling
boreholes toedepthofpiles
SPTtestingIndextesting
someinsitutestingformodulus,laboratory
testingforpermeability,modulusandstrength
insituandlaboratorytestingformodulus,
strengthandpermeability,staticpileloadtesting
GeotechnicalEngineer
LimitedexperienceNonexpert
ExperiencedLimitedinexpertise
ExperiencedExpert
ExperiencedExpert
DesignG d G i Si ifi E h d i ifi
gParameters
Guessed Generic Sitespecific Enhancedsitespecific
Analysis None EmpiricalSilver+simple
theoreticalorbasicnumerical modelling
Gold+advancednumericalmodelling
numericalmodelling
Design Rulesofthumb(overlyconservative)
Empirical,Loadbased,standardindustry
ImprovedServiceabilitybased
OptimisedServiceabiltybased
FoundationsUsuallyoverdesignedMay be impractical
UsuallyoverdesignedPartiallyoptimiseddesign
Practical to buildOptimiseddesignPractical to buildFoundations Maybeimpractical
MaybeunsafeSafe
PracticaltobuildSafe
PracticaltobuildSafe
Risk High Low VeryLow VeryLowCost $50k $80k $120k $250k
6
-
Implications of Enhanced Geotechnical Input
How does enhanced geotechnical input help you? g p p y Relatively small increase in initial cost (as % of total foundation cost) Potential significant savings in overall foundation costs due to:
i. Improved strength reduction factors (AS2159 2009)ii. Improved design parametersiii Improved estimate of foundation performance (design foriii. Improved estimate of foundation performance (design for
serviceability)iv. Improved confidence (due to ii and iii and reduced risk) allowing
optimisationv. Reduced duration for foundation works
Reduction in risk due to improved knowledge Reduction in risk due to improved knowledge
7
-
Improved Strength Reduction FactorsPiling Code AS2159 2009Piling Code AS2159 2009
8
-
Hypothetical Example 1
Simple Geology 30 m compressible soils over weathered rock, high d t t blgroundwater table
50 No. 1.2 m diameter bored piles, no basement 40 m x 40 m in plan 40 m x 40 m in plan Pile working load of 15 MN
9
-
Improved Strength Reduction factorsSame Design ParametersSame Design Parameters
10
-
Improved Parameters, Analysis and Design
11
-
Pile Construction TimeImproved Parameters, Analysis and DesignImproved Parameters, Analysis and Design
12
-
Hypothetical Example 2
Complex Geology e.g. Two separate flows of basalt of variable thi k lit d t t t d b tiff il l ithickness, quality and extent separated by stiff soil over sloping weathered bedrock surface. Bedrock varies in weathering with depth and location and is intersected by dykes. High groundwater table.
50 No. 1.2 m diameter bored piles, 3 level basement, diaphragm wall 40 m x 40 m in plan
Pil ki l d f 10 MN t 50 MN Pile working loads from 10 MN to 50 MN
13
-
Example 2 - Risks and Opportunities
Risks Opportunities
ExcavationG d /d i
Optimised retention system Groundwater/dewatering
Pile founding levels
system Optimised pile lengths
e g piles founding atSi ifi t t iti f Socket lengths - dykes Differential settlement/tilt
e.g. piles founding at different levels in basalt/bedrock
Significant opportunities for reducing foundation costs,
Longer piles Construction difficulties
Alternative footing systems
construction time and risk
Delays Latent conditions
Shorter construction time
14
-
Case StudiesCase Studies
15
-
Case Study 1 Royal Domain Towers, Melbourne
EW-MW siltstone from f d
0
5GARSP - as
t t d
0
5GARSP - as
t t dsurface - deep weathering
dykes
5
10EW - MW Siltstone/Sandstone
constructed5
10EW - MW Siltstone/Sandstone
constructed
~ 85 piles0.75 m to 1.5 m dia
i bilit l d
15
D
e
p
t
h
(
m
) Traditional approach15
D
e
p
t
h
(
m
) Traditional approachGold level investigation provided significant
cost and time savings to projectserviceability loads5 MN to 15 MN
design pile head ttl t 1 % di
20
Saving of 9.5 m
20
Saving of 9.5 m
Benefits - savings 950 m socket length
950 3 t
cost and time savings to project
settlement : 1 % dia2525
1.2 m dia. pile, SL= 15.3 MN
950 m3 concrete 1400 m3 spoil $$ + 42 days Additional Cost for
P t t ti UCS30301.2 m dia. pile, SL 15.3 MN Pressuremeter testing, UCS
testing, analysis on-site presence
-
Case Study 2 Freshwater Place, Melbourne
30 m overburden over HW MW ilt t
1.2 m diameter pile, serviceability load = 27 MN30
HW-MW siltstone (variable)
70 x 1.2 m dia. Piles ( l th )
35 GARSP - as constructed
(plus others)
serviceability loads17 MN to 30 MN
Benefits - savings
40HW - SW Siltstone /
Gold level investigation provided significant cost and time savings to project
design top of socket settlement : 1 % dia
FE l i
Benefits savings 900 m socket length 1000 m3 concrete 1500 m3 spoil
45
D
e
p
t
h
(
m
)
Sandstone
Traditional approach Saving of up to 17 m
cost and time savings to project
FE analysis $$ + 40 days Additional Cost for Pressuremeter testing, UCS
testing analysis +$20k
50
testing, analysis, +$20k on-site presence55
60
-
Case Study 3 SU Building, Melbourne
Multi storey building Subsurface stratigraphy weathered siltstoneg p y Recommended Gold level geotechnical investigation. Client wanted
only to pay for silver (for about $20 k less)Sil i d t f ti d i d di l Silver carried out, footings designed accordingly
Piling contractor engaged on lump sum price design and construct Golder novated to piling contractor Golder novated to piling contractor Piling contractor requested additional geotech Gold Footings redesigned significant savings to piling contractor (>>$20k) Original client unhappy !!!!!
The piling contractor saw the benefits of a GoldThe piling contractor saw the benefits of a Gold level investigation and reaped the benefits
-
Case Study 4 - Eureka Tower, Melbourne
19
-
Case Study 5 - Eureka Tower, Melbourne
-
Inferred Stratigraphy Section AA
Upper basalt
Lower basaltLower basalt
Siltstone
-
Inferred Stratigraphy Section BB
Upper basaltUpper basalt
25m
35 m
Lower basalt
Siltstone
-
Limits of basalt
Upper Basalt
L B ltLower Basalt
-
CFA and Bored Pile solution
Gold level investigation provided significant cost and time savings to project and managed g p j g
the risks of complex ground conditions
-
Case Study 6 Residential Building, Melbourne
40 level building, small site Subsurface stratigraphy weathered siltstone shallow footings/raftg p y g Recommended Gold level geotechnical investigation. Silver (by others) carried out (for $30 k less), piled footings
d d t ti l f thi itrecommended not practical for this site. Original Gold investigation carried out to estimate deformation
propertiesp p Raft footing proposed and built
Silver investigation provided impractical solution. Gold provided practical footing p p g
solution at reduced cost and construction time.
-
Case Study 5 Esplanade, Darwin
Case StudyDarwin
Deeply weathered phyllite
Bored piles
Difficult to sample
UCS not possibleThe original Silver level investigation did not
identify the risks Gold level investigationIs(50) < 0.05 MPaPressuremetertesting unsuccessful
identify the risks. Gold level investigation identified the risks and resulted in significant
foundation cost and construction time savingsSlakesPDA testing allowed modulus estimate
foundation cost and construction time savings
modulus estimate
Analysis
Founded on shallow f ifootings
-
Case Study 6 Oracle Towers, Gold Coast
Two x 40 level towers Stratigraphy 25 m sand, 8 m
clay, 4 m gravel, hard rock Original design bored pilesTh i i l Sil l l i ti ti t Original design bored piles socketed into rock. Piled raft
considered but discounted.
The original Silver level investigation was not sufficient for alternative design options. Gold
No bored piling rigs available Delay to project start Further borehole test clay
level investigation allowed alternative footing options to be considered and resulted in Further borehole test clay
Piled raft using CFA piles Reduction in piling costs and
options to be considered and resulted in significant foundation cost and construction
time savingsconstruction time time savings
27
-
Case Study 6 Nakheel Tower, Dubai
> 1km high tower Mass > 2,000,000 tonnes, , 90 m diameter 20 m deep basement, 120 m diameter High saline groundwater Soft calcareous rock to 200 m
-
Worlds Tallest Towers
-
Platinum Level Investigation
Initial investigation Boreholes to 60 m, one borehole to 120 m, lower standard of drilling, laboratory testing only (disturbed samples) Preliminary recommendations piles possibly in excess of 120 m
d th (t li it ttl t )depth (to limit settlements) Settlement estimate of about 500 mm risk of tilt
Subsequent InvestigationTh Pl ti l l i ti tiq g Boreholes to 300 m, triple tube coring Extensive laboratory testing for strength, stiffness and constitutive
behaviour
The Platinum level investigation gave everyone the confidence that
Extensive insitu testing including pressuremeter, crosshole seismic, full scale pile load tests and construction trials
Extensive 3D finite element analysis plus others
this could be done y p
Settlement estimate of about 80 mm Basement retention no anchors
30
-
Footing Layout
Barrette toe levels
-55 m DMD
-60 m DMD
-79 m DMD
Barrette sizes
1 5 m x 2 8 m 1.5 m x 2.8 m
1.2m x 2.8 m
Raft thicknesses
2.5 m
4.0 m
6.0 m to 8.0 m
-
Case Study 7 Basement
2 level basement in alluvium on beach
Tertiary clay at about 12 m depth Potential buried channels
S t il t t d i i Secant piles to extend minimum 3 m into tertiary clay
Additional investigation The original Silver level investigation identified risks but insufficient for design Constructiongrecommended to confirm depth to tertiary clay not done
Penetration to be confirmed
risks but insufficient for design. Construction difficulties with increased cost and time followed. Penetration to be confirmed
during CFA piling Not done - not all piles
penetrated to tertiary clay Construction issues
32
-
Concluding Comments
Numerous examples of the value of better geotechnical investigations But ... Our clients continue to accept lower cost investigationsp g The market is competitive you are not being ripped off. Dont take bids for geotechnical advice based on price look what they
ff If i i hi h th b bl t h i l i k thoffer. If a price is higher there are probably geotechnical risks the others have not forseen or there is opportunity for significant savings on foundations.
Be open minded - foundation solution, pile type or installation technique. Some piling methods can be impractical for some ground conditions.
You get what you pay forYou pay for the ground investigation sooner or laterp y g g
Thank you33