hafencity development, process vs project
DESCRIPTION
Brief description of the development of city-rivitalization HafenCity Hamburg.TRANSCRIPT
19 November 2010 PETER KUIPER
PETER SANDERSSIMON HOITEMABERT LANKHEET
PROCESS MANAGEMENT: ASSIGNMENT I
Development of HafenCity HamburgProcess vs. Project
1/6Development of Hafencity Hamburg - University of Twente
1
Content
Results of assignment 1
Brief historyProblem formulationGoalsInformationDecision makingImplementation
25-04-23Projectgroep 6
2
Brief history
1980s First ideas to revitalize the Hamburg inner-city
1989 Because of the fall of the iron curtain, the port of Hamburg regains his hinterland
Mid 90s Most of the area in hands of Hamburg port & warehouse company (HHLA)
Window of opportunityto present the plans to a broader public
25-04-23Projectgroep 6
3
Problem formulation
Problems Port too small for its new role in international trade Financing a state-of-the-art container terminal Area’s importance as an industrial location continued to
decline The risk of a flood over Hamburg Hamburg needs a economic, social, and cultural boost to
regain popularity Hamburg is not sustainable
Process based problem formulation
4
4/13Measuring the quality of bicycle routes in Pune, India - University of Twente
Goals
1. Goalsa) Revitalize city center
a) Building a container terminalb) Preparing Hamburg for its
new role in Europe
Used goal seeking toolsa) Goal stretchingb) Naming & framing
5
5/13Measuring the quality of bicycle routes in Pune, India - University of Twente
Information
First phase 1991 Mayor Henning Voscherau commissioning a study Plans were kept secret till 1997 1997 Presentation of the plan “HafenCity Vision”
Second phase Green light of city council Involvement of stakeholders Nice-to-know information gathering principle
6
6/13Measuring the quality of bicycle routes in Pune, India - University of Twente
Decision-making
Project-based go ahead
Followed by: Process-based decision making Masterplan decision of senate: ‘’ticking of’’ General plan
Decision making process “Backstage” process-based “Frontstage” project-based
25-04-23Projectgroep 6
7
Implementation
A process-based implementation After the go decision many
aspects of the plan were still open
Concrete results/projects neededproject-based implementation
25-04-23Projectgroep 6
8