haldia refinery project appraisal report
TRANSCRIPT
Sub: Detailed Feasibility Report on "Installation of Facilities for Improvement in
Diesel Quality and Distillate Yield (Hydrocracker) Project at Haldia Refinery.
This Project Evaluation Committee of the Board considered the subject item in its
meeting held on 12th November, 2005.
After deliberations, the Project Evaluation Committee recommended the proposal with
the following resolution to the Board for consideration and approval:-
"RESOLVED THAT approval of the Board be and is hereby accorded to the proposal for
installation of facilities for Hydrocracker Project at Haldia Refinery at an estimated cost
of Rs. 1876 crore (as of July, 2005)."
xxxxxxxxxxx
Sub: Detailed Feasibility Report on "Installation of Facilities for Improvement in
Diesel Quality and Distillate Yield (Hydrocracker) Project at Haldia Refinery.
1.0 Background
1.1 The Board of Directors in its meeting held on 29th November 2000 had accorded 'in-
principle' approval for setting up of facilities for improvement in Diesel Quality and
Distillate Yield at Haldia Refinery at an estimated cost of Rs. 1518 cr. inclusive of foreign
exchange component of Rs. 357.8 cr. based on April 2000 prices, subject to obtaining
Environmental Clearance from MoE&F. The Board had also sanctioned and amount of
Rs. 44 cr. inclusive of a foreign exchange component of Rs. 18 cr. for carrying out pre-
project activities pending Environmental Clearance.
Three major process units, vis., Once Through Hydrocracker Unit (OHCU), Hydrogen
Generation Unit (HGU) and Sulphur Recovery Unit (SRU) were envisaged in the subject
proposal.
Environmental Clearance for the project was received in May'02.
1.2 Subsequently, the Board in its meeting held on 24th April'03 approved the road-map
to meet the quality requirements of HSD & MS and suggested deferment of completion
of Hydrocracker Project at Haldia till January 2010 so as to match with the quality
requirements of April 2010 onwards. Hence, all activities relating to the project were kept
on hold.
1.3 As against the installed crude processing capacity of 6.0 MMTPA
at Haldia Refinery, the operation of last three years has been as
follows.
Particulars 2002-032003-042004-05
Crude Intake, MMTPA 4.51 4.52 5.41
Distillate Yield (excluding LOBS), %w63.23 63.76 62.26
LOBS, TMTPA 124 154 187
(%w on crude) (2.75) (3.41) (3.45)
FO, TMTPA 723 777 961
Bitumen, TMTPA 310 313 415
Fuel & Loss (%w) 10.02 9.98 8.90
As can be seen from above, the distillate yield in the refinery is about 62-63% w on
crude (without LOBS), which is on lower side and needs improvements.
2.0 Quality Road-Map
2.1 As per road-map approved by the Board for quality improvement, the quality of
MS/HSD would have to be upgraded from BS-II/Euro-III levels to Euro-III/Euro-IV levels
by April 2010.
2.2 The refinery would be able to meet the above requirements in respect of MS after
commissioning of the on-going MS Quality Upgradation Project at Haldia. The facilities
are likely to be commissioned by October 2005.
2.3 For meeting HSD quality requirement beyond April 2010, it is
necessary to initiate activities for installation of facilities for HSD
quality improvement. Comparison of key HSD specifications
conforming to the three emissions norms are tabulated below:
Specification BS-II
Eqv.
Euro-III
Eqv.
Euro-IV
Eqv.
Density @ 150C, kg/M3 820.860 820.845 820.845
Sulphur Content, ppmw (max) 500 350 50
Cetane No. (min) 48 51 51
Distillation, 95% vol. (0C max) 370 360 360
Polycyclic Aromatic Hydrocarbons (PAH), %mass
max.
No spec 11 11
2.4 Accordingly, necessary facilities are required to be set up to meet the future
specification of HSD.
3.0 Options for Diesel quality improvement
3.1 The improvement in diesel quality to Euro-III/Euro-IV emission norms can be
achieved by installing a Diesel Hydrotreating (DHDT) Unit. Since the refinery has to
produce Euro-III/Euro-IV conforming diesel w.e.f. April 2010, facilities such as DHDT,
HGU, SRU, GT and other offisite facilities shall be required to be installed at the installed
crude processing capacity, i.e., 6.0 MMTPA.
3.2 The objective of producing HSD meeting Euro-III / Euro-IV equivalent quality
requirements can alternatively be met by installing OHCU and associated facilities, 'in-
principle' approval for which was obtained from the Board in Nov. 2000. This option has
been studies in detail in the present context at a crude throughput level of 7.5 MMTPA
and would facilitate higher crude processing and better distillate yield in addition to
improvement in diesel quality to Euro-III/Euro-IV emission standards.
3.3 Accordingly, a detailed study of the following cases has been carried out:
Installation of DHDT and associated facilities at 6.0 MMTPA (Base Case)
Installation of OHCU and associated facilities at 7.5 MMTPA (Project Case)
3.4 The project cost for DHDT case has been estimated as Rs. 1175
cr. as against Rs. 1876 cr. for OHCU case based on study by the
consultant M/s Lurgi India. A comparison of major facilities envisaged
in the two cases is furnished below:
S. No.Unit Capacity
DHDT CaseOHCU Case
1. OHCU, MMTPA -- 1.7
2. DHDT, MMTPA 1.0 --
3. HGU, TMTPA 18 75
4. AAU/ARU, TPH 77 272
5. SWS, TPH 6 25
6. SRU, TPD 1x60 2x80
7. CDU-II revamp, MMTPA-- from 2.5 to 4.0
4.0 APPROACH FOR TECHNO-ECONOMIC EVALUATION (INTEGRATED
PLANNING MODEL)
The above cases (DHDT and OHCU) were evaluated by integrating with Global IOC
Refining, Pipeline and Marketing networks based on Integrated Planning (IP) Models of
Corporate Optimization (Report attached as Appendix).
4.1 To carry out the above economic evaluation, following Integrated Planning (IP)
Models were developed:
a. Haldia Refinery with DHDT and Crude processing at 6 MMTPA (Base Case)
b. Haldia Refinery with OHCU and Crude processing 7.5 MMTPA (Project Case)
4.2 In all the above models following common considerations were made:
Panipat refinery at 15 MMTPA capacity (P-15)
Koyali refinery at 13.7 MMTPA with Residue Upgradation Project
Mathura with capacity limit of 8.4 MMTPA having Diesel Hydrotreater (DHDT)
and MS Quality Improvement (MSQ) Project in place.
Barauni with capacity limit of 6.0 MMTPA
Chennai with capacity limit of 10.0 MMTPA
North East Refineries operating at existing level
KBPL on crude service
Paradip-Haldia crude Pipeline
Koyali-Dahej Pipeline
Branch lines from KVSS to Ajmer and Chittorgarh
Chennai-Bangalore Pipeline
Panipat-Tikrikalan Pipeline and
Koyali-Ratlam-Itarsi-Khapri with branches to Indore and Nishatpura (with rail
loading facilities at Koyali. Ratlam and Khapri)
Further, since Paradip refinery (15 MMTPA) and the proposed Paradip-Rengali-Korba-
Raipr product PL with the branch from Rengali to Bundu could have an impact on the
subject proposal, impact of the same was also studied. Since the yield of Paradip
refinery also included petrochemicals, the same was however configured as an extreme-
point refinery (fixed Crude processing and fixed yield pattern) in the IP model with crude
mix, product pattern and prices for petrochemicals (IPP as well as EPP) as provided by
Ref. HQ Project.
4.3 Basis Adopted
(A) Demand
Product-wise demands were considered under following scenarios:
Scenario-1 & 4 (Low Demand)
Product-wise demand was considered at the same levels as in the Low-Demand
scenario considered for Gujarat Residue Upgradation Project and P-15, basis of which
was as below:
The demand numbers under this scenario are close to the levels per the outlook
for the year 2005-06.
Demand of Naphtha and FO have been substantially reduced considering the
projections by Corporate Planning regarding switch-over by major customers to
Natural Gas.
As regards LSHS, it has been assumed that the switch-over to gas would not be
major.
Demand of SKO is about 6.7% lower than the current outlook for the year 2005-
06.
Scenario-2 (High Demand)
Demand for 2011-12 for all products as currently projected by Planning Dept., Mktng
HO.
Scenario-3 & 5(Moderate Demand)
Product-wise demand level is similar to the High-Demand scenario considered for the
Gujarat expansion and P-15 study, basis for which is as below:
Growth rite of 10% for HSD and 15% for MS has been applied oil the demand
nos. per Scn-1.
In addition, ATF has also been escalated at 18% over and above the level in
Scn-I
The level of product-wise demand considered under the various
scenarios is provided in the table hereunder. Marketing HO's latest
outlook of product-wise demand for the year 2005-06 has also been
provided therein for the purposes of comparison.
Product
2005-06 Outlook
Demand Adopted in the Study
Scenario-1&4 Scenario-2Scenario-3&5
Comparative level Low High Moderate
MS 3818 3893 5353 4477
HSD 21032 21920 27151 24112
SKO 6313 5888 5211 5888
ATF 2174 2185 2936 2579
Naphtha 2574 907 873 907
FO 4300 3556 5482 3556
LSHS 3413 2571 1274 2571
LDO 667 657 582 657
Bitumen 2323 2475 3143 2475
Flexibility was kept in the model under all the scenarios in respect of meeting of the
LSHS demand, i.e. the model had the option in all cases of not meeting the LSHS
demand (Min. limit of LSHS kept as zero). In other words, LSHS production at the
refineries was based on economics.
(B) Product Exchange & Purchase
For all Scenarios it has been assumed that HPC's proposed Mundra-Delhi
product PL as well as BPC's proposed extension of its Mumbai-Manmad -Indore
product PL to Loni/Piyala would be in place. Gives to HPC and BPC ex-Koyali,
Mathura and Panipat have accordingly been reduced from normal levels
No takes by HPC ex-Haldia has been envisaged under any scenario/case since it
was observed under all the cases and scenarios that the subject expansion of
Haldia refinery/commissioning of the proposed Paradip-Raipur PL/
commissioning of Paradip refinery result in substantial reduction in IOC's takes
(vis-a-vis current levels) ex-HPC's Vizag refinery.
Subject to the above, gives to BPC & HPC ex-all refineries in each scenario are
based on the refinery-wise numbers finalized per the MoU for the quarter Jan-
Mar'06 duly annualized and escalated by the product-wise demand growth rates
adopted for IOC & Associates under the concerned scenario. Exchange of SKO
has been assumed on a tonne-to-tonne basis since no company would be
interested in taking additional SKO from another company.
Refinery-wise takes from BPC & HPC as well as purchases from RIL and ONGC
have been retained at economic levels under all scenarios.
(C) Product Import & Export
Options for imports/ exports kept open at refineries/ ports in the IP
model under all scenarios are detailed hereunder:
Product HaldiaParadipCPCLDahejBarauniPanipatMathuraKandla/IOTL
Export Options
MS √ √ √ √
Naphtha √ √ √ √ √ 000000000000000000000000000000000000000000000000000
ATF √ √ √ √
HSD √ √ √ √ √ (Pak)
FO √ √
Bitumen √
Petchem √
Import Options
FO √ √
(D) Price
Crude prices considered as per average for last 3 years: April'02-March'05
adjusted for changes in duty (Post-Budget 2005-06).
Product RTPs, assessable values and transaction values considered at the
average of the actuals during the 3-yr period, April 02 - March 05, duly adjusted
For changes in pricing methodology as per the Industry agreement during 2004-
05 as well as for the changes in duty rates (Post-Budget 2005-06). Necessary
adjustments have also been made for the changes in quality of MS & HSD.
Price sensitivity of higher LS-HS spread and product cracks broadly inline with
the latest long term IT forecast have also been carried out under following
scenarios:
Scenario-4: Price sensitivity for Scenario-1 (low demand) with higher LS-HS
spread and Product cracks
Scenario-5: Price sensitivity for Scenario-3 (moderate demand) with higher LS-
HS spread and Product cracks.
A comparison of the 3-year average crude spreads and product cracks considered for
Scenarios-l, 2 & 3 vis-a-vis those considered for Scenarios-4 & 5 are provided
hereunder:
(figs. in $/bbl)
Scenario Scenarios-1, 2 & 3Scenarios-4 & 5
Pricing basis Apr 02-Mar 05 IT forecast
Brent-Dubai 3.04 5.00
MS (S'pore)-Dubai8.22 13.80
HSD-Dubai 5.67 9.84
Naphtha-Dubai 2.30 4.49
SKO-Dubai 6.86 12.34
FO-Dubai (-)5.76 (-)10.00
No change has, however, been effected (from the 3-year average) in any
scenario as regards the selling price of SKO in the market place, since the same
continues to be controlled by the Govt.
As regards Paradip Refinery, petrochemicals price realization from tile domestic
as well as export market, and the input cost for Benzene have been considered
based on the 3-year average for the period Apr'02-Mar'05 (as worked out by Ref.
HQ).
(E) Crude Choice & Crude Mix
All regular crude oils being currently processed at Refineries have been kept open for
the model for economic selection.
(F) Cases Studied
Under each Scenario as defined at para 4.3 (A) above, 8 cases with
different configuration (i.e. with/without Paradip refinery, with/without
Paradip-Raipur PL and with/without subject project) were also
examined as described hereunder:
Case Paradip
Refinery
(PDRP)
Paradip-Raipur
Product
pipeline
(PRPL)
OHCU
Project at
Haldia
Case-
1
Yes Yes Yes
Case-
2
Yes Yes Yes
Case-
3
Yes No Yes
Case-
4
Yes No No
Case-
5
No Yes Yes
Case-
7
No Yes No
Case-
6
No No Yes
Case-
8
No No NOo
4.4 Results Summary
Considering Paradip Refinery and Paradip-Raipur pipeline in place,
the results of economic evaluation of the subject project for all of
above scenarios for Case-1 and Case-3 is summarized below:
Cases Objective Function* Rs. Cr./Yr (Profit)
Scenario-1 Scenario-2 Scenario-3 Scenario-
4
Scenario-
5
Demand level Low High Moderate Low Moderate
Pricing basis Apr 02- Apr 02- Apr 02- IT forecast IT forecast
Mar'05 Mar'05 Mar'05
Project case with Paradip
(Case-1)
21092 25272 22802 30120 32432
Base case with Paradip
(Case-3)
20930 25064 22626 29874 32203
Delta Objective Function,
Rs Cr/Yr
162 208 176 246 229
*Objective Function = Product Realization - Raw Material Cost - Catalyst & Chemical
Cost - Logistic Cost
The scenario-wise projected incremental margin (i.e. delta in the LP Objective Function
vis-a-vis the corresponding Base case) from commissioning of tile expansion of Haldia
refinery under the various cases, i.e. with/ without Paradip refinery, with/ without Paradip
product PL, is provided at Aanexure-1.
As can be seen from the above table, even after commissioning of Paradip Refinery and
Pipeline, IOC's margin on a global basis improves by installation of OHCU at Haldia as
compared to Base Case, i.e., installation of DHDT.
Under the low demand scenario (scenario-1), overall incremental margin is Rs. 162
Cr./year over the base case. This further improves to Rs. 246 Cr./year under Scenario-4
(price sensitivity for scenario-1).
Under a moderate demand level scenario (scenario-3), overall incremental margin is Rs.
176 Cr./year over the base case. This further improves to Rs. 229 Cr./year under
Scenario-.5 (price sensitivity for scenario-3)
Under tile high demand scenario (scenario-2), overall incremental margin is Rs. 208
Cr./year.
4.5 Product Pattern of Haldia Refinery for Scenario-1 and Scenario-5 are given in
Annexure-2
4.6 Refinery-wise capacity utilization under Scenario-1 and Scenario-5 is Presented in
Annexure-3.
5.0 FACILITIES ENVISAGED
5.1 The process units envisaged under Hydrocracker Project are
given below:
S. No.Unit Capacity
1. OHCU, MMTPA 1.7
2. HGU, TMTPA 75
3. AAU / ARU, TPH 272
4. SWS, TPH 25
5. SRU, TPD 2 x 80
6. CDU-II revamp, MMTPAfrom 2.5 to 4.0
5.2 In addition to the above, certain utilities and off-site facilities such as Gas Turbine
(20MW), ETP, Tankages, etc., have also been envisaged, which have been enumerated
at Annexure-4. No additional facilities have been considered for product evacuation as
the existing facilities are found to be adequate for despatch of incremental products.
6.0 PROJECT COST
Based on the study by M/s Lurgi India, the capital coat of the Project with facilities as
mentioned in Para 5.0 above is estimated m he Rs. 1876 crore inclusive of a Foreign
exchange component of Rs. 308 crore (1 USD = Rs. 43.8) and financial cost of Rs.104
crore (based on July,'05 price level). The accuracy of cost estimates is -/+l0`%. The
details of the capital cost are given in Annexure-5. Estimated cost of DHDT case is Rs.
1175 cr (July'05 prices), as estimated by Lurgi and considered in the base case.
7.0 FINANCIAL ANALYSIS
7.1 It is seen from the Integrated Planning Model Output, incremental GRM between the
base case and the configured case varies with the following:
Product demand
Spread between Brent-Dubai prices and Product Cracks.
7.2 IRR has been worked out based on the incremental GRM considering the following:
Scenario-1, i.e., lower product demand with LS-HS spread of $3.04/bbl for first
10 years of the project life of 15 years. This implies that the demand of major
products like MS, HSD and ATF approximately at the level of 2005-06 outlook till
the first ten years of operation and last 3 years' average Brent-Dubai FOB spread
of $3.04/bbl also remains constant for the first ten years of operation.
Subsequently, for balance 5 years out of 15 years, Scenario-5, i.e., moderate
product demand with spread of 5.00$/bbl has been considered.
Debt to equity ratio of 1:1 and
Interest on long term loan has been considered as 9%.
7.3 The above basis is in line with the basis adopted for financial analysis of recently
approved proposal for Residue Upgradation and MS/HSD Quality Improvement Project
at Gujarat Refinery.
7.4 IRR based on the above is 17.52%. The sensitivity cases are as
under:
Sl.
No.
Sensitivity cases IRR
(%)
1. With 10% increase in capital cost 16.05
2. With 10% increase in operating cost 17.47
3. With 90% sales realization 15.63
4. With 10% increase in capital cost, 10% increase in operating cost and 90%
sales realisation
14.24
5. With no demand growth and 3.04 $/bbl spread over entire 15 years of
project life
16.63
6. Simultaneous occurence of 1, 2, 3 & 5 above 13.30
7. With 10% reduction in capital cost of DHDT case keeping Capital cost of 14.36
OHCU case unchanged
7.5 From the above analysis, it is evident that even in the most conservative scenario of
simultaneous occurrence of 10'% increase in capital cost, 10% increase in operating
cost, 90% sales realisation and considering no demand growth and 3.04$/bbl spread
over entire 15 years of project life, IRR for the project works out to 13.30%, which is
higher than hurdle rate of 11%. This indicates the robustness of the proposed project.
7.6 In addition to the attractive IRR, the installation of' OHCU has following advantages
over DHDT:
i. In case OHCU and associated facilities are installed, the expenditure incurred so
far on process design / royalty for OHCU & HGU will get utilized.
ii. Process Design of major units (except SRU) is readily available. SRU licensor
selection has already been done. So installation of OHCU alongwith associated
facilities will take much less time as compared to that for DHDT.
8.0 FINANCIAL APPRAISAL:
The financial appraisal for the project has been carried out by M/s. Industrial
Development Bank of India (IDBI). As per their findings, the subject project is viable. The
relevant excerpts from the appraisal report is enclosed as Annwure-6.
9.0 LAND
The facilities are proposed to be installed within the refinery premises after dismantling
of six tanks (three crude oil tanks, one tank for holding surface run-off and two fire-water
tanks). LPG Bottling Plant and Old Flare Stack etc. It is worthwhile to note that a
proposal for installation of a new LPG Bottling Plant of M/s IPPL is under approval.
10.0 PROJECT SCHEDULE
The project will take about 38 months for mechanical completion from the date of
approval and 3 months thereafter for commissioning. The activity chart is enclosed as
Annexure-7.
11.0 PHASING OF EXPENDITURE
Phasing of expenditure has been considered to be as follows:
Year Amout (Rs. Lakh)
1st Year 9060
2nd Year54777
3rd Year 84478
4thYear 39246
Total 187561
The details are enclosed as Annexure-8.
12.0 PLAN PROVISION
The pre-project / construction activities of the project are to be started in X plan period
and the project is proposed to be completed during XI plan period. The provision under
Budget Estimates (BE) for the year '05-06' is Rs. 1.0 cr.
13.0 ENVIRONMENTAL ASPECTS
On commissioning of these facilities, there will not be any increase in the SO2 emission
from the refinery in excess of 1466 kg/hr, the maximum limit imposed by West Bengal
State Pollution Control Board (WBSPCB) while granting 'No-objection' to the Project.
An estimated amount of Rs. 185 crore has already been earnmarked in the total project
cost towards the Installation of ETP, SRU, AAU/ARU, SWS, etc. units under the project.
Environmental Clearance to the project was received front the Ministry of Environment &
Forest (MOE&F) in May '02. NOC obtained From WBSPCB in July 01 was valid till May
05. Extension of validity upto 31.12.09 has been now obtained from them.
14.0 PROJECT MANAGEMENT
14.1 Process packages of OHCU including SWSU & AAU (Licensor-Axens) and HGU
(Licensor- Technip Benelux) are available- Basic Envu. for CDU-II revamp has been
completed in-house.
For SRU, M/s KTI S.p.A, Italy were selected as the licensor and SIA approval was
obtained, but the job of preparation of process package was not pursued further. In view
of the need to go ahead with the project, action has now been initiated for preparation of
process package.
14.2 A reputed consultant who has experience in project management of OHCU shall be
engaged as PMC whose services shall be utilized for preparation of' process package
for ARU and Off-site/Utilities. The project is envisaged to be implemented on Lump Sum
Turn Key (LSTK) basis for licensed units, offsites / utilities and all open art units except
the revamp of CDU-II which is envisaged to be implemented in conventional mode.
15.0 Pre-Project Activities
Break- up of expenditure made for pre-project activities out of
sanctioned amount of Rs. 44.0 crore is summarized below:
(Rs Lakh)
S.No.Description Amount
1 Fees for preparation of DFR Cost
Estimates (In-Principle Approval)
41.8
2 Fees for Plant Cost Estimates for
Licensor selection
5.7
3 Fees for Fin. Appraisal (in-
principle approval)
10.0
4 Site Development 69.8
5 License and Engg Fees for OHCU617.3
6 Know-How Engg Fees for
Reformer/PSA
1635.8
7 Consultant's Fees for preparation 37.9
of DFR Estimates (Investment
Approval)
8 Fees for Financial Appraisal
(Investment Approval)
15.0
Total 2433.3
Say. Rs. Cr. 24.0
16.0 Delegation of Authority (DOA)
As per the Clause No.9 (i) of Enclosure - I of Delegation of Authority, this proposal
requires approval of Board of Directors.
17.0 Proposal
It is proposed to obtain the approval of the Board of Directors for final investment
approval for installation of facilities for Hydrocracker Project at Haldia refinery at an
estimated cost of Rs.1876 cr. (as of July 2005) inclusive of a foreign exchange
component of Rs.308 cr and financial cost of Rs. 104 cr.
18.0 Resolution
It is proposed that the Board of Directors may consider the above proposal and pass the
following resolution with or without modifications as may deem fit.
"Resolved that the approval of the Board of Directors be and is hereby accorded to the
proposal for installation of facilities for Hydrocraker Project at Haldia Refinery a an
estimated cost of Rs.1876 crore (as of July 2005) inclusive of a foreign exchange
component of Rs.308 crore and financial cost of Rs.104 crore."
Director (F) has concurred in the proposal.
====
Annexure - I
Scenario-wise projected overall incremental margins from
commissioning of the OHCU at Haldia vis-a-vis the base case
Scenario No....> Scenario -
1
Scenario -
2
Scenario -
3
Scenario -
4
Scenario -
5
Demand Level ... > Low High Moderate Low Moderate
Price ....> 3-Yr Avg 3-Yr Avg 3-Yr Avg IT F cast IT F cast
With PDRP & PRPPL 162.4 208.5 176.3 246.2 229.3
With PDRP and w/o
PRPPL
158.0 192.0 179.1 244.7 225.1
W/o PDRP with PRPPL 213.7 314.3 282.3 254.6 233.5
W/o PDRP & w/o PRPPL 186.8 330.7 260.3 253.6 229.0
PDRP : Paradip Refinery Project
PRPPL : Paradip-Raipur Product Pipeline
Annexure - 2
Product Pattern
1) Under Scenario - 1
(Figures in
TMTPA)
Case -3 (Base
Case)
Case - 1 (Project
Case)Difference
LPG 183 248 65
Naphtha 548 598 50
MS-Normal 165 150 (-) 15
MS-Premium 130 130 0
Total MS 295 280 (-) 15
SKO 224 392 168
ATF 280 371 91
JBO 37 37 0
HSD-Normal 1182 1732 550
HSD-UL 628 628 0
HSD-HF 189 189 0
Total HSD 1999 2549 550
Sub-Total (%) 3566 (61.2%) 4475 (64.2%) 909
FO 834 895 61
Bitumen 632 630 (-) 2
Sulphur 30 55 25
MCW 3 3 0
LOBS 244 244 0
F&L 514 667 151
Total 5823 6969 1146
LPG 184 254 70
Naphtha 464 598 134
MS-Normal 150 167 17
MS-Premium 227 149 (-) 78
Total MS 377 316 (-)61
SKO 264 706 442
ATF 360 449 89
JBO 37 37 0
HSD -Normal 1193 1740 547
HSD-UL 742 742 0
HSD-HF 208 208 0
Total HSD 2143 2690 547
Sub total distillate
(%)3829 (63.98) 5050(67.33) 1221
FO 721 805 84
Bitumen 632 630 (-) 2
Sulpher 30 56 26
MCW 3 3 0
LOBS 244 244 0
F & L 526 712 186
Total 5985 7500 1515
Annexure -3
Refinery-wise capacity utilization under different scenario (T puts in TMT)
i) Scenario - 1
Case-1 Case-2 Case-3 Case-4 Case-5 Case-6 Case-7 Case-8
Gujarat 12374 12374 12548 12589 12377 12308 12855 12722
Panipat 15000 15000 15000 15000 15000 15000 15000 15000
Mathura 8353 8351 8286 8301 8368 8355 8400 8400
Barauni 3177 3178 3141 3141 3179 3182 3494 3739
Haldia 6969 7155 5823 5869 7325 7495 6000 6000
Guwahati 800 800 800 800 800 800 800 800
Digboi 600 600 600 600 600 600 600 600
BRPL 2350 2350 2350 2350 2350 2350 2350 2350
CBDU 464 464 464 464 464 464 464 464
CPCL 10000 10000 10000 10000 10000 10000 10000 10000
Paradip 15205 15205 15205 15205 0 0 0 0
Total 75291 75476 74217 74318 60463 60552 59962 60074
ii) Scenario - 5
Case-1 Case-2 Case-3 Case-4 Case-5 Case-6 Case-7 Case-8
Gujarat 13700 13700 13700 13700 13700 13700 13700 13700
Panipat 15000 15000 15000 15000 15000 150000 15000 15000
Mathura 8400 8400 8400 8400 8400 8400 8400 8400
Barauni 4141 4141 4080 4090 4169 4422 5620 5750
Haldia 7500 7500 5985 5985 7500 7500 6000 6000
Guwahati 800 800 800 800 800 800 800 800
Digboi 600 600 600 600 600 600 600 600
BRPL 2350 2350 2350 2350 2350 2350 2350 2350
CBDU 464 464 464 464 464 464 464 464
CPCL 10000 10000 10000 10000 10000 10000 10000 10000
Paradip 15205 15205 15205 15205 0 0 0 0
Total 78160 78160 76584 76593 62982 63236 62933 63063
Case definition
Case Paradip Refinery Paradip-Raipur
Product pipeline
OHCU Project at
Haldia
Case
1
Yes Yes Yes
Case
2
Yes Yes Yes
Case
3
Yes Yes Yes
Case
4
Yes Yes Yes
Case
5
Yes Yes Yes
Case Yes Yes Yes
6
Case
7
Yes Yes Yes
Case
8
Yes Yes Yes
Annexure -4
Utilities and Off-Site Facilities envisaged under Hydrocraker
Project at Haldia Refinery
S.
No
Facility Capacity
1. Plant & Instrument Air System 1x4800 NM3/hr compressor
2x3600 NM3/hr Instrument Air
dryer
2. Nitrogen System 2000 NM3/hr cryogenic Nitrogen
Plant
2x100 M3 liquid nitrogen storage
2x200 NM3/hr Nitrogen vaporiser
3. Cooling Water System 3x2250 M3/hr CT cells
3x2250 M3/hr CW circulation
pumps
4. Storage System 1x400 M3/hr IFO tank + 2 pumps
1x15000 M3 OHCU feed tank + 2
pumps
1x15000 M3 OHCU bottom tank
+ 2 pumps
3x1500 M3 LPG mounded bullets
2x200 M3 Hydrogen bullets +
Top-off Hydrogen compressor of
1x3000 NM3/hr capacity
2x60000 M3 crude oil tanks
1x10000 M3 ATF Tanks + 2
pumps
5. Electrical System 20 MW GT alongwith HRSG
6. Effluent Treatment Plant with
R.O. System for generation of
DM water
New ETP of 600 M3/hr
Teritary Treatment Plant of 1275
M3/hr to generate about 700
M3/hr Cooling water make - up
and 150 M3/hr DM water
DM water pumps - 2 x 150 M3/hr
CRWS pumps - 2x552 M3/hr
DM water tanks - 1x500 M3
CRWS tank - 1x 1000 M3
7. Fire Fighting System & alarms
8. Flare System augmentation
9 DCS and instrumentation
Annexure - 5
Capital Cost (Basis: July 2005)
(Rs. Lakh)
S. No. Description F. EX Ind. Comp Total
1. Land 0 0 0
2 Site Development 0 1519 1519
3 Royalty & Know - How 1516 303 1819
4 Process Design/Engg. 2565 5013 7578
5 Plant & Machinery 25483 136571 162054
6 Roads & Buildings 0 842 842
7 Water Sply/Pub. Health 0 0 0
8 Office Equipment and furniture 0 200 200
9 Railway Siding 0 0 0
10 Construction site requirements 0 435 435
11 Const. Period Expenses 103 517 620
12 Start-up Expenses 1165 390 1555
13 Township 0 500 500
Sub Total 30832 146290 177122
14 Financial Cost 0 10439 10439
Grand Total 30832 156729 187561
Say (Rs. Cr) 308 1568 1876
Annexure -6
Excerpts from Financial appraisal Report
Conclusion
IOCL is India's flagship National Oil company accounting for 42% of the national
refining capacity, 46% of the downstream pipeline transportation network and
48% of the petroleum products market share in the country. IOCL, on its own as
well as subsidiaries, operates 10 out of the India's 18 refineries with a combined
rated capacity of 54.2 MMTPA as against the aggregate refining capacity of
127.4 MMTPA in the country is on April 1, 2004.
The petroleum refining / marketing industry in India was governed by the
Administered Price Mechanism (APM) till April 2002, which provided assured
returns to oil companies. Subsequent to the dismantling of APM, the prices of
petroleum products have been market determined, except in the case of'
kerosene and domestic LPG where the prices are still controlled by GOI.
Domestic prices of HSD & Motor spirit, although de-regulated, are yet to be
linked to global prices and continue to be subsidized by GOI due to various social
considerations. In the present deregulated scenario and dismantling of the APM,
the refining margins of oil companies have Substantially improved but in view of
the non-increase in prices of POL products in line with crude oil prices. the
marketing margins have come under tremendous pressure. IOCL has, thus,
recognized the need to Improve its profitability by debottlenccking of existing
refining capacities at minimum costs and thus adding greater value. This strategy
is being adopted in keeping with IOCL's vision, which envisages becoming a
transnational, integrated energy company, expanding its activities across the
hydrocarbon value chain into oil exploration and production, as, petrochemicals
and globalization of its core activities'.
As a part of its ongoing diversification strategies, IOCL has recently
commissioned Linear Alkyl Benzene (LAB) project at Vadodara and is presently
implementing petrochemicals projects i.e PX / PTA & Naphtha Cracker with
downstream units at Panipat. It has also ventured into Exploration and
Production of Oil and NG. It has also expanded its market to Sri Lanka, Mauritius
and UAE. It is also planning to set up an integrated refinery cum petrochemicals
complex at Paradip.
IOCL proposes to implement a scheme, at its Haldia Refinery, envisaging
revamping of existing Crude Distillation Unit - II as Well Set up additional
secondary processing facilities like Once Through Hydrocracking Unit (OHCU)
with capacity of 1.7 MMTPA, Hydrogen Generation Unit and Sulphur Recovery
Unit so as to enhance the overall crude processing capacity of the refinery form 6
MMTPA to 7.5 MMTPA, for improvement in diesel quality so at to meet the Euro
III/Euro IV norms as also to improve the distillate yield from 65.7% wt. to 69.48%
wt. The proposed project of IOCL envisages maximum utilization/revamp of
existing units and the incremental product slate can be sold in the Eastern
Region which is deficient in POL products.
The project is planned to be implemented over a period of 39 months (including 3
months of trial run period) form the zero date (November 2005) and the COD is
expected to be February 2009.
The aggregate project cost is estimated at Rs.1875 crore. The cost estimate are
based on the cost estimates furnished by Lurgi, DFR Consultant considering
price levels prevailing during July 2005 and has an accuracy levels of +/ - 10% .
The project costs could vary, on completion on final negotiations and
conventional bidding of contracts and also based on the final financing terms.
The Internal Rate of Return (IRR) of the project (base case) works out to 14.7%
as against average cost of capital of 11%. The financial viability of the project
would, however, be critically dependent upon the POL and crude prices. The
sensitive analysis shows that the project would be viable under all likely
scenarios but the IRR would be very sensitive to combined effect of increase in
project cost by 10% and decrease in gross margins by 10%. Even after taking
into account the capital expenditure of Rs 1175 crore required to be incurred for
conforming to the statutory quality requirements is not expected to yield any
significant return, the IRR, even in the most sensitive scenario, is still higher than
the hurdle rate of 11 % approved by IOCL's Board for capital investment
proposals. Debt servicing parameters are satisfactory. The proposed project is
therefore considered to be financially viable.
Annexure - 8
Phasing of Expenditure
Year PCWOFCFC Proj. CostEquityLoan ACC Loan
1st 8856 204 9060 4530 4530 4522
2nd 53137 1640 54777 27388 2738831864
3rd 79705 4773 84478 42239 4223974032
4th 35424 3822 39246 19623 1962393622
Total177122 10439187561 93780 93780
PCWOFC = Project cost without financial cost
FC = Financial Cost
ACC Loan = Accumulated Loan
Basis:
Debt: Equity = 1:1
Interest Rate = 9% PER Annum
Phasing
First Year 5%
Second Year30%
Third Year 45%
Fourth Year 20%
Annexure 9
Project Appraisal Group (Project appreciation note)
Project: Detailed Feasibility Report (DFR) on Installation of facilities for improvement in
Diesel Quality and Distillates yield (Hydrocracker) Project at Haldia Refinery.
Project at a Glance
Justification onEconomics GroundsOperating NecessitySafety Requirements
Project Cost Stage - IDFR
Total (Rs. Crores)1518 1876
FE Component 357 308
Price Base Apr 00 July 05
Completion Schedule (Stage - I)
Mechanical Completion 36 moths
Commissioning 3 months
Completion Schedule (DFR)
Mechanical Completion 38 months
Commissioning 3 months
Project Economics - IRR
State - I12.99% - Price Cycle (Apr 97 to Mar 00)
DFR 17.5% - Price Cycle (Apr. 02 to Mar 05)
Project Financing
Stage - IDFR
Debt: Equity 1:1 1:1
Capacity (TMT)
Crude 6.0 7.5
Technology/Facilities
1. CDU - II revamp : 2.5 to 4.0 MMTPA
2. New units:
OHCU : 1.7 MMTPA
HGU : 75 TMTPA
AAU/ARU : 272 TPH
SWS : 25 TPH
SRU : 2 x 80 TPD
3. Gas Turbine : 20 MW along with HRSG
4. New ETP of 600 M3/hr, Cooling water system (3x 2250 M3/hr), Nitrogen system,
Storage system etc.
1.0 Proposal
1.1 The proposal seeks final approval of DFR from the Board of Directors for:
Installation of Hydrocracker facilities at Haldia Refinery at an estimated cost. of Rs. 1876
crore (as of July 2005) inclusive of foreign exchange component of Rs. 308 crore.
2.0 Background
2.1 Vide agenda item No. R/936 dated 29.11.2000, Board has accorded i principle
approval for installation of facilities for improvement in Diesel Quality and Distillate Yield
at an estimated cost of Rs. 1518 crore inclusive of foreign exchange component of Rs.
357 crore based on April 2000 price level subject to obtaining statutory environment
clearance from MOE&F. Board has also accorded expenditure approval of Rs. 44 crore
inclusive of a foreign exchange component of Rs. 18 crore for carrying out pre - project
activities pending Environmental Clearance.
2.2 Subsequently vide agenda item No. R/1005 dated 24.4.2003, Board has approved
the road map to meet the quality requirement of HSD and MS and suggested deferment
of completion of Hydrocracker Project at Haldia Refinery till January 2010 so as to match
with quality requirement of April 2010 onwards. Hence, all activities relating to the project
were kept on hold.
2.3 As per auto fuel quality road map, it has been stipulated that Euro IV specification for
MS and HSD shall be implemented in Metros and Other Seven Cities from 1st April 2010
while rest of the country will have Euro III equivalent specification on that date.
To meet the future quality norm of HSD, it is proposed to install Hydro - Cracker facilities
at Haldia Refinery.
3.0 Technology/Facilities:
3.1 The following facilities are envisaged in the proposal:
CDU-II revamp from 2.5 to 4.0 MMTPA.
New OHCU of capacity 1.7 MMTPA.
New AAU/ ARU of capacity 272 TPH.
New SWS of capacity 25 TPH
New SRU of capacity 2 x 80 TPD
One Gas Turbine of 20 MW with HRSG
New ETP with RO system of 600 M3/Hr
Cooling water system of 3 x 2250 M M3/ Hr CT cells
Cryogenic Nitrogen System of 200 N M3/ Hr
Plant and Instrument Air System
4.0 Project Cost
Estimated cost of the project is Rs. 1876 crore (as of July 2(305) inclusive of foreign
exchange component of Rs. 308 crore. The accuracy of the cost estimates is ±10%. The
operating cost of the proposed facilities is Rs 26.5 crore / year.
5.0 Economics:
Optimization Group has carried out the economic evaluation of the proposed proposal
using Integrated Planning (IP) Model. The project has been studied considering five
demand scenario and two pricing scenario. The summary of economic evaluation as per
IP model is as under:
Objective Function Rs. Cr/Yr (Profit)
Scenario 1 Scenario 2 Scenario 3 Scenario
4
Scenario
5
Demand level Low High Moderate Low Moderate
Pricing level Apr 02 - Mar
05
Apr 02 -
March 05
April 02 to
March 05
IT forecastIT forecast
Project case with
Paradip (Case - 1)
21092 25272 22802 30120 32432
Base case with Paradip
(Case - 3)
20930 25064 22626 29874 32203
Delta Objective
Function, Rs. Cr/Yr
162 208 176 246 229
Objective Function = Product Realization - Raw Material Cost - Catalysts & Chemical
cost - Logistic Cost
Case - I : with Hydrocracker configuration
Case - III: with DHDT configuration
6.0 Manpower:
Additional manpower of 97 nos. has been proposed
7.0 Phasing of Expenditure of the project is as follows:
(Figs. in Rs./crores)
1st year2nd Year3rd Year4th YearTotal
91 548 845 392 1876
8.0 Financial Appraisal :
The financial appraisal of the Project has been carried out by M/s. IDBI. It has been
concluded that the proposed project is financially viable. The financial viability of the
project would, however be critically dependent on the POL and Crude Prices.
9.0 Points for consideration:
9.1 The IRR based on incremental Gross Refinery Margin and project
cost differential (Rs.1876 - 1175 = 701 crore) is as under:
Sl.
No.
Attributes IRR (%) Hurdle rate
(%)
1. Base case 17.52 11.0
2. With 10% increase in capital cost 16.05
3. With 10% increase in operating cost 17.47
4. With 90% sales realization 15.63
5. With 10% increase in capital cost, 10%
increase in operating cost and 90% sales
realization
14.24
6. With no demand growth and 3.04 $/bbl
spread over entire 15 years of project life
16.63
7. Simultaneous occurrence of 1,2,3, & 5
above
13.30
8. With 10% reduction in capital cost of
DHDT case keeping Capital cost of
OHCU case unchanged
14.36
Note :
Base Case - Lower product demand scenario with LS-HS crude spread of $ 3.04/bbl (3
years average) for first 10 years of project life and balance 5 years with moderate
product demand with spread of 5.00 $/bbl (IT projection) has been considered.
It may be seen from above, that the project is economically viable. The Break Even IRR
of 11 % will be achieved with the investment of about Rs. 893 Crore in DHDT case.
9.2 An amount of Rs. 176 Crore (approx) has been considered if, the base case (Le with
DHDT option) for procurement of 20 MW Gas Turbine. Presently Haldia Refinery has a
generating capacity of 92 MW (4 TGs and 2 GTs) and the requirement of power with
DHDT option will be 54 Mw (approx). In this case the requirement at GT in DHDT option
may hot be required and hence the total cost will be Rs. 1000 Crore (excluding GT cost).
In this scenario the IRR of the project will be reduced from 17.5% to 12.8%.
9.3 While working out the economics of the proposal it has been projected that in the low
and moderate demand scenario the throughput of Barauni Refinery will be in the range
of 3.2 to 4.2 MMTPA level post Hydrocracker and PDRP project. In view of the low
throughput operation at Barauni the necessity for the third reactor of DHDT at Barauni at
an estimated cost of Rs. 63 Crore at this stage .way be reviewed.
9.4 An additional manpower of 97 numbers has been proposed to operate the new
facilities. A detailed manpower study is required to be carried out before separate
approval of manpower requirement.
9.5 An amount of Rs. 5.00 Crore has been provided for the township in the cost
estimate. In view of the present housing scenario there is a need to review the
requirement of houses.
9.6 A new ETP of 600 M3/ Hr is proposed in addition to the existing ETP. Division may
explore a combined ETP operation instead of two ETP operation.
9.7 While working out the economics. it has been projected in the IP model that 1.5
MMTPA diesel is being exported to Pakistan from Panipat Refinery. If the same is not
materializes there will be an impact on margins.
9.8 After implementation of the Hydrocracker project there is an improvement in the
distillate yield 3.0% to 3.4% wt (excluding LOBS yield).
9.9 It has been proposed to implement the project by LSTK mode for all units except
revamp of CDU-II. An amount of Rs.79 Crores has been provided for LSTK mode of
execution.
The agenda may be considered for submission to the Board of Directors at an estimated
cost of Rs. 1876 crore as per DOA clause of 9 (i) of Enclosure-I
xxxxxxxx
Sub: Installation of facilities for Improvement in Diesel Quality
and Distillates Yield at Haldia Refinery
Summary of the reply given by Refineries Division to the queries
raised by Chairman's Office In seriatim is as under:
1. The major variation in project cost (DFR V/s in-principle i.e 1876 vs
1518 crore) is as under:
Sr.No.Attributes Variation
1. FE variation (-) 48.0
2 Impact of pricing index (WPI/CPI-escalation)(+) 188.0
3 Change in Scope
Revamp of CDU-II (+) 43.0
Higher capacity of Effluent Treatment Plant (+) 39.0
Addition of Tertiary Treatment Plant (+) 26.0
2 Nos. crude tank* (+) 25.0
4. Impact of high steel price over WPI/CPI (+) 19.0
5 Site development charge (+) 13.0
6 Financial cost (change in interest rate) (-) 8.0
7 others including inaccuracy of estimates (+) 61.0
8 Total (+) 358.0
* Discussion with Pipelines Divisions is on for sparing of tanks at HBCPL tank farm
area. Based on the feed back from Pipelines Division, final view will be taken on
construction of two crude tanks for which provision has been kept in Capital Cost
Estimate.
2. With regards to completion period, it has been stated that actual completion including
commissioning is 43 - 47 months in conventional mode and in case of Panipat
expansion, it is 45 months (approx.) in LSTK mode as against 41 months proposed for
Hydrocracker project in LSTK mode.
3 As stated by Optimization Group, in the post Panipat Expansion, Hydrocracker at
Haldia and Paradip Refinery scenario, the projected throughput at Barauni is likely in the
range of 3.2 to 3.7 MMTPA level with existing HB capacity and considering high LS - HS
crude differential of last 3 years average of $3.04/ bbl which is expected to continue in
future. In view of this, further investment (third reactor in DHDT) at this stage at Barauni
is to be kept under hold and can be reviewed at a later stage..
4. The proposed hydrocracker facility will be installed in the existing refinery premises.
5. Considering investment approval in November, 2005 and 41 months of completion
schedule, the facility is expected to be ready by April, 2009 as against requirement of
completion of project by Jan, 2010 by earlier Board decision.
xxxxxx
Sub: Study of Installation of facility at Haldia Refinery for Improvement in Diesel
Quality and increase in Capacity
Background:
HSD quality requirement beyond April 2010 cannot be met by Haldia refinery with its
existing configuration/facilities various alternatives for meeting the twin objectives of
upgrading the diesel quality as well as the feasibility of processing crude up to 7.5
MMTpa at Haldia were evaluated by Refy HQ through LP modeling and installation of a
Once Tarough-Hydrocracker (OHCU) was selected as the best option. Optimisation
Dept. was accordingly requested to carry out a study through the Integrated Planning
(IP) model and arrive at the savings from installation of the OHCU at Haldia refinery.
The study was to compare the savings between the following two configurations at
Haldia:
A. Crude processing at 6 MMTpa with DHDT- necessary for meeting Diesel specs
(BaseCase)
B. Crude capacity at 7.5 MMTpa with OHCU (project Case)
The concerned RMPS models were accordingly developed and tuned along with the
representative from Haldia refinery. Since by the time of completion of the subject
project, Panipat expansion to 15 MMTpa, Gujarat Resid Upgradation Project and
expansion to 13.7 MMTpa would also be in place, the RPMS models of Panipat and
Gujarat included in the IP model for the subject study were as utilized earlier for the
respective studies. Further, since Paradip refinery and the proposed Paradip-Rengali-
Korba-Raipur product PL with the branch from Renglai to Bundu could have an impact
on the subject proposal, impact of the same was also studied. Since the yield of Paradip
refinery also included petrochemicals, the same was however configured as an extreme
point refinery in the IP model with crude mix, product pattern and prices for
petrochemicals (IPP as well as EPP) as provided by Refy EQ.
As desired, the scenarios studied, details of the basis adopted and the summary of the
findings thereform are provided hereunder:
Scenarios Studied:
Scenario-1 : Low-Demand scenario as considered for Gujatrat expansion and P-15
study (and utilized in the IRR workings for years 1 to 10 of the said study).
Scenario-2: Demand for 2011-12 for all products as currently projected planning Dept.
Mktng HO.
Scenario-3 : Growth rate of 10% for HSD, 15% for MS and 18% for ATF applied on the
demand nos. per Scn-1, i.e. similar to the High-Demand scenario as considered for
Gujarat expansion and P-15 study (and utilized in the IRR workings for years 11 to 15 of
the said study).
Scenario-4: Price sensitivity for Sen-1 with higher LS-HS spread and product cracks
9per details at Table-E of Attachment-A).
Scenario- 5 : Price Sensitivity for Sen-3 with higher LS-HS spread and product cracks.
Under each Scenario, 8 cases with different configuration (i.e. with/without Paradip
refinery, with/without Paradip-Raipur PL and with/without Haldia expansion) were also
examined as described at Table-1 hereunder:
Table:1: Cases Studied under each Scenairo
Case NumberParadip Refy.Paradip PLHaldia Project
Case 1 Y Y Y
Case 3 Y Y N
Case 2 Y N Y
Case 4 Y N N
Case 5 N Y Y
Case 7 N Y N
Case 6 N N Y
Case 8 N N N
Basis Adopted:
Details of the basis adopted are provided at Attachment-A.
Findings:
Details of the optimal crude thoughput levels at refineries, arrived at on a global basis
through the IP model, under various scenarios and cases in provided at Tables-2 & 3A
hereunder:
Table-2: Crude Thruput Levels-Scn-1,2 & 3 (MMTPa)
Scenario No Scn-1 Scn-2 Scn-3
Demand Level Low High Moderate
Case No. Cs-1Cs-3Cs-6Cs-8Cs-1Cs-3Cs-6Cs-8Cs-1Cs-3Cs-6Cs-8
Paradip Refy & PLY Y N N Y Y N N Y Y N N
Haldia Expansion Y N Y N Y N Y N Y N Y N
Haldia 7.0 5.8 7.5 6.0 7.2 6.0 7.5 6.0 7.0 5.7 7.5 6.0
Barauni 3.2 3.1 3.2 3.7 3.9 3.9 4.7 5.7 3.5 3.5 3.7 4.3
Paradip 15.0 15.0 0.0 0.0 75.0 15.0 0.0 0.0 15.0 15.0 0.0 0.0
IOC Total 75.1 74.0 60.6 60.1 77.5 76.2 63.6 63.1 75.6 74.2 62.5 61.6
It can be seen from Table-2 above that based on the average prices during the 3-year
period April 02 - March 05:
The Commissioning of Paradip refinery has an impact on the optimal thruput of Haldia
refinery . Under scn-1 to 3, Haldia refinery achieves its maximum thruput post
expansion of 7.5 MMTPa in cases where Paradip refinery has not been commissioned
whereas post-commissioning of Paradip refinery, the optimal thruput of Haldia post-
expansion on a global basis is about 7 MMTpa.
Expansion of Haldia has an impact on the thruput of Barauni (which basically acts as the
swing refinery based on the demand level, especially consequent to additional
availabilities ex-Gujarat, Panipat and Paradip).
Table-2 : Crude Thruput Levels-Scn-4&5 (MMTpa)
Scenario No Scn-4 Scn-5
Demand Level Low Moderate
Case No. Cs-1Cs-3Cs-6Cs-8Cs-1Cs-3Cs-6Cs-8
Paradip Refy & PLY Y N N Y Y N N
Haldia Expansion Y N Y N Y N Y N
Haldia 7.5 6.0 7.5 6.0 7.5 6.0 7.5 6.0
Barauni 4.0 3.6 4.2 3.9 4.1 4.1 4.4 5.8
Paradip 15.0 15.0 0.0 0.0 15.0 15.0 0.0 0.0
IOC Total 77.8 75.9 62.9 61.2 78.0 76.4 63.2 63.1
It can be seen from Table-2A above that based on pricing as per the latest IT forecast
for the year 2010 (i.e. higher LS-HS spreads and higher product cracks vis-avis the 3-
year average during '02-05 considered for scn-1 to 3):
Haldia refinery achieves its maximum thruput post expansion under both the scenarios
irrespective of the status of the commissioning of Paradip refinery.
Barauni's thruput also increases due to higher product cracks and the viability of exports
ex-other refineries. Barauni almost achieves its maximum throughput in case-8 w/o
Paradip & Haldia project) of Sen-5 (price sensitivity for Scn-3 Moderate Demand Level)
Details of the product-wise and location-wise exports under various scenarios and cases
are provided at Annexure-I.
Details of the product pattern at Haldia refinery pre and post-expansion under the
various scenarios/cases is provided at Tables-3 & 3A hereunder:
Table3: Product Pattern-Scn-1,2&3 (TMTpa)
Scenario No Scn-1 Scn-2 Scn-3
Demand Level Low High Moderate
Case No. Cs-1Cs-3Cs-6Cs-8Cs-1Cs-3Cs-6Cs-8Cs-1Cs-3Cs-6Cs-8
Paradip Refy & PLY Y N N Y Y N N Y Y N N
Haldia Expansion Y N Y N Y N Y N Y N Y N
LPG 248 183 256 186 252 186 258 187 254 185 257 188
Naphtha 598 548 599 587 576 493 523 455 598 536 603 550
MS-K 150 165 174 155 228 218 223 223 136 122 155 167
MS-P 130 130 130 130 98 131 170 170 149 149 149 149
Total-MS 280 295 304 285 326 349 393 393 285 271 304 316
SKO 392 224 610 359 279 121 126 73 433 109 532 263
ATF 371 280 350 259 421 403 412 402 386 335 352 332
JBO 37 37 37 37 37 37 37 37 37 37 37 37
N-HSD 17321182198912861674949 217312241569103619491293
UL-HSD 628 628 628 628 787 787 796 787 691 691 691 691
HFHSD 189 189 189 189 272 272 234 119 208 208 208 168
Total-HSD 254919992806210327332008320321302468193528482152
Distillate Yield % 63.7 60.6 65.7 63.0 63.4 59.3 65.6 60.7 63.4 59.7 65.8 63.4
FO 895 834 884 758 10361014935 931 960 817 886 729
Bitumen 630 632 630 632 582 582 582 582 571 628 598 632
Sulfur 55 30 57 30 58 31 57 31 58 30 58 30
MCW 3 3 3 3 3 3 3 3 3 3 3 3
Lubes 244 244 244 244 244 244 244 244 244 244 244 244
Fuel & Loss % 9.6 8.9 9.6 8.7 9.6 8.9 9.7 8.9 9.8 9.2 9.7 8.8
Table 3A: Product Pattern -Scn-4 & 5 (TMTpa)
Scenario No Scn-1 Scn-3
Demand Level Low Moderate
Case No. Cs-1Cs-3Cs-6Cs-8Cs-1Cs-3Cs-6Cs-8
Paradip Refy & PLY Y N N Y Y N N
Haldia Expansion Y N Y N Y N Y N
LPG 260 181 259 185 254 184 255 187
Naphtha 598 501 598 515 598 464 598 480
MS-K 173 222 176 215 167 150 182 225
MS-P 134 129 130 129 149 227 132 149
Total-MS 307 351 306 344 316 377 314 374
SKO 790 327 794 438 706 264 536 301
ATF 429 290 427 271 449 360 443 352
JBO 37 37 37 37 37 37 37 37
N-HSD 17381309173412801740119319851278
UL-HSD 628 628 628 628 742 742 691 691
HFHSD 189 189 189 220 208 208 208 208
Total-HSD 25552126255121282690214328842177
Distillate Yield % 65.9 63.0 65.8 64.7 66.9 63.4 67.1 64.5
FO 794 754 794 653 805 721 794 659
Bitumen 704 632 706 632 630 632 623 632
Sulfur 63 30 63 29 56 30 55 30
MCW 3 3 3 3 3 3 3 3
Lubes 243 244 243 244 244 244 244 245
Fuel & Loss % 9.6 8.8 9.6 8.8 9.5 8.9 9.6 8.8
It can be seen from the above that in addition to increase in the crude processing
capacity, the project also results in an improvement in the distillate yield at Haldia
refinery.
Product-wise details of the levels of additional gives to EPC & BPC and purchase from
ONGC & RIL under the various scenariors and cases are provided at Tables-4 & 4A
hereunder.
Table-4: Addl. Given & Purchases - scn-1,2&3 (TMTpa)
Scenario No Scn-1 Scn-2 Scn-3
Demand Level Low High Moderate
Case No. Cs-1Cs-3Cs-6Cs-8 Cs-1Cs-3Cs-6Cs-8 Cs-1Cs-3Cs-6Cs-8
Paradip Refy &
PLY Y N N Y Y N N Y Y N N
Haldia
ExpansionY N Y N Y N Y N Y N Y N
Addl Gives to
HPC
WS 241 242 221 221 259 254 27 38 228 230 160 167
HSD 730 730 730 730 947 947 257 257 800 803 803 778
Addl Gives to
BPC
WS 472 472 472 472 568 555 390 412 539 539 532 532
HSD 14841484148414841878187815351535 1633162916291633
Purchase-
ONGC
WS 93 93 93 93 150 150 150 150 107 107 141 117
SKO 316 316 757 815 279 279 737 732 342 351 815 815
HSD 494 494 494 494 722 722 722 722 544 544 544 544
Purchase-RIL
WS 25 25 25 25 104 104 140 140 67 67 78 78
SKO 258 258 650 650 158 158 650 650 215 562 650 650
HSD 217 217 217 217 269 269 402 676 239 239 239 239
Table-4A: Addl Gives & Purchases-Scn-4&5 (TMTpa)
Scenario No Scn-4 Scn-5
Demand Level Low Moderate
Case No. Cs-1 Cs-3 Cs-6 Cs-8 Cs-1 Cs-3 Cs-6 Cs-8
Paradip Refy & PL Y Y N N Y Y N N
Haldia Expansion Y N Y N Y N Y N
Addl Gives to HPC
WS 242 242 242 242 278 278 227 254
HSD 733 733 733 733 803 803 800 800
Addl Gives to BPC
WS 502 502 502 502 543 543 543 543
HSD 1485 1485 1485 1485 1629 1629 1633 1633
Purchase-ONGC
WS 93 93 93 93 107 107 107 107
SKO 314 333 426 815 350 356 815 815
HSD 494 494 494 494 544 544 544 544
Purchase-RIL
WS 25 25 25 25 29 29 67 29
SKO 265 550 650 650 220 565 650 650
HSD 217 217 217 217 239 239 239 239
The scenario-wise projected savings (i.e. delta in the LP Objective Function vis-a-vis the
corresponding Basecase) from commissioning of the expansion of Haldia refinery under
the various case, i.e. with/without Paradip refinery, with/without Paradip product PL, is
provided at Table-5 hereunder:
Table-5 : Saving from Haldia Expansion (Rs. Crores pa)
Scenario No. Scn-1 SCN-2 SCN-3 SCN-4 SCN-5
Demand Level Low High ModerateLow Moderate
Price 3-Yr Avg3-Yr Avg3- Yr AvgIT F' castIT F' cast
With Paradip Refy&Pl 162.4 208.5 176.3 246.2 229.3
With Paradip Refy, w/o Pl 158.0 192.0 179.1 244.7 225.1
w/o Paradip Refy, With PL213.7 314.3 282.3 254.6 233.5
w/o Paradip Refy & PL 186.8 330.7 260.3 253.6 229.0
Note: LP Obj. Fn. = Product Realization minus Raw material costs minus Catalysts and
Chemical costs minus Fuel & Loss minus Logistic costs.
The impact on the savings from the subject project due to the commissioning of Paradit
refinery and PL is minimal under Scn-4 &5 due to lower differential in the overall thruput
levels and higher utilization of Barauni in the concerned basecases (since the forecasted
increase in product cracks vis-avis 3-year average is higher than the forecasted
increase in LS-HS spreads:
It can be seen from Tables-5 above that:
With pricing based on the 3-years average, savings on global basis from
commissioning of the subject project varies from about Rs.160 to Rs.330 Crores
per Annum based on the demand level/commissioning of Paradip Refinery.
With pricing based on the long term IT forecast, savings from commissioning of
the subject project varies from about Rs.230 to Rs.255 Crores per Annum.
Attachment-A
Basis Adopted
Demand
Scn-1 & 4:
Product-wise demand was considered at the same levels as in the Low-Demand
scenario considered for Gujarat expansion and -15 study (and utilized in the IR workings
for years 1 to 10 of the said study).
The demand numbers under this scenario are close to the levels per the outlook of the
year 2005-06. However, demand of Naphtha and FO have been substantially reduced
considering the projections by Corporate Planning regarding switch-over by major
customers to Natural Gas. As regards LSHS, it has been assumed that the switch-over
to gas would not be major. Further, demand of SKO is about 6.7% lower than the current
outlook for the year 2005-06.
Scn-2:
Product-wise demand has been considered at the levels per the latest projections by
Planning Dept Mktng HO for the year 2011-12.
Scn-3 &5:
Product-wise demand level is similar to the High-Demand scenario considered for the
Gujarat expansion and P-15 study land utilized in the IRR workings for year 11 to 15 of
the said study), i.e. growth rate of 10% for HSD and 15% for MS has been applied on
the demand nos. per Scn-1. However, in addition, ATF has also been escalated at 18%
over and above the level in Scn-1.
The level of product-wise demand considered under the various scenarios is provided at
Table-A hereunder. Marketing HO's latest outlook of product-wise demand for the year
2005-06 has also been provided therein for the purposes of comparison.
Table-A: Scenario-wise Demand Numbers (TMTpa)
Product05-06
Outlook
Sc-1&4 Low
Demand per P-
15 Study
Scn-2 Projections for 11-12
per Mktng HO
Scn-3&5 High Demand
per P-15 Study plus
ATF Growth
Comparative LevelLow High Moderate
MS 3818 3893 5353 4477
HSD 21032 21920 27151 24112
SKO 6313 5888 5211 5888
ATF 2174 2185 2936 2579
Naptha 2574 907 873 907
FO 4300 3556 5482 3556
LSHS 3413 2571 1274 2571
LDO 667 657 582 657
Bitumen 2323 2475 3143 2475
Flexibility was kept in the model under all the scenarios in respect of meeting of the
LSHS demand, i.e. the model had the option in all cases of not meeting the LSHS
demand (Min limit of LSHS kept as zero). In other words, LSHS production at the
refineries was based on economics.
The CARG adopted by Planning Dept Mktng HO for arriving at the demand numbers for
the terminal years of the Plans (number for 2011-12 adopted for Scenario-3) is provided
at Table-B hereunder:
Table-B: CARG adopted by Planning Dept Mktng HO
Product'06-7-08090809-11121112-16171617-2122
MS 5.2% 5.2% 5.0% 4.0%
HSD 3.8% 3.8% 4.0% 3.0%
SKO -4.0% -4.0% -1.8% 0.1%
ATF 4.1% 5.0% 5.0% 5.0%
Production:
The maximum crude processing capacities at various refineries considered for the Study
are provided at Table-C hereunder:
Table-C: Max, Crude Capacities at Refineries (TMTpa)
GujaratPanipatMathuraBarauniHaldiaGujaratDigboiBRPLCBDUCPCL Paradip
13,700 15,000 8,400 6,000 7,500 800 600 2,350 517 10,00015,000
Exchanges & Purchases
For all Scenarios it has been assumed that HPC's proposed Mindra-Delhi product PL as
well as EPC's proposed extension of its Mumbai-Manmad-Indore product PL to
Loni/Piyala would be in place. Gives to HPC and BPC ex-Koyali, Mathura and Panipat
have accordingly been reduced from normal levels as detailed at Table-D hereunder
(based on the OMC 's current & takes from IOC at their future ToPs):
Table-D: % Redn in Gives to HPC & BPC due to their PLS
Refy % Redn from normal level
HPC BPC
HSD MS HSD MS
Koyali 65% 47% 45% 39%
Mathura52% 43 39% 36%
Panipat 14% 5% 10% 4%
Further, since it was observed under all the cases and scenarios that the subject
expansion of Haldia refinery / commissioning of the proposed Paradip-Raipur
PL/commissioning of Paradip refinery result in substantial reduction in IOC's takes (vis-
a-vis current levels) ex-HPC's Vizag refinery, no takes by HPC ex-Haldia has been
envisaged under any scenario/case.
Subject to the above mentioned adjustments, gives to BPC & HPC ex-all refineries in
each scenario are based on the refinery-wise numbers finalized per the MoU for the
quarter Jan-Mar'06 duly annualized and escalated by the product-wise demand growth
rates adopted for IOC & Associates under the concerned scenario. Exchange of SKO
has been assumed on a ton-to-ton basis since no company would be interested in taking
additional SKO from another company.
Refinery-wise takes from BPC & HPS as well as purchases from RIL and ONGC have
been retained at economic levels under all scenarios.
Prices:
Prices of Crudes and Products RTPs, Assessable Values and Transaction Values were
considered at the average of the actuals during the 3-year period Apr'02 - Mar'05, duly
adjusted for changes in the pricing methodology as per the Industry agreement for the
year 2004-05 as well as for the changes in the rates of Customs and Excise Duty per
Budget for the year 2005-06. Necessary adjustments have also been made for the
changes in quality of MS & HSD.
Price sensitivity of higher LS-HS spread and product cracks (broadly in line with the
latest IT forecast) on the results of Scn-I (Low demand) and Scn-3 (Moderate demand)
has also been examined vide Scenarios 4 & 5 respectively. A comparison of the 3-year
average crude spreads and product cracks considered for Scenarios-1, 2 & 3 vis-a-vis
those considered for Scenarios-4 & 5 as well as the forecast by IT Dept for the year
2010 are provided at Table-E hereunder:
Table-E: Comparison of Crude Spreads and Product Cracks
(Figs in US$/bbl)
Scenario Basis IT F'cast 2010Scn-1, 2 & 3 '02-'05 AvgScn-4 & 5
Brent-Dubai 4.55 3.04 5.00
MS (Sing)-Dubai13.14 8.22 3.80
HSD-Dubai 9.84 5.67 9.84
Naphtha-Dubai 4.49 2.30 4.49
SKO-Dubai 13.38 6.86 12.34
FO-Dubai (10.43) (5.76) (10.00)
No changes has however been effected (from the 3-year average) in any scenarios as
regards the selling price of SKO in the market place, since the same continues to be
controlled by the Govt.
As regards Paradip refinery, as also mentioned earlier, petrochemicals price realization
from the domestic as well as export market, and the input cost of Benzene have been
considered per workings provided by Refy HQ (based on 3-year average price data
during the period Apr'02 - Mar'05).
Imports & Exports:
Options for imports / exports kept open at refineries / ports in the IP model under all
scenarios are detailed at Table-F hereunder:
Table-F: Imports / Exports Option in IP mode-I
Product HaldiaParadipCPCLDahejBarauniPanipatMathuraKandla/IOTL
Exports
MS √ √ √ √
Naphtha √ √ √ √ √
ATF √ √ √ √
HSD √ √ √ √ √ (Pak)
FO √ √
Bitumen √
Petrochem √
Imports
FO √ √
Pipelines:
KBPL has been considered as on crude service. The Paradip-Haldia crude PL has been
considered to be operational.
The following other proposed product pipelines have been considered as operational:
Koyali-Dahej, Branch lines from KVSS to Ajmer and Chittorgarh, Chennai-Bangalore,
Panipat-Tikrikalan and Koyali-Ratlam-Itarsi-Khapri with branches to Indore and
Nishatpura (with rail loading facilities at Koyali, Ratlam and Khapri) under all scenarios.
Further, for cases 1, 3, 5 & 7 under each scenario the proposed Paradip-Jatni-Rengali
(Sambalpur+Rourkela) - Korba (Eilaspur+Bishrampur)-Raipur product PL with branch
line from Rengali to Bundu (Tatnagar+Namkum) has also been considered to be
operational with a variable operating cost of Rs. 125/MT.