FIRM COMMITMENT
1. G&G Studies2. 2 (two) core holes3. 1 (one) Exploratory well
(Vertical)4. Production Test
-
31-Oct-16 231/10/20162
Kementerian ESDM Republik Indonesia
Data Availability
-
31-Oct-16 331/10/20163
Kementerian ESDM Republik Indonesia
Geological Setting & Prospect Area
Figure. Prospect map of GMB Raja
GEOLOGICAL SETTING
The GMB Raja is located inSouth Sumatra Basin which is tothe east of the BarisanMountains and extends into theoffshore areas to the northeastand is regarded as a back-arcbasin, which is bounded by theBarisan Mountains to thesouthwest, and the pre-Tertiaryof the Sunda Shelf to thenortheas. The South SumatraBasin was formed during east-west extension at the end of thepre-Tertiary to the beginning ofTertiary times (Daly et al., 1987).
-
31-Oct-16 431/10/20164
Kementerian ESDM Republik Indonesia
GMB Raja Block Terms and Conditions
No.
Wilayah Kerja
Bentuk Kontrak
Kerja Sama
Ketentuan Pokok Kontrak Kerja Sama (Term and Conditions)
Mekanisme Penawaran Blok Luas (Km2)
Relinquishment FTP**
(%)
DMO*** (%)
Split (GOI : Kontraktor)**** Cost
Recovery***** (%)
Bonus Tanda
Tangan (US$)
Minimum Komitmen Pasti 3 tahun pertama
(%)
Sisa Akhir tahun ke-6* (%)
Bagian Pemerintah
(%) After Tax/
Before Tax
Bagian Kontraktor
(%) After Tax/
Before Tax
2. GMB Raja 580,5 Kontrak
Bagi Hasil
10 80 10 25 100
- G&G Studies - 2 Core Hole - 1 Exploratory Well - 1 Production Test
Penawaran Langsung
-
31-Oct-16 531/10/20165
Kementerian ESDM Republik Indonesia
The Terms & Conditions is the owner estimate for the Government Tender participants are free to bid the sharing split and signature bonus The Government chooses the winner of tender from the best offering based on the owner estimate.
Basic assessment consists of financial ability and technical commitment that is offered by tender participants. Participants which pass the basic assessment are those who fulfill administrative requirements; fulfill technical aspect; and have financial ability to support the firm commitment.
The Final Assessment is a combination of participants proposal of work program & commitment, signature bonus and sharing split.
NEW CONCEPT IN THE PETROLEUM BIDDING ROUND 2016New Concept in the Petroleum Bidding Round 2016
-
31-Oct-16 631/10/20166
Kementerian ESDM Republik Indonesia
E-Tendere-wkmigas.esdm.go.id
Profile DocumentPreparation
Bid Document Payment Account Registeration(Profile & Document Upload)
Document & Payment Validation
Username & Password
Administration
Bid Document Download &
Clarification Forum
Participation Document
Submission
E-Tender Procedure
-
31-Oct-16 731/10/20167
Kementerian ESDM Republik Indonesia
BIDDING ROUND SCHEDULE
Interested companies are invited to participate and access Bid Document by accessing our website at e-wkmigas.esdm.go.id
Companies which intend to participate in the tender shall submit their Participation Documents before
the deadline to this following address :
Secretariat of OfferingUnconventional Oil & Gas Working Working Acreage Team
Migas Investment Service RoomDirectorate General of Oil and Gas
Ministry of Energy and Mineral ResourcesMigas Building 1st Floor Jl. H.R. Rasuna Said Kav.B-5 Jakarta 12910
Activity ScheduleAccess Bid Document 31 October 15 December 2016
Clarification Forum 4 November 15 December 2016Documents Submission Deadline 15 December 2016, 14.30 WIB
GMB Raja Block Bidding Round Schedule